Bradley Corporation S19-130F Installation Manual

Page 1
Installation
S19-130F
Table of Contents
Pre-Installation Information . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
S19-130F Components and Parts List . . . . . . . . . . . . . . . . . . 4
Model S19-130F is not ANSI compliant.
215-152CO Rev. S; ECN 12-05-016G © 2012 Bradley Page 1 of 4 11/8/2012
P.O. Box 309, Menomonee Falls, WI USA 53052-0309 PHONE 800.BRADLEY (800.272.3539) FAX 262.251.5817 bradleycorp.com
Page 2
S19-130F Installation
IMPORTANT
Installation
R
WI 53051 alls,
HENTLICH ZU WEEK WÖC
P.O. Box 309, Menomonee F
DAIRE
e(s) each week and sign
UNIT EACH
y malfunctions immediatel
hentlich im
TEST THIS
hrift. Jeglic
DIESES GERÄT 1ST ESSAI HEBDOMA
Test-operate valv Report an
Ventil(e) wöc
t immédiatement.
durch Untersc
Test le fonctionnement des v signe en bas. S'il y à quelqu
un rappor
Date
Datum Date
114-051
PRÜFEN.
Testbetrieb prüfen, he Störung sofor
Signed Unterschrift
below.
bestätigt t melden.
y.
alves chaque semaine et e chose qui ne v
Date Signed
Signe
THIS SIDE UP
a pas fait
Signed Signed
Date Date
P.O. BOX 309, MENOMONEE FALLS, WI 53052-0309 USA
TEL: 1-800-BRADLEY FAX: (262-251-5817)
http://www.bradleycorp.com
Packing List
Read this installation manual completely to ensure proper installation, then file it with the
owner or maintenance department. Compliance and conformity to drain requirements and other local codes and ordinances is the responsibility of the installer.
Separate parts from packaging and make sure all parts are accounted for before discarding
any packaging material. If any parts are missing, do not begin installation until you obtain the missing parts.
Flush the water supply lines before beginning installation and after installation is complete.
Test the unit for leaks and adequate water flow. Main water supply to the eyewash should be “ON” at all times. Provisions shall be made to prevent unauthorized shutoff.
The ANSI Z358.1 standard requires an uninterrupted supply of flushing fluid. Bradley
plumbed emergency fixtures require a minimum of 30 PSI (0.21 MPa) flowing pressure. Flushing fluid should be tepid per ANSI Z358.1.
The inspection and testing results of this equipment should be recorded weekly to verify
proper operation. Emergency fixtures with self-closing ball valves do not comply with ANSI Z358.1.
Workers who may come in contact with potentially hazardous materials should be trained
regarding the placement and proper operation of emergency equipment per ANSI Z358.1.
For questions regarding the operation or installation of this product, visit www.bradleycorp.
com or call 1-800-BRADLEY.
Product warranties and service parts information may also be found under ”Products” on our
web site at www.bradleycorp.com.
2
11/8/2012 Bradley • 215-152CO Rev. S; ECN 12-05-016G
Page 3
Installation S19-130F
Installation
Supplies Required:
• Teflon tape and pipe sealant
• Piping to 1" NPT water supply inlet
• Adequate supply pipe supports
• Appropriate hardware to mount pulley to wall
• Minimum 4" (102 mm) drain to accommodate
30 gallons (115 liters) per minute discharge for shower waste
• Sign-mounting hardware
Step 1: Assemble components
1. Assemble components as shown on page 4.
• Apply pipe sealant or tape (by installer) to all male-threaded pipe joints.
• Bottom edge of showerhead should be 7'-0" (2134 mm) from the floor.
Step 2: Connect water supply
8⁷⁄₁₀"
(221mm)
Ø 3¹⁄₁₀" (79mm)
24"
(610mm)
IMPORTANT! Do not rely on Bradley’s Drench
Shower to support supply piping.
1. Connect water supply piping to 1" NPT inlet on unit (piping supplied by installer). Provide adequate supports (supplied by installer) for supply pipe using pipe hangers or other means.
2. Mount the pulley and the eye screw to the wall (pulley hardware supplied by installer).
3. Secure one end of the nylon cord to the “S” hook on the eyewash valve handle. Feed the cord through the pulley and then secure it to the eye screw.
4. Mount the safety sign to the wall using sign­mounting hardware supplied by installer.
5. Open water supply lines. Test for leaks and adequate water flow.
7'-0"
(2134mm)
Suggested
Height to
Floor
4"
(102mm)
3'-0"
(914mm)
to Floor
All dimensions assume standard thread engagement.
Variations in manufacturing allow for +/- ¹⁄₈” (3mm) per threaded joint. To find the tolerance of a dimension, add the number of thread joints in between a dimension and multiply it by ¹⁄₈” (3mm).
Bradley • 215-152CO Rev. S; ECN 12-05-016G 11/8/2012
3
Page 4
S19-130F Installation
Assembly of Components
1" NPT
Supply Inlet
2.1
2.5
2
2.4
2.3
8
3
2.2
2.11
114-050
P.O. BOX 309, MENOMONEE FALLS, WI 53052-0309 USA
TEL: 1-800-BRADLEY FAX: (262-251-5817)
http://www.bradleycorp.com
10
5
9
P.O. Box 309, Menomonee Falls, WI 53051
TEST THIS UNIT EACH WEEK DIESES GERÄT 1ST WÖCHENTLICH ZU PRÜFEN. ESSAI HEBDOMADAIRE
Test-operate valve(s) each week and sign below. Report any malfunctions immediately. Ventil(e) wöchentlich im Testbetrieb prüfen, bestätigt durch Unterschrift. Jegliche Störung sofort melden. Test le fonctionnement des valves chaque semaine et signe en bas. S'il y à quelque chose qui ne va pas fait un rapport immédiatement.
Date
Signed
Date Signed
Datum
Unterschrift
Date
Date
Signe
Date
R
Signed Signed
1
NOTE: Use
teflon tape
only.
4
6
Parts List
Item Part No. Qty. Description
1 S24-188 1 Plastic Showerhead Assembly
2 S19-0011 1 Self-Closing Spring Assembly
2.1 S27-286 1 Ball Valve with Jam Nut
2.11 110-214 1 Jam Nut only
2.2 142-002CH 1 Washer
2.3 128-129 1 Handle
2.4 140-720 1 Stop Bracket
2.5 S19-001 1 Kit, Spring Torsion
4
11/8/2012 Bradley • 215-152CO Rev. S; ECN 12-05-016G
7
Item Part No. Qty. Description
3 113-006LN 1 Pipe Nipple 1" Close
4 169-860A 1 1/4" Nylon Cord
5 269-646 1 “S” Hook
6 269-655 1 Pulley
7 269-765 1 Eye Screw
8 114-050 1 Safety Sign
9 204-421 1 Emergency Inspection Tag
10 169-1027 1 Coupling 1" NPT
Loading...