INSTALLATION INSTRUCTIONS
CONTINUOUS FLOW ICEMAKER SERIES 1400R
Disconnect power to the unit before servicing. Follow all lock out/tag out procedures established by the user. Verify all
power is off to the unit before performing any work.
Failure to comply could result in serious injury, death or damage to the equipment.
This manual covers unpacking and inspection, selecting location, installing unit, and preparing for operation.
The unit is a split system; it consists of a condensing unit, an icemaker and a line kit.
• The condensing unit is an outdoor component; it contains the compressor, condenser, receiver and fan motor. It is
controlled by a low-pressure switch.
• The icemaker is an indoor component; it contains two gear motors, two evaporators, two water level controls and
two bin thermostats. The bin thermostats control a liquid line solenoid.
• Line Kit: precharged 3/8” liquid line and 3/4” suction line.
NOTE: In a rack refrigeration application, only the ice maker is required (condensing unit and line kit are
not used). Ice maker installed on a -23° F (-30.56° C) low state saturation temperature (14 psig sat
uration pressure for R404A) requires the installation of one EPR valve, set at 20 psig downstream
of the common suction line of WCC-1400R unit. Approved EPR model is ORIT-6-0/50.
-
REMOVE UNITS CARTON
1. Keep unit in the upright position, remove carton and pallet from unit and inspect for damage.
2. Locate startup card either on outside of container or on plastic liner. Fill in proper information and send one
copy to factory, and other copy to distributor. Postage is prepaid.
CABINET REMOVAL
Condensing Unit
• Remove 19 screws and lift upward.
Icemaker
1. Front Panel – Remove 4 screws and pull forward.
2. Top Panel – Remove 4 screws and lift upward.
3. Side Panels – Remove 3 screws and pull forward.
4. Back Panel – Should not be removed.
PREPARATION OF INSTALLATION SITE
Condensing Unit
The refrigeration system is air-cooled, it requires airflow, so a well-ventilated area should be chosen. A minimum of
4 feet must be maintained for air intake and exhaust.
Revision Date: March 18, 2014 www.cornelius.com Revision: D
© 2005-2014, Cornelius Inc. - 1 - Publication Number: 630460310INS

Continuous Flow Icemaker 1400R Installation Instructions
Icemaker
The unit can be installed either on an ice storage bin or ice dispenser using proper adapter kits. (Refer to sales
literature for information.) The install kit provided with each icemaker and adapter kits will supply everything to
locate unit correctly. In all cases the icemaker should be sealed all around the base with an NSF listed sealant.
(63804815B)
WATER INLET HOOK UP
1. Water Inlet – Fitting is a ¼ SAE male flare located at the rear of the unit. Connect water supply with a ¼ SAE
flare nut and ¼” or larger copper or flexible tubing.
2. Water Pressure – Unless otherwise specified, the unit is designed to operate on water pressures between 10
P.S.I. and 90 P.S.I. (NOTE: for pressures above 90 P.S.I. a regulator must be installed.)
3. Filter/Conditioners are recommended on supply lines to icemaker.
NOTE: Unit must be installed per local plumbing code BOCA.
DRAIN CONNECTION
Overflow Line – is a 3/8” I.D. flexible tube located at the rear of the icemaker. Extend this line to proper drain.
NOTE: Unit must be installed per local plumbing code BOCA.
ELECTRICAL SUPPLY
1. Power Access — is provided with a 7/8” diameter. knockout hole in the rear panel. Route incoming power in
conduit, through rear panel to icemaker electrical control box. Make connections to wires provided in the con
trol box and ground lug/screw.
2. Fused Line — should be checked and sized according to electrical rating shown on unit nameplate.
-
AUGER ENGAGEMENT
Be certain that auger is fully engaged to lower drive and extruding head is fully engaged into evaporator.
INITIAL START UP, CHECKS AND ADJUSTMENT INSTRUCTIONS
NOTE: Do not start unit before completing installation steps on the previous page.
Turn on water supply (if unit is water cooled turn water on to condenser also) turn on main power switch (located on
top of electrical box), and make the following system checks:
NOTE: If unit will not start be sure water reservoir is full. Low water safety control must be properly
adjusted to start and shut down unit. If water level drops below bottom of reservoir, unit must
shut down. Adjustment is made by moving magnet up or down.
Water Level — If necessary adjust float by bending float arm up or down as needed, push float assembly down
until unit stops running. Release float and unit will restart. Keep water in reservoir at level line while unit is in
operation.
Low Water Safety Control — Adjust magnet by bending magnet arm as needed to shut unit down if water level
drops below bottom of reservoir.
Publication Number: 630460310INS - 2 - © 2005-2014, Cornelius Inc.