The information contained in this operation and maintenance manual is subject to
change without notice from AERCO International, Inc.
AERCO makes no warranty of any kind with respect to this material, including but not
limited to implied warranties of merchantability and fitness for a particular application.
AERCO International is not liable for errors appearing in this manual. Nor for
incidental or consequential damages occurring in connection with the furnishing,
performance, or use of this material.
Printed in U.S.A.
CONTENTS
Para.
Subject
Page
1.1
Warnings & Cautions
1-1
1.2
Emergency Shutdown
1-2
Para.
Subject
Page
1.3
Prolonged Shutdown
1-2
Para.
Subject
Page
2.1
Receiving the Unit
2-1
2.2
Unpacking
2-1
2.3
Installation
2-2
2.4
Gas Supply Piping
2-4
2.5
Electrical Supply
2-5
Control Wiring
Para.
Subject
Page
2.7
I/O Box Connections
2-8
2.8
Auxiliary Relay Contacts
2-10
2.9
Flue Gas Vent Installation
2-10
2.10
Combustion Air
2-10
Para.
Subject
Page
3.1
Introduction
3-1
3.2
Control Panel Description
3-1
3.3
Control Panel Menus
3-3
3.4
Operating Menu
3-4
3.5
Setup Menu
3-4
Para.
Subject
Page
3.6
Configuration Menu
3-5
3.7
Tuning Menu
3-6
3.8
Start Sequence
3-7
3.9
Start/Stop Levels
3-9
Para.
Subject
Page
4.1
Initial Startup Requirements
4-1
4.2
Tools and Instrumentation for
Combustion Calibration
4-1
4.3
Combustion Calibration
4-2
Para.
Subject
Page
4.4
Propane Combustion Calibration
4-5
4.5
Unit Reassembly
4-6
4.6
Over-Temperature Limit Switch
Adjustments
4-6
Para.
Subject
Page
5.1
Introduction
5-1
5.2
Indoor/Outdoor Reset Mode
5-1
5.3
Constant Setpoint Mode
5-2
5.4
Remote Setpoint Modes
5-2
5.5
Direct Drive Modes
5-3
Para.
Subject
Page
(BMS)
(CCS)
GF-109 - THE AERCO KC1000 GAS FIRED BOILER
Operating & Maintenance Instructions
FOREWARD A
SECTION 1 – SAFETY PRECAUTIONS 1-1
SECTION 2 – INSTALLATION PROCEDURES 2-1
2.6 Mode of Operation and Field
2-6
SECTION 3 – CONTROL PANEL OPERATING PROCEDURES 3-1
SECTION 4 – INITIAL START-UP 4-1
Section 5 – MODE OF OPERATION 5-1
5.6 Boiler Management System
5.7
Combination Control System
5-4
5-5
i
CONTENTS
Para.
Subject
Page
6.1
Testing of Safety Devices
6-1
6.2
Low Gas Pressure Fault Test
6-1
6.3
High Gas Pressure Fault Test
6-1
6.4
Low Water Level Fault Test
6-2
6.5
Water Temperature Fault Test
6-2
6.6
Interlock Fault Tests
6-3
6.7
Flame Fault Test
6-3
Para.
Subject
Page
6.8
Air Flow Fault Test
6-4
6.9
SSOV Proof of Closure Switch
6-4
6.10
Purge Switch Open During
Purge
6-5
6.11
Ignition Switch Open During
Ignition
6-5
6.12
Safety Pressure Relief Valve
Test
6-6
Para.
Subject
Page
7.1
Maintenance Schedule
7-1
7.2
Spark Ignitor
7-1
7.3
Flame Detector
7-2
7.4
Combustion Calibration
7-2
Para.
Subject
Page
7.5
Safety Device Testing
7-2
7.6
Manifold and Exhaust Tubes
7-2
7.7
Heat Exchanger Water Side
Injection
7-5
7.8
Condensate Drain Assembly
7-6
Para.
Subject
Page
8.1
Introduction
8-1
Para.
Subject
Page
Para.
Subject
Page
9.1
Introduction
9-1
9.2
RS232 Communication Setup
9-1
Para.
Subject
Page
RS232 Communication
9.4
Data Logging
9-2
App
Subject
Page
A
Boiler Menu Item Descriptions
A-1
B
Startup, Status and Fault
Messages
B-1
C
Temperature Sensor Resistance
Chart
C-1
D
Indoor/Outdoor Reset Ratio
Charts
D-1
App
Subject
Page
E
Boiler Default Settings
E-1
F
Dimensional and Part Drawings
F-1
G
Piping Drawings
G-1
H
Wiring Schematics
H-1
I
KC1000 Control Panel Views
I-1
J
Recommended Spare Parts
J-1
SECTION 6 – SAFETY DEVICE TESTING PROCEDURES 6-1
SECTION 7 – MAINTENANCE 7-1
SECTION 8 – TROUBLESHOOTING 8-1
SECTION 9 – RS232 COMMUNICATION 9-1
9.3 Menu Processing Utilizing
9-1
APPENDICES
WARRANTIES W-1
ii
FOREWORD
Foreword
The AERCO KC boiler is a true industry advance that meets the needs of today's energy and
environmental concerns. Designed for application in any closed loop hydronic system, the load
tracking capability relates energy input directly to fluctuating system loads through a 20:1
modulating turndown ratio for natural gas units and 14:1 for propane units. The boiler’s
condensing capability offers extremely high efficiencies and makes the KC boiler ideally suited
for modern low temperature, as well as, conventional heating systems.
The KC boiler can be used singular or in modular arrangements for inherent standby with
minimum space requirements. Venting capabilities offer maximum flexibility and allow
installation without normal restrictions. The advanced electronics of each boiler module offer
selectable modes of operation and interface capabilities.
After prolonged shutdown, it is recommended that the startup procedures in Section 4 and test
procedures in Section 6 of this manual be performed, to verify system operating parameters. If
there is an emergency, turn off the electrical power supply to the Aerco boiler or close the
manual gas valve located before the unit. The installer is to identify the emergency shut-off
device. FOR SERVICE OR PARTS, contact your local sales representative or AERCO
INTERNATIONAL.
Installers and operating personnel MUST, at all
times, observe all safety regulations. The
following warnings and cautions are general and
must be given the same attention as specific
precautions included in these instructions. In
addition to all the requirements included in this
AERCO Instruction Manual, the installation of
units MUST conform with local building codes,
or, in the absence of local codes, ANSI Z223.1
(National Fuel Gas Code Publication No. NFPA-
54) for gas-fired boilers and ANSI/NFPASB for
LP gas-fired boilers. Where applicable, the
equipment shall be installed in accordance with
the current Installation Code for Gas Burning
Appliances and Equipment, CSA B149.1, and
applicable Provincial regulations for the class;
which should be carefully followed in all cases.
Authorities having jurisdiction should be
consulted before installations are made.
See pages 1-2, 1-3 and 1-4 for important
information regarding installation of units
within the Commonwealth of Massachusetts.
IMPORTANT
This Instruction Manual is an integral
part of the product and must be
maintained in legible condition. It must
be given to the user by the installer
and kept in a safe place for future
reference.
WARNINGS
MUST BE OBSERVED TO PREVENT
SERIOUS INJURY.
WARNING
BEFORE ATTEMPTING TO
PERFORM ANY MAINTENANCE ON
THE UNIT, SHUT OFF ALL GAS AND
ELECTRICAL INPUTS TO THE UNIT.
WARNING
DO NOT USE MATCHES, CANDLES,
FLAMES, OR OTHER SOURCES OF
IGNITION TO CHECK FOR GAS
LEAKS.
WARNING
A DOUBLE-POLE SWITCH MUST BE
INSTALLED ON THE ELECTRICAL
SUPPLY LINE OF THE UNIT. THE
SWITCH MUST BE INSTALLED IN
AN EASILY ACCESSIBLE POSITION
TO QUICKLY AND SAFELY DISCONNECT ELECTRICAL SERVICE.
DO NOT AFFIX SWITCH TO UNIT
SHEET METAL ENCLOSURES.
WARNING
THE EXHAUST VENT PIPE OF THE
UNIT OPERATES UNDER A POSITIVE PRESSURE AND THEREFORE MUST BE COMPLETELY
SEALED TO PREVENT LEAKAGE
OF COMBUSTION PRODUCTS INTO
LIVING SPACES.
WARNING
FLUIDS UNDER PRESSURE MAY
CAUSE INJURY TO PERSONNEL
OR DAMAGE TO EQUIPMENT
WHEN RELEASED. BE SURE TO
SHUT OFF ALL INCOMING AND
OUTGOING WATER SHUTOFF
VALVES. CAREFULLY DECREASE
ALL TRAPPED PRESSURES TO
ZERO BEFORE PERFORMING
MAINTENANCE.
WARNING
ELECTRICAL VOLTAGES OF 120
VAC ARE USED IN THIS EQUIPMENT. THEREFORE THE COVER
ON THE UNIT’S POWER BOX
(LOCATED ON THE FRONT RIGHT
SIDE OF THE UNIT UNDER THE
HOOD AND SHEET METAL SIDE
PANEL) MUST BE INSTALLED AT
ALL TIMES, EXCEPT DURING
MAINTENANCE AND SERVICING.
CAUTIONS
Must be observed to prevent equipment damage or loss of operating
effectiveness.
1-1
SAFETY PRECAUTIONS
MANUAL GAS SHUTOFF VALVE
VALVE OPEN
VALVE CLOSED
CAUTION
Many soaps used for gas pipe leak
testing are corrosive to metals. The
piping must
be rinsed thoroughly with
clean water after leak checks have
been completed.
CAUTION!
DO NOT use this boiler if any part has
been under water. Call a qualified
service technician to inspect and
replace any part that has been under
water.
1.2 EMERGENCY SHUTDOWN
If overheating occurs or the gas supply fails to
shut off, close the manual gas shutoff valve
(Figure 1-1) located external to the unit.
IMPORTANT
The Installer must identify and indicate
the location of the emergency shutdown
manual gas valve to operating personnel.
1.3 PROLONGED SHUTDOWN
After prolonged shutdown, it is recommended
that the startup procedures in Chapter 4 and the
safety device test procedures in Chapter 5 of
this manual be performed, to verify all systemoperating parameters. If there is an emergency,
turn off the electrical power supply to the
AERCO boiler and close the manual gas valve
located upstream the unit. The installer must
identify the emergency shut-off device.
Boiler Installations within the Commonwealth of Massachusetts must conform to the following
requirements:
• Boiler must be installed by a plumber or a gas fitter who is licensed within the Commonwealth of
• Prior to unit operation, the complete gas train and all connections must be leak tested using a
• If a glycol solution is used as anti-freeze protection, a backflow preventer must be installed
• The vent termination must be located a minimum of 4 feet above grade level.
• If side-wall venting is used, the installation must conform to the following requirements extracted
(a) For all side wall horizontally vented gas fueled equipment installed in every dwelling, building or
structure used in whole or in part for residential purposes, including those owned or operated by the
Commonwealth and where the side wall exhaust vent termination is less than seven (7) feet above
finished grade in the area of the venting, including but not limited to decks and porches, the following
requirements shall be satisfied:
Figure 1-1: Manual Gas Shutoff Valve
IMPORTANT – FOR MASSACHUSETTS INSTALLATIONS
Massachusetts.
non-corrosive soap.
upstream of the Fill/Makeup Valve.
from 248 CMR 5.08 (2):
1-2
SAFETY PRECAUTIONS
1. INSTALLATION OF CARBON MONOXIDE DETECTORS. At the time of installation of the
side wall horizontal vented gas fueled equipment, the installing plumber or gasfitter shall observe
that a hard wired carbon monoxide detector with an alarm and battery back-up is installed on the
floor level where the gas equipment is to be installed. In addition, the installing plumber or
gasfitter shall observe that a battery operated or hard wired carbon monoxide detector with an
alarm is installed on each additional level of the dwelling, building or structure served by the side
wall horizontal vented gas fueled equipment. It shall be the responsibility of the property owner to
secure the services of qualified licensed professionals for the installation of hard wired carbon
monoxide detectors.
a. In the event that the side wall horizontally vented gas fueled equipment is installed in
a crawl space or an attic, the hard wired carbon monoxide detector with alarm and
battery back-up may be installed on the next adjacent floor level.
b. In the event that the requirements of this subdivision can not be met at the time of
completion of installation, the owner shall have a period of thirty (30) days to comply with
the above requirements; provided, however, that during said thirty (30) day period, a
battery operated carbon monoxide detector with an alarm shall be installed.
2. APPROVED CARBON MONOXIDE DETECTORS. Each carbon monoxide detector as
required in accordance with the above provisions shall comply with NFPA 720 and be ANSI/UL
2034 listed and IAS certified.
3. SIGNAGE. A metal or plastic identification plate shall be permanently mounted to the exterior
of the building at a minimum height of eight (8) feet above grade directly in line with the exhaust
vent terminal for the horizontally vented gas fueled heating appliance or equipment. The sign
shall read, in print size no less than one-half (1/2) inch in size, "GAS VENT DIRECTLY BELOW.
KEEP CLEAR OF ALL OBSTRUCTIONS".
4. INSPECTION. The state or local gas inspector of the side wall horizontally vented gas fueled
equipment shall not approve the installation unless, upon inspection, the inspector observes
carbon monoxide detectors and signage installed in accordance with the provisions of 248 CMR
5.08(2)(a)1 through 4.
(b) EXEMPTIONS: The following equipment is exempt from 248 CMR 5.08(2)(a)1 through 4:
1. The equipment listed in Chapter 10 entitled "Equipment Not Required To Be Vented" in the
most current edition of NFPA 54 as adopted by the Board; and
2. Product Approved side wall horizontally vented gas fueled equipment installed in a room or
structure separate from the dwelling, building or structure used in whole or in part for residential
purposes.
(c) MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM PROVIDED. When
the manufacturer of Product Approved side wall horizontally vented gas equipment provides a venting
system design or venting system components with the equipment, the instructions provided by the
manufacturer for installation of the equipment and the venting system shall include:
1. Detailed instructions for the installation of the venting system design or the venting system
components; and
2. A complete parts list for the venting system design or venting system.
1-3
SAFETY PRECAUTIONS
(d) MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM NOT PROVIDED.
When the manufacturer of a Product Approved side wall horizontally vented gas fueled equipment does
not provide the parts for venting the flue gases, but identifies "special venting systems", the following
requirements shall be satisfied by the manufacturer:
1. The referenced "special venting system" instructions shall be included with the appliance or
equipment installation instructions; and
2. The "special venting systems" shall be Product Approved by the Board, and the instructions
for that system shall include a parts list and detailed installation instructions.
(e) A copy of all installation instructions for all Product Approved side wall horizontally vented gas fueled
equipment, all venting instructions, all parts lists for venting instructions, and/or all venting design
instructions shall remain with the appliance or equipment at the completion of the installation.
_______________________________ [End of Extracted Information From 248 CMR 5.08 (2)
1-4
SECTION 2 -INSTALLATION PROCEDURES
2.1. RECEIVING THE UNIT
Each KC1000 Boiler is shipped as a single
crated unit. The crated unit shipping weight is
approximately 1500 pounds. It must be moved
with the proper rigging equipment for safety and
to avoid unit damages. The unit should be
completely inspected for shipping damage and
completeness at the time of receipt from the
carrier and before the bill of lading is signed.
Each unit has Tip-N-Tell indicator on the outside
of the crate, that indicates if the unit has been
turned on its side. If the Tip-N-Tell indicator is
tripped, do not sign for the shipment. Request a
freight claim and inspection by a claims adjuster
before proceeding or refuse delivery of the
equipment.
2.2. UNPACKING
Carefully unpack the unit. Take care not to
damage the unit jacket when cutting away
packaging materials. An inspection of the unit
should be made to determine if damage during
shipment occurred that was not indicated by the
Tip-N-Tell. The freight carrier should be notified
INSTALLATION
immediately if any damage is detected. The
following accessories come standard with each
unit and are packed separately within the unit’s
packing container
• Spare Spark Ignitor
• Spare Flame Detector
• Manual 1-1/4" Gas Shutoff Valve
• Drain Valve Assembly
• ASME Pressure Relief Valve
• Ignitor Removal Tool (One per Site)
• Temperature/Pressure Gauge and Fittings
• 2 Lifting Lugs
• Stainless Steel Condensate Cup
• Shell Cap
• Wing Nut for Shell Cap
Optional accessories are also separately packed
within the unit’s packing container. Standard and
optional accessories shipped with the unit
should be identified and put in a safe place until
installation or use.
Figure 2.1. Boiler Clearances
2-1
INSTALLATION
LIFTING LUGS
2.3 INSTALLATION
The unit must be installed with the prescribed
clearances for service as shown in Figure 2.1.
The minimum
AERCO, are listed below. Local building codes
may require more clearance and take
precedence
Minimum clearances required:
Sides 24"
Front 18"
Rear 18"
Top 18"
All gas piping, water piping, and electrical
conduit or cable must be arranged so that they
do not interfere with the removal of any cover, or
inhibit service or maintenance of the unit.
KEEP UNIT AREA CLEAR AND FREE
FROM COMBUSTIBLE MATERIALS AND
FLAMMABLE VAPORS AND LIQUIDS.
MASSACHUSETTS INSTALLATIONS
For boiler installations within the
Commonwealth of Massachusetts, the
boiler must be installed by a plumber or
gas fitter who is licensed within the
Commonwealth. In addition, the boiler
installation must comply with all
requirements specified in Section 1
(Safety Precautions), pages 1-2 and 1-3.
2.3.1. SETTING THE UNIT
Remove the unit from the wooden skid and
place in position using a block and tackle or
hoist attached to the lifting lugs, (see Figure
2.2). USE ONLY THE LIFTING LUGS TO
MOVE THE UNIT.
The KC-1000 is U/L approved for installation on
combustible flooring. A 4” to 6" high housekeeping concrete pad is recommended and
allows for sufficient drainage of the condensate.
It is suggested that units be secured using the
holes provided in the frame base. Piping must
not be used to secure the unit in place. See
drawing AP-A-568 in Appendix F for the base
frame dimensions.
clearance dimensions, required by
WARNING!
In multiple unit installations, it is important to
plan the position of each unit. Sufficient space
for piping connections and future maintenance
requirements must be given. All piping must
include ample provision for expansion.
If installing a Combination Control (CCP)
system, it is important to identify and place the
Combination Mode units in the proper physical
location.
Figure 2.2
Lifting Lug Location
2.3.2 SUPPLY AND RETURN PIPING
The locations of the 4" flanged system supply,
and return piping connections, to the unit are
shown in Figure 2.3. The return connection is
located on the left side near the base of the
unit’s shell. The supply connection is located on
the left side near the top of the unit’s shell.
Whether installing single or multiple units, install
the piping and accessories as shown in the
appropriate piping diagram located in the
Appendix G. For applications other than standard space heating, consult the AERCO Boiler
Application Guide, GF-1070, or AERCO for the
appropriate piping schematics.
The minimum flow rate through the unit is 25
GPM and the maximum flow rate is 150 GPM.
Each unit is fitted with 4" flanges for high flow
application and the system velocity at the unit
return should not exceed 5 feet per second.
Each unit must have individual valves on the
supply, and return, for maintenance. In multiple
unit installations, the flow through each unit must
be balanced.
2-2
INSTALLATION
Every boiler plant must have a source of makeup water to it. As with any closed loop hydronic
system, air elimination and expansion equipment must be provided as part of the overall
installation. All piping MUST include ample
provision for expansion.
The relief piping must be full size without
reduction. No valves, restrictions, or other
blockages should be allowed in the discharge
line. In multiple unit installations the relief valve
discharge lines must not
(connected), together. Each must be individually
run to a suitable discharge location. The drain
valve provided should be installed on the right
hand side of the unit towards the bottom of the
shell. The valve should be pointed in the down
position, (see Figure 2.4).
be manifolded,
Figure 2.3
Supply and Return Location
NOTE:
The maximum working pressure for
installations within the Province of Alberta is
87 psig. Therefore a pressure relief valve
with a setting of 75 psig (or lower) should be
installed for these installations. See Drawing
AP-A-863 in Appendix F.
2.3.3 PRESSURE RELIEF AND DRAIN
VALVE INSTALLATION
An ASME rated Relief Valve is supplied with
each unit. The supplied pressure relief valve
setpoint will be 30, 50, 75, 100, or 150
ordered from the factory. Install the pressure
relief valve in the tapping provided opposite the
system supply connection, (see Figure 2.4). The
pressure relief valve should be piped in the
vertical positionusing the fittings supplied. A
suitable pipe compound should be used on the
threaded connections, and excess should be
wiped off to avoid getting any into the valve
body. The discharge from the relief valve should
be piped to within 12 inches of the floor to
prevent injury in the event of a discharge.
psig as
Figure 2.4
Relief and Drain Valve Location
2.3.4 TEMPERATURE/PRESSURE
INDICATOR
The unit is supplied with one of two styles of
Temperature/Pressure Indicators that must be
installed in the tapping on the supply flange of
the unit (see Figures. 2.5a and 2.5b). A suitable
pipe compound should be used sparingly to the
threaded connection.
2-3
INSTALLATION
SHELL
CAP
PARTIAL TOP VIEW OF BOILER
FOR INSTALLATION OF PRESS./TEMP. GAUGE
PART NO. 122994-1 (PRESS. RANGE 0 – 75 PSI)
SYSTEM
SUPPLY
1/2" x 1 /4"
REDUCING BUSHING
PRESS./TEMP. GAUGE
SHELL
CAP
PARTIAL TOP VIEW OF BOILER
FOR INSTALLATION OF PRESS./TEMP. GAUGE
PART NO. 122994-2 (PRESS. RANGE 0 – 200 PSI)
PART NO. 122994-3 (PRESS. RANGE 0 – 300 PSI)
SYSTEM
SUPPLY
1/2" NIPPLE
1/2" UNION
PRESS./TEMP. GAUGE
TEMPERATURE SENSOR
EXHAUST
MANIFOLD
CONDENSATE
DRAIN
BURNER
HOSE CLAMP
1-3/4" O.D. x 8-1 /2
“ LG.
SILICONE HOSE
5/8" O.D. TUBE CONN.
CONDENSATE CUP
PLACED ON FLOOR
Figure 2.5a
Pressure /Temperature Gauge Installation
route it to a floor drain. If a floor drain is not
available, a condensate pump can be used to
remove the condensate to drain. The
condensate drain line must be removable for
routine maintenance. Therefore, DO NOT hardpipe.
4. Replace the rear cover and side panel on the
unit.
Pressure/Temperature Gauge Installation
2.3.5 CONDENSATE PIPING
The KC Boiler is designed to condense.
Therefore, the installation site must include
suitable provisions for condensate drainage or
collection. A stainless steel condensate cup is
separately packed within the unit’s shipping
container. To install the condensate cup,
proceed as follows:
1. Remove the left side panel and only the left
half of the rear cover to provide access to the
exhaust manifold and burner (Figure 2.6).
2. Insert the 1-3/4 inch manifold drain hose into
the condensate cup. Allow the cup to rest on
the floor directly beneath the manifold drain
hole (Figure 2.6).
3. Attach a length of 3/4 inch I.D. polypropylene
tubing to the condensate cup drain tube and
2-4
Figure 2.5b
Figure 2.6
Condensate Drain System Location
2.4. GAS SUPPLY PIPING
The AERCOGas Fired Equipment Gas Components and Supply Design Guide (GF-1030) must be
consulted before any gas piping is designed or
started.
WARNING!
