Heat medium
A = Natural gas
E = Electric
F = Fuel oil
S = Steam
W = Hot water
Y = None
Design vintage
Cooling coil size
S = Standard (low airflow)
L = Large (high airflow)
Y = None or contractor coil
This manual provides general information about the “C”
vintage McQuay RoofPak applied rooftop unit, models RDS
and RAH. In addition to an overall description of the unit, it
includes mechanical and electrical installation procedures,
commissioning procedures, sequence of operation information,
and maintenance instructions. For further information on the
optional forced draft gas-fired furnace, refer to Bulletin No.
IM 684 or IM 685.
Introduction
Gas Burner Nameplate
On units that include gas heat, the nameplate is located on the
lower right corner of the main control box door. It includes the
burner model number, minimum/maximum input, maximum
temperature rise, and minimum cfm.
Hazard Identification Information
The MicroTech III applied rooftop unit controller is available.
For a detailed description of the MicroTech III components,
input/output configurations, field wiring and information on
using and programming the MicroTech III unit controller, refer
to OM 920.
For a description of operation and information on using the
keypad to view data and set parameters, refer to the
appropriate program-specific operation manual (see Table 1).
Table 1: Program Specific Rooftop Unit Literature
Rooftop unit control configuration
McQuay 208 - 460 VOM 844-1
VFDs
Figure 1: Nomenclature
McQuay 575 VOM 895
Non-McQuaySee vendor manuals
Operation manual
number
DANGER
Dangers indicate a hazardous situation which will result in
death or serious injury if not avoided.
WARNING
Warnings indicate potentially hazardous situations, which can
result in property damage, severe personal injury, or death if
not avoided.
CAUTION
Cautions indicate potentially hazardous situations, which can
result in personal injury or equipment damage if not avoided.
McQuay IM 9873
Introduction
Economizer
Filter
DX
Heat
section
Supply fan
discharge
plenum
section
C19, 20
RAT
LT11 (optional)
S11, REC11
SD2
RAE
ACT3
PC5
OAE
VM1
LT10 (optional)
DAT
OAT
SV1, 2
(optional)
section
section
return air
(optional)
(optional)
(optional)
(optional)
C9
FS1
(optional)
SV5, 6 (optional)
S10, REC10 (optional)
SD1 (optional)
ACT6
Typical Component Locations
Figure 2 shows a typical unit with locations of major
components. These figures are for general information only.
See the project’s certified submittals for actual specific
dimensions and locations.
Control Locations
All controls are optional. If controls are ordered, Figure 2
shows the locations of the various control components
Figure 2: Control Locations
mounted throughout the units. See Figure 3, page 5 for the
locations of control components mounted in control panels.
Additional information is included in Table 2, page 12 and the
wiring diagram legend, which is included in "Wiring
Diagrams"‚ page 59. Figure 2 shows the blow-through heat
and the blow-through coil sections.
4McQuay IM 987
Control Panel
Main control panel
Electric heat
control panel
(optional)
Supply fan
section
VFDs, line reactors, and
manual bypass
(optional)
Prop exhaust VFDs
(not shown)
(optional)
The unit control panels and their locations are shown in the
following figures. These figures show a typical unit
configuration. Specific unit configurations may differ slightly
from these figures depending on the particular unit options.
Figure 3: Control Panel Locations
Introduction
McQuay IM 9875
Introduction
R24 R25 R28
R20 R26 R27 R28
R30
R45
R60
R69
R58
GCB1
Resistor
keypad
Remote
MCB
EHB1
ERB1
VFD remote
display
REC1
TB1
DHL
SPS1
SPS2
MMP60MMP10MMP20
R46
R48
HS1 S1
S7S4
Keypad display
Serial conn
M60
M10
F3
M20
supply
Power
F1A
F1B
F1C
T1
DS1
GND LUG DS1
TB7
blocks
remaining
TB2,
blocks
first seven
TB3,
detail, page 14.
