The information contained in this
operation and maintenance manual
is subject to change without notice
from AERCO International, Inc.
AERCO makes no warranty of any
kind with respect to this material,
including but not limited to implied
warranties of merchantability and
fitness for a particular application.
AERCO International is not liable for
errors appearing in this manual. Nor
for incidental or consequential
damages occurring in connection
with the furnishing, performance, or
use of this material.
Page 3
CONTENTS
GF-109LN - AERCO KC1000 GAS FIRED LOW NOx BOILER
Operating & Maintenance Instructions
FOREWORD A
SECTION 1 – SAFETY PRECAUTIONS 1-1
Para. Subject Page
1.1 Warnings & Cautions 1-1
1.2 Emergency Shutdown 1-2
SECTION 2 – INSTALLATION PROCEDURES 2-1
Para. Subject Page
2.1 Receiving the Unit 2-1
2.2 Unpacking 2-1
2.3 Installation 2-2
2.4 Gas Supply Piping 2-4
2.5 Electrical Supply 2-6
2.6 Mode of Operation and Field
Control Wiring
2-6
Para. Subject Page
1.3 Prolonged Shutdown 1-2
Para. Subject Page
2.7 I/O Box Connections 2-8
2.8 Auxiliary Relay Contacts 2-10
2.9 Flue Gas Vent Installation 2-10
2.10 Combustion Air 2-10
SECTION 3 – CONTROL PANEL OPERATING PROCEDURES 3-1
Para. Subject Page
3.1 Introduction 3-1
3.2 Control Panel Description 3-1
3.3 Control Panel Menus 3-3
3.4 Operating Menu 3-4
3.5 Setup Menu 3-4
Para. Subject Page
3.6 Configuration Menu 3-5
3.7 Tuning Menu 3-7
3.8 Start Sequence 3-7
3.9 Start/Stop Levels 3-9
SECTION 4 – INITIAL START-UP 4-1
Para. Subject Page
4.1 Initial Startup Requirements 4-1
4.2 Tools and Instrumentation for
Combustion Calibration
4.3 Natural Gas Combustion
Calibration
4-1
4-2
Para. Subject Page
4.4 Propane Combustion Calibration 4-5
4.5 Unit Reassembly 4-7
4.6 Over-Temperature Limit Switch
Adjustments
4-8
Section 5 – MODE OF OPERATION 5-1
Para. Subject Page
5.1 Introduction 5-1
5.2 Indoor/Outdoor Reset Mode 5-1
5.3 Constant Setpoint Mode 5-2
5.4 Remote Setpoint Modes 5-2
5.5 Direct Drive Modes 5-3
Para. Subject Page
5.6 Boiler Management System
(BMS)
5.7 Combination Control System
(CCS)
5-4
5-5
i
Page 4
CONTENTS
SECTION 6 – SAFETY DEVICE TESTING PROCEDURES 6-1
Para. Subject Page
6.1 Testing of Safety Devices 6-1
6.2 Low Gas Pressure Fault Test 6-1
6.3 High Gas Pressure Fault Test 6-1
6.4 Low Water Level Fault Test 6-2
6.5 Water Temperature Fault Test 6-2
6.6 Interlock Fault Tests 6-3
6.7 Flame Fault Test 6-3
Para. Subject Page
6.8 Air Flow Fault Test 6-4
6.9 SSOV Proof of Closure Switch 6-4
6.10 Purge Switch Open During
Purge
6.11 Ignition Switch Open During
Ignition
6.12 Safety Pressure Relief Valve
Test
6-5
6-5
6-6
SECTION 7 – MAINTENANCE 7-1
Para. Subject Page
7.1 Maintenance Schedule 7-1
7.2 Spark Igniter 7-1
7.3 Flame Detector 7-2
7.4 Combustion Calibration 7-2
7.5 Safety Device Testing 7-2
Para. Subject Page
7.5 Safety Device Testing 7-2
7.6 Manifold and Exhaust Tubes 7-2
7.7 Heat Exchanger Water Side
Inspection
7.8 Condensate Drain Assembly 7-5
7-4
SECTION 8 – TROUBLESHOOTING 8-1
Para. Subject Page
8.1 Introduction 8-1
Para. Subject Page
APPENDICES
App Subject Page
A Boiler Menu Item Descriptions A-1
B Startup, Status and Fault
Messages
C Temperature Sensor Resistance
Chart
D Indoor/Outdoor Reset Ratio
Charts
B-1
C-1
D-1
App Subject Page
E Boiler Default Settings E-1
F Dimensional and Part Drawings F-1
G Piping Drawings G-1
H Wiring Schematics H-1
I KC1000 Control Panel Views I-1
J KC1000 Low NOx Dual-Fuel
Switch-Over Instructions
J-1
WARRANTIES W-1
ii
Page 5
FOREWORD
Foreword
This system can be operated using natural gas or propane fuel. A simple spring change in the
differential regulator and combustion calibration is all that is needed to switch fuels.
The AERCO KC Low NOx Boiler is a true industry advance that meets the needs of today's
energy and environmental concerns. Designed for application in any closed loop hydronic
system, the load tracking capability relates energy input directly to fluctuating system loads
through a 11:1 modulating turndown ratio. The boiler’s condensing capability offers extremely
high efficiencies and makes the KC Boiler ideally suited for modern low temperature, as well as,
conventional heating systems.
When installed and operated on natural gas in accordance with this Instruction Manual, the KC
Boiler complies with the NOx emission standards outlined in:
• South Coast Air Quality Management District (SCAQMD), Rule 1146.2
• Texas Commission on Environmental Quality (TCEQ), Title 30, Chapter 117,
In addition, when operated using propane fuel, the KC Boiler is certified by AERCO to provide
NOx emissions of less than 30 ppm at full rated input.
The KC Boiler can be used singular or in modular arrangements for inherent standby with
minimum space requirements. Venting capabilities offer maximum flexibility and allow
installation without normal restrictions. The advanced electronics of each KC Boiler control
system offer selectable modes of operation and interface capabilities.
After prolonged shutdown, it is recommended that the startup procedures in Section 4 and the
safety device test procedures in Section 6 of this manual be performed, to verify system
operating parameters. If there is an emergency, turn off the electrical power supply to the KC
Boiler or close the manual gas valve located before the unit. The installer is to identify the
emergency shut-off device. FOR SERVICE OR PARTS, contact your local sales representative
or AERCO INTERNATIONAL.
Installers and operating personnel MUST, at all
times, observe all safety regulations. The
following warnings and cautions are general and
must be given the same attention as specific
precautions included in these instructions. In
addition to all the requirements included in this
AERCO Instruction Manual, the installation of
units MUST conform with local building codes,
or, in the absence of local codes, ANSI Z223.1
(National Fuel Gas Code Publication No. NFPA-
54) for gas-fired boilers and ANSI/NFPASB for
LP gas-fired boilers. Where applicable, the
equipment shall be installed in accordance with
the current Installation Code for Gas Burning
Appliances and Equipment, CGA B149, and
applicable Provincial regulations for the class;
which should be carefully followed in all cases.
Authorities having jurisdiction should be
consulted before installations are made.
IMPORTANT
This Instruction Manual is an integral
part of the product and must be
maintained in legible condition. It must
be given to the user by the installer
and kept in a safe place for future
reference.
WARNINGS!
MUST BE OBSERVED TO PREVENT
SERIOUS INJURY.
WARNING!
BEFORE ATTEMPTING TO
PERFORM ANY MAINTENANCE ON
THE UNIT, SHUT OFF ALL GAS AND
ELECTRICAL INPUTS TO THE UNIT.
WARNING!
THE EXHAUST VENT PIPE OF THE
UNIT OPERATES UNDER A
POSITIVE PRESSURE AND THEREFORE MUST BE COMPLETELY
SEALED TO PREVENT LEAKAGE
OF COMBUSTION PRODUCTS INTO
LIVING SPACES.
WARNING
DO NOT USE MATCHES, CANDLES,
FLAMES, OR OTHER SOURCES OF
IGNITION TO CHECK FOR GAS
LEAKS.
WARNING!
FLUIDS UNDER PRESSURE MAY
CAUSE INJURY TO PERSONNEL
OR DAMAGE TO EQUIPMENT
WHEN RELEASED. BE SURE TO
SHUT OFF ALL INCOMING AND
OUTGOING WATER SHUTOFF
VALVES. CAREFULLY DECREASE
ALL TRAPPED PRESSURES TO
ZERO BEFORE PERFORMING
MAINTENANCE.
WARNING!
ELECTRICAL VOLTAGES OF 120
VAC ARE USED IN THIS
EQUIPMENT. THEREFORE THE
COVER ON THE UNIT’S POWER
BOX (LOCATED ON THE FRONT
RIGHT SIDE OF THE UNIT UNDER
THE HOOD AND SHEET METAL
SIDE PANEL) MUST BE INSTALLED
AT ALL TIMES, EXCEPT DURING
MAINTENANCE AND SERVICING.
CAUTIONS!
Must be observed to prevent
equipment damage or loss of
operating effectiveness.
CAUTION!
Many soaps used for gas pipe leak
testing are corrosive to metals. The
piping must be rinsed thoroughly with
clean water after leak checks have
been completed.
CAUTION!
DO NOT use this boiler if any part has
been under water. Call a qualified
service technician to inspect and
replace any part that has been under
water.
1-1
Page 8
SAFETY PRECAUTIONS
1.2 EMERGENCY SHUTDOWN
If overheating occurs or the gas supply fails to
shut off, close the manual gas shutoff valve
(Figure 1-1) located external to the unit.
IMPORTANT
The Installer must identify and indicate
the location of the emergency shutdown
manual gas valve to operating personnel.
1.3 PROLONGED SHUTDOWN
After prolonged shutdown, it is recommended
that the startup procedures in Chapter 4 and the
safety device test procedures in Chapter 6 of
this manual be performed, to verify all systemoperating parameters. If there is an emergency,
turn off the electrical power supply to the
AERCO boiler and close the manual gas valve
located upstream the unit. The installer must
identify the emergency shut-off device.
Figure 1-1
Manual Gas Shutoff Valve
1-2
Page 9
SECTION 2 -INSTALLATION PROCEDURES
2.1. RECEIVING THE UNIT
Each KC1000 Boiler is shipped as a single
crated unit. The crated shipping weight of the
unit is approximately 1500 pounds, and must be
moved with the proper rigging equipment for
safety and to avoid damages. The unit should be
completely inspected for shipping damage and
completeness at the time of receipt from the
carrier and before the bill of lading is signed.
Each unit has Tip-N-Tell indicator on the outside
of the crate that indicates if the unit has been
turned on its side. If the Tip-N-Tell indicator is
tripped, do not sign for the shipment. Request a
freight claim and inspection by a claims adjuster
before proceeding or refuse delivery of the
equipment.
2.2. UNPACKING
Carefully unpack the unit. Take care not to
damage the unit jacket when cutting away
packaging materials. An inspection of the unit
should be made to determine if damage during
shipment occurred that was not indicated by the
Tip-N-Tell. The freight carrier should be notified
immediately if any damage is detected. The
following accessories come standard with each
INSTALLATION
unit and are packed separately within the unit’s
packing container
• Spare Spark Ignitor
• Spare Flame Detector
• Manual 1-1/4" Gas Shutoff Valve
• Drain Valve Assembly
• ASME Pressure Relief Valve
• Differential Regulator Spring:
P/N 122548 (Propane) or
P/N 124803 (Natural Gas)
• Ignitor Removal Tool (One per Site)
• Regulator Adjustment Tool (One per
site)
•Temperature/Pressure Gauge and
Fittings
• 2 Lifting Lugs
• Stainless Steel Condensate Cup
• Shell Cap
• Wing Nut for Shell Cap
Optional accessories are also separately packed
within the unit’s packing container. Standard and
optional accessories shipped with the unit
should be identified and put in a safe place until
installation or use.
Figure 2.1. Boiler Clearances
2-1
Page 10
2.3 INSTALLATION
The unit must be installed with the prescribed
clearances for service as shown in Figure 2.1.
The minimum
AERCO, are listed below. Local building codes
may require additional clearance and take
precedence
Minimum clearances required:
Sides 24"
Front 18"
Rear 18"
Top 18"
All gas piping, water piping, and electrical
conduit or cable must be arranged so that they
do not interfere with the removal of any cover, or
inhibit service or maintenance of the unit.
KEEP UNIT AREA CLEAR AND FREE
FROM COMBUSTIBLE MATERIALS AND
FLAMMABLE VAPORS AND LIQUIDS.
2.3.1. SETTING THE UNIT
Remove the unit from the wooden skid and
place in position using a block and tackle or
hoist attached to the lifting lugs, (see Fig. 2.2).
USE ONLY THE LIFTING LUGS TO MOVE
THE UNIT.
The KC-1000 is U/L approved for installation on
combustible flooring. A 4 to 6 inch high housekeeping concrete pad is recommended and
allows for sufficient drainage of the condensate.
It is suggested that units be secured using the
holes provided in the frame base. Piping must
not be used to secure the unit in place. See
drawing AP-A-816 in Appendix F for the base
frame dimensions.
In multiple unit installations, it is important to
plan the position of each unit. Sufficient space
for piping connections and future maintenance
requirements must be given. All piping must
include ample provision for expansion.
If installing a Combination Control (CCP)
system, it is important to identify and place the
Combination Mode units in the proper physical
location.
clearance dimensions, required by
WARNING!
Figure 2.2
Lifting Lug Location
2.3.2 SUPPLY AND RETURN PIPING
The locations of the 4" flanged system supply,
and return piping connections, to the unit are
shown in figure 2.3. The return connection is
located on the left side near the base of the
unit’s shell. The supply connection is located on
the left side near the top of the unit’s shell.
Whether installing single or multiple units, install
the piping and accessories as shown in the
appropriate piping diagram located in Appendix
G. For applications other than standard space
heating, consult the AERCO Boiler Application
Guide, GF-1070, or AERCO for the appropriate
piping schematics.
The minimum flow rate through the unit is 25
GPM and the maximum flow rate is 150 GPM.
Each unit is fitted with 4" flanges for high flow
application and the system velocity at the unit
return should not exceed 5 feet per second.
Each unit must have individual valves on the
supply, and return, for maintenance. In multiple
unit installations, the flow through each unit must
be balanced.
Every boiler plant must have a source of makeup water to it. As with any closed loop hydronic
system, air elimination and expansion equipment must be provided as part of the overall
installation. All piping MUST include ample
provision for expansion.
2-2
Page 11
Figure 2.3
Supply and Return Location
INSTALLATION
2.3.4 TEMPERATURE/PRESSURE
INDICATOR
The unit is supplied with one of two styles of
Temperature/Pressure Indicators that must be
installed in the tapping on the supply flange of
the unit (see Figs. 2.5a and 2.5b). A suitable
pipe compound should be used sparingly to the
threaded connection.
2.3.3 PRESSURE RELIEF AND DRAIN
VALVE INSTALLATION
An ASME rated Relief Valve is supplied with
each unit. The supplied pressure relief valve
setpoint will be 30, 50, 75, 100, or 150
ordered from the factory. Install the pressure
relief valve in the tapping provided opposite the
system supply connection, (see figure 2.4). The
pressure relief valve should be piped in the
vertical positionusing the fittings supplied. A
suitable pipe compound should be used on the
threaded connections, and excess should be
wiped off to avoid getting any into the valve
body. The discharge from the relief valve should
be piped to within 12 inches of the floor to
prevent injury in the event of a discharge.
The relief piping must be full size without
reduction. No valves, restrictions, or other
blockages should be allowed in the discharge
line. In multiple unit installations the relief valve
discharge lines must not
(connected), together. Each must be individually
run to a suitable discharge location. The drain
valve provided should be installed on the right
hand side of the unit towards the bottom of the
shell. The valve should be pointed in the down
position, (see Fig. 2.4).
psig as
be manifolded,
Figure 2.4
Relief and Drain Valve Location
Figure 2.5a
Pressure /Temperature Gauge Installation
2-3
Page 12
Figure 2.5b
Pressure/Temperature Gauge Installation
2.3.5 CONDENSATE PIPING
The KC Boiler is designed to condense. Therefore, the installation site must include suitable
provisions for condensate drainage or collection.
A stainless steel condensate cup is separately
packed within the unit’s shipping container. To
install the condensate cup, pro-ceed as follows:
1. Remove the left side panel and only the left
half of the rear cover to provide access to the
exhaust manifold and burner (Figure 2.6).
2. Insert the 1-3/4 inch manifold drain hose into
the condensate cup. Allow the cup to rest on
the floor directly beneath the manifold drain
hole (Figure 2.6).
3. Attach a length of 3/4 inch I.D. polypropylene
tubing to the condensate cup drain tube and
route it to a floor drain. If a floor drain is not
available, a condensate pump can be used to
remove the condensate to drain. The
condensate drain line must be removable for
routine main-tenance. Therefore, DO NOT
hard-pipe.
4. Replace the rear cover and side panel on the
unit.
Figure 2.6
Condensate Drain System Location
2.4. GAS SUPPLY PIPING
The AERCOGas Fired Equipment Gas Components and Supply Design Guide (GF-1030) must
be consulted before any gas piping is designed
or started.
WARNING!
DO NOT USE MATCHES, CANDLES,
FLAMES OR OTHER SOURCES OF
IGNITION TO CHECK FOR GAS LEAKS.
CAUTION!
Soaps used for gas pipe leak testing can be
corrosive to metals. Piping must be rinsed
thoroughly with clean water after leak
checks have been completed.
NOTE:
All gas piping must be arranged so that it
does not interfere with removal of any
cover, inhibit service or maintenance, or
prevent access between the unit and walls,
or another unit.
2-4
Page 13
INSTALLATION
The location of the 1-1/4" inlet gas connection is
on the right side of the unit as shown in Figure
2.7.
All pipe should be de-burred and internally
cleared of any scale or iron chips before
installation. No flexible connectors or nonapproved gas fittings should be installed. Piping
should be supported from floor or walls only and
must not be secured to the unit.
A suitable piping compound, approved for use
with gas, should be used spar ingly. Any excess
must be wiped off to prevent clogging of
components.
To avoid damage to the unit, when pressure
testing gas piping, isolate the unit from the
supply gas piping. At no time should there be
more than 14” W.C. the unit. Bubble test all
external piping thoroughly for leaks using a soap
and water solution or suitable equivalent. The
gas piping must meet all applicable codes.
Figure 2.7
Gas Supply Regulator and Manual Shut -Off
Valve Location
2.4.1 GAS SUPPLY PRESSURE
REGULATOR
A mandatory external, in-line, supply gas regulator (supplied by others) must be installed
upstream of each KC1000 and positioned as
shown in Figure 2.7. Union connections should
be placed in the proper locations to allow
maintenance of the regulator if required. The
regulator must be capable of providing the
required gas pressures for natural gas and
propane units as described in the paragraphs
which follow.
