TRISTAR MPPT TS-MPPT-60, TS-MPPT-45 Operation Manual

0 (0)

TRISTAR MPPT TM

Solar System Controller

Installation and Operation Manual

Solar Battery Charger

with

TrakStarTM Maximum Power Point Tracking Technology

8 Pheasant Run

Newtown, PA 18940 USA email: info@morningstarcorp.com

www.morningstarcorp.com

Models

MAXIMUM POWER POINT TRACKING

TS-MPPT-60 TS-MPPT-45

TRISTAR MPPT TS-MPPT-60, TS-MPPT-45 Operation Manual

Dimensions in Inches [Millimeters]

Contents

1.0 Important Safety Information

4

2.0 Getting Started

8

2.1

Overview

8

2.2

Versions and Ratings

8

2.3

Features

9

2.4

Regulatory Information

11

2.5

Optional Accessories

12

3.0 Installation

13

3.1

General Information

13

3.2

Controller Installation

15

4.0 Operation

30

4.1 TrakStarTM MPPT Technology

30

4.2

Battery Charging Information

32

4.3

Push button

40

4.4

LED Indications

41

4.5

Protections, Faults & Alarms

43

4.6

Inspection and Maintenance

46

5.0 Networking and Communication

47

5.1

Introduction

47

5.2

Morningstar MeterBusTM

48

5.3

Serial RS-232

49

5.4

EIA-485 (formerly RS-485)

51

5.5

Ethernet

52

6.0

Troubleshooting

55

7.0

Warranty

57

8.0

Specifications

58

1.0 Important Safety Information

Save These Instructions

This manual contains important safety, installation and operating instructions for the

TriStar MPPT solar controller.

The following symbols are used throughout this manual to indicate potentially dangerous conditions or mark important safety instructions:

WARNING:

Indicates a potentially dangerous condition. Use extreme caution when performing this task.

!CAUTION:

Indicates a critical procedure for safe and proper operation of the controller.

NOTE:

Indicates a procedure or function that is important for the safe and proper operation of the controller.

AVERTISSEMENT :

Indique une condition potentiellement dangereuse. Faites preuve d’une prudence extrême lors de la réalisation de cette tâche.

!PRUDENCE :

Indique une procédure critique pour l’utilisation sûre et correcte du contrôleur.

REMARQUE :

Indique une procédure ou fonction importante pour l’utilisation sûre et correcte du contrôleur.

Safety Information

Read all of the instructions and cautions in the manual before beginning installation.

There are no user serviceable parts inside the TriStar MPPT. Do not disassemble or attempt to repair the controller.

Disconnect all sources of power to the controller before installing or adjusting the

TriStar MPPT.

There are no fuses or disconnects inside the TriStar MPPT. Do not attempt to repair.

Install external fuses/breakers as required.

Informations de sécurité

Lisez toutes les instructions et les avertissements figurant dans le manuel avant de commencer l’installation.

Le TriStar MPPT ne contient aucune pièce réparable par l’utilisateur. Ne démontez pas ni ne tentez de réparer le contrôleur.

Déconnectez toutes les sources d’alimentation du contrôleur avant d’installer ou de régler le TriStar MPPT.

Le TriStar MPPT ne contient aucun fusible ou interrupteur. Ne tentez pas de réparer.

Installez des fusibles/coupe-circuits externes selon le besoin.

4

Important Safety Information

Installation Safety Precautions

WARNING:

This unit is not provided with a GFDI device. This charge controller must be used with an external GFDI device as required by the Article 690 of the National Electrical Code for the installation location.

Mount the TriStar MPPT indoors. Prevent exposure to the elements and do not allow water to enter the controller.

Use insulated tools when working with batteries.

Avoid wearing jewelry during installation.

The battery bank must be comprised of batteries of same type, make, and age.

Do not smoke in the vicinity of the battery bank.

Power connections must remain tight to avoid excessive heating from a loose connection.

Use properly sized conductors and circuit interrupters.

The grounding terminal is located in the wiring compartment and is identified by the symbol below.

Ground Symbol

This charge controller is to be connected to DC circuits only. These DC connections are identified by the symbol below.

