Information and illustrations cover the McQuay International products at the time of publication and we reserve the right to make
®™ The following are trademarks or registered trademarks of their respective companies: BACnet from ASHRAE; Modbus from Gould, Inc;
L
ONMARK and LONWORKS from Echelon Corporation; and MicroTech II from McQuay International; Victaulic from Victaulic Company;
changes in design and construction at anytime without notice.
¤2005 McQuay International
2 Centrifugal Chillers IMM WMC-1
Introduction
General Description
The McQuay Model WMC Centrifugal Water Chiller is a complete, self-contained, automatically
controlled, fluid-chilling unit featuring dual, oil-free, magnetic bearing compressors. Each unit is
completely assembled and factory tested before shipment.
The WMC chillers are equipped with two compressors operating in parallel with a single evaporator
and single condenser.
The chillers use refrigerant R-134a that operates at a positive pressure over the entire operation
range, so no purge system is required.
The controls are pre-wired, adjusted and tested. Only normal field connections such as water piping,
relief valve piping, electric power and control interlocks are required, thereby simplifying
installation and increasing reliability. Necessary equipment protection and operating controls are
included.
All McQuay centrifugal chillers are factory-tested prior to shipment and must be commissioned by a
factory-trained McQuay service technician. Failure to follow this startup procedure can affect the
equipment warranty.
The standard limited warranty on this equipment covers parts that prove defective in material or
workmanship. Specific details of this warranty can be found in the warranty statement furnished
with the equipment.
Cooling towers used with McQuay centrifugal chillers are normally selected for condenser water
inlet water temperatures between 75°F and 90°F (24°C and 32°C). Lower entering water
temperatures are desirable from the standpoint of energy reduction, but a minimum does exist. For
recommendations on optimum entering water temperature and cooling tower fan control, consult the
“Condenser Water” section on page 30.
Nomenclature
W = Water-cooled
M = Magnetic B earings
Centrifugal Compressor
W
M C 035 T
Twin Compressors
Impeller Diameter
3.5 inches
IMM WMC-1 Centrifugal Chillers 3
Installation
k
t
Receiving and Handling
The unit should be inspected immediately after receipt for possible damage.
All McQuay centrifugal water chillers are shipped FOB factory and all claims for handling and
shipping damage are the responsibility of the consignee.
On units with factory-installed insulation, the insulation is removed from the vessel lifting hole
(also used for transportation tie-downs) locations and are shipped loose. They should be glued in
place after the unit is finally placed. Neoprene vibration pads are also shipped loose. Check that
these items have been delivered with the unit. They are usually placed in a control panel.
If so equipped, leave the shipping skid in place until the unit is in its final position. This will aid
in handling the equipment.
Extreme care must be used when rigging the unit to prevent damage to the control panels and
refrigerant piping. See the certified dimension drawings included in the job submittal for the
center of gravity of the unit. If the drawings are not available, consult the local McQuay sales
office for assistance.
The unit can be lifted by fastening the rigging hooks to the four corners of the unit where the
rigging eyes are located (see Figure 1). Spreader bars must be used between the rigging lines to
prevent damage to the control panels, piping and electrical panels.
Figure 1, WMC Major Component Locations
Control Panel
Operator Interface
Touch Screen, OITS
Evaporator Relief Valve
Combined
Discharge Chec
Compressor #1
Suction Shutoff Valve
Compressor #2
Rigging Holes
Each Corner
Outle
Evaporator
Outlet
Inlet
Condenser
Condenser
Relief Valves
Optional Single-Point
Power Block or
Disconnect Switch
Electronic Expansion Valve
4 Centrifugal Chillers IMM WMC-1
Circuit #2
Power Panel
Circuit #1
Power Panel
Location and Mounting
Clearance
The unit must be mounted on a level concrete or steel base and must be located to provide service
clearance at one end of the unit for possible removal of evaporator and/or condenser tubes. Evaporator
and condenser tubes are rolled into the tube sheets to permit replacement if necessary. The length of the
vessel should be allowed at one end. Doors or removable wall sections can be utilized for tube clearance.
Clearance at all other points, including the top, is 3 feet (1 meter). The U.S. National Electric Code
(NEC) can require more clearance in and around electrical components (4-feet in front of electrical
panels) and must be checked.
Vibration Pads
The shipped-loose neoprene vibration pads should be located under the corners of the unit (unless the job
specifications state otherwise). They are installed to be flush with the sides and outside edge of the feet.
Mounting
Make sure that the floor or structural support is adequate to support the full operating weight of the
complete unit.
It is not necessary to bolt the unit to the mounting slab or framework; but should this be desirable, 1 1/8"
(28.5 mm) mounting holes are provided in the unit support at the four corners.
Note: Units are shipped with refrigerant valves closed to isolate the refrigerant in the unit
condenser. Valves must remain closed until start-up by the McQuay technician.
Nameplates
There are several identification nameplates on the chiller:
• The unit nameplate is located on the Unit Control Panel. It has a Model No. XXXX and Serial No.
XXXX. Both are unique to the unit and will identify it. These numbers should be used to identify
the unit for service, parts, or warranty questions. This plate also has the unit refrigerant charge.
• Vessel nameplates are located on the evaporator and condenser. Along with other information, they
have a National Board Number (NB) and a serial number, either of which identify the vessel (but
not the entire unit).
Water Piping
Evaporator and Condenser Water Piping
All evaporators and condensers come standard with groove-type nozzles for Victaulic couplings (also
suitable for welding), or optional flange connections. The installing contractor must provide matching
mechanical connections of the size and type required.
CAUTION
Freeze Notice: Neither the evaporator nor the condenser is self-draining;
both must be blown out to help avoid damage from freezing.
The piping should include thermometers at the inlet and outlet connections and air vents at the high points.
The water heads can be interchanged (end for end) so that the water connections can be made at either end of
the unit. If this is done, new head gaskets must be used and control sensors relocated.
In cases where the water pump noise can be objectionable, vibration isolation sections are recommended at
both the inlet and outlet of the pump. In most cases, it will not be necessary to provide vibration eliminator
sections in the condenser inlet and outlet water lines. But they can be required where noise and vibration are
critical.
IMM WMC-1 Centrifugal Chillers 5
Important Notes on Welding
If welding is to be performed on the mechanical or flange connections:
1. Remove the solid-state temperature sensor, thermostat bulbs and optional nozzle mounted
flow switches (if so equipped) from the wells to prevent damage to those components.
2. Properly ground the unit or severe damage to the MicroTech II unit controller can occur.
Welding should never be performed on a vessel shell or tube sheet, as this will revoke the ASME
certification.
Water pressure gauge connection taps and gauges must be provided in the field piping at the inlet
and outlet connections of both vessels for measuring the water pressure drop. The pressure drops
and flow rates for the various evaporators and condensers are job specific and the original job
documentation can be consulted for this information. Refer to the nameplate on the vessel shell
for identification.
Connections
Be sure that water inlet and outlet connections match certified drawings and stenciled nozzle
markings. The condenser is connected with the coolest water entering at the bottom connection
to maximize subcooling. The evaporator outlet is on the side of the unit with the two power
panels, regardless of which end the connections are on. See Figure 1.
CAUTION
When common piping is used for both building heating and cooling modes, care must
be taken to provide that water flowing through the evaporator cannot exceed 110°F
which can cause the relief valve to discharge refrigerant or damage controls.
Piping must be supported to eliminate weight and strain on the fittings and connections. Chilled
water piping must be adequately insulated. A cleanable 20-mesh water strainer must be installed
in both water inlet lines. Sufficient shutoff valves must be installed to permit draining the water
from the evaporator or condenser without draining the
complete system.
Figure 2, Unit-Mounted Flow Switch
Flow Switch
Chiller units must be provided with flow switches for
the evaporator and condenser. McQuay furnishes
factory-installed and wired, thermal-type flow
switches as standard equipment on WMC chillers.
They prevent the unit from starting without sufficient
water flow through the vessels. They also serve to
shut down the unit in the event that water flow is
interrupted to guard against evaporator freeze-up or
excessive discharge pressure.
Additionally, for a higher margin of protection,
normally open auxiliary contacts in the pump starters
can be wired in series with the flow switches as shown in the Field Wiring Diagram.
Cooling Towers
The condenser water flow rate must be checked to be sure that it conforms to the system design.
