APPLICATION
These series class 'A' gas valves are used for control and regulation of gaseous fluids in gas power burners, atmospheric gas boilers, melting furnaces, incinerators and other gas consuming appliances.
Models
GV Series solenoid gas valves: threaded:
GVS20-230 (DN20, ¾") GVS50-230 (DN50, 2") GVS25-230 (DN25, 1") GVS65-230 (DN65, 2½") GVS32-230 (DN32, 1¼") GVS80-230 (DN80, 3") GVS40-230 (DN40, 1¾")
flanged: GVF65-230 (DN65, 2½") GVF100-230 (DN100, 4") GVF80-230 (DN80, 3")
All versions are provided with 1/4" bottom plug to accommodate a Closed Position Indication switch accessory (GVCPI).
Duty cycle
Coil suitable for permanent energization.
Opening time
Less than 1 second
Closing time Less than 1 second
Maximum working frequency
20 cycles per minute
GV Series
CLASS ‘A‘ GAS VALVES
DATA SHEET
SPECIFICATIONS
Pipe sizes GVS series Inlet and outlet 20 mm (¾") up to 80 mm (3") internal parallel pipe thread according to ISO 7-1
Pipe sizes GVF series
Flanged connection DN65 (2½"), DN80 (3"), and DN100 (4") according to PN16 ISO 7005-1.
Torsion and bending stress
Pipe connections meet group 2 according to EN161 requirements.
Ambient temperature
-15 °C ... 60 °C
Supply voltage
220 ... 240 Vac, 50/60 Hz The applicable voltage is applied to the solenoid coil via a rectifying circuit.
Maximum operating pressure
200 mbar
Electrical connection
Plug connection according to PG 11.
Coil insulation solenoid valves
Insulation material according to class F.
Operational voltage range
The gas valve will function satisfactorarily between 85% and 110% of rated voltage.
Enclosure
IP 54
3
Capacity in m
DN20 14.8 DN25 16.7 DN32 38.5 DN40 47.1 DN50 66.7 DN65 94.2 DN80 131.0 DN100 225.0
Strainer
A strainer is incorporated in the gas valve.
Approvals
Class 'A' in accordance with EN161 Safety: EN60335 household and industrial EMC standards for industrial and non-industrial appliances Gas Appliance directive (90/396/EEC) Low Voltage directive (73/23/EEC)
/h air at Dp = 2.5 mbar
GV Series Data Sheet TA200888 Issue 1/A 05/09/05 1
EN2C-0053SZ20 R0705
GV Series Data Sheet
INSTALLATION
WARNING
• Take care that installer is a trained experienced service man.
• Turn off gas supply before starting installation.
• Disconnect power supply to prevent electrical shock and/or equipment damage.
Mounting position
The gas valve may be mounted in any position between plus or minus 90 degrees from the vertical.
Mounting location
The distance between the gas valve and the wall/ground, must be at least 30 cm.
Main gas connection threaded valves
• Take care that dirt cannot enter the gas valve during handling.
• Ensure the gas flows in the same direction as the arrow on the housing of the gas valve.
• Use a sound taper fitting with thread according to ISO 7-1 (BS 21, DIN 2999) or a piece of new properly reamed pipe, free from swarf.
• Do not thread or tighten the pipe or pipe fitting too far, otherwise valve distortion and malfunction could result.
• Apply a moderate amount of good quality thread compound to the pipe or fitting only, leaving the two end threads bare; PTFE tape may be used as an alternative.
• In order to tighten the pipe in the valve, do not use the actuator as a lever but use a suitable wrench operating on the wrench boss.
Main gas connection flanged valves
• Take care that dirt cannot enter the gas valve during handling.
• Ensure the gas flows in the same direction as the arrow on the housing of the gas valve.
• Ensure that the inlet and outlet flanges are in line and separated from each other enough to allow the valve to be mounted between them without damaging the gasket.
• Place gasket. If necessary, grease it slightly to keep it in place.
• Mount gas valve between flanges using the bolts for each flange.
Electrical connection
CAUTION
• Switch off power supply before making electrical connections.
• Take care that wiring is in accordance with local regulations.
Use connection cable which can withstand 105 °C ambient.
Wiring
Follow the instructions supplied by the appliance manu­facturer.
ADJUSTMENTS AND FINAL CHECKOUT
WARNING
Adjustments must be made by qualified persons only.
GVS80, GVF65, 80 (see fig. below)
Flow rate adjustment
• Remove the cap screw from top of the coil.
• Place a socket head wrench into the adjustment nut.
• Turn wrench counter-clockwise to increase or clockwise to decrease flow rate.
• Replace cap screw.
CAUTION
To ensure safe valve closure, it is essential that voltage supplied to the terminals is reduced to 0 volt.
Final checkout of the installation
Set appliance in operation after any adjustment and observe several complete cycles to ensure that all burner com­onents function correctly.
WARNING
Tightness test after installation.
• Spray all pipe connections and gaskets with a good quality gas leak detection spray.
• Start the application and check for bubbles. If a leak is found in a pipe connection, remake the joint. A gasket leak can usually be stopped by tightening the mounting screws. Otherwise, replace the gas valve
Manufactured for and on behalf of the Environmental and Combustion Controls Division of Honeywell Technologies Sàrl, Ecublens, Route du Bois 37,Switzerland by its Authorized Representative.
Trend Control Systems Limited reserves the right to revise this publication from time to time and make changes to the content hereof without obligation to notify any person of such revisions or changes.
DISPOSAL
WEEE Directive :
At the end of their useful life the packaging and product should be disposed of by a suitable
recycling centre. Do not dispose of with normal household waste. Do not burn.
Trend Control Systems Limited
P.O. Box 34, Horsham, West Sussex, RH12 2YF, UK. Tel:+44 (0)1403 211888 Fax:+44 (0)1403 241608 www.trend-controls.com
Trend Control Systems USA
6670 185th Avenue NE, Redmond, Washington 98052, USA. Tel: (425)897-3900, Fax: (425)869-8445 www.trend-controls.com
2 GV Series Data Sheet TA200888 Issue 1/A 05/09/05 EN2C-0053SZ20 R0705
Loading...