See separate
SPS1,2 fittings
for static
pressure tubing
Figure 4: Typical Main Control Panel, Sizes 800C to 802C, 460 Volt
6McQuay IM 987
Figure 5: Typical Main Control Panel, Size 047C, 460 Volt
VFD remote
display
GFR1
TB7
SPS1,2
fittings for
static pressure
tubing
TB2
F1A
F1B
F1C
Harness
Plugs
Introduction
McQuay IM 9877
Introduction
Unit powered outlet and
associated disconnect in
seperate panel
Figure 6: Typical Main Control Panel, Size 077C, 460 Volt
8McQuay IM 987
Introduction
e
A
M41M42M41
M33M32M31
FB33FB32FB31
FB43FB42FB41
PB3
SR2
SR3
SR1
TB11
Figure 7: TypicaL Gas Heat Panel, 1000 MBH
IT
R22
TD10
R20
S
R23R21
LS2
Figure 9: VFD Bypass Panel, 40 Hp, 460 Volt
LR10, 20
MMP30, 40
M30, 40
LS1
S3
Figure 10: Electric Heat Panel, Sizes 800C, 802C
FSG
FSG Tim
Figure 8: TypiCal Propeller Exhaust Panel, 3 Fans, 460 Volt
McQuay IM 9879
Introduction
GLG3
DS3
M41M43
FB41FB42FB43
H53
TB11
M31M32M33
FB31FB32FB33
M42
Figure 11: Electric Heat Panel, Size 047CFigure 12: Electric Heat Panel, Size 077C
FB31FB32FB33
M31M32M33
FB34FB44
M34M44
FB41FB42FB43
M41M42M43
GLG3
DS3
H53
TB11
10McQuay IM 987
Figure 13: Harness Plug Connector Detail
LT OP1LT OP2
LT11LT1 0
DFRH DFLHOPEN4
SD1SD2
GSHT1GSHT2
HL22OPEN3
OAEPC7PC5
ACT3OPEN2
SV12SV56
AFD10AFD20
FP1OPEN1EPTS
RATSOATSDATS
Introduction
McQuay IM 98711
Introduction
Controls, Settings, and Functions
Table 2 below lists all of the unit control devices and
Converts static pressure
signals to voltage signals
and sends them to
MicroTech III controller
Converts static pressure
signals to voltage signals.
Shuts off entire control circuit
(except crankcase heaters)
Used to manually switch unit
N/A
N/A
N/A
N/A
Main control
box
Main control
box
Main control
box
Main control
box
N/A
N/A
N/AN/AN/A001355000
N/AN/AN/A
0–5" wc
(0–1245.4 Pa)
1–6 V (dc) out
-025–0.25" wc
(-62.3–62.3
Pa)
1–5 V (dc) out
N/A049545007
N/A049545006
McQuay IM 98713
Mechanical Installation
Mechanical Installation
Note: The installation of this equipment shall be in accordance
with the regulations of authorities having jurisdiction and
all applicable codes. It is the responsibility of the installer
to determine and follow the applicable codes.
CAUTION
Sharp edges on sheet metal and fasteners can cause personal
injury.
This equipment must be installed, operated, and serviced only
by an experienced installation company and fully trained
personnel.
Receiving Inspection
When the equipment is received, all items should be carefully
checked against the bill of lading to be sure all crates and
cartons have been received. If the unit has become dirty
during shipment (winter road chemicals are of particular
concern), clean it when received.
Figure 14: Service Clearances, Unit with Housed DWDI Supply Fan
72"
(1829 mm)
All units should be inspected carefully for damage when
received. Report all shipping damage to the carrier and file a
claim. In most cases, equipment ships F.O.B. factory and
claims for freight damage should be filed by the consignee.
Before unloading the unit, check the unit nameplate to make
sure the voltage complies with the power supply available.
Unit Clearances
Service Clearance
Allow an approximate service clearance as indicated in
Figure 14. Also, McQuay recommends providing a roof
walkway to the rooftop unit as well as along two sides of the
unit that provide access to most controls and serviceable
components.
72"
(1829 mm)
Roof
Walkway
Note:
Sections with heating and/or cooling coils or DWDI
supply fan must have noted service clearance on the
control box side.
Note:
Sections with heating and/or cooling coils or DWDI
supply fan must have noted service clearance on the
control box side.
X
EF
Mechanical Installation
Ventilation Clearance
Below are minimum ventilation clearance recommendations.
The system designer must consider each application and
provide adequate ventilation. If this is not done, the unit will
not perform properly.