A tower bypass valve is required to control the minimum condenser entering temperature. Unless
the system and chiller unit are specifically designed for them, condenser bypass or variable
condenser flow is not recommended, since low condenser flow rates can cause unstable operation
and excessive tube fouling.
6 Centrifugal Chillers IMM WMC-1
Figure 3, Bypass, Mild Weather Operation
Bypass, Cold Weather Operation
Low Condenser Water Temperature Operation
When ambient wet bulb temperature are lower than design, the entering condenser water
temperature can be allowed to fall to improve chiller performance. This is especially true of an
advanced design such as the McQuay WMC that features variable compressor speed.
It is an engineering fact that as the compressor discharge pressure is reduced the amount of power
to pump a given amount of gas also is reduced. The reduction can result in significant energy
savings.
However, as with most centrifugal chiller applications, a tower bypass valve must be installed.
Figure 16 illustrates two temperature actuated tower bypass arrangements. The “Cold Weather”
scheme provides better startup under cold ambient air temperature conditions. The check valve
may be required to prevent entraining air at the pump inlet.
Minimum Condenser Water Temperatur e
The McQuay WMC centrifugal chiller will start and run with 55°F (12.8°C) entering condenser
water temperature.
It is highly recommended that the condenser water pumps cycle on and off with the unit to reduce
the possibility of refrigerant migration to the condenser. See on page 19 for wiring details.
CAUTION
Tower water treatment is essential for continued efficient and reliable unit operation.
If not available in-house, competent water treatment specialists should be contracted.
Field Insulation
If the optional factory-installation of thermal insulation is not ordered, insulation should be field
installed to reduce heat loss and prevent condensation from forming. Insulation should cover the
evaporator barrel, tube sheet, and water heads, plus the suction line to the compressor flange and
the compressor end bell opposite the suction connection.
The optional factory-installed insulation of cold surfaces includes the evaporator and nonconnection water head, suction piping, compressor inlet, and motor housing.
Insulation is UL recognized (File # E55475). It is 3/4" thick ABS/PVC flexible foam with a skin.
The K factor is 0.28 at 75°F. Sheet insulation is fitted and cemented in place forming a vapor
barrier, then painted with a resilient epoxy finish that resists cracking.
The insulation complies to, or has been tested in accordance, with the following:
ASTM-C-177 ASTM-C-534 Type 2 UL 94-5V
ASTM-D-1056-91-2C1 ASTM E 84 MEA 186-86-M Vol. N
CAN/ULC S102-M88
IMM WMC-1 Centrifugal Chillers 7
Physical Data and Weights
Evaporator
Refrigerant-side design pressure is 200 psi (1380 kPa). Water-side is 150 psi (1034 kPa).
In the event insulation is to be field-installed, none of the cold surfaces identified above will be
factory insulated. Approximate total square footage of insulation surface required for individual
packaged chillers is tabulated by evaporator code and can be found below.
1. Refrigerant charge is for the entire unit and is approximate since the actual charge will depend on other variables.
Actual charge will be shown on the unit nameplate.
2. Water capacity is based on s tandard t ube configuration and standard dished heads.
Maximum
Refrigerant Charge
lb. (kg)
Evaporator
Water
Capacity, gal (L)
Insulation
Area
sq. ft. (m
Vessel
2
)
Weight
lb. (kg)
Condenser
With positive pressure systems, the pressure variance with temperature is always predictable, and
the vessel design and pressure relief protection are based upon pure refrigerant characteristics.
R-134a requires ASME vessel design, inspection and testing and uses spring-loaded pressure
relief valves. When an over pressure condition occurs, spring-loaded relief valves purge only that
refrigerant required to reduce system pressure to their set pressure, and then close.
Refrigerant-side design pressure is 200 psi (1380 kPa). Water-side design is 150 psi (1034 kPa).
1. Condenser pumpdown capacity based on 90% full at 90°F.
2. Water capacity based on standard conf i guration and standard heads and can be less with lower tube counts.
3. See Relief Valves section for additional information.
Maximum
Pumpdown
Capacity lb. (kg)
Water Capacity
gal. (L)
Vessel Weight
lb. (kg)
Number of
Relief Valves
Pumpdown
To facilitate compressor service, all McQuay centrifugal chillers are designed to permit
pumpdown and isolation of the entire refrigerant charge in the unit’s condenser. Model WMC
chillers are equipped with suction and discharge shutoff valves and the refrigerant charge can also
be pumped down into the evaporator.
1. The dimension drawing above is for standard production units. Certain early production units will have a different control panel
arrangement and a greater height dimension.
2. Left-hand connections shown. Right-hand connections are available for either vessel.
1. The dimension drawing above is for standard production units. Certain early production units will have a different
control panel arrangement and a greater height dimension.
2. Left-hand connections shown. Right-hand connections are available for either vessel.
3. For right-hand evaporator, the inlet and outlet are reversed. That is, the inlet is on the right end and looking at the head,
the connection is on the left side.
As a safety precaution and to meet code requirements,
each chiller is equipped with pressure relief valves
located on the condenser and evaporator for the purpose
of relieving excessive refrigerant pressure (caused by
equipment malfunction, fire, etc.) to the atmosphere.
Most codes require that relief valves be vented to the
outside of a building, and this is a desirable practice for
all installations. Relief piping connections to the relief
valves must have flexible connectors.
Note: Remove plastic shipping plug s (if installed)
from the inside of t he valves prior to making pipe
connections. Whenever vent piping is installed,
the lines must be run in accordance with local
code requirements; where local codes do not
apply, the latest issue of ANSI/ASHRAE Standard
15 code recommendations must be followed.
Condensers have two relief valves as a set with a threeway valve separating the two valves. One valve
remains active at all times and the second valve acts as a standby.
Figure 9, Condenser 3-Way Relief Valve
Refrigerant Vent Piping
Relief valve connection sizes are one-inch FPT and are in the quantity shown in Table 1 and Table
2 on page 8. Twin relief valves mounted on a transfer valve are used on the condenser so that one
relief valve can be shut off and removed, leaving the other in operation. Only one of the two is in
operation at any time.
Vent piping is sized for only one valve of the set (but connected to both) since only one can be in
operation at a time. In no case would a combination of evaporator and condenser sizes require
more refrigerant than the pumpdown capacity of the condenser. Condenser pumpdown capacities
are based on the current ANSI/ASHRAE Standard 15 that recommend 90% full at 90°F (32°C). To
convert values to the older ARI standard, multiply pumpdown capacity by 0.888.
Sizing Vent Piping (ASHRAE Method)
Relief valve pipe sizing is based on the discharge capacity for the given evaporator or condenser
and the length of piping to be run. Discharge capacity for R-134a vessels is calculated using a
complicated equation that accounts for equivalent length of pipe, valve capacity, Moody friction
IMM WMC-1 Centrifugal Chillers 13
factor, pipe ID, outlet pressure and back pressure. The formula, and tables derived from it, are
contained in ASHRAE Standard 15-2001.
The McQuay WMC centrifugal units have a relief valve setting of 200 psi.
Using the ASHRAE formula and basing calculations on the 225 psi design yields a conservative
pipe size, which is summarized in Table 3. The table gives the pipe size required per relief valve.
When valves are piped together, the common piping must follow the rules set out in the following
paragraph on common piping.
NOTE: A 1-inch pipe is too small to handle these valves. A pipe increaser must always be installed at the valve outlet.
Common Piping
According to ASHRAE Standard 15, the pipe size cannot be less than the relief valve outlet size.
The discharge from more than one relief valve can be run into a common header, the area of which
cannot be less than the sum of the areas of the connected pipes. For further details, refer to
ASHRAE Standard 15. The common header can be calculated by the formula:
The above information is a guide only. Consult local codes and/or latest version of ASHRAE
Standard 15 for sizing data.
Electrical
Wiring, fuse and wire size must be in accordance with the National Electric Code (NEC).
Important: The voltage to these units must be within ±10% of nameplate voltage, and the voltage
unbalance between phases must not
exceed 2%. Since a 2% voltage
unbalance will cause a current
unbalance of 6 to 10 times the voltage
unbalance per NEMA MG-1, 1998
Standard, it is most important that the
unbalance between phases be kept at a
minimum.
