In-Warranty Return Material Procedure................... 105
Introduction
This manual provides general information about the “C”
vintage McQuay RoofPak applied rooftop unit, models RDE
and RPE. In addition to an overall description of the unit, it
includes mechanical and electrical installation procedures,
commissioning procedures, sequence of operation information,
and maintenance instructions. For further information on the
optional forced draft gas-fired furnace, refer to Bulletin No.
IM 684 or IM 685.
The MicroTech II applied rooftop unit controller is available
on “C” vintage applied rooftop units. For a detailed description
of the MicroTech II components, input/output configurations,
field wiring options and requirements, and service procedures,
refer to IM696 for a description of operation and information
on using and programming the MicroTech II unit controller,
refer to the appropriate operation manual (see Figure 1).
For a description of operation and information on using the
keypad to view data and set parameters, refer to the
appropriate program-specific operation manual (see Figure 1).
Table 1: Operation Manuals
UnitManual
VFD’sVendor IM Manuals
Discharge Air Control (VAV or CAV) OM 137
Space Comfort Control
(CAV-Zone Temperature Control)
Non-Chemical Water Treatment OptionIM 827
OM 138
Introduction
Unit Nameplate
The unit nameplate is located on the outside lower right corner
on the main control box door. It includes the unit model
number, serial number, unit part number, electrical
characteristics, and refrigerant charge.
Gas Burner Nameplate
On units which include gas heat, the nameplate is located on
the lower right corner on the main control box door. It includes
the burner model number, minimum/maximum input,
maximum temperature rise and minimum CFM.
Hazard Identification Information
WARNING
Warnings are provided throughout this manual to indicate to
installing contractors, operators, and service personnel
potentially hazardous situatio n s wh i c h, if no t avo i d ed , ca n
result in severe personal injury or property damage.
CAUTION
Cautions are provided throughout this manual to indicate to
installing contractors, operators, and service personnel
potentially hazardous situatio n s wh i c h, if no t avo i d ed , ca n
result in personal injury or equipment damage.
Nomenclature
RoofPak
Unit Configuration
P = Blow through Cooling
D = Draw through Cooling
Evaporative Condensers
Nominal Capacity (Tons)
RPE, RDE: 076, 089, 100, 110, 130, 140, 150
R P E - 150 C S E
Heat Medium
A = Natural Gas
E = Electric
S = Steam
W = Hot Water
Y = None (Cooling Only)
Cooling Coil Size
S = Standard (Low Airflow)
L = Large (High Airflow)
Design Vintage
McQuay IM 791-23
Introduction
Unit Description
Typical Component Lo ca tio ns
Figure 1 shows a typical RPE unit with the locations of the
major components. Figure 2, page 4 shows a typical RDE unit
Figure 1: Typical Component Locations - RPE Units
with the locations of the major components. These figures are
for reference only. See the certified submittals for actual
specific dimensions.
Figure 2: Component Locations - RDE Units
4McQuay IM 791-2
Condenser Fan Arrangement
Table 2 shows the condenser fan numbering conventions and
Spray System Plumbing with Optional Non-Chemical Water Treatment
WARNING
Failure to maintain and continually provide water
treatment may result in severe equipment damage and
may create biologically hazardous conditions. See
Figure 26 for water connection sizes and locations.
Figure 6: Spray System Piping
NOTE:
The cyclone separator is on a side stream. A hand
valve controls water flow. The hand valve should be
opened until the inlet pressure to the separator is
about 12 psi as determined by the factory-installed
gauge. This will yield about 20 gpm of blowdown
whenever the blowdown solenoid opens.
Dolphin
makeup water
Dolphin sump water
treatment module
Dolphin
sump water
transformer
To Spraybar
transformer
Introduction
To Spraybar
Conductivity sensor
Conductivity controller
Makeup water
control valve
Auto purge controller
Flowmeter
Cyclone seperator
Sump
overflow
Ball valve
actuators
Heat-tape all components
from customer connection
point to makeup water
control valve
Dolphin makeup water
treatment module
Makeup water connection
point to sump tank.
