Kit 020003211 Installation (230 & 115 VAC 50/60 HZ)
Kit 020003211 Contents
Qty Description Part Number
1 Mot or/Pu mp Cir culat or MAG 215 020003095
1 Plate Adapter Mounting 020003094
1 Harness Motor Pump 230V MAG 215 020003207
1 Harness Motor Pump 115V MAG 215 020003246
1 Boot Motor/Pump Front MAG 215 020003212
1 Boot Motor/Pump Rear MAG 215 020003214
4 Screw #12-24 X ½” Zinc Plated 020003203
4 Nut #12-24 Hex Zinc Plated 020003202
4 Washer Split Lock #12 Zinc Plated 020003204
1 Bolt Carriage ¼ - 20 X ½ Plt Stl 00855408
1 Nut ¼ - 20 Hex W/Lock 00850700
020003427
5/12
Instructions
Must first verify if circulating motor is 230V or 115V. Failure
to do so may cause electrical shock or injury!
1. Disconnect Power to chiller and turn off water and CO2 supply.
2. You will need to access the inside of chiller by removing the top, front and side panel screws
(See Figure 1) to access the control board. Do not discard the screws removed; they will be
needed to put the panels back on in Step 9.
3. Depressurize system and bleed water from lines.
4. Disconnect wires from their connections in the control box. Route wires through the grommet.
5. Remove foam boots from pump head then the circulation input & output tubing by
unscrewing fittings (See Figure 4).
6. Remove bolt and nut securing pump motor to motor shelf (See Figure 2).
7. Slide pump out of motor brace and lift pump from motor deck.
8. Installation of MAG 215 Circulator Motor/Pump(s):
A.Attach adapter plate to bottom of pump with provided screws, nuts and washers
(See Figure 5).
B.Slide motor/pump into the motor brace on pump deck and secure with provided carriage
bolt and nut.
C.Connect circulation input & output tubing by screwing fittings onto pump (See Figure 4).
NOTE: Verify that the input & output tubing are on the correct pump fittings.
D.Peel off adhesive from provided foam boots and enclose the pump head(s).
E.Attach correct voltage harness to motor connector. Then route it through the
grommet and connect harness leads to the appropriate connections in the control
box (See Figure 3).
NOTE: Verify using correct voltage motor harness, labeled 230V or 115V.
9. Install the front and side panels with the screws that were removed in Step 2.
10. Reconnect power to the chiller and turn on water and CO
2 supply.