Direct Current Symbol

TriStar MPPT Operator’s Manual

5

AVERTISSEMENT :

L’appareil n’est pas fourni avec un dispositif GFDI. Ce contrôleur de charge doit être utilisé avec un dispositif GFDI externe tel que requis par l’Article 690 du Code électrique national de l’emplacement de l’installation.

Montez le TriStar MPPT à l’intérieur. Empêchez l’exposition aux éléments et la pénétration d’eau dans le contrôleur.

Utilisez des outils isolés pour travailler avec les batteries.

Évitez le port de bijoux pendant l’installation.

Le groupe de batteries doit être constitué de batteries du même type, fabricant et âge.

Ne fumez pas à proximité du groupe de batteries.

Les connexions d’alimentation doivent rester serrées pour éviter une surchauffe excessive d’une connexion desserrée.

Utilisez des conducteurs et des coupe-circuits de dimensions adaptées.

La borne de mise à la terre se trouve dans le compartiment de câblage et est identifiée par le symbole ci-dessous.

Ce contrôleur de charge ne doit être connecté qu’à des circuits en courant continu. Ces connexions CC sont identifiées par le symbole ci-dessous.

Le contrôleur TriStar MPPT doit être installé par un technicien qualifié conformément aux règlementations électriques du pays où est installé le produit.

Un moyen d’assurer la déconnexion de tous les pôles de l’alimentation doit être fourni. Cette déconnexion doit être incorporée dans le câblage fixe.

À l’aide de la borne de mise à la masse du TriStar MPPT (dans le compartiment de câblage), un moyen permanent et fiable de mise à la terre doit être fourni. La fixation de la mise à la terre doit

être fixée contre tout desserrage accidentel.

Les ouvertures d’entrée au compartiment de câblage du TriStar MPPT doivent être protégées avec un conduit ou une bague.

6

Important Safety Information

About this Manual

This manual provides detailed installation and usage instructions for the TriStar MPPT controller.

Only qualified electricians and technicians who are familiar with solar system design and wiring practices should install the TriStar MPPT. The usage information in this manual is intended for

the system owner/operator.

TriStar MPPT Operator’s Manual

7

2.0Getting Started

2.1Overview

Thank you for selecting the TriStar MPPT solar charge controller with TrakStarTM MPPT Technology. The TriStar MPPT (TS-MPPT) is an advanced maximum power point tracking solar battery charger. The controller features a smart tracking algorithm that finds and maintains operation at the solar array peak power point, maximizing energy harvest.

The TriStar MPPT battery charging process has been optimized for long battery life and improved system performance. Self-diagnostics and electronic error protections prevent damage when installation mistakes or system faults occur. The controller also features eight (8) adjustable settings switches, several communication ports, and terminals for remote battery temperature and voltage measurement.

Please take the time to read this operator’s manual and become familiar with the controller. This will help you make full use of the many advantages the TriStar MPPT can provide for your PV system.

2.2 Versions and Ratings

There are two versions of TriStar MPPT controllers.

TriStar-MPPT-45

maximum 45 amps continuous battery current

12, 24, 36, and 48 Volt dc systems

maximum 150 Volt dc solar input voltage

RS-232 and MeterBusTM communication ports

TriStar-MPPT-60

maximum 60 amps continuous battery current

12, 24, 36, and 48 Volt dc systems

maximum 150 Volt dc solar input voltage

RS-232, EIA-485, MeterBusTM, and Ethernet communication ports

To comply with the National Electric Code (NEC), the current rating of the controller must be equal to or greater than 125% of the solar array’s short circuit current output (Isc). Therefore, the maximum allowable solar array input to the TriStar MPPT controller for compliance with the NEC is:

TS-MPPT-45: 36 amps Isc*

TS-MPPT-60: 48 amps Isc*

*Solar array Isc @ STC

TriStar MPPT Operator’s Manual

8

2.3 Features

The features of the TriStar MPPT are shown in Figure 2-1 below. An explanation of each feature is provided.