DO NOT USE MATCHES, CANDLES,
FLAMES OR OTHER SOURCES OF
IGNITION TO CHECK FOR GAS LEAKS.
CAUTION!
Soaps used for gas pipe leak testing can be
corrosive to metals. Piping must be rinsed
thoroughly with clean water after leak
checks have been completed.
NOTE:
All gas piping must be arranged so that it
does not interfere with removal of any
cover, inhibit service or maintenance, or
prevent access between the Unit and walls,
or another unit.
INSTALLATION
The location of the 1-1/4" inlet gas connection is
on the right side of the unit as shown in Figure
2.7.
All pipe should be de-burred and internally
cleared of any scale or iron chips before
installation. No flexible connectors or nonapproved gas fittings should be installed. Piping
should be supported from floor or walls only and
must not be secured to the unit.
A suitable piping compound, approved for use
with gas, should be used sparingly. Any excess
must be wiped off to prevent clogging of
components.
To avoid damage to the unit, when pressure
testing gas piping, isolate the unit from the
supply gas piping. At no time should there be
more than 14” W.C. the unit. Bubble test all
external piping thoroughly for leaks using a
soap and water solution or suitable equivalent.
The gas piping must meet all applicable codes.
it. When the gas supply pressure will not exceed
14” W.C. a non-lock up or flow through style
regulator may be used. When supply gas
pressure will exceed 14” W.C., a lock up style
regulator must be used. The gas supply
regulator must be propery vented to outdoors.
Consult the local gas utility for exact
requirements concerning venting of supply gas
regulators.
CAUTION!
A lockup style regulator must be used when
gas supply pressure exceeds 14” W.C.
2.4.2 MANUAL GAS SHUTOFF VALVE
A 1-1/4” manual gas shut-off valve is furnished
with each unit. The valve should be positioned
as shown in Figure 2.7. The manual gas shut-of
valve must be installed upstream of the supply
regulator in a readily accessible location.
2.4.1 GAS SUPPLY PRESSURE
REGULATOR
An external, in-line, supply gas regulator
(supplied by others) should be positioned as
shown in Figure 2.7. Union connections should
be placed in the proper locations to allow
maintenance of the regulator if required
NOTE:
An individual gas pressure regulator must
be installed upstream of each KC1000. The
regulator must regulate gas pressure to 8.5”
W.C. at 1,000,000 BTU/H for natural gas
and propane units.
The maximum static inlet pressure to the unit
must be no more than 14” water column.
Minimum gas pressure is 8.5” W.C. for FM gas
trains and 8.9” W.C. for IRI gas trains when the
unit is firing at maximum input. Gas pressure
should not exceed 10.5” W.C. at any time when
firing. Proper sizing of the gas supply regulator
in delivering the correct gas flow and outlet
pressure is mandatory. The gas supply pressure
regulator must maintain the gas pressure at a
regulated 8.5” W.C. minimum for FM gas trains
and 8.9” W.C. for IRI gas trains at maximum
BTU input (1,000,000 BTU/HR) for natural gas
and propane installations. The supply gas
regulator must be of sufficient capacity volume,
(1000 cfh), for the unit and should have no more
than 1" droop from minimum to full fire. The
supply gas regulator must also be rated to
handle the maximum incoming gas pressure to
Gas Supply Regulator and Manual Shut -Off
2.4.3 IRI GAS TRAIN KIT
The IRI gas train is an optional gas train
required in some areas by code or for insurance
purposes. The IRI gas train is factory pre-piped
and wired. (Refer to Appendix F, Drawing No.
SD-A-584).
2.5 ELECTRICAL SUPPLY
The AERCO Gas Fired Equipment Electrical
Power Wiring Guide, (GF-1060), must be
consulted in addition to the following material
before wiring to the unit is started. AC power
connection to the unit are made at the Power
Box.This box is located on the front right side of
the unit as shown in Figure 2.8. Conduit should
Figure 2.7
Valve Location
2-5
INSTALLATION
POWER BOX
BLOWER
SSOV
ACTUATOR
FRAME
USE COPPER CONDUCTORS ONLY FOR FIELD WIRING
60 HZ
DISCONNECT POWER BEFORE SERVICING
DANGER: HIGH VOLTAGE
20 AMP
120 VAC,
NEUTRAL
GROUND
LINE
POWER BOX
AERCO INTERNATIONAL INC.
INPUT POWER
I/O
BOX
GAS SHUT-OFF VALVE
BLOWER
be run from the knockouts in the side of the box
in such a manner that it does not interfere with
the removal of any sheet metal covers. A flexible
electrical connection may be utilized to allow the
covers to be easily removed.
Figure 2.8
AC Power Box Location
NOTE:
All electrical conduit and hardware should
be installed so that it does not interfere with
the removal of any cover, inhibit service or
maintenance, or prevent access between
the unit and walls or another unit.
2.5.1 ELECTRICAL REQUIREMENTS
Electrical requirements for each unit are 120
VAC, 1 Phase, 60 Hz, 20 Amps from a
dedicated electrical circuit. No other devices
should be on the same electrical circuit as a
KC1000 unit.
A double-pole switch must be installed on the
electrical supply line in an easily accessible
location to quickly and safely disconnect
electrical service. DO NOT attach the switch to
sheet metal enclosures of the unit.
After placing the boiler in service, the ignition
safety shutoff device must be tested. If an
external electrical power source is used, the
installed boiler must be electrically bonded to
ground in accordance with the requirements of
the authority having jurisdiction. In the absence
of such requirements, the installation shall
2-6
conform to National Electrical Code (NEC),
ANSI/NFPA 70 and/or the Canadian Electrical
Code (CEC) Part I, CSA C22.1 Electrical Code.
The AC power wiring diagram is shown in Figure
2.9.
Figure 2.9
AC Power Wiring Diagram
2.6 MODE OF OPERATION and FIELD
CONTROL WIRING
The KC Boiler is available in several different
modes of operation. While each unit is factory
configured and wired for the mode specified on
the equipment order, some field wiring may be
required to complete the installation. This wiring
is typically routed to the Input/Output (I/O) Box
located on the left side of the unit beneath the
removable side panel (see Figure 2.10). Field
wiring for each particular mode of operation is
described in the following paragraphs. For
additional information concerning modes of
operations, refer to Section 5.
Figure 2.10
Input/Output (I/O) Box Location
INSTALLATION
mA OUT
RS-485
COMM.
+
-
+
-
ANALOG IN
SENSOR COMMON
OUTDOOR SENSOR IN
REMOTE INTL'K IN
B.M.S. (PWM) IN
SHIELD
+
-
+
-
AUX SENSOR IN
NOT USED
EXHAUST SWITCH IN
DELAYED INTL'K IN
FAULT RELAY
120 VAC, 5A, RES
AUX RELAY
120 VAC, 5A, RES
G
RELAY CONTACTS:
120 VAC, 30 VDC
5 AMPS RESISTIVE
DANGER
120 VAC USED
IN THIS BOX
NOT USED
NOT USED
NC
COM
NO
NC
COM
NO
NOT USED
2.6.1 CONSTANT SETPOINT MODE
The Constant Setpoint Mode is used when it is
desired to have a fixed setpoint that does not
deviate. No wiring connections other than
electrical supply connections are required for
this mode. However, if desired, fault monitoring
or enable/disable interlock wiring can be utilized
(see paragraphs 2.7.9 and 2.7.10).
2.6.2 INDOOR/OUTDOOR RESET MODE
This mode of operation increases supply water
temperature as outdoor temperatures decrease.
An outside air temperature sensor (AERCO PN
122790) is required. The sensor MUST BE
wired to the I/O Box wiring terminals (see Figure
2.11). For more information concerning the
outside air sensor installation, refer to paragraph
2.7.1. For programming and setup instructions
concerning the indoor/outdoor-reset mode of
operation, refer to Section 5, paragraph 5.1.
.
2.6.3 BOILER MANAGEMENT SYSTEM
When using an AERCO Boiler Management
System (BMS), the field wiring is connected
between the BMS Panel and each Boiler’s I/O
Box terminal strip (Figure 2-11). Twisted
shielded pair wire from 18 to 22 AWG must be
utilized for the connections. The BMS Mode can
utilize either pulse width modulation (PWM)
signaling, or RS485 Modbus signaling. For PWM
I/O Box Terminal Strip
(BMS) MODE
NOTE
BMS Model 168 can utilize either pulse
width modulation (PWM) or RS485
Modbus signaling to the Boiler. BMS II
Model 5R5-384 can utilize only RS485
signaling to the Boiler.
Figure 2.11
signaling, connections are made from the
AERCO Boiler Management System to the
B.M.S. (PWM) IN terminals on the I/O Box
terminal strip. For RS485 Modbus signaling,
connections are made from the BMS to the
RS485 COMM terminals on the I/O Box terminal
strip. Polarity must be maintained and the shield
must be connected only at the AERCO BMS.
The boiler end of the shield must be left floating.
For additional instructions, refer to Chapter 5,
paragraph 5.6 in this manual. Also, refer to GF108M (BMS Model 168) and GF-124 (BMS II
Model 5R5-384), BMS -Operations Guides.
2-7
INSTALLATION
2.6.4 REMOTE SETPOINT and DIRECT
DRIVE MODES
The KC1000 Boiler can accept several types of
signal formats from an Energy Management
System or other source to control either the
setpoint (Remote Setpoint Mode) or valve
position (Direct Drive Mode) of the Boiler. These
formats are:
4 to 20 mA/1 to 5 Vdc
0 to 20 mA/0 to 5 Vdc
PWM – (Pulse Width Modulated signal. See
paragraph 2.7.4)
Network – (RS485 Modbus. See para. 2.7.7)
While it is possible to control one or more boilers
using one of the above modes of operation, it
may not be the method best suited for the
application. Prior to selecting one of the above
modes of operation, it is recommended that you
consult with your local AERCO representative or
the factory for the mode of operation that will
work best with your application. For more
information on wiring the 4 to 20 mA / 1to 5VDC
or the 0 to 20 mA / 0 to 5 VDC, see paragraph
2.7.3.
2.6.5 COMBINATION MODE
NOTE
Only BMS Model 168 can be utilized for
the Combination Mode, not the BMS II
(Model 5R5-384).
With a Combination Mode unit, field wiring is
between the unit’s I/O Box, the CCP
(Combination Control Panel), and the BMS
Model 168 (Boiler Management System). The
wiring must be done using a shielded twisted
pair of 22 AWG wire. Polarity must be
maintained between the unit, the CCP, and the
BMS. For further instructions and wiring
diagrams, refer to the GF-108 Boiler
Management System Operations Guide and the
CCP-1 data sheet.
2.7 I/O BOX CONNECTIONS
The types of input and output/signals and
devices to be connected to the I/O Box terminals
shown in Figure 2.11 are described in the
following paragraphs.
CAUTION!
DO NOT make any connections to the I/O
Box terminals labeled “NOT USED”.
Attempting to do so may cause equipment
damage.
2.7.1 OUTDOOR SENSOR IN
An outdoor air temperature sensor (AERCO Part
No. 122790) will be required mainly for the
Indoor/Outdoor Reset mode of operation. It can
also be used with another mode if it is desired to
use the outdoor sensor enable/disable feature.
This feature allows the boiler to be enabled or
disabled based on the outdoor air temperature.
The factory default for the outdoor sensor is
DISABLED. To enable the sensor and/or select
an enable/disable outdoor temperature, see the
Configuration menu in Section 3.
The outdoor sensor may be wired up to 200 feet
from the boiler and is connected to the
OUTDOOR SENSOR IN and the SENSOR
COMMON terminals in the I/O box (see Figures
2.10 and 2.11). Wire the sensor using a twisted
shielded pair cable of 18-22 AWG wire. There is
no polarity when terminating the wires. The
shield is to be connected only to the terminals
labeled SHEILD in the I/O Box. The sensor end
of the shield must be left free and ungrounded.
When mounting the sensor, it must be located
on the North side of the building where an
average outside air temperature is expected.
The sensor must be shielded form direct sunlight
as well as impingement by the elements. If a
shield is used, it must allow for free air
circulation.
2.7.2 AUX SENSOR IN
The AUX SENSOR IN terminals can be used to
add an additional temperature sensor for
monitoring purposes. This input is always
enabled and is a view only input that can be
seen in the operating menu. The sensor must be
wired to the AUX SENSOR IN and SENSOR
COMMON and must be similar to AERCO
BALCO wire sensor P/N 12449. A resistance
chart for this sensor can be found in Appendix
C.
2-8
INSTALLATION
2.7.3 ANALOG IN
The ANALOG IN + and – terminals are used
when an external signal is used to drive the
valve position (Direct Drive Mode) or change the
setpoint (Remote Setpoint Mode) of the Boiler.
Either a 4 to 20 mA / 1 to 5 VDC or a 0 to 20 mA
/ 0 to 5 VDC signal may be used to vary the
setpoint or valve position. The factory default
setting is 4 to 20 mA / 1 to 5 VDC, however this
may be changed to 0 to 20 mA / 0 to 5 VDC
using the Configuration Menu described in
Section 3. If voltage rather than current is
selected as the drive signal, a DIP switch must
be set on the PMC Board located inside the
Control Box. Contact the AERCO factory for
information on setting DIP switches.
All supplied signals must be floating
(ungrounded) signals. Connections between the
source and the Boiler’s I/O Box must be made
using twisted shielded pair of 18 –22 AWG wire
such as Belden 9841(see Figure 2.11). Polarity
must be maintained and the shield must be
connected only at the source end and must be
left floating (not connected) at the Boiler’s I/O
Box.
Whether using voltage or current for the drive
signal, they are linearly mapped to a 40°F to
240°F setpoint or a 0% to 100% valve position.
No scaling for these signals is provided.
2.7.4 B.M.S. (PWM) IN
NOTE
Only BMS Model 168 can utilize Pulse
Width Modulation (PWM), not the BMS II
(Model 5R5-384).
These terminals are used to connect the
AERCO Boiler Management System (BMS)
Model 168 to the unit. The BMS Model 168
utilizes a 12 millisecond, ON/OFF duty cycle.
This duty cycle is Pulse Width Modulated (PWM)
to control valve position. A 0% valve position =
a 5% ON pulse and a 100% valve position = a
95% ON pulse.
2.7.5 SHIELD
The SHIELD terminals are used to terminate any
shields used on sensor wires connected to the
unit. Shields must only be connected to these
terminals.
2.7.6 mA OUT
These terminals provide a 4 to 20 mA output
that can be used to monitor setpoint ( 40°F to
220°F), outlet temperature (30°F to 245°F), or
valve position (0% to 100%). This function is
enabled in the Configuration Menu (Section 3,
Table 3-4).
2.7.7 RS-485 COMM
These terminals are used for RS-485 MODBUS
serial communication between the unit and an
external “Master”, such as a Boiler Management
System or other suitable device.
2.7.8 EXHAUST SWITCH IN
These terminals permit an external exhaust
switch to be connected to the exhaust manifold
of the boiler. The exhaust sensor should be a
normally open type switch (such as AERCO Part
No. 123463) that closes (trips) at 500
o
F.
2.7.9 INTERLOCKS
The unit offers two interlock circuits for
interfacing with Energy Management Systems
and auxiliary equipment such as pumps or
louvers. These interlocks are called the Remote
Interlock and Delayed Interlock (Figure 2.11).
The wiring terminals for these interlocks are
located inside the I/O Box on the left side of the
unit. The I/O Box cover contains a wiring
diagram which shows the terminal strip locations
for these interlocks which are labeled REMOTE
INTL’K IN and DELAYED INTL’K IN. Both
interlocks, described in the following
paragraphs, are factory wired in the closed
position.
NOTE:
Both the Delayed Interlock and Remote
Interlock must be in the closed position to
allow the unit to fire.
2.7.9.1 REMOTE INTERLOCK IN
The remote interlock circuit (REMOTE INTL’K
IN) is provided to remotely start (enable) and
stop (disable) the Boiler if desired. The circuit is
24 VAC and comes factory pre-wired closed
(jumpered).
2-9
INSTALLATION
2.7.9.2 DELAYED INTERLOCK IN
The delayed interlock circuit (DELAYED INTL’K
IN) is typically used in conjunction with the
auxiliary relay described in paragraph 2.8. This
interlock circuit is located in the purge section of
the start string. It can be connected to the
proving device (end switch, flow switch etc.) of
an auxiliary piece of equipment started by the
boiler’s auxiliary relay. The delayed interlock
must be closed for the boiler to fire. If the
delayed interlock is connected to a proving
device that requires time to close (make), a time
delay (Aux Start On Dly) that holds the start
sequence of the boiler long enough for for a
proving switch to make can be programmed.
Should the proving switch not prove within the
programmed time frame, the boiler will shut
down. The Aux Start On Dly can be
programmed from 0 to 120 seconds. This option
is locate in the Configuration Menu (Section 3).
2.7.10 FAULT RELAY
The fault relay is a single pole double throw
(SPDT) relay having a normally open and
normally close set of relay contacts that are
rated for 5 amps at 120 VAC and 5 amps at 30
VDC. The relay energizes when any fault
condition occurs and remains energized until the
fault is cleared and the CLEAR button is
depressed. The fault relay connections are
shown in Figure 2.11.
2.8 AUXILIARY RELAY CONTACTS
Each Boiler is equipped with a single pole
double throw (SPDT) relay that is energized
when there is a demand for heat and de-
energized after the demand for heat is satisfied.
The relay is provided for the control of auxiliary
equipment, such as pumps and louvers, or can
be used as a Boiler status indictor (firing or not
firing). Its contacts are rated for 120 VAC @ 5
amps. Refer to Figure 2.11 to locate the AUX
RELAY terminals for wiring connections.
2.9 FLUE GAS VENT INSTALLATION
The AERCO Venting and Combustion Air Guide,
GF-1050, must be consulted before any flue or
inlet air venting is designed or installed.
Suitable, U/L approved, positive pressure,
water-tight vent materials as specified in
AERCO’s GF-1050, must be used for safety and
UL certification. Because the unit is capable of
discharging low temperature exhaust gases, the
flue must be pitched back to the unit a minimum
of 1/4" per foot to avoid any condensate pooling
and to allow for proper drainage.
While there is a positive flue pressure during
operation, the combined pressure drop of vent
and combustion air systems must not exceed
140 equivalent feet of 0.81” W.C.. Fittings as
well as pipe lengths must be calculated as part
of the equivalent length. For a natural draft
installation the draft must not exceed - 0.25”
W.C..These factors must be planned into the
vent installation. If the maximum allowable
equivalent lengths of piping are exceeded, the
unit will not operate properly or reliably.
2.10 COMBUSTION AIR
The AERCO Venting and Combustion Air Guide,
GF-1050, MUST be consulted before any flue or
combustion supply air venting is designed or
started. Combustion air supply is a direct
requirement of ANSI 223.1, NFPA-54, CSA
B149.1 and local codes. These codes should be
consulted before a permanent design is
determined.
The combustion air must be free of chlorine,
halogenated hydrocarbons, or other chemicals
that can become hazardous when used in gasfired equipment. Common sources of these
compounds are swimming pools, degreasing
compounds, plastic processing and refrigerants.
Whenever the environment contains these types
of chemicals, combustion air must be supplied
from a clean area outdoors for the protection
and longevity of the equipment.
The more common methods of combustion air
supply venting are outlined below. For
combustion air supply from ducting, consult the
AERCO GF-1050, Venting and Combustion Air
Guide.
2.10.1 COMBUSTION AIR FROM
OUTSIDE THE BUILDING
Air supplied from outside the building must be
provided through two permanent openings. For
each unit these two openings must have a free
area of not less than one square inch for each
4000 BTUs input of the equipment or 250
square inches of free area. The free area must
take into account restrictions such as louvers
and bird screens. For Canada installations, refer
to the requirements specified in CSA B149.1.10,
8.4.1 and 8.4.3.
2.10.2 COMBUSTION AIR FROM INSIDE
THE BUILDING
When combustion air is provided from within the
building, it must be supplied through two
permanent openings in an interior wall. Each
opening must have a free area of not less than
one square inch per 1000 BTUH of total input or
2-10
INSTALLATION
1000 square inches of free area. The free area
must take into account any restrictions such as
louvers.
2.10.3 SEALED COMBUSTION
The KC Boiler is UL approved for 100% sealed
combustion application when installed properly.
When a sealed combustion air application is
installed, the sealed combustion air piping must
be deducted from the maximum allowable
discharge piping amounts. Each unit must have
a minimum 6" diameter connection made to the
special Inlet Air Adapter # GP-18917 available
from AERCO. This adapter bolts directly on to
the air inlet of the unit’s blower. See installation
instructions with adapter. All inlet air ducts must
be sealed air tight.
2-11
CONTROL PANEL OPERATING PROCEDURES
3
1
2
7
4
6
10
8
9
5
11
12
SECTION 3 - CONTROL PANEL OPERATING PROCEDURES
3.1. INTRODUCTION
The information in this Section provides a guide
to the operation of the KC1000 Boiler using the
Control Panel mounted on the front of the unit.
It is imperative that the initial startup of this unit
be performed by factory trained personnel.
Operation prior to initial startup by factory
trained personnel will void the equipment
warranty. In addition, the following WARNINGS
and CAUTIONS must be observed at all times.
CAUTION:
All initial installation procedures must be
satisfied before attempting to start the unit.
WARNING:
ELECTRICAL VOLTAGES IN THIS
SYSTEM INCLUDE 120 AND 24 VOLTS
AC. IT MUST NOT BE SERVICED OR
ACCESSED BY OTHER THAN FACTORY
CERTIFIED SERVICE TECHNICIANS.
WARNING:
DO NOT ATTEMPT TO DRY FIRE THE
BOILER. STARTING THE UNIT WITHOUT
A FULL WATER LEVEL CAN SERIOUSLY
DAMAGE THE UNIT AND MAY RESULT IN
PERSONNEL INJURY OR PROPERTY
DAMAGE. THIS SITUATION WILL VOID
ANY WARRANTY.
3.2. CONTROL PANEL DESCRIPTION
The KC1000 Control Panel shown in Figure 3-1
contains all of the controls, indicators and
displays necessary to operate, adjust and
troubleshoot the KC1000 Boiler. These operating controls, indicators and displays are listed
and described in Table 3-1. Additional information on these items are provided in the individual
operating procedures provided in this Section.
Figure 3-1. Control Panel Front View
3-1
CONTROL PANEL OPERATING PROCEDURES
FUNCTION
follows:
COMM
Lights when RS-232 communication is occurring
keypad.
from an Energy Management System
DEMAND
Lights when there is a demand for heat.
Menu Selection
in degrees Fahrenheit or degrees Celsius.
connected to the boiler Control Panel.
5
READY Indicator
Lights when all Pre-Purge conditions have been satisified.
6
ON/OFF Switch
Enables and disables boiler operation.
Pressing CLEAR resets the display.
condition occurs. An alarm message will appear in the VFD.
alarms
the Control Panel Menus:
The Menu categories wrap around in the order shown.
category.
Table 3-1. Operating Controls, Indicators and Displays
ITEM
NO.
CONTROL, INDICATOR
OR DISPLAY
1 LED Status Indicators Four Status LEDs indicate the current operating status as
MANUAL
REMOTE
2 VFD Display Vacuum Fluorescent Display (VFD) consists of 2 lines, each
3
OUTLET
TEMPERATURE
Display
4 RS-232 Port Port permits a Laptop Computer or External Modem to be
7
LOW WATER LEVEL
TEST/RESET Switches
Lights when the unit is being controlled using the front panel
Lights when the unit is being controlled by an external signal
capable of displaying up to 16 alphanumeric characters. The
information displayed includes:
Startup Messages
Alarm Messages
Operating Status Messages
3–Digit, 7–Segment LED display continuously displays the
outlet water temperature. The °F or °C LED next to the
display lights to indicate whether the displayed temperature is
Allow the operator to test the operation of the water level
monitor.