Natural Gas:
The maximum static inlet pressure to the unit
must be no more than 14” W.C. Minimum gas
pressure is 8.8” W.C. for FM gas trains and
9.2” W.C. for IRI gas trains when the unit is
firing at maximum input. Gas pressure should
not exceed 11.5” W.C. at any time when firing.
Proper sizing of the gas supply regulator in
delivering the correct gas flow and outlet
pressure is mandatory. The gas supply
pressure regulator must maintain the gas
pressure at a regulated 8.8” W.C. minimum
for FM gas trains and 9.2” W.C. for IRI gas
trains at maximum BTU input (970,000
BTU/HR) for natural gas installations. The
supply gas regulator must be of sufficient
capacity volume, (1000 cfh), for the unit and
should have no more than 1" droop from
minimum to full fire.
Propane:
The maximum static inlet pressure to the unit
must be no more than 14” W.C. Minimum gas
pressure is 7.7” W.C. for FM gas trains and
8.1” W.C. for IRI gas trains when the unit is
firing at maximum input. Gas pressure should
not exceed 11.5” W.C. at any time when firing.
Proper sizing of the gas supply regulator in
delivering the correct gas flow and outlet
pressure is mandatory. The gas supply
pressure regulator must maintain the gas
pressure at a regulated 7.7” W.C. minimum
for FM gas trains and 8.1” W.C. for IRI gas
trains at maximum BTU input (1,000,000
BTU/HR) for propane installations. The supply
gas regulator must be of sufficient capacity
volume, (400 cfh), for the unit and should
have no more than 1" droop from minimum to
full fire.
The supply gas regulator must be rated to
handle the maximum incoming supply gas
pressure. When the gas supply pressure will not
exceed 14” W.C. a non-lo ck up or flow through
style regulator may be used. When supply gas
pressure will exceed 14” W.C., a lock up style
regulator must be used. The gas supply
regulator must be propery vented to outdoors.
Consult the local gas utility for exact
ments concerning venting of supply gas
regulators.
require-
CAUTION!
A lockup style regulator must be used when
gas supply pressure exceeds 14” W.C.
2-5
Page 14
2.4.2 MANUAL GAS SHUTOFF VALVE
A 1-1/4” manual gas shut-off valve is furnished
with each unit. The valve should be positioned
as shown in Figure 2.7. The manual gas shut-of
valve must be installed upstream of the supply
regulator in a readily accessible location.
2.4.3 IRI GAS TRAIN KIT
The IRI gas train is an optional gas train
required in some areas by code or for insurance
purposes. The IRI gas train is factory pre-piped
and wired. (See Appendix F, Drawing No. SD-A-
660).
2.5 ELECTRICAL SUPPLY
The AERCO Gas Fired Equipment Electrical
Power Wiring Guide, (GF-1060), must be
consulted in addition to the following material
before wiring to the unit is started. AC power
connection to the unit are made at the Power
Box.This box is located on the front right side of
the unit as shown in Figure 2.8. Conduit should
be run from the knockouts in the side of the box
in such a manner that it does not interfere with
the removal of any sheet metal covers. A flexible
electrical connection may be utilized to allow the
covers to be easily removed.
POWER BOX
NOTE:
All electrical conduit and hardware should
be installed so that it does not interfere with
the removal of any cover, inhibit service or
maintenance, or prevent access between
the unit and walls or another unit.
2.5.1 ELECTRICAL REQUIREMENTS
Electrical requirements for each unit are 120
VAC, Single Phase, 60 Hz, 20 Amps from a
dedicated electrical circuit. No other devices
should be on the same electrical circuit as the
KC1000 unit. A means for disconnecting AC
power from the unit (such as a service switch)
must be installed near the unit for normal operation and maintenance. All electrical connections
should be made in accordance with the National
Electrical Code and/or with any applicable local
codes.
The AC power wiring diagram is shown in Figure
2.9.
FRAME
2-6
SSOV
ACTUATOR
Figure 2.8
AC Power Box Location
BLOWER
Figure 2.9
AC Power Wiring Diagram
2.6 MODE OF OPERATION and FIELD
CONTROL WIRING
The KC Boiler is available in several different
modes of operation. While each unit is factory
configured and wired for the mode specified on
the equipment order, some field wiring may be
required to complete the installation. This wiring
is typically routed to the Input/Output (I/O) Box
located on the left side of the unit beneath the
removable side panel (see Fig. 2.10). Field
wiring for each particular mode of operation is
described in the following paragraphs. For
additional information concerning modes of
operations, refer to Section 5.
Page 15
Figure 2.10
Input/Output (I/O) Box Location
INSTALLATION
2.6.1 CONSTANT SETPOINT MODE
The Constant Setpoint Mode is used when it is
desired to have a fixed setpoint that does not
deviate. No wiring connections other than
electrical supply connections are required for
this mode. However, if desired, fault monitoring
or enable/disable interlock wiring can be utilized
(see paragraphs 2.7.9 and 2.7.10).
2.6.2 INDOOR/OUTDOOR RESET MODE
This mode of operation increases supply water
temperature as outdoor temperatures decrease.
An outside air temperature sensor (AERCO PN
122790) is required. The sensor MUST BE
wired to the I/O Box wiring terminals (see Fig.
2.11). For more information concerning the
outside air sensor installation, refer to paragraph
2.7.1. For programming and setup instructions
concerning the indoor/outdoor-reset mode of
operation, refer to Section 5, paragraph 5.1.
OUTDOOR SENSOR IN
SENSOR COMMON
AUX SENSOR IN
NOT USED
ANALOG IN
B.M.S. (PWM) IN
SHIELD
mA OUT
RS-485
COMM.
+
+
-
+
+
G
-
RELAY CONTACTS:
120 VAC, 30 VDC
5 AMPS RESISTIVE
DANGER
REMOTE INTL'K IN
EXHAUST SWITCH IN
DELAYED INTL'K IN
NOT USED
NC
FAULT RELAY
COM
120 VAC, 5A, RES
NO
NC
AUX RELAY
COM
NO
120 VAC, 5A, RES
NOT USED
120 VAC USED
NOT USED
IN THIS BOX
Figure 2.11
I/O Box Terminal Strip
2-7
Page 16
2.6.3 BOILER MANAGEMENT SYSTEM
(BMS) MODE
NOTE
BMS Model 168 can utilize either pulse
width modulation (PWM) or RS485
Modbus signaling to the Boiler. BMS II
Model 5R5-384 can utilize only RS485
signaling to the Boiler.
When using an AERCO Boiler Management
System (BMS), the field wiring is connected
between the BMS Panel and each Boiler’s I/O
Box terminal strip (Figure 2-11). Twisted
shielded pair wire from 18 to 22 AWG must be
utilized for the connections. The BMS Mode can
utilize either pulse width modulation (PWM)
signaling, or RS485 Modbus signaling. For PWM
signaling, connections are made from the
AERCO Boiler Management System to the
B.M.S. (PWM) IN terminals on the I/O Box
terminal strip. For RS485 Modbus signaling,
connections are made from the BMS to the
RS485 COMM terminals on the I/O Box terminal
strip. Polarity must be maintained and the shield
must be connected only at the AERCO BMS.
The boiler end of the shield must be left floating.
For additional instructions, refer to Chapter 5,
paragraph 5.6 in this manual. Also, refer to GF108M (BMS Model 168) and GF-124 (BMS II
Model 5R5-184), BMS -Operations Guides.
2.6.4 REMOTE SETPOINT and DIRECT
DRIVE MODES
The KC1000 Boiler can accept several types of
signal formats from an Energy Management
System or other source to control either the
setpoint (Remote Setpoint Mode) or firing rate
(Direct Drive Mode) of the Boiler. These formats
are:
4 to 20 mA/1 to 5 Vdc
0 to 20 mA/0 to 5 Vdc
PWM – (Pulse Width Modulated signal. See
paragraph 2.7.4)
Network – (RS485 Modbus. See para. 2.7.7)
While it is possible to control one or more boilers
using one of the above modes of operation, it
may not be the method best suited for the
application. Prior to selecting one of the above
modes of operation, it is recommended that you
consult with your local AERCO representative or
the factory for the mode of operation that will
work best with your application. For more
information on wiring the 4 to 20 mA / 1to 5VDC
or the 0 to 20 mA / 0 to 5 VDC, see paragraph
2.7.3.
2.6.5 COMBINATION MODE
NOTE
Only BMS Model 168 can be utilized for
the Combination Mode, not the BMS II
(Model 5R5-384).
With a Combination Mode unit, field wiring is
between the unit’s I/O Box, the CCP
(Combination Control Panel), and the BMS
Model 168 (Boiler Management System). The
wiring must be done using a shielded twisted
pair of 22 AWG wire. Polarity must be
maintained between the unit, the CCP, and the
BMS. For further instructions and wiring
diagrams, refer to the GF-108 Boiler
Management System Operations Guide and the
CCP-1 data sheet.
2.7 I/O BOX CONNECTIONS
The types of input and output/signals and
devices to be connected to the I/O Box terminals
shown in Figure 2.11 are described in the
following paragraphs.
CAUTION!
DO NOT make any connections to the I/O
Box terminals labeled “NOT USED”.
Attempting to do so may cause equipment
damage.
2.7.1 OUTDOOR SENSOR IN
An outdoor air temperature sensor (AERCO Part
No. 122790) will be required mainly for the
Indoor/Outdoor Reset mode of operation. It can
also be used with another mode if it is desired to
use the outdoor sensor enable/disable feature.
This feature allows the boiler to be enabled or
disabled based on the outdoor air temperature.
The factory default for the outdoor sensor is
DISABLED. To enable the sensor and or choose
an enable/disable outdoor temperature, see the
Configuration menu in Section 3 and Appendix
A.
The outdoor sensor may be wired up to 200 feet
from the boiler and is connected to the
OUTDOOR SENSOR IN and SENSOR
COMMON terminals in the I/O box (see Figs.
2.10 and 2.11). Wire the sensor using a twisted
shielded pair cable of 18-22 AWG wire. There is
no polarity when terminating the wires. The
2-8
Page 17
INSTALLATION
shield is to be connected only to the terminals
labeled SHEILD in the I/O Box. The sensor end
of the shield must be left free and ungrounded.
When mounting the sensor, it must be located
on the North side of the building where an
average outside air temperature is expected.
The sensor must be shielded form direct sunlight
as well as impingement by the elements. If a
shield is used, it must allow for free air
circulation.
2.7.2 AUX SENSOR IN
The AUX SENSOR IN terminals can be used to
add an additional temperature sensor for
monitoring purposes. This input is always
enabled and is a view only input that can be
seen in the operating menu. The sensor must be
wired to the AUX SENSOR IN and SENSOR
COMMON and must be similar to AERCO
BALCO wire sensor P/N 12449. A resistance
chart for this sensor is provided in Appendix C.
2.7.3 ANALOG IN
The ANALOG IN + and – terminals are used
when an external signal is used to drive the
firing rate (Direct Drive Mode) or change the
setpoint (Remote Setpoint Mode) of the Boiler.
Either a 4 to 20 mA / 1 to 5 VDC or a 0 to 20
mA / 0 to 5 VDC signal may be used to vary the
setpoint or firing rate. The factory default setting
is 4 to 20 mA / 1 to 5 VDC, however this may be
changed to 0 to 20 mA / 0 to 5 VDC using the
Configuration Menu described in Section 3. If
voltage rather than current is selected as the
drive signal, a DIP switch must be set on the
PMC Board located inside the Control Box.
Contact the AERCO factory for information on
setting DIP switches.
All of the supplied signals must be floating
(ungrounded) signals. Connections between the
source and the Boiler’s I/O Box must be made
using twisted shielded pair of 18 –22 AWG wire
such as Belden 9841(see Fig. 211). Polarity
must be maintained and the shield must be
connected only at the source end and must be
left floating (not connected) at the Boiler’s I/O
Box.
Whether using voltage or current for the drive
signal, they are linearly mapped to a 40°F to
240°F setpoint or a 0% to 100% firing rate. No
scaling for these signals is provided.
2.7.4 B.M.S. (PWM) IN
NOTE
Only BMS Model 168 can utilize Pulse
Width Modulation (PWM), not the BMS II
(Model 5R5-384).
These terminals are used to connect the
AERCO Boiler Management System (BMS)
Model 168 to the unit. The BMS Model 168
utilizes a 12 millisecond, ON/OFF duty cycle.
This duty cycle is Pulse Width Modulated (PWM)
to control firing rate. A 0% firing rate = a 5% ON
pulse and a 100% firing rate = a 95% ON pulse.
2.7.5 SHIELD
The SHIELD terminals are used to terminate any
shields used on sensor wires connected to the
unit. Shields must only be connected to these
terminals.
2.7.6 mA OUT
These terminals provide a 4 to 20 mA output
that can be used to monitor setpoint (40°F to
220°F), outlet temperature (30°F to 245°F), or
fire rate (0% to 100%). This function is enabled
in the Configuration Menu (Section 3, Table 3.4).
2.7.7 RS-485 COMM
These terminals are used for RS-485 MODBUS
serial communication between the unit and an
external “Master”, such as a Boiler Management
System or other suitable device.
2.7.8 EXHAUST SWITCH IN
These terminals permit an external exhaust
switch to be connected to the exhaust manifold
of the boiler. The exhaust sensor should be a
normally open type switch (such as AERCO Part
No. 123463) that closes (trips) at 500
o
F.
2.7.9 INTERLOCKS
The unit offers two interlock circuits for interfacing with Energy Management Systems and
auxiliary equipment such as pumps or louvers.
These interlocks are called the Remote Interlock
and Delayed Interlock (Fig. 2.11). The wiring
terminals for these interlocks are located inside
the I/O Box on the left side of the unit. The I/O
Box cover contains a wiring diagram which
shows the terminal strip locations for these interlocks which are labeled REMOTE INTL’K IN and
DELAYED INTL’K IN. Both interlocks, described
in the following paragraphs, are factory wired in
the closed position.
2-9
Page 18
NOTE:
Both the Delayed Interlock and Remote
Interlock must be in the closed position to
allow the unit to fire.
2.7.9.1 REMOTE INTERLOCK IN
The remote interlock circuit (REMOTE INTL’K
IN) is provided to remotely start (enable) and
stop (disable) the Boiler if desired. The circuit is
24 VAC and comes factory pre-wired closed
(jumpered).
2.7.9.2 DELAYED INTERLOCK IN
The delayed interlock circuit (DELAYED INTL’K
IN) is typically used in conjunction with the
auxiliary relay described in paragraph 2.8. This
interlock circuit is located in the purge section of
the start string. It can be connected to the
proving device (end switch, flow switch etc.) of
an auxiliary piece of equipment started by the
boiler’s auxiliary relay. The delayed interlock
must be closed for the boiler to fire. If the
delayed interlock is connected to a proving
device that requires time to close (make), a time
delay (Aux Start On Dly) that holds the start
sequence of the boiler long enough for for a
proving switch to make can be programmed.
Should the proving switch not prove within the
programmed time frame, the boiler will shut
down. The Aux Start On Dly can be
programmed from 0 to 120 seconds. This option
is locate in the Configuration Menu (Section 3).
2.7.10 FAULT RELAY
The fault relay is a single pole double throw
(SPDT) relay having a normally open and
normally close set of relay contacts that are
rated for 5 amps at 120 VAC and 5 amps at 30
VDC. The relay energizes when any fault condition occurs and remains energized until the
fault is cleared and the CLEAR button is
depressed. The fault relay connections are
shown in Figure 2.11.
2.8 AUXILIARY RELAY CONTACTS
Each KC Boiler is equipped with a single pole
double throw (SPDT) relay that is energized
when there is a demand for heat and deenergized after the demand for heat is satisfied.
The relay is provided for the control of auxiliary
equipment, such as pumps and louvers, or can
be used as a Boiler status indictor (firing or not
firing). Its contacts are rated for 120 VAC @ 5
amps. Refer to Figure 2.11 to locate the AUX
RELAY terminals for wiring connections.
2.9 FLUE GAS VENT INSTALLATION
The AERCO Venting and Combustion Air Guide,
GF-1050, must be consulted before any flue or
inlet air venting is designed or installed.
Suitable, U/L approved, positive pressure,
water-tight vent materials as specified in
AERCO’s GF-1050, must be used for safety and
UL certification. Because the unit is capable of
discharging low temperature exhaust gases, the
flue must be pitched back to the unit a minimum
of 1/4" per foot to avoid any condensate pooling
and to allow for proper drainage.
While there is a positive flue pressure during
operation, the combined pressure drop of vent
and combustion air systems must not exceed
140 equivalent feet of 0.81” W.C. Fittings as well
as pipe lengths must be calculated as part of the
equivalent length. For a natural draft installation
the draft must not exceed - 0.25” W.C. These
factors must be planned into the vent
installation. If the maximum allowable equivalent
lengths of piping are exceeded, the unit will not
operate properly or reliably.
2.10 COMBUSTION AIR
The AERCO Venting and Combustion Air Guide,
GF-1050, MUST be consulted before any flue or
combustion supply air venting is designed or
started. Combustion air supply is a direct
requirement of ANSI 223.1, NFPA-54, and local
codes. These codes should be consulted before
a permanent design is determined.
The combustion air must be free of chlorine,
halogenated hydrocarbons, or other chemicals
that can become hazardous when us ed in gasfired equipment. Common sources of these
compounds are swimming pools, degreasing
compounds, plastic processing and refrigerants.
Whenever the environment contains these types
of chemicals, combustion air must be supplied
from a clean area outdoors for the protection
and longevity of the equipment.
The more common methods of supplying
combustion air are outlined below. For more
information on combustion air, consult the
AERCO GF-1050, Venting and Combustion Air
Guide.
2.10.1 COMBUSTION AIR FROM
OUTSIDE THE BUILDING
Air supplied from outside the building must be
provided through two permanent openings. For
each unit these two openings must have a free
area of not less than one square inch for each
4000 BTUs input of the equipment or 250
2-10
Page 19
INSTALLATION
square inches of free area. The free area must
take into account restrictions such as louvers
and bird screens.
2.10.2 COMBUSTION AIR FROM INSIDE
THE BUILDING
When combustion air is provided from within the
building, it must be supplied through two
permanent openings in an interior wall. Each
opening must have a free area of not less than
one square inch per 1000 BTUH of total input or
1000 square inches of free area. The free area
must take into account any restrictions such as
louvers.
NOTE
KC1000 units equipped with Low NOx
Burners require an optional Cold Air
Damper for operation with Direct Vent/
Sealed Combustion. The Cold Air Damper
is also required when the unit is installed
in an area where the combustion air
supply temperature can drop below 55°F.
