Danfoss EVUP 2.7, EVUP 1.5 Installation guide

Installation guide
Electric expansion valve
Type EVUP 2.7 & 1.5
032R9553
2
Refrigerants:
R134a, R513a, R1234yf
*Note: Flammable refrigerant is approved by compliance acc. to IEC/EN 60335-2-89 with a charge <150 g for the above listed valve code numbers and with combination of below listed coil code numbers. This product is approved for R1234yf by ignition source assessment in accordance to standard IEC 60335-2-89:2012, IEC 60079-15, EN378. (Ignition assessments: ) It is important that all pipe connections are not exposed to excessive vibrations/pulsations which can create leaks.
Media temperature:
-10 °C to +60 °C (short term +65 °C)
Max. working pressure:
22.5 bar
-35 °C to +65 °C for max 2 minutes after stand still
Ambient temperature running condition:
-30 °C to +55 °C
Max. opening diff. pressure (MOPD):
18 Bar
032R9553
Mounting angle +/- 5°
Installation: Armature tube vertical upwards ±5°.
© Danfoss | DCS (rm) | 2020.11
AN317722501425 en-000201
Brazing of valve:
Permanent Magnet to open valve
N2
Permanent Magnet to open valve
1
2
Temperature valve Max 150 °C
1
2
2
1
1. Cobber tube: 10 - 15 sec
2. Valve connection: 2 - 5 sec
Minimum 5% Ag solder material
Mounting coil:
Be sure that th e O-rin g is in place
To ensure correct sealing between coil and valve mount the coil in the proper position and make sure that the coil is FULLY clicked on to the valve.
2
Use of coils:
Temperature pipe Max 700 °C
N2
Temperature valve Max 150 °C
Dismounting coil:
2
Always disconnect power from the coil when dismounted from the valve. Otherwise the coil may be damaged and there is risk of injuries and burns.
*Note: For the coil a hazard analysis to IEC/EN 60335-2-89 (ref. IEC/EN 60079-15) has been carried out. An external current fuse shall be installed to prevent sparks arcs under short circuit.