TemperZone OPA 2000RKTM01 Installation & Maintenance

OPA 2000RKTM01
Packaged Reverse Cycle R410A Air Cooled Air Conditioner
GENERAL
This OPA 2000RKTM Outdoor Unit must be installed in accordance with all national and local safety codes.
REFRIGERATION SYSTEM General
The OPA 2000 has four independent refrigeration circuits and four compressors
to provide the exibility and economy of
four stage operation, i.e. utilising one or more circuits as conditions vary, plus the advantage of staggered starting.
Each refrigeration system has been charged with HFC-410A (R410A) refrigerant; refer
wiring diagram specication table for
amount. Tapping points are provided to measure discharge and suction operating pressures.
Compressors
The compressors are directional scroll type. The compressor lubricant is polyol ester oil (POE). Note, this oil absorbs
moisture quickly if exposed to open air.
On commissioning, the compressors must be checked for correct rotation (refer Start Up Procedure). A time delay prevents simultaneous starting of the compressors.
ECONOMISER (Option)
If the outdoor air temperature or heat content preferably, is below that of the return air the fresh air damper opens and the return
air damper closes to provide the rst stage
of cooling. A spill air facility in the building may be necessary for when the return air damper is closed. The fresh air damper should return to minimum setting and the return air damper open before compressors are allowed to operate to provide further cooling.
INSTALLATION
Positioning
Refer to dimension diagrams for minimum clearances. If multiple units are to be placed side-by-side then allow at least 2 m between coil faces.
Mounting
The unit should be fastened to a rm at
horizontal base using the holes supplied in the mounting channels.
When the unit is being installed on a roof it is recommended that the unit is installed on a substantial structure with vibration isolating springs beneath the unit. These springs are not supplied with the unit.
Flexible duct connections are recommended
between the supply and return ducts and the unit.
Condensate Drain
The condensate drain should be 'U' trapped outside the unit. The trap should have a vertical height of at least 100 mm. The drain should have a slope of at least 1 in 50 and must not be piped to a level above the unit drain pipe.
OPEN DRAIN
VENT PIPE FOR LONG CONDENSATE DRAIN RUNS
100 mm
APPROX.
100 mm MINIMUM
200 mm
APPROX.
'U' TRAP
Electrical Requirements
Electrical work must be done by a qualied
electrician. The outdoor unit must be wired directly from a distribution board by means of a circuit breaker or H.R.C. fuse, and a mains isolator provided - preferably close to the unit. Note: DO NOT USE REWIRABLE FUSES.
The OPA 2000 is provided with a 24V AC control circuit for a thermostat, on/off switch and/or time clock.
The control transformer 240V primary voltage is used for countries with 230-240V power supply. For countries with supply voltages 200-220V, change the primary voltage on the transformer to 208V.
Standard units are suitable for use with thermostats with either manual Heat/Cool selection or automatic changeover subject to the contact ratings of the thermostats.
A 24 hour power supply to the control circuit is required, otherwise the warranty is void.
CHECK TESTS
1. Check that the shipping block beneath the compressor has been removed and that the compressor is secure on its mounts.
2. Check by hand that all fan motors can turn freely.
3. Check that the air lters have been correctly installed, if tted.
4. Check air diffuser dampers are open if appropriate.
5. Check that the thermostat, or external
24V controller, is correctly wired to the unit and is set at the desired temperature.
6. Check the tightness of all electrical connections and sign the check label.
7. Leave the thermostat, or external 24V
controller, in the off position and close the mains isolating switch. (A four hour delay period is required to allow the crankcase heater to drive any liquid refrigerant out of the compressor oil.)
MINIMUM SLOPE 20 mm PER m (1 IN 50)
Installation & Maintenance
8. Check the supply voltage between each phase and neutral.
START UP PROCEDURE
After the four hour delay for the crankcase
heater has expired, use the supplied
Commissioning Sheet (Form NS 228) to record results when completing the following
‘Start-up’ procedure. A UC6 Service Interface tool is supplied to read, pressures,
superheat and its set-point, compressor amps etc.
1. Select a sensible Fan speed (or Auto Fan mode), operating cycle (cool or heat), and room temperature set point, depending on the time of year, such that the compressor will start and run at a high capacity.
2. Turn ON the thermostat / External
controller. Wait for the compressors to start.
3. Compressors tted are directional. Check
for correct rotation. If rotation is incorrect the compressor will not pump, be noisy, and will draw minimal current. To correct motor rotation, change the phasing at the main power terminal. If changing the phasing, check the indoor air fan then runs in the correct direction also.
3. Measure the current draw on each phase to the compressor motors and measure the current draw of each fan motor.
Check all readings against the specied
values in the wiring diagram.
4. Use the UC6 Service Interface tool to check operating pressures and status. If the UC6 Service Interface is not available,
t gauges and measure the suction and
discharge pressures of both refrigeration circuits.