Pressing TEST opens the water level probe circuit and
simulates a Low Water Level alarm.
Pressing RESET resets the water level monitor circuit.
8 FAULT Indicator Red FAULT LED indicator lights when a boiler alarm
9 CLEAR Key Turns off the FAULT indicator and clears trhe alarm message
if the alarm is no longer valid. Lockout type alarms will be
latched and cannot be cleared by simply pressing this key.
Troubleshooting may be required to clear these types of
10 MENU Keypad Consists of 6 keys which provide the following functions for
MENU
BACK
Steps through the main menu categories shown in Figure 3-2.
Allows you to go back to the previous menu level without
changing any information. Continuously pressing this key will
bring you back to the default status display in the VFD. Also,
this key allows you to go back to the top of a main menu
3-2
CONTROL PANEL OPERATING PROCEDURES
FUNCTION
pressing the ▲ arrow key will increment the selected setting.
setting.
flashing will increment or decrement the displayed setting.
display will stop flashing.
100%
Table 3-1. Operating Controls, Indicators and Displays - Continued
ITEM
NO.
CONTROL, INDICATOR
OR DISPLAY
10
(Cont.)
▲ (Up) Arrow When in one of the main menu categories (Figure 3-2),
pressing this key will select the displayed menu category. If
the CHANGE key was pressed and the menu item is flashing,
▼ (Down) Arrow
When in one of the main menu categories (Figure 3-2),
pressing this key will select the displayed menu category. If
the CHANGE key was pressed and the menu item is flashing,
pressing the ▼ (Down) arrow key will increment the selected
Permits a setting to be changed (edited). When the
CHANGE key is pressed, the displayed menu item will begin
to flash. Pressing the ▲ or ▼ arrow key when the item is
Saves the modified menu information in memory. The
CHANGE
ENTER
11 AUTO/MAN Switch This switch toggles the boiler between the Automatic and
Manual modes of operation. When in the Manual (MAN)
mode, the front panel controls are enabled and the MANUAL
status LED lights.
When in the Automatic (AUTO) mode, the MANUAL status
LED will be off and the front panel controls disabled.
12
VALVE POSITION
Bargraph
20 segment red LED bargraph continuously shows the
Air/Fuel Valve Position (% open) in 5% increments from 0 to
3.3. CONTROL PANEL MENUS
The Control Panel incorporates an extensive
menu structure which permits the operator to set
up, and configure the unit. The menu structure
consists of four major menu categories as
shown in Figure 3-2. Each of the menus shown,
contain options which permit operating
parameters to be viewed or changed. The
menus are protected by a password to prevent
unauthorized use.
Prior to entering the correct password, the
options contained in the Operating, Setup,
Configuration and Tuning Menu categories can
be viewed. However, with the exception of
Internal Setpoint Temperature (Configuration
Menu), none of the viewable menu options can
be changed.
Once the valid password (159) is entered, the
options listed in the Setup, Configuration and
Tuning menus can be viewed and changed, if
desired.
3.3.1. Menu Processing Procedure
Accessing each menu and option is
accomplished using the Menu Keys shown in
Figure 3-1. Therefore, it is imperative that you
be thoroughly familiar with the following basic
steps before attempting to perform specific
menu procedures.
1. The Control Panel will normally be in the
Operating Menu and the VFD will display the
current unit status. Pressing the ▲ or ▼
arrow key will display the other available data
items in the Operating Menu.
2. Press the MENU key. The display will show
the Setup Menu which is the next menu
category shown in Figure 3-2. This menu
contains the Password option which must be
entered if other menu options will be
changed.
3. Continue pressing the MENU key until the
desired menu is displayed.
3-3
CONTROL PANEL OPERATING PROCEDURES
OPERATION
SETUP
CONFIGURATION
TUNING
PASSWORD
4. With the desired menu displayed, press the
▲ or ▼ arrow key. The first option in the
selected menu will be displayed.
5. Continue to press the ▲ or ▼ arrow key until
the desired menu option is displayed.
Pressing the ▲arrow key will display the
available menu options in the Top-Down
sequence. Pressing the ▼ arrow key will
display the options in the Bottom-Up
sequence. The menu options will wraparound after the first or last available option
is reached.
6. To change the value or setting of a displayed
menu option, press the CHANGE key. The
displayed option will begin to flash. Continue
to press the ▲ or ▼ arrow key for the option
to be changed. The available menu option
choices will be displayed. The menu option
choices do not wrap around.
7. To select and store a changed menu option,
press the ENTER key.
NOTE:
The following paragraphs provide brief
descriptions of the options contained in each
menu. Refer to Appendix A for detailed
descriptions of each menu option. Refer to
Appendix B for listings and descriptions of
displayed startup, status and error messages.
3.4. OPERATING MENU
The Operating Menu displays a number of key
operating parameters for the unit as listed in
Table 3-2. This menu is “Read-Only” and does
not allow personnel to change or adjust any of
the displayed items. Since this menu is “ReadOnly”, it can be viewed at any time without
entering a password. Press the ▲ arrow key to
display the menu items in the order listed (TopDown). Pressing the ▼ arrow key will display
the menu items in reverse order (Bottom-Up).
3.5. SETUP MENU
The Setup Menu (Table 3-3) permits the
operator to set the unit password which is
required to change any of the menu options. To
prevent unauthorized use, a previously entered
password entry will time-out after 1 hour. Therefore, the password must be reentered when
required. In addition to permitting password
entries, the Setup Menu is also used to enter
date and time, language to be used for display
messages, units of temperature measurements
and entries required for external communication
and control of the unit via the RS-232 port. A
view-only software version display is also
provided to indicate the current Control Box
software version.
Figure 3-2. Menu Structure
3-4
CONTROL PANEL OPERATING PROCEDURES
Available Choices or Limits
Menu Item Display
Minimum
Maximum
Menu Item
Display
Available Choices or Limits
Menu Item Display
Minimum
Maximum
Default
NOTE
The Outdoor Temp display item shown with an asterisk in Table
3-2 will not be displayed unless the Outdoor Sensor function has
been enabled in the Configuration Menu (Table 3-4).
Table 3-2. Operating Menu
Status Message
Active Setpoint 40°F 240°F
AIR Temp -70°F 245°F
Outdoor Temp* -70°F 130°F
Valve Position In 0% 100% Valve
Flame Strength 0% 100%
Run Cycles 0 999,999,999
Position
Run Hours 0 999,999,999
Fault Log 0 19 0
Passsword 0 9999 0
Language English English
Time 12:00 am 11:59 pm
Date 01/01/00 12/31/99
Unit of Temp Fahrenheit or Celsius Fahrenheit
Comm Address 0 127 0
Baud Rate 2400, 4800, 9600, 19.2K 9600
Software Ver 0.00 Ver 9.99
Table 3-3. Setup Menu
3-5
CONTROL PANEL OPERATING PROCEDURES
Available Choices or Limits
Menu Item Display
Minimum
Maximum
Default
3.6. CONFIGURATION MENU
The Configuration Menu shown in Table 3-4
permits adjustment of the Internal Setpoint
(Setpt) temperature regardless of whether the
valid password has been entered. Setpt is
required for operation in the Constant Setpoint
mode. The remaining options in this menu
require the valid password to be entered, prior to
changing existing entries. This menu contains a
number of other configuration settings which
may or may not be displayed, depending on the
current operating mode setting.
Table 3-4. Configuration Menu
Internal Setpt Lo Temp Limit Hi Temp Limit 130°F
Unit Type
Unit Size
Fuel Type Natural Gas, Propane Natural Gas
Boiler Mode
Remote Signal
(If Mode = Remote
Setpoint, Direct Drive
or Combination)
Bldg Ref Temp
(If Mode = Outdoor
Reset)
Reset Ratio
(If Mode = Outdoor
Reset)
Outdoor Sensor Enabled or Disabled Disabled
System Start Tmp
(If Outdoor Sensor =
Enabled)
KC Boiler, KC Boiler LN,
BMK Boiler, BMK Boiler LN,
BMK Boiler Dual, KC Water
Heater, KC Water Heater LN,
Water Heater 2010
0.5 MBTU, 1.0 MBTU
1.5 MBTU, 2.0 MBTU
3.0 MBTU, 3.5 MBTU
4.0 MBTU, 5.0 MBTU
Constant Setpoint,
Remote Setpoint,
Combination
Outdoor Reset
4 – 20 mA/1 – 5V
0 -20 mA/0 – 5V
PWM Input (BMS)
40°F 230°F 70°F
0.1 9.9 1.2
30°F 100°F 60°F
NOTE:
The Configuration Menu settings shown in
Table 3-4 are Factory-Set in accordance
with the requirements specified for each
individual order. Therefore, under normal
operating conditions, no changes will be
required.
KC Boiler
1.0 MBTU
6.0 MBTU
Constant
Setpoint
Direct Drive
4 – 20 mA,
1-5V
Network
3-6
CONTROL PANEL OPERATING PROCEDURES
Available Choices or Limits
Menu Item Display
Minimum
Maximum
Default
Available Choices or Limits
Menu Item Display
Minimum
Maximum
Default
Prop Band
1°F
120°F
70°F
Integral Gain
0.00
2.00
1.00
Derivative Time
0.0 min
2.0 min
0.0 min
Reset Defaults?
Yes
Are You Sure?
No
Table 3-4. Configuration Menu - Continued
Setpt Lo Limit 40°F Setpt Hi Limit 60°F
Setpt Hi Limit Setpt Lo Limit 220°F 195°F
Temp Hi Limit 40°F 240°F 195°F
Max Valve Position 40% 100% 100%
Pump Delay Timer 0 min. 30 min. 0 min.
Aux Start On Dly 0 sec. 120 sec. 0 sec.
Failsafe Mode Shutdown or Constant Setpt Shutdown
*Analog Output
(See CAUTION at
end of Table 3-4 )
Low Fire Timer 2 sec. 600 sec. 2 sec.
Setpt Limiting Enabled or Disabled Disabled
Setpt Limit Band 0°F 10°F 5°F
Network Timeout 5 Sec 999 Sec 30 Sec
HI DB Setpt EN 0% 100% 30%
Demand Offsert 0 25 10
Deadband High 0 25 2
Deadband Low 0 25 2
Off, Setpoint, Outlet Temp,
Valve Position 4-20 mA,
Valve Position 0-10V
*CAUTION:
DO NOT CHANGE the Analog Output Menu Item from its Default setting
(Valve Position 0-10V).
3.7. TUNING MENU
The Tuning Menu items in Table 3-5 are Factory
set for each individual unit.
Table 3-5. Tuning Menu
*Valve
Position
0-10V
Do not change these menu entries unless
specifically requested to do so by FactoryTrained personnel.
No
3-7
CONTROL PANEL OPERATING PROCEDURES
STEPPER
MOTOR
DETAIL "A"
DIAL
(DETAIL “A”)
100
BLOWER
BURNER
3.8. START SEQUENCE
When the Control Box ON/OFF switch is set to
the ON position, it checks all pre-purge safety
switches to ensure they are closed. These
switches include:
• Safety Shut-Off Valve Proof of Closure
(POC) switch
• Low Water Level switch
• High Water Temperature switch
• High Gas Pressure switch
• Low Gas Pressure switch
If all of the above switches are closed, the
READY light above the ON/OFF switch will light
and the unit will be in the Standby mode.
When there is a demand for heat, the following
events will occur:
NOTE:
If any of the Pre-Purge safety device switches
are open, the appropriate fault message will be
displayed. Also, the appropriate fault messages
will be displayed throughout the start sequence,
if the required conditions are not observed.
3. With all required safety switches closed, a
purge cycle will be initiated and the following
events will occur:
(a) Blower relay energizes and turns on
blower.
(b) Air/Fuel Valve rotates to the full-open
purge position and closes purge position
switch. The dial on the Air/Fuel Valve
(Figure 3-4) will read 100 to indicate that
the valve is full-open (100%).
(c) The VALVE POSITION bargraph will
show 100%.
1. The DEMAND LED status indicator will light.
2. The unit checks to ensure that the proof of
closure switch in the Safety Shut-Off Valve
(SSOV) is closed (Figure 3-3).
Figure 3-4.
Air/Fuel Valve In Purge Position
4. Next, the blower proof switch (Figure 3-5)
closes and the display will show Purging and
indicate the elapsed time of the purge cycle
in seconds.
3-8
Figure 3-3.
Safety Shut-Off Valve
CONTROL PANEL OPERATING PROCEDURES
154
155
AIR/FUEL VALVE
BLOWER PROOF
SWITCH
TO FRAME
HARNESS
STEPPER
MOTOR
DETAIL "A"
DIAL
(DETAIL “A”)
BLOWER
BURNER
25
Figure 3-5.
Blower Proof Switch
5. Upon completion of the purge cycle, the
Control Box initiates an ignition cycle and the
following events occur:
(a) The Air/Fuel Valve rotates to the low-fire
ignition position and closes the ignition
switch. The dial on the Air/Fuel Valve
(Figure 3-6) will read between 25 and 35
to indicate that the valve is in the lowfire position.
(b) The igniter relay is activated and
provides ignition spark.
Figure 3-6.
Air/Fuel Valve In Ignition Position
9. Once the demand for heat has been
satisfied, the Control Box will turn off the gas
valve. The blower relay will be deactivated
and the Air/Fuel Valve will be closed.
Standby will be displayed.
(c) The gas Safety Shut Off Valve (SSOV)
is energized (opened) allowing gas to
flow into the Air/Fuel Valve.
6. Up to 7 seconds will be allowed for ignition to
be detected. The igniter relay will be turned
off one second after flame is detected.
7. After 2 seconds of continuous flame, Flame Proven will be displayed and the flame
strength will be indicated. After 5 seconds,
the current date and time will be displayed in
place of the flame strength.
8. With the unit firing properly, it will be
controlled by the temperature controller
circuitry. The VALVE POSITION will be
continuously displayed on the front panel
bargraph.
3.9. START/STOP LEVELS
The start and stop levels are the valve position
percentages that start and stop the unit, based
on load. These levels are Factory preset as
follows for natural gas and propane units:
• Start Level: 20% (All units)
• Stop Level: 13% (Natural Gas)
• Stop Level: 16% (Propane)
Normally, these settings should not require
adjustment.
Note that the energy input of the boiler is not
linearly related to the valve position percentage
(Air/Fuel Valve Position). Refer to Table 3-6 for
the relationship between the energy input and
valve position percentage for a unit running on
natural gas.
3-9
CONTROL PANEL OPERATING PROCEDURES
Table 3-6.
Relationship Between Air/Fuel Valve Position and Energy Input of a Unit Running on Natural Gas
Valve position,
Air/Fuel Valve
Position
(% Open)
0 0 0
10 0 0
13
(Stop Level)
20 89,000 9%
30 191,000 19%
40 311.000 31%
50 460,000 46%
60 600,000 60%
70 699,000 70%
80 836,000 84%
90 955,000 96%
100 1,000,000 100%
Energy Input
(BTU/Hr)
50,000 5 %
Boiler Energy Input
(% of Full Capacity)
3-10
SECTION 4 - INITIAL START- UP
4.1 INITIAL START- UP REQUIREMENTS
The initial start-up of the KC-1000 Boiler is
comprised of the following steps:
• installation completed 100%
• combustion calibration
• proper setting of controls and limits
• mode of operation settings (see Section 5)
• safety device testing (see Section 6)
Installation procedures should be completed
100% before performing initial start-up and initial
the start-up must be complete prior to putting the
unit into service. Starting a unit without the
proper piping, venting, or electrical systems can
be dangerous and void the product’s warranty.
These start-up instructions should be precisely
followed in order for the unit to operate safely, at
a high thermal efficiency, and with low flue gas
emissions.
Initial unit start-up is to be performed ONLY by
AERCO factory trained start-up and service
personnel. After following the steps in this
section, it will be necessary to perform the mode
of operation settings in section 5, and the safety
control test procedures in section 6 to complete
the initial unit start-up.
An AERCO Gas Fired Startup Sheet included
with each KC-1000 must be completed for each
unit for warranty validation and a copy must be
returned promptly to AERCO at:
AERCO International, Inc.
159 Paris Ave.
Northvale, NJ 07647
WARNING!
DO NOT ATTEMPT TO FIRE THE UNIT
WITHOUT FULL WATER LEVEL. THIS
CAN SERIOUSLY DAMAGE THE UNIT
AND MAY RESULT IN PERSONAL
INJURY OR PROPERTY DAMAGE. THIS
IS NOT COVERED BY WARRANTY.
CAUTION!
All installation procedures in Section 2 must
be completed before attempting to start the
unit.
INITIAL START-UP
4.2 TOOLS AND INSTRUMENTATION
FOR COMBUSTION CALIBRATION
To properly perform combustion calibration, the
proper instruments and tools must be used and
correctly installed on the unit. The following
paragraphs outline the necessary tools and
instrumentation as well as their installation.
4.2.1 REQUIRED TOOLS AND
INSTRUMENTATION
The following tools and instrumentation are
necessary to perform combustion calibration of
the unit:
1. A digital combustion analyzer with oxygen
accuracy to 0.4%, and carbon monoxide in
PPM.
2. *A 16" W.C. manometer and plastic tubing.
3. One 1/4” and two 1/8” NPT-to-barbed fittings
for use with manometers.
4. A flat-tip screwdriver for adjusting the
AERCO differential gas pressure regulator.
5. Small and large flat blade screwdrivers.
6. 7/16" open end wrench and small adjustable
wrenches.
7. Tube of silicone adhesive
*For propane fired units: an additional 8" W.C.
manometer and 1/2" NPT to barbed fitting is
needed.
4.2.2 INSTALLING THE SUPPLY GAS
MANOMETER
1. Close the main manual gas supply valve up
stream of the unit.
2. Remove the 1/4" NPT pipe plug from the
port on the inlet side of the safety shut off
valve (see Figure 4.1).
3. Install a barbed fitting into the pipe plug
tapping.
4. Attach one end of a length of plastic tubing
to the barbed fitting and one end to the 16"
W.C. manometer.
4-1
SSOV
1/8" NPT PLUG
(INSTALL
MANOMETER
HERE)
3/8" - 1/2"
HOLE FOR
COMBUSTION
ANALYZER
PROBE
EXHAUST
MANIFOLD
12" - 18"
INITIAL START-UP
Figure 4.1
1/8” Gas Plug Location
4.2.3 PREPARING THE FLUE VENT
PROBE HOLE
1. If the unit has been installed using the
recommended AL29-4C vent, there will be a
3/8” hole, 18” to 24” above the exhaust
manifold. The outer vent section, that covers
vent section connections must be loosened
and moved to uncover the hole (see
Fig. 4.2).
2. If equipped with one, adjust the stop on the
combustion analyzer probe so that it
extends into the flue gas flow without hitting
the opposite wall of the flue. Do not insert
the probe at this time.
4-2
Figure 4.2
Analyzer Probe Hole Location
IMPORTANT
The unit is shipped from the factory set up for
either natural gas or propane, as specified by
the Style No. on the Sales Order.
For propane units, refer to paragraph 4.4 for
some additional setup procedures unique to
propane units. The oxygen and carbon
monoxide levels in Tables 1, 2 and 3 apply to
both natural gas and propane. However, it
should be noted that in Table 2 the oxygen and
carbon monoxide levels are measured at 13%
for natural gas and 16% for propane.
4.3 NATURAL GAS COMBUSTION
CALIBRATION
The KC-1000 is shipped combustion calibrated
from the factory. Recalibration as part of a startup is necessary due to altitude, gas BTU
content, gas supply piping and supply
regulators. Factory test data sheets are shipped
with each unit as a reference.
The following combustion calibration procedure
closely follows the factory procedure. By
following this procedure, readjustment of the
combustion settings will be kept to a minimum.
1. Open the water supply and return valves to
the unit and ensure that the system pumps
are running.
2. Open the gas supply valve(s) to the unit.
3. If a lockup style regulator is installed as a
gas supply regulator, adjust the gas supply
until a reading of 12” W.C. static pressure is
obtained.
4. Set the ON/OFF switch to the OFF position.
Turn on AC power to the unit. The display
will show LOSS OF POWER and the time
and date.
5. Set the unit to the Manual Mode by pressing
the AUTO/MAN switch. A flashing Manual Valve Position message will be displayed
with the present Air/Fuel Valve position in %
open. Also, the MANUAL LED will light.
NOTE:
For a review of control panel operating
procedures, refer to Section 3.
6. Adjust the Valve Position to 0% by pressing
the ▼ arrow key.
7. Set the ON/OFF switch to the ON position.
8. Change the Valve Position to 25% using the
▲ arrow key. This will put the unit into the
starting sequence.
INITIAL START-UP
Inlet Air
Temp
Oxygen
(+0.2/-1.0)
Carbon
Monoxide
-20°F
7.5 %
<50 ppm
0°F
7.3 %
<50 ppm
10°F
7.2 %
<50 ppm
30°F
6.8 %
<50 ppm
50°F
6.4 %
<50 ppm
60°F
6.2 %
<50 ppm
70°F
6.0 %
<50 ppm
80°F
5.8 %
<50 ppm
90°F
5.6 %
<50 ppm
100°F
5.4 %
<50 ppm
DIFFERENTIAL PRESSURE
REGULATOR
REGULATOR
CAP
CAP GASKET
NOTE:
On initial start-up, or return to service from a
fault condition, the unit will remain at a 29%
valve position for two-minutes, although the
control signal may indicate a greater input.
9. Following the warm-up period, increase the
valve position in 20% increments while
monitoring the gas pressure after each
increase. If gas pressure dips below 8.5”
W.C. for FM gas trains and 8.9” for IRI gas
trains at any valve position percentage, stop
and raise the pressure. Once 100% is
reached, adjust the gas pressure for 8.5”
W.C. or 8.9” W.C.
NOTE:
If 8.5” W.C. for FM gas trains or 8.9” W.C. for IRI
gas trains cannot be obtained at the 100% valve
position, it will be necessary to stop calibration
and contact the local AERCO representative in
your area. Running the unit on insufficient gas
pressure will void the warranty
10. Once 8.5” W.C. or 8.9” W.C. is set at the
100% valve position, change the valve
position to 30% and insert the combustion
analyzer probe into the stack.
NOTE:
Always go to a percentage of valve position from
the same direction, (i.e., 100% to 30% or 30% to
20%). Whenever going to a valve position from
below (i.e., 20% to 30%), first go above then
back down to the desired valve position. This is
necessary due to hysteresis in the air/fuel valve
stepper motor. Hysteresis causes the air/fuel
valve to stop in a slightly different position if the
valve position percentage is approached from
below or above. This results in a difference in
oxygen readings for the same valve position
percentage causing unnecessary recalibration.
11. Allow enough time for the combustion
analyzer to settle. Compare the measured
oxygen level to the oxygen range for the
existing intake air temperature in Table 1.
12. If the measured oxygen level is within the
range listed in Table 1, no adjustment is
necessary. Proceed to step 19.
13. If the measured oxygen level is not within
the range listed in Table 1, remove the
regulator cap and cap gasket from the
differential pressure regulator (see
Figure 4.3) and proceed to step 14.