Figure 2-1. TriStar MPPT features

TriStar MPPT Operator’s Manual

9

1 - Heatsink

Aluminum heatsink to dissipate controller heat

2 - Mounting Hanger

Keyhole slot for mounting

3 - Settings Switches

Eight (8) settings switches to configure operation of the TriStar MPPT

4 - Battery Positive Terminal (red)

Power connection for Battery (+)

5 - Remote Temperature Sensor Terminals

Connection point for a Morningstar RTS (optional) to remotely monitor battery temperature

6 - LED Indicators

Three state of charge (SOC) LED indicators show charging status and controller faults

7 - MeterBusTM Port

RJ-11 socket for Morningstar MeterBusTM network connections

8 - Battery Voltage Sense Terminals

Terminals for battery voltage input provide accurate battery voltage measurement

9 - Ground Terminal

A chassis ground terminal for system grounding

10 - Ethernet Port

RJ-45 socket for LAN/internet connections (TS-MPPT-60 model only)

11 - Wiring Box with Conduit Knockouts

Termination points for wiring conduit and wire glands

12 - Wiring Box Cover

Sheet metal wiring box cover protects power connections

13 - Serial RS-232 Port

9-pin serial connector (female)

14 - EIA-485 Port

Four (4) position screw terminal for EIA-485 bus connections (TS-MPPT-60 model only)

15 - Solar Positive Terminal (yellow)

Power connection for Solar (+)

16 - Common Negative Power Terminals

Two (2) negative terminals for negative system cable termination

17 - Push-button Switch

Manually reset from an error or fault, also used to start/stop a manual equalization.

10

Getting Started

2.4 Regulatory Information

NOTE:

This section contains important information for safety and regulatory requirements.

The TriStar MPPT controller should be installed by a qualified technician according to the electrical rules of the country in which the product will be installed.

TriStar MPPT controllers comply with the following EMC standards:

Immunity: EN61000-6-2:1999

Emissions: EN55022:1994 with A1 and A3 Class B1

Safety: EN60335-1 and EN60335-2-29 (battery chargers)

A means shall be provided to ensure all pole disconnection from the power supply. This disconnection shall be incorporated in the fixed wiring.

Using the TriStar MPPT grounding terminal (in the wiring compartment), a permanent and reliable means for grounding shall be provided. The clamping of the earthing shall be secured against accidental loosening.

The entry openings to the TriStar MPPT wiring compartment shall be protected with conduit or with a bushing.

FCC requirements:

This device complies with Part 15 of the FCC rules. Operation is subject to the following two conditions: (1) This device may not cause harmful interference, and (2) this device must accept any interference received, including interference that may cause undesired operation.

Changes or modifications not expressly approved by Morningstar for compliance could void the user’s authority to operate the equipment.

Note:

This equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to Part 15 of the FCC rules. These limits are designed to provide reasonable protection against harmful interference in a residential installation. This equipment generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio communication. However, there is no guarantee that interference will not occur in a particular installation. If this equipment does cause harmful interference to radio or television reception, which can be determined by turning the equipment on and off, the user is encouraged to try to correct the interference by one or more of the following measures:

Reorient or relocate the receiving antenna.

Increase the separation between the equipment and receiver.

Connect the equipment into an outlet on a circuit different from that to which the receiver is connected.

Consult the dealer or an experienced radio/TV technician for help.

This Class B digital apparatus complies with Canadian ICES-003.

Cet appareil numerique de la classe B est conforme a la norme NMB-003 du Canada.

TriStar MPPT Operator’s Manual

11

2.5 Optional Accessories

The following accessories are available for purchase separately from your authorized Morningstar dealer.

TriStar Digital Meter 2 / TriStar Remote Meter 2 (Models: TS-M-2 / TS-RM-2)

The TriStar Digital Meter mounts directly on the TS-MPPT controller, replacing the wiring box cover. The TriStar Remote Meter can be flush mounted in a wall or into a standard duplex (2- gang) electrical box. A 2 x 16 character display shows system operating information, error indications, and self-diagnostic information. Four (4) buttons make navigating the meter menus easy.

For systems where multiple TS-MPPT controllers are networked together, one (1) meter can display full system information. The TriStar meters connect to the RJ11 MeterBusTM port on the

TriStar-MPPT.

Meter Hub (HUB-1)

A Morningstar MeterBusTM network with multiple controllers requires a Meter Hub for electrical isolation. The HUB-1 allows communication between MeterBusTM compatible Morningstar products, including the TriStar MPPT controller. DIN rail compatible. See section 5.2 for more details.