Power Wiring
The standard power wiring connection
to WMC chillers is multi-point, i.e. a
separate power supply to each circuit’s
terminal box. Single-point connection
to a terminal box, located under the
low voltage control panel, is available
as an option, in which case the
individual circuit breakers for each
circuit are retained. The single point
connection is to a standard power block
or optional single unit disconnect
switch.
Figure 10, Electrical Panel, Mul t i-Point
Connection
(3) Controller
Transformers
120V-24V
Control Power
Transformer
480V-120V
Power
Entry
Incoming
Lugs
Circuit
Breaker
Line
Reactors
14 Centrifugal Chillers IMM WMC-1
The electrical panel (as shown to the right) contains the circuit breaker/ disconnect (standard on
both multi-point connection and single-point connection), a line reactor, and a radio frequency (RF)
filter. The circuit breakers provide compressor overload protection.
Proper phase sequence to the unit is not required as far as the unit operation is concerned. Correct
motor rotation is established by the chiller control system regardless of the connected phase
sequence.
WARNING
Qualified and licensed electricians must perform wiring. Shock hazard exists.
The RLA for use in the following tables is obtained by the selection of a specific unit by McQuay.
When shipped, a unit will bear the specific RLA, stamped on the nameplate, for the selected
operating conditions.
Electrical Data
Table 4, Multi-Point Connection, Each Circuit – 1 Compressor per Ci rcuit
(Per Compressor)
52 to 55 Amps 72 60 65 to 69 3 4 GA 110 Amps
56 to 65 Amps 72 60 70 to 82 3 4 GA 125 Amps
68 to 77 Amps 94 50, 60 85 to 97 3 3 GA 150 Amps
78 to 85 Amps 94 50, 60 98 to 107 3 2 GA 175 Amps
89 to 91 Amps 124 50, 60 112 to 114 3 2 GA 200 Amps
92 to 103 Amps 124 50, 60 115 to 129 3 1 GA 200 Amps
104 to 110 Amps 124 50, 60 130 to 138 3 1/0 225 Amps
111 to 113 Amps 124 50, 60 139 to 142 3 1/0 250 Amps
LRA Hz
Minimum Circuit
Ampacity (MCA)
Field Wire RLA
Quantity Wire GA
Max Fuse
Size
Table 5, Single Point Connection, Total Unit – 2 Compressors per Unit
Per Compressor Per Unit
(Per Compressor)
52 to 53 Amps 72 50 117 to 120 3 1 GA 150 Amps
54 to 57 Amps 72 50 122 to 129 3 1 GA 175 Amps
58 to 61 Amps 72 50 131 to 138 3 1/0 175 Amps
62 to 65 Amps 72 50 140 to 147 3 1/0 200 Amps
68 to 69 Amps 94 50, 60 153 to 156 3 2/0 200 Amps
70 to 76 Amps 94 50, 60 158 to 171 3 2/0 225 Amps
77 to 85 Amps 94 50, 60 174 to 192 3 3/0 250 Amps
89 to 92 Amps 124 50, 60 201 to 207 3 4/0 250 Amps
93 to 102 Amps 124 50, 60 210 to 230 3 4/0 300 Amps
103 to 107 Amps 124 50, 60 232 to 241 3 250 300 Amps
108 to 113 Amps 124 50, 60 243 to 255 3 250 350 Amps
LRA Hz
Minimum Circuit
Ampacity (MCA)
Field Wire RLA
Quantity Wire GA
Max Fuse
Size
IMM WMC-1 Centrifugal Chillers 15
Table 6, Single Point and Multi-point Connect i on
RLA
(Per Compressor)
Type of Connection Disconnect Switch Only Power Block Disconnect Switch
52 to 65 Amps 100 Amps
68 to 85 Amps 150 Amps 335 Amps 400 Amps
89 to 113 Amps 175 Amps
See Note 1 See Note 2 See Note 2
NOTES 1: Disconnect Switch will also be a Circuit Breaker.
2: Circuit Breaker in each circuit after Power Block or Molded Case Disconnect Switch.
3: A high short circuit current rated (HSCCR) panel rated at 65 kA is an option.
Connections to terminals must be made with copper lugs and copper wire.
Multi-Point Connection Single Point Connection
CAUTION
Care must be taken when attaching leads to compressor terminals.
Control Wiring
The control circuit on the McQuay centrifugal packaged chiller is designed for 115-volts. Control
power is supplied from a factory-wired transformer located in the electrical box.
Use with On-Site Generators
WMC chillers have their total tonnage divided between two compressors that start sequentially and
they are operated with variable frequency drives. These features make WMC chillers especially
appropriate for use in applications where they may be required to run with on-site electrical
generators. This is particularly true when the generators are used for temporary power when the
utility power is lost.
Generator Sizing: Gas and diesel generators are sensitive to the compressor’s locked-rotor
characteristics when the chillers start up. Use the electrical data supplied with the performance
output sheet, obtained from the McQuay sales office, for generator sizing purposes. The chiller
data sheet will show the RLA, which is for both compressors. Refer to Table 4or Table 5 on the
previous page to determine the LRA, based on the RLA. It is important to size the generator to
handle the LRA at start up.
Starting/Stopping Procedure: The stopping of the chiller in the event of a power failure should be
uneventful. The chiller will sense a loss of voltage and the compressors will stop, coasting down
using power generated from their dynamic braking to maintain the bearing magnetic field. The stop
signal will initiate a three-minute stop-to-start timer, effectively preventing compressor restart for
three minutes. The timer is adjustable from three to fifteen minutes, but the recommended, and
default value, is three minutes. This interval allows the generator sufficient time to get up to speed
and stabilize. The chiller will restart automatically when the start-to-start timer expires.
Transfer Back to Grid Power: Proper transfer from stand-by generator power back to grid power
is essential to avoid compressor damage.
CAUTION
Stop the chiller before transferring supply power from the generator back
to the utility power grid. Transferring power while the chiller is running can
cause severe compressor damage.
16 Centrifugal Chillers IMM WMC-1
The necessary procedure for reconnecting power from the generator back to the utility grid is show
below. These procedures are not peculiar to McQuay units only, but should be observed for any
chiller manufacturer.
1. Set the generator to always run five minutes longer than the unit start-to-start timer, which
could be set from 15 to 60 minutes. The actual setting can be viewed on the operator interface
panel on the Setpoint/Timer screen.
2. Configure the transfer switch, provided with the generator, to automatically shut down the
chiller before transfer is made. The automatic shut-off function can be accomplished through a
BAS interface or with the “remote on/off” wiring connection shown in Figure 11. A start signal
can be given anytime after the stop signal since the three-minute start-to-start timer will be in
effect.
Chiller Control Power: For proper operation on standby power, the chiller control power must
remain as factory-wired from a unit-mounted transformer. Do not supply chiller control power
from an external power source because the chiller may not sense a loss of power and do a normal
shutdown sequence.
System Pumps
Operation of the chilled water pump can be to 1) cycle the pump with the compressor, 2) operate
continuously, or 3) start automatically by a remote source.
The cooling tower pump must cycle with the machine. The holding coil of the cooling tower pump
motor starter must be rated at 115 volts, 60 Hz, with a maximum volt-amperage rating of 100. A
control relay is required if the voltage-amperage rating is exceeded. See the Field Wiring Diagram
on page 19 or in the cover of control panel for proper connections.
All interlock contacts must be rated for no less than 10 inductive amps. The alarm circuit provided
in the control center utilizes 115-volts AC. The alarm used must not draw more than 10 volt
amperes.
IMM WMC-1 Centrifugal Chillers 17
Field Wiring Diagram Notes (Page 19)
1. Compressor terminal boxes are factory-mounted and wired. All line-side wiring must be in accordance with the NEC
and be made with copper wire and copper lugs only. Power wiring between the terminal box and compressor terminals
is factory installed.
2. Minimum wire size for 115 VAC is 12 ga. for a maximum length of 50 feet. If greater than 50 feet refer to McQuay for
recommended wire size minimum. Wire size for 24 VAC is 18 ga. All wiring to be installed as NEC Class 1 wiring
system. All 24 VAC wiring must be run in separate conduit from 115 VAC wiring. Wiring must be wired in
accordance with NEC and connection to be made with copper wire and copper lugs only.
3. A customer furnished 24 or 120 Vac power for alarm relay coil may be connected between UTB1 terminals 84 power
and 81 neutral of the control panel. For normally open contacts wire between 82 & 81. For normally closed wire
between 83 & 81. The alarm is operator programmable. Maximum rating of the alarm relay coil is 25VA.