Unit(s) surrounded by a screen or a fence:
The bottom of the screen or fence should be at least 1 ft.
1
(305 mm) above the roof surface.
2 The distance between the unit and a screen or fence
should be as described in Figure 15.
3 The distance between any two units within a screen or
fence should be at least 120" (3048 mm).
Unit(s) surrounded by solid walls:
1
If there are walls on one or two adjacent sides of the unit,
the walls may be any height. If there are walls on more
than two adjacent sides of the unit, the walls should not
be higher than the unit.
2 The distance between the unit and the wall should be at
least 96" (2438 mm) on all sides of the unit.
3 The distance between any two units within the walls
should be at least 120" (3048 mm).
Do not locate outside air intakes near exhaust vents or other
sources of contaminated air.
If the unit is installed where windy conditions are common,
install wind screens around the unit, maintaining the
clearances specified (see Figure 16). This is particularly
important to prevent blowing snow from entering the outside
air intake and to maintain adequate head pressure control when
mechanical cooling is required at low outdoor air
temperatures.
Overhead Clearance
1 Unit(s) surrounded by screens or solid walls must have
no overhead obstructions over any part of the unit.
2 The following restrictions must be observed for overhead
obstructions above the air handler section (see
Figure 16):
a There must be no overhead obstructions above the
furnace flue, or within 9" (229 mm) of the flue box.
b Overhead obstructions must be no less than 96"
(2438 mm) above the top of the unit.
c There must be no overhead obstructions in the areas
above the outside air and exhaust dampers that are
farther than 24" (610 mm) from the side of the unit.
McQuay IM 98715
Mechanical Installation
24" (610 mm)
Maximum
2" (51 mm)
Minumum
Top of Unit
to Overhead
Obstruction
24" (610 mm)
Maximum
Overhead
Canopy
9" (229 mm)
Minumum to Flue Box
Typical All Sides
Flue Box
Figure 16: Overhead Clearance
Figure 17: Side Discharge
NOTICE
On units with side discharge, access to plenum-mounted
components becomes difficult once ductwork is installed.
Installer must provide access in the ductwork for plenum
mounted controls
Side Discharge Opening
(Access in Ductwork
Must be Removed)
16McQuay IM 987
Mechanical Installation
Roof Curb Assembly and Installation
Locate the roof curb and unit on a portion of the roof that can
support the weight of the unit. The unit must be supported to
prevent bending or twisting of the machine.
If building construction allows sound and vibration into the
occupied space, locate the unit over a non-critical area. It is
the responsibility of the system designer to make adequate
provisions for noise and vibration in the occupied space.
WARNING
Mold can cause personal injury. Some materials such as
gypsum wall board can promote mold growth when damp.
Such materials must be protected from moisture that can enter
units during maintenance or normal operation.
Install the curb and unit level to allow the condensate drain to
flow properly and allow service access doors to open and close
without binding.
Integral supply and return air duct flanges are provided with
the RAH roof curb, allowing connection of duct work to the
curb before the unit is set. The gasketed top surface of the duct
flanges seals against the unit when it is set on the curb. These
flanges must not support the total weight of the duct work.
Assembly of a typical RAH roof curb is shown in Figure 18,
page 18. Parts A through H are common to all units having
bottom return openings. Depending on the unit length, Parts L
and M may be included with the roof curb kit to create the
correct overall curb length.
Assembly instructions
1 Set curbing parts A through H per dimensions shown
over roof opening or on a level surface (see Figure 18,
page 18). Note location of return and supply air
openings.
2 If applicable, set other curbing parts (D, L, M, etc.) in
place making sure that the orientation complies with the
assembly instructions (see Detail A). Check alignment of
all mating bolt holes.
3 Bolt curbing parts together using fasteners provided.
Tighten all bolts finger tight.
4 Square entire curbing assembly and securely tighten all
bolts.
5 Position curb assembly over roof openings. Curb must be
level from side to side and over its length. Check that top
surface of the curb is flat with no bowing or sagging.
6 Weld curbing in place. Caulk all seams watertight.
Remove backing from 0.25" (6 mm) thick × 1.50"
(38 mm) wide gasketing and apply to surfaces shown by
cross-hatching.
