American Dish HT-25 Service Manual

Effective Date: April, 15,2009
American Dish Service
MODEL HT-25
DISHWASHER
SERVICE MANUAL
900 Blake Street
Edwardsville, Kansas 66111
(913)-422-3700
American Dish Service provides this information as a service to our customers. Keep all instructions for future reference. Although ADS will make every effort to make sure the information in this service manual is correct and up-to-date, ADS does not certify that this is the case, and should you decide to utilize this manual, you do so at your own risk. ADS reserves the right to alter or update this information at any time with out notice. Should you desire to make sure that you have the most up-to-date information, we would
direct you to the appropriate document on our web site: www.AmericanDish.com. The instructions
and guidelines in this owners manual are given with the assumption that the dishwasher has been installed, operated, and maintained properly and in accordance with all applicable Codes, Ordinances, and Safety requirements. Failure to install, operate, and maintain the machine in this manner will void the ADS Warranty. ADS assumes no liability or control over the installation, maintenance(service), or operation of the equipment. Product fail­ure due to improper installation, maintenance, and operation is not covered under the ADS Warranty.
WARNING:
During the operation of all dishmachines, chemicals, high voltage electricity, and normal operational func­tions can cause harm, bodily injury, or worse if proper installation, operation, and maintenance are not observed. It is imperative that the operator(s) are trained in the operation and made aware of the hazards that can exist. This is the responsibilty of the owner of this equipment. When installing, operating, or maintaining your dishwasher you must follow all applicable safety requirements, including the wearing of approved personal protective equipment.
2
TABLE OF CONTENTS
Description
Installation, Tables Plumbing Electrical Dispensers Spray Arms Operation Motor Replacement Hi Temp Design Problem Evaluation Preventive Maintenance Warranty Statement Cleaning Process Water Control (“float”) Specifications Spec Diagram Wire Diagram, 3 Phase Timer Modification Kit #388-1007 Wire Diagram, 1 Phase Ladder Diagram, HT-25 (including all options of 2005) Ladder Diagram, HT-25 (original 1995 wiring) Ladder Diagram, HT-34/25 (including all options of 2005) Layout, 3 Phase Layout, 1 Phase Wire Diagram, 3 Phase with Booster Spray Arm Drawing Bulletin #022-44 Motor Shaft Diagram Replace Mercury Relay with Contactor Booster Spec Sheet Cam Timer Sequence Chart
Page
5 5 6 7 7
9 11 12 12 13 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
3
NSF DATA PLATE
NSF Operational Requirements for
MODEL HT-25, Hot water sanitizing, single rack dishmachine
as manufactured by AMERICAN DISH SERVICE
Wash tank minimum temperature: 160° F
Final sanitizing rinse minimum temperature: 180° F
Final rinse minimum pressure: 20 psi
Wash cycle minimum time: 35 seconds
Final rinse minimum time: 10 seconds
MODEL HT-25, Chemical sanitizing, single rack dishmachine
Wash tank minimum temperature: 120° F Final rinse minimum temperature: 120° F
Final rinse minimum pressure: 20 psi
Wash cycle time: 35 seconds
Final rinse minimum time: 10 seconds
Sanitizer required: 50 ppm available chlorine
To convert from hot water sanitizing to chemical sanitizing or the reverse,
adjustments shall be conducted by the manufacturer or its authorized service
agent.
Listing date 11/4/96
4
OPERATING INSTRUCTIONS FOR HT-25
INSTALLATION
First steps: Remove the packing material, including the cardboard shield for the tank heater. Place the dishmachine in the desired position, then level the unit by adjusting the bullet feet in each leg. The HT-25 can be used in either corner or inline arrangements. IMPORTANT. Do not
run this machine with the spray arm installed for the fi rst two cycles following the installa­tion. Rinse out any installation debris (such as grinding shavings or fl oor grout) that may dam-
age bearings or rotating parts.
TABLE LAYOUT
Both corner table or inline arrangements can be attached to this machine model. For corner layouts, the best arrangement will be with the table intersection meeting on the machine’s front left-hand corner (your right hand side). This makes the scrap trap and control box more acces­sible. The only machine modifi cation needed when changing between the two table layout styles (inline/corner) is moving the tray track rail from the front position to the side position. This is done by removing the two ¼” x 20 hex bolts and re-positioning the rail on the adjacent side. Note: If
you are installing this model in a corner confi guration and the table backsplash is over 6” in height, you may be required to modify the table backsplash by cutting a relief for the door arm handle.
