Installing, starting up, and servicing air-conditioning equipment can be hazardous due to system pressures, electrical
components, and equipment location (roofs, elevated structures, etc.).
Only trained, qualified installers and service mechanics
should install, start up, and service this equipment (Fig. 1).
Untrained personnel can perform basic maintenance functions such as cleaning coils. All other operations should be
performed by trained service personnel.
When working on the equipment, observe precautions in
the literature and on tags, stickers, and labels attached to the
equipment.
• Follow all safety codes.
• Wear safety glasses and work gloves.
• Keep, quenching cloth and fire extinguisher nearby when
brazing.
• Use care in handling, rigging, and setting bulky
equipment.
• See Table 1A or 1B for physical data.
ELECTRIC SHOCK HAZARD
Open all remote disconnects before
servicing this equipment.
BEFORE INSTALLATION
Rigging —
above the unit. Use 2-in. (50 mm) OD pipe or hooks in lifting holes. Rig with 4 cables and spreader bars. All panels
must be in place when rigging. See rigging label on unit for
details concerning shipping weights, distance between lifting holes, center of gravity, and spreader bar dimensions.
See Fig. 2.
If overhead rigging is not possible, place unit on skid or
pad for rolling or dragging. When rolling, use minimum of
3 rollers. When dragging, pull the pad. Do not apply forceto the unit. When in final position, raise from above to lift
unit off pad.
Preferred method is with spreader bars from
All panels must be in place when rigging.
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 1
Tab 3a
PC 111Catalog No. 533-820Printed in U.S.A.Form 38A-5SIPg 17-94Replaces: 38AK-3SI
and 80% full), kg
CONDENSER FANS, TypePropeller Type, Direct Driven
No. ...Diameter, mm2...7623...762
Total Airflow, L/s7,40011,200
Speed, R/s (60/50 Hz)19.0/15.819.0/15.8
CONDENSER COIL, TypeHorizontal Plate Fin
Rows...Fins/mm2...1.343...1.493...1.49
Total Face Area, sq m3.643.645.43
*See Service, Oil Charge, for Carrier-approved oil.
NOTE: Circuit breaker is in main power circuit.
17.125.738.3
2
Placing Unit — There must be 4 ft (1220 mm) for ser-
vice on all sides of unit, and a minimum of 8 ft (2440 mm)
clear air space above unit. For multiple units, allow 8 ft
(2440 mm) separation between units for airflow and service.
Mounting Unit — When unit is in proper location, use
of mounting holes in base rails is recommended for securing
unit to supporting structure or for mounting unit on vibration isolators, if required. Fasteners for mounting unit are
field supplied. Be sure to mount unit level to ensure proper
oil return to compressors.
Compressor Mounting — As shipped, compressor
is held down by 4 bolts. After unit is installed loosen each
bolt using nut indicated in Fig. 3 until flatwasher (3⁄8in.
[9.5 mm]) can be moved with finger pressure.
Fig. 1 — 38AKS Units
NOTES:
1. Use 2 in. OD (50 mm) pipe or hooks in lifting holes.
2. Rig with 4 cables and spread with 2 ‘‘D’’ long and two ‘‘A’’ long
2 x 4’s in. (50 x 100 mm) or equal.
3. Run the rigging cables to a central suspension point so that the
angle from the horizontal is not less than 45 degrees.
pend on length of piping required between condensing unit
and evaporator. See Table 2A or 2B. It is important to consider liquid lift and compressor oil return. Refer to Part 3 of
Carrier System Design Manual for line sizing information,
and Fig. 4 for recommended piping details.
Line sizes de-
Liquid Line Solenoid Drop Control — The factory-
supplied solenoid valve must be installed at the indoor unit
(fan coil) per Fig. 5, and wired per wiring label found on
unit. The solenoid assures that system refrigerant is in the
high-pressure side (condenser and liquid line) of the system
during the off cycle. Refrigerant migration is minimized.
Factory-supplied liquid line solenoid valve connecting sizes
7
⁄8-in. (22.2 mm) ODF for inlet and7⁄8-in. (22.2 mm)
are
ODM for outlet.