7 Flash curbing into roof as shown in detail view B
(Figure 19).
8 Parts E and F are not required on units with no return
shaft within the curb perimeter.
9 Parts G and H are not required on units with no supply
shaft within the curb perimeter.
10 Be sure that electrical connections are coordinated (see
Figure 26).
McQuay IM 98717
Mechanical Installation
D
Return
Air
F
B
F
E
"X"
Inside
87.00"
(2210 mm)
Inside
90.00"
(2286 mm)
94.75"
(2407 mm)
A
B
E
8.75"
(222mm)
D
See Detail "A"
70.75"
(1797 mm)
C
G
G
C
H
H
A
"Y"
Inside
81.00"
(2057 mm)
Inside
8.75"
(222 mm)
3.50"
(90 mm)
7.50"
(191 mm)
2.00"
(51 mm)
Supply
Air
3.50"
(90mm)
Equal Length
Side Supports
L
Using remaining side supports
in this area, align lengths on
opposite sides of assembly
and install a cross support
"D" at each side.
D
M
L
M
Detail A
RAH unit
Dimensions
XY
in mm in mm
047C
38 965 28 711
077C with flat cooling coil and /or 44"
SWSI plenum supply fan
62
157
5
38 965
077C with staggered or no cooling coil,
and/or 49" SWSI plenum supply fan
62
157
5
46 1168
Main unit
curb
Unit base
Curb gasketing
2 × 4 nailer strip
Galvanized
curb
Cant strip
(not furnished)
Roffing material
(not furnished)
Rigid insulation
(not furnished)Counterflashing
(not furnished)
Flashing (not furnished)
Figure 18: RAH Roof Curb Assembly Instructions
Figure 19: Roofing Detail “B”
18McQuay IM 987
Figure 20: RDS Roof Curb Assembly Instructions
D
Return
Air
F
B
F
E
"X"
Inside
"Y"
Inside
85.00"
(2159 mm)
62.80"
(1594 mm)
A
B
E
"YY"
"XX"
D
See Detail "A"
38.80"
(984 mm)
C
G
G
C
H
H
A
20.00"
(508 mm)
Inside
76.00" (1930 mm)
Inside
6.80"
(173 mm)
1.50"
(38 mm)
7.50"
(191 mm)
2.00"
(5.1 mm)
Supply
Air
Mechanical Installation
Table 3: Rds Roof Curb Assembly Instructions
Unit sizeFan
None24.0 610 82.0 2083 6.8 1731.538
800–802C
(2) 15” FC 24.0 610 82.0 2083 6.81731.538(2) 15" FC 24.0 610 82.0 2083 6.81731.538
It is important to follow these installation instructions for all
IBC Seismic compliant McQuay Rooftop units.
IBC Seismic compliant McQuay Rooftop units can be
mounted to either a roof curb or a post and rail setup. If using a
roof curb, it must be specifically designed for seismic restraint
and be IBC seismic compliant (spring isolated or non-isolated
type seismic roof curbs are available). Typical construction of
a seismic rated roof curb is from structural steel framing and
contains seismic hold down brackets for attachment of the
rooftop unit (see Figure 21). Post and rail arrangements rated
for seismic applications are also available (spring isolated or
non-isolated).
IMPORTANT: An acceptable IBC seismic installation
provides a direct positive attachment to both the building
structure and the roof mounted equipment.
Refer to the roof curb manufacturer’s submittal drawings for
actual roof curb assembly, attachment details and rigging
instructions for both roof curb and post and rail arrangements.
Roof Curb Arrangement
1 Set the rooftop unit on the roof curb (McQuay Rooftop
units are designed to overhang from the roof curb).
2 Adjust the seismic hold down brackets so they come into
contact with the unit base per Figure 22 and Figure 23,
page 21.
a The seismic hold down brackets should be adjustable
and accommodate the overhang of the rooftop unit.
b If the hold down bracket cannot reach the unit base,
use a shim spacer. See Figure 23, page 21.
3 Weld each seismic hold down bracket (and shim spacer,
if required) to the unit base as shown in the acceptable
weld zone detail in Figure 22, page 21.