The tray track can be confi gured in corner or inline styles. The scrap box can be installed on the right or left side. Note: For the corner setup the box must be on the left side of the machine and the front panel (machine’s skirt) removed. The opening for the table lip is 21”. If the table lip is wider than 21’ it must be cut to fi t within the door guide opening. The “down turn” lip of the table should not exceed ¾” in length. It is recommended that a distance of at least eight inches (8”) of table surface between the scrap sink and the dishmachine.
PLUMBING
Incoming water supply is a single point ½” FPT, with a minimum of 20 PSI (at the fi nal rinse gauge), 180F fi nal rinse, at 60 GPH recovery rate. Note: A booster heater is required for the fi nal rinse temperature of 180F. The installation point for incoming water is located on top of the machine, approximately center and toward the rear. DO NOT supply a commercial dishmachine with a 3/8” NPT incoming water line. SERVICE NOTE: If you are having problems getting enough pressure during fi nal rinse, the problem will usually be found in the supply system. Think of the machine as a sprayer on the end of a garden hose. If all of a sudden the water spray drops in pressure, or will not come out with enough pressure, the problem will be found along the hose somewhere. Usually the line is branched to other fi xtures, which causes a reduced fl ow to the machine. It is recommended that a
5
single line from the primary water heating system extend to the dishmachine or booster. The pressure regulator on the machine is there to regulate pressure down to 20 psi, if the line pres­sure is too high. It cannot regulate the pressure up—that is a supply problem. Usually the prob­lem is found in the booster heater, gate valve, inline regulators, or supply pipes.
LINE PRESSURE: Having too little or too much pressure in the fi nal rinse sprays creates result problems. With pressures much above 20 psi, the water begins to atomize and rinsing is threatened. Too little pressure (below 20), spray arm rotation drops, coverage is reduced, ‘make-up’ water volume is lessened, and soiled wash water stays on the ware. Static line pressure means nothing to the process; running pressure (the pressure reading during fi nal rinse spraying) is the dynamic pressure or fl ow pressure. The dynamic pres­sure is what is required to be 20 psi.
[ This information is critical but is often overlooked ] The drain on the HT-25 is made from two inch (2”) copper pipe, the manifold is attached by “no­hub” plumbing connections to the tank and scrap box drains. The machine is normally shipped with the scrap-box installed on the machine’s right-hand side. If the installation requires the scrap-box installed on the machine’s left-hand side, the scrap box will require a different drain manifold. This manifold can be order from ADS or soldered in place using “Tees,” “elbows,” “45 degrees,” and straight pipe. SERVICE NOTE: The drain manifold is attached with a plumbing coupler called a “no-hub” which uses a 5/16” nut-driver tool to attach. Any commercial dishma­chine of high capacity, should use 2” plumbing for drains; smaller drain lines are more liable to clog. Reducers and 180-degree bends create severe clogging problems.
ELECTRICAL HOOK UP
The electrical hookup on a machine that has motors and heaters is important because of the potential for injury and premature part failure due to faulty supply conductors or service voltage. Undersized wire can cause early failure or intermittent operation. Loose connections can cause burned wires and components over time. Operation of the machine without following manufac­turer’s specifi cations will result in costly failures.
IMPORTANT >>>> This equipment requires a NEUTRAL wire
Three Phase Power Requirements:
(Single circuit) 208-230, 3 Phase, 40 amp, 60 Hz service
Wires: three 8 AWG copper wires for power, One 10 AWG wire for Neutral, and a ground
wire. NOTE: 3 Phase has a rotational aspect, check for proper rotation, switch L1 and L2 to reverse the rotation. (If the wash pump sounds loud and the sprays are very low, this indicates the rota­tion is backward.)
Single Phase Power Requirements:
(Dual circuits) 208-230, 1 Phase, 30/60 amp dual circuit, 60 Hz service
6
(1) Wires: two 10 AWG copper wires for power, One 10 AWG wire for Neutral, and a
ground wire. (2) Wires: two 6 AWG copper wires for power NOTE: 1 Phase has no rotational aspect.
SERVICE NOTE: 5/32 Allen wrench is needed for the main power distribution block. The control box electrical conduit hole for the power supply wires is a “one inch conduit” hole. The actual size of the hole is 1 3/8” located on the back wall, left hand side. Also, there is a ½” conduit hole, which is actually 7/8” in diameter, located on the bottom of the control box for dispenser connections.
IT IS RECOMMENDED THAT NEW CIRCUIT BREAKERS BE INSTALLED FOR ANY EQUIPMENT THAT CONTAINS ELECTRICAL HEATERS.