4. Remote on/off control of unit can be accomplished by installing a set of dry contacts between terminals 70 and 54.
5. If field supplied pressure differential switches are used, they must be installed across the vessel and not the pump. They
must be suitable for 24vac and low current application. Field wiring not required with the standard factory-mounted
flow switches.
6. Customer supplied 115 VAC 20 amp power for optional evaporator and condenser water pump control power and tower
fans is supplied to unit control terminals (UTB1) 85 power / 86 neutral, PE equipment ground.
7. Optional customer supplied 115 VAC, 25 VA maximum coil rated, chilled water pump relay (ep1 & 2) may be wired as
shown. This option will cycle the chilled water pump in response to chiller demand.
8. The condenser water pump must cycle with the unit. A customer supplied 115 VAC 25 VA maximum coil rated,
condenser water pump relay (CP1 & 2) is to be wired as shown. Units with free-cooling must have condenser water
above 60°F before starting.
9. Optional customer supplied 115 VAC 25 VA maximum coil rated cooling tower fan relays (C1 - C2 standard, C3-C4
optional) may be wired as shown. This option will cycle the cooling tower fans in order to maintain unit head pressure.
10. Auxiliary 24 VAC rated contacts in both the chilled water and condenser water pump starters should be wired as shown.
11. Optional Control Inputs. The following 4-20 ma optional inputs are connected as shown:
• Demand Limit; Terminals 58 and 71 common
• Chilled Water Reset; Terminals 51 and 71 common
• Evaporator Water Flow; Terminals 59 and 71 common
• Condenser Water Flow; Terminals 60 and 71 common
12. Optional Control Power Source. 115 volt control power can be supplied from a separate circuit and fused at 20 amps
inductive load. Connection is to terminals 85 and 86 common.
13. 4-20mA external signal for chilled water reset are wired to terminals 71 and 51 on the unit controller; load limit is wired
to terminals 71 and 58 on the unit controller.
18Centrifugal Chillers IMM WMC-1
A
* COOLING
CROTECH CO
A
A
A
TOWER
FOURTH
STAGE
STARTER
* COOLING
TOWER
THIRD
STAGE
STARTER
* COOLING
TOWER
SECOND
STAGE
STARTER
* COOLING
TOWER
FIRST
STAGE
STARTER
Field Wiring Diagram
Figure 11, Field Wiring Diagram
MI
BOX TERMINALS
(115V) (24V)
GND
POWER
*
NOTE 6
NEUTRAL
NOTE 9
*
H
O
C4
A
NOTE 9
*
H
O
C3
A
NOTE 9
*
H
O
C2
A
NOTE 9
*
H
O
C1
A
COMMON
*
NOTE 3
POWER
NTROL
UTB1
PE
54
70
55
CF1
EF1
EF2
CF2
(NOTE 5)
SWITCH
DELTA P
FLOW OR
EVAP.
*ALARM RELAY
A
(NOTE 3)
85
86
80
74
86
86
79
73
78
77
76
75
81
82(NO)
83(NC)
84
*
MODE SWITCH
(NOTE 5)
SWITCH
DELTA P
FLOW OR
COND.
* REMOTE
ON/OFF
(NOTE 4)
*NOTE 7
EP2
NOTE 10
NOTE 7
*
EP1
NOTE 10
O
EWI-2
O
EWI-1
*
NOTE 8
NOTE 10
H
H
CP2
C
* CHILLED
WATER
PUMP
STARTERS
C
H
O
C
CWI-2
* CONDENSER
WATER
PUMP
STARTERS
*COOLING TOWER BYPASS VALUE
*COOLING TOWER VFD
0-10 VDC
0-10 VDC
52
71
71
53
NOTE 8
*
NOTE 10
CP1
H
O
CWI-1
C
330617801 REV. 00
See notes on page 18.
IMM WMC-1 Centrifugal Chillers 19
VFD Line Harmonics
Despite their many benefits, care must be taken when applying VFDs due to the effect of
line harmonics on the building electric system. VFDs cause distortion of the AC line
because they are nonlinear loads, that is, they don't draw sinusoidal current from the line.
They draw their current from only the peaks of the AC line, thereby flattening the top of the
voltage waveform. Some other nonlinear loads are electronic ballasts and uninterruptible
power supplies.
Line harmonics and their associated distortion can be critical to ac-drives for three reasons:
1. Current harmonics can cause additional heating to transformers, conductors,
and switchgear.
2. Voltage harmonics upset the smooth voltage sinusoidal waveform.
3. High-frequency components of voltage distortion can interfere with signals
transmitted on the AC line for some control systems.
th
The harmonics of concern are the 5
divisible by three, and high magnitude harmonics are usually not a problem.
Current Harmonics
An increase in reactive impedance in front of the VFD helps reduce the harmonic currents.
Reactive impedance can be added in the following ways:
1. Mount the drive far from the source transformer.
2. Add line reactors. They are standard equipment on WMC chillers.
3. Use an isolation transformer.
4. Use a harmonic filter.
Voltage Harmonics
Voltage distortion is caused by the flow of harmonic currents through a source impedance.
A reduction in source impedance to the point of common coupling (PCC) will result in a
reduction in voltage harmonics. This can be done in the following ways:
, 7th, 11th, and 13th. Even harmonics, harmonics
1. Keep the PCC as far from the drives (close to the power source) as possible.
2. Increase the size (decrease the impedance) of the source transformer.
3. Increase the capacity (decrease the impedance) of the busway or cables from
the source to the PCC.
4. Make sure that added reactance is "downstream" (closer to the VFD than the
source) from the PCC.
Line Reactors
Five-percent line reactors are standard equipment on WMC chillers and located in each
compressors power panel. They are employed to improve the power factor by reducing the
effects of harmonics.
Harmonic Filter
The harmonic filter is an option for field mounting and wiring outside of the power panel.
It works in conjunction with the line reactor to further minimize harmonic distortion. It is
wired between the line reactor and compressor. IEEE 519-1991 Standard defines
acceptable limits.
See the WMC certified drawings for harmonic filter dimensions and wiring information.
EMI (Electro Magnetic Interference) and RFI (Radio Frequency Interference) Filter
This filter is a factory-installed option. The terms EMI and RFI are often used
interchangeably. EMI is actually any frequency of electrical noise, whereas RFI is a
specific subset of electrical noise on the EMI spectrum. There are two types of EMI.
Conducted EMI is unwanted high frequencies that ride on the AC wave form.
20 Centrifugal Chillers IMM WMC-1
EMI-Radiated EMI is similar to an unwanted radio broadcast being emitted from the power
lines. There are many pieces of equipment that can generate EMI, variable frequency
drives included. In the case of variable frequency drives, the electrical noise produced is
primarily contained in the switching edges of the pulse width modulation (PWM)
controller.
As the technology of drives evolves, switching frequencies increase. These increases also
increase the effective edge frequencies produced, thereby increasing the amount of
electrical noise.
The power line noise emissions associated with variable frequency and variable speed
drives can cause disturbances in nearby equipment. Typical disturbances include:
• Dimmer and ballast instability
• Lighting disturbances such as flashing
• Poor radio reception
• Poor television reception
• Instability of control systems
• Flow meter totalizing
• Flow metering fluctuation
• Computer system failures including the loss of data
• Thermostat control problems
• Radar disruption
• Sonar disruption
RFI
Three-phase filters are supplied as an option for factory mounting in the compressor power
panels. They use a combination of high frequency inductors and capacitors to reduce noise
in the critical 150kHz to 30MHz frequency range. The inductors act as open circuits and
the capacitors act as short circuits at high frequencies while allowing the lower power line
frequencies to pass untouched. The filters assist with cost effective compliance to Electro
Magnetic Compatibility (EMC) directives, in a compact, efficient, light-weight design. The
high common mode and differential mode reduction in the critical 150kHz to 30MHz
frequencies assures that potential interference from AC drives is reduced or eliminated.
The filters are current-rated devices. In order to properly size a filter, it is necessary to
know the operating voltage, and the input current rating of the drive. No derating or rerating is necessary when applying the filter at voltages that are less than or equal to the
maximum voltage listed on the filter.
The IEEE 519-1991 Standard
The Institute of Electrical and Electronics Engineers (IEEE) has developed a standard that
defines acceptable limits of system current and voltage distortion. A simple form is
available from McQuay that allows McQuay to determine compliance with IEEE 519-1991.