Table 1
Combustion Oxygen Levels for a 30%
Valve Position
Figure 4.3
Differential Regulator
14. Use a flat-tip screwdriver to adjust the
differential pressure regulator. Turn the
screwdriver:
•counterclockwise to increase the
oxygen level
•clockwise to decrease the oxygen level
15. Replace the regulator cap and cap gasket
and wait for the analyzer reading to settle.
16. When the analyzer reading settles, compare
the new oxygen reading to Table 1.
17. If necessary, repeat the adjustment until the
oxygen level is within the range specified in
Table 1.
18. Replace the regulator cap and cap gasket.
NOTE:
Adjust only the differential regulator at 30%
control signal; Do Not adjust the air shutter.
4-3
INITIAL START-UP
Temp
(+0.2/-1.0)
Monoxide
-20°F
<12 %
<50 ppm
0°F
<12 %
<50 ppm
10°F
<12 %
<50 ppm
30°F
<12 %
<50 ppm
50°F
<11 %
<50 ppm
60°F
<11 %
<50 ppm
70°F
<11 %
<50 ppm
80°F
<11 %
<50 ppm
90°F
<10 %
<50 ppm
100°F
<10 %
<50 ppm
Temp
(+0.2/-1.0)
Monoxide
-20°F
6.5 %
<150 ppm
0°F
6.3 %
<150 ppm
10°F
6.2 %
<150 ppm
30°F
5.8 %
<150 ppm
50°F
5.4 %
<150 ppm
60°F
5.2 %
<150 ppm
70°F
5.0 %
<150 ppm
80°F
4.8 %
<150 ppm
90°F
4.6 %
<150 ppm
100°F
4.4 %
<150 ppm
BLOWER
OUTLET
BLOWER
INLET
SCREEN
SHUTTER
SHUTTER
LOCKING
NUTS
NOTE:
In the following step, adjust the valve position to
13% for natural gas, or 16% for propane.
19. When the oxygen level is within the
specified range at 30%, change the valve
position to 13% for natural gas (or 16% for
propane).
20. The oxygen levels at the 13% valve position
(or 16% for propane) should be as shown in
Table 2. No adjustment should be
necessary. Contact the factory if the oxygen
or carbon monoxide levels are not within the
specified range.
Table 2
Combustion Oxygen Levels for a 13%
(Natural Gas) or 16% (Propane) Valve
Position
Inlet Air
Oxygen
Carbon
22. If the measured oxygen reading is below the
oxygen range in Table 3, loosen the two
bolts that secure the inlet air shutter to the
unit using a 7/16” wrench (see Fig. 4.4).
Open the shutter 1/4” to 1/2” to increase the
oxygen level, then tighten the nuts.
23. Wait for the analyzer to settle then compare
the new oxygen reading to Table 3. Repeat
the inlet air shutter adjustment until the
oxygen is within the specified range. Firmly
tighten the inlet air shutter locking nuts when
finished.
24. If the measured oxygen reading is above the
oxygen range in Table 3, loosen the two
7/16" locking nuts securing the inlet air
shutter.
REMINDER:
At 30% valve position, adjust only the differential
pressure regulator. At 100% valve position,
adjust only the inlet air shutter.
21. Change the valve position to 100%. After the
combustion analyzer has settled, compare
the measured oxygen level with the levels in
Table 3.
Table 3
Combustion Oxygen Levels for a 100%
Valve Position
Inlet Air
Oxygen
Carbon
Figure 4.4
Air Shutter Locking Nut Location
25. Close the air shutter 1/4” to 1/2” to decrease
the oxygen level and tighten the two nuts.
26. Allow the analyzer to settle then compare
the new oxygen reading to Table 3.
27. Repeat the adjustment until the oxygen is
within the specified range. Firmly tighten the
inlet air shutter locking nuts when finished.
4-4
INITIAL START-UP
NOTE:
Adjust the inlet air shutter only at 100% valve
position. Do not adjust the differential pressure
regulator.
28. Change the valve position to 30%. Allow
time for the combustion analyzer to settle.
Check the measured oxygen reading to
insure that it is still within the range as per
Table 1.
29. Continue this procedure until all oxygen
levels are within the ranges specified in
Tables 1, 2 and 3.
30. Record all readings on the AERCO start-up
sheet provided with each unit. Proceed to
paragraph 4.5.
6. If the pressure drop is not within this range,
remove the cap from the air pressure
regulator.
7. Using a flat blade screwdriver adjust the
regulator until 3.8” to 4.0” W.C. is obtained.
Clockwise will increase the reading and
counterclockwise will decrease the reading.
8. It adjustments are made to this regulator, it
will be necessary to recheck oxygen
readings at 16%, 30%, and 100% valve
positions.
NOTE:
After an adjustment is made to the air regulator,
the cap must be replaced and securely tightened
to obtain an accurate reading
4.4 PROPANE COMBUSTION
CALIBRATION
For propane units it will be necessary to install
an additional 8” W.C. This manometer will be
used to measure the pressure drop across the
air/propane mixing orifice. After performing the
setup procedures in paragraphs 4.2.2 through
4.2.4, install the 8” W.C. manometer as
described in steps 1, 2 and 3 which follow.
1. Refer to Fig. 4.5 and remove the 1/8” NPT
plug from the gas inlet pipe ahead of the
burner. Install a 1/8” NPT barbed fitting.
2. Remove the 1/2” NPT plug from the tee
located after the air pressure regulator and
Propane Air Differential Pressure Taps
Figure 4.5
install a 1/2” barbed fitting (see Fig. 4.5).
3. Attach the 8” W.C. manometer to the barbed
fittings installed in steps 1, and 2.
NOTE:
The combustion calibration data in Tables 1, 2
and 3 apply to both natural gas and propane
units. Therefore, refer to these Tables when
performing propane combustion calibration.
Note that Table 2 checks the oxygen and carbon
monoxide levels at a valve position of 16% for
propane instead of the 13% used for natural
gas.
4. While performing the combustion calibration
procedure in paragraph 4.3, measure the
pressure drop across the air/propane mixing
orifice using the 0-8” W.C. manometer.
5. This reading should remain constant at 3.8”
4.5 UNIT REASSEMBLY
Once combustion calibration is set properly, the
unit can be reassembled for permanent
operation as follows:
1. Set the ON/OFF switch to the OFF position.
Disconnect the AC power supply from the
unit.
2. Shut off the gas supply to the unit.
3. Remove the differential pressure regulator
cap and cap gasket (see Figure 4.3).
4. Apply a drop of silicone adhesive to the
regulator adjusting screw to lock its setting.
5. Reinstall the regulator cap and gasket on
the regulator. Tighten the cap using a
screwdriver or wrench.
to 4.0” W.C. throughout the operating range.
4-5
INITIAL START-UP
OVER-TEMPERATURE
SWITCHES
SHELL SENSOR
209
TEMPERATURE SWITCH DETAILS
137
HARNESS
136
FROM SHELL
NCNCCNO
C
LIQUID LEVEL SWITCH
OVER TEMP. SWITCH
6. Remove all of the manometers and barbed
fittings and reinstall the pipe plugs using a
suitable thread compound.
7. Remove the combustion analyzer probe
from the vent hole. Seal the probe hole and
replace the vent connection cover.
8. Replace the unit’s panels and hood.
4.6 OVER-TEMPERATURE LIMIT
SWITCH ADJUSTMENTS
There are two Over-Temperature limit switches
that turn off the unit when the outlet water
temperature becomes too hot. The lower overtemperature limit switch is adjustable and should
be adjusted 20
header temperature. The upper overtemperature limit switch is a manual reset device
and is not adjustable. It will shut off the unit if the
water temperature reaches 240°F. DO NOT
attempt to adjust its setpoint.
To adjust the lower over-temperature switch limit
h:
switc
1. Remove the wing nut from the top center of
the shell cap. Lift the cap off the shell.
2. The two over-temperature limit switches are
located at the top of the shell (see Fig. 4.6).
Do not attempt to adjust the upper switch. It
has been factory preset.
0
to 40o F above the operating
Figure 4.6
Over Temperature Limit Switch Location
3. Adjust the lower switch between 20°F to
40°F higher than the maximum header
temperature the unit may see.
4. Replace the shell cap and wing nut.
4-6
MODE OF OPERATION
SECTION 5 - MODE OF OPERATION
5.1 INTRODUCTION
The following paragraphs provide detailed
descriptions of the six different modes of
operation for the KC1000 Boiler. Each unit is
shipped from the factory tested and configured
for the ordered mode of operation. All
temperature related parameters are at factory
defaults and work well in most applications.
However, it may be necessary to change certain
parameters to customize the unit to the system.
A complete listing and descriptions of the
temperature related parameters are included in
Appendix A. Factory defaults are listed in
Appendix E. After reading this section,
parameters can be customized to suit the needs
of the specific application.
5.2 INDOOR/OUTDOOR RESET MODE
This mode of operation is based on outside air
temperatures. As the outside air temperature
decreases, the supply header temperature will
increase and vice versa. For this mode, it is
necessary to install an outside air sensor as well
as select a building reference temperature and a
reset ratio.
5.2.1 RESET RATIO
Reset ratio is an adjustable number from 0.1 to
9.9. Once it is adjusted, the supply header
temperature will increase by that number for
each degree that the outside air temperature
decreases. For instance, if a reset ratio of 1.6 is
used, for each degree that outside air
temperature decreases the supply header
temperature will increase by 1.6 degrees.
5.2.2. BUILDING REFERENCE
TEMPERATURE
This is a temperature from 40°F to 240°F. Once
selected, it is the temperature that the system
references to begin increasing its temperature.
For instance, if a reset ratio of 1.6 is used and
we select a building reference temperature of
70°F, then at an outside temperature of 69°F,
the supply header temperature will increase by
1.6° to 71.6°F.
5.2.3 OUTDOOR AIR TEMPERATURE
SENSOR INSTALLATION
The outdoor air temperature sensor must be
mounted on the North side of the building in an
area where the average outside air temperature
is expected. The sensor must be shielded from
the sun's direct rays, as well as from direct
impingement by the elements. If a cover or
shield is used, it must allow free air circulation.
The sensor may be mounted up to 200 feet from
the unit. Sensor connections are made inside
the Input/Output (I/O) Box on the left side of the
KC1000 Boiler. Connections are made at the
terminals labeled OUTDOOR SENSOR IN and
SENSOR COMMON inside the I/O Box using
shielded 18 to 22 AWG wire. A wiring diagram
is provided on the cover of the I/O Box. Refer to
Section 2, paragraph 2.6.2 for additional wiring
information.
5.2.4 INDOOR/OUTDOOR STARTUP
1. Refer to the indoor/outdoor reset ratio charts
in Appendix D.
2. Choose the chart corresponding to the
desired building reference temperature.
3. Go down the left column of the chart to the
coldest design outdoor air temperature
expected in your area.
NOTE:
A design engineer typically provides design
outdoor air temperature and supply header
temperature data
4. Once the design outdoor air temperature is
chosen, go across the chart to the desired
supply header temperature for the design
temperature chosen in step 3.
5. Next, go up that column to the Reset Ratio
row to find the corresponding reset ratio.
6. Access the Configuration Menu and scroll
through it until the display shows Bldg Ref Temp (Building Reference Temperature).
7. Press the CHANGE key. The display will
begin to flash.
8. Use the ▲ and ▼ arrow keys to select the
desired building reference temperature.
9. Press ENTER to save any changes.
10. Next, scroll through the Configuration Menu
until the display shows Reset Ratio.
5-1
MODE OF OPERATION
MENU OPTION
SETTING
Boiler Mode
Constant Setpoint
Internal Setpt
Select desired setpoint
keys (40°F to 240°F)
11. Press the CHANGE key. The display will
begin to flash.
12. Use the ▲ and ▼ arrow keys to select the
reset ratio determined in step 5.
13. Press ENTER to save the change.
Refer to paragraph 3.3 for detailed instructions
on menu changing.
5.3 CONSTANT SETPOINT MODE
The Constant Setpoint mode is used when a
fixed header temperature is desired. Common
uses of this mode of operation include water
source heat pump loops, and indirect heat
exchangers for potable hot water systems or
processes.
There are no external sensors necessary to
operate in this mode. While it is necessary to set
the desired setpoint temperature, it is not
necessary to change any other temperaturerelated functions. The unit is factory preset with
settings that work well in most applications.
Prior to changing any temperature-related
parameters, other than the setpoint, it is
suggested that an AERCO representative be
contacted. For a complete listing of factory
defaults and descriptions of temperature related
functions, see Appendices A and E.
5.3.1 SETTING THE SETPOINT
The setpoint temperature of the unit is
adjustable from 40°F to 240°F. To set the unit
for operation in the Constant Setpoint Mode, the
following menu settings must be made in the
Configuration Menu:
5.4 REMOTE SETPOINT MODES
The unit’s setpoint can be remotely controlled by
an Energy Management System (EMS) or
Building Automation System (BAS). The Remote
Setpoint can be driven by a current or voltage
signal within the following ranges:
4-20 mA/1-5 Vdc
0-20 mA/0-5 Vdc
The factory default setting for the Remote
Setpoint mode is 4 - 20 mA/1 - 5 Vdc. With this
setting, a 4 to 20 mA/1 to 5 Vdc signal, sent by
an EMS or BAS, is used to change the unit's
setpoint. The 4 mA/1V signal is equal to a 40°F
setpoint while a 20 mA /5V signal is equal to a
240°F setpoint. When a 0 to 20 mA/0 to 5 Vdc
signal is used, 0 mA is equal to a 40°F setpoint.
In addition to the current and voltage signals
described above, the Remote Setpoint mode
can also driven by a RS485 Modbus Network
signal from an EMS or BAS.
The Remote Setpoint modes of operation can be
used to drive single as well as multiple units.
NOTE:
If a voltage, rather than current signal is used to
control the remote setpoint, a DIP switch
adjustment must be made on theCPU Board in
the Control Box. Contact your local AERCO
representative for details.
In order to enable the Remote Setpoint Mode,
the following menu setting must be made in the
Configuration Menu:
MENU OPTION SETTING
Boiler Mode Remote Setpoint
Refer to paragraph 3.3 for detailed instructions
on changing menu options.
5-2
using ▲ and ▼ arrow
Remote Signal 4-20mA/1-5V,
0-20mA/0-5V, or
Network
Refer to paragraph 3.3 for detailed instructions
on changing menu options.
MODE OF OPERATION
If the Network setting is selected for RS485
Modbus operation, a valid Comm Address must
be entered in the Setup Menu. Refer to Modbus
Communication Manual GF-114 for additional
information.
While it is possible to change the settings of
temperature related functions, the unit is factory
preset with settings that work well in most
applications. It is suggested that an AERCO
representative be contacted, prior to changing
any temperature related function settings. For
descriptions of temperature-related functions
and their factory defaults, refer to Appendices A
and E.
5.4.1 REMOTE SETPOINT FIELD WIRING
The only wiring connections necessary for the
Remote Setpoint mode are connection of the
remote signal leads from the source to the unit’s
I/O Box. The I/O Box is located on the front
panel of the Benchmark Boiler. For either a 420mA/0-5V or a 0-20mA/0-5V setting, the
connections are made at the ANALOG IN
terminals in the I/O Box. For a Network setting,
the connections are made at the RS-485 COMM
terminals in the I/O Box. The signal must be
floating, (ungrounded) at the I/O Box and the
wire used must be a two wire shielded pair from
18 to 22 AWG. Polarity must be observed. The
source end of the shield must be connected at
the source. When driving multiple units, each
unit’s wiring must conform to the above.
5.4.2 REMOTE SETPOINT STARTUP
Since this mode of operation is factory preset
and the setpoint is being externally controlled,
no startup instructions are necessary. In this
mode, the REMOTE LED will light when the
external signal is present.
To operate the unit in the Manual mode, press
the AUTO/MAN switch. The REMOTE LED will
go off and the MANUAL LED will light.
To change back to the Remote Setpoint mode,
simply press the AUTO/MAN switch. The
REMOTE LED will again light and the MANUAL
LED will go off.
5.5 DIRECT DRIVE MODES
The unit’s air/fuel valve position can be changed
by a remote signal which is typically sent from
an Energy Management System (EMS) or from
a Building Automation System (BAS). The Direct
Drive mode can be driven by a current or
voltage signal within the following ranges:
4-20 mA/1-5 Vdc
0-20 mA/0-5 Vdc
The factory default setting for the Direct Drive
mode is 4-20 mA/1-5 Vdc. With this setting, a 4
to 20 mA signal, sent by an EMS or BAS is used
to change the unit’s valve position from 0% to
100%. A 4 mA/1V signal is equal to a 0% valve
position, while a 20 mA /5V signal is equal to a
100% valve position. When a 0-20 mA/0-5 Vdc
signal is used, zero is equal to a 0% valve
position.
In addition to the current and voltage signals
described above, the Direct Drive mode can also
driven by a RS485 Modbus Network signal from
an EMS or BAS.
When in a Direct Drive mode, the unit is a slave
to the EMS or BAS and does not have a role in
temperature control. Direct Drive can be used to
drive single, or multiple units.
NOTE:
If a voltage, rather than current signal is used to
control the valve position, a DIP switch
adjustment must be made on thePMC Board in
the Control Box. Contact your local AERCO
representative for details.
To enable the Direct Drive Mode, the following
menu setting must be made in the Configuration
Menu:
MENU OPTION SETTING
Boiler Mode Direct Drive
Remote Signal 4-20mA/1-5V,
0-20mA/0-5V, or
Network
Refer to paragraph 3.3 for instructions on
changing menu options.
5-3
MODE OF OPERATION
MENU OPTION
SETTING
If the Network setting is selected for RS485
Modbus operation, a valid Comm Address must
be entered in the Setup Menu. Refer to Modbus
Communication Manual GF-114 for additional
information.
5.5.1 DIRECT DRIVE FIELD WIRING
The only wiring connections necessary for Direct
Drive mode are connection of the remote signal
leads from the source to the unit’s I/O Box. For
either a 4-20mA/0-5V or a 0-20mA/0-5V setting,
the connections are made at the ANALOG IN
terminals in the I/O Box. For a Network setting,
the connections are made at the RS-485 COMM
terminals in the I/O Box. The signal must be
floating, (ungrounded) at the I/O Box and the
wire used must be a two wire shielded pair from
18 to 22 AWG. Polarity must be observed. The
source end of the shield must be connected at
the source. When driving multiple units, each
unit’s wiring must conform to the above.
5.5.2 DIRECT DRIVE STARTUP
Since this mode of operation is factory preset
and the valve position is being externally
controlled, no startup instructions are necessary.
In this mode, the REMOTE LED will light when
the signal is present.
For BMS programming, operation and Header
Sensor installation details, see GF-108M (BMS
Model 168) and GF-124 (BMS II Model 5R5-
384), BMS Operations Guides. For operation via
an RS485 Modbus network, refer to Modbus
Communication Manual GF-114.
To enable the BMS Mode, the following menu
settings must be made in the Configuration
Menu:
Boiler Mode Direct Drive
Remote Signal
Refer to paragraph 3.3 for instructions on
changing menu options.
BMS (PWM Input)
or
Network (RS485)
5.6.1 BMS EXTERNAL FIELD WIRING
Wiring connections for BMS control using PWM
signaling are made between connector JP2 on
the BMS panel (boilers 1 through 8), and the
B.M.S. (PWM) IN terminals in the I/O Box on the
front of the Benchmark Boilers. Refer to the
wiring diagram provided on the cover of the I/O
Box.
To operate the unit in manual mode, press the
AUTO/MAN switch. The REMOTE LED will go
off and the MANUAL LED will light.
To change back to the Direct Drive mode, simply
press the AUTO/MAN switch. The REMOTE
LED will again light and the MANUAL LED will
go off.
5.6 BOILER MANAGEMENT SYSTEM
(BMS) MODE
NOTE
BMS Model 168 can utilize either pulse
width modulation (PWM) or RS485
Modbus signaling to the Boiler. BMS II
Model 5R5-384 can utilize only RS485
signaling to the Boiler.
The BMS mode of operation is used in
conjunction with an AERCO Boiler Management
System. The BMS mode is used when it is
desired to operate multiple units in the most
efficient manner possible. For this mode of
operation, a BMS Header Sensor must be
installed between 2 and 10 feet downstream of
the LAST boiler in the boiler plant’s supply water
header. The BMS can control up to 40 boilers; 8
via pulse width modulation (PWM) and up to 32
via Modbus (RS485) network communication.
Wiring connections for RS485 Modbus control
are made between connector JP11 on the BMS
(boilers 9 through 40) and the RS485 COMM
terminals in the I/O Box on the front of the unit.
Wire the units using shielded twisted pair wire
between 18 and 22 AWG. Observe the proper
polarity for the B.M.S. (PWM) IN and/or RS485
COMM wiring connections. Shields should be
terminated only at the BMS and the boiler end
must be left floating. Each unit’s wiring must
conform to the above.
5.6.2 BMS SETUP AND STARTUP
This mode of operation is factory preset and the
AERCO BMS controls the air/fuel valve position.
There are no setup instructions for each
individual unit.
To operate the unit in manual mode, press the
AUTO/MAN switch. The REMOTE LED will go
off and the MANUAL LED will light
To change back to the BMS mode, simply press
the AUTO/MAN switch. The REMOTE LED will
again light and the MANUAL LED will go off.
5-4
MODE OF OPERATION
5.7 COMBINATION CONTROL SYSTEM
(CCS)
NOTE
Only BMS Model 168 can be utilized for
the Combination Mode, not the BMS II
(Model 5R5-384).
A Combination Control System (CCS) is one
that uses multiple boilers to cover both spaceheating and domestic hot water needs. An
AERCO Boiler Management System (BMS)
Model 168 and a Combination Control Panel
(CCP) are necessary to configure this system.
Typically, an adequate number of boilers are
installed to cover the space-heating load on the
design day, however one or more units are used
for the domestic hot water load.
The theory behind this type of system is that the
maximum space-heating load and the maximum
domestic hot water load do not occur simultaneously. Therefore, boilers used for the domestic
hot water are capable of switching between
constant setpoint and BMS modes of operation.
These boilers are the combination units and are
referred to as the combo boilers. The combo
boilers heat water to a constant setpoint
temperature. That water is then circulated
through a heat exchanger in a domestic hot
water storage tank.
When the space-heating load is such that all the
space-heating boilers are at 100% valve
position, the BMS will then ask the Combination
Control Panel for the domestic boilers to
become space-heating boilers. Provided the
domestic hot water load is satisfied, the combo
(hot water) boilers will then become spaceheating boilers. If the domestic hot water load is
not satisfied, the combo boiler(s) remain on the
domestic hot water load. If the combo boilers
switch over to space heating, but there is a call
for domestic hot water, the CCP switches the
combo units back to the domestic load.
When the combo units are satisfying the
domestic load they are in constant setpoint
mode of operation. When the combo units
switch over to space heating, their mode of
operation changes to the BMS mode. For more
information concerning the operation of the
Combination Control Panel see the AERCO
CCP-1 literature.
5.7.1 COMBINATION CONTROL SYSTEM
FIELD WIRING
Wiring for this system is between the BMS
Model 168 panel, the CCP and the B.M.S.
(PWM) IN terminals in the I/O Box. Wire the
units using a shielded twisted pair of 18 to 22
AWG wire. When wiring multiple units, each
unit’s wiring must conform to the above. For a
complete CCP system-wiring diagram see the
AERCO CCP-1 literature.
5.7.2 COMBINATION CONTROL SYSTEM
SETUP AND STARTUP
Setup for the Combination Mode requires entries
to be made in the Configuration Menu for boiler
mode, remote signal type and setpoint. The
setpoint is adjustable from 40°F to 240°F.