Wire size is important to electrical component life, undersized wire will result in premature failure of contactors and motors. We do not recommend using power from the HT-25 control box to supply power for controls or devices such as exhaust fans. WARNING: Always turn the power off for the machine before servicing the electrical system.
DISPENSING HOOK UP
The signal for dispensers is 120v and comes from the control circuit (unlike the ADC convey- or’s dispenser signal, which is 208v and comes from the power circuit). The dispenser hook­up points are marked by a yellow sticker labeled “rinse” and “on” signals. The terminals are located in the lower left-hand corner of the control box. There is an electrical conduit hole on the bottom of the box for the dispenser wires. The control circuit supply power comes from L1 and the Neutral line; it is protected by a 10 amp fuse and has the capacity of running the dispenser’s power needs. A female threaded (1/8” FPT) port is provided on the fi nal rinse manifold. It is located at the base of the manifold fl ange (mixing chamber) mounted to the hood and pointed toward the rear. A 7/8” hole is provided at the back and center of the wash tank for a chemical inlet posi­tion. This is where you would install the bulkhead fi tting for detergent feeding into the tank. There is another 7/8” hole for a Chemical Probe located on the front wall of the lower tank, near the machine’s centerline. Do not mount the dispenser on top of the control box (reason: chemical leaking inside electrical controls). Secure all chemical lines and attachment points. Make sure that chemi­cal lines do not run over the top of electrical devices or inlet plumbing. (a leaking sanitizer line can destroy the stainless cabinet and machine components)
SPRAY ARMS
The wash arms are interchangeable and rotate on bearings mounted horizontally in the top of the wash arm hub. The four spray arm spokes are welded to the hub. Running a knife or fork across the slot cleans the wash spray slots. Cleaning out the arms can be accomplished by opening the captive end
7
cap and running water through the arm. The bearing can be disassembled for cleaning with a screwdriver, should the need arise. It is not anticipated that disassembly would be required; each time the machine goes into fi nal rinse, a jet of water cleans out the bearing shell. The wash base has a dome, which is held by the fi nal rinse tube. This dome controls the direction of water being pumped into the spray base. WARNING: Should metal installa­tion materials become lodged between the dome and the hub, the wash arms will stop turn­ing. Metal shavings, and especially sand can score these parts and cause rotation problems for the wash arm. However, once these construction materials are gone, the hub and dome interface will process food-related soils. The fi nal rinse arms are interchangeable and rotate on a bushing pivot. The pivot is hollow and supplies the fi nal rinse water to the rotating arm. There is a twist grip attached to the top of the pivot by means of a snap ring. There are two washers made of polymer ma­terial, which serve as the rotational bushings for the rinse arm. After the wash arm is set in place over the spray base dome, the fi nal rinse pivot, holding the spray arm, can be screwed into the fi nal rinse tube which holds down the wash dome (There is a hole through the wash arm bearing shells, the pivot goes through that hole and holds the wash arm in place along with securing the fi nal rinse pivot).
AFTER THE INSTALLATION CHECK-UP
1. Check rotation of the Wash motor—see arrow on pump housing. There is a 50% chance that a 3 Phase motor will turn the right direction on installation. If you need to reverse rotation, change the incoming L1 wire with the incoming L2 wire. Single phase machines do not need this procedure.
2. Check for a high leg (delta system, 240v), if a high leg is present (200v) use L3 on the power distribution block for that leg.
3. Check the heater circuit breaker located in the control box; make certain it is in the “on” position. The toggle should be up.
4. Check the water level control mechanism located at the machine’s right rear top of cabi­net. Take the cover off the box and inspect the movement of the lever and rod. They should be free moving and without restriction. When the machine is turned on, the water control will fi ll automatically to the upper limit of the control. It is normal for the water level to be below the scrap trays after initial fi ll. Several cycles later the machine will begin to overfl ow into the scrap trap mounted on the side. SERVICE NOTE: to test the water control system, turn the machine on and let it fi ll completely. Then move the lever in the water level box up with your fi nger, it should begin to fi ll but shut off as soon as you take your fi nger away. Do this rapidly 10 or 20 times, it should never stick on or continue to fi ll. If it does, the problem will be caused by something rubbing on the rod, lever, or weight. In rare cases, the water level switch may have lost the required tension on its return button, and must be replaced. These switches are specifi cally designed with a certain tension on the button (marked with a 5); other switches will not work in this system.
Check the machine’s operation by placing a rack inside, close the door and push the start button located on either side of the control box. The indicator
8
1. lamps will show the wash and rinse cycle duration, when the rinse lamp turns off, the cycle is over. The door may now be opened and the rack removed. During the rinse cycle, check the pressure gauge at the fi nal rinse manifold. It should read 20 psi. It can be ad­justed to a lower pressure by turning the regulator screw counter-clock wise (CCW)—Re­member, up = is down.
