Vulcan VSC3 Installation Manual

INSTALLATION &
OPERATION MANUAL
VSC SERIES STEAMERS WITH STEAM COIL REGENERATOR
VSC2 VSC3
MODEL VSC2
For additional information on Vulcan-Hart Company or to locate an authorized
parts and service provider in your area, visit our website at www.vulcanhart.com
VULCAN-HART COMPANY, P.O. BOX 696, LOUISVILLE, KY 40201-0696, TEL. (502) 778-2791
FORM 30914 Rev. A (Jan. 2003)
© VULCAN-HART COMPANY, 2003
– 2 –
Installation, Operation and Care of
VSC SERIES STEAMERS
With Steam Coil Regenerator
SAVE THESE INSTRUCTIONS

GENERAL

Model VSC2 and VSC3 Steamers have two or three pressurized steaming compartments for cooking vegetables, fish, eggs and other foods.
The heat exchanger in the cabinet base requires approximately 200 lb per hour of steam at 30 to 50 psi. (Refer to Steam Connection.)
Accessory 12" x 20" stainless steel pans are available, solid or perforated, in 2.5", 4" and 6" depths. Each compartment has a 0 to 60 minute timer. (The buzzer requires manual shutoff.) Doors cannot be
opened during pressurized cooking.
3
An optional steam take-off connection (
/4" NPT) can provide steam for adjacent equipment.
ACCOMMODATION
TOTAL NUMBER OF PANS
MODEL COMPARTMENTS
2.5" Depth 4" Depth 6" Depth 2.5" Depth 4" Depth 6" Depth
VSC2 2 16 8 4
VSC3 3 24 12 6
NUMBER OF PANS PER
COMPARTMENT
842
– 3 –

INSTALLATION

UNPACKING
Immediately after unpacking, check for possible shipping damage. If the steamer is found to be damaged, save the packaging material and contact the carrier within 15 days of delivery.
LOCATION
Before installing, verify that the electrical supply agrees with the specifications on the data plate. Position the steamer in its final location. Check that there are sufficient clearances to service the
controls, for door swings, etc., so there will be no problem in making the required supply and drain connections.
Allow enough space between any other piece of equipment or a wall for service access. Service for the controls for the upper steamer compartments requires access to the upper left side panel. Service on the cabinet base may require access to the left and/or right side panels.
INSTALLATION CODES AND STANDARDS
In the United States, the steamer must be installed in accordance with:
1. State and local codes.
2. National Electrical Code, ANSI/NFPA No. 70 (latest edition). Copies may be obtained from the National Fire Protection Association, Batterymarch Park, Quincy, MA 02269.
3. NFPA Standard # 96 National Fire Protection Association, Batterymarch Park, Quincy, MA 02269.
LEVELING
Using a spirit level or pan of water, level the appliance; then elevate the right side about 1/8" (3 mm) to assure proper compartment drainage. After installation, bolt and anchor the appliance securely to the floor. Seal bolts and rear flanged feet with an NSF approved sealer (Silastic or equivalent).
EXHAUST HOOD
An exhaust system should be located directly above the steamer to exhaust steam and heat generated by the steamer.
Vapor Removal from Cooking Equipment,