Failure to properly install liquid line solenoid at the indoor unit as described, without Carrier authorization, may
VOID warranty.
Filter Drier and Moisture Indicator — Every unit
should have a filter drier and a sight glass (moisture indicator) field installed. Select the filter drier for maximum unit
capacity and minimum pressure drop. Figure 5 shows recommended locations of filter drier(s) and sight glass. Complete the refrigerant piping from the evaporator to the condenser before opening the liquid and suction lines at the
condensing unit. One filter drier may be installed at location
A in Fig. 5, or 2 filter driers may be installed at locations B.
Fig. 2 — Rigging with Spreader Bars
(Field Supplied)
3
NOTE: All dimensions are in inches (mm).
Fig. 3 — Compressor Mounting
TXV — Thermostatic Expansion Valve
NOTES:
1. Suction line is connected to coil on same side as the entering air.
2. Lower section is first on and last off.
3. For more complete piping information, refer to Carrier System
Design Manual, Part 3.
Fig. 4 — Suction Line Piping to Unit
with 2 Section Coil Split
TXV — Thermostatic Expansion Valve
Fig. 5 — Liquid Line Solenoid Valve,
Filter Drier(s) and Sight Glass Locations
Receiver — No receiver is provided with the unit; it is
recommended that one not be used.
Piping Procedure — Do not remove run-around pipe
from suction and liquid line stubs until piping connections
are ready to be made. Pass nitrogen or other inert gasthrough
piping while brazing, to prevent formation of copper oxide.
Install field-supplied thermostatic expansion valve (TXV)
in liquid line ahead of each evaporator section. For 2-stage
cooling, the field-supplied capacity controlsolenoidusedmust
be wired to be opened by control from a 2-stage thermostat.
SUCTION PIPING AT EVAPORATOR AND TXV BULB
LOCATION (See Fig. 5) — The purpose of these recommendations is to achieve good mixing of the refrigerant leaving the evaporator suction header for proper sensing by the
TXV bulb.
1. A minimum of two 90° elbows must be installed up-
stream of the expansion valve bulb location.
2. The TXV sensing bulb should be located on a vertical
riser where possible. If a horizontal location is necessary,
secure the bulb at approximately the 4 o’clock position.
3. Size the suction line from the evaporator throughthe riser
for high velocity. Enter the suction pipe sizing charts in
the CarrierSystemDesignManual at design tons and equivalent length (for 2° F [1.1° C] loss). If reading falls between 2 sizes on chart, choose the smaller pipe size.
Suction piping for the high velocity section should be
selected for about 0.5° F (0.3° C) friction loss. If a 2° F
(1.1° C) loss is allowed for the entire suction line, 1.5° F
(0.8° C) is left for the balance of the suction line, and it should
be sized on that basis. Check that the high-velocity sizing
is adequate for oil return up the riser.
If an oil return connection at the bottom of this suction
header is supplied with an evaporator, this connection must
be teed-in ahead of first mixing elbow. When the compressor is below the evaporator, the riser at the evaporator does
not have to extend as high as the top level. After a
15-diameter riser has been provided, the suction line may
elbow down immediately.
SAFETY RELIEF — Afusible plug is located on unit liquid
line before the liquid valve.
*IMPORTANT — Requires a double suction riser, if evaporator is below condensing unit. See table below.
NOTE: Liquid and suction line sizes are OD (in.) Equivalent sizes in mm are listed below.
applicable localandnationalcodes.Install field-supplied branch
circuit fused disconnect(s) per NEC (National Electrical Code,
U.S.A.) of a type that can be locked OFF or OPEN. Disconnect(s) must be within sight from and readily accessible
from unit in compliance with NEC Article 440-14.
GENERAL WIRING NOTES
1. A crankcase heater is wired in the control circuit so it is
always operable as long as power supply disconnect is
on, even if any safety device is open or unit stop-start
switch is off. It is protected by a 5-amp circuit breaker in
control power.