CAUTION
When welding unit to the curb, do not damage wiring (control
panel side). Weld ONLY in the specified zone in the acceptable
weld zone (see Figure 22, page 21). Welding must comply with
weld fillet size, etc. as indicated in Figure 22, page 21.
Note: High temperature insulation is installed at the factory to
allow for field welding along the lower front edge region
of the unit base.
Figure 22: Welding Of Hold Down Brackets—Unit Base, Cross-Sectional View
Unit base
Seismic hold down bracket
Unit power wiring
(by factory)
Unit control wiring
(by factory)
High temp
Insulation
Roof curb
Acceptable weld zone
Field attachment
weld
Weld
zone
.25
.50"
Unit base
Seismic hold
down bracket
Unit power wiring
(by factory)
Unit control wiring
(by factory)
Roof curb
Shim
spacer
It may be necessary for
the contractor to field
fabricate spacers or new
seismic hold-downs for
rooftop units having larger
overhang dimensions.
Figure 23: Shim Spacers On Hold Down Brackets
Mechanical Installation
McQuay IM 98721
Mechanical Installation
2–48
Rail
.25
Unit power wiring
(by factory)
Unit control wiring
(by factory)
High temp
insulation
Rail
Acceptable weld zone
Field attachment
weld
Weld
zone
.50"
Unit base
Unit base
6–12"
2–48
Rooftop unit
.25
Weld every 48"
6–12"
Rails
Post and Rail Arrangement
1 Set the rooftop unit on the rails. The rails should run
lengthwise and support the entire unit base.
2 Weld both sides of the unit directly to each rail as shown
in Figure 24 and Figure 25.
The total number of welds
required is dependent on the length of the unit.
a Make the fillet welds 2 inches long, spaced 48 inches
apart on centers.
b Place the end welds 6 to 12 inches from the unit edge.
Figure 24: Welding of Unit To Rail—Unit Base, Cross-Sectional View
When welding unit to the curb, do not damage wiring (control
panel side). Weld ONLY in the specified zone in the acceptable
weld zone (see Figure 24). Welding must comply with weld
fillet size, etc. as indicated in Figure 24.
Note: High temperature insulation is installed at the factory to
CAUTION
allow for field welding along the lower front edge region
of the unit base.
Figure 25: Weld Locations for Rail Arrangement
22McQuay IM 987
Mechanical Installation
Unit length minus 6.4
12.1
See Detail A
Detail A
3.4
5.1
0.9 Dia.
K.O.
3.0 Dia.
K.O.
4.6
4.8
2.0
2.1
4.3
3.1
9.7
E
8.0
97.0
76.0
6.0
7.5
20.0
1.5
6.0
6.8
RA
OPNG
B
2Typ
A
A
D
C
D
4Typ
A
B
B
SA
OPNG
RPS only
Figure 26: Typical Power Wire Entrance, Curb View (RDS 800C–802C Shown (For Exact Values, Refer to Submittal)
McQuay IM 98723
Mechanical Installation
99"
5" *
Max.
Note: Maximum recommended width for structural member is 5" (127
mm) to allow for adequate space for duct connections and
electrical entry.
Unit has either four or six lifting points (four-point shown below).
Rigging cables must be at least as long as distance “A.”
Spreader bars
required
Lift only as indicated
Caution: Lifting points may not
be symmetrical to center of
gravity of unit. Balast or unequal
cable lengths may be required.
A
Post and Rail Mounting
When mounting by post and rail, run the structural support the
full length of the unit. Locate the structural member at the base
of the unit as shown in Figure 27, assuring the I-beam is well
supported by the structural member.
CAUTION
The unit must be level side to side and over the entire length.
Equipment damage can result if the unit is not level.
If resilient material is placed between the unit and the rail,
insert a heavy steel plate between the unit and the resilient
material to distribute the load. Seal cabinet penetrations
(electrical, piping, etc.) properly to protect against moisture
and weather.
Figure 27: Post and Rail Mounting
1 Support the unit well along the length of the base rail.
2 Level the unit (no twists or uneven ground surface).
3 Provide proper drainage around the unit to prevent
flooding of the equipment.
4 Provide adequate protection from vandalism, mechanical
contact, etc.
5 Securely close the doors.
6 If there are isolation dampers, make sure they are
properly installed and fully closed to prevent the entry of
animals and debris through the supply and return air
openings.
