Installation
Instructions
R520
CENTRAL THERMOSTAT WITH VOLUME CONTROL
Thank you for selecting American-Standard...the benchmark of fine quality for over 100 years.
ROUGHING-IN DIMENSIONS
CONNECTIONS ARE: 1/2" NPT
1/2" NPT SHOWER
3-15/16
1/2" NPT INLET
II II
3-5/8
1/2" NPT TUB
5-7/8
1/2" NPT INLET
7
1-5/8 - 2-1/2
OP
T
Certified to comply with ANSI A112.18.1M ASSE 1016
M968255Rev.1.1
6-1/4
THERMOSTATIC BATH/ SHOWER INSTALLATION USING A TWIN ELL, DIVERTER SPOUT AND FIXED SHOWER
C/L
80"-86"
18"
(OPTIONAL)
TWIN
ELL
TOP OF TUB RIM
BOTTOM OF TUB
IMPORTANT: WHEN NOT USING A DIVERTER SPOUT A SEPARATE DIVERTER VALVE MUST BE USED.
TUB PORT
MUST BE
PLUGGED
4"
THERMOSTATIC SHOWER INSTALLATION USING A DIVERTER VALVE, FIXED SHOWER HEAD AND ADJUSTABLE HAND HELD SHOWER
DIVERTER
VALVE
HOT
1/2" 1/2"
TUB PORT MUST BE PLUGGED
COLD
THERMOSTATIC SHOWER INSTALLATION USING A DIVERTER VALVE, FIXED SHOWER HEAD, ADJUSTABLE HAND HELD SHOWER, ON/OFF VALVE AND TWO BODY SPRAYS
DIVERTER
VALVE
ON/OFF
VALVE
HOT
1/2" 1/2"
TUB PORT MUST BE PLUGGED
NOTE: MINIMUM FLOWING PRESSURE REQUIRED FOR THIS SYSTEM OPERATING WITH ONE SHOWER HEAD AND 2 BODY SPRAYS IS 40 PSI
COLD
ROUGHING-IN THE VALVE
1
Prepare water supplies per ROUGHING-IN DIMENSIONS. Make sure the finished wall is between the minimum and maximum rough dimension.
Install VALVE at indicated height and depth. Make sure the "TOP" marking on the PLASTER GUARD is up.
Connect the hot and cold water supplies. Assemble all connecting pipes. Flush lines to remove any dirt. Connections are 1/2" NPT.
Assemble the connection pipe to one of the MIXED OUTLETS of the VALVE. Cap the other MIXED OUTLET. (Tub port is fitted with a plug at the factory).
WARNING
DO NOT SOLDER DIRECTLY TO THE VALVE BODY; THIS WILL DAMAGE THE TEMPERATURE CONTROL ELEMENT AND CHECK STOP VALVES.
WOOD
BRACE
HOT
MIXED
COLD
OP
T
IMPORTANT! INSTALL ANY REQUIRED SHUT OFF OR DIVERTER VALVES INTO THE PIPING SYSTEM.
If the CHECK STOPS (4, 5) were removed during installation, ensure the hot and cold CHECK STOPS (4, 5) are not reversed. The hot CHECK STOP (4) has a red top and the cold CHECK STOP (5) has a blue top.
CHECK STOPS (4,5) are supplied in the open position. Closing using 5/32" (4 mm) hex wrench to pressure test and to check for leaks.
To flush lines, remove the CHECK STOPS (4,5) and run water. If desired, the TEMPERATURE CONTROL UNIT can be removed. Reinstall CHECK STOPS (4,5) and CONTROL UNIT (6), if it was removed.
Remove PLASTER GUARD (2) if still installed. Turn on water supplies and check for leaks.
Reassemble PLASTER GUARD (2) and FINISH WALL.
Beware of Freezing. No water should remain in the MIXING VALVE if freezing is a possibility. Remove the CHECK STOPS (4,5) to completely drain the MIXER UNIT (1).
TEMPERATURE ADJUSTMENT
2
Unscrew PLASTER GUARD SCREWS and remove PLASTER GUARD.
Check that arrow marking B points vertically upwards. If not, push the BLACK CLAMP on the SECURING RING to the right, pull off KNOB MOUNT and reinstall KNOB MOUNT with arrow "B" pointing upwards.
The maximum mixed water temperature is set at 109 F at the factory. This setting can be changed if desired.
Remove the TEMPERATURE LIMIT STOP (H shaped Black Plastic part). Reinstall it at the desired notch as indicated in the diagram to limit the maximum mixed water temperature to 104 F or 112 F.
For 100 F adjustment, turn the water supply on. Turn KNOB MOUNT until the spout temperature is 100 F. Check that arrow marking A on the KNOB MOUNT still points upward after adjusting the thermostat to 100 F. If not, pull out the RED LOCKING DEVICE. Remove KNOB MOUNT by pulling it towards you while standing directly in front of the valve.
HOT
1
3
PLUG TUB
PORT
CHECK STOP
(HOT RED)
6
4
TEMPERATURE
LIMIT STOP
COLD
2
104
109
112
SECURING
RING
RED LOCKING
DEVICE
ARROW
"B"
5
CHECK STOP (COLD BLUE)
PLUG TUB
PORT
BLACK
CLAMP
TOP
ARROW
"A"
KNOB
MOUNT
Reinstall the KNOB MOUNT so that the arrow marking A points upwards.
Reinstall RED LOCKING DEVICE.
TRANSPOSED SUPPLY PIPING OR BACK TO BACK INSTALLATION
3
Should the hot and cold water supply pipes have been transposed making adjustment impossible, proceed as follows:
Shut off water supply. Remove handle and rim
Remove check stops and re-install them transposed.
Important note: RED CHECK STOP is now on the right of the mixer body and the BLUE CHECK STOP is now on the left.
Turn the water supply back on and perform the temperature adjustment in step 2.
CHECK STOP
(RED TO BLUE)
CHECK STOP
(BLUE TO RED)