Line reactors, isolation transformers, or phase-shifting transformers can be required on
some installations.
IMM WMC-1 Centrifugal Chillers 21
Figure 12, Typical WMC Power Wiring
WMC Wiring
GND
Contactor
Optional
EMI
Filter
AC Input
Voltage
L1
L2
L3
(1)
C
Manual
Disconnect
Optional
Notes:
(1) Single hole, crimp type compression terminal required.
(2) Connect to filter circuit breaker lugs.
(3) Conductors to be sized for 125 minimum circuit ampacity.
Size 1 AWG, 75°C wire recommended.
Multiple Chiller Setup
WMC dual compressor units have the four main control components; two compressor
controllers, one unit controller, and the operator interface panel with touchscreen (OITS).
factory wired to a pLAN local area network so that they can communicate with each other.
Two dual compressor chillers can be interconnected and operated in unison by simple field
RS485 interconnecting wiring and the addition of some MicroTech II control settings.
pLAN Setup
To interconnect multiple chillers, MicroTech II pLAN RS485 wiring must be installed by
the installing contractor prior to start-up.
1. With no pLAN connections between chillers, disconnect unit control power and set the
DIP switches as shown in Table 7. They are located on the upper-front of the
controllers, above the screen.
Standard
Line
Reactor
(3)
(2) Hamonic
Filter with
Circuit Breaker
2. With all manual switches off, turn on control power to each chiller and set each OITS
address (see Note 2 on page 23).
3. Verify correct nodes on each OITS Service Screen.
4. Connect chillers together (pLAN, RS485 wiring) between J6 connections on each unit
controller’s isolation board. Wiring should be 22 ga., twisted pair, shielded cable.
5. Verify correct nodes on each OITS Service Screen.
22 Centrifugal Chillers IMM WMC-1
Table 7, Address DIP Switch Settings for Controllers Usi ng pLAN.
Chiller Comp
1
1
2
1
2
2
NOTES:
1. Up to four compressors can be interconnected.
2. The Operator Interface Touch Screen (OITS) setting is not a DIP switch setting. The OITS
address is selected by selecting the ‘service’ set screen. Then, with the Technician level password
active, select the ‘pLAN Comm’ button. Buttons A(7), B(15), C(23), D(31) will appear in the
middle of the screen, then select the letter for the OITS address for the chiller that it is on. Then
close the screen. Note that A is the default setting from the factory.
3. Six Binary Switches: Up is ‘On’, indicated by ‘1’. Down is ‘Off’, indicated by ‘0’
Comp 1
Controller
1 2 5 6 7 8
100000 010000 101000 011000 111000 000100
9 10 13 14 15 16
100100 010100 101100 011100 111100 000010
17 18 21 22 23 24
100010 010010 101010 011010 111010 000110
25 26 29 30 31 32
100110 010110 101110 011110 111110 000001
Comp 2
Controller
Unit
Controller
Reserved
Operator
Interface (2)
Reserved
.
MicroTech II Operator Interface Touch Screen (OITS) Settings
Settings for any type of linked multiple compressor operation must be made to the
MicroTech II controller. Settings on a dual compressor unit are made in the factory prior to
shipment, but must be verified in the field before startup. Settings for multiple chiller
installations are set in the field on the Operator Interface Touch Screen as follows:
Maximum Compressors O N
– SETPOINTS - MODES screen, Selection #9 = 2 for a dual, 4
for 2 duals.
Sequence and Staging
– SETPOINTS - MODES screen, Selection #10 & #12; #11 & #13.
Sequence sets the sequence in which compressors will start. Setting all to “1” evokes the
automatic lead/lag feature and is the preferred setting.
Nominal Capacity
compressor
design tons. Compressors on dual units are always of equal capacity.
– SETPOINTS - MOTOR screen, Selection #14. The setting is the
Operating Sequence
For multiple-chiller, parallel operation, the MicroTech II controllers are tied together by a
pLAN network and stage and control compressor loading among the chillers. Each chiller,
will stage on or off depending on the sequence number programmed into it. If all are set to
“1”, the automatic lead/lag will be in effect.
When chiller #1 is fully loaded, the leaving chilled water temperature will rise slightly.
When the Delta-T above setpoint reaches the Staging Delta-T, the next chiller scheduled to
start will receive a start signal and start its pumps. This procedure is repeated until all
chillers are running. The compressors will load-balance themselves.
Water system operated and flow-balanced to meet unit requirements ..............................
Electrical
Power leads connected to the unit power panel(s) ............................................................ V V V
All interlock wiring complete between control panel and complies with specifications ...
Pump starters and interlock wired ....................................................................................
Cooling tower fans and controls wired .............................................................................
Wiring complies with National Electrical Code and local codes ......................................
Condenser pump starting relay (CWR) installed and wired ..............................................
Miscellaneous
Relief valve piping complete ............................................................................................ V V V
V V V
V V V
V V V
V V V
V V V
V V V
V V V
V V V
V V V
V V V
V V V
V V V
Thermometer wells, thermometers, gauges, control wells, controls, etc., installed ..........
Minimum system load of 80% of machine capacity available for testing
and adjusting controls .......................................................................................................
Control wiring between multiple units, if applicable.........................................................
V V V
V V V
V V V
Note: This checklist must be completed and sent to the local McQuay service location two
weeks prior to start-up.
24 Centrifugal Chillers IMM WMC-1
Operation
Operator Responsibilities
It is important that the operator become familiar with the equipment and the system before
attempting to operate the chiller.
During the initial startup of the chiller, the McQuay technician will be available to answer any
questions and instruct in the proper operating procedures.
It is recommended that the operator maintain an operating log for each individual chiller unit. In
addition, a separate maintenance log should be kept of the periodic maintenance and servicing
activities.
Now that you have made an investment in modern, efficient McQuay® equipment, its care and
operation should be a high priority. For training information on all McQuay HVAC products, please
visit us at www.mcquay.com and click on Training or phone 540-248-0711 and ask for the Training
Department. These sessions are structured to provide basic classroom instruction and include handson operating and troubleshooting exercises.
Compressor Operation
The WMC compressors are two-stage. Suction gas enters the compressor through inlet guide vanes
that can be opened and closed to control refrigerant flow as the cooling load changes. The suction
gas enters the first stage impeller, is compressed, travels through the vaned radial diffuser to the
second stage impeller where compression is completed. The gas travels to the condenser via the
discharge volute, which converts any remaining velocity pressure to static pressure.
Motor cooling is accomplished by utilizing the refrigerant effect of high-pressure refrigerant from
the condenser expanded to a gas within the compressor. The refrigerant cools heat sinks and the
motor.
A five-axis magnetic bearing system supports the motor/compressor shaft, resisting radial and thrust
forces. The bearing control system uses shaft position feedback to continually adjust the bearing to
keep the shaft in the correct position. In the event of a power failure, the compressor motor acts as a
generator and powers the bearing support system during coastdown. There is also a system to gently
de-levitate the shaft.
Many controls are mounted directly on the compressor where they monitor and control compressor
operation. These compressor controls are interfaced with the conventional MicroTech II controls to
provide a complete chiller control system.
Operating Limits:
Maximum standby ambient temperature, 130°F (55°C)
Minimum operating ambient temperature (standard), 35°F (2°C)
Leaving chilled water range, 38°F to 60°F (3°C to 15°C)
Maximum operating evaporator inlet fluid temperature, 66°F (19°C)
Maximum startup evaporator inlet fluid temperature, 90°F (32°C)
Maximum non-operating inlet fluid temperature, 100°F (38°C)
Minimum condenser water entering temperature, 55°F (12.8°C)
Maximum entering condenser water temperature, 105°F (40.6°C)
Maximum leaving condenser water temperature, 115°F (46.1°C)
IMM WMC-1 Centrifugal Chillers 25
System Water Volume
It is important to have adequate water volume in the system to provide an opportunity for the chiller
to sense a load change, adjust to the change, and stabilize. As the expected load change becomes
more rapid, a greater water volume is needed. The system water volume is the total amount of water
in the evaporator, air handling products and associated piping. If the water volume is too low,
operational problems can occur including rapid compressor cycling, rapid loading and unloading of
compressors, erratic refrigerant flow in the chiller, improper motor cooling, shortened equipment life
and other undesirable consequences.