Relay Driver (RD-1)

The Relay DriverTM accessory enables the TriStar MPPT to control external devices. Four (4) relay control ports can be configured (in various combinations) to perform the following tasks:

generator control (2-, 3-, and 4-wire configurations)

dry contacts for alarms and other signals

advanced load control

vent fan control

DIN rail compatible or surface mount

For more information on the Relay Driver, visit our website at www.morningstarcorp.com or inquire with your local Morningstar dealer.

EIA-485 / RS-232 Communications Adapter (RSC-1)

Connect one or more TriStar MPPT controllers to a PC or to other serial devices using the RSC-1

EIA-485 adapter. The adapter converts an RS-232 serial interface to EIA-485 compliant signals.

An LED shows network activity and errors. DIN rail compatible.

12

Getting Started

3.0Installation

3.1General Information

The mounting location is important to the performance and operating life of the controller. The environment must be dry and protected from water ingress. If required, the controller may be installed in a ventilated enclosure with sufficient air flow. Never install the TriStar MPPT in a sealed enclosure. The controller may be mounted in an enclosure with sealed batteries, but never

with vented/flooded batteries. Battery fumes from vented batteries will corrode and destroy the

TriStar MPPT circuits.

Multiple TriStars can be installed in parallel on the same battery bank to achieve higher charging current. Additional parallel controllers can also be added in the future. Each TriStar MPPT must have its own solar array.

!

!

CAUTION: Equipment Damage or Risk of Explosion

Never install the TriStar MPPT in an enclosure with vented/flooded batteries. Battery fumes are flammable and will corrode and destroy the TriStar MPPT circuits.

CAUTION: Equipment Damage

When installing the TriStar MPPT in an enclosure, ensure sufficient ventilation. Installation in a sealed enclosure will lead to over-heating and a decreased product lifetime.

!N’installez jamais le TriStar MPPT dans une enceinte avec des batteries à évent/à électrolyte liquide. Les vapeurs des batteries sont inflammables et corroderont et détruiront les circuits du TriStar MPPT.

PRUDENCE : Endommagement de l’équipement

!Assurez une ventilation suffisante en cas d’installation du TriStar MPPT dans une enceinte. L’installation dans une enceinte hermétique entraîne une surchauffe et une réduction de la durée de vie du produit.PRUDENCE : Endommagement de l’équipement ou risque d’explosion

The installation is straightforward, but it is important each step is done correctly and safely. A mistake can lead to dangerous voltage and current levels. Be sure to carefully follow each instruction in this section. Read all instructions first before beginning installation.

The installation instructions are for installation of a negative grounded system. National Electrical

Code (NEC) requirements are noted on occasion for convenience, however the installer should have a complete understanding of NEC and UL requirements for photovoltaic installations.

13

Installation

Recommended Tools:

Wire strippers

Wire cutters

#2 & #0 Phillips screwdriver

slotted screwdrivers

Pliers

Drill

3/32” (2.5 mm) drill bit

Level

hack saw (cutting conduit)

14

Installation

3.2 Controller Installation

Step 1 - Remove the wiring box cover

!Disconnect all power sources to the controller before removing the wiring box cover. Never remove the cover when voltage exists on any of the TriStar MPPT power connections.

PRUDENCE : Risque de décharge électrique

!Déconnectez toutes les sources d’alimentation du contrôleur avant d’enlever le couvercle du boîtier de câblage. Ne retirez jamais le couvercle en présence de tension sur une des connexions d’alimentation du TriStar MPPT.CAUTION: Shock Hazard

Use a #2 Phillips screw driver to remove the four (4) screws that secure the wiring box cover as shown in figure 3-1 below.

Figure 3-1. Remove the wiring box cover.

If a TriStar Digital Meter 2 display is installed, be sure to disconnect the RJ-11 cable.

TriStar MPPT Operator’s Manual

15

Step 2 - Remove the knockouts

Knockouts are provided for routing cables through conduit or wire glands. Table 3-1 below provides the knockout sizes and quantity on the TriStar MPPT wiring box. Knockout locations and dimensions are on the inside front cover.