Enter the following settings in the Configuration
Menu:
MENU OPTION SETTING
Boiler Mode Combination
Remote Signal BMS (PWM Input)
Internal Setpt 40°F to 240°F
Refer to paragraph 3.3 for instructions on
changing menu options.
While it is possible to change other temperaturerelated functions for combination mode, these
functions are preset to their factory default
values. These default settings work well in most
applications. It is suggested that AERCO be
contacted prior to changing settings other than
the unit’s setpoint. For a complete listing of
temperature related function defaults, see
Appendix E.
To set the unit to the manual mode, press the
AUTO/MAN switch. The MANUAL LED will
light.
To set the unit back to the auto mode, press the
AUTO/MAN switch. The MANUAL LED will go
off and the REMOTE LED will light.
When the boiler is switched to BMS mode, the
AERCO BMS controls the valve position. There
are no setup requirements to the boiler(s) in this
mode.
5-5
SECTION 6-SAFETY DEVICE TESTING PROCEDURES
1/4" NPT PLUG
(INSTALL
MANOMETER
HERE)
SSOV
6.1 TESTING OF SAFETY DEVICES
Periodic testing of all controls and safety devices
is required to insure that they are operating as
designed. Precautions must be taken while tests
are being performed to protect against bodily
injury and property damage.
Systematic and thorough testing of the operating
and safety controls should be performed on a
scheduled basis, or whenever a control compo-
nent has been serviced or replaced. All testing
must conform to local jurisdictions or codes such
as ASME CSD-1.
NOTE:
MANUAL and AUTO modes are required to
perform the following tests. For a complete
explanation of these modes, see Section 3.
NOTE:
It will be necessary to remove the sheet
metal covers and cap from the unit to
perform the following tests.
WARNING!
ELECTRICAL VOLTAGES IN THIS
SYSTEM INCLUDE 120 AND 24 VOLTS
AC. POWER MUST BE REMOVED PRIOR
TO PERFORMING WIRE REMOVAL OR
OTHER TESTING PROCEDURES THAT
CAN RESULT IN ELECTRICAL SHOCK.
6.2 LOW GAS PRESSURE FAULT TEST
1. Shut off the gas supply to the unit.
2. Install a 0-16” W.C. manometer in the gas
pipe assembly below the low gas pressure
switch. (See Fig. 6.1)
3. Open the gas supply to the unit and depress
the CLEAR button to clear any fault
messages..
4. Place the unit in Manual Mode and fire the
unit at a valve position between 25% and
30%.
5. Slowly close the manual gas supply valve
while monitoring the gas pressure. The unit
should fault and shutdown on LOW GAS PRESSURE when the manometer indicates
approximately 6.5” W.C.
SAFETY DEVICE TESTING
6. Open the gas supply to the unit and press
the CLEAR button on the Control Box.
7. The unit should restart.
Figure 6.1
1/8” Pipe Plug Position for Manometer
Installation
NOTE:
After faulting the unit, the fault message will
be displayed and the fault indicator light will
flash until the CLEAR button is pressed.
6.3 HIGH GAS PRESSURE TEST
1. Start the unit in manual mode and fire
between 25% and 30%.
2. Remove either wire # 150 or wire #151 from
the high gas pressure switch. See Fig. 6.2.
3. The unit should shut down on a HIGH GAS PRESSURE FAULT.
4. Reconnect the wire previously removed from
the high gas pressure switch and depress
the CLEAR button.
5. The unit should restart.
6-1
HIGH GAS
PRESSURE
SWITCH
209
137
HARNESS
136
FROM SHELL
NC
NC
CNO
C
120
180
150
DIAL
TEMPERATURE LIMIT SWITCH
SETTING
SAFETY DEVICE TESTING
Figure 6.2
High Gas Pressure Switch
6.4 LOW WATER LEVEL FAULT TEST
1. Set the ON/OFF switch in the OFF position.
2. Close shut-off valves in the supply and
return piping to the unit.
3. Open the drain valve on the unit.
4. Allow air flow into the unit by either opening
the relief valve or by removing the 1/4” plug
in the top of the unit.
5. The LOW WATER LEVEL message will be
displayed and the FAULT LED will flash
after the water level has gone below the
level of the probe.
6. Set the ON/OFF switch to ON. The READY
light should remain off and the unit should
not start. If the unit does start, shut the unit
off immediately and refer fault to qualified
service personnel.
7. Close the drain and pressure relief valve or
reinstall the plug in the top of the unit if
removed.
8. Open the water shut-off valve in the return
piping to the unit to fill the shell.
9. Open the water shut-off valve in the supply
piping to the unit.
10. After the shell is full, press the LOW WATER LEVEL RESET button to reset the
low water cutoff. Press the CLEAR button
to reset the FAULT LED and clear the error
message.
11. Set the ON/OFF switch to the ON position.
The unit is now ready for operation.
6.5 WATER TEMPERATURE FAULT
TEST
1. In the normal operating mode, allow the unit
to stabilize at its setpoint.
2. Lower the adjustable temperature limit
switch setting to match the outlet water
temperature. (See Fig. 6.3).
Figure 6.3
Temperature Limit Switch Setting
3. Once the switch setting is approximately at
the actual water temperature, the unit should
shutdown. The FAULT LED should be
flashing and the message HIGH WATER TEMP SWITCH OPEN should be displayed.
The unit should not start.
4. Reset the temperature limit switch setting to
its prior setting.
5. The unit should start once the adjustable
temperature limit switch setting is above the
actual outlet water temperature.
6-2
SAFETY DEVICE TESTING
6.6 INTERLOCK TESTS
The unit is equipped with two interlock circuits
called the Remote Interlock and Delayed Interlock. Terminal connections for these circuits are
located in the I/O Box and are labeled REMOTE
INTL’K IN and DELAYED INTL’K IN. These
circuits can shut down the unit in the event that
an interlock is opened. These interlocks are
shipped from the factory jumped (closed).
However, each of these interlocks may be
utilized in the field as a remote stop and start, an
emergency cut-off, or to prove that a device
such as a pump gas booster, or louver is
operational.
6.6.1 REMOTE INTERLOCK
1. Remove the cover from the I/O Box and
locate the REMOTE INTL’K IN terminals.
2. Start the unit in the manual mode and fire at
a 25% to 30% valve position.
3. If there is a jumper across the REMOTE
INTL’K IN terminals, remove one side of the
jumper. If the interlock is being controlled by
an external device, either open the interlock
via the external device or disconnect one of
the wires leading to the external device.
4. The unit should shut down and display
INTERLOCK OPEN.
5. Once the interlock connection is reconnected, the INTERLOCK OPEN message
should automatically clear and the unit
should resume running.
6.6.2 DELAYED INTERLOCK
1. Remove the cover from the I/O Box and
locate the DELAYED INTL’K IN terminals.
2. Start the unit in the manual mode and fire at
a 25% to 30% valve position.
3. If there is a jumper across the DELAYED
INTL’K IN terminals, remove one side of the
jumper. If the interlock is connected to a
proving switch of an external device,
disconnect one of the wires leading to the
proving switch.
4. The unit should shut down and display
DELAYED INTERLOCK OPEN. The
FAULT LED should be flashing.
5. Once the interlock connection is reconnected, depress the CLEAR button. The unit
should start.
6.7 FLAME FAULT TEST
1. Place the ON/OFF switch in the OFF
position.
2. Place the unit in the Manual Mode and set
the valve position between 25% and 30%.
3. Close the manual leak detection valve
located between the safety shut-off valve
and the differential regulator (see Fig. 6.4).
4. Start the unit.
5. The unit should shut down after reaching the
Ignition cycle and display FLAME LOSS
DURING IGN.
6. Open the valve previously closed in step 3
and depress the CLEAR button.
7. Restart the unit and allow it to prove flame.
8. Once flame is proven, close the manual leak
detection valve located between the safety
shut-off valve and the differential regulator.
9. The unit should shut down and execute an
IGNITION RETRY cycle by performing the
following steps:
(a) The unit will execute a shutdown purge
cycle for a period of 15 seconds and
display WAIT FAULT PURGE.
(b) The unit will execute a 30 second re-
ignition delay and display WAIT RETRY PAUSE.
(c) The unit will then execute a standard
ignition sequence and display WAIT IGNITION RETRY.
10. Since the manual gas shutoff valve is still
closed, the unit will shut down and display
FLAME LOSS DURING IGNITION following
the IGNITION RETRY cycle.
11. Open the valve previously closed in step 8
and depress the CLEAR button. The unit
should restart and fire.
6-3
SAFETY DEVICE TESTING
154
155
AIR/FUEL VALVE
BLOWER PROOF
SWITCH
TO FRAME
HARNESS
Figure 6.4
Manual Leak Detection Valve
6.8 AIR FLOW FAULT TEST
1. Start the unit in manual mode and set the
valve position between 25% and 30%.
2. Once the unit has proved flame, remove
either wire #154 or #155 from the blower
proof switch (see Fig. 6.5) located on the
air/fuel valve.
3. The unit should shut down and execute an
IGNITION RETRY cycle by performing the
following steps:
(a) The unit will execute a 30 second re-
ignition delay and display WAIT RETRY PAUSE.
(b) The unit will then execute a standard
ignition sequence and display WAIT IGNITION RETRY.
4. The unit should perform an IGNITION RETRY cycle and then shut down. The unit
will display AIRFLOW FAULT DURING PURGE.
5. Replace the wire previously removed from
the blower-proof switch and depress the
CLEAR button. The unit should restart.
WARNING!
ELECTRICAL VOLTAGES IN THIS
SYSTEM INCLUDE 120 AND 24 VOLTS
AC. POWER MUST BE REMOVED PRIOR
TO PERFORMING WIRE REMOVAL OR
OTHER TESTING PROCEDURES THAT
CAN RESULT IN ELECTRICAL SHOCK.
Blower Proof Switch Location and Wiring
6.9 SSOV PROOF OF CLOSURE SWITCH
1. Set the unit’s ON/OFF switch to the OFF
position. Place the unit in manual mode and
set the valve position between 25% and
30%.
2. Remove the Safety Shut-Off Valve (SSOV)
cover to access the terminal connections.
See Fig. 6.6. For units with IRI gas trains,
access the terminals of the downstream
SSOV (see drawing SD-A-584 in Appendix
F).
3. Remove either wire #149 or #148 from the
SSOV.
4. The unit should fault and display SSOV SWITCH OPEN.
5. Replace the wire previously removed and
depress the CLEAR button.
6. Start the unit.
7. Remove the wire again when the unit
reaches the purge cycle.
8. The unit should shut down and display
SSOV FAULT DURING PURGE.
9. Replace the wire on the SSOV and depress
the CLEAR button. The unit should restart.
Figure 6.5
6-4
SSOV
ACTUATOR
COVER
SSOV
COVER
SCREW
VALVE
COVER
IGNITION
POSITION
SWITCH
PURGE
POSITION
SWITCH
169
170
172
171
STEPPER
MOTOR
DIAL
BLOWER
BURNER
Figure 6.6
SSOV Actuator Cover Screw Location
6.10 PURGE SWITCH OPEN DURING
PURGE
1. Set the unit’s ON/OFF switch to the OFF
position. Place the unit in manual mode and
set the valve position between 25% and
30%.
2. Remove the air/fuel valve cover by rotating
the cover counterclockwise to unlock it and
then pulling it towards you. See Figure 6.7.
3. Remove one of the two wires from the purge
switch (Figuire 6.8) and start the unit.
4. The unit should begin to start, then shut
down and display PRG SWITCH OPEN DURING PURGE.
5. Replace the wire on the purge switch and
depress the CLEAR button. The unit should
restart.
SAFETY DEVICE TESTING
Figure 6.7
Air/Fuel Valve Cover Location
Figure 6.9
Air/Fuel Valve Purge and Ignition Switch
Locations
6-5
SAFETY DEVICE TESTING
6.11 IGNITION SWITCH OPEN DURING
IGNITION
1. Set the unit’s ON/OFF switch to the OFF
position. Place the unit in manual mode and
set the valve position between 25% and
30%.
2. Remove the air/fuel valve cover (Fig. 6.7) by
rotating the cover counterclockwise to
unlock it then pulling it towards you.
3. Remove one of the two wires from the
ignition switch (Fig. 6.8) and start the unit.
4. The unit should begin to start then shut
down and display IGN SWITCH OPEN DURING IGNITION.
5. Replace the wire on the ignition switch and
depress the CLEAR button. The unit should
restart.
6.12 SAFETY PRESSURE RELIEF
VALVE TEST
Test the safety Pressure Relief Valve in accordance with ASME Boiler and Pressure Vessel
Code, Section VI.
6-6
SECTION 7 - MAINTENANCE
Sect Item
Mos.
Mos.
Mos.
Time
(GP-122435-S)
(GM-123428)
Adj.
Safety Devices
sary
7.1 MAINTENANCE SCHEDULE
The unit requires regular routine maintenance to
keep up efficiency and reliability. For best operation and life of the unit, the following routine
maintenance procedures should be carried out
in the time periods specified in Table 7-1.
Appendix J contains recommended spare parts
lists for maintenance of the KC1000 Boiler.
Table 7-1. Maintenance Schedule
7.2 Spark
Ignitor
7.3 Flame Detector
7.4 Combustion
7.5 Testing of
7.6 *Manifold &
Tubes
7.7 Water Side
Inspection
7.8 Condensate
Drain
* Recommended only when unit will be run in an
extreme condensing mode for prolonged periods
of time.
TO AVOID PERSONAL INJURY, BEFORE
SERVICING:
(A) DISCONNECT THE AC SUPPLY BY
TURNING OFF THE SERVICE SWITCH
AND AC SUPPLY CIRCUIT BREAKER
(B) SHUT OFF THE GAS SUPPLY AT THE
MANUAL SHUT-OFF VALVE PROVIDED
WITH THE UNIT
(C) ALLOW THE UNIT TO COOL TO A
SAFE TEMPERATURE TO PREVENT
BURNING OR SCALDING
7.2 SPARK IGNITOR
The spark ignitor assembly (part no.
GP-122435-S) is located in the body of the
burner (see Figure 7.1). The ignitor may be
HOT. Care should be exercised. It is easier to
remove the ignitor from the unit after the unit has
cooled to room temperature.
6
Inspect Replace
Inspect Replace
Check Check
Test
Inspect
Inspect
& Clean
WARNING!
12
24
Labor
15
mins.
15
mins.
1 hr.
20
mins.
Inspect
& clean
neces-
Inspect 2 hr.
4 hrs.
if
30
mins.
MAINTENANCE
To inspect/replace the Ignitor :
1. Set the ON/OFF switch on the control panel
to the OFF position and disconnect AC
power from the unit.
2. For access to the spark ignitor
(GP-122435-S), remove the unit’s right side
panel. Access can also be gained by
removing the rear panels and condensate
drainage system
3. Disconnect the ignitor cable from the ignitor
extension. Remove the silicone ignitor plug
from the burner shell by simultaneously
twisting and pulling downward.
4. Insert the ignitor removal tool into the burner
shell, where the ignitor plug was removed.
Screw the outer barrel of the tool into the
burner shell. Push the inner barrel up and fit
the hexagonal end of the tool over the
ignitor. Unscrew the ignitor from the burner
head and then the tool from the burner shell.
5. The ignitor is gapped at 1/8-inch. If there is a
substantial erosion of the spark gap or
ground electrode, the ignitor should be replaced. If carbon build-up is present, clean
the ignitor using fine emery cloth. Repeated
carbon build-up on the ignitor is an
indication that a check of the combustion
settings is required (see Section 4 for
Combustion Calibration).
6. Prior to reinstalling the ignitor, an anti-seize
compound must
threads.
The ignitor must be removed and installed using
the ignitor removal tool provided with the unit(s).
Damage to the burner due to using a socket for
removal and installation of the ignitor is not
covered under warranty.
7. Reinstall the ignitor assembly using the
ignitor removal tool. Do not over tighten the
ignitor. A slight snugging up is sufficient.
8. Reinstall the ignitor plug into the burner shell
by simultaneously twisting and pushing it
into the shell.
9. Reattach the ignitor cable to the extension
and verify that it “clicks” into place.
be applied to the ignitor
CAUTION!
7-1
MAINTENANCE
SPARK IGNITOR
ASSEMBLY
BURNER
SHELL
FLAME
DETECTOR
SILICONE
PLUG
GP-122537
Exhaust Manifold to
Gasket
GP-18900
Manifold to Tubesheet
Gasket
GP-18899
Burner Gasket
GP-122551
Burner Release Gasket
*GP-161151
Combustion Chamber Liner
10. Replace the rear cover panels or right side
panel. Replace the condensate cup to drain
tubing.
Figure 7.1
Spark Ignitor and Flame Detector Locations
7.3 FLAME DETECTOR
The flame detector assembly (part no.
GM 123428) is located in the body of the burner
(see Figure 7.1). The flame detector may be
HOT. Allow the unit to cool sufficiently before
removing the flame detector.
To inspect or replace the flame detector (part
no. GM 123428):
1. Set the ON/OFF switch on the control panel
to the OFF position and disconnect AC
power from the unit.
2. Remove the left side panel from the unit.
3. Disconnect the flame detector lead wire.
Unscrew the flame detector and remove it
from its guide tube. The detector is flexible
and may be bent to ease its removal.
4. Inspect the detector thoroughly. If eroded,
the detector should be replaced. Otherwise
clean the detector with a fine emery cloth.
5. Reinstall the flame detector hand-tight only.
6. Reconnect the flame detector lead wire.
7. Replace the rear cover panels or left side
panel and reconnect the rear covers to the
unit. Replace the condensate cup to drain
tubing.
7.4 COMBUSTION CALIBRATION
Combustion settings must be checked at the
intervals shown in Table 7-1 as part of the
maintenance requirements. Refer to Section 4
for the combustion calibration instructions.
7.5 SAFETY DEVICE TESTING
Systematic and thorough tests of the operating
and safety devices should be performed to
ensure that they are operating as designed.
Certain code requirements, such as ASME
CSD-1, require that these tests be performed on
a scheduled basis. Test schedules must
conform to local jurisdictions. The results of the
tests should be recorded in a log book. See
Section 6-Safety Device Testing Procedures.
7.6 MANIFOLD AND EXHAUST TUBES
The presence of even trace amounts of
chlorides and/or sulfur, in the combustion air and
fuel sources, can lead to the formation of
deposits on the inside of the exchanger tubes,
the exhaust manifold, and/or the condensate
cup. The degree of deposition is influenced by
the extent of the condensing operation and the
chloride and sulfur levels that vary significantly
from application to application.
The following parts will be necessary for
reassembly after inspection:
Combustion Chamber
*Change only if damage occurs during the
inspection.
To remove the manifold for inspection:
1. Disconnect AC power and turn off the gas
supply to the unit.
2. Remove the sheet metal covers from the
unit.
3. Disconnect the plastic tubing from the
condensate cup to drain and remove the
rear covers.
4. Remove the condensate cup from under the
unit and the condensate drainage tubing
from the manifold.
7-2
MAINTENANCE
TO FRAME
HARNESS
BLOWER PROOF
SWITCH
AIR/FUEL VALVE
5. Remove the flame detector and ignition
cable wires from the flame detector and
ignitor contactor. Remove the ignitor and
flame detector per paragraphs 7.2, and 7.3.
6. Remove the grounding terminal from the
burner by loosening the upper screw and
sliding the connector from the grounding
rod. (See Figure 7.2).
Figure 7.2
Grounding Terminal Location
7. Using a 7/16” socket or open end wrench
remove the four 1/4”-20 nuts on the gas inlet
pipe flange at the burner (See Figure 7.3).
8. Using two 9/16” wrenches remove the 3/8"16 hex nuts and bolts on the gas inlet pipe
flange at the air/fuel valve (See Figure 7.3).
9. Loosen the hose clamp nearest the air/fuel
valve outlet on the air/fuel valve to burner
adapter (See Figure 7.3).
10. Using a 1/2” socket wrench remove six
5/16-18 hex nuts supporting the burner (See
Fig. 7.3).
11. Lower the burner while sliding the air hose
off the air/fuel valve. Remove the burner
through the rear of the unit.
12. Disconnect the exhaust temperature sensor
by unscrewing it from the exhaust manifold
(See Fig. 7.4).
Figure 7.4
Exhaust Sensor Connector Location
13. Disconnect the air/fuel valve wire harness,
the 12 pin connector, from the control panel.
14. Disconnect wires #24 and #17 from the
blower proof switch (See Figure 7.5).
Figure 7.3
Burner Disassembly Diagram
Blower Proof Switch Wire Locations
15. Loosen the hose clamp on the air/fuel valve
inlet and slide the clamp back towards the
blower (See Figure 7.6).
Figure 7.5
7-3
MAINTENANCE
Figure 7.6
Air/Fuel Valve Inlet Hose Clamp
16. Using an 11/16” wrench, loosen the
compression fittings on the feedback tube
between the air/fuel valve and the
differential pressure regulator. Remove the
feedback tube (See Figure 7.7).
17. Using two 9/16” wrenches remove the two
3/8-16 hex nuts and bolts holding the air/fuel
valve to the differential pressure regulator
(See Figure 7.7).
18. Remove the air/fuel valve taking care not to
damage the flange “O”- ring.
19. Remove the flue venting from the exhaust
manifold.
20. To prevent damage to and for easier
handling of the exhaust manifold it will be
necessary to remove the exhaust manifold
insulation. Using a 7/16” wrench or socket,
remove the 3 bolts and fender washers
securing the insulation to the exhaust
manifold.
21. Loosen the three 1-1/16” nuts that hold the
manifold. Remove the two side nuts. DO NOT REMOVE THE FRONT NUT (See
Figure 7.8).
22. Carefully pull the manifold down and back,
removing it through the back of the unit.
23. Inspect the manifold and exhaust tubes for
debris. Clean out any debris as necessary.
24. Inspect the combustion chamber and the
combustion chamber liner. Replace the liner
if any signs of cracking or warpage are
evident.
NOTE:
The combustion chamber liner should be
installed prior to reinstalling the exhaust
manifold
Figure 7.7
Feedback Tube and Air/Fuel Valve to
Differential Regulator Bolts
7-4
Figure 7.8
Manifold Nut and Bolt Locations
25. Replace the gasket between the manifold
and the combustion chamber (P/N
GP-122537). The use of Permatex or a
similar gasket adhesive is recommended.
Replace the gasket between the manifold
and tubesheet (P/N GP-18900). Do not use
any gasket adhesive; this gasket has an
adhesive backing
26. Beginning with the manifold, reinstall all the
components in the reverse order that they
were removed.
MAINTENANCE
RELIEF VALVE
DRAIN VALVE
REDUCING
1/4" PLUG
HOT WATER
HOT WATER
SUPPLY (OUTLET)
RETURN (INLET)
BUSHING
REDUCING
BUSHING
7.6.1 PROPANE UNITS
For propane units it will be necessary to remove
the air mix assembly in addition to the
components outlined in Section 7.6. Proceed as
follows:
1. Follow steps 1 through 5 in paragraph 7.6.
2. Using a wrench, loosen the two
compression fittings holding the 1/4”
feedback tube between the burner and air
regulator and remove the feedback tube
(See Figure 7.9).
3. Using a 1-1/16” wrench or an adjustable
wrench loosen and remove the 12” flexible
gas hose.
4. Go back to paragraph 7.6 and continue at
Step # 6.