Refer to the following paragraph (2.10.3)
and GF-1050 for installation details.
2.10.3 SEALED COMBUSTION
The KC Boiler is UL approved for 100% sealed
combustion application when installed properly.
When a sealed combustion air application is
installed, the sealed combustion air piping must
be deducted from the maximum allowable
discharge piping amounts. Each unit must have
a minimum 6" diameter connection made to the
special Inlet Air Adapter # GP-18917 available
from AERCO. This adapter bolts directly on to
the air inlet of the unit’s blower. See installation
instructions with adapter. All inlet air ducts must
be sealed air tight.
In addition, Cold Air Damper # 99026 must be
installed. It should be located along the inlet duct
run as close as possible to the KC1000 (See
Figure 2.12). The Cold Air Damper must be
placed on individual sections (one Damper per
unit), not in a manifold section. The adjustment
screw on the Damper should be moved to the
center of the slot position and tightened 1/2 turn
past “finger-tight”. DO NOT over-tighten.
See AERCO Venting Guide GF-1050 for further
details.
Figure 2.12
Sealed Combustion Air Connection
2-11
Page 20
Page 21
CONTROL PANEL OPERATING PROCEDURES
SECTION 3 - CONTROL PANEL OPERATING PROCEDURES
3.1. INTRODUCTION
The information in this Section provides a guide
to the operation of the KC1000 Boiler using the
Control Panel mounted on the front of the unit.
It is imperative that the initial startup of this unit
be performed by factory trained personnel.
Operation prior to initial startup by factory
trained personnel will void the equipment
warranty. In addition, the following WARNINGS
and CAUTIONS must be observed at all times.
CAUTION:
All initial installation procedures must be
satisfied before attempting to start the unit.
WARNING:
THE ELECTRICAL VOLTAGES IN THIS
SYSTEM INCLUDE 120 AND 24 VOLTS
AC. IT MUST NOT BE SERVICED OR
ACCESSED BY OTHER THAN FACTORY
CERTIFIED SERVICE TECHNICIANS.
WARNING:
DO NOT ATTEMPT TO DRY FIRE THE
BOILER. STARTING THE UNIT WITHOUT
A FULL WATER LEVEL CAN SERIOUSLY
DAMAGE THE UNIT AND MAY RESULT IN
PERSONNEL INJURY OR PROPERTY
DAMAGE. THIS SITUATION WILL VOID
ANY WARRANTY.
3.2. CONTROL PANEL DESCRIPTION
The KC1000 Control Panel shown in Figure 3-1
contains all of the controls, indicators and
displays necessary to operate, adjust and
troubleshoot the KC1000 Boiler. These operating controls, indicators and displays are
listed and described in Table 3-1. Additional
information on these items are provided in the
individual operating procedures provided in this
Section.
Figure 3-1. Control Panel Front View
3-1
Page 22
CONTROL PANEL OPERATING PROCEDURES
Table 3-1. Operating Controls, Indicators and Displays
ITEM
NO.
CONTROL, INDICATOR
OR DISPLAY
1 LED Status Indicators Four Status LEDs indicate the current operating status as
follows:
COMM
MANUAL
REMOTE
DEMAND
2 VFD Display Vacuum Fluorescent Display (VFD) consists of 2 lines, each
3
OUTLET
TEMPERATURE
Display
4 RS-232 Port Port permits a Laptop Computer or External Modem to be
5 READY Indicator Lights when all Pre-Purge conditions have been satisified.
6 ON/OFF Switch Enables and disables boiler operation.
7
LOW WATER LEVEL
TEST/RESET Switches
8 FAULT Indicator Red FAULT LED indicator lights when a boiler alarm
9 CLEAR Key Turns off the FAULT indicator and clears trhe alarm message
10 MENU Keypad Consists of 6 keys which provide the following functions for
MENU
BACK
Lights when RS-232 communication is occurring
Lights when the unit is being controlled using the front panel
keypad.
Lights when the unit is being controlled by an external signal
from an Energy Management System
Lights when there is a demand for heat.
capable of displaying up to 16 alphanumeric characters. The
information displayed includes:
Startup Messages
Alarm Messages
Operating Status Messages
Menu Selection
3–Digit, 7–Segment LED display continuously displays the
outlet water temperature. The °F or °C LED next to the
display lights to indicate whether the displayed temperature is
in degrees Fahrenheit or degrees Celsius.
connected to the boiler Control Panel.
Allow the operator to test the operation of the water level
monitor.
Pressing TEST opens the water level probe circuit and
simulates a Low Water Level alarm.
Pressing RESET resets the water level monitor circuit.
Pressing CLEAR resets the display.
condition occurs. An alarm message will appear in the VFD.
if the alarm is no longer valid. Lockout type alarms will be
latched and cannot be cleared by simply pressing this key.
Troubleshooting may be required to clear these types of
alarms
the Control Panel Menus:
Steps through the main menu categories shown in Figure 3-2.
The Menu categories wrap around in the order shown.
Allows you to go back to the previous menu level without
changing any information. Continuously pressing this key will
bring you back to the default status display in the VFD. Also,
this key allows you to go back to the top of a main menu
category.
FUNCTION
3-2
Page 23
ITEM
NO.
10
(Cont.)
CONTROL PANEL OPERATING PROCEDURES
Table 3-1. Operating Controls, Indicators and Displays - Continued
CONTROL, INDICATOR
OR DISPLAY
▲ (Up) Arrow When in one of the main menu categories (Figure 3-2),
pressing this key will select the displayed menu category. If
the CHANGE key was pressed and the menu item is flashing,
pressing the ▲ arrow key will increment the selected setting.
▼ (Down) Arrow When in one of the main menu categories (Figure 3-2),
pressing this key will select the displayed menu category. If
the CHANGE key was pressed and the menu item is flashing,
pressing the ▼ (Down) arrow key will increment the selected
setting.
FUNCTION
CHANGE
Permits a setting to be changed (edited). When the
CHANGE key is pressed, the displayed menu item will begin
to flash. Pressing the ▲ or ▼ arrow key when the item is
flashing will increment or decrement the displayed setting.
ENTER
Saves the modified menu information in memory. The
display will stop flashing.
11 AUTO/MAN Switch This switch toggles the boiler between the Automatic and
Manual modes of operation. When in the Manual (MAN)
mode, the front panel controls are enabled and the MANUAL
status LED lights.
When in the Automatic (AUTO) mode, the MANUAL status
LED will be off and the front panel controls disabled.
12 FIRE RATE Bargraph 20 segment red LED bargraph continuously shows the Fire
Rate in 5% increments from 0 to 100%
3.3. CONTROL PANEL MENUS
The Control Panel incorporates an extensive
menu structure which permits the operator to set
up, and configure the unit. The menu structure
consists of four major menu categories as
shown in Figure 3-2. Each of the menus shown,
contain options which permit operating
parameters to be viewed or changed. The
menus are protected by a password to prevent
unauthorized use.
Prior to entering the correct password, the
options contained in the Operating, Setup,
Configuration and Tuning Menu categories can
be viewed. However, with the exception of
Internal Setpoint Temperature (Configuration
Menu), none of the viewable menu options can
be changed.
Once the valid password (159) is entered, the
options listed in the Setup, Configuration and
Tuning menus can be viewed and changed, if
3.3.1. Menu Processing Procedure
Accessing each menu and option is accomplished using the Menu Keys shown in Figure 3-
1. Therefore, it is imperative that you be
thoroughly familiar with the following basic steps
before attempting to perform specific menu
procedures.
1. The Control Panel will normally be in the
Operating Menu and the VFD will display the
current unit status. Pressing the ▲ or ▼
arrow key will display the other available data
items in the Operating Menu.
2. Press the MENU key. The display will show
the Setup Menu which is the next menu
category shown in Figure 3-2. This menu
contains the Password option which must be
entered if other menu options will be
changed.
3. Continue pressing the MENU key until the
desired menu is displayed.
desired.
3-3
Page 24
CONTROL PANEL OPERATING PROCEDURES
4. With the desired menu displayed, press the
▲ or ▼ arrow key. The first option in the
selected menu will be displayed.
5. Continue to press the ▲ or ▼ arrow key until
the desired menu option is displayed.
Pressing the ▲arrow key will display the
available menu options in the Top-Down
sequence. Pressing the ▼ arrow key will
display the options in the Bottom-Up
sequence. The menu options will wraparound after the first or last available option
is reached.
6. To change the value or setting of a displayed
menu option, press the CHANGE key. The
displayed option will begin to flash. Continue
to press the ▲ or ▼ arrow key for the option
to be changed. The available menu option
choices will be displayed. The menu option
choices do not wrap around.
7. To select and store a changed menu option,
press the ENTER key.
OPERATION
PASSWORD
SETUP
CONFIGURATION
NOTE:
The following paragraphs provide brief descriptions of the options contained in each menu.
Refer to Appendix A for detailed descriptions of
each menu option. Refer to Appendix B for
listings and descriptions of displayed startup,
status and error messages.
3.4. OPERATING MENU
The Operating Menu displays a number of key
operating parameters for the unit as listed in
Table 3-2. This menu is “Read-Only” and does
not allow personnel to change or adjust any of
the displayed items. Since this menu is “ReadOnly”, it can be viewed at any time without
entering a password. Press the ▲ arrow key to
display the menu items in the order listed (TopDown). Pressing the ▼ arrow key will display
the menu items in reverse order (Bottom-Up).
3.5. SETUP MENU
The Setup Menu (Table 3-3) permits the
operator to set the unit password which is
required to change any of the menu options. To
prevent unauthorized use, a previously entered
password entry will time-out after 1 hour.
Therefore, the password must be reentered
when required. In addition to permitting
password entries, the Setup Menu is also used
to enter date and time, language to be used for
display messages, units of temperature
measurements and entries required for external
communication and control of the unit via the
RS-232 port. A view-only software version
display is also provided to indicate the current
Control Box software version.
3-4
TUNING
Figure 3-2. Menu Structure
Page 25
CONTROL PANEL OPERATING PROCEDURES
NOTE
The Outdoor Temp display item shown with an asterisk in Table 32 will not be displayed unless the Outdoor Sensor function has
been enabled in the Configuration Menu (Table 3-4).
Table 3-2. Operating Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Status Message
Active Setpoint 40°F 240°F
Aux Temp 30°F 245°F
Outdoor Temp* -70°F 130°F
Fire Rate In 0% Max Fire Rate
Flame Strength 0% 100%
Run Cycles 0 999,999
Run Hours 0 999,999
Fault Log 0 9 0
Table 3-3. Setup Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Passsword 0 9999 0
Language English English
Time 12:00 am 11:59 pm
Date 01/01/00 12/31/99
Unit of Temp Fahrenheit
Comm Address 0 127 0
Baud Rate 2400
Software Ver 0.00 Ver 9.99
3.6. CONFIGURATION MENU
The Configuration Menu shown in Table 3-4
permits adjustment of the Internal Setpoint
(Setpt) temperature regardless of whether the
valid password has been entered. Setpt is
required for operation in the Constant Setpoint
mode. The remaining options in this menu
require the valid password to be entered, prior to
changing existing entries. This menu contains a
number of other configuration settings which
may or may not be displayed, depending on the
current operating mode setting.
Fahrenheit
Celsius
9600
4800
9600
19.2K
NOTE:
The Configuration Menu settings shown in
Table 3-4 are Factory-Set in accordance
with the requirements specified for each
individual order. Therefore, under normal
operating conditions, no changes will be
required.
3-5
Page 26
CONTROL PANEL OPERATING PROCEDURES
Table 3-4. Configuration Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Internal Setpt Lo Temp Limit Hi Temp Limit 130°F
Unit Type Boiler
Unit Size 0.5 MBTU
Boiler Mode Constant Setpoint
Remote Signal
(If Mode = Remote
Setpoint, Direct Drive
or Combination)
Bldg Ref Temp
(If Boiler Mode =
Outdoor Reset)
Reset Ratio
(If Boiler Mode =
Outdoor Reset)
Outdoor Sensor Enabled or Disabled Disabled
System Start Tmp
(If Outdoor Sensor =
Enabled)
Setpt Lo Limit 40°F Setpt Hi Limit 60°F
Setpt Hi Limit Setpt Lo Limit 240°F 200°F
Temp Hi Limit 40°F 240°F 215°F
Max Fire Rate 40% 100% 100%
Pump Delay Timer 0 min 30 min 0 min
Aux Start On Dly 0 sec 120 sec 0 sec
Failsafe Mode Shutdown or Constant Setpt Shutdown
mA Output Setpoint, Outlet Temp,
Lo Fire Timer 2 sec 120 sec 2 sec
Setpt Limiting Enabled or Disabled Disabled
Setpt Limit Band 0°F 10°F 5°F
40°F 240°F 70°F
30°F 100°F 60°F
Water Heater
1.0 MBTU
1.5 MBTU
2.0 MBTU
2.5 MBTU
3.0 MBTU
Remote Setpoint
Direct Drive
Combination
Outdoor Reset
4 – 20 mA/1 – 5V
0 -20 mA/0 – 5V
PWM Input (BMS)
Network
0.1 9.9 1.2
Fire Rate Out, Off
Boiler
1.0 MBTU
Constant
Setpoint
4 – 20 mA,
1-5V
Off
3-6
Page 27
CONTROL PANEL OPERATING PROCEDURES
3.7. TUNING MENU
The Tuning Menu items in Table 3-5 are Factory
set for each individual unit.
Table 3-5. Tuning Menu
Available Choices or Limits
Menu Item Display Minimum Maximum Default
Prop Band 1°F 120°F 70°F
Integral Gain 0.00 2.00 1.00
Derivative Time 0.0 min 2.0 min 0.0 min
Reset Defaults? Yes
3.8. START SEQUENCE
When the Control Box ON/OFF switch is set to
the ON position, it checks all pre-purge safety
switches to ensure they are closed. These
switches include:
• Safety Shut-Off Valve Proof of Closure
(POC) switch
• Low Water Level switch
• High Water Temperature switch
• High Gas Pressure switch
• Low Gas Pressure switch
If all of the above switches are closed, the
READY light above the ON/OFF switch will light
and the unit will be in the Standby mode.
When there is a demand for heat, the following
events will occur:
NOTE:
If any of the Pre-Purge safety device switches
are open, the appropriate fault message will be
displayed. Also, the appropriate fault messages
will be displayed throughout the start sequence,
if the required conditions are not observed.
1. The DEMAND LED status indicator will light.
2. The unit checks to ensure that the proof of
closure switch in the Safety Shut-Off Valve
(SSOV) is closed (Figure 3-3).
Do not change these menu entries unless
specifically requested to do so by FactoryTrained personnel.
No
No
Are You Sure?
Figure 3-3.
Safety Shut-Off Valve
3. With all required safety switches closed, a
purge cycle will be initiated and the following
events will occur:
3-7
Page 28
CONTROL PANEL OPERATING PROCEDURES
(a) Blower relay energizes and turns on
blower.
(b) Air/Fuel Valve rotates to the full-open
purge position and closes purge position
switch. The dial on the Air/Fuel Valve
(Figure 3-4) will read 100 to indicate that
the valve is full-open (100%).
(c) The FIRE RATE bargraph will show
100%.
STEPPER
MOTOR
DIAL
(DETAIL “A”)
Figure 3-5.
Blower Proof Switch
5. Upon completion of the purge cycle, the
Control Box initiates an ignition cycle and the
following events occur:
100
DETAIL "A"
Figure 3-4.
Air/Fuel Valve In Purge Position
4. Next, the blower proof switch (Figure 3-5)
closes and the display will show Purging and
indicate the elapsed time of the purge cycle
in seconds. The normal (default) time for the
purge cycle is 7 seconds.
(a) The Air/Fuel Valve rotates to the low-fire
ignition position and closes the ignition
switch. The dial on the Air/Fuel Valve
(Figure 3-6) will read between 25 and 35
to indicate that the valve is in the lowfire position.
(b) The igniter relay is activated and
provides ignition spark.
(c) The gas Safety Shut Off Valve (SSOV)
is energized (opened) allowing gas to
flow into the Air/Fuel Valve.
6. Up to 7 seconds will be allowed for ignition to
be detected. The igniter relay will be turned
off one second after flame is detected.
7. After 2 seconds of continuous flame, Flame Proven will be displayed and the flame
strength will be indicated. After 5 seconds,
the current date and time will be displayed in
place of the flame strength.
3-8
Page 29
CONTROL PANEL OPERATING PROCEDURES
8. With the unit firing properly, it will be
controlled by the temperature controller
circuitry. The FIRE RATE will be continu-
ously displayed on the front panel bargraph.
9. Once the demand for heat has been
satisfied, the Control Box will turn off the gas
BLOWER
BURNER
valve. The blower relay will be deactivated
and the Air/Fuel Valve will be closed.
Standby will be displayed.
3.9. START/STOP LEVELS
The start and stop levels are the fire rate
percentages that start and stop the unit, based
on load. These levels are Factory preset as
follows:
• Start Level: 20%
• Stop Level: 16%
Normally, these settings should not require
adjustment.
Figure 3-6.
Air/Fuel Valve In Ignition Position
3-9
Page 30
Page 31
SECTION 4 - INITIAL START- UP
4.1 INITIAL START- UP REQUIREMENTS
The initial start-up of the KC-1000 Low NOx
Boiler is comprised of the following steps:
• Installation completed 100%
• Combustion calibration
• Proper setting of controls and limits
• Mode of operation settings (see Section 5)
• Safety device testing (see Section 6)
Installation procedures should be completed
100% before performing initial start-up. Also, the
initial start-up must be complete prior to putting
the unit into service. Starting a unit without the
proper piping, venting, or electrical systems can
be dangerous and void the product’s warranty.
These start-up instructions should be precisely
followed in order for the unit to operate safely, at
a high thermal efficiency, and with low flue gas
emissions.
Initial unit start-up must be performed ONLY by
AERCO factory trained start-up and service
personnel. After following the steps in this
section, it will be necessary to perform the mode
of operation settings in Section 5, and the safety
device test procedures in Section 6 to complete
the initial unit start-up.
An AERCO Gas Fired Startup Sheet included
with each KC-1000 must be completed for each
unit for warranty validation and a copy must be
returned promptly to AERCO at:
AERCO International, Inc.
159 Paris Ave.
Northvale, NJ 07647
WARNING!
DO NOT ATTEMPT TO FIRE THE UNIT
WITHOUT FULL WATER LEVEL. THIS
CAN SERIOUSLY DAMAGE THE UNIT
AND MAY RESULT IN PERSONAL
INJURY OR PROPERTY DAMAGE. THIS
IS NOT COVERED BY WARRANTY.