2. The power circuit field supply disconnect should never be
open except when unit is being serviced or is to be down
for a prolongedperiod.Whenoperationisresumed, crankcase heater should be energized for 24 hours before startup. If unit is to be shut down for a prolonged period, it
is recommended that the suction and discharge valves be
closed to prevent an excessive accumulation of refrigerant in the compressor oil.
3. Power entry is one end only.
4. Maximum field wire sizes allowed by lugs on terminal
block are:
UNIT
38AKS
028208/230-3-60
034
044
LEGEND
AWG — American Wire Gage
kcmil — Thousand Circular Mils
*All other units use 2/0 AWG (67.4 mm
V-Ph-Hz
208/230-3-60
230-3-50
208/230-3-60
230-3-50
2
).
WIRE
SIZE*
350 kcmil
5. Terminals for field power supply are suitable for copper,
copper-clad aluminum, or aluminum conductors. Insulation must be rated 167 F (75 C) minimum.
CONDENSER FANS— The fans must rotate counterclockwise when viewed from above. If necessary, correct direction of fan rotation by interchanging any 2 powerinput wires
at disconnect switch. Affix crankcase heater decal (located
in installer’s packet) to unit disconnect switch.
Table 3 — Electrical Data
60 HZ
UNIT
38AKS
500
028
034
044
028
034
044
CSA— Canadian Standards Association
FLA— Full Load Amps
ICF— Maximum InstantaneousCurrentFlow duringstarting(the point
LRA— Locked Rotor Amps
MCA— Minimum Circuit Amps (complies with National
1. Main Power — Bring wires from the fused disconnect
switch through hole in bottom rail of unit to control box
12
(Fig. 6 and 7) and connect terminals,, and
line side of terminal block TB1 (see Fig. 8 and 9A
13
11
or 9B). To comply with NECArticle 440-14, the disconnect must be located within sight from and readily accessible from unit.
2. 24-v ControlPower—Unitshavesinglepointpower connections. Control circuit is directly connected internally
to unit. Maximum 24-v control circuit is 3 amps.
NOTE: Wire runs use the following insulated wire:
LENGTH
0-50180.82
50-75161.30
Over 75142.08
AWG — American Wire Gage
*35 C minimum.
INSULATED WIRE SIZE*
AWGmm
2
3. Control Circuit Interlock — An airflow switch may be
installed in the indoor air handler to prevent unit from
running when indoor air is not flowing. This switch (no.
HR81JE001) is available from Service Parts Center, or
equivalent can be field supplied. This should be electrically interlocked in the control circuit, between thermo-
2
stat TC1 (stage 1, cooling) and terminalon TB3.
Y1
See Fig. 8 for typical field wiring. This is in the 24-v circuit. Wires must be run in conduit with ground wire.
4. Transformer Connections — See unit wiring label diagram, notes 1 and 2, located behind compressor compartment end access door.
IMPORTANT: Ensure power to the crankcase heater
is always on (except when servicing the unit). If circuit breakerinsideunitshutsdown the compressor,crankcase heater remains on.
UNBALANCED 3-PHASE SUPPLY VOLTAGE — Never
operate a motor where a phase imbalance in supply voltage
is greater than 2%. Use the following formula to determine
the percent voltage imbalance:
% Voltage Imbalance
= 100 x
max voltage deviation from average voltage
average voltage
Example: Supply voltage is 240-3-60.
AB = 243 v
BC = 236 v
AC = 238 v
Average Voltage =
243 + 236 + 238
3
= 239 volts
Determine maximum deviation from average voltage:
(AB) 243 − 239=4v
(BC) 239 − 236=3v
(AC) 239 − 238=1v
Maximum deviation is 4 v. Determine percent voltage
imbalance:
% Voltage Imbalance = 100 x
4
239
= 1.7%
This amount of phase imbalance is satisfactory as it is be-
low the maximum allowable 2%.
IMPORTANT: Contact your local electric utility company immediately if the supply voltage phase imbalance is more than 2%.
7
LEGEND
NEC — National Electrical Code
VAV — Variable Air Volume
NOTES:
1. There must beminimum(2440mm) 8 ft. clear air spaceabove
unit.
2. The approximate operating weight of the unit is: