DVCP Installation
STEP 1
Mark the positions to drill the 4 holes on the bottom plate of the unit.
Figure 1
STEP 2
Drill holes to mount the mounting base.
STEP 4
Install the unit onto the mounting base using pop rivets.
Figure 4
Commissioning (Balancing): The balancing port is positioned on the side
behind the decor strip. The K-factor of the unit is stated on the K-factor
label mounted on one of the side of the balancing port. The k-factor can
also be found on our website in the relevant k-factor guide. See Figure 5
Figure 2
STEP 3
Install mounting base to the floor using anchor screws.
Figure 3
Redefine your comfort zone. ™ | www.titus-hvac.com
Redefine your comfort zone. ™ | www.titus-hvac.com
DVCP Duct Cover Installation (continued)
STEP 1
Mount the duct cover bottom on the top of the unit.
Figure 1
STEP 2
Mount the duct cover support assembly on the top of the unit. Align the
holes on the flange of the duct cover bottom and the duct cover support
assembly and cut the support according to the ceiling height keeping
2” distance between the ceiling and the top of the duct covert support
assembly. Align the duct cover top with the three holes on the support
assembly and rivet the duct cover top with the duct cover support assembly
in 2 places.
Figure 2
Redefine your comfort zone. ™ | www.titus-hvac.com
Install the duct onto the unit. Install the second duct cover top to the duct
cover support assembly enclosing the duct. Assemble both the duct cover
top together using pop rivets.
STEP 4
Assemble all four duct cover support assemblies to the duct cover bottom
using pop rivets.
Redefine your comfort zone. ™ | www.titus-hvac.com
DVCP Duct Cover Installation (continued)
STEP 5
Align the top edge of the duct cover support assembly with the top face
of the extension and install the extension assembly onto the duct cover
support assembly using screws. (Décor strip of the unit should align with
the décor strip of the duct cover assembly)
STEP 6
Place the duct cover on the top of the unit and assemble it to the duct
cover support assembly using screws. Snap the décor strips into the
springs of the duct cover support assemblies.
Figure 5 Figure 6
Redefine your comfort zone. ™ | www.titus-hvac.com
Drill the holes on the bottom plate of the unit and the mounting base.
Install the mounting base into place using screws.
Figure 1
STEP 2
Install wall brackets to the wall using screws and slide the bottom of the
unit into the angle wall brackets.
STEP 3
Install wall bracket to the wall to hold the top of the unit using screws.
Figure 3
Commissioning (Balancing): The balancing port is positioned on the side
behind the decor strip. The K-factor of the unit is stated on the K-factor
label mounted on one of the side of the balancing port. The k-factor can
also be found on our website in the relevant k-factor guide. See Figure 4