7 Cover the supply and return air openings on units
without isolation dampers.
Figure 28 shows an example of the rigging instruction label
shipped with each unit.
WARNING
Use all lifting points. Improper lifting can cause severe personal
injury and property damage.
Figure 28: Rigging and Handling Instruction Label
Rigging and Handling
Lifting brackets with 2" (51 mm) diameter holes are provided
on the sides of the unit.
Use spreader bars, 96" to 100" (2438 to 2540 mm) wide, to
prevent damage to the unit cabinet. Avoid twisting or uneven
lifting of the unit. The cable length from the bracket to the
hook should always be longer than the distance between the
outer lifting points.
If the unit is stored at the construction site for an intermediate
period, follow these additional precautions:
24McQuay IM 987
CAUTION
Lifting points may not be symmetrical to the center of gravity of
the unit. Ballast or unequal cable lengths may be required.
Mechanical Installation
X
6 Lifting Points
B
A
Z
RDS 800: B Min. = 62" (1515 mm)
RDS 802: B Min. = 84" (2134 mm)
RAH 47: B Min. = 96" (2438 mm)
RAH 77: B Min. = 120" (3048 mm)
Lifting Points
To determine the required lifting cable lengths and whether
four-point or six-point lifting is required, use Tables 4 and 5
and Figure 29.
Referring toFigure 29, note that dimension A is the distance
between the outer lifting points. The four outer rigging cables
must be equal to or longer than dimension A. Dimension B
shows the minimum distance between the outer and the inner
lifting points for six-point lifting. Use this to roughly
determine the required length of the middle cables for sixpoint lifting. Determine dimension A by subtracting
dimensions X and Y from dimension Z (e.g., A = Z – X – Y).
• Where:
• Z = Total unit length in inches
(refer to certified drawings for this dimension).
• X = Outdoor/return air section length (refer to Figure 29 and
Table 5 for this dimension).
• If A 288" (7315 mm), 4-point lifting is sufficient.
• If A > 288" (7315 mm), 6-point lifting is required.
Table 4: RAH X Dimension (See Figure 29) Economizer
Section
Type of economizer
section
100% OA00
Plenum48” (1219 mm)72” (1829 mm)
0–30% OA48” (1219 mm)72” (1829 mm)
0–100% economizer72” (1829 mm)96” (2438 mm)
0–100% economizer with return fan 72” (1829 mm)96” (2438 mm)
047C077C
Figure 29: Unit Type RAH Lifting Points
4 Lifting Points
A
Z
X
Table 5: RDS X Dimension (See Figure 29) Outdoor/return
Air Section
0–100% economizer with 15" return fan 62" (1575 mm)—
0–100% economizer with 30" return fan 52" (1321 mm) 52" (1321 mm)
0–100% economizer with 40" return fan—80" (2032 mm)
Outdoor/return air section800C802C
100% OA00
Plenum40” (1016 mm) 52" (1321 mm)
0–30% OA40” (1016 mm) 52" (1321 mm)
0–100% economizer40” (1016 mm) 52" (1321 mm)
McQuay IM 98725
Mechanical Installation
Remove top cap and
save for reassembly.
Remove plywood and retaining
angles from unit and discard.
Discharge end of unit
Fan end of unit
Remove screws on fan panel,
leaving retainer clips in place.
Save screws for reassembly.
Split Units
Although units typically ship from the factory as complete
units, they can be factory split at the supply fan bulkhead and
connected later on the roof. This configuration is ordered if the
shipping length or a weight limitation prevents ordering a
packaged unit.
A single nameplate is attached to the air handler section and
power is supplied to both sections through the optional main
control box as in a packaged unit.
RAH Factory Split at Fan
Field reassembly of an RAH unit that shipped split at the fan
takes place in three phases: (1) setting the sections,
Figure 30: Set Sections
(2) mechanically recoupling the cabinet, and (3) reconnecting
power and control wiring.
Phase I. Set sections
1 Remove top cap and save for Phase II, Step 1.
2 Remove screws on fan panel, leaving retainer clips in
place to secure bulkhead. Save screws for Phase II,
Step 5.
3 Remove plywood and retaining angles from unit and
discard.