For normal comfort cooling applications, where the cooling load changes relatively slowly, we
reco mmend a min imu m syst em vo lume of t hre e min ute s times the flow rate (gpm). For example, if
the design chiller flow rate is 300 gpm, we recommend a minimum system volume of 900 gallons
(300 gpm x 3 minutes).
For process applications where the cooling load can change rapidly, additional system water volume
is needed. A process example would be a quenching tank. The load would be very stable until the
hot material is immersed in the water tank. Then, the load would increase drastically. For this type
of application, system volume may need to be increased.
Since there are many other factors that can influence performance, systems may successfully operate
below these suggestions. However, as the water volume decreases below these suggestions, the
possibility of problems increases.
Variable Speed Pumping
Variable water flow involves inversely changing the water flow through the evaporator as the load
changes. McQuay chillers are designed for this duty provided that the rate of change in water flow
is slow and the minimum and maximum flow rates for the vessel, as shown in Figure 7 on page 12
are not exceeded.
The recommen ded max imum cha nge in wa ter fl ow is 10 percent of the allowable flow change per
minute. Flow is usually not reduced below 50 percent of design flow (provided vessel minimum
flow rates are not exceeded).
For example, a 150 ton chiller might have chilled water flow of 360 gpm, reduced to 50 percent,
would be 180 gpm. However, the minimum flow rate is 216 gpm, so the flow change would be 360
gpm minus 216 gpm, or 144 gpm. This means that the allowable flow rate change would be 10
percent of 144 or 14.4 gpm per minute.
26 Centrifugal Chillers IMM WMC-1
MicroTech II™ Control
Figure 13, MicroTech II Control Panel
The WMC chillers are equipped with the
McQuay MicroTech II control system consisting
of:
• Operator interface touchscreen panel
(shown at the left). It contains of a 12-inch
Super VGA color screen.
• Control Panel containing the MicroTech II
unit
compressor
the compressor-mounted controls, and
various switches and field connection
terminals.
Operating instructions for the MicroTech II controller are contained in Operating
Manual OM WMC-2.
Building Automation Systems
controller, two MicroTech II
controllers with connections to
All MicroTech II controllers are capable of BAS communications, providing seamless
integration and comprehensive monitoring, control, and two-way data exchange with
industry standard protocols such as L
ONMARK®, Modbus® or BACnet®.
Protocol Selectability™ Benefits
• Easy to integrate into your building automation system of choice
• Factory-installed and tested communication module
• Comprehensive point list for system integration, equipment monitoring and alarm
notification
• Provides efficient equipment operation
• Owner/designer can select the BAS that best meets building requirements
• Comprehensive data exchange
Integration Made Easy
McQuay unit controllers strictly conform to the interoperability guidelines of the
L
ONMARK® Interoperability Association and the BACnet Manufacturers Association.
They have received:
ONMARK certification with optional LONWORKS communication module
• L
Protocol Options
• BACnet MS/TP • LONWORKS® (FTT-10A)
• BACnet IP • Modbus RTU
• BACnet Ethernet
The BAS communication module can be ordered with a chiller and factory-mounted or can
be field-mounted at any time after the chiller unit is installed.
IMM WMC-1 Centrifugal Chillers 27
Table 8, Typical Data Point Availability
Typical Data Points
Active Setpoint R Cond EWT R Evap Water Pump Status R
Actual Capacity R Cond Flow Switch St atus R Liquid Line Refrigerant Pres sure R
Capacity Limit Output R Cond LWT R Liquid Line Refrigerant Temp R
Capacity Limit Setpoint W Cond Pump Run Hours R Maximum Send Time W
Chiller Enable W Cond Refrigerant P ressure R Minimum Send Time W
Chiller Limited R
Chiller Local/Remote R Cond Wat er P ump Status R Pump Select W
Chiller Mode Output R Cool Setpoint W Run Enabled R
Chiller Mode Setpoint W Current Alarm R
Chiller On/Off R Default Values W
Chiller Status R Evap EWT R
Compressor Discharge Temp R Evap Flow Switch Status R
Compressor Percent RLA R Evap LWT for Unit R
Compressor Run Hours R Evap LWT for Compressor R
Compressor Select W Evap Pump Run Hours R
Compressor Starts R Evap Ref rigerant Pressure R
Compressor Suction Li ne
Temp
Cond Sat. Refrigerant
Temp
Evap Sat. Refrigerant
R
Temp
Note: Data points available are dependent upon options selected.
1
(W = Write, R = Read)
R Network Clear Alarm W
R
Connection to Chiller
Connection to the chiller for all BAS protocols will be at the unit controller. An interface card,
depending on the protocol being used, will have been factory installed in the unit controller if so
ordered, or it can be field installed.
Protocols Supported
Table 9, Standard Protocol Data
Protocol Physical Layer Data Rate Controller Other
BACnet®/IP
BACnet MSTP RS485 (TBD)
LonTalk®
ModbusRTU RS-485 (TBD)
NOTE: For additional information on the protocol data available through the BACnet or LonTalk
communications modules, reference McQuay ED 15062, MicroTech II Chiller Unit Controller
Protocol Information.
Modbus - When selected, the ident number and baud can also be changed to suit the application.
LONWORKS – When selected, the ident number and baud rate setpoints are not available. Baud
rate is locked at 4800.
BACnet – When selected, the ident number and baud rate setpoints are not available. Baud rate is
locked at 19200.
The factory installed kits on the MicroTech II™ controller are as follows:
If an interface module was ordered, one of the following BAS interface installation manuals was
shipped with the unit. If necessary, contact your local McQuay sales office for a replacement or
obtain from www.mcquay.com.
Ethernet 10 Base-T 10 Megabits/sec Color graphics SBC Reference ED 15057: BACnet PICS
• IM 736, BACnet® Communication Module Installation
• IM 743, Modbus® Communication Module Installation
28 Centrifugal Chillers IMM WMC-1
Figure 14, Unit Control Panel
SW1, Unit Switch
SW12, Circ #1 Switch
SW22, Circ #2 Switch
Control Circuit Breaker
Unit T erminal Board
UTB1
Unit Controller
Circuit # 1 Controller
Circuit #1 Terminal
Board, TB1
MOD1, MOD2
Circuit # 2 Controller
Circuit #2 Terminal
Board, TB2
Ground
Capacity Control System
The capacity of the chiller is controlled by, 1) staging the compressors on and off, 2) by
adjusting the capacity of each compressor by opening or closing the inlet vanes to control
the quantity of refrigerant entering the impeller, and 3) varying compressor speed to change
capacity.
The speed control and vane control work in conjunction. As load decreases, compressor
speed is reduced as low as possible but above the point where stall might begin. If further
IMM WMC-1 Centrifugal Chillers 29
capacity reduction is required, the guide vanes will close to whatever position is required to
match the compressor capacity to the load.
Surge and Stall
Stall and surge are a characteristic of all centrifugal compressors. These conditions can
occur at low load conditions when the operating point moves to the left of the compressor
surge line on the performance curve.
In surge, the discharge gas alternately flows backward and forward through the impeller
reversing about every two seconds. Increased noise, vibration and heat occur and motor
current varies widely. Surge can damage a compressor. The compressors are equipped with
safety features that help prevent surge from occurring.
Another instability is stall or incipient surge, which occurs a little to the left, or before, the
surge condition. Discharge gas in the diffuser forms rotating stall pockets or cells. The
compressor sound level will change and the impeller starts to heat up. Motor current
remains steady.
Condenser Water Temperature
When the ambient wet bulb temperature is lower than design, the entering condenser water
temperature can be allowed to fall, improving chiller performance.
McQuay chillers will start with entering condenser water temperature as low as 55°F
(12.8°C) providing the chilled water temperature is below the condenser water temperature.
Depending on local climatic conditions, using the lowest possible entering condenser water
temperature can be more costly in total system power consumed than the expected savings
in chiller power would suggest due to the excessive fan power required.
To obtain lower than 55°F (12.8°C) entering condenser water temperature with a tower
selected to produce 85°F (29.4°C) water temperature at design ambient air temperatures,
cooling tower fans must continue to operate at 100% capacity at low wet bulb temperatures.
As chillers are selected for lower kW per ton, the cooling tower fan motor power becomes a
higher percentage of the peak load chiller power. The offsets of compressor power and fan
power must be examined. On the other hand, the low condenser water temperatures can be
easy and economical to achieve in mild climates with low wet bulb temperatures.