2. Check all end caps in the wash and rinse arms. Make sure all the screens and pump fi lter are in place. Make sure the cardboard packing material is removed from around the tank heater.
THE RULE FOR ALL DISHMACHINES: The Installation is KEY to reduced service prob-
lems and complaints.
Important Note:
Before running the machine for the fi rst time, wash out the inside by operating without the spray arms. This will help remove the installation debris and metal fi lings that cause the spray arms to bind. If they lock up during the fi rst cycle, remove the four arms, then clean the spray base and wash arm hubs. Rinse out the machine by running a cycle without the arms, then dump the tank and refi ll. Food soil will not cause this problem. However, installation grit, metallic or PVC shavings will stop the arms from turning. They are forced into the hub and bearing clearances when the pump fi rst starts up. These fragments cause rotation stoppages. This problem will cease after the machine is cleaned and normal operations begin.
MACHINE OPERATION
After the machine is operational and the tables are cleared, remove all packing material (heat­er supports) then wash out the tank, give attention to any installation debris left over. DO NOT PUT THE SPRAY ARMS IN UNTIL THE MACHINE HAS RUN SEVERAL CYCLES. Now, fi ll the machine by turning on the master switch. The HT-25 will automatically fi ll with water to an operational level. After the pump motor starts, the machine will fi ll once more to compensate for the water used by the pump. This is normal operation. Now, place the wash arm on the spray base dome, the wash arms are interchangeable up and down. Now screw in the fi nal rinse spray arm by turning the twist grip pivot into the spray base center tube. It is easier to hold the upper wash arm in place while turning the fi nal rinse arm and securing the entire up­per assembly.
Place a rack in the machine and close the doors, push the start button. As the machine runs through the cycle (Both 60 seconds or 45 seconds are available), you will hear the sound of the wash sprays, however, when the fi nal rinse begins, the noise level drops dramatically. Some people have thought it was fi nished, but observe the cycle light to see when the fi nal rinse is completed. Then open the doors and remove the rack.
WHAT TURNS THE MACHINE ON AND OFF
There is a timer that causes the machine to run. The cycle is started when the start button is pressed and the instant start relay is energized, which energizes
9
the cam timer. Everything is keyed off the master cam. The fi rst cam is the master and it begins the cycle by sending power to the timer motor. The second cam immediately turns on the contac­tor for the wash motor. The third cam will turn on the fi nal rinse solenoid. The fourth cam switch is a spare.
The heater is controlled by the thermostat and the level control switch (fl oat). If there is no water present in the tank when the machine is turned on, the level control switch will turn off the heater and open the fi ll solenoid. When the tank is full, the switch will shut off the water and then turn on the heater. If the incoming water is hotter than the settings on the thermostat, the ther­mostat will shut the heater down until the water temperature drops below the set point. NOTE: To increase the temperature set point, turn the thermostat center-rod counter clock-wise (turn to the left). The red light above the Mercury Relay in the control box will show (on) when the thermostat is sending power or when it is satisfi ed (off) in the temperature of the tank.
A test to see if the machine’s tray track and tables are set up right is to place a rack on the soil table then push it through the machine and on to the clean table. It should slide easily across all points. CAUTION: Always disconnect power to the machine before servicing. Heaters will remain hot immediately after emptying of machine. Turn machine off before opening for inspection.
MOTORS
It is recommended that the pump motor be replaced as a unit. This is classifi ed by ADS as “pump motor complete, less cover.” The reasoning is: High Temps are generally placed in high volume accounts, which have little space or time for major repairs. The simplest procedure for a fast replacement is to remove the four housing bolts, disconnected the electrical connection and replace with a new unit. This can be accomplished without extensive service knowledge or down time for the restaurant. If there is a problem with the seal, shaft, or impeller the resulting time
investment could cause an extended disruption.
This is best managed by preparation rather then reaction. The primary events include heater/cir- cuit breaker, wash pump/contactor, and damaged or broken parts. Any of these events can be replaced and operations returned to normal within 20 minutes if the assembles are readily avail­able. ADS has kits or lists of these major items and they can be purchased in assembled form.
Once a replacement is speedily made, the faulty part can be returned to the shop. At the shop there is enough time and resources to perform an adequate repair; the repaired part then be­comes the replacement assembly for the next event. This is the most effi cient way to service the high volume business. Expecting even qualifi ed service persons to repair system assemblies can be a risk. It can lead to multiple-day events. All possible or needed resources are simply not available at the restaurant.