CAUTION!
All installation procedures in Section 2 must
be completed before attempting to start the
unit.
INITIAL START-UP
4.2 TOOLS AND INSTRUMENTATION
FOR COMBUSTION CALIBRATION
To properly perform combustion calibration on a
KC Boiler equipped with a low NOx burner, the
proper instruments and tools must be used and
correctly installed on the unit. The following
paragraphs outline the necessary tools and
instrumentation as well as their installation.
4.2.1 REQUIRED TOOLS AND
INSTRUMENTATION
The following tools and instrumentation are
necessary to perform combustion calibration of a
low NOx unit:
1. Digital Combustion Analyzer - Oxygen
accuracy to ± 0.4%; Carbon Monoxide and
NOx resolution to 1 PPM.
2. A16" W.C. manometer and plastic tubing.
3. One 1/4” and two 1/8” NPT-to-barbed fittings
for use with manometers.
4. AERCO differential gas pressure regulator
adjustment tool P/N GM-122643 (one
supplied per installation site)
5. Small and large flat blade screwdrivers.
6. 7/16" open end wrench and small adjustable
wrenches.
7. Tube of silicone adhesive
4.2.2 INSTALLING THE SUPPLY GAS
MANOMETER
1. Close the main manual gas supply valve up
stream of the unit.
2. Remove the 1/4" NPT pipe plug from the
port on the inlet side of the safety shut off
valve (see Figure 4.1).
3. Install a barbed fitting into the pipe plug
tapping.
4. Attach one end of a length of plastic tubing
to the barbed fitting and one end to the 16"
W.C. manometer.
4-1
Page 32
INITIAL START-UP
Figure 4.1
1/8” Gas Plug Location
4.2.3 PREPARING THE FLUE VENT
PROBE HOLE
1. If the unit has been installed using the
recommended AL29-4C vent, there will be a
3/8” hole, 18” to 24” above the exhaust
manifold. The outer vent section, that covers
vent connections must be loosened and
moved to uncover the hole (see Figure 4.2).
2. If equipped with one, adjust the stop on the
combustion analyzer probe so that it extends
into the flue gas flow without hitting the
opposite wall of the flue. Do not insert the
probe at this time.
4.2.4 INSTALLING THE DIFFERENTIAL
REGULATOR ADJUSTMENT TOOL
1. First, remove the cap from the differential
pressure regulator (see Figure 4.3).
2. Place the gasket from the regulator cap onto
the regulator adjustment tool.
3. Prior to Installing the tools on the regulator,
pull up the tool's screwdriver blade. Then,
thread the tool into the regulator.
4. Engage the tool’s screwdriver blade into the
regulator’s adjustment screw slot.
Figure 4.3
Differential Regulator Adjustment Tool
Installation
IMPORTANT
The unit is shipped from the factory set up for
either natural gas or propane, as specified by the
Style No. on the Sales Order. If desired, the unit
can be easily switched from natural gas to
propane (or vice versa) using the regulator
spring change procedure in Appendix J.
For propane units, disregard paragraph 4.3 and
proceed to paragraph 4.4.
4-2
Figure 4.2
Analyzer Probe Hole Location
4.3 NATURAL GAS COMBUSTION
CALIBRATION
The KC-1000 is shipped combustion calibrated
from the factory. Recalibration as part of a startup is necessary due to differences in altitude,
gas BTU content, gas supply piping and supply
regulators. Factory test data sheets are shipped
with each unit as a reference.
The following combustion calibration procedure
closely follows the factory procedure. By
following this procedure, readjustment of
combustion will be kept to a minimum.
Page 33
INITIAL START-UP
1. Open the supply and return valves to the unit
and ensure that the system pumps are
running.
2. Open the gas supply valve(s) to the unit.
3. If a lockup style regulator is installed as a
gas supply regulator, adjust the gas supply
until a reading of 12” W.C. static pressure is
obtained.
4. Set the ON/OFF switch to the OFF position.
Turn on AC power to the unit. The display
will show LOSS OF POWER and the time
and date.
5. Set the unit to the Manual Mode by pressing
the AUTO/MAN switch. A flashing Manual Fire Rate message will be displayed with the
present rate in %. Also, the MANUAL LED
will light.
NOTE:
For a review of the control panel operating
procedures, refer to Section 3.
6. Adjust the rate to 0% by pressing the ▼
arrow key.
7. Set the ON/OFF switch to the ON position.
8. Change the firing rate to 25% using the ▲
arrow key. This will put the unit into the
starting sequence.
NOTE:
On initial start-up, or return to service from a
fault condition, the unit will remain at a 29% firing
rate for two-minutes, although the control signal
may indicate a greater input.
9. Following the warm-up period, increase the
firing rate in 20% increments while
monitoring the gas pressure after every
increase. If gas pressure dips below 8.8”
W.C. for FM gas trains and 9.2” for IRI gas
trains at any input firing rate percentage,
stop and raise the pressure. Once 100% is
reached, adjust the gas pressure for 8.8”
W.C. (FM) or 9.2” W.C. (IRI).
NOTE:
If 8.8” W.C. for FM gas trains or 9.2” W.C. for IRI
gas trains cannot be obtained at the 100% firing
rate, it will be necessary to stop calibration and
contact the local AERCO representative in your
area. Running the unit on insufficient gas
pressure will void the warranty
10. Once 8.8” W.C. or 9.2” W.C. is set at the
100% level change the firing rate to 30%.
Insert the combustion analyzer probe into
the stack.
NOTE:
Always approach a firing rate percentage from
the same direction, (i.e., 100% to 30%, 30% to
20%, etc.). Whenever going to an increased
firing rate from below (i.e., 20% to 30%), first go
above and then back down to the desired firing
rate. This is necessary due to hysteresis in the
air/fuel stepper motor. Hysteresis causes the
air/fuel valve to stop in a slightly different position
if the firing rate percentage is approached from
below or above. This results in a difference in
oxygen readings for the same firing rate
percentage causing unnecessary recalibration.
11. Allow enough time for the combustion
analyzer to settle. Compare the measured
oxygen level to the oxygen range for intake
air temperature in Table 1 (page 4-5). Also,
ensure that the carbon monoxide (CO) and
nitrogen oxide (NOx) readings do not
exceed the values shown.
12. If the measured oxygen level, CO and NOx
emissions are within the ranges shown in
Table 1, no adjustment is necessary.
Proceed to step 17.
13. If the measured oxygen level is below the
range in Table 1, rotate the differential
regulator adjustment tool counterclockwise
1/4 to 1/2 revolution to decrease gas flow.
14. Wait for the combustion analyzer to settle,
then compare the new oxygen reading to
Table 1. Repeat adjustment until oxygen is
within the specified range.
15. If the measured oxygen level is above the
oxygen range in Table 1, rotate the
differential regulator adjustment tool
clockwise 1/4 to 1/2 revolution to increase
gas flow.
16. Wait for the analyzer reading to settle, then
compare the new reading to Table 1. Repeat
adjustment until oxygen is within the
specified range.
NOTE:
Adjust only the differential regulator at 30%
control signal; do not adjust the air shutter.
17. Once the oxygen level is within the specified
range at 30%, change the firing rate to 16%.
4-3
Page 34
INITIAL START-UP
18. Oxygen levels at the 16% firing rate should
be as shown in Table 2 (page 4-5). Also,
ensure that the CO and NOx readings do not
exceed the values shown. No adjustment
should be necessary. Contact the Factory if
the oxygen, CO or NOx levels are not within
the specified ranges.
NOTE:
At a 100% firing rate, the KC1000 will not
operate reliably at inlet air temperatures below
55°F if the Cold Air Damper (P/N 99026) is not
installed. See paragraphs 2.10.2 and 2.10.3.
19. Change the firing rate to 100% and allow the
combustion analyzer to settle. If the optional
Cold Air Damper (P/N 99026) is installed,
compare the measured oxygen level with the
levels in Table 3. If the Cold Air Damper is
not installed, compare the oxygen levels with
the readings in Table 3A.
20. If the measured oxygen reading is below the
oxygen range in Table 3 (or 3A), loosen the
two bolts that secure the inlet air shutter to
the unit using a 7/16” wrench (see Figure
4.4). Open the shutter 1/4” to 1/2” to
increase the oxygen level, then tighten the
nuts.
BLOWER
INLET
Figure 4.4
Air Shutter Locking Nut Location
SCREEN
SHUTTER
SHUTTER
LOCKING NUTS
BLOWER
OUTLET
REMINDER:
At 30% firing rate, adjust only the differential
pressure regulator. At 100% firing rate, adjust
only the inlet air shutter.
22. If the measured oxygen reading is above the
oxygen range in Table 3, loosen the two
7/16" locking nuts securing the inlet air
shutter. Close the air shutter 1/4” to 1/2” to
decrease the oxygen level and tighten the
two nuts.
23. Allow the analyzer to settle then compare the
new oxygen reading to Table 3 (or 3A).
24. Repeat the adjustment until the oxygen is
within the specified range. Also, ensure that
the CO and NOx readings do not exceed the
values shown. Firmly tighten the inlet air
shutter locking nuts when finished.
NOTE:
Adjust the inlet air shutter only at 100% firing
rate. Do Not adjust the differential pressure
regulator.
25. Change the firing rate to 30%. Allow time for
the combustion analyzer to settle. Check the
measured oxygen level, CO and NOx
emissions to ensure that they are still within
the ranges shown in Table 1.
26. Continue these procedures until all oxygen
levels are within the ranges specified in
Tables 1, 2 and 3 (or 3A) on page 4-5.
27. Record all readings on the AERCO start-up
sheet provided with each unit. Proceed to
paragraph 4.5 when all natural gas
combustion calibration procedures are
completed.
21. Wait for the analyzer to settle then compare
the new oxygen reading to Table 3 (or 3A).
Repeat the inlet air shutter adjustment until
the oxygen is within the specified range.
Also, ensure that the CO and NOx
emissions do not exceed the values shown.
Firmly tighten the inlet air shutter locking
nuts when finished.
The unit is shipped from the factory set up for
either natural gas or propane, as specified by the
Style No. on the Sales Order. If desired, the unit
can be easily switched from natural gas to
propane (or vice versa) using the regulator
spring change procedure in Appendix J.
Since the required gas supply pressures for
propane differ from those required for natural
gas, the Propane Combustion Calibration
procedures are repeated in their entirety in
paragraph 4.4. It should be noted that the
Combustion Calibration data in Tables 1, 2, 3
(and 3A) apply to both natural gas and propane
units.
4.4 PROPANE COMBUSTION
CALIBRATION
The KC-1000 is shipped combustion calibrated
from the factory. Recalibration as part of a startup is necessary due to differences in altitude,
gas BTU content, gas supply piping and supply
regulators. Factory test data sheets are shipped
with each unit as a reference.
Prior to starting these procedures, ensure that
the KC1000 has been set up as specified in
paragraphs 4.2 through 4.2.4.
The following combustion calibration procedure
closely follows the factory procedure. By
following this procedure, readjustment of
combustion will be kept to a minimum.
4-5
Page 36
INITIAL START-UP
1. Open the supply and return valves to the unit
and ensure that the system pumps are
running.
2. Open the gas supply valve(s) to the unit.
3. If a lockup style regulator is installed as a
gas supply regulator, adjust the gas supply
until a reading of 11” W.C. static pressure is
obtained.
4. Set the ON/OFF switch to the OFF position.
Turn on AC power to the unit. The display
will show LOSS OF POWER and the time
and date.
5. Set the unit to the Manual Mode by pressing
the AUTO/MAN switch. A flashing Manual Fire Rate message will be displayed with the
present rate in %. Also, the MANUAL LED
will light.
For a review of the control panel operating
procedures, refer to Section 3.
6. Adjust the rate to 0% by pressing the ▼
arrow key.
7. Set the ON/OFF switch to the ON position.
8. Change the firing rate to 25% using the ▲
arrow key. This will put the unit into the
starting sequence.
On initial start-up, or return to service from a
fault condition, the unit will remain at a 29% firing
rate for two-minutes, although the control signal
may indicate a greater input.
9. Following the warm-up period, increase the
firing rate in 20% increments while
monitoring the gas pressure after every
increase. If gas pressure dips below 7.7”
W.C. for FM gas trains and 8.1” for IRI gas
trains at any input firing rate percentage,
stop and raise the pressure. Once 100% is
reached, adjust the gas pressure for 7.7”
(FM) W.C. or 8.1” W.C. (IRI).
If 7.7” W.C. for FM gas trains or 8.1” W.C. for IRI
gas trains cannot be obtained at the 100% firing
rate, it will be necessary to stop calibration and
contact the local AERCO representative in your
area. Running the unit on insufficient gas
pressure will void the warranty
NOTE:
NOTE:
NOTE:
10. Once 7.7” W.C. or 8.1” W.C. is set at the
100% level change the firing rate to 30%.
Insert the combustion analyzer probe into
the stack.
NOTE:
Always approach a firing rate percentage from
the same direction, (i.e., 100% to 30%, 30% to
20%, etc.). Whenever going to an increased
firing rate from below (i.e., 20% to 30%), first go
above and then back down to the desired firing
rate. This is necessary due to hysteresis in the
air/fuel stepper motor. Hysteresis causes the
air/fuel valve to stop in a slightly different position
if the firing rate percentage is approached from
below or above. This results in a difference in
oxygen readings for the same firing rate
percentage causing unnecessary recalibration.
11. Allow enough time for the combustion
analyzer to settle. Compare the measured
oxygen level to the oxygen range for intake
air temperature in Table 1. Also, ensure that
the carbon monoxide (CO) and nitrogen
oxide (NOx) readings do not exceed the
values shown.
12. If the measured oxygen level, CO and NOx
emissions are within the ranges shown in
Table 1, no adjustment is necessary.
Proceed to step 17.
13. If the measured oxygen level is below the
range in Table 1, rotate the differential
regulator adjustment tool counterclockwise
1/4 to 1/2 revolution to decrease gas flow.
14. Wait for the combustion analyzer to settle,
then compare the new oxygen reading to
Table 1. Repeat adjustment until oxygen is
within the specified range.
15. If the measured oxygen level is above the
oxygen range in Table 1, rotate the
differential regulator adjustment tool
clockwise 1/4 to 1/2 revolution to increase
gas flow.
16. Wait for the analyzer reading to settle, then
compare the new reading to Table 1. Repeat
adjustment until oxygen is within the
specified range.
NOTE:
Adjust only the differential regulator at 30%
control signal; do not adjust the air shutter.
4-6
Page 37
INITIAL START-UP
17. Once the oxygen level is within the specified
range at 30%, change the firing rate to 16%.
18. Oxygen levels at the 16% firing rate should
be as shown in Table 2. Also, ensure that
the CO and NOx readings do not exceed the
values shown. No adjustment should be
necessary. Contact the Factory if the
oxygen, CO or NOx levels are not within the
specified ranges.
NOTE:
At a 100% firing rate, the KC1000 will not
operate reliably at inlet air temperatures below
55°F if the Cold Air Damper (P/N 99026) is not
installed. See paragraphs 2.10.2 and 2.10.3.
19. Change the firing rate to 100% and allow the
combustion analyzer to settle. If the optional
Cold Air Damper (P/N 99026) is installed,
compare the measured oxygen level with the
levels in Table 3. If the Cold Air Damper is
not installed, compare the oxygen levels with
the readings in Table 3A.
20. If the measured oxygen reading is below the
oxygen range in Table 3 (or 3A) , loosen the
two bolts that secure the inlet air shutter to
the unit using a 7/16” wrench (see Figure
4.4). Open the shutter 1/4” to 1/2” to
increase the oxygen level, then tighten the
nuts.
21. Wait for the analyzer to settle then compare
the new oxygen reading to Table 3 (or 3A).
Repeat the inlet air shutter adjustment until
the oxygen is within the specified range.
Also, ensure that the CO and NOx
emissions do not exceed the values shown.
Firmly tighten the inlet air shutter locking
nuts when finished.
REMINDER:
At 30% firing rate, adjust only the differential
pressure regulator. At 100% firing rate, adjust
only the inlet air shutter.
22. If the measured oxygen reading is above the
oxygen range in Table 3, loosen the two
7/16" locking nuts securing the inlet air
shutter. Close the air shutter 1/4” to 1/2” to
decrease the oxygen level and tighten the
two nuts.
23. Allow the analyzer to settle then compare the
new oxygen reading to Table 3 (or 3A).
24. Repeat the adjustment until the oxygen is
within the specified range. Also, ensure that
the CO and NOx readings do not exceed the
values shown. Firmly tighten the inlet air
shutter locking nuts when finished.
NOTE:
Adjust the inlet air shutter only at 100% firing
rate. Do Not adjust the differential pressure
regulator.
25. Change the firing rate to 30%. Allow time for
the combustion analyzer to settle. Check the
measured oxygen level, CO and NOx
emissions to ensure that they are still within
the ranges shown in Table 1.
26. Continue these procedures until all oxygen
levels are within the ranges specified in
Tables 1, 2 and 3.
27. Record all readings on the AERCO start-up
sheet provided with each unit. Proceed to
paragraph 4.5 when all propane combustion
calibration procedures are completed.
4.5 UNIT REASSEMBLY
Once combustion calibration is set properly, the
unit can be re-assembled for permanent
operation.
1. Set the ON/OFF switch to the OFF position.
Disconnect the AC power supply from the
unit.
2. Shut off the gas supply to the unit.
3. Remove the regulator adjustment tool by
first pulling up the screwdriver blade to
disengage it from the regulator adjusting
screw, and then turning the tool out of the
top of the regulator.
4. Apply a drop of silicone adhesive to the
regulator adjusting screw to lock its setting.
5. Remove the gasket from the tool and place it
back onto the regulator cap.
6. Reinstall the cap and gasket back on the
regulator. Tighten the cap using a
screwdriver or wrench.
7. Remove all of the manometers and barbed
fittings and reinstall the pipe plugs using a
suitable thread compound.
8. Remove the combustion analyzer probe
from the vent hole. Seal the probe hole and
replace the vent connection cover.
9. Replace the unit’s panels and hood.
4-7
Page 38
INITIAL START-UP
4.6 OVER TEMPERATURE LIMIT
SWITCH ADJUSTMENTS
There are two Over-Temperature Limit switches
that turn off the unit when the outlet water
temperature becomes too hot. The lower overtemperature limit switch is adjustable and should
be adjusted 20° to 40°F above the operating
header temperature. The upper over-temperature limit switch is a manual reset device and is
not adjustable. It will shut the unit off if the water
temperature reaches 240°F. DO NOT attempt to
adjust its setpoint.
To adjust the lower over temperature switch limit
h:
switc
1. Remove the wing nut from the top center of
the shell cap. Lift the cap off the shell.