Even with tower fan control, some form of water flow control such as tower bypass must be
used. The MicroTech II control is capable of controlling tower fans and bypass valve.
Figure 16 and Figure 17 illustrate two temperature actuated tower bypass arrangements.
The “Cold Weather” scheme provides better startup under cold ambient air temperature
conditions. The check valve may be required to prevent air at the pump inlet.
30 Centrifugal Chillers IMM WMC-1
Figure 15, Tower Bypass Valve, Pressure Actuated
Figure 16, Tower Bypass, Mild Weather Operation
Figure 17, Tower Bypass, Cold Weather Operation
IMM WMC-1 Centrifugal Chillers 31
Normal Unit Startup/Shutdown
Startup and shutdown, other than seasonal shutdowns, are considered to be normal
operation and the following procedures apply (assuming that the equipment room
temperature are above freezing). The procedures would be used for a weekend shutdown,
for example.
Note that the chiller is part of an entire building heating and cooling system that are usually
unique to a particular site. For example, the chilled water loop and chilled water pump can
also be used for heating and therefore must be operational year-around. The cooling tower
can be used for other equipment besides the chiller and may have to remain functional even
though the chiller is not. The following procedures, therefore, must take the peculiarities of
the entire system into account.
Shutdown
If the unit is to be secured for several days, and is already off due to lack of load, the UNIT
switch in the Unit Control Panel (and the remote Start/Stop switch, if used) should be
placed in the OFF position. If the chilled water pump and cooling tower are not required
for other purposes, they too can be turned off. If the pumps are controlled by the WMC
unit controller, they will shut down after the compressors.
If the chiller is running, the chilled water and condenser water pumps must remain on until
the compressors are stopped. This is true regardless of how the unit is turned off, whether
by the local switches or through a remote signal. The compressors go through a short
shutdown sequence, shutting guide vanes and performing other functions, before it finally
stops. The pumps must remain on during this shutdown period.
Once the compressors and pumps have stopped, no further action is required other than
opening disconnects, if so desired.
Startup
Any disconnects that were opened must be closed. The chilled water pump and cooling
tower should be turned on and flow verified. The chiller can then be started by placing the
UNIT switch (and the remote Start/Stop switch, if used) in the ON position. There is no
lube warm-up period required. The compressors go through a starting sequence and may
not start immediately. Once started, it is prudent to observe unit operation on the operator
interface screen for several minutes to check for normal functioning.
Start/Stop Switching
There are four ways to start/stop the chiller. Three are selected in SETPOINT\ MODE\SP3,
the fourth way is through panel-mounted switches:
1. Operator Interface Panel, (LOCAL) Home Screen 1 has AUTO and STOP buttons
that are only active when the unit is in "LOCAL CONTROL". This prevents the unit
from being accidentally started or stopped when it is under control from a remote
switch or BAS. When these buttons are pressed, the unit will cycle through its normal
starting or stopping sequence, both compressors will be stopped and normal dual
compressor starting procedure will be in effect.
2. Remote SWITCH, Selecting SWITCH in SP3 will put the unit under the control of a
remote switch that must be wired into the control. See Field Wiring Diagram, page 19.
3. BAS, BAS input is field-wired into a card that is factory-installed on the unit controller.
32 Centrifugal Chillers IMM WMC-1
4. Control Panel Switches
Three On/Off switches are located in the upper left corner of the main Control Panel,
which is adjacent to the operator interface panel, and have the following function:
• UNIT
• COMPRESSOR
• CIRCUIT BREAKER
A fourth switch located on the left outside of the Unit Control Panel and labeled
EMERGENCY STOP SWITCH
with the COMPRESSOR On/Off switches.
shuts down the chiller through the normal shutdown cycle of unloading the
compressors.
one switch for each compressor on the unit, executes an
immediate shutdown without the normal shutdown cycle.
disconnects optional external power to system pumps and
tower fans.
stops the compressor immediately. It is wired in series
Annual Unit Startup/Shutdown
Annual Shutdown
Where the chiller can be subject to freezing temperatures, the condenser and chiller must be
drained of all water. Dry air blown through the condenser will aid in forcing all water out.
Removal of condenser heads is also recommended. The condenser and evaporator are not
self-draining and tubes must be blown out. Water permitted to remain in the piping and
vessels can rupture these parts if subjected to freezing temperature.
Forced circulation of antifreeze through the water circuits is one method of avoiding
freeze up.
1. Take measures to prevent the shutoff valve in the water supply line from being
accidentally turned on.
2. If a cooling tower is used, and if the water pump will be exposed to freezing
temperatures, be sure to remove the pump drain plug and leave it out so any water that
can accumulate will drain away.
3. Open the compressor disconnect switch. Set the manual COMPRESSOR and UNIT
ON/OFF switches in the Unit Control Panel to the OFF position.
4. Check for corrosion and clean and paint rusted surfaces.
5. Clean and flush water tower for all units operating on a water tower.
6. Remove condenser heads at least once a year to inspect the condenser tubes and clean if
required.
Annual Startup
1. Check and tighten all electrical connections.
2. Replace the drain plug in the cooling tower pump if it was removed at shutdown time
the previous season.
3. Install fuses in main disconnect switch (if removed).
4. Reconnect water lines and turn on supply water. Flush condenser and check for leaks.
IMM WMC-1 Centrifugal Chillers 33
Maintenance
Pressure/Temperature Chart
Danger
Wait 10 minutes after compressor shutdown before opening any
compressor access panel. The DC link capacitors store enough
Maintenance of the refrigerant cycle includes maintaining a log of the operating conditions, and
checking that the unit has the proper refrigerant charge.
At every inspection, the suction, and discharge pressures should be noted and recorded, as well as
condenser and chiller water temperatures.
The suction line temperature at the compressor should be taken at least once a month. Subtracting
the saturated temperature equivalent of the suction pressure from this will give the suction
superheat. Extreme changes in subcooling and/or superheat over a period of time will indicate
losses of refrigerant or possible deterioration or malfunction of the expansion valve. The
evaporator operates at 0 to 1 degree F (0.5 degree C) of superheat through most of the load range.
The refrigerant used for compressor cooling dumps at the compressor suction, where the suction
temperature sensor is located. This results in a warming of the suction gas and superheat readings
of 4 to 5 degrees F (2 to 3 degrees C).
The discharge superheat should be between 16 and 18 degrees F (9 to 10 degrees C), and remains
fairly constant through most of the load range.
Liquid subcooling is in the range of 8 to 9 degrees F (4.5 to 5.0 degrees C).
The MicroTech II interface panel can display all superheat and subcooling temperatures.
Electrical System
Maintenance of the electrical system involves the general requirement of keeping contacts clean
and connections tight and checking on specific items as follows:
1. The compressor current draw should be checked and compared to nameplate RLA value.
Normally, the actual current will be lower, since the nameplate rating represents full load
operation. Also check all pump and fan motor amperages, and compare with nameplate
ratings.
2. At least once a quarter, all equipment protection controls, except compressor overloads, should
be made to operate and their operating points checked. A control can shift its operating point
as it ages, and this must be detected so the controls can be adjusted or replaced. Pump
interlocks and flow switches should be checked to be sure they interrupt the control circuit
when tripped.
Cleaning and Preserving
A common cause of service calls and equipment malfunction is dirt. This can be prevented with
normal maintenance. The system components most subject to dirt are:
1. Permanent or cleanable filters in the air handling equipment must be cleaned in accordance
with the manufacturer’s instructions; throwaway filters should be replaced. The frequency of
this service will vary with each installation.
2. Remove and clean strainers in the chilled water system and condenser water system at every
inspection.
Water Treatment
Make sure tower blowdown or bleed-off is operating. Set up and use a good maintenance program
to prevent “liming up” of both tower and condenser. It should be recognized that atmospheric air
contains many contaminants that increase the need for proper water treatment. The use of
untreated water can result in corrosion, erosion, sliming, scaling or algae formation. It is
recommended that the service of a reliable water treatment company be used. McQuay
International assumes no responsibility for the results of untreated or improperly treated water.
IMM WMC-1 Centrifugal Chillers 35
Repair of System
Pressure Relief Valve Replacement
Current condenser designs use two relief valves separated by a three-way shutoff valve (one set).