Quantity

Trade Size

Hole Dimension

8

1/2” or M20

7/8” (22.2 mm)

6

1 “

1 - 23/64 “

(34.5 mm)

4

1 - 1/4 “

1 - 23/32 “

(43.7 mm)

Table 3-1. Knockout sizes

!Always use bushings, connectors, clamp connectors, or wire glands in the knockout openings to protect wiring from sharp edges.

PRUDENCE : Risque de décharge électrique

!Utilisez toujours des bagues, des connecteurs, des raccordements à collets ou des fouloirs dans les ouvertures afin de protéger le câblage des bords coupants.

!CAUTION: Shock Hazard

Never route network cables in the same conduit as the power conductors.

PRUDENCE : Risque de décharge électrique

!N’acheminez jamais les câbles réseau dans le même conduit que les conducteurs d’alimentation.CAUTION: Shock Hazard

Plan the routing of each conductor that will connect to the TriStar MPPT before removing any knockouts. The 1/2” (M20) knockouts are ideal for routing network cables, which must be placed in separate conduit.

16

Installation

Step 3 - Mount to a Vertical Surface

Figure 3-2. Attaching the mounting hanger

1.Attach the mounting hanger to the bottom of the TriStar MPPT with the M6 screw provided as shown in figure 3-2.

2.Place the TriStar MPPT on a vertical surface protected from direct sun, high temperatures, and water. The TriStar MPPT requires at least 6” (150 mm) of clearance above and below and at least 1” (25 mm) on each side for proper air flow as shown in figure 3-3 below.

Figure 3-3. Required mounting clearance for air flow.

3.Place a mark on the mounting surface at the top of the keyhole.

4.Remove the controller and drill a 3/32” (2.5 mm) hole at the drill mark.

5.Insert a #10 screw (included) into the top pilot hole. Do not tighten the screw completely.

Leave a 1/4” (6 mm) gap between the mounting surface and screw head.

TriStar MPPT Operator’s Manual

17

6.Carefully align the keyhole on the TriStar MPPT with the screw head. Slide the TriStar MPPT down over the keyhole.

7.Check for vertical plumb with a level.

8.Mark two (2) mounting hole locations in the wiring box.

9.Remove the controller and drill 3/32” (2.5 mm) holes at the drill marks.

10.Carefully align the keyhole on the TriStar MPPT with the screw head. Slide the TriStar MPPT down over the keyhole.

11.The pre-drilled pilot holes should align with the mounting holes in the wiring box. Secure the controller with two (2) #10 mounting screws.

12.Tighten the keyhole screw.

Step 4 - Adjust Settings Switches

Switch 1: Reserved for Future Use

Settings switch 1 should remain in the “OFF” position.

Mode

Switch 1

Solar Charging

OFF

future use

ON

Switches 2 & 3: System Voltage

Four (4) system voltage configurations are available as shown in the table below:

System Voltage

Switch 2

Switch 3

Auto

OFF

OFF

12

OFF

ON

24

ON

OFF

48

ON

ON

The “auto” setting allows the TriStar MPPT to detect the system voltage automatically on start up.

The test is only performed at start up and the detected system voltage will never change during operation.

Generally, it is best to choose a specific system voltage. The auto detect feature should only be used in situations where the system voltage is unknown ahead of time or in systems where the system voltage may change periodically.

18

Installation

Switches 4, 5, & 6: Battery Charging Settings

It is important to select the battery type that matches the system battery to ensure proper charging and long battery life. Refer to the specifications provided by the battery manufacturer and choose a setting that best fits the recommended charging profile.

Settings

 

Battery

Absorp.

Float

Equalize

Equalize

Switches

 

Type

Stage

Stage

Stage

Interval

4 - 5 - 6

 

 

(Volts)

(Volts)

(Volts)

(Days)

off-off-off

1 - Gel

14.00

13.70

 

 

off-off-on

2 - Sealed*

14.15

13.70

14.40

28

off-on-off

3 - Sealed*

14.30

13.70

14.60

28

off-on-on

4 - AGM/Flooded

14.40

13.70

15.10

28

on-off-off

5

- Flooded

14.60

13.50

15.30

28

on-off-on

6

- Flooded

14.70

13.50

15.40

28

on-on-off

7

- L-16

15.40

13.40

16.00

14

on-on-on

8

- Custom

Custom

Custom

Custom

Custom

* “Sealed” battery type includes gel and AGM batteries

All settings are for 12 Volt nominal systems. Multiply the charge voltage settings by 2 for 24 Volt systems or by 4 for 48 Volt systems. A description of each setting is provided below. See section 4.3 for full details on battery charging and a description of each of the settings in the battery charging table.