2. The two over-temperature limit switches are
located at the top of the shell (see Fig. 4.6).
Do not adjust the upper switch it has been
factory preset. Adjust the lower switch
between 20° to 40°F higher than the
maximum header temperature the unit may
see.
3. Replace the shell cap and wing nut.
Figure 4.6
Over Temperature Limit Switch Location
4-8
Page 39
MODE OF OPERATION
SECTION 5 - MODE OF OPERATION
5.1 INTRODUCTION
The following paragraphs provide detailed
descriptions of the six different modes of
operation for the KC1000 Boiler. Each unit is
shipped from the factory tested and configured
for the ordered mode of operation. All
temperature related parameters are at factory
defaults and work well in most applications.
However, it may be necessary to change certain
parameters to customize the unit to the system.
A complete listing and descriptions of the
temperature related parameters are included in
Appendix A. Factory defaults are listed in Appendix E. After reading this section, parameters can
be customized to suit the needs of the specific
application.
5.2 INDOOR/OUTDOOR RESET MODE
This mode of operation is based on outside air
temperatures. As the outside air temperature
decreases, the supply header temperature will
increase and vice versa. For this mode, it is
necessary to install an outside air sensor as well
as select a building reference temperature and a
reset ratio.
5.2.1 RESET RATIO
Reset ratio is an adjustable number from 0.1 to
9.9. Once it is adjusted, the supply header
temperature will increase by that number for
each degree that the outside air temperature
decreases. For instance, if a reset ratio of 1.6 is
used, for each degree that outside air
temperature decreases the supply header
temperature will increase by 1.6 degrees.
5.2.2. BUILDING REFERENCE
TEMPERATURE
This is a temperature from 40°F to 240°F. Once
selected, it is the temperature that the system
references to begin increasing its temperature.
For instance, if a reset ratio of 1.6 is used and
we select a building reference temperature of
70°F, then at an outside temperature of 69°F,
the supply header temperature will increase by
1.6° to 71.6°F.
5.2.3 OUTDOOR AIR TEMPERATURE
SENSOR INSTALLATION
The outdoor air temperature sensor must be
mounted on the North side of the building in an
area where the average outside air temperature
is expected. The sensor must be shielded from
the sun's direct rays, as well as from direct
impingement by the elements. If a cover or
shield is used, it must allow free air circulation.
The sensor may be mounted up to 200 feet from
the unit. Sensor connections are made inside
the Input/Output (I/O) Box on the left side of the
KC1000 Boiler. Connections are made at the
terminals labeled OUTDOOR SENSOR IN and
SENSOR COMMON inside the I/O Box using
shielded 18 to 22 AWG wire. A wiring diagram is
provided on the cover of the I/O Box. Refer to
Section 2, paragraph 2.6.2 for additional wiring
information.
5.2.4 INDOOR/OUTDOOR STARTUP
1. Refer to the indoor/outdoor reset ratio charts
in Appendix D.
2. Choose the chart corresponding to the
desired building reference temperature.
3. Go down the left column of the chart to the
coldest design outdoor air temperature
expected in your area.
NOTE:
A design engineer typically provides design
outdoor air temperature and supply header
temperature data
4. Once the design outdoor air temperature is
chosen, go across the chart to the desired
supply header temperature for the design
temperature chosen in step 3.
5. Next, go up that column to the Reset Ratio
row to find the corresponding reset ratio.
6. Access the Configuration Menu and scroll
through it until the display shows Bldg Ref Temp (Building Reference Temperature).
7. Press the CHANGE key. The display will
begin to flash.
8. Use the ▲ and ▼ arrow keys to select the
desired building reference temperature.
9. Press ENTER to save any changes.
10. Next, scroll through the Configuration Menu
until the display shows Reset Ratio.
5-1
Page 40
MODE OF OPERATION
11. Press the CHANGE key. The display will
begin to flash.
12. Use the ▲ and ▼ arrow keys to select the
reset ratio determined in step 5.
13. Press ENTER to save the change.
Refer to paragraph 3.3 for detailed instructions
on menu changing.
5.3 CONSTANT SETPOINT MODE
The Constant Setpoint mode is used when a
fixed header temperature is desired. Common
uses of this mode of operation include water
source heat pump loops, and indirect heat
exchangers for potable hot water systems or
processes.
There are no external sensors necessary to
operate in this mode. While it is necessary to set
the desired setpoint temperature, it is not
necessary to change any other temperaturerelated functions. The unit is factory preset with
settings that work well in most applications.
Prior to changing any temperature-related
parameters, other than the setpoint, it is
suggested that an AERCO representative be
contacted. For a complete listing of factory
defaults and descriptions of temperature related
functions, see Appendices A and E.
5.3.1 SETTING THE SETPOINT
The setpoint temperature of the unit is adjustable
from 40°F to 240°F. To set the unit for operation
in the Constant Setpoint Mode, the following
menu settings must be made in the
Configuration Menu:
Refer to paragraph 3.3 for detailed instructions
on changing menu options.
5.4 REMOTE SETPOINT MODES
The unit’s setpoint can be remotely controlled by
an Energy Management System (EMS) or
Building Automation System (BAS). The Remote
Setpoint can be driven by a current or voltage
signal within the following ranges:
4-20 mA/1-5 Vdc
0-20 mA/0-5 Vdc
The factory default setting for the Remote
Setpoint mode is 4 - 20 mA/1 - 5 Vdc. With this
setting, a 4 to 20 mA/1 to 5 Vdc signal, sent by
an EMS or BAS, is used to change the unit's
setpoint. The 4 mA/1V signal is equal to a 40°F
setpoint while a 20 mA /5V signal is equal to a
240°F setpoint. When a 0 to 20 mA/0 to 5 Vdc
signal is used, 0 mA is equal to a 40°F setpoint.
In addition to the current and voltage signals
described above, the Remote Setpoint mode can
also driven by a RS485 Modbus Network signal
from an EMS or BAS.
The Remote Setpoint modes of operation can be
used to drive single as well as multiple units.
NOTE:
If a voltage, rather than current signal is used to
control the remote setpoint, a DIP switch
adjustment must be made on thePMC Board in
the Control Box. Contact your local AERCO
representative for details.
In order to enable the Remote Setpoint Mode,
the following menu setting must be made in the
Configuration Menu:
MENU OPTION SETTING
Boiler Mode Remote Setpoint
Remote Signal 4-20mA/1-5V,
0-20mA/0-5V, or
Network
Refer to paragraph 3.3 for detailed instructions
on changing menu options.
5-2
Page 41
MODE OF OPERATION
If the Network setting is selected for RS485
Modbus operation, a valid Comm Address must
be entered in the Setup Menu. Refer to Modbus
Communication Manual GF-114 for additional
information.
While it is possible to change the settings of
temperature related functions, the unit is factory
preset with settings that work well in most
applications. It is suggested that an AERCO
representative be contacted, prior to changing
any temperature related function settings. For
descriptions of temperature-related functions
and their factory defaults, refer to Appendices A
and E.
5.4.1 REMOTE SETPOINT FIELD WIRING
The only wiring connections necessary for the
Remote Setpoint mode are connection of the
remote signal leads from the source to the unit’s
I/O Box. The I/O Box is located on the front
panel of the Benchmark Boiler. For either a 420mA/0-5V or a 0-20mA/0-5V setting, the
connections are made at the ANALOG IN
terminals in the I/O Box. For a Network setting,
the connections are made at the RS-485 COMM
terminals in the I/O Box. The signal must be
floating, (ungrounded) at the I/O Box and the
wire used must be a two wire shielded pair from
18 to 22 AWG. Polarity must be observed. The
source end of the shield must be connected at
the source. When driving multiple units, each
unit’s wiring must conform to the above.
5.4.2 REMOTE SETPOINT STARTUP
Since this mode of operation is factory preset
and the setpoint is being externally controlled, no
startup instructions are necessary. In this mode,
the REMOTE LED will light when the external
signal is present.
To operate the unit in the Manual mode, press
the AUTO/MAN switch. The REMOTE LED will
go off and the MANUAL LED will light.
5.5 DIRECT DRIVE MODES
The unit’s fire rate can be changed by a remote
signal which is typically sent from an Energy
Management System (EMS) or from a Building
Automation System (BAS). The Direct Drive
mode can be driven by a current or voltage
signal within the following ranges:
4-20 mA/1-5 Vdc
0-20 mA/0-5 Vdc
The factory default setting for the Direct Drive
mode is 4-20 mA/1-5 Vdc. With this setting, a 4
to 20 mA signal, sent by an EMS or BAS is used
to change the unit’s fire rate from 0% to 100%. A
4 mA/1V signal is equal to a 0% fire rate, while a
20 mA /5V signal is equal to a 100% fire rate.
When a 0-20 mA/0-5 Vdc signal is used, zero is
equal to a 0% fire rate.
In addition to the current and voltage signals
described above, the Direct Drive mode can also
driven by a RS485 Modbus Network signal from
an EMS or BAS.
When in a Direct Drive mode, the unit is a slave
to the EMS or BAS and does not have a role in
temperature control. Direct Drive can be used to
drive single, or multiple units.
NOTE:
If a voltage, rather tt signal is used to han curren
control the fire rate, a DIP switch adjustment
must be made on thePMC Board in the Control
Box. Contact your local AERCO representative
for details.
To enable the Direct Drive Mode, the following
menu setting must be made in the Configuration
Menu:
MENU OPTION SETTING
Boiler Mode Direct Drive
Remote Signal 4-20mA/1-5V,
To change back to the Remote Setpoint mode,
simply press the AUTO/MAN switch. The
REMOTE LED will again light and the MANUAL
LED will go off.
0-20mA/0-5V, or
Network
Refer to paragraph 3.3 for instructions on
changing menu options.
5-3
Page 42
MODE OF OPERATION
If the Network setting is selected for RS485
Modbus operation, a valid Comm Address must
be entered in the Setup Menu. Refer to Modbus
Communication Manual GF-114 for additional
information.
5.5.1 DIRECT DRIVE FIELD WIRING
The only wiring connections necessary for Direct
Drive mode are connection of the remote signal
leads from the source to the unit’s I/O Box. For
either a 4-20mA/0-5V or a 0-20mA/0-5V setting,
the connections are made at the ANALOG IN
terminals in the I/O Box. For a Network setting,
the connections are made at the RS-485 COMM
terminals in the I/O Box. The signal must be
floating, (ungrounded) at the I/O Box and the
wire used must be a two wire shielded pair from
18 to 22 AWG. Polarity must be observed. The
source end of the shield must be connected at
the source. When driving multiple units, each
unit’s wiring must conform to the above.
5.5.2 DIRECT DRIVE STARTUP
Since this mode of operation is factory preset
and the fire rate is being externally controlled, no
startup instructions are necessary. In this mode,
the REMOTE LED will light when the signal is
present.
To operate the unit in manual mode, press the
AUTO/MAN switch. The REMOTE LED will go
off and the MANUAL LED will light.
To change back to the Direct Drive mode, simply
press the AUTO/MAN switch. The REMOTE
LED will again light and the MANUAL LED will
go off.
5.6 BOILER MANAGEMENT SYSTEM
(BMS) MODE
NOTE
BMS Model 168 can utilize either pulse
width modulation (PWM) or RS485
Modbus signaling to the Boiler. BMS II
Model 5R5-384 can utilize only RS485
signaling to the Boiler.
The BMS mode of operation is used in
conjunction with an AERCO Boiler Management
System. The BMS mode is used when it is
desired to operate multiple units in the most
efficient manner possible. The BMS can control
up to 40 boilers; 8 via pulse width modulation
(PWM) and up to 32 via Modbus (RS485)
network communication. For BMS programming
and operation, see GF-108M (BMS Model 168)
and GF-124 (BMS II Model 5R5-384), BMS
Operations Guides. For operation via an RS485
Modbus network, refer to Modbus
Communication Manual GF-114.
To enable the BMS Mode, the following menu
settings must be made in the Configuration
Menu:
MENU OPTION SETTING
Boiler Mode Direct Drive
Remote Signal BMS (PWM Input)
or
Network (RS485)
Refer to paragraph 3.3 for instructions on
changing menu options.
5.6.1 BMS EXTERNAL FIELD WIRING
Wiring connections for BMS control using PWM
signaling are made between connector JP2 on
the BMS panel (boilers 1 through 8), and the
B.M.S. (PWM) IN terminals in the I/O Box on the
front of the Benchmark Boilers. Refer to the
wiring diagram provided on the cover of the I/O
Box.
Wiring connections for RS485 Modbus control
are made between connector JP11 on the BMS
(boilers 9 through 40) and the RS485 COMM
terminals in the I/O Box on the front of the unit.
Wire the units using shielded twisted pair wire
between 18 and 22 AWG. Observe the proper
polarity for the B.M.S. (PWM) IN and/or RS485
COMM wiring connections. Shields should be
terminated only at the BMS and the boiler end
must be left floating. Each unit’s wiring must
conform to the above.
5.6.2 BMS SETUP AND STARTUP
This mode of operation is factory preset and the
AERCO BMS controls the firing rate. There are
no setup instructions for each individual unit.
To operate the unit in manual mode, press the
AUTO/MAN switch. The REMOTE LED will go
off and the MANUAL LED will light
To change back to the BMS mode, simply press
the AUTO/MAN switch. The REMOTE LED will
again light and the MANUAL LED will go off.
5-4
Page 43
MODE OF OPERATION
5.7 COMBINATION CONTROL SYSTEM
(CCS)
NOTE
l 168 caOnly BMS Moden be utilized for
the Combination Mode, not the BMS II
(Model 5R5-384).
Combination Control System (CCS) is one that
A
uses multiple boilers to cover both space-heating
and domestic hot water needs. An AERCO
Boiler Management System (BMS) Model 168
and a Combination Control Panel (CCP) are
necessary to configure this system. Typically, an
adequate number of boilers are installed to cover
the space-heating load on the design day,
however one or more units are used for the
domestic hot water load.
The theory behind this type of system is that the
maximum space-heating load and the maximum
domestic hot water load do not occur simultaneously. Therefore, boilers used for the domestic
hot water are capable of switching between
constant setpoint and BMS modes of operation.
These boilers are the combination units and are
referred to as the combo boilers. The combo
boilers heat water to a constant setpoint
temperature. That water is then circulated
through a heat exchanger in a domestic hot
water storage tank.
When the space-heating load is such that all the
space-heating boilers are at 100% firing rate, the
BMS will then ask the Combination Control
Panel for the domestic boilers to become spaceheating boilers. Provided the domestic hot water
load is satisfied, the combo (hot water) boilers
will then become space-heating boilers. If the
domestic hot water load is not satisfied, the
combo boiler(s) remain on the domestic hot
water load. If the combo boilers switch over to
space heating, but there is a call for domestic
hot water, the CCP switches the combo units
back to the domestic load.
When the combo units are satisfying the
domestic load they are in constant setpoint
mode of operation. When the combo units switch
over to space heating, their mode of operation
changes to the BMS mode. For more information
concerning the operation of the Combination
Control Panel see the AERCO CCP-1 literature.
5.7.1 COMBINATION CONTROL SYSTEM
FIELD WIRING
Wiring for this sy
Model 168 panel, the CCP and the B.M.S.
(PWM) IN terminals in the I/O Box. Wire the
units using a shielded twisted pair of 18 to 22
AWG wire. When wiring multiple units, each
unit’s wiring must conform to the above. For a
complete CCP system-wiring diagram see the
AERCO CCP-1 literature.
stem is between the BMS
5.7.2 COMBINATION CONTROL SYSTEM
SETUP AND STARTUP
Setup for the Combination Mode requires entries
to be made in the Configuration Menu for boiler
mode, remote signal type and setpoint. The
setpoint is adjustable from 40°F to 240°F.
Enter the following settings in the Configuration
Menu:
MENU OPTION SETTING
Boiler Mode Combination
Remote Signal BMS (PWM Input)
Internal Setpt 40°F to 240°F
Refer to paragraph 3.3 for instructions on
changing menu options.
While it is possible to change other temperaturerelated functions for combination mode, these
functions are preset to their factory default
values. These default settings work well in most
applications. It is suggested that AERCO be
contacted prior to changing settings other than
the unit’s setpoint. For a complete listing of
temperature related function defaults, see
Appendix E.
To set the unit to the manual mode, press the
AUTO/MAN switch. The MANUAL LED will light.
To set the unit back to the auto mode, press the
AUTO/MAN switch. The MANUAL LED will go
off and the REMOTE LED will light.
When the boiler is switched to BMS mode, the
AERCO BMS controls the firing rate. There are
no setup requirements to the boiler(s) in this
mode.
5-5
Page 44
Page 45
SECTION 6-SAFETY DEVICE TESTING PROCEDURES
6.1 TESTING OF SAFETY DEVICES
Periodic testing of all controls and safety devices
is required to insure that they are operating as
designed. Precautions must be taken while tests
are being performed to protect against bodily
injury and property damage.
Systematic and thorough testing of the operating
and safety controls should be performed on a
scheduled basis, or whenever a control
component has been serviced or replaced. All
testing must conform to local jurisdictions or
codes such as ASME CSD-1.
NOTE:
MANUAL and AUTO modes are required to
perform the following tests. For a complete
explanation of these modes, see Section 3.
NOTE:
It will be necessary to remove the sheet
metal covers and cap from the unit to
perform the following tests.
WARNING!
ELECTRICAL VOLTAGES USED IN THIS
SYSTEM INCLUDE 120 AND 24 VOLTS
AC. POWER MUST BE REMOVED PRIOR
TO PERFORMING WIRE REMOVAL OR
OTHER TESTING PROCEDURES THAT
CAN RESULT IN ELECTRICAL SHOCK.
6.2 LOW GAS PRESSURE FAULT TEST
1. Shut off the gas supply to the unit.
2. Install a 0-16” W.C. manometer in the gas
pipe assembly below the low gas pressure
switch. (See Fig. 6.1)
3. Open the gas supply to the unit and depress
the CLEAR button to clear any displayed
fault messages..
4. Place the unit in Manual Mode and fire the
unit at a firing rate between 25% and 30%.
5. Slowly close the manual gas supply valve
while monitoring the gas pressure. The unit
should fault and shutdown on LOW GAS PRESSURE when the manometer indicates
approximately 6.5” W.C.
SAFETY DEVICE TESTING
6. Open the gas supply to the unit and press
the CLEAR button on the Control Box.
7. The unit should restart.
Figure 6.1
1/8” Pipe Plug Position for Manometer
Installation
NOTE:
After faulting the unit, the fault message will
be displayed and the fault indicator light will
flash until the CLEAR button is pressed.
6.3 HIGH GAS PRESSURE TEST
1. Start the unit in manual mode and fire
between 25% and 30%.
