Sterling QVF User Manual

HVAC PRODUCTS
INSTALLATION INSTRUCTIONS & PARTS LIST
FOUR TO TWO-POINT SUSPENSION KIT
ADAPTS FOUR-POINT TO TWO-POINT BALANCED SUSPENSION
FOR PROPELLER UNIT HEATERS (QVF-100/400 & QVEF-100/400)
KIT CONTENTS
1. (2) BRACKETS, 12 GA. C.R.S.
2. (2) BOLTS, 1/2''-13 UNC* x 3'' lg.
3. (4) WASHERS, PLAIN
4. (2) WASHERS, LOCK
5. (2) NUTS, 1/2''-13 UNC
IISK-2
J30-03386
*1/2" diameter, 13 threads per inch (Unified National Course).
A. PRIOR TO INSTALLATION: Prior to adapting any existing four-point suspension, determine that it is secure by inspecting the
existing heater mounting, wood joists, I-beams, bolts washers and clamps.
so as to permit access to the appliance. Clearance between the vertical walls and vertical sides of the appliance shall be no less than 18 inches. Minimum clearance between top of the appliance and the ceiling is 6 inches. Minimum clearance from combustibles to the bottom of the unit is 12 inches. However, this bottom clearance should be maintained at 21 inches for access to the burners. The minimum clearance from combustible to the flue collector is 6''. Adequate clearance must be maintained around air openings into the combustion chamber.
HEATER MOUNTING
STEEL CONSTRUCTION* WOOD CONSTRUCTION JOISTS*
* ALL HANGING HARDWARE & WOOD BY OTHERS.
260 NORTH ELM ST., WESTFIELD, MA 01085 TEL: (413) 564-5540 FAX: (413) 562-5311
HVAC PRODUCTS
www.sterlinghvac.com
Loading...