4 Carefully lower both sections of unit (fan end and
discharge end) into place, making sure the roof curb
engages the recesses in the unit base.
26McQuay IM 987
Phase II. Reassemble cabinet (Figure 31)
Reinstall top cap
saved in step 1
Caulk ends
of splice cap
See detail
Splice cover,
provided
#10 screws,
provided
Nut clip-on,
provided
Caulk
vertical
seam
Install screws
(.25 to 20 × .75)
saved from step 1
1 Reinstall top cap removed in Phase I, Step 1.
2 Caulk (watertight) ends of splice cap.
3 Caulk (watertight) vertical seam.
4 Install #10 screws (provided).
5 Install screws (.25–20 ×.75) removed in Phase I, Step 2.
6 Install splice cover (provided).
Figure 31: Reassemble Cabinet
Mechanical Installation
McQuay IM 98727
Mechanical Installation
If applicable, install as shown
with provided fasteners.
After routing wires,
install inner raceway
cover (see step 6).
3.72 ref.
(94 mm)
Phase III. Reconnect power and control wiring
Once the sections are physically reconnected, the ends of the
power harness are fed back through the unit base into the
junction box, per the unit’s electrical schematics.
CAUTION
Connect the power block correctly and maintain proper
phasing. Improper installation can cause severe equipment
damage.
1 Make electrical connections and reinstall inner raceway
cover as shown in Figure 32.
Figure 32: Electrical Connections and Raceway Cover
Installation
6 Reinstall the external raceway covers after routing of the
control wires is complete.
Field Refrigerant Piping and Charging of DX Coils
Units that ship from the factory with DX coils installed do not
include refrigerant piping or refrigerant controls. The coil
assembly is ready for field connections at the distributors and
at the suction headers. Piping kits that provide the necessary
liquid and hot gas piping and control components are available
for field installation. Field-installed refrigerant piping may exit
the unit cabinet at one of the following locations:
• Through the floor of the unit.
• Through the discharge and bulkhead of the unit.
• Through a cabinet door near the DX coil that is not required
for service areas.
CAUTION
For any of the above cabinet penetrations, tightly seal the hole
to prevent water or air leakage.
In preparing for field piping, remove the plastic plugs on the
distributors and unsweat the copper caps at the suction header
connections.
2
3 Run the control harnesses by removing the external
4 Remove the excess harness length from the external
5 Make all electrical connections per the unit’s electrical
When power wire reconnection is complete, reinstall the
inner raceway cover in the blank or heat section.
Figure 32 shows a typical installation of the raceway
cover.
raceway covers on either side of the unit split.
raceway on the downstream side of the split; then route
along the raceway, through the bushed hole in the fan
section and into the junction box where control wiring
terminal blocks are provided for reconnection.
schematics.
Follow piping design, sizing, and installation information
presented in ASHRAE handbooks in the design and
installation of interconnecting piping. The DX coil and
condensing unit are intended to be set at the same elevation, as
close as possible to each other to minimize refrigerant pressure
drop. Design piping to prevent liquid refrigerant carryover to
the compressor and to provide a continuous return of
compressor oil from the system.
CAUTION
The pounds of refrigerant in the system may exceed the
capacity of the condenser, depending on the amount of
refrigerant in the liquid lines between the DX coil and the
condensing unit.
Refer to condenser manufacturer for information about
refrigerant capacity. Suitable means of containing the
refrigerant is required.
CAUTION
To prevent liquid return and damage to the compressor on
systems with optional hot gas bypass, it is important to locate
the bypass solenoid valve at the condensing unit and not at the
DX coil.
28McQuay IM 987
Mechanical Installation
Piping Recommendations
1 Use type K or L clean copper tubing. Thoroughly clean
or braze all joints with high temperature solder.Base
piping sizes on temperature/pressure limitations as
recommended in the following paragraphs. Under no
circumstances should pipe size be based strictly upon
coil or condensing unit piping connection size.
2 Do not exceed suction line piping pressure drop
equivalent to 2°F (1°C), 3 psi (20.7 kPa) per 100 feet
(30.5 m) of equivalent pipe length. After the suction line
size is determined, check the vertical suction risers to
verify that oil will be carried up the riser and back to the
compressor. Pitch the suction line(s) in the direction of
refrigerant flow and make sure they are adequately
supported. Lines should be free draining and fully
insulated between the evaporator and the compressor.