7.7 HEAT EXCHANGER WATER SIDE
INSPECTION
Per CSD-1, the water side of the heat exchanger
requires an inspection. To inspect the heat exchanger, proceed as follows:
1. Shut off AC power to the unit.
2. Close the supply and return valves to the
unit (Fig 7.10).
3. Open the drain valve and allow the unit to
fully drain. The 1/4 inch plug in the top of
the shell may be removed to aid in drainage
or the relief valve may be opened (Fig 7.10).
4. Remove the 2 ½ inch plug located in the
shell at the rear of the unit (Fig. 7.11).
5. Remove the relief valve, drain valve
(Fig. 7.10) and any reducing bushings.
6. Perform the inspection and reassemble the
unit once the inspection is completed.
7. Open the supply and return valves and
reconnect AC power to the unit.
Figure 7.9
Propane Unit Component Location
NOTE:
Older propane units have a 1/8” feedback
tube and 1/8” OD tube compression fittings.
Figure 7.10
Heat Exchanger Supply and Return
Locations
7-5
MAINTENANCE
2-1/2" PLUG
Figure 7.11
Heat Exchanger 2 ½ Inch Inspection Plug
Location
7.8 CONDENSATE DRAIN ASSEMBLY
KC Boilers contain a condensate drain cup
(Figure 2.6) which should be inspected and
cleaned annually to ensure proper operation.
To inspect and clean the assembly, proceed as
follows:
1. Remove the left side panel and left rear
cover to provide access to the condensate
drain components (see Figure 2.6).
2. Disconnect the drain hose attached to the
exhaust manifold.
3. Disconnect the plastic tubing from the
condensate cup drain tube to the drain
4. Remove the condensate cup from under the
unit. Thoroughly clean the cup and inspect
drain tube for blockage.
5. Check to ensure that the condensate drain
opening in the exhaust manifold is not
blocked.
6. Flush out the drain hose and plastic tubing.
7. After the above items have been cleaned
and inspected, reassemble the condensate
drain components by reversing the previous
steps.
7-6
Section 8 - TROUBLESHOOTING GUIDE
8.1 INTRODUCTION
This troubleshooting guide is intended to aid
service/maintenance personnel in isolating the
cause of a fault in a KC1000 Boiler. The troubleshooting procedures contained in this section
are presented in tabular form in Table 8-1 on the
following pages This table is comprised of three
columns labeled: Fault Indication, Probable
Cause and Corrective Action. The numbered
items in the Probable Cause and Corrective
Action columns correspond to each other. For
example, Probable Cause No. 1 corresponds to
Corrective Action No. 1, etc.
NOTE:
The front panel of the C-More Control Box
contains an RS232 port which can be interfaced
to a laptop computer or other suitable device.
This RS232 communication feature permits
service personnel to view menu items and data
logs which can be useful in isolating faults. Refer
to Section 9 of this manual for detailed RS232
communication set-up and procedures.
TROUBLESHOOTING
When a fault occurs in the KC1000 Boiler,
proceed as follows to isolate and correct the
fault:
1. Observe the fault messages displayed in the
Control Box display.
2. Refer to the Fault Indication column in the
following troubleshooting table and locate
the Fault that best describes the existing
conditions.
3. Proceed to the Probable Cause column and
start with the first item (1) listed for the Fault
Indication.
4. Perform the checks and procedures listed in
the Corrective Action column for the first
Probable Cause candidate.
5. Continue checking each additional Probable
Cause for the existing fault until the fault is
corrected.
6. If the fault cannot be corrected using the
information provided in the Troubleshooting
Tables, contact your local AERCO Representative.
8-1
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
resistance reading is greater than zero ohms, replace the switch.
service personnel.
combustion calibration.
AIRFLOW FAULT
DURING IGNITION
AIRFLOW FAULT
DURING PURGE
TABLE 8-1. BOILER TROUBLESHOOTING
1. Blower stopped running due to thermal
or current overload
2. Blocked Blower inlet or inlet ductwork
3. Blocked airflow switch
4. Defective airflow switch
1. Blower not running or running too slow
2. Defective Air Flow Switch
3. Blocked Air flow Switch
4. Blocked Blower inlet or inlet ductwork.
5. No voltage to switch from control box.
1. Check combustion blower for signs of excessive heat or high
current drain that may trip thermal or current overload devices.
2. Inspect the inlet to the combustion blower including any
ductwork leading up to the combustion blower for signs of
blockage.
3. Remove the airflow switch and inspect for signs of blockage,
clean or replace as necessary.
4. Measure the airflow switch for continuity with the combustion
blower running. If there is an erratic resistance reading or the
1. Start the unit. If the blower does not run check the blower solid
state relay for input and output voltage. If the relay is okay,
check the blower.
2. Start the unit. If the blower runs, check the airflow switch for
continuity. Replace the switch if there is no continuity.
3. Remove the air flow switch and inspect for signs of blockage,
clean or replace as necessary.
4. Inspect the inlet to the combustion blower including any
ductwork leading up to the combustion blower for signs of
blockage.
5. Measure for 24 VAC during start sequence from each side of the
switch to ground. If 24VAC is not present refer to qualified
AIRFLOW FAULT
DURING RUN
8-2
1. Blower stopped running due to thermal
or current overload
2. Blocked Blower inlet or inlet ductwork
3. Blocked airflow switch
4. Defective airflow switch
5. Combustion oscillations
1. Check combustion blower for signs of excessive heat or high
current draw that may trip thermal or current overload devices.
2. Inspect the inlet to the combustion blower including any
ductwork leading up to the combustion blower for signs of
blockage.
3. Remove the airflow switch and inspect for signs of blockage,
clean or replace as necessary.
4. Measure the airflow switch for continuity with the combustion
blower running. If there is an erratic resistance reading or the
resistance reading is greater than zero ohms, replace the switch.
5. Run unit to full fire. If the unit rumbles or runs rough, perform
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
functional. (jumper may be temporarily installed to test interlock
type (voltage or current).
Configuration Menu.
and reinstall
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
DELAYED
INTERLOCK OPEN
DIRECT DRIVE
SIGNAL FAULT
FLAME LOSS
DURING IGN
1. Delayed Interlock Jumper not
installed or removed.
2. Device proving switch hooked to
interlocks is not closed
1. Direct drive signal is not present:
Not yet installed.
Wrong polarity.
Signal defective at source.
Broken or loose wiring.
2. Signal is not isolated (floating).
3. Control Box signal type selection
switches not set for correct signal
1. Burner Ground Screw not installed
or loose.
2. Worn flame detector
3. No spark from Spark Plug
4. Defective Ignition Transformer
5. Defective Ignition/Stepper (IGST)
Board
6. Defective SSOV
7. Defective Differential Pressure
Regulator.
8. Carbon or other debris on Burner.
1. Check for a jumper properly installed across the delayed
interlock terminals in the I/O box.
2. If there are 2 external wires on these terminals, check to see if
an end switch for a device (i.e. a pump, louver, etc.) is tied to
these interlocks. Ensure that the device and its end switch are
1. Check I/O Box to ensure signal is hooked up.
Hook up if not installed.
If installed, check polarity.
Measure signal level.
Check continuity of wiring between source and boiler.
2. Check signal at source to ensure it is isolated.
3. Check DIP switch on PMC board to ensure it is set correctly for
the type of signal being sent. Check control signal type set in
1. Inspect and install/retighten Burner Ground Screw.
2. Remove and inspect the flame detector for signs of wear.
Replace if necessary.
3. Close the internal gas valve in the boiler. Install and arc a spark
ignitor outside the unit.
4. If there is no spark, check for 120VAC at the primary side to the
ignition transformer during the ignition cycle.
5. If 120VAC is not present, the IGST Board in the Control Box
may be defective. Refer fault to qualified service personnel.
6. While externally arcing the spark ignitor, observe the
open/close indicator in the Safety Shut-Off Valve to ensure it is
opening. If the valve does not open, check for 120VAC at the
valves input terminals. If 120VAC is not present, the IGST
board in the Control Box may be defective. Refer fault to
qualified service personnel.
7. Check gas pressure using gauge or manometer into and out of
the Air/Fuel Valve to ensure gas is getting to burner.
8. Remove burner and inspect for any carbon or debris. Clean
8-3
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
5. Blocked condensate drain.
5. Remove blockage in condensate drain.
Demand
incorrect combustion calibration
combustion calibration. Calibrate or repair as necessary.
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
FLAME LOSS
DURING RUN
HEAT DEMAND
FAILURE
HIGH EXHAUST
TEMPERATURE
1. Worn Flame Detector or cracked
ceramic.
2. Defective Differential Regulator.
3. Poor combustion calibration.
4. Debris on burner.
1. The Heat Demand Relays on the
Ignition/Stepper board failed to
activate when commanded
2. Relay is activated when not in
1. Defective exhaust sensor.
2. Carboned heat exchanger due to
1. Remove and inspect the Flame Detector for signs of wear or
cracked ceramic. Replace if necessary.
2. Check gas pressure readings using a gauge or manometer into
and out of the Air/Fuel Valve to ensure that the gas pressure
into and out of the valve is correct.
3. Check combustion calibration. Adjust as necessary.
4. Remove the burner and inspect for any carbon or debris. Clean
and reinstall.
1. Press CLEAR button and restart the unit. If the fault persists,
replace Ignition/Stepper (IGST) Board.
2. Defective relay. Replace IGST Board.
1. Measure the actual exhaust temperature and continuity of the
exhaust sensor. If the exhaust temperature is less than 475
and the exhaust sensor shows continuity replace the sensor.
2. If exhaust temperature is greater than 500 o F, check
o
F
HIGH GAS
PRESSURE
1. Incorrect supply gas pressure.
2. Defective Supply Regulator or
3. Defective High Gas Pressure Switch
8-4
Wrong Style Regulator
1. If using a non-lock up style regulator for the gas supply,
measure static gas pressure downstream, it should be 14”WC
or less. Adjust as necessary.
2. If gas supply pressure cannot be lowered, a lock-up style
regulator may be required or the supply regulator may be
defective.
3. Remove the leads from the high gas pressure switch. Measure
continuity across the common and normally closed terminals
with the unit not firing. Replace the switch if it does not show
continuity.
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
2. Temp HI Limit setting is too low.
2. Check Temp HI Limit setting.
Ignition/Stepper (IGST) board
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
HIGH WATER TEMP
SWITCH OPEN
HIGH WATER
TEMPERATURE
1. Faulty Water temperature switch.
2. Incorrect PID settings.
3. Faulty shell temperature sensor.
4. Unit in Manual mode
5. Unit setpoint is greater than Over
Temperature Switch setpoint.
6. Boiler Management System PID or
other settings not correctly setup.
7. No interlock to boiler or BMS to
disable boiler(s) in event that system
pumps have failed.
8. System flow rate changes are
occurring faster than boilers can
respond.
1. See HIGH WATER TEMPERATURE
SWITCH OPEN.
1. Test the temperature switch to insure it trips at its actual water
temperature setting.
2. Check PID settings against Menu Default settings in the
Appendix. If the settings have been changed, record the current
readings then reset them to the default values.
3. Using the resistance charts in the Appendix C, Measure the
resistance of Shell sensor and BTU sensor at a known water
temperature.
4. If unit is in Manual Mode switch to Auto Mode.
5. Check setpoint of unit and setpoint of Temperature Switch;
Ensure that the temperature switch is set higher than the unit’s
setpoint.
6. Check the BMS for changes to PID default values, correct as
necessary.
7. If system pump is controlled by Energy Management System
other than BMS or pumps are individually controlled by boiler,
check to see if there are flow switches interlocked to the BMS or
boiler.
8. If the system is a variable flow system, monitor system flow
changes to ensure that the rate of flow change is not faster than
what the boilers can respond to.
1. See HIGH WATER TEMPERATURE SWITCH OPEN.
IGN BOARD
COMM FAULT
8-5
1. Communication fault has occurred
between the PMC board and
1. Press CLEAR button and restart unit. If fault persists, contact
qualified Service Personnel.
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
every second. If not, replace IGST Board
every second. If not, replace IGST Board.
interlocks is not closed.
IGN SWTCH CLOSED
DURING PURGE
IGN SWTCH OPEN
DURING IGNITION
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
1. Air/Fuel Valve not rotating
2. Defective or shorted switch
3. Switch wired incorrectly
4. Defective Power Supply Board or
fuse
5. Defective IGST Board
1. Air/Fuel Valve not rotating to ignition
position.
2. Defective ignition switch
3. Defective Power Supply Board or
fuse
4. Defective IGST Board
1. Start the unit. The Air/Fuel Valve should rotate to the purge
(open) position. If the valve does not rotate at all or does not
rotate fully open, check the Air/Fuel Valve calibration. If
calibration is okay, the problem may be in the Air-Fuel Valve or
the Control Box. Refer to qualified service personnel
2. . If the Air/Fuel Valve does rotate to purge, check the ignition
switch for continuity between the N.O. and COM terminals. If the
switch shows continuity when not in contact with the cam
replace the switch.
3. Check to ensure that the switch is wired correctly (correct wire
numbers on the normally open terminals). If the switch is wired
correctly, replace the switch
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
5. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
1. Start the unit. The Air/Fuel Valve should rotate to the purge
(open) position, then back to ignition position (towards closed)
during the ignition cycle. If the valve does not rotate back to the
ignition position, check the Air/Fuel Valve calibration. If
calibration is okay, the problem may be in the Air/Fuel Valve or
the Control Box. Refer fault to qualified service personnel.
2. If the Air/Fuel Valve does rotate to the ignition position, check
the ignition position switch for continuity between the N.O. and
COM terminals when in contact with the cam.
3. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
4. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
INTERLOCK
OPEN
8-6
1. Interlock jumper not installed or
removed
2. Energy Management System does
not have boiler enabled.
3. Device proving switch hooked to
1. Check for a jumper properly installed across the interlock
terminals in the I/O box
2. If there are two external wires on these terminals check any
Energy Management system to see if they have the units
disabled (a jumper may be temporarily installed to see if the
interlock circuit is functioning).
3. Check that proving switch for any device hooked to the interlock
circuit is closing and that the device is operational.
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
wiring.
replace if necessary.
is no continuity.
FAULT
Modbus network
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
LINE VOLTAGE
OUT OF PHASE
LOW GAS
PRESSURE
LOW WATER
LEVEL
MODBUS COMM
PRG SWTCH CLOSED
DURING IGNITION
1. Line and Neutral switched in AC
Power Box.
2. Incorrect power supply transformer
1. Incorrect supply gas pressure.
2. Defective or incorrectly sized Gas
Supply Regulator.
3. Defective Low Pressure Gas Switch
1. Insufficient water level in system
2. Defective water level circuitry.
3. Defective water level probe.
1. Boiler not seeing information from
1. A/F Valve rotated open to purge and
did not rotate to ignition position
2. Defective or shorted switch.
3. Switch wired incorrectly.
4. Defective Power Supply Board or
fuse
1. Check hot and neutral in AC Power Box to ensure they are not
reversed
2. Check transformer wiring, in AC Power Box, against the power
box transformer wiring diagram to ensure it is wired correctly
1. Measure gas pressure upstream of the supply gas regulator with
the unit firing ensure it is 14” WC or greater.
2. Measure gas pressure downstream of the supply regulator with
unit firing and adjust the gas supply regulator to increase the
outlet gas pressure; if outlet gas pressure cannot be increased,
check the sizing of the Supply regulator.
3. Measure gas pressure at the low gas pressure switch, if it is
greater than 5” WC, measure continuity across the switch and
1. Check system for sufficient water level.
2. Test water level circuitry using the Control Box front panel LOW
WATER TEST and RESET buttons. Replace water level
circuitry if it does not respond.
3. Check continuity of probe end to the shell, change probe if there
1. Check network connections. If fault persists, contact qualified
Service Personnel.
1. Start the unit. The Air/Fuel Valve should rotate to the purge
(open) position, then back to ignition position (towards closed)
during the ignition cycle. If the valve does not rotate back to the
ignition position, check the Air/Fuel Valve calibration. If
calibration is okay, the problem may be in the Air/Fuel Valve or
the Control Box. Refer fault to qualified service personnel.
2. If the Air/Fuel Valve does rotate to the ignition position, check
the purge switch for continuity between the N.O. and COM
terminals. If the switch shows continuity when not in contact
with the cam, check to ensure that the switch is wired correctly
(correct wire numbers on the normally open terminals).
3. If the switch is wired correctly, replace the switch.
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
8-7
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
every second. If not, replace IGST Board.
every second. If not, replace IGST Board.
3. Incorrect Sensor.
3. Ensure that the correct sensor is installed.
2. Defective Flame Detector.
2. Replace Flame Detector.
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
continued 5. Defective IGST Board 5. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
PRG SWTCH OPEN
DURING PURGE
OUTDOOR TEMP
SENSOR FAULT
REMOTE SETPT
SIGNAL FAULT
RESIDUAL
FLAME
1. Defective purge switch.
2. No voltage present at switch.
3. Switch wired incorrectly.
4. Defective Power Supply Board or
fuse
5. Defective IGST Board
1. Loose or broken wiring.
2. Defective Sensor.
1. Remote setpoint signal not present:
Not yet installed.
Wrong polarity.
Signal defective at source.
Broken or loose wiring.
2. Signal is not isolated (floating) if 4 to
20 mA.
3. Control Box signal type selection
switches not set for correct signal
type (voltage or current).
1. SSOV not fully closed.
1. If the air-fuel valve does rotate, check the purge switch for
continuity when closing. Replace switch if continuity does not
exist.
2. Measure for 24 VAC from each side of the switch to ground. If
24VAC is not present, refer fault to qualified service personnel.
3. Check to ensure that the switch is wired correctly (correct wire
numbers on the normally open terminals).
4. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
5. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
1. Inspect Outdoor Temperature sensor for loose or broken wiring.
2. Check resistance of sensor to determine if it is within
specification.
1. Check I/O Box to ensure signal is hooked up.
Hook up if not installed.
If installed, check polarity.
Measure signal level.
Check continuity of wiring between source and boiler.
2. Check signal at source to ensure it is isolated.
3. Check DIP switch on PMC board to ensure it is set correctly for
the type of signal being sent. Check control signal type set in
Configuration Menu.
1. Check open/close indicator window of Safety Shut-Off Valve
(SSOV) and ensure that the SSOV is fully closed. If not fully
closed, replace the valve and or actuator.
Close gas shut-off valve downstream of SSOV. Install a
manometer or gauge in a gas test port between the SSOV and
the gas shut off valve. If a gas pressure reading is observed
replace the SSOV valve and or actuator.
8-8
TROUBLESHOOTING
FAULT INDICATION
PROBABLE CAUSES
CORRECTIVE ACTION
SSOV FAULT
DURING PURGE
SSOV FAULT
during run.
Ignition/Stepper (IGST) Board.
4. Incorrectly wired switch.
every second. If not, replace IGST Board.
See SSOV SWITCH OPEN
TABLE 8-1. BOILER TROUBLESHOOTING – Continued
DURING RUN
SSOV RELAY
FAILURE
SSOV
SWITCH OPEN
1. SSOV switch closed for 15 seconds
1. SSOV relay failed on board. 1. Ensure that Neutral and Earth Ground are connected at the
1. Actuator not allowing for full closure
of gas valve
2. SSOV powered when it should not
be
3. Defective Switch or Actuator
1. Replace SSOV actuator.
source and there is no voltage measured between them.
Measurement should indicate near zero or no more than a few
millivolts.
2. Check the SSOV power wiring.
3. Press CLEAR button and restart unit. If fault persists, replace
1. Observe operation of the Safety Shut-Off Valve (SSOV) through
indicator on the Valve actuator and ensure that the valve is fully
and not partially closing.
2. If the SSOV never closes, it may be powered continuously.
Close the gas supply and remove power from the unit. Refer
fault to qualified service personnel.
3. Remove the electrical cover from the SSOV and check switch
continuity. If the switch does not show continuity with the gas
valve closed, either adjust or replace the switch or actuator.
4. Ensure that the SSOV Proof of Closure switch is correctly wired.
STEPPER MOTOR
FAILURE
8-9
1. Air/Fuel Valve out of calibration.
2. Air/Fuel Valve unplugged.
3. Loose wiring connection to the
stepper motor.
4. Defective Air/Fuel Valve stepper
motor.
5. Defective Power Supply Board or
fuse
6. Defective IGST Board
1. Refer to GF-112 and perform Stepper Test (para. 6.3.5) to
ensure stepper motor rotates properly between the 0% (fully
closed) and 100% (fully open) positions. Verify that the VALVE
POSITION bargraph and the dial on the Air/Fuel Valve track
each other to indicate proper operation. If operation is not
correct, perform the Stepper Feedback Calibration (GF-112,
para. 6.2.1).
2. Check that the Air/Fuel Valve is connected to the Control Box.
3. .Inspect for loose connections between the Air/Fuel Valve motor
and the wiring harness.
4. Replace stepper motor.
5. Check DS1 & DS2 LEDs on Power Supply Board. If they are not
steady ON, replace Power Supply Board.
6. Check “Heartbeat” LED DS1 and verify it is blinking ON & OFF
Section 9 - RS232 COMMUNICATION
9.1 INTRODUCTION
The RS232 port on the front panel of the C-More
Control Box (Figure 3-1) can be interfaced to a
laptop computer or other suitable terminal using
a RS232 adapter cable. RS232 communication
can be accomplished using any “Dumb
Terminal” emulation, such as “Hyper Terminal”
which is included with Microsoft Windows. The
RS232 communication feature permits viewing
or changing of Control Panel menu options and
also provides access to data logs showing Event
Time Line, Fault and Sensor log displays.
9.2 RS232 COMMUNICATION SETUP
Regardless of the terminal emulation utilized,
the following guidelines must be adhered to
when setting up the RS232 communication link:
1. Baud Rate – The baud rates which can be
used with the C-More Control Panel are:
1. 2400
2. 4800
3. 9600 (Default)
4. 19.2K
2. Data Format – The program must be set for: 8
data bits, 1 stop bit, no parity and either
Xon/Xoff or No flow control.
9.3 MENU PROCESSING UTILIZING RS232
COMMUNICATION
Viewing data logs and viewing or changing
Control Panel menu options using RS232
communication is accomplished as follows:
1. Start the emulator software program and
ensure that the specified baud rate and data
formats have been entered.
2. Press the Enter key on the laptop. An
asterisk (*) prompt should appear.
3. At the prompt, enter the valid RS232
password (jaguar) in lower case letters and
press Enter.
4. “Welcome to Aerco” will appear in the laptop
or “dumb terminal” display with a listing of
the following available entry choices:
RS232 COMMUNICATION
M = Display next Menu
D = Display menu items
N = Display next menu items
Cxx = Change item xx
F = Fault log display
S = Sensor log display
T = Time line display
L = Log off
NOTE:
The Level 1 password (159) must be entered to
change options in the Setup, Configuration and
Tuning Menus. The Level 2 password (6817)
must be entered to view or change options in the
Calibration and Diagnostics Menus.
With the exception of the password entry, all
other keyboard entries can be made using either
upper or lower case.
5. To view the available menus in the top-down
sequence shown in Figure 3-2, enter M <Rtn>. The Menu title and first 10 options
will be displayed.
6. When viewing menus containing more than
10 options, enter N <Rtn> to display the
remaining options.
7. Shortcut keys are also available to go directly
to a specific menu. These shortcut keys are:
m0 Default (Operating) Menu
m1 Setup Menu
m2 Configuration Menu
m3 Tuning Menu
m4 Calibration Menu
m5 Diagnostic Menu
8. To change a value or setting for a displayed
menu option, proceed as follows:
(a) Enter C, followed by the number to the
right of the displayed option to be
changed, and then press <Rtn>.
