92167500
76-86 Jeep CJ 4” Lift System
Thank you for choosing Rough Country for all your suspension needs.
Rough Country recommends a certified technician install this system. In addition to these instructions, professional
knowledge of disassemble/reassembly procedures as well as post installation checks must be known. Attempts to install
this system without this knowledge and expertise may jeopardize the integrity and/or operating safety of the vehicle.
Please read instructions before beginning installation. Check the kit hardware against the parts list on this page. Be sure
you have all needed parts and know where they go. Also please review tools needed list and make sure you have
needed tools.
As a general rule, the taller a vehicle is, the easier it will roll. Seat belts and shoulder harnesses should be worn at all
times. Avoid situations where a side rollover may occur.
Generally, braking performance and capability are decreased when larger/heavier tires and wheels are used. Take this
into consideration while driving. Do not add, alter, or fabricate any factory or after-market parts to increase vehicle height
over the intended height of the Rough Country product purchased. Mixing component brands is not recommended.
Rough Country makes no claims regarding lifting devices and excludes any and all implied claims. We will not be responsible for any product that is altered.
If question exist we will be happy to answer any questions concerning the design, function, and correct use of our products.
This suspension system was developed using a 33x12.50x15, tire with factory wheels. Note if wider tires are used, offset
wheels will be required and trimming will be required.
NOTICE TO DEALER AND VEHICLE OWNER
Any vehicle equipped with any Rough Country product should have a “Warning to Driver” decal installed on the inside of
the windshield or on the vehicle’s dash. The decal should act as a constant reminder for whoever is operating the vehicle of its unique handling characteristics.
INSTALLING DEALER - it is your responsibility to install the warning decal and forward these installation instructions on
to the vehicle owner for review. These instructions should be kept in the vehicle for its service
PRODUCT USE INFORMATION
Kit Contents
2– 8019 Front Springs
2– 8020 Rear Springs
1-6606 Power Steering Pitman Arm
1675 Kit Box containing
7-1/2”x2 3/4”x6 1/4” U-bolts
1-1/2” x 3 1/4” x 6 3/4” U-bolts
1 1/2” Bag
2– 3/8” x 4” Center Pins
1-1675Bag1 Spring Bushing Bag
1– 1675Bag2 Sway Bar Bag
1– 1675Bag3 Transfer Spacer Case Bag
2– Sway Bar Links
8114/9114 Shocks
Torque Specs
Size Grade 5 Grade 8
5/16” 15 ft/lbs 20 ft/lbs
3/8” 30 ft/lbs 35 ft/lbs
7/16” 45 ft/lbs 60 ft/lbs
1/2” 65 ft/lbs 90 ft/lbs
9/16” 95 ft/lbs 130 ft/lbs
5/8” 135 ft/lbs 175 ft/lbs
3/4” 185 ft/lbs 280 ft/lbs
Installation Instructions
1. Jack up the front of the vehicle and support the vehicle with jack stands, so that the front wheels are off the ground
2. Remove the front tires/wheels.
3. Remove front shocks
4. Remove front u-bolts and nuts.
5.
Raise axle housing with floor jack until axle is free from spring. Support axle with floor jack.
6. Remove spring-eye bolts (Retain stock bolts for reuse) from the front springs, and remove springs.
7. Locate supplied bushings and sleeves. Grease bushings and insta ll in #8019. Install new springs, part # 8019 for the
front using factory hardware.
8. Lower axle housing until center pin is located in spring pad.
9. Do not tighten spring bolts until the weight of the vehicle is being supported by the springs. Over-tightening the
spring eye bushings can result in a rough ride and premature bushing failure. Tighten only to make the poly bushings slightly swell.
10. Install new u-bolts and hardware. Tighten u-bolts, alternating from bolt to bolt. Torque ½” u-bolts to 60 ft./lbs. and
9/16” u-bolts to 87 ft. /lbs.
11. On the front of the vehicle assemble new sway bar links with poly bushings and sleeves. The factory hardware will
not be reused on the upper sway bar mount. Use the supplied 12mm x 1.75 x 80mm bolts, washers a nd nuts for the
upper sway bar mount and reuse the lower factory hardware. See Photo 1.
Photo 1 Photo 2
12. Lower vehicle to the ground and install front shocks.
13.
After the tires and wheels have been installed and the vehicle has been lowered to the ground the transfer case can
be lowered.
14. With a floor jack supporting the transfer case skid plate loosen but do not remove the bolts that secure it to the frame
rail. On the opposite side of the vehicle remove the bolts that secure it to the frame rail.
15. nstall the transfer case spacer in between the transfer case skid plate and the frame rail and install the 3/8” bolts and
washers. See Photo 2
.