Battery Type - The most common battery type associated with the specified charging settings.

Absorption Stage - This stage limits input current so that the Absorption voltage is maintained. As the battery becomes more charged, the charging current continues to taper down until the battery is fully charged.

Float Stage - When the battery is fully charged, the charging voltage will be reduced to the Float voltage setting.

Equalize Stage - During an equalization cycle, the charging voltage will be held constant at the specified voltage setting.

Equalize Interval - The number of days between equalization charges when the controller is con-

figured for automatic equalizations (settings switch 7).

Switch 7: Battery Equalization

Choose between manual and automatic battery equalization charging. In the manual equalization setting, an equalization will only occur when manually started with the pushbutton or when requested from the equalize menu on the TriStar meter. Automatic equalization will occur according to the battery program specified by settings switches 4, 5, & 6 in the previous step.

In both settings (auto and manual), the pushbutton can be used to start and stop battery equalization. If the selected battery charging setting does not have an equalization stage an equalization will never occur, even if requested manually.

TriStar MPPT Operator’s Manual

19

Equalize

Switch 7

manual

OFF

automatic

ON

Switch 8: Ethernet Security

The Ethernet Security switch enables or disables configuration of the TriStar MPPT settings through the Ethernet connection. When switch eight is set to disabled, write commands to the

TriStar MPPT custom memory are not allowed. This a safety feature to prevent unintended changes to custom settings, but it is not a replacement for proper network security.

Configuration via TCP/IP

Switch 8

disabled

OFF

enabled

ON

NOTE:

Adjustment of network settings and custom setpoints is always enabled via the RS-232 and EIA485 connections. The Ethernet Security switch only enables/disables remote configuration via TCP/IP.

!The Ethernet Security settings switch does not block write commands to devices bridged via EIA- 485.CAUTION: Risk of Tampering

REMARQUE :

Le réglage des paramètres de réseau et des points de consignes personnalisés est toujours activé par les connexions RS-232 et EIA-485. Le contacteur de sécurité Ethernet n’active/ désactive que la configuration à distance par TCP/IP.

!Le contacteur des paramètres de sécurité Ethernet ne bloque pas les commandes d’écriture sur les dispositifs reliés par EIA-485.PRUDENCE : Risque de tentative d’altération

20

Installation

Step 5 - Remote Temperature Sensor

The included Remote Temperature Sensor (RTS) is recommended for effective temperature compensated charging. Connect the RTS to the 2-position terminal located between the pushbutton and the LED’s (see figure 2-1). The RTS is supplied with 33 ft (10 m) of 22 AWG (0.34 mm2) cable. There is no polarity, so either wire (+ or -) can be connected to either screw terminal. The

RTS cable may be pulled through conduit along with the power wires. Tighten the connector screws to 5 in-lb (0.56 Nm) of torque. Separate installation instructions are provided inside the

RTS bag.

!CAUTION:

The TriStar MPPT will not temperature compensate charging parameters if the RTS is not used.

CAUTION: Equipment Damage

!Never place the temperature sensor inside a battery cell. Both the RTS and the battery will be damaged.

NOTE:

The RTS cable may be shortened if the full length is not needed. Be sure to reinstall the ferrite choke on the end of the RTS if a length of cable is removed. This choke ensures compliance with electromagnetic emissions standards.

!Le TriStar MPPT ne compense pas la température des paramètres de charges si le RTS n’est pas utilisé.

PRUDENCE : Endommagement de l’équipement

!Ne placez jamais la sonde de température dans un élément de batterie. Le RTS et la batterie seraient endommagés.PRUDENCE :

REMARQUE :

Le câble de RTS peut être raccourci si la totalité de la longueur n’est pas nécessaire. Assurezvous de réinstaller la bobine en ferrite sur l’extrémité du RTS si une longueur de câble est enlevée. Cette bobine assure la conformité avec les normes d’émissions électromagnétiques.

TriStar MPPT Operator’s Manual

21