(b) Enter the desired value or setting for the
option and press <Rtn>. Refer to
Section 3, Tables 3-2 through 3-5 for
allowable entry ranges and settings for
the Operating, Setup, Configuration and
Tuning Menus. (The Calibration and
Diagnostic Menus should only be used
by Factory-Trained service personnel).
9-1
RS232 COMMUNICATION
(c) Menu changes will be stored in non-
volatile memory.
9. To redisplay the menu and view the option
which was just changed in step 5, enter D
and press <Rtn>.
10. To display the Fault (F) Log, Sensor (S) Log
or Time (T) Line Log, press F, S or T
followed by <Rtn>. Refer to paragraph 9.4 for
descriptions and samples of these data logs.
11. To log off and terminate the RS232 communication link, press L followed by <Rtn>.
9.4 DATA LOGGING
During operation, the C-More Control Panel
continuously monitors and logs data associated
with operational events, faults and sensor
readings associated with the boiler or water
heater system. Descriptions of these data logs
are provided in the following paragraphs. The
basic procedure for accessing each data log is
described in paragraph 9.3, step 7.
within the C-More Control Panel. Events such
as power-up, ignition and turn-off are time
stamped. Data logged while the unit is running
are run-length encoded. Data is logged or the
run-length incremented every 30 seconds. For a
new run record to be logged, the fire rate or
flame strength must change by more than 5%,
or the run mode must change. At steady-state,
the run-length is allowed to reach a maximum of
30 minutes before the record is logged. This
means that no more than 30 minutes of data can
be lost if the unit loses power. Table 9-2 shows
a sample Operation Time Log for a boiler:
The Operation Time Log can only be accessed
through the RS232 interface using a laptop or
other terminal device. Ten operation time
records are displayed for each T command
entry. The operation time log can be cleared
ONLY by factory authorized personnel using the
Clear Log option in the Factory menu.
9.4.1 Fault Log
The C-More Control Panel logs the last 20 faults
(0 – 19) starting with the most recent (#0). They
can be viewed in the front panel display or via
the RS232 port. The Fault Log cannot be
cleared. If the Fault Log already contains 10
faults, the earliest fault is overwritten when a
new fault occurs. A sample Fault Log display is
shown in Table 9-1.
NOTE:
The Operation Time (T) Log can store
thousands of records. Therefore, to view the
most recently logged record, enter “T” followed
by 0 (zero) and press Enter
(i.e. T0 <Enter>). To view earlier records in
reverse chronological order, enter T and press
Enter. To go back 200 or 1000 records, enter
T200 or T1000, etc. and press Enter.
9.4.2 Operation Time Log
NOTE:
The Sensor (S) Log can store up to 1200
records. Therefore, to view the most recently
logged record, enter “S” followed by 0 (zero) and
then press Enter (i.e. S0 <Enter>). To view
earlier records in reverse chronological order,
enter S and press Enter. To go back 200 or 700
records, enter S200 or S700, etc. and press
Enter.
9.4.3 Sensor Log
The sensor values can be logged at a different
rate if needed by setting the Sensor Log Interval
in the Diagnostics Menu. The log interval can
vary from once every minute to once every day.
Table 9-3 shows a sample Sensor Log every 5
minutes for a boiler running in Constant Setpoint
mode.
The Operation Time Log consists of a string of
ASCII records stored in non-volatile memory
9-2
RS232 COMMUNICATION
No.
Fault Message
Cycle
Date
Time
0
Direct Drive Signal Fault
609
1/10/02
8:42am
1
Low Gas Pressure
366
7/04/01
5:29pm
2
Loss of Power
0
1/01/01
11:50am
Status
Fire Rate
Flame
Run Length
Date
Time
Off, Direct Drive
0
0
8
1/15/02
2:35pm
Run, Direct Drive
38
100
34
1/15/02
2:27pm
Run, Direct Drive
31
100
30
1/15/02
1:53am
Run, Direct Drive
35
100
2
1/15/02
1:23pm
Run, Direct Drive
29
100
0
1/15/02
1:21pm
Ignition
0
0
0
1/15/02
1:20pm
Off, Switch
0
0
35
1/15/02
12:30pm
Run, Manual
40
100
0
1/15/02
11:55am
Ignition
0
0
0
1/15/02
11:55am
Power-up
0
0
0
1/15/02
11:50am
Setpt
Outlet
Outdr
FFWD
Aux
Inlet
Exhst
CO
O2
Flow
Date
Time
130
181
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:51pm
130
180
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:46pm
130
180
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:41pm
130
179
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:36pm
130
180
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:31pm
130
180
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:26pm
130
180
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:21pm
130
180
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:16pm
130
179
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:11pm
130
180
OPEN
OPEN
OPEN
OPEN
OPEN
0
.0
0
1/15/02
5:06pm
Table 9-1. Sample Fault Log Display
Table 9-2. Sample Operation Time Log Display
Table 9-3. Sample Sensor Log Display
9-3
MENU LEVEL & OPTION
DESCRIPTION
OPERATING MENU
derived value from the charts in Appendix D.
Air Temp
For monitoring purposes only
Outdoor Temp
Displayed only if outdoor sensor is installed and
enabled.
operating.
Flame Strength
Displays flame strength from 0% to 100%.
Run Cycles
Displays the total number of run cycles from 0 to
999,999.
9,999,999.
Fault Log
Displays information on the last 20 faults (0 – 19).
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS
Active Setpoint This is the setpoint temperature to which the
control is set when operating in the Constant
Setpoint, Remote Setpoint or Outdoor Reset
Mode. When in the Constant Setpoint Mode, this
value is equal to the Internal Setpoint setting in the
Configuration Menu. When in the Remote
Setpoint Mode, this value is the setpoint equivalent
to the remote analog signal supplied to the unit.
When in the Outdoor Reset Mode, this is the
APPENDIX A
Valve Position In Desired input valve position. This would normally
be the same as the fire valve position shown on
the bargraph (valve position out) when the boiler is
Run Hours Displays total run time of unit in hours from 0 to
A-1
APPENDIX A
MENU LEVEL & OPTION
DESCRIPTION
SETUP MENU
Password
Allows password to be entered.
modified.
Language
Permits selection of English, Spanish or French for
displayed messages. Default is English.
Time
Displays time from 12:00 am to 11:59 pm.
Date
Displays dates from 01/01/00 to 12/31/99
Unit of Temp
Permits selection of temperature displays in degrees
°F.
Comm Address
For RS-485 communications (0 to 127). Default
(programmable) password.
Baud Rate
Allows communications Baud Rate to be set (2400
to 19.2K). Default is 9600.
Software Version
Identifies the current software version of the control
box (Ver 0.0 to Ver 9.9).
CONFIGURATION MENU
Internal Setpoint
Allows internal setpoint to be set . Default is 130°F.
Unit Type
Allows selection of KC Boiler, KC Boiler LN, BMK
Heater, KC Water Heater LN, Water Heater 2010
Unit Size
Sets unit size from 0.5 to 6.0 MBTUs. Default is 1.0
MBTU.
Fuel Type
Allows selection of Natural Gas or Propane
Reset Mode. Default is Constant Setpoint Mode.
Remote Signal
Used to set the type of external signal which will be
4-20 mA/1-5V.
Bldg Ref Temp
Allows the building reference temperature to be set
Default is 70°F.
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS - CONTINUED
Once the valid password (159) is entered, options in
the Setup, Configuration and Tuning Menus can be
Fahrenheit (°F) or degrees Celsius (°C). Default is
address is 0. RS-232 should have its own
Boiler, BMK Boiler LN, BMK Boiler Dual, KC Water
Boiler Mode It allows selection of: Constant Setpoint, Remote
Setpoint, Direct Drive, Combination, or Outdoor
used when operating in the Remote Setpoint, Direct
Drive or Combination Mode. The factory default is
when operating a boiler in the Outdoor Reset Mode.
A-2
APPENDIX A
MENU LEVEL & OPTION
DESCRIPTION
CONFIGURATION MENU (Cont.)
Reset Ratio
Permits setting of Reset Ratio when operating boiler
adjustable from 0.1 to 9.9. Default is 1.2.
Outdoor Sensor
Allows outdoor sensor function to be enabled or
disabled. Default is disabled.
System Start Tmp
If outdoor sensor is enabled, this menu item allows
100°F. Default is 60°F.
Setpoint Lo Limit
Used to set the minimum allowable setpoint (40°F to
Setpoint Hi Limit). Default is 60°F
Setpoint Hi Limit
Used to set the maximum allowable setpoint
(Setpoint Lo Limit to 220°F). Default is 195°F.
Temp Hi Limit
This is the maximum allowable outlet temperature
Hi Limit is 195°F.
Max Valve Positon
Sets the maximum allowable valve position for the
unit (40% to 100%). Default is 100%.
zero.
Aux Start On Dly
Specifies the amount of time to wait (0 to 120 sec.)
Default is 0 sec.
Failsafe Mode
Allows the Failsafe mode to be set to either
Shutdown.
Analog Output
Must be set to Valve Pos 0-10V.
Lo Fire Timer
Specifies how long (2 to 600 sec.) to remain in the
desired output. Default is 2 sec.
Network Timeout
Specifies the timeout value (seconds) before a
from 5 to 999 seconds. Default is 30 seconds.
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS - Continued
in the Outdoor Reset Mode. Reset Ratio is
the system start temperature to be set from 30 to
(40 to 240°F). Any temperature above this setting
will turn off the unit. The temperature must then drop
5° below this setting to allow the unit to run. Default
Pump Delay Timer Specifies the amount of time (0 to 30 min.) to keep
the pump running after the unit turns off. Default is
between activating the Aux Relay (due to a demand)
and checking the pre-purge string to start the boiler.
Constant Setpoint or Shutdown. Default is
low fire position after ignition, before going to the
Modbus fault is declared. Available settings range
A-3
APPENDIX A
MENU LEVEL & OPTION
DESCRIPTION
CONFIGURATION MENU (Cont.)
HI DB Setpt EN
Operating at a Valve Position below this value will
Setting range is from 0 to 100. (Default is 30)
Setting range is 0 to 25. (Default is 10)
Deadband High and Deadband Low)
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS - Continued
inhibit the DEADBAND feature. When operating at a
Valve Position below this value, the effective
Setpoint is equal to Active Setpoint + DEADBAND
HIGH.
Demand Offset This entry will reduce excessive ON/OFF cycling in
AUTO mode. When this entry is a non-zero value,
the unit will not turn on again until Valve Position In
reaches the Start Level value AND the Outlet
Temperature goes below the Active Setpoint – Demand Offset. In addition, the boiler will fire at the
29% Valve Position level or below for a period of
one minute.
When this entry is set to zero, the unit will turn on
again as soon as the Valve Position in reaches the
Start Level value. There will not be a one minute
delay when firing at the 29% Valve Position level.
Deadband High
Deadband Low
Deadband High and Deadband Low settings create
an “Outlet Temperature” Zone. In which no Valve
Position corrections will be attempted.
The Deadband ZONE is defined as operating with
an Outlet Temperature between Active Setpoint +
Deadband High and Active Setpoint – Deadband
Low.
When the Outlet Temperature reaches Active
Setpoint and remains there for a period of 15
seconds, the unit will go into a DEADBAND MODE
at which point no Valve Position corrections will be
attempted while the Outlet Temperature remains
anywhere within the Deadband ZONE. When the
unit is in the DEADBAND MODE, the °F or °C LED
will flash on and off. When the Outlet Temperature
drifts out of the Deadband ZONE, the DEADBAND
MODE will be terminated and the PID LOOP will
again attempt Valve Position corrections.
Setting range is 0 to 25. (Default is 2 for both
A-4
APPENDIX A
MENU LEVEL & OPTION
DESCRIPTION
TUNING MENU
Prop Band
Generates a valve position based on the error that
setting, the valve position will be 100%.
Integral Gain
This sets the fraction of the output, due to setpoint
from 0.00 to 1.00 (Default is 0.10).
Derivative Time
This value (0.0 to 20.0 min.) responds to the rate of
this action advances the output.
Reset Defaults?
Allows Tuning Menu options to be reset to their
Factory Default values.
APPENDIX A - BOILER MENU ITEM DESCRIPTIONS - CONTINUED
exists between the setpoint temperature and the
actual outlet temperature. If the actual error is less
than the proportional band setting (1 to 120°F), the
valve position will be less than 100%. If the error is
equal to or greater than the proportional band
error, to add or subtract from the output each minute
to move towards the setpoint. Gain is adjustable
change of the setpoint error. This is the time that
A-5
APPENDIX B
DEMAND DELAY
XX sec
Displayed if Demand Delay is active.
DISABLED
MM/DD/YY
Displayed if ON/OFF switch is set to OFF. The display also
disabled.
of flame strength.
IGNITION TRIAL
XX sec
Displayed during ignition trial of startup sequence. The
duration of cycle counts up in seconds.
PURGING
XX sec
Displayed during the purge cycle during startup. The
duration of the purge cycle counts up in seconds.
STANDBY
Displayed when ON/OFF switch is in the ON position, but
displayed.
WAIT
Prompts the operator to wait.
WARMUP
XX sec
Displayed for 2 minutes during the initial warm-up only.
APPENDIX B - STARTUP, STATUS AND FAULT MESSAGES
TABLE B-1. STARTUP AND STATUS MESSAGES
MESSAGE DESCRIPTION
HH:MM pm, pm
FLAME PROVEN
shows the time (am or pm) and date that the unit was
Displayed after flame has been detected for a period of 2
seconds. Initially, the flame strength is shown in %. After 5
seconds has elapsed, the time and date are shown in place
there is no demand for heat. The time and date are also
B-1
APPENDIX B
AIRFLOW FAULT
DURING PURGE
The Blower Proof Switch opened during purge,
or air inlet is blocked.
AIRFLOW FAULT
DURING IGN
The Blower Proof Switch opened during ignition.
AIRFLOW FAULT
DURING RUN
The Blower Proof Switch opened during run.
DELAYED
INTERLOCK OPEN
The Delayed Interlock is open.
DIRECT DRIVE
SIGNAL FAULT
The direct drive signal is not present or is out of range.
FFWD TEMP
SENSOR FAULT
The temperature measured by the Feed Forward (FFWD)
Sensor is out of range.
FLAME LOSS
DURING IGN
The Flame signal was not seen during ignition or lost within 5
seconds after ignition.
FLAME LOSS
DURING RUN
The Flame signal was lost during run.
HEAT DEMAND
FAILURE
The Heat Demand Relays on the Ignition board failed to
activate when commanded.
HIGH EXHAUST
TEMPERATURE
The High Exhaust Temperature Limit Switch is closed.
HIGH GAS
PRESSURE
The High Gas Pressure Limit Switch is open.
HIGH WATER
TEMPERATURE
The temperature measured by the Outlet Sensor exceeded
the Temp Hi Limit setting.
HIGH WATER TEMP
SWITCH OPEN
The High Water Temperature Limit Switch is open.
IGN BOARD
COMM FAULT
A communication fault has occurred between the PMC board
and Ignition board.
IGN SWTCH CLOSED
DURING PURGE
The Ignition Position Limit switch on the Air/Fuel Valve closed
during purge.
IGN SWTCH OPEN
DURING IGNITION
The Ignition Position Limit switch on the Air/Fuel Valve
opened during ignition.
INTERLOCK
OPEN
The Remote Interlock is open.
LINE VOLTAGE
OUT OF PHASE
The Line (Hot) and Neutral wires are reversed.
LOW GAS
PRESSURE
The Low Gas Pressure Limit Switch is open.
LOW WATER
LEVEL
The Low Water Cutoff board is indicating low water level.
NETWORK COMM
FAULT
The RS-485 network information is not present or is
corrupted.
FAULT MESSAGE FAULT DESCRIPTION
TABLE B-2. FAULT MESSAGES
B-2
APPENDIX B
SENSOR FAULT
of range.
OUTLET TEMP
The temperature measured by the Outlet Sensor is out of
is open-circuited
PRG SWTCH CLOSED
DURING IGNITION
The Purge Position Limit Switch on the Air/Fuel Valve closed
during ignition.
PRG SWTCH OPEN
DURING PURGE
The Purge Position Limit Switch on the Air/Fuel Valve
opened during purge.
REMOTE SETPT
SIGNAL FAULT
The Remote Setpoint signal is not present or is out of range.
RESIDUAL
FLAME
The Flame signal was seen for more than 60 seconds during
standby.
SSOV
SWITCH OPEN
The SSOV switch opened during standby.
SSOV FAULT
DURING PURGE
The SSOV switch opened during purge.
SSOV FAULT
DURING IGN
The SSOV switch closed or failed to open during ignition.
SSOV FAULT
DURING RUN
The SSOV switch closed for more than 15 seconds during
run.
SSOV RELAY
FAILURE
A failure has been detected in one of the relays that control
the SSOV.
STEPPER MOTOR
FAILURE
The Stepper Motor failed to move the Air/Fuel Valve to the
desired position.
TABLE B-2. FAULT MESSAGES - Continued
FAULT MESSAGE FAULT DESCRIPTION
OUTDOOR TEMP
The temperature measured by the Outdoor Air Sensor is out
SENSOR FAULT
range:
• OUTLET TEMPERATURE display = SHt Indicates sensor
is shorted
• OUTLET TEMPERATURE display = OPn indicates sensor
B-3
Temperature Sensor Resistance Chart
(Balco)
APPENDIX C
C-1
APPENDIX D
RESET RATIO
Air
Temp
50F
50
50
50
50
50
50
50
50
50
50
45F
53
54
55
56
57
58
59
60
60
62
40F
56
58
60
62
64
66
68
70
72
74
35F
59
62
65
68
71
74
77
80
83
86
30F
62
66
70
74
78
82
86
90
94
98
25F
65
70
75
80
85
90
95
100
105
110
20F
68
74
80
86
92
98
104
110
116
122
15F
71
78
85
92
99
106
113
120
127
134
10F
74
82
90
98
106
114
122
130
138
146
5F
77
86
95
104
113
122
131
140
149
158
0F
80
90
100
110
120
130
140
150
160
170
-5F
83
94
105
116
127
138
149
160
171
182
-10F
86
98
110
122
134
146
158
170
182
194
-15F
89
102
115
128
141
154
167
180
193
206
-20F
92
106
120
134
148
162
176
190
204
218
RESET RATIO
Air
Temp
60F
60
60
60
60
60
60
60
60
60
60
55F
63
64
65
66
67
68
69
70
71
72
50F
66
68
70
72
74
76
78
80
82
84
45F
69
72
75
78
81
84
87
90
93
96
40F
72
76
80
84
88
92
96
100
104
108
35F
75
80
85
90
95
100
105
110
115
120
30F
78
84
90
96
102
108
114
120
126
132
25F
81
88
95
102
109
116
123
130
137
144
20F
84
92
100
108
116
124
132
140
148
156
15F
87
96
105
114
123
132
141
150
159
168
10F
90
100
110
120
130
140
150
160
170
180
5F
93
104
115
126
137
148
159
170
181
192
0F
96
108
120
132
144
156
168
180
192
204
-5F
99
112
125
138
151
164
177
190
203
216
-10F
102
116
130
144
158
172
186
200
214
-15F
105
120
135
150
165
180
195
210
-20F
108
124
140
156
172
188
204
INDOOR/OUTDOOR RESET RATIO CHARTS
Header Temperature for a Building Reference Temperature of 50F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
Header Temperature for a Building Reference Temperatrure of 60F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
D-1
APPENDIX D
RESET RATIO
Air
Temp
65
65
65
65
65
65
65
65
65
65
65
60
68
69
70
71
72
73
74
75
76
77
55
71
73
75
77
79
81
83
85
87
89
50
74
77
80
83
86
89
92
95
98
101
45
77
81
85
89
93
97
101
105
109
113
40
80
85
90
95
100
105
110
115
120
125
35
83
89
95
101
107
113
119
125
131
137
30
86
93
100
107
114
121
128
135
142
149
25
89
97
105
113
121
129
137
145
153
161
20
92
101
110
119
128
137
146
155
164
173
15
95
105
115
125
135
145
155
165
175
185
10
98
109
120
131
142
153
164
175
186
197
5
101
113
125
137
149
161
173
185
197
209
0
104
117
130
143
156
169
182
195
208
-5
107
121
135
149
163
177
191
205
219
-10
110
125
140
155
170
185
200
215
-15
113
129
145
161
177
193
209
-20
116
133
150
167
201
218
RESET RATIO
Air
Temp
70F
70
70
70
70
70
70
70
70
70
70
65F
73
74
75
76
77
78
79
80
81
82
60F
76
78
80
82
84
86
88
90
92
94
55F
79
82
85
88
91
94
97
100
103
106
50F
82
86
90
94
98
102
106
110
114
118
45F
85
90
95
100
105
110
115
120
125
130
40F
88
94
100
106
112
118
124
130
136
142
35F
91
98
105
112
119
126
133
140
147
154
30F
94
102
110
118
126
134
142
150
158
166
25F
97
106
115
124
133
142
151
160
169
178
20F
100
110
120
130
140
150
160
170
180
190
15F
103
114
125
136
147
158
169
180
191
202
10F
106
118
130
142
154
166
178
190
202
214
5F
109
122
135
148
161
174
187
200
213
0F
112
126
140
154
168
182
196
210
-5F
115
130
145
160
175
190
205
-10F
118
134
150
166
182
198
214
-15F
121
138
155
172
189
206
-20F
124
142
160
178
196
214
Header Temperature for a Building Reference Temperature of 65F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
Header Temperature for a Building Reference Temperature of 70F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
D-2
APPENDIX D
RESET RATIO
Air
Temp
75F
75
75
75
75
75
75
75
75
75
75
70F
78
79
80
81
82
83
84
85
86
87
65F
81
83
85
87
89
91
93
95
97
99
60F
84
87
90
93
96
99
102
105
108
111
55F
87
91
95
99
103
107
111
115
119
123
50F
90
95
100
105
110
115
120
125
130
135
45F
93
99
105
111
117
123
129
135
141
17
40F
96
103
110
117
124
131
138
145
152
159
35F
99
107
115
123
131
139
147
155
163
171
30F
102
111
120
129
138
147
156
165
174
183
25F
105
115
125
135
145
155
165
175
185
195
20F
108
119
130
141
152
163
174
185
196
207
15F
111
123
135
147
159
171
183
195
207
219
10F
114
127
140
153
166
179
192
205
218
5F
117
131
145
159
173
187
201
215
0F
120
135
150
165
180
195
210
-5F
123
139
155
171
187
203
219
-10F
126
143
160
177
194
211
-15F
129
147
165
183
201
219
RESET RATIO
Air
Temp
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
80F
80
80
80
80
80
80
80
80
80
80
75F
83
84
85
86
87
88
89
90
91
92
70F
86
88
90
92
94
96
98
100
102
104
65F
89
92
95
98
101
104
107
110
113
116
60F
92
96
100
104
108
112
116
120
124
128
55F
95
100
105
110
115
120
125
130
135
140
50F
98
104
110
116
122
128
134
140
146
152
45F
101
108
115
122
129
136
143
150
157
164
40F
104
112
120
128
136
144
152
160
168
176
35F
107
116
125
134
143
152
161
170
179
188
30F
110
120
130
140
150
160
170
180
190
200
25F
113
124
135
146
157
168
174
190
201
212
20F
116
128
140
152
164
176
188
200
212 15F
119
132
145
158
171
184
197
210
10F
122
136
150
164
178
192
206
5F
125
140
155
170
185
200
215 0F
128
144
160
176
192
208
-5F
131
148
165
182
199
216
-10F
134
152
170
188
206
Header Temperature for a Building Reference Temperature of 75F
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
Header Temperature for a Building Reference Temperature of 80F
D-3
APPENDIX D
RESET RATIO
Temp
90F
90
90
90
90
90
90
90
90
90
90
85F
93
94
95
96
97
98
99
100
101
102
80F
96
98
100
102
104
106
108
110
112
114
75F
99
102
105
108
111
114
117
120
123
126
70F
102
106
110
114
118
122
126
130
134
138
65F
105
110
115
120
125
130
135
140
145
150
60F
108
114
120
126
132
138
144
150
156
162
55F
111
118
125
132
139
146
153
160
167
174
50F
114
122
130
138
146
154
162
170
178
186
45F
117
126
135
144
153
162
171
180
189
198
40F
120
130
140
150
160
170
180
190
200
210
35F
123
134
145
156
167
178
189
200
30F
126
138
150
162
174
186
198
210
25F
129
142
155
168
181
194
207
20F
132
146
160
174
188
202
216
15F
135
150
165
180
195
210
10F
138
154
170
186
202
218
5F
141
158
175
192
209
0F
144
162
180
198
216
Header Temperature for a Building Reference Temperature of 90F
Air
0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4
D-4
APPENDIX E
System Start Tmp
Temp Hi Limit
Max Fire Rate
100%
MENU & OPTION FACTORY DEFAULT
BOILER DEFAULT SETTINGS
Setup Menu
Password 0
Language English
Unit of Temp Fahrenheit
Comm Address 0
Baud Rate 9600
Configuration Menu
Internal Setpt 130°F
Unit Type KC Boiler
Unit Size 1.0 MBTU
Boiler Mode Constant Setpoint
Remote Signal
(If Mode = Remote Setpoint, Direct Drive or
Combination)
Bldg Ref Temp
(If Boiler Mode = Outdoor Reset)
4 – 20 mA / 1-5V
70°F
Reset Ratio
(If Boiler Mode = Outdoor Reset)
Outdoor Sensor Disabled
(If Outdoor Sensor = Enabled)
Setpt Lo Limit 60°F
Setpt Hi Limit 195°F
Pump Delay Timer 0 min
Aux Start On Dly 0 sec
Failsafe Mode Shutdown
Analog Output Valve Position 0-10V
CAUTION: DO NOT Change
Lo Fire Timer 2 sec
Setpt Limit Band (If Setpt Limiting = Enabled) 5°F
1.2
60°F
195°F
E-1
APPENDIX E
MENU & OPTION FACTORY DEFAULT
Configuration Menu --Continued
BOILER DEFAULT SETTINGS - Continued
Network Timeout 30 seconds
Hi DB Setpt En 30
Demand Offset 10
Deadband High 2
Deadband Low 2
Tuning Menu
Prop Band 70°F
Integral Gain 1.00
Derivative Time 0.0 min
E-2
APPENDIX F
F-1
APPENDIX F
35 (89)
49 (124)
57 (145)
47 (119)
30-1/8
16-3/4
23-1/4
68-1/2
77-1/8
72-1/2
14-3/8
19 (48)
22-1/4 (57)
15-1/2 (39)
29
3 (8)
6 (15) I.D.