This three-way valve allows either relief valve to be shut off, but at no time can both be shut off.
In the event one of the relief valves are leaking in the two valve set, these procedures must be
followed:
• If the valve closest to the valve stem is leaking, back seat the three-way valve all the way,
closing the port to the leaking pressure relief valve. Remove and replace the faulty relief
valve. The three-way shutoff valve must remain either fully back seated or fully forward to
normal operation. If the relief valve farthest from the valve stem is leaking, front seat the
three-way valve and replace the relief valve as stated above.
• The refrigerant must be pumped down into the condenser before the evaporator relief valve
can be removed.
Pumping Down
If it becomes necessary to pump the system down, extreme care must be used to avoid damage to
the evaporator from freezing. Always make sure that full water flow is maintained through the
chiller and condenser while pumping down. To pump the system down, close all liquid line valves.
With all liquid line valves closed and water flowing, start the compressor. Set the MicroTech II
control to the manual load. The vanes must be open while pumping down to avoid a surge or other
damaging condition. Pump the unit down until the MicroTech II controller cuts out at
approximately 20 psig. It is possible that the unit might experience a mild surge condition prior to
cutout. If this should occur, immediately shut off the compressor. Use a portable condensing unit
to complete the pump down, condense the refrigerant, and pump it into the condenser or pumpout
vessel using approved procedures.
Pressure Testing
No pressure testing is necessary unless some damage was incurred during shipment. Damage can
be determined by a visual inspection of the exterior piping, checking that no breakage occurred or
fittings loosened. Service gauges should show a positive pressure. If no pressure is evident on the
gauges, a leak may have occurred, discharging the entire refrigerant charge. In this case, the unit
must be leak tested to determine the location of the leak.
Leak Testing
In the case of loss of the entire refrigerant charge, the unit must be checked for leaks prior to
charging the complete system. This can be done by charging enough refrigerant into the system to
build the pressure up to approximately 10 psig (69 kPa) and adding sufficient dry nitrogen to bring
the pressure up to a maximum of 125 psig (860 kPa). Leak test with an electronic leak detector.
Halide leak detectors do not function with R-134a. Water flow through the vessels must be
maintained anytime refrigerant is added or removed from the system.
W ARNING
Do not use oxygen or a mixture of a refrigerant and air to build up pressure
as an explosion can occur causing serious personal injury.
If any leaks are found in welded or brazed joints, or it is necessary to replace a gasket, relieve the
test pressure in the system before proceeding. Brazing is required for copper joints.
After making any necessary repair, the system must be evacuated as described in the following
section.
36 Centrifugal Chillers IMM WMC-1
Evacuation
After it has been determined that there are no refrigerant leaks, the system must be evacuated using a
vacuum pump with a capacity that will reduce the vacuum to at least 1000 microns of mercury.
A mercury manometer, or an electronic or other type of micron gauge, must be connected at the
farthest point from the vacuum pump. For readings below 1000 microns, an electronic or other
micron gauge must be used.
The triple evacuation method is recommended and is particularly helpful if the vacuum pump is
unable to obtain the desired 1 millimeter of vacuum. The system is first evacuated to approximately
29 inches of mercury. Dry nitrogen is then added to the system to bring the pressure up to zero
pounds.
Then the system is once again evacuated to approximately 29 inches of mercury. This is repeated
three times. The first pulldown will remove about 90% of the noncondensables, the second about
90% of that remaining from the first pulldown and, after the third, only 1/10-1% noncondensables
will remain.
Charging the System
McQuay water chillers are leak tested at the factory and shipped with the correct charge of
refrigerant as indicated on the unit nameplate. In the event the refrigerant charge was lost due to
shipping damage, the system should be charged as follows after first repairing the leaks and
evacuating the system.
1. Connect the refrigerant drum to the gauge port on the liquid line shutoff valve and purge the
charging line between the refrigerant cylinder and the valve. Then open the valve to the midposition.
2. Turn on both the cooling tower water pump and chilled water pump and allow water to
circulate through the condenser and the chiller. (It may be necessary to manually close the
condenser pump starter.)
3. If the system is under a vacuum, stand the refrigerant drum with the connection up, and open
the drum and break the vacuum with refrigerant gas to a saturated pressure above freezing.
4. With a system gas pressure higher than the equivalent of a freezing temperature, invert the
charging cylinder and elevate the drum above the condenser. With the drum in this position,
valves open, water pumps operating, liquid refrigerant will flow into the condenser.
Approximately 75% of the total requirement estimated for the unit can be charged in this
manner.
5. After 75% of the required charge has entered the condenser, reconnect the refrigerant drum and
charging line to the service valve on the bottom of the evaporator. Again purge the connecting
line, stand the drum with the connection up, and place the service valve in the open position.
IMPORTANT: At this point, the charging procedure should be interrupted and prestart
checks made before attem pting to complete refrig erant charge. The compressor must not
be started at this time. (Prelim inar y check m ust first be completed.)
NOTE: It is of utmost importance that all local, national, and international regulations
concerning the handling and emission of r efrigerants are observed.
IMM WMC-1 Centrifugal Chillers 37
Maintenance Schedule
I. Compressor
A. Performance Evaluation (Log & Analysis) * O
B. Motor
• Motor Cooling (check tem perature)
C. Vane Operation
• Compressor Loads:
Operate Manual Switch X
Record Motor Amps X
• Compressor Unloads:
Operate manual Switch X
Record Motor Amps X
• Vanes Will Hold (place m anual switch in "hold")
Observe Water Tem p and Record Amps X
D. Internal Compressor Check X
II. Controls
A. Operating Controls
• Check Settings and Operati on
• Check Vane Control Setting and Operation
• Verify Motor Load Limit Control
• Verify Load Balance Operation
B. Protective Controls
• Test Operation of:
Alarm Relay X
Pump Interlocks X
III. Condenser
A. Performance Evaluat i on O
B. Test Water Quality X
C. Clean Condenser Tubes X
D. Eddy current Test - Tube Wall Thickness X
E. Seasonal Protecti on X
IV. Evaporator
A. Performance Evaluation (Log Conditions And Analysis) O
B. Test Water Quality X
C. Clean Evaporator Tubes (as required) X
D. Eddy current Test - Tube Wall thickness (as required) X
E. Seasonal Protecti on X
V. Expansion Valve
A. Performance Evaluation (Superheat Control) X
VI. Compressor - Chiller Unit
A. Performance Evaluat i on O
B. Leak Test:
• Compressor Fittings and Terminal
• Piping Fittings
• Vessel Relief Valves
C. Vibration Isolation Test X
D. General Appearance:
• Paint
• Insulation
VII. Electrical
A. Capacitors, Replac e every 5 years from startup, include bus
bar. Consult McQuay for parts and instructions.
Key: O = Performed by in-house personnel X = Performed by McQuay Service personnel
X
X
X
X
X
X
X
X
X
X
X
X
38 Centrifugal Chillers IMM WMC-1
Service Programs
It is important that an air conditioning system receive adequate maintenance if the full equipment life
and full system benefits are to be realized.
Maintenance should be an ongoing program from the time the system is initially started. A full
inspection should be made after 3 to 4 weeks of normal operation on a new installation, and on a
regular basis thereafter.
McQuay offers a variety of maintenance services through the local McQuay service office, its
worldwide service organization, and can tailor these services to suit the needs of the building owner.
Most popular among these services is the McQuay Comprehensive Maintenance Contract.
For further information concerning the many services available, contact your local McQuay service
office.
Operator Schools
Training courses for Centrifugal Maintenance and Operation are held through the year at the McQuay
Training Center in Staunton, Virginia. The school duration is three and one-half days and includes
instruction on basic refrigeration, MicroTech controllers, enhancing chiller efficiency and reliability,
MicroTech troubleshooting, system components, and other related subjects. Further information can
be found on www.mcquay.com or call McQuay at 540-248-0711 and ask for the Training
Department.
Warranty Statement
Limited Warranty
Consult your local McQuay Representative for warranty details. Refer to Form 933-43285Y. To find
your local McQuay Representative, go to www.mcquay.com.
IMM WMC-1 Centrifugal Chillers 39
This document contains the most current product information as of this printing. For t he m ost up-todate product information, please go to www.mcquay.com.
Post Office Box 2510, Staunton, Virginia • (800) 432-1342 • www.mcquay.com IMM WMC-1 (6/05)
Loading...
+ hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.