2. Remove either wire # 150 or wire #151 from
the high gas pressure switch. See Fig. 6.2.
3. The unit should shut down on a HIGH GAS PRESSURE FAULT.
4. Reconnect the wire previously removed from
the high gas pressure switch and depress
the CLEAR button.
5. The unit should restart.
6-1
Page 46
SAFETY DEVICE TESTING
Figure 6.2
High Gas Pressure Switch
6.4 LOW WATER LEVEL FAULT TEST
1. Set the ON/OFF switch in the OFF position.
2. Close shut-off valves in the supply and
return piping to the unit.
3. Open the drain valve on the unit.
4. Allow air flow into the unit by either opening
the relief valve or by removing the 1/4” plug
in the top of the unit.
5. The LOW WATER LEVEL message will be
displayed and the FAULT LED will flash after
the water level has gone below the level of
the probe.
6. Set the ON/OFF switch to ON. The READY
light should remain off and the unit should
not start. If the unit does start, shut the unit
off immediately and refer fault to qualified
service personnel.
7. Close the drain and pressure relief valve or
reinstall the plug in the top of the unit if
removed.
8. Open the water shut-off valve in the return
piping to the unit to fill the shell.
9. Open the water shut-off valve in the supply
piping to the unit.
10. After the shell is full, press the LOW WATER LEVEL RESET button to reset the
low water cutoff. Press the CLEAR button to
reset the FAULT LED and clear the error
message.
11. Set the ON/OFF switch to the ON position.
The unit is now ready for operation.
6.5 WATER TEMPERATURE FAULT
TEST
1. In the normal operating mode, allow the unit
to stabilize at its setpoint.
2. Lower the adjustable temperature limit
switch setting to match the outlet water
temperature. (See Fig. 6.3).
Figure 6.3
Temperature Limit Switch Setting
3. Once the switch setting is approximately at
the actual water temperature, the unit should
shutdown. The red FAULT LED should be
flashing and the message HIGH WATER TEMP SWITCH OPEN should be displayed.
The unit should not start.
4. Reset the temperature limit switch setting to
its prior setting.
5. The unit should start once the adjustable
temperature limit switch setting is above the
actual outlet water temperature.
6-2
Page 47
SAFETY DEVICE TESTING
6.6 INTERLOCK TESTS
The unit is equipped with two interlock circuits
called the Remote Interlock and the Delayed
Interlock. Terminal connections for these circuits
are located in the I/O Box and are labeled
REMOTE INTL’K IN and DELAYED INTL’K IN.
These circuits can shut down the unit in the
event that an interlock is opened. These
interlocks are shipped from the factory jumped
(closed). However, each of these interlocks may
be utilized in the field as a remote stop and start,
an emergency cut-off, or to prove that a device
such as a pump gas booster, or louver is
operational.
6.6.1 REMOTE INTERLOCK
1. Remove the cover from the I/O Box and
locate the REMOTE INTL’K IN terminals.
2. Start the unit in manual mode and fire at
25% to 30% firing rate.
3. If there is a jumper across the REMOTE
INTL’K IN terminals, remove one side of the
jumper. If the interlock is being controlled by
an external device, either open the interlock
via the external device or disconnect one of
the wires leading to the external device.
4. The unit should shut down and display
INTERLOCK OPEN.
5. Once the interlock connection is reconnected, the INTERLOCK OPEN message
should automatically clear and the unit
should resume running.
6.6.2 DELAYED INTERLOCK
6.7 FLAME FAULT TEST
1. Place the ON/OFF switch in the OFF
position.
2. Place the unit in the Manual Mode and set
the firing rate between 25% and 30%.
3. Close the manual leak detection valve
located between the safety shut-off valve
and the differential regulator (see Fig. 6.4).
4. Start the unit.
5. The unit should shut down after reaching the
Ignition cycle and display FLAME LOSS
DURING IGN.
6. Open the valve previously closed in step 3
and depress the CLEAR button.
7. Restart the unit and allow it to prove flame.
8. Once flame is proven, close the manual leak
detection valve located between the safety
shut-off valve and the differential regulator.
9. The unit should shut down and display
FLAME LOSS DURING RUN.
10. Open the valve previously closed in step 8
and depress the CLEAR button. The unit
should restart and fire.
1. Remove the cover from the I/O Box and
locate the DELAYED INTL’K IN terminals.
2. Start the unit in manual mode and fire at a
25% to 30% firing rate.
3. If there is a jumper across the DELAYED
INTL’K IN terminals, remove one side of the
jumper. If the interlock is connected to a
proving switch of an external device, disconnect one of the wires leading to the
proving switch.
4. The unit should shut down and display
DELAYED INTERLOCK OPEN. The FAULT
LED should be flashing.
5. Once the interlock connection is reconnected, depress the CLEAR button. The unit
should start.
Figure 6.4
Manual Leak Detection Valve
6-3
Page 48
SAFETY DEVICE TESTING
6.8 AIR FLOW FAULT TEST
1. Start the unit in manual mode and set the
fire rate between 25% and 30%.
2. Once the unit has proved flame, remove
either wire #154 or #155 from the blower
proof switch (see Fig. 6.5) located on the
air/fuel valve.
3. The unit should shut down and display
AIRFLOW FAULT DURING RUN.
4. Replace the wire previously removed from
the blower-proof switch and depress the
CLEAR button. The unit should restart.
WARNING!
ELECTRICAL VOLTAGES USED IN THIS
SYSTEM INCLUDE 120 AND 24 VOLTS
AC. POWER MUST BE REMOVED PRIOR
TO PERFORMING WIRE REMOVAL OR
OTHER TESTING PROCEDURES THAT
CAN RESULT IN ELECTRICAL SHOCK.
6.9 SSOV PROOF OF CLOSURE
SWITCH
1. Set the unit’s ON/OFF switch to the OFF
position. Place the unit in manual mode and
set the fire rate between 25% and 30%.
2. Remove the Safety Shut-Off Valve (SSOV)
cover to access the terminal connections.
See Fig. 6.6. For units with IRI gas trains,
access the terminals of the downstream
SSOV (see drawing SD-A-660 in Appendix
F.
3. Remove either wire #149 or #148 from the
SSOV.
4. The unit should fault and display SSOV SWITCH OPEN.
5. Replace the wire previously removed and
depress the CLEAR button.
6. Start the unit.
7. Remove the wire again when the unit
reaches the purge cycle.
8. The unit should shut down and display
SSOV FAULT DURING PURGE.
9. Replace the wire on the SSOV and depress
the CLEAR button. The unit should restart.
Figure 6.5
Blower Proof Switch Location and Wiring
6-4
Figure 6.6
SSOV Actuator Cover Screw Location
Page 49
SAFETY DEVICE TESTING
6.10 PURGE SWITCH OPEN DURING
PURGE
1. Set the unit’s ON/OFF switch to the OFF
position. Place the unit in manual mode and
set the fire rate between 25% and 30%
2. Remove the air/fuel valve cover by rotating
the cover counterclockwise to unlock it and
then pulling it towards you. See Fig. 6.7.
3. Remove one of the two wires from the purge
switch (Fig. 6.8) and start the unit.
4. The unit should begin to start, then shut
down and display PRG SWITCH OPEN DURING PURGE.
5. Replace the wire on the purge switch and
depress the CLEAR button. The unit should
restart.
6.11 IGNITION SWITCH OPEN DURING
IGNITION
1. Set the unit’s ON/OFF switch to the OFF
position. Place the unit in manual mode and
set the fire rate between 25% and 30%.
2. Remove the air/fuel valve cover (Fig. 6.7) by
rotating the cover counterclockwise to
unlock it then pulling it towards you.
3. Remove one of the two wires from the
ignition switch (Fig. 6.8) and start the unit.
4. The unit should begin to start then shut
down and display IGN SWITCH OPEN DURING IGNITION.
5. Replace the wire on the ignition switch and
depress the CLEAR button. The unit should
restart.
Figure 6.7
Air/Fuel Valve Cover Location
Figure 6.8
Air/Fuel Valve Purge and Ignition Switch
Locations
6-5
Page 50
SAFETY DEVICE TESTING
6.12 SAFETY PRESSURE RELIEF VALVE
TEST
Test the unit’s Safety Pressure Relief Valve in
accordance with ASME Boiler and Pressure
Vessel Code, Section VI.
6-6
Page 51
SECTION 7 - MAINTENANCE
7.1 MAINTENANCE SCHEDULE
The unit requires regular routine maintenance to
keep up efficiency and reliability. For best
operation and life of the unit, the routine
maintenance procedures listed in Table 1 should
be performed within the specified time periods.
Table 1 Maintenance Schedule
Para Item
7.2 Spark
Igniter
7.3 Flame
Detector
7.4 Combustion
Cal.
7.5 Testing of
Safety
Devices
7.6 *Manifold
& Tubes
7.7 Water Side
Inspection
7.8 Condensate
Drain
* Recommended only when unit will be run in an
extreme condensing mode for prolonged periods
of time.
TO AVOID PERSONAL INJURY, BEFORE
SERVICING:
(A) DISCONNECT AC POWER FROM THE
UNIT.
(B) SHUT OFF THE GAS SUPPLY TO THE
UNIT.
(C) ALLOW THE UNIT TO COOL TO A SAFE
TEMPERATURE.
7.2 SPARK IGNITER
The spark igniter assembly is located in the body
of the burner (Figure 7.1). The igniter may be
HOT. Care should be exercised. It is easier to
remove the igniter from the unit after the unit has
cooled to room temperature.
To inspect or replace the Igniter :
1. Set the ON/OFF switch on the control panel
to the OFF position and disconnect AC
power from the unit.
6
Mos.
Inspect Replace 20
Inspect Replace 20
Check Check 1 hr.
Test 20
Inspect
Inspect 2 hr.
Inspect
12
Mos.
& clean
24
Mos.
& clean
needed
30
Labor
Time
mins.
mins.
mins.
4 hrs.
if
mins.
WARNING!
MAINTENANCE
2. To access the spark igniter, remove the
unit’s left side paneland left rear cover.
3. Disconnect the igniter cable from the igniter
contact.
4. Using a 15/16” open-end wrench, remove
the igniter from the burner shell.
5. Inspect the igniter for erosion or carbon
build-up. If there is substantial erosion of the
spark gap or ground electrode, the igniter
should be replaced. If carbon build-up is
present, clean the igniter using fine emery
cloth. Repeated carbon build-up on the
igniter is an indication that a check of the
combustion settings is required. See Section
4 for Combustion Calibration procedures.
6. Prior to reinstalling the igniter, a conductive
anti-seize compound must
igniter threads.
7. Reinstall the igniter in the burner shell. Do
Not over-tighten. A slight snugging up is
sufficient.
8. Reconnect the igniter cable.
9. Replace the left side panel and left rear
cover on the unit.
Figure 7.1
Spark Igniter and Flame Detector Location
be applied to the
7-1
Page 52
MAINTENANCE
7.3 FLAME DETECTOR
The flame detector assembly is located in the
body of the burner (Figure 7.1). The flame
detector may be HOT. Allow the unit to cool
sufficiently before removing the flame detector.
To inspect or replace the flame detector:
1. Set the ON/OFF switch on the control panel
to the OFF position and disconnect AC
power from the unit.
2. To access the flame detector, remove the
unit’s left side panel and left rear cover.
3. Disconnect the flame detector wire lead.
4. Using a 15/16” open-end wrench, loosen
and remove the flame detector from the
burner shell.
5. Inspect the detector thoroughly. If eroded,
the detector should be replaced. Otherwise,
clean the detector with a fine emery cloth.
6. Reinstall the flame detector in the burner
shell. Do Not over-tighten. A slight snugging
up is sufficient.
7. Reconnect the flame detector wire lead.
8. Replace the left side panel and left rear
cover on the unit.
7.4 COMBUSTION CALIBRATION
Combustion settings must be checked at the
intervals shown in Table 1 as part of the scheduled maintenance requirements. Refer to the
combustion calibration instructions in Section 4..
7.5 SAFETY DEVICE TESTING
Systematic and thorough testing of the operating
and safety devices should be performed to
ensure that they are operating properly. Certain
code requirements, such as ASME CSD-1,
require that these tests be performed on a
scheduled basis. Test schedules must conform
to local jurisdictions. The results of the tests
should be recorded in a log book. See Section 6
- Safety Device Testing Procedures.
7.6 MANIFOLD AND EXHAUST TUBES
The presence of even trace amounts of
chlorides and/or sulfur, in the combustion air and
fuel sources, can lead to the formation of
deposits on the inside of the exchanger tubes,
exhaust manifold, and/or the condensate cup.
The degree of deposition is influenced by the
extent of the condensing operation and the
chloride and sulfur levels that vary significantly
from application to application.
The following replacement parts will be required
for reassembly after inspection:
*Not necessary to change but should be on hand
in case damage occurs during the inspection.
To remove the manifold for inspection:
1. Remove the sheet metal covers from the
unit.
2. Disconnect the plastic tubing from the
condensate cup to drain and remove the
rear covers.
3. Remove the condensate cup from under the
unit Disconnect AC power and turn off the
gas supply to the unit.
4. and disconnect the condensate drain tubing
from the exhaust manifold.
5. Remove the flame detector and ignition
cable wires from the flame detector and
igniter contactor. Remove the igniter and
flame detector per paragraphs 7.2, and 7.3.
6. Remove the grounding terminal from the
burner by loosening the upper screw and
sliding the connector from the grounding rod.
(See Fig. 7.2)
Figure 7.2
Grounding Terminal Location
7-2
Page 53
7. Loosen the 1/4” NPT union on the low NOx
staged ignition assembly (Figure 7.3).
8. Disconnect the staged ignition assembly 1/8”
elbow from the 3” long NPT nipple at the
bottom of the burner shell.
MAINTENANCE
Figure 7.3
Burner Disassembly Diagram
9. Remove the 3” long NPT nipple and 1/4”
O.D. tube (Figure 7.3) from the burner shell.
10. Using a 7/16” socket or open end wrench,
remove the four 1/4-20 nuts on the gas inlet
pipe flange at the burner.
11. Using two 9/16” wrenches, remove the two
3/8-16 hex nuts and bolts on the gas inlet
pipe flange at the air/fuel valve (Figure 7.3).
Remove the gas inlet pipe.
12. Loosen the hose clamp on the air/fuel valve
outlet (Figure 7.3).
13. Using a 1/2” socket wrench, remove the six
5/16-18 hex nuts supporting the burner
(Figure 7.3).
14. Lower the burner while sliding the air hose
off the air/fuel valve. Remove the burner
through the rear of the unit. Due to space
limitations, it will be necessary to separate
the burner head and shell during the removal
process.
15. Disconnect the exhaust temperature sensor
by unscrewing it from the exhaust manifold
(Figure 7.4).
Figure 7.4
Exhaust Sensor Connector Location
16. Disconnect the air/fuel valve 12-pin connector from the KC wiring harness.
17. Disconnect wires #24 and #17 from the
blower proof switch (Figure 7.5).
Figure 7.5
Blower Proof Switch Wire Locations
18. Loosen the hose clamp on the air/fuel valve
inlet and slide the clamp back towards the
blower (Figure 7.6).
Figure 7.6
Air/Fuel Valve Inlet Hose Clamp
7-3
Page 54
MAINTENANCE
19. Using an 11/16” wrench, loosen the
compression fittings on the feedback tube
between the air/fuel valve and the differential
pressure regulator. Remove the feedback
tube (Figure 7.7).
20. Using two 9/16” wrenches, remove the two
3/8-16 hex nuts and bolts securing the
air/fuel valve to the differential pressure
regulator (Figure 7.7).
21. Remove the air/fuel valve, taking care not to
damage the flange “O”- ring.
AIR/FUEL
VALVE
COMPRESSION
FITTINGS
NOTE:
The combustion chamber liner should be
installed prior to reinstalling the exhaust
manifold
Figure 7.8
Manifold Nut and Bolt Locations
3/8 - 16
HEX NUT/BOLT
DIFFERENTIAL PRESS.
REGULATOR
Figure 7.7
Feedback Tube and Air/Fuel Valve to
Differential Regulator Bolts
22. Remove the flue venting from the exhaust
manifold.
23. To prevent damage and simplify handling of
the exhaust manifold, it will be necessary to
remove the exhaust manifold insulation.
Using a 7/16” wrench or socket, remove the
3 bolts and fender washers securing the
insulation to the exhaust manifold (Figure
7.8).
24. Loosen the three 1-1/16” nuts that hold the
manifold. Remove the two side nuts. DO NOT REMOVE THE FRONT NUT (Figure
7.8).
25. Carefully pull the manifold down and back,
removing it through the back of the unit.
26. Inspect the manifold and exhaust tubes for
debris. Clean out any debris as necessary.
27. Inspect the combustion chamber and liner.
Replace the liner if any signs of cracking or
warping are observed.
28. Replace the gasket between the manifold
and the combustion chamber (Part Number
GP-122537). The use of Permatex or a
similar gasket adhesive is recommended.
Replace the gasket between the manifold
and tubesheet (Part No. GP-18900). Do not
use any gasket adhesive; this gasket has an
adhesive backing.
29. Beginning with the manifold, reinstall all the
components in the reverse order that they
were removed.
7.7 HEAT EXCHANGER WATER SIDE
INSPECTION
Per CSD-1, the water side of the heat exchanger
requires an inspection. To inspect the heat
exchanger, proceed as follows:
1. Shut off AC power to the unit.
2. Close the supply and return valves to the
unit (Figure 7.9).
3. Open the drain valve and allow the unit to
fully drain. The 1/4 inch plug in the top of
the shell may be removed to aid in drainage
or the relief valve may be opened (Figure
7.9).
7-4
Page 55
HOT WATER
SUPPLY (OUTLET)
1/4" PLUG
RELIEF VALVE
REDUCING
BUSHING
MAINTENANCE
HOT WATER
RETURN (INLET)
REDUCING
BUSHING
DRAIN VALVE
Figure 7.9
Heat Exchanger Supply and Return
Locations
4. Remove the 2 ½ inch plug located in the
shell at the rear of the unit (Figure 7.10).
5. Remove the relief valve, drain valve (Figure
7.9) and any reducing bushings.
6. Perform the inspection. Reassemble the unit
once the inspection is completed.
7. Open the supply and return valves and
reconnect AC power to the unit.
Figure 7.10
Heat Exchanger 2 ½ Inch Inspection Plug
Location
7.8 Condensate Drain Assembly
KC Boilers contain a condensate drain cup
(Figure 2.6) which should be inspected and
cleaned annually to ensure proper operation.
To inspect and clean the assembly, proceed as
follows:
1. Remove the left side panel and left rear
cover to provide access to the condensate
drain components (see Figure 2.6).