10
3HP MOTOR REPLACEMENT
SEAL REPLACEMENT PROCEDURE 1 TURN OFF POWER TO THE MACHINE. Empty water from the wash tank and open pet­cock on wash pump motor. 2 Remove the two mounting bolts that secure motor to frame. Take out the (4) four 3/8” bolts that hold rear pump housing to the front pump cover. 3 Slide motor and rear pump housing out of the pump cover. Place the unit on the fl oor and open the rear access plate on the motor. 4 Disconnect the (3) three lead wires that are attached to terminals L1, L2, and L3. Remove the conduit from the motor. 5 Remove the impeller by taking out the secure bolt and. The impeller slides off the keyway. If it does not slide off easily, gently tap it from behind. Heavy blows from a hammer will dam­age the impeller and shaft alignment. 6 Remove the (4) four 3/8” x7/8” bolts that hold the rear pump housing to the motor. Carefully slide the housing off the motor; pay particular attention to the shaft seal. The graphite section (black face) is the part that slides on the motor shaft. The ceramic section (white race) is the part that seats in the rubber boot in the housing. Slide the graphite section off. Be careful not to crack the ceramic when the pump housing is removed from the motor.
Important Note: The 3hp motor shaft extension with the pinned and set screws adapter is not fi eld repairable or serviced. It is installed at the factory and must be replaced as an integral part of this motor. However, the 1999 7/8” motor shaft, has only a 1.5” diam­eter collar that slides over the motorshaft. It is sealed with internal O rings and held in place by the impeller. This motor is simpler and can be setup in the fi eld without special tools.
7 To assemble, reverse the order above. If you are replacing the seal make sure the rubber
boot on the ceramic is fully seated at the bottom of the pump
housing. Make sure the shaft is clean. Put the boot and ceramic section together fi rst, then press it into the housing fi rst. It will be helpful to use some hand soap or dishsoap (Dial) to slide the boot with white ceramic section into the pump housing. The smooth surface will face out toward you; the grooved side will face the housing. Do not put grease or oil on the seal. Inspect the graphite section; make sure there are no cracks or chips on the face of the black graphite. Slide this section onto the motor shaft and install the spring and fi nally the retainer shield. Place the impeller on next. The keyway and slot should be free from damage or distortion. If the keyway is enlarged, the motor will need replacement. If the impeller is also has a damage key slot, it must be replaced.
8 When the pump assembly is placed back into the pump cover, properly seat the o-ring gas­ket and use some lubricant to avoid pinching the o-ring. To
11
determine whether the O ring is good or not, roll it between your fi ngers. You should not feel a fl at spot.
HI TEMP DESIGN
The term “Hi Temp” refers to the sanitation process of the dishmachine. Or, in other words, the type of process used to achieve an acceptable kill rate in bacteria. There are typically two meth­ods, chemical or thermal sanitizing. In high temperature (thermal kill) sanitizing, the surface of the dishware must reach a temperature of 165F for a minimum of ten seconds. This is accomplished by spraying 180F water over the dishware during the fi nal rinse. This elevated temperature meets the Heat Unit Equivalent (H.U.E.) tests required for NSF certifi cation.
The HT-25 supports both methods of sanitizing, NSF lists the HT-25 as a dual sanitizer. This means the machine’s design can serve in both roles. The fi nal rinse system delivers high temper­ature sanitizing or chemical sanitizing sprays with the same water consumption rates. The choice of the boosted incoming hot water (min. 180F) or chemical dispenser application (min. 50 ppm chlorine) is a result of the equipment added to the machine (booster or 3 product dispenser). The best application of the HT-25 is the High Temp sanitizing.
HT-25 Commercial Dishmachine
QUESTIONS TO EVALUATE OPERATION OF MACHINE
1. Will the machine fi ll with water when it is turned on for the fi rst time during a new work period? If it does not, is the “ON” light illuminated when the master switch is turned on? If not, the ma­chine will need electrical service. [Service issue]
2. When the machine fi lls with water, what is the incoming water temperature? It should be 158F for Hot Water Sanitizing and 120F for Chemical Sanitizing. This requirement is supplied by the building’s primary water heating source. [Building maintenance issue]
3. After the machine has fi lled with water, a rack of dishes can be pushed into the machine on the “soil table” side, and the door closed. Push the start button, the wash pump should begin operation. If it does not, look at the inspection door, is it fully closed? [Operator issue]
Does the machine continually fi ll, causing the primary water-heating source to run out of hot wa­ter? This condition will be a result of water escaping from the
12