FLUE CONN.
3/4 (2) DIA.
(ENCLOSURE)
c.g.
PRESSURE
RELIEF
4-150# FLG'D
4-150# FLG'D
SYS. WATER SUPPLY
SYS. WATER RETURN
AC SERVICE CONN.
3/4 CONDUIT
120VAC SINGLE PHASE
20 AMP W/GRD
c.g.
3-1/8
(184)
5-3/4 (15)
REMOTE ALARM & CONTROL
CONNECTION - 3/4 CONDUIT
1-1/4NPT GAS INLET
(77)
(174)
(59)
(43)
(196)
(37)
SHELL CAP
VALVE
COMB. AIR INTAKE
(OPTIONAL O.A.
INLET ADAPTER
1"NPT
DRAIN
VALVE
5/8" I.D
MALE HOSE
CONDENSATE
DRAIN
MODEL KC
STYLE
KC SERIES GAS FIRED BOILER
DIMENSIONAL DRAWING
AP-A-816
A
NOTES:
1) DRAIN VALVE AND RELIEF VALVE ARE INCLUDED SEPARATELY IN SHIPMENT
2) A 1/4" PER FOOT FLUE PITCH BACK TOWARDS THE HEATER MUST BE
MAINTAINED TO ALLOW THE FLOW OF ANY CONDENSATE FORMED IN THE
FLUE TO FLOW TO THE DRAIN
3) ALL DIMENSIONS SHOWN ARE IN INCHES (CENTIMETERS)
22 (56)
(FLOOR FLANGE)
(TYP)
(OUTLET)
(INLET)
GK 2-1-95
TYP.
4-PLCS
(
)
14-3/4 (37)
AERCO
INTERNATIONAL INC.
NORTHVALE, NEW JERSEY 07647
CHKD
APPD
13-9/16
(34.4)
TRAIN OPTION" ONLY
CONN. FOR "IRI GAS
3/4" NPT GAS VENT
AVAIL. - 6" OD)
ASME B & PV CODE SECTION IV STAMP H
HEAT EXCHANGER DESIGN STANDARDS
SHELL SIDE
PRESS. (PSIG)
150
MAX. WORKING
225
TEST PRESS.
(PSIG)TEMP. (°F)
25
MAXIMUM
REV.
F-2
APPENDIX F
35(89)
49(124)
57(145)
47(119)
30-1/8
16-3/4
23-1/4
68-1/2
77-1/8
72-1/2
14-3/8
19(48)
22-1/4(57)
15-1/2(39)
29
3(8)
6(15)I.D.
FLUE CONN.
3/4(2)DIA.
(ENCLOSURE)
c.g.
PRESSURE
RELIEF
4-150# FLG'D
4-150# FLG'D
SYS. WATER SUPPLY
SYS. WATER RETURN
AC SERVICE CONN.
3/4 CONDUIT
120VAC SINGLE PHASE
20 AMP W/GRD
c.g.
3-1/8
(184)
5-3/4(15)
REMOTE ALARM & CONTROL
CONNECTION - 3/4 CONDUIT
1-1/4NPT GAS INLET
(77)
(174)
(59)
(43)
(196)
(37)
SHELL CAP
VALVE
COMB. AIR INTAKE
(OPTIONAL O.A.
INLET ADAPTER
1"NPT
DRAIN
VALVE
5/8" I.D
MALE HOSE
CONDENSATE
DRAIN
HEAT EXCHANGER DESIGN STANDARDS
SHELL SIDE
87
PRESS. (PSIG)
MAX. WORKINGMAXIMUM
TEMP. (°F)
TEST PRESS.
(PSIG)
250130.5
ASME B & PV CODE SECTION IV STAMP H
KCGWB-DP GAS FIRED BOILER
DIMENSIONAL DRAWING
AP-A-863
A
NOTES:
1) DRAIN VALVE AND RELIEF VALVE ARE INCLUDED SEPARATELY IN SHIPMENT
2) A 1/4" PER FOOT FLUE PITCH BACK TOWARDS THE HEATER MUST BE
MAINTAINED TO ALLOW THE FLOW OF ANY CONDENSATE FORMED IN THE
FLUE TO FLOW TO THE DRAIN
3) ALL DIMENSIONS SHOWN ARE IN INCHES (CENTIMETERS)
22(56)
(FLOOR FLANGE)
(TYP)
(OUTLET)
(INLET)
CZ 100206
TYP.
4-PLCS
(
)
14-3/4(37)
DWN.BY
APPD
13-9/16
(34.4)
TRAIN OPTION" ONLY
CONN. FOR "IRI GAS
3/4" NPT GAS VENT
AVAIL. - 6" OD)
REV.
(PROVINCE OF ALBERTA INSTALLATIONS)
INTERNATIONAL INC.
AERCO
NORTHVALE, NEW JERSEY 07647
F-3
APPENDIX F
22
51
46
DESCRIPTIONQTYITEM PART NO.
BLOWER PROOF SWITCH1
61002-14
43
44
45
37
24
11
38 39
25
26
23
XX NOT SHOWN IN THE DRAWING
TEMP./PRESS. GAUGE
DRAIN VALVE ASSEMBLY
1" NPT CLOSE NIPPLE - RED BRASS
1" NPT PRESSURE RELIEF VALVE
69087-
GM-122743
9-308
GP-5130-
19
***
11
12
1
1
1
1
TEMPERATURE SWITCH THERMOWELL
1/4" MNPT x 1/8" FNPT RED. BUSHING
1
123463
49
52
51
50
1
124334
161569
123711
1
2
46
48
47
45
44
1
GP-122821
122843
123448
1
1
123536
GP-122403
1
1
EXHAUST TEMPERATURE SWITCH
EXHAUST TEMP. SWITCH HARNESS
SHELL WIRING HARNESS
LOW WATER CUT-OFF
TEMPERATURE SWITCH
LOW PRESSURE GAS SWITCH
SHELL SENSOR
HOSE CLAMP 13/16" - 1-3/4"∅ RANGE
EXH. MANIFOLD TO COMB. CHAMB.
GASKET
48
12
8
50
QTYITEM PART NO.DESCRIPTION
OTHER ACCESSORIES
TEFLON RELEASE GASKET
BURNER FLANGE GASKET
COMBUSTION CHAMBER LINER
EXH. MANIFOLD TO LOWER HEAD SEAL
GP-18899
1
16
GP-161151
GP-122537
17
18
1
1
GP-122551
GP-18900
14
15
1
1
VENT MOUNTING FLANGE
CONDENSATE CUP ASSEMBLY
EXHAUST MANIFOLD
EXHAUST MANIFOLD INSULATION
EXHAUST MANIFOLD DRAIN HOSE
EXHAUST MANIFOLD
GP-122849
GP-123337
7
6
2
1
GM-20844-2
GP-20885
GP-122540
GM-123352
PART NO.
4
5
3
ITEM
2
1
1
1
QT
Y
1
GASKETS
DESCRIPTION
HEAT EXCHANGER ASS'Y
HEAT EXCHANGER
GM-20881
PART NO.
ITEM
1
QT
Y
1
DESCRIPTION
INPUT/OUTPUT (I/O) BOX ASSEMBLY
3/8" NPT x 3/8" O.D. TUBE AL. COMP. FTG.
1/8" NPT x 3/8" O.D. TUBE AL. COMP. FTG.
GAS INLET PIPE1
GM-20934
35
40
42
41
39
38
1
161560
161450
181198
1
1
GP-122569
GP-122464
1
1
ITEM
37
PART NO.
161559
QTY
1
GAS TRAIN WIRING HARNESS
IGNITION CABLE ASSEMBLY
IGNITION TRANSFORMER
CONTROL BOX ASSEMBLY
DESCRIPTION
POWER BOX ASSEMBLY
CONTROLS
BURNER AND AIR/FUEL VALVE
34
31
32
30
GP-122614
GP-161147
1
GP-18894
123581
1
1
1
ITEM
29
PART NO.
GP-161146
QTY
1
VALVE TO BURNER AIR HOSE
GAS PRESS. CONTROL TUBE
DESCRIPTION
BLOWER TO AIR VA. INLET HOSE
1-1/2" X 1" REDUCING BUSHING1
8
1" NPT X 4" LG. NIPPLE - RED BRASS
1" NPT 90° ELBOW - BRONZE
8-22
GP-9-428
GP-122789
9
10
1
1
**
** INDICATE PRESSURE RELIEF VALVE SETTING
9
10
19
47
HIGH PRESS. GAS SWITCH
53
1
GP-122412
(30, 50, 75, 100, OR 150 PSI)
GP-18532
13
1 SHELL GASKET
20
EXTERNAL GAS SHUT-OFF VALVE
XX
GP-123050
1
*** -2 (30 AND 50 PSI RELIEF VALVE SETTING)
-3 (75 AND 100 PSI RELIEF VALVE SETTING)
-4 (150 PSI RELIEF VALVE SETTING)
123863
54
1 1/8" NPT BALL VALVE
20
*
*
*
*
*
* SEE DRAWING PL-A-136 FOR INSTALLATION DETAIL
APPD.
DWN.BY
SCALE
CZ
DATE
041304
DATE
PL-A-139
(SH. 1 OF 2)
J
INTERNATIONAL, INC.
NORTHVALE, NJ 07647
PARTS LIST
KC1000 WATER BOILER
AERCO
BURNER ASSEMBLY (PROPANE)
BURNER ASSEMBLY (NATURAL GAS)
GM-20933
GM-20874
36
1
AIR/FUEL VALVE (PROPANE)
AIR/FUEL VALVE (NATURAL GAS)
201222
201211
33
1
GAS TRAIN ASSEMBLY (IRI; PROPANE)
GAS TRAIN ASSEMBLY (FM; PROPANE)
DESCRIPTION
GAS TRAIN ASSEMBLY (FM; NAT. GAS)
GAS TRAIN ASSEMBLY (IRI; NAT. GAS)
181191
181123
181182
PART NO.
GM-18997
22
ITEM
1
QT
Y
GAS TRAIN
65029
BLOWER MOTOR CAPACITOR
WITH AMETEK/A.O. SMITH MOTOR)
BLOWER MOTOR CAP. (FOR BLOWERS
(FOR BLOWERS WITH BALDOR MOTOR)
BLOWER MOTOR CAPACITOR
(FOR ACI BLOWERS)
BLOWER AIR INLET SHUTTER
AIR INLET SCREEN
DAMPER TO BLOWER INLET HOSE
1
26
GP-122669
GP-122835
85003
28
27
1
2 SPACER
124936
GP-122553
GP-161152
25
24
1
1
DESCRIPTION
BLOWER (INCLUDES CAPACITOR 65029)
PART NO.
124935
23
ITEM
1
QTY
BLOWER
BURNER & AIR/FUEL VALVE O-RING
OTHER PARTS
GP-122406
PART NO.
ITEM
55
QTY
3
DESCRIPTION
F-4
APPENDIX F
14
6
36
4
5
16
35
34
15
49
17
52
18
29
33
43
31
32
30
40
41
1
42
2
3
7
2728
CPLG. W/PLUG
SIGHT PORT
53
54
13
PARTS LIST
NORTHVALE, NJ 07647
INTERNATIONAL, INC.
PL-A-139
(SH. 2 OF 2)
KC1000 WATER BOILER
SCALE
APPD.
DWN.BY
DATE
CZ
DATE
041304
AERCO
J
55
55
F-5
APPENDIX F
1 1/2" SAFETY SHUT-OFF VALVE
DIFFERENTIAL PRESSURE REGULATOR W/ BROWN SPRING
BURNER/GAS VA. ADAPTOR
2
3
4
5
1GM-161095
GAS COCK
GP-122415
GP-122409 1
1
1241501
534
2
1
1
640471 SSOV ACTUATOR
FRONT VIEWLEFT SIDE VIEWREAR VIEW
DESCRIPTIONITEM PART NO. REQ
PARTS LIST
AERCO
INTERNATIONAL, INC.
NORTHVALE, NJ 07647
(FACTORY MUTUAL)
APPD.
SCALE
DATE
CZ
DWN.BYDATE
043002
PL-A-135
F
REV.
6
7
GP-122548
6
1 SPRING (BROWN) FOR DIFFERENTIAL PRESSURE REGULATOR
- THE SECOND O-RING (NOT SHOWN IN THE DRAWING) GOES TO THE GAS OUTLET FLANGE OF THE AIR-FUEL VALVE.
*
GAS TRAIN O-RING
*
GP-122406 2
7
RIGHT SIDE VIEW
KC1000 NAT. GAS TRAIN ASSEMBLY
8
8
9
GP-122403
GP-122412
1
1
LOW GAS PRESSURE SWITCH
HIGH GAS PRESSURE SWITCH
**
- WHEN ORDERING GAS TRAIN ASSEMBLIES, THE GAS PRESSURE SWITCH IS ORDERED SEPARATELY
9
LOCATION OF
HIGH GAS
PRESSURE
SWITCH
*
*
**
F-6
HIGH GAS
PRESSURE SWITCH
PN: GP-122412
REV.
KC1000 BOILER IRI GAS TRAIN
030801PDR
DWN.BYDATE
NTS
SCALE
APPD.DATE
SD-A-584G
NORTHVALE, NJ 07647
INTERNATIONAL, INC.
AERCO
HEATER BOUNDARY
TO AIR-FUEL VALVE ASS'Y
1 1/4" NPT GAS REGULATOR
P/N GP-122415 (NAT. GAS)
123543 (PROPANE)
1 1/2" IRI SSOV
P/N 124137
3/4" NORMALLY OPEN
VENT VALVE
P/N GP-122774
VENT TO ATMOSPHERE
PER ANSI Z223.1 (NFPA54)
SSOV ACTUATOR
W/ P.O.C. SWITCH
P/N 64047
LOW GAS PRESSURE SWITCH
P/N GP-122403
TOP VIEW
SSOV ACTUATOR
W/O P.O.C. SWITCH
P/N 69038
APPENDIX F
F-7
APPENDIX G
G-1
APPENDIX G
G-2
APPENDIX H
CLOSURE SWITCH
PROOF OF
GRN
WHT
60 Hz
120 VAC IN
20 A
NEU
GND
HOT
NC
C
GNH
GND
H
G
N
123456123456789
123456789101112131415
123456789101112
CONTROL BOX CONNECTORS
LOW GAS PRESS. SW.
BLOWER PROOF SW.
SAFETY SHUTOFF VALVE
OVER TEMPERATURE SWITCHES
BLOWER
IGNITOR
TRANSFORMER
WATER LEVEL PROBE
FLAME ROD
AC WIRING BOX
SHELL
TEMP.
SENSOR
GAS FIRED
SYSTEM SCHEMATIC
161613
16-PIN CONNECTOR
19-PIN CONNECTOR
9-PIN CONNECTOR7-PIN CONNECTOR
MANUAL RESET
HIGH GAS PRESS. SW.
BLK
STEPPING
MOTOR
PURGE
POSITION
IGNITION
POSITION
SWITCH
SWITCH
AIR/FUEL VALVE
BLK
YEL
WHT
53
5K
C
B
A
3
RED
GRN
BLU
2
10K
1
(KC 1000)
150
151153
152
153
152
151
150
7
133134
181917 16
14151613
154
AUTO RESET
IGNITION
265200
BLOWER
XFORMER
RELAY
24 VAC
194
193
192
191
190
195
201
206
209
208
210
203
202
204
FUSE
FUS
E
203
206
207
265
205
210
204
202
207
209
200
201
SENSOR
* FFWD
TEMP.
180
* BTU PUMP
183
183
184
182
191
141
184
194
193
137
155
136
154
135
192
138182
140
190
195
172
171
170
169
168
167
166
165
164
163
162
161
149
148
147
146
145
141
149
148
146145
147
181
136
137
209
208
* WATER HEATERS ONLY
6-PIN CONNECTOR
SHEET 1 OF 2
321
TO CONTROL BOX
320
321
322
TO BURNER
GND
AS FOLLOWS UNLESS OTHERWISE SPECIFIED
THIRD ANGLE PROJECTION
ALL DIMENSIONS ARE IN INCHES AND ALL TOLERANCES ARE
XX ±.015 XXX ± .005 FRACTIONS 1/32± ANGLES ±1°
PERPENDICULARITY/PARALLELISM/FLATNESS .003 TOTAL
DIAMETERS ON A COMMON AXIS
ALL DIMENSIONS ARE AFTER FINISH OR PLATING
RELEASED FOR PRODUCTION
THESE DRAWINGS AND/OR SPECIFICATIONS ARE THE PROPERTY OF AERCO INTERNATIONAL, INC. THEY ARE ISSUED IN STRICT CONFIDENCE AND
SHALL NOT BE REPRODUCED, COPIED, OR USED AS THE BASIS FOR MANUFACTURE OR SALE OF APPARATUS WITHOUT PERMISSION OF THE OWNER.
FIM
A
REVISIONS
REV ECO
061302 MD
CK'D
DATEBY
159 PARIS AVE, NORTHVALE, N.J.
061302MD
ORIGINAL
B
DRAWN BY:
DATE:
DATE:CHECKED BY:
DWG. SIZE
MAT'L SPEC.:
TITLE
.005 TOTAL
C
REVDWG. NO.:
B
FYP
ADDED GROUND WIRES 320, 321 & 322
100703 JM
031603
GENERAL CORRECTIONS TO SCHEMATIC
C
GKU
MC
173
1K
INTERNATIONAL INC.
H-1
APPENDIX H
CONTROL BOX CONNECTORS
GAS FIRED BOILER SYSTEM
WIRING SCHEMATIC
161613
1210 1113 14161517 18 19212022 23 24
24-PIN CONNECTOR
241
240242
243
244
245251
246250
247
252254
253
968 75 4 312
212
220
221
211
219
16-PIN CONNECTOR
8546 791 2 31116141513 1210
226
213
214
216
215
7
6
7
5
3
4
6
1
2
OUT
IN
OUT
IN
IN
OUT
FAULT
RELAY
NOT USED
DELAYED INTLK
EXHAUST TEMP
REMOTE INTLK
N.O.
C
4
3
5
1
2
NOT USED
N.C.
C
N.O.
N.C.
RELAY
AUX
12
13
14
11
SENSOR EXCIT. (12 VDC)
BMS (PWM) IN
ANALOG IN
OXYGEN SENSOR IN
FLOW SENSOR IN
CO SENSOR IN
+
-
-
+
-
+
-
+
AUX SENSOR IN
SENSOR COMMON IN
-
+
1
OUTDOOR AIR SENSOR IN
9
8
7
5
3
4
2
6
10
OUT
IN
LONWORKS
A
B
GND
4
1
2
1
-
+
2
2
1
3
3
ANALOG OUT
15
16
SHIELD
B
RS-485 IN
A
1 2437 8659 101211
87654321
87654321121110913 14 15
231
234232
233
238236
235237239
INPUT/OUTPUT BOX
(KC 1000)
+
-
LS2
1
LS1
LS4
LS3
J3J2
J1
SHEET 2 OF 2
AS FOLLOWS UNLESS OTHERWISE SPECIFIED
THIRD ANGLE PROJECTION
ALL DIMENSIONS ARE IN INCHES AND ALL TOLERANCES ARE
XX ±.015 XXX ± .005 FRACTIONS 1/32± ANGLES ±1°
PERPENDICULARITY/PARALLELISM/FLATNESS .003 TOTAL
DIAMETERS ON A COMMON AXIS
ALL DIMENSIONS ARE AFTER FINISH OR PLATING
SEE SHEET ONE
THESE DRAWINGS AND/OR SPECIFICATIONS ARE THE PROPERTY OF AERCO INTERNATIONAL, INC. THEY ARE ISSUED IN STRICT CONFIDENCE AND
SHALL NOT BE REPRODUCED, COPIED, OR USED AS THE BASIS FOR MANUFACTURE OR SALE OF APPARATUS WITHOUT PERMISSION OF THE OWNER.
REVISIONS
REV ECO
CK'D
DATEBY
159 PARIS AVE, NORTHVALE, N.J.
061302MD
ORIGINAL
B
DRAWN BY:
DATE:
DATE:CHECKED BY:
DWG. SIZE
MAT'L SPEC.:
TITLE
.005 TOTAL
C
REVDWG. NO.:
16
INTERNATIONAL INC.
H-2
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.