Description/Application
Option DH1, Draft Booster Relay Package, includes the required relay,
hardware, and wires to provide proper operation of a field-supplied
draft booster on a Reznor
The option package (P/N 110780) includes:
Qty P/N Description
1 103318 RBM Relay, Essex #134-50203-301
2 38529 Sheet metal screws, #8 x 1/2" long
1 110774 White Wire Assembly consisting of 6" long,
1 110775 Orange Wire Assembly consisting of 5" long,
1 110777 Black Wire Assembly consisting of 7" long,
1 110779 Red Wire Assembly consisting of 4" long,
1 111066 Yellow Wire Assembly consisting of 5" long, 14-
1 16354 Wire Nut #73B
®
oil-fired unit heater.
18-gauge, 105°C white wire with one terminal
18-gauge, 105°C orange wire with one terminal
14-gauge, 105°C black wire with one terminal
14-gauge, 105°C red wire with one terminal
gauge, 105°C yellow wire with one terminal
5. Following the appropriate wiring diagram below and the wiring
diagram on the heater, make the proper wire connections. Use the
wire nut to attach the 14-gauge yellow wire to the draft booster field
wiring. The field-supplied draft booster must include proof of flow
contacts (exhaust flow switch). This switch must be capable of
handling a 7.5 amp inductive load. Wire these contacts according to
the diagram on the heater.
WARNING: Orange jumper wire must be
removed. Models RA/RAD, orange wire is between
Terminals 5 and 6; Models OH/OB, orange wire
is between Terminals 6 and 7.
Installation Instructions
These instructions are designed to assist a qualified electrician in installing this draft booster relay. All electrical wiring and connections,
including electrical grounding, MUST be in accordance with the National Electric Code ANSI/NFPA No. 70 (latest edition) or, in Canada,
with the Canadian Electrical Code, Part 1-C.S.A. Standard C22.1 In
addition, the installation must comply with local ordinances.
1. Assemble the relay and wires. The wire connections on the relay are
numbered. Push the terminals onto the proper connections.
Terminal No. 1- 6", 18 gauge white wire.
Terminal No. 2- 7", 14 gauge black wire.
Terminal No. 3- 5", 18 gauge orange wire.
Terminal No. 4- 5", 14 gauge yellow wire.
Terminal No. 5- 4", 14 gauge red wire.
2. Turn off the electrical power to the unit by putting the disconnect
switch in the “off” position.
3. Open the main electrical box on the end of the heater. Above the
terminal blocks, there is provision made to add a row of relays in the
junction box. The draft booster relay is designed for the extreme left
position. Using the two screws provided, fasten the relay in this
position.
4. Above the draft booster relay, remove one of the hole plugs in the
top of the electrical box. Use this for entry of the draft booster
wiring.
800-695-1901 www.RezSpec.com
©2014 Reznor, LLC. All rights reserved. Printed in the U.S.A.
Trademark Note: Reznor
0514 POD OG Form I-OIL-DBR (Version 0.1)
®
is registered in the United States and other countries.
6. Close the electrical box. Turn on the power by putting the disconnect switch in the “on” position.
7. Check for proper operation of the draft booster and heater.
Sequence of Operation:
Start-Up
1) Thermostat calls for heat, energizing ignition controller.
2) Ignition controller activates draft booster relay which energizes draft
booster motor.
3) Exhaust flow switch closes, activating the burner motor and fuel
valve.
4) Heater fires and operates until thermostat is satisfied.
Shutdown
1) Thermostat shuts off power to ignition controller.
2) Draft booster motor and fan/ blower continue to operate until fan
control is cooled (approximately 2-1/2 minutes).
Form RZ-NA-I-OIL-DBR, Mfg #110781, Page 1