2. Disconnect the plastic tubing from the
condensate cup drain tube to the drain.
3. Remove the condensate cup from the unit.
Thoroughly clean the cup and inspect the
cup drain tube for blockage.
4. After the above items have been cleaned
and inspected, reassemble the drain
components by reversing the previous steps.
7-5
Page 56
Page 57
Chapter 8- TROUBLESHOOTING GUIDE
8.1 INTRODUCTION
This troubleshooting guide is intended to aid
service/maintenance personnel in isolating the
cause of a fault in a KC1000 Boiler. The troubleshooting procedures contained herein are
presented in tabular form on the following pages.
These tables are comprised of three columns
labeled: Fault Indication, Probable Cause and
Corrective Action. The numbered items in the
Probable Cause and Corrective Action columns
correspond to each other. For example,
Probable Cause No. 1 corresponds to Corrective
Action No. 1, etc.
When a fault occurs in the KC1000 Boiler,
proceed as follows to isolate and correct the
fault:
1. Observe the fault messages displayed in the
Control Box display.
TROUBLESHOOTING
2. Refer to the Fault Indication column in the
following troubleshooting tables and locate
the Fault that best describes the existing
conditions.
3. Proceed to the Probable Cause column and
start with the first item (1) listed for the Fault
Indication.
4. Perform the checks and procedures listed in
the Corrective Action column for the first
Probable Cause candidate.
5. Continue checking each additional Probable
Cause for the existing fault until the fault is
corrected.
6. If the fault cannot be corrected using the
information provided in the Troubleshooting
Tables, please contact your local AERCO
Representative.
1. Blower stopped running due to thermal
or current overload
2. Blocked Blower inlet or inlet ductwork
3. Blocked airflow switch
4. Defective airflow switch
1. Blower not running or running too slow
2. Defective Air Flow Switch
3. Blocked Air flow Switch
4. Blocked Blower inlet or inlet ductwork.
5. No voltage to switch from control box.
1. Blower stopped running due to thermal
or current overload
2. Blocked Blower inlet or inlet ductwork
3. Blocked airflow switch
4. Defective airflow switch
5. Combustion oscillations
1. Check combustion blower for signs of excessive heat or high
current drain that may trip thermal or current overload devices.
2. Inspect the inlet to the combustion blower including any ductwork
leading up to the combustion blower for signs of blockage.
3. Remove the airflow switch and inspect for signs of blockage,
clean or replace as necessary.
4. Measure the airflow switch for continuity with the combustion
blower running. If there is an erratic resistance reading or the
resistance reading is greater than zero ohms, replace the switch.
1. Start the unit. If the blower does not run check the blower solid
state relay for input and output voltage. If the relay is okay, check
the blower.
2. Start the unit. If the blower runs, check the airflow switch for
continuity. Replace the switch if there is no continuity.
3. Remove the air flow switch and inspect for signs of blockage,
clean or replace as necessary.
4. Inspect the inlet to the combustion blower including any ductwork
leading up to the combustion blower for signs of blockage.
5. Measure for 24 VAC during start sequence from each side of the
switch to ground. If 24VAC is not present refer to qualified
service personnel.
1. Check combustion blower for signs of excessive heat or high
current draw that may trip thermal or current overload devices.
2. Inspect the inlet to the combustion blower including any ductwork
leading up to the combustion blower for signs of blockage.
3. Remove the airflow switch and inspect for signs of blockage,
clean or replace as necessary.
4. Measure the airflow switch for continuity with the combustion
blower running. If there is an erratic resistance reading or the
resistance reading is greater than zero ohms, replace the switch.
5. Run unit to full fire. If the unit rumbles or runs rough, perform
combustion calibration.
1. Delayed Interlock Jumper not
installed or removed.
2. Device proving switch hooked to
interlocks is not closed
1. Direct drive signal is not present:
Not yet installed.
Wrong polarity.
Signal defective at source.
Broken or loose wiring.
2. Signal is not isolated (floating).
3. Control Box signal type selection
switches not set for correct signal
type (voltage or current).
1. Burner Ground Screw not installed
or loose.
2. Worn flame detector
3. No spark from Spark Plug
4. Defective Ignition Transformer
5. Defective Ignition/Stepper (IGST)
Board
6. Defective SSOV
7. Defective Differential Pressure
Regulator.
8. Carbon or other debris on Burner.
1. Check for a jumper properly installed across the delayed
interlock terminals in the I/O box.
2. If there are 2 external wires on these terminals, check to see if
an end switch for a device (i.e. a pump, louver, etc.) is tied to
these interlocks. Ensure that the device and its end switch are
functional. (jumper may be temporarily installed to test interlock
1. Check I/O Box to ensure signal is hooked up.
Hook up if not installed.
If installed, check polarity.
Measure signal level.
Check continuity of wiring between source and boiler.
2. Check signal at source to ensure it is isolated.
3. Check DIP switch on PMC board to ensure it is set correctly for
the type of signal being sent. Check control signal type set in
Configuration Menu.
1. Inspect and install/retighten Burner Ground Screw.
2. Remove and inspect the flame detector for signs of wear.
Replace if necessary.
3. Close the internal gas valve in the boiler. Install and arc a spark
ignitor outside the unit.
4. If there is no spark, check for 120VAC at the primary side to the
ignition transformer during the ignition cycle.
5. If 120VAC is not present, the IGST Board in the Control Box
may be defective. Refer fault to qualified service personnel.
6. While externally arcing the spark ignitor, observe the
open/close indicator in the Safety Shut-Off Valve to ensure it is
opening. If the valve does not open, check for 120VAC at the
valves input terminals. If 120VAC is not present, the IGST
board in the Control Box may be defective. Refer fault to
qualified service personnel.
7. Check gas pressure using gauge or manometer into and out of
the Air/Fuel Valve to ensure gas is getting to burner.
8. Remove burner and inspect for any carbon or debris. Clean and
reinstall
1. The Heat Demand Relays on the
Ignition/Stepper board failed to
activate when commanded
2. Relay is activated when not in
Demand
1. Defective exhaust sensor.
2. Carboned heat exchanger due to
incorrect combustion calibration
1. Incorrect supply gas pressure.
2. Defective Supply Regulator or
Wrong Style Regulator
3. Defective High Gas Pressure Switch
1. Remove and inspect the Flame Detector for signs of wear or
cracked ceramic. Replace if necessary.
2. Check gas pressure readings using a gauge or manometer into
and out of the Air/Fuel Valve to ensure that the gas pressure
into and out of the valve is correct.
3. Check combustion calibration. Adjust as necessary.
4. Remove the burner and inspect for any carbon or debris. Clean
and reinstall.
5. Remove blockage in condensate drain.
1. Press CLEAR button and restart the unit. If the fault persists,
replace Ignition/Stepper (IGST) Board.
2. Defective relay. Replace IGST Board.
1. Measure the actual exhaust temperature and continuity of the
exhaust sensor. If the exhaust temperature is less than 475
and the exhaust sensor shows continuity replace the sensor.
2. If exhaust temperature is greater than 500
combustion calibration. Calibrate or repair as necessary.
1. If using a non-lock up style regulator for the gas supply,
measure static gas pressure downstream, it should be 14”W C
or less. Adjust as necessary.
2. If gas supply pressure cannot be lowered, a lock-up style
regulator may be required or the supply regulator may be
defective.
3. Remove the leads from the high gas pressure switch. Measure
continuity across the common and normally closed terminals
with the unit not firing. Replace the switch if it does not show
continuity.
5. Unit setpoint is greater than Over
Temperature Switch setpoint.
6. Boiler Management System PID or
other settings not correctly setup.
7. No interlock to boiler or BMS to
disable boiler(s) in event that system
pumps have failed.
8. System flow rate changes are
occurring faster than boilers can
respond.
1. See HIGH WATER TEMPERATURE
SWITCH OPEN.
2. Temp HI Limit setting is too low.
1. Communication fault has occurred
between the PMC board and
Ignition/Stepper (IGST) board
1. Test the temperature switch to insure it trips at its actual water
temperature setting.
2. Check PID settings against Menu Default settings in the
Appendix. If the settings have been changed, record the current
readings then reset them to the default values.
3. Using the resistance charts in the Appendix C, Measure the
resistance of Shell sensor and BTU sensor at a known water
temperature.
4. If unit is in Manual Mode switch to Auto Mode.
5. Check setpoint of unit and setpoint of Temperature Switch;
Ensure that the temperature switch is set higher than the unit’s
setpoint.
6. Check the BMS for changes to PID default values, correct as
necessary.
7. If system pump is controlled by Energy Management System
other than BMS or pumps are individually controlled by boiler,
check to see if there are flow switches interlocked to the BMS or
boiler.
8. If the system is a variable flow system, monitor system flow
changes to ensure that the rate of flow change is not faster than
what the boilers can respond to.
1. See HIGH WATER TEMPERATURE SWITCH OPEN.
2. Check Temp HI Limit setting.
1. Press CLEAR button and restart unit. If fault persists, contact
qualified Service Personnel.
1. Air/Fuel Valve not rotating to ignition
position.
2. Defective ignition switch
3. Defective Power Supply Board or
fuse
4. Defective IGST Board
1. Interlock jumper not installed or
removed
2. Energy Management System does
not have boiler enabled.
3. Device proving switch hooked to
interlocks is not closed.
1. Start the unit. The Air/Fuel Valve should rotate to the purge
(open) position. If the valve does not rotate at all or does not
rotate fully open, check the Air/Fuel Valve calibration. If
calibration is okay, the problem may be in the Air-Fuel Valve or
the Control Box. Refer to qualified service personnel
2. . If the Air/Fuel Valve does rotate to purge, check the ignition
switch for continuity between the N.O. and COM terminals. If the
switch shows continuity when not in contact with the cam replace
the switch.
3. Check to ensure that the switch is wired correctly (correct wire
numbers on the normally open terminals). If the switch is wired
correctly, replace the switch
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
5. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
every second. If not, replace IGST Board
1. Start the unit. The Air/Fuel Valve should rotate to the purge
(open) position, then back to ignition position (towards closed)
during the ignition cycle. If the valve does not rotate back to the
ignition position, check the Air/Fuel Valve calibration. If
calibration is okay, the problem may be in the Air/Fuel Valve or
the Control Box. Refer fault to qualified service personnel.
2. If the Air/Fuel Valve does rotate to the ignition position, check the
ignition position switch for continuity between the N.O. and COM
terminals when in contact with the cam.
3. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
4. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
every second. If not, replace IGST Board.
1. Check for a jumper properly installed across the interlock
terminals in the I/O box
2. If there are two external wires on these terminals check any
Energy Management system to see if they have the units
disabled (a jumper may be temporarily installed to see if the
interlock circuit is functioning).
3. Check that proving switch for any device hooked to the interlock
circuit is closing and that the device is operational.
2. Defective or incorrectly sized Gas
Supply Regulator.
3. Defective Low Pressure Gas Switch
1. Insufficient water level in system
2. Defective water level circuitry.
3. Defective water level probe.
1. Boiler not seeing information from
Modbus network
1. A/F Valve rotated open to purge and
did not rotate to ignition position
2. Defective or shorted switch.
3. Switch wired incorrectly.
4. Defective Power Supply Board or
fuse
1. Check hot and neutral in AC Power Box to ensure they are not
reversed
2. Check transformer wiring, in AC Power Box, against the power
box transformer wiring diagram to ensure it is wired correctly
1. Measure gas pressure upstream of the supply gas regulator with
the unit firing ensure it is 14” WC or greater.
2. Measure gas pressure downstream of the supply regulator with
unit firing and adjust the gas supply regulator to increase the
outlet gas pressure; if outlet gas pressure cannot be increased,
check the sizing of the Supply regulator.
3. Measure gas pressure at the low gas pressure switch, if it is
greater than 5” WC, measure continuity across the switch and
replace if necessary.
1. Check system for sufficient water level.
2. Test water level circuitry using the Control Box front panel LOW
WATER TEST and RESET buttons. Replace water level
circuitry if it does not respond.
3. Check continuity of probe end to the shell, change probe if there
is no continuity.
1. Check network connections. If fault persists, contact qualified
Service Personnel.
1. Start the unit. The Air/Fuel Valve should rotate to the purge
(open) position, then back to ignition position (towards closed)
during the ignition cycle. If the valve does not rotate back to the
ignition position, check the Air/Fuel Valve calibration. If
calibration is okay, the problem may be in the Air/Fuel Valve or
the Control Box. Refer fault to qualified service personnel.
2. If the Air/Fuel Valve does rotate to the ignition position, check the
purge switch for continuity between the N.O. and COM terminals.
If the switch shows continuity when not in contact with the cam,
check to ensure that the switch is wired correctly (correct wire
numbers on the normally open terminals).
3. If the switch is wired correctly, replace the switch.
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
continued 5. Defective IGST Board 5. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
every second. If not, replace IGST Board.
PRG SWTCH OPEN
DURING PURGE
OUTDOOR TEMP
SENSOR FAULT
REMOTE SETPT
SIGNAL FAULT
RESIDUAL
FLAME
1. Defective purge switch.
2. No voltage present at switch.
3. Switch wired incorrectly.
4. Defective Power Supply Board or
fuse
5. Defective IGST Board
1. Loose or broken wiring.
2. Defective Sensor.
3. Incorrect Sensor.
1. Remote setpoint signal not present:
Not yet installed.
Wrong polarity.
Signal defective at source.
Broken or loose wiring.
2. Signal is not isolated (floating) if 4 to
20 mA.
3. Control Box signal type selection
switches not set for correct signal
type (voltage or current).
1. SSOV not fully closed. 1. Check open/close indicator window of Safety Shut-Off Valve
1. If the air-fuel valve does rotate, check the purge switch for
continuity when closing. Replace switch if continuity does not
exist.
2. Measure for 24 VAC from each side of the switch to ground. If
24VAC is not present, refer fault to qualified service personnel.
3. Check to ensure that the switch is wired correctly (correct wire
numbers on the normally open terminals).
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
5. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
every second. If not, replace IGST Board.
1. Inspect Outdoor Temperature sensor for loose or broken wiring.
2. Check resistance of sensor to determine if it is within
specification.
3. Ensure that the correct sensor is installed.
1. Check I/O Box to ensure signal is hooked up.
Hook up if not installed.
If installed, check polarity.
Measure signal level.
Check continuity of wiring between source and boiler.
2. Check signal at source to ensure it is isolated.
3. Check DIP switch on PMC board to ensure it is set correctly for
the type of signal being sent. Check control signal type set in
Configuration Menu.
(SSOV) and ensure that the SSOV is fully closed. If not fully
closed, replace the valve and or actuator.
Close gas shut-off valve downstream of SSOV. Install a
manometer or gauge in a gas test port between the SSOV and
the gas shut off valve. If a gas pressure reading is observed
replace the SSOV valve and or actuator.
1. SSOV relay failed on board. 1. Press CLEAR button and restart unit. If fault persists, replace
1. Actuator not allowing for full closure
of gas valve
2. SSOV powered when it should not be
3. Defective Switch or Actuator
4. Incorrectly wired switch.
1. Air/Fuel Valve out of calibration.
2. Air/Fuel Valve unplugged.
3. Loose wiring connection to the
stepper motor.
4. Defective Air/Fuel Valve stepper
motor.
5. Defective Power Supply Board or
fuse
6. Defective IGST Board
1. Replace or adjust microswitch in SSOV actuator. If fault
persists, replace actuator.
Ignition/Stepper (IGST) Board.
1. Observe operation of the Safety Shut-Off Valve (SSOV) through
indicator on the Valve actuator and ensure that the valve is fully
and not partially closing.
2. If the SSOV never closes, it may be powered continuously. Close
the gas supply and remove power from the unit. Refer fault to
qualified service personnel.
3. Remove the electrical cover from the SSOV and check switch
continuity. If the switch does not show continuity with the gas
valve closed, either adjust or replace the switch or actuator.
4. Ensure that the SSOV Proof of Closure switch is correctly wired.
1. Refer to GF-112 and perform Stepper Test (para. 6.3.5) to
ensure stepper motor rotates properly between the 0% (fully
closed) and 100% (fully open) positions. Verify that the FIRE
RATE bargraph and the dial on the Air/Fuel Valve track each
other to indicate proper operation. If operation is not correct,
perform the Stepper Feedback Calibration (GF-112, para. 6.2.1).
2. Check that the Air/Fuel Valve is connected to the Control Box.
3. .Inspect for loose connections between the Air/Fuel Valve motor
and the wiring harness.
4. Replace stepper motor.
5. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
6. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
every second. If not, replace IGST Board.
8-9
Page 66
Page 67
APPENDIX A
BOILER MENU ITEM DESCRIPTIONS
MENU LEVEL & OPTION DESCRIPTION
OPERATING MENU
Active Setpoint This is the setpoint temperature to which the
control is operating when operating in the
Constant Setpoint, Remote Setpoint or Outdoor
Reset Mode. When in the Constant Setpoint
Mode, this value is equal to the Internal Setpoint
setting in the Configuration Menu. When in the
Remote Setpoint Mode, this value is the setpoint
equivalent to the remote analog signal supplied to
the unit. When in the Outdoor Reset Mode, this is
the derived value from the charts in Appendix D.
Aux Temp For monitoring purposes only
Outdoor Temp Displayed only if an outdoor sensor is installed and
enabled in the Configuration Menu.
Fire Rate In Indicates desired input fire rate. This will normally
be the same as the fire rate shown on the bar-
graph (fire rate out) when the boiler is operating.
Flame Strength Displays flame strength from 0 to 100%.
Run Cycles Displays the total number of run cycles from 0 to
999,999.
Run Hours Displays total run time of unit in hours from 0 to
999,999.
Fault Log Displays information on the last 9 faults.
A-1
Page 68
APPENDIX A
MENU LEVEL & OPTION DESCRIPTION
BOILER MENU ITEM DESCRIPTIONS - Continued
SETUP MENU
Password Allows password to be entered.
Language English Only
Time Displays time from 12:00am to 11:59pm.
Date Displays dates from 01/01/00 to 12/31/99
Unit of Temp Permits selection of temperature displays in
Comm Address For RS-485 (MODBUS) communications (0 to 255).
Baud Rate Allows communications Baud Rate to be set (2400
Software Version Identifies the current software version of the control
Once the valid password (159) is entered, options in
the Setup, Configuration and Tuning Menus can be
modified.
degrees Fahrenheit (°F) or degrees Celsius (°C).
Default is °F.
Default address is 0. RS-232 should have its own
(programmable) password.
to 19.2K). Default is 9600.
box.
CONFIGURATION MENU
Internal Setpoint Allows internal setpoint to be set . Default is 130°F.