5. Check that the outdoor air fan motors are running smoothly and drawing less than
the full load amps specied.
6. Test the operation of the reversing valve by running the unit in both the heating and cooling mode.
7. Check the supply air ow at each outlet.
8. Touch up any outdoor unit paintwork damage to prevent corrosion.
SETTING SUPPLY AIR FLOW
Consult OPA 2000 Technical Data pamphlet
at www.temperzone.biz for details of airow/
duct static pressure, if required.
If the indoor air returning to the unit is
regularly expected to be above 50%RH,
then the coil face velocity should be limited to be 2.5 m/s or less (refer Air Handling graph in Technical Data pamphlet).
High humidity levels can occur in tropical or subtropical conditions, and/or when heavily moisture laden fresh air is introduced.
Select a fan speed that avoids water carry-
PROJECTION
over problems.
In a free blow or low resistance application,
beware of exceeding the fan motor's full
load amp limit (refer wiring diagram).
The indoor air fan motor is tted with
a factory set adjustable pitch pulley. Instructions for the adjustment of pulleys is included on the back page of the supplied Commissioning Sheet. One revolution of
adjustment is equal to approx. 7% change in air volume ow rate.
UNIT CONTROLLER (UC6)
The Unit Controller provides system protection functions such as coil frost protection, de-icing, high head pressure and low suction pressure cut-out. It also protects against rapid cycling of the compressor(s) and loss of refrigerant. The UC regulates the superheat of the refrigeration system by controlling the position of an electronic
expansion valve (EEV). Various methods
of head pressure control (or limiting) are employed in temperzone units. The particular method used varies from model to model, but is also handled by the Unit Controller. In combination, these features deliver optimised performance across a wide operating temperature range.
As a result of the UC’s control of these
inter-related functions, the outdoor fans may take some time to start rotating after each
compressor start. They may also run on when the compressor stops. The fans will stop during a de-ice cycle and the speed will vary either smoothly, or in steps, in order to
protect against excessively low or high head
pressure.
Refer to UC6 Controller label on the unit for operation & fault diagnostics information. Many operating status conditions can be deternined, without gauges, simply by using the UC6 Service Interface graphical display supplied with the unit.
MAINTENANCE Monthly
1. Check air lters, if tted, and vacuum or
wash clean as necessary.
2. Check condensate drain for free drainage.
3. Check compressor compartment for oil stains indicating refrigerant leaks.
Three Monthly (or every 1200 hrs of operation)
Check the indoor unit's fan belt tension and adjust if necessary.
Six Monthly
1. Check the tightness of electrical connections.
2. Check the tightness of all fans, motor mountings, pulleys and belt tension.
3. Check suction and discharge operating pressures. (Using the UC6 Service
Interface avoids tting and removing
gauges with consequential refrigerant loss.)
4. Replace indoor air lters (if tted).
5. Check condensate drain for free drainage.
Yearly
1. Check all refrigerant piping for chang
and vibration.
2. Check the operation of electric heaters,
if tted.
3. Check air supply at all diffusers.
4. Check for excessive noise and vibration
and correct as necessary.
5. Check for insulation and duct damage and repair as necessary.
6. Remove lint and dust accumulation from
outdoor coil ns.
7. Touch up any paintwork damage to prevent corrosion.
NOTE
The manufacturer reserves the right to
make changes in specications at any time without notice or obligation. Certied data is
available on request.
This pamphlet replaces the previous issue no. 3735 dated 05/14. Wiring revision F & G.
DIMENSIONS (mm)
OPA 2000RKTM01 – Horizontal Supply & Return Air
1000 MIN. CLEARANCE
FILTER
ACCESS PANEL
FAN
ACCESS
DOOR
U V
ELECTRICAL
ACCESS
DOOR
2430 OA
1000 MIN. CLEARANCE
ELECTRICAL
ACCESS
DOOR
Z
OUTDOOR AIR FLOW
OUTDOOR
AIR FLOW
2000 MIN. CLEARANCE
Y
1000 MIN. CLEARANCE
W
X
RETURN
AIR
DRAIN 11/2" BSP MALE
MOUNTING
SUPPLY
AIR
2278
CENTRES
OPA 2000RKTM
Not to Scale
POINT LOADS (kg)
U V W X Y Z
544 474 415 507 543 587
Net Weight 3070 kg
Note : A 2 m clearance
is required above the
exhaust air fans
630
OPTIONAL WEATHER
HOOD
2435
OVERALL
185
2939 CENTRES
6248 OA
2939 CENTRES
185
955
805
100
560 615
280
1710
225
430
600 MIN.
GROUND
CLEARANCE
OPA 2000RKTM – Wiring Diagram Part 1, of 2
OPA 2000RKTM – Wiring Diagram Part 2, of 2
Options
03/16 Pamphlet No. 3735
© temperzone limited 2016
Loading...