Install a trap on the vertical riser to the compressor.
3 To determine the minimum tonnage required to carry oil
up suction risers of various sizes, check the vertical
suction risers using Table 6. Insulate suction lines inside
the unit cabinet to prevent condensation.
Table 6: Minimum Tonnage (R-22) to Carry Oil Up Suction
Riser at 40°F Saturated Suction
4 Size the liquid line for a pressure drop not to exceed
the pressure equivalent of 2°F (1°C), 6 psi (41.4 kPa)
saturated temperature.
Leak Testing
In the case of loss of the nitrogen holding charge, the unit
should be checked for leaks prior to charging the complete
system. If the full charge was lost, leak testing can be done by
charging the refrigerant into the unit to build the pressure to
approximately 10 psig and adding sufficient dry nitrogen to
bring the pressure to a maximum of 125 psig. The unit should
then be leak tested with halide or electronic leak detector.
After making any necessary repair, the system should be
evacuated as described in the following paragraphs.
WARNING
Do not use oxygen or air to build up pressure. Explosion hazard
can cause severe personal injury or death.
Evacuation
After determining the unit is tight and there are no refrigerant
leaks, evacuate the system. Use a vacuum pump with a
pumping capacity of approximately 3 cu.ft./min. and the
ability to reduce the vacuum in the unit to at least 1 mm (1000
microns).
1 Connect a mercury manometer or an electronic or other
type of micron gauge to the unit at a point remote from
the vacuum pump. For readings below 1 millimeter, use
an electronic or other micron gauge.
2 Use the triple evacuation method, which is particularly
helpful if the vacuum pump is unable to obtain the
desired 1 mm of vacuum. The system is first evacuated
to approximately 29" (740 mm) of mercury. Then add
enough refrigerant vapor to the system to bring the
pressure up to 0 pounds (0 microns).
3 Evacuate the system again to 29" (740 mm) of vacuum.
Repeat his procedure three times. This method is most
effective by holding system pressure at 0 pounds
(0 microns) for a minimum of 1 hour between
evacuations. The first pulldown removes about 90% of
the noncondensables; the second removes about 90% of
that remaining from the first pulldown. After the third
pulldown, only 1/10 of 1% of noncondensables remains.
Table 7, page 30 shows the relationship between pressure,
microns, atmospheres, and the boiling point of water.
CAUTION
Before replacing refrigerant sensors or protective devices, see
"Refrigerant Charge"‚ page 31 for an important warning to
Units are leak tested at the factory and shipped with a nitrogen
holding charge. If the holding charge has been lost due to
shipping damage, charge the system with enough refrigerant to
raise the unit pressure to 30 psig after first repairing the leaks
and evacuating the system.
1 After all refrigerant piping is complete and the system is
evacuated, it can be charged as described in the
paragraphs following. Connect the refrigerant drum to
the gauge port on the liquid shutoff valve and purge the
charging line between the refrigerant cylinder and the
valve. Then open the valve to the mid position.
2 If the system is under a vacuum, stand the refrigerant
drum with the connection up, open the drum, and break
the vacuum with refrigerant gas.
3 With a system gas pressure higher than the equivalent of
a freezing temperature, invert the charging cylinder and
elevate the drum above the condenser. With the drum in
this position and the valves open, liquid refrigerant flows
into the condenser. Approximately 75% of the total
requirement estimated for the unit can be charged in this
manner.
4 After 75% of the required charge enters the condenser,
reconnect the refrigerant drum and charging line to the
suction side of the system. Again, purge the connecting
line, stand the drum with the connection side up, and
place the service valve in the open position.
Important: At this point, interrupt the charging procedure and
do prestart checks before attempting to complete the
refrigerant charge.
Note: Stamp the total operating charge per circuit on the unit
nameplate for future reference.
CAUTION
Adding refrigerant to the suction always risks liquid-related
damage to the compressor.
Take special care to add refrigerant slowly enough to the
suction to prevent damage. Adjust the charging tank hand
valve so liquid leaves the tank but vapor enters the compressor.
30McQuay IM 987
Loading...
+ 92 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.