Unit Type Allows selection of Boiler or Water Heater. Default
Unit Size Sets unit size from 0.5 to 3.0 MBTUs. Default is 1.0
Boiler Mode It allows selection of: Constant Setpoint, Remote
Remote Signal Used to set the type of external signal which will be
Bldg Ref Temp
is Boiler.
MBTU.
Setpoint, Direct Drive, Combination, or Outdoor
Reset Mode. Default is Constant Setpoint Mode.
used when operating in the Remote Setpoint, Direct
Drive or Combination Mode. The factory default is
4-20 mA/1-5V.
Allows the building reference temperature to be set
when operating a boiler in the Outdoor Reset Mode.
Default is 70°F.
A-2
Page 69
APPENDIX A
BOILER MENU ITEM DESCRIPTIONS - Continued
MENU LEVEL & OPTION DESCRIPTION
Reset Ratio Permits setting of Reset Ratio when operating boiler
in the Outdoor Reset Mode. Reset Ratio is
adjustable from 0.1 to 9.9. Default is 1.2.
Outdoor Sensor Allows outdoor sensor function to be enabled or
disabled. Default is Disabled.
System Start Tmp If outdoor sensor is enabled in the Configuration
Menu, this menu item allows the system start
temperature to be set from 30°F to 100°F. Default
is 60°F.
Setpoint Lo Limit Used to set the minimum allowable setpoint (40°F to
Setpoint Hi Limit). Default is 60°F
Setpoint Hi Limit Used to set the maximum allowable setpoint
(Setpoint Lo Limit to 240°F). Default is 200°F.
Temp Hi Limit Used to set the maximum allowable outlet
temperature (40°F to 240°F). Any temperature
above this setting will turn off the unit. The
temperature must then drop 5°F below this setting
to allow the unit to run. Default Temp Hi Limit is
215°F.
Max Fire Rate Sets the maximum allowable fire rate for the unit
(40% to 100%). Default is 100%.
Pump Delay Timer Specifies the amount of time (0 to 30 min.) to keep
the pump running after the unit turns off. Default is
zero.
Aux Start On Dly Specifies the amount of time to wait (0 to 120 sec.)
between activating the Aux Relay (due to a demand)
and checking the pre-purge string to start the boiler.
Default is 0 sec.
Failsafe Mode Allows the Failsafe mode to be set to either
Constant Setpoint or Shutdown. Default is
Shutdown.
mA Output Can be set to allow this output to monitor Setpoint,
Outlet Temperature, Fire Rate Out or be set to OFF.
Default is OFF.
Lo Fire Timer Specifies how long (2 to 120 sec.) to remain in the
low fire position after ignition, before going to the
desired output. Default is 2 sec.
A-3
Page 70
APPENDIX A
BOILER MENU ITEM DESCRIPTIONS - Continued
MENU LEVEL & OPTION DESCRIPTION
Setpt Limiting Allows Setpoint Limiting to be enabled or disabled.
Default is disabled.
Setpt Limit Band If Setpoint Limiting is enabled, this menu item allows
the Setpt Limit Band to be set from 0°F to 10°F.
Default is 5°F.
TUNING MENU
Prop Band Generates a fire rate based on the error that exists
Integral Gain This sets the fraction of the output, due to setpoint
Derivative Time This value (0.0 to 2.00 min.) responds to the rate of
Reset Defaults? Allows Tuning Menu options to be reset to their
between the setpoint temperature and the actual
outlet temperature. If the actual error is less than
the proportional band setting (1 to 120°F), the fire
rate will be less than 100%. If the error is equal to
or greater than the proportional band setting, the fire
rate will be 100%. Default is 70°F.
error, to add or subtract from the output each minute
to move towards the setpoint. Gain is adjustable
from 0.00 to 2.00. Default is 1.00.
change of the setpoint error. This is the time that
this action advances the output. Default is 0.0 min.
Factory Default values.
A-4
Page 71
MESSAGE DESCRIPTION
DISABLED
HH:MM pm MM/DD/YY
STANDBY Displayed when ON/OFF switch is in the ON position, but
DEMAND DELAY
XX sec
PURGING
XX sec
IGNITION TR IAL
XX sec
FLAME PROVEN
WARMUP
XX sec
WAIT Prompts the operator to wait.
APPENDIX B
STARTUP, STATUS AND FAULT MESSAGES
STARTUP AND STATUS MESSAGES
Displayed if ON/OFF switch is set to OFF. The display also
shows the time and date that the unit was disabled.
there is no demand for heat. The time and date are also
displayed.
Displayed if Demand Delay is active.
Displayed during the purge cycle during startup. The
duration of the purge cycle counts up in seconds.
Displayed during ignition trial of startup sequence. The
duration of cycle counts up in seconds.
Displayed after flame has been detected for a period of 2
seconds. Initially, the flame strength is shown in %. After 5
seconds has elapsed, the time and date are shown in place
of flame strength.
Displayed for 2 minutes during the initial warmup only.
B-1
Page 72
APPENDIX B
FAULT MESSAGE FAULT DESCRIPTION
HIGH WATER TEMP
SWITCH OPEN
LOW WATER
LEVEL
LOW GAS
PRESSURE
HIGH GAS
PRESSURE
INTERLOCK
OPEN
DELAYED
INTERLOCK OPEN
AIRFLOW FAULT
DURING PURGE
PRG SWTCH OPEN
DURING PURGE
IGN SWTCH OPEN
DURING IGNITION
IGN SWTCH CLOSED
DURING PURGE
PRG SWTCH CLOSED
DURING IGNITION
AIRFLOW FAULT
DURING IGN
AIRFLOW FAULT
DURING RUN
SSOV
SWITCH OPEN
SSOV FAULT
DURING PURGE
SSOV FAULT
DURING IGN
SSOV FAULT
DURING RUN
SSOV RELAY
FAILURE
FLAME LOSS
DURING IGN
FLAME LOSS
DURING RUN
HIGH EXHAUST
TEMPERATURE
LOSS OF POWER
FAULT MESSAGES
The High Water Temperature Limit Switch is open.
The Water Level Control board is indicating low water level.
The Low Gas Pressure Limit Switch is open.
The High Gas Pressure Limit Switch is open.
The Remote Interlock is open.
The Delayed Interlock is open.
The Blower Proof Switch opened during purge.
The Purge Position Limit switch on the air/fuel valve opened
during purge.
The Ignition Position Limit switch on the air/fuel valve opened
during ignition.
The Ignition Position Limit switch on the air/fuel valve closed
during purge.
The Purge Position Limit switch on the air/fuel valve closed
during ignition.
The Blower Proof Switch opened during ignition.
The Blower Proof Switch opened during run.
The SSOV switch opened during standby.
The SSOV switch opened during purge.
The SSOV switch closed or failed to open during ignition.
The SSOV switch closed for more than 15 seconds during
run.
A failure has been detected in one of the relays that control
the SSOV.
The Flame signal was not seen during ignition or lost within 5
seconds after ignition.
The Flame signal was lost during run.
The High Exhaust Temperature Limit Switch is closed.
A power loss had occurred. The time and date when power
was restored is displayed.
B-2
Page 73
APPENDIX B
FAULT MESSAGES - Continued
FAULT MESSAGE FAULT DESCRIPTION
RESIDUAL
FLAME
HEAT DEMAND
FAILURE
IGN BOARD
COMM FAULT
DIRECT DRIVE
SIGNAL FAULT
REMOTE SETPT
SIGNAL FAULT
OUTDOOR TEMP
SENSOR FAULT
OUTLET TEMP
SENSOR FAULT
FFWD TEMP
SENSOR FAULT
HIGH WATER
TEMPERATURE
LINE VOLTAGE
OUT OF PHASE
STEPPER MOTOR
FAILURE
NETWORK COMM
FAULT
The Flame signal was seen for more than 60 seconds during
standby.
The Heat Demand Relays on the Ignition board failed to
activate when commanded.
A communication fault has occurred between the PMC board
and Ignition board.
The direct drive signal is not present or is out of range.
The remote setpoint signal is not present or is out of range.
The temperature measured by the Outdoor Air Sensor is out
of range.
The temperature measured by the Outlet Sensor is out of
range.
The temperature measured by the FFWD Sensor is out of
range.
The temperature measured by the Outlet Sensor exceeded
the Temp Hi Limit setting.
The High AC voltage is out of phase from the low AC voltage.
The stepper motor failed to move the valve to the desired
position.
The RS-485 network information is not present or is
corrupted.
B-3
Page 74
Page 75
Temperature Sensor Resistance Chart
(Balco)
APPENDIX C
C-1
Page 76
Page 77
Air
Temp
50F
45F
40F
35F
30F
25F
20F
15F
10F
5F
0F
-5F
-10F
-15F
-20F
Air
Temp
60F
55F
50F
45F
40F
35F
30F
25F
20F
15F
10F
5F
0F
-5F
-10F
-15F
-20F
APPENDIX D
INDOOR/OUTDOOR RESET RATIO CHARTS
Header Temperature for a Building Reference Temperature of 50F
Remote Signal
(If Mode = Remote Setpoint, Direct Drive or
Combination)
Bldg Ref Temp
(If Boiler Mode = Outdoor Reset)
4 – 20 mA /1-5V
70°F
Reset Ratio
(If Boiler Mode = Outdoor Reset)
Outdoor Sensor Disabled
System Start Tmp
(If Outdoor Sensor = Enabled)
Setpt Lo Limit 60°F
Setpt Hi Limit 200°F
Temp Hi Limit
Max Fire Rate 100%
Pump Delay Timer 0 min
Aux Start On Dly 0 sec
Failsafe Mode Shutdown
mA Output Off
Lo Fire Timer 2 sec
Setpt Limit Band (If Setpt Limiting = Enabled) 5°F
1.2
60°F
215°F
Tuning Menu
Prop Band 70°F
Integral Gain 1.00
Derivative Time 0.0 min
E-1
Page 82
Page 83
APPENDIX F
F-1
Page 84
APPENDIX F
F-2
Page 85
APPENDIX F
F-3
Page 86
APPENDIX F
F-4
Page 87
APPENDIX F
F-5
Page 88
APPENDIX F
F-6
Page 89
APPENDIX G
G-1
Page 90
APPENDIX G
G-2
Page 91
APPENDIX G
G-3
Page 92
Page 93
APPENDIX H
H-1
Page 94
APPENDIX H
C
REVDWG. NO.:
161613
SHEET 2 OF 2
CONTROL BOX CONNECTORS
16-PIN CONNECTOR
24-PIN CONNECTOR
OUT
1
211
212
213
214
215
216
9687 5 4 312
219
220
221
LS1
LS2
IN
2
OUT
3
IN
4
OUT
5
IN
6
7
N.C.
1
C
2
N.O.
3
N.C.
1
4
C
5
N.O.
6
7
REMOTE INTLK
EXHAUST TEMP
DELAYED INTLK
NOT USED
RELAY
FAULT
RELAY
AUX
NOT USED
INTERNATIONAL INC.
061302MD
159 PARIS AVE, NORTHVALE, N.J.
GAS FIRED BOILER SYSTEM
(KC 1000)
WIRING SCH EMATIC
MAT'L SPEC.:
TITLE
DATE:CHECKED BY:
124378659 101211
LS3
LS4
226
4
J3J2
87654321
253
252254
3
2
1
3
2
1
2
247
246250
245251
244
243
16
1210 1113 14161517 18 19212022 23 24
241
24024 2
8546791231116141513 1210
238236
876543211211109131415
1
16
15
14
13
12
11
10
9
8
7
6
23523 7239
234232
233
5
4
3
2
231
1
B
OUT
A
B
IN
A
LONWORKS
-
GND
RS-485 IN
+
-
+
ANALOG OUT
SHIELD
-
+
-
+
BMS (PWM) IN
ANALOG IN
SENSOR EXCIT. (12 VDC)
-
+
-
+
-
+
OXYGEN SENSOR IN
FLOW SENSOR IN
CO SENSOR IN
AUX SENSOR IN
SENSOR COMMON IN
OUTDOOR AIR SENSOR IN
INPUT/OUTPUT BOX
DRAWN BY:DATE:
B
ORIGINAL
DWG. SIZE
THIRD ANGLE PROJECTION
.005 TOTAL
AS FOLLOWS UNLESS OTHERWISE SPECIFIED
ALL DIMENSIONS ARE IN INCHES AND ALL TOLERANCES ARE
ALL DIMENSIONS ARE AFTER FINISH OR PLATING
DIAMETERS ON A COMMON AXIS
PERPENDICULARITY/PARALLELISM/FLATNESS .003 TOTAL
XX ±.015 XXX ± .005 FRACTIONS 1/32± ANGLES ±1°
CK'D
DATEBY
REVISIONS
SEE SHEET ONE
J1
H-2
THESE DRAWINGS AND/OR SPECIFICATIONS ARE THE PROPER TY OF AERCO INTERNATIONAL, INC. THEY ARE ISSUED IN STRICT CONFIDENCE AND
SHALL NOT BE REPRODUCED, COPIED, OR USED AS THE BASIS FOR M ANUFACTURE OR SALE OF APPARATUS WITHOUT PERMISSION OF THE OWNER.
REV ECO
Page 95
APPENDIX I
KC1000 CONTROL PANEL EXPLODED VIEW
I-1
Page 96
APPENDIX I
KC1000 CONTROL PANEL REAR VIEW
I-2
Page 97
APPENDIX J
KC1000 LOW NOx DUAL-FUEL
SWITCH-OVER INSTRUCTIONS
The KC1000 Low NOx Boiler is shipped from the factory configured for either natural gas or
propane operation, as specified on the Sales Order. However, if required, the unit’s operating
configuration can be easily switched from natural gas to propane (or vice-versa) by performing a
simple change to the spring contained in the unit’s differential regulator.
The extra spring required to switch from natural gas to propane, or from propane to natural gas
is included with the unit accessories (see Chapter 2, para. 2.2). Units configured for natural gas
operation include a zinc-plated regulator spring, part no. 124803. Units configured for propane
operation include a brown painted spring, part no. 122548.
The following instructions provide the steps necessary to convert the unit from Natural Gas to
Propane operation. Proceed as follows:
1. Shut down the unit and close the external gas supply valve.
2. Remove the sheet metal covers and locate the differential regulator on the left side of
the unit.
3. Refer to Figure 1 and remove the cap on the differential regulator.
4. Using a flat-blade screwdriver, remove the adjustment screw by turning it counterclockwise. Remove the installed zinc-plated regulator spring (124803) used for Natural
Gas operation. DO NOT DISCARD THE REMOVED SPRING.
5. Install the brown painted spring (122548) required for Propane operation.
6. Replace the regulator adjustment screw. Rotate the screw clockwise to a depth of 1-1/2
inches from the top of the regulator housing.
7. Upon completion of the spring change, perform the combustion calibration procedures in
Section 4 of this Instruction Manual.
FIGURE 1. REGULATOR SPRING REPLACEMENT
J-1
Page 98
Page 99
INTERNATIONAL, INC.
Model KC-1000GWB & PWB (Propane)
STANDARD WARRANTY:
Gas-Fired Hydronic Boiler
PRESSURE VESSEL: 10 YEARS NON-PRORATED
The shell shall carry a non-prorated 10 year guarantee from shipment against leakage due to
thermal shock, mechanical defects or workmanship. The shell will not be covered for waterside
corrosion.
HEAT EXCHANGER TUBES/COMBUSTION CHAMBER: 5 YEARS
The heat exchanger/combustion chamber shall carry a 5 year, non-prorated, warranty from
shipment against any condensate corrosion, thermal stress failure, mechanical defects or
workmanship. Operation of the boiler using contaminated air will void the warranty. The heat
exchangers combustion chamber shall not be warranted from failure due to scaling, liming,
corrosion, or erosion due to water or installation conditions. AERCO will repair, rebuild or
exchange, at its option the heat exchanger/combustion chamber for the warranted time period.
“C-MORE” CONTROL PANEL: 2 YEARS FROM SHIPMENT
AERCO labeled control panels are conditionally warranted against failure for (2) two years from
shipment.
OTHER COMPONENTS: 18 MONTHS FROM SHIPMENT
All other components, with the exception of the ignitor and flame detector, are conditionally
guaranteed against any failure for 18 months from shipment.
AERCO shall accept no responsibility if such item has been improperly installed, operated, or
maintained or if the buyer has permitted any unauthorized modification, adjustment, and/or
repairs to the item.
The warranty as set forth on the back page of the Operations & Maintenance Manual is in lieu
of and not in addition to any other express or implied warranties in any documents, or under
any law. No salesman or other representative of AERCO has any authority to expand
warranties beyond the face of the said warranty and purchaser shall not rely on any oral
statement except as stated in the said warranty. Any modifications to this warranty must be
done in writing by an Officer of AERCO. AERCO MAKES NO WARRANTY OF
MERCHANTABILITY OR FITNESS FOR PARTICULAR PURPOSE OR ANY OTHER
EXPRESS OR IMPLIED WARRANTIES. AERCO disclaims all responsibility for any special,
incidental or consequential damages. any claim relating to the product must be filed with
AERCO not later than 14 days after the event giving rise to such claim. Any claims relating to
this product shall be limited to the sale price of the product at the time of sale. The sale of the
product is specifically conditioned upon acceptance of these terms.
03/01/05 W-1 (C102.0)
Page 100
INTERNATIONAL, INC.
Model KC-1000GWB & PWB (Propane)
STANDARD WARRANTY:
Gas-Fired Hydronic Boiler
CONDITIONS OF WARRANTY
Should an AERCO gas-fired (natural gas or propane only) water heater or hydronic boiler fail
for any of the above reasons within the specified time period from the date of original
shipment(s), AERCO shall at its option modify, repair or exchange the defective item. AERCO
shall have the option of having the item returned, FOB its factory, or to make field replacements
at the point of installation. In no event shall AERCO be held liable for replacement labor
charges or for freight or handling charges.
AERCO shall accept no responsibility if such item has been improperly installed, operated, or
maintained or if the buyer has permitted any unauthorized modification, adjustment, and/or
repairs to the item. The use of replacement parts not manufactured or sold by AERCO will void
any warranty, express or limited.
In order to process a warranty claim a formal purchase order number is required prior to
shipment of any warranty item. In addition, the returned item must include a Returned Goods
Authorization (RGA) label, attached to the shipping carton, which identifies the item's return
address, register number and factory authorized RGA number.
Warranty coverage for all components and equipment mentioned in said warranty are not valid
unless the water heater or hydronic boiler is started up by a factory certified SST (Service,
Start-Up and Troubleshooting) Technician and an AERCO start-up sheet is completed.
This warranty coverage is only applicable within the United States and Canada. All other
geographical areas carry a standard warranty of 18 months from date of shipment or 12 months
from startup, whichever comes first.
03/01/05 W-2 (C102.1)
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.