Cleanout
Customer makeup
water connection point
Manual shutoff
Sump Pump
McQuay IM 791-29
Freeze protection
valve and actuator
Blow down and drain
Introduction
Bleed Off and Water Consumption
Controlled bleed off [or blow down] is required on McQuay
RPE/ RDE units as it should be with all evaporative
condensing products. It involves draining off a portion of the
highly concentrated water from the bottom of the sump and
replacing it with lower concentration make-up water to inhibit
scale. Scale protection is required because the evaporation
process leaves behind solids (scale) that will coat the heat
exchanger surfaces and sump. This reduces the capacity,
efficiency, and life expectancy of the equipment.
Manual bleed off occurs whenever the spray pump operates. A
manual valve adjusts flow and is provided as standard. Refer
to Figure 6. This inevitably bleeds off too much [increased
water costs] or too little [risking scale build up] water.
Automatic bleed off control is superior and usually is provided
with the water treatment system.
Theoretical water consumption required for proper heat
rejection is 1.8 gallons per ton hour. All of this water
evaporates and none goes into the sewer. An additional 0.6 to
0.9 gallons per ton hour (.03 to .05 with McQuay nonchemical water treatment) is also required for make up and
bleed off. The exact amount should be determined by water
Figure 7: Control Locations - RPE Units
analysis. The RPE/ RDE includes a float valve and solenoid
that automatically refills the sump as required.
Bleed off must be handled in accordance with local codes and
normally is drained into the sanitary sewer. Normally, this
water should not be drained onto the roof or into a storm drain.
One possible exception to this is with the McQuay nonchemical water treatment option (consult local codes
carefully). Because most water utilities charge for both intake
and sewer water flows based on intake meter readings, sewer
charges may be reduced if sewer flow is proven to be less than
water intake. McQuay offers both intake and bleed off water
meters to document reduced sewer flow [confirm details with
your local utility]. These meters are not included in the basic
water treatment option.
Control Locations
Figure 7 (RPE Units) and Figure 8, page 11 (RDE Units) show
the locations of the various control components mounted
throughout the units. See Control Locations‚ page 10 for the
locations of control components mounted in control panels.
Additional information is included in Table 3, page 15 and the
Legend‚ page 47.
Return Air
Economizer
Heat
Section
Discharge
Plenum
Section
HL22 (Optional)
LT10 (Optional)
S10, REC10 (Optional)
Service
Section
SD1
(Optional)
Condensor
Section
VM1
(Optional)
Exhaust
Fan
Water Treatment
(Optional)
Oil Pressure Box
Water Pump
Control Box
Space Heater
(Optional)
Water Level
Switches
(WL63, WL64)
Sump Heater (Optional)
Sump Water Temp Sensor
ACT5 (optional)
ACT6 (optional)
OAT
LT11
(Optional)
S11
REC11
OAE
RAE (optional)
10McQuay IM 791-2
Figure 8: Control Locations - RDE Units
(
)
C
ondensor
Section
Introduction
C19,20
(Optional)
Economizer
Return Air
Filter
Section
Heat
Section
SV1, 2
Supply Fan
Discharge
Plenum
Section
OAE
OAT
Service
Section
FS1
(Optional)
LT10 (Optional)
S10, REC10 (Optional)
SD1 (Optional)
Exhaust
Fan
Water Treatment
(Optional)
Water Pump
Control Box
Space Heater
(Optional)
Sump Heater (Optional)
Sump Water Temp Sensor
Oil Pressure Box
Water Level
Switches
(WL63, WL64)
LT11 (Optional)
S11, REC11
SD2
Optional
McQuay IM 791-211
Introduction
Control Panel Locations
The unit control panels and their locations are shown in the
following figures. These figures show a typical unit
configuration. Specific unit configurations may differ slightly
from these figures depending on the particular unit options.
See Wiring Diagrams‚ page 47 for the Legend and component
description.
Figure 9: Control Panel Locations - Service Compartment
WARNING
Electrical shock can cause severe personal injury or
death.
The control panel must be serviced by trained, experienced
technicians.
Oil
Pressure
Instruments
Control
Panel
Power
Disconnect
12McQuay IM 791-2
Figure 10: Main Control Panel - 076C - 150C
Introduction
See page page 47 for Legend
UP
for Control
Connections
Terminal Block
2 Feet to Floor
Main Disconnect
or Power Block
McQuay IM 791-213
Introduction
Figure 11: Electric Heat Control Panel - Sizes 075C- 135C
FB31FB32FB33
M31M32M33
FB34FB44
M34M44
FB41FB42FB43
M41M42M43
GLG3
DS3
H53
TB11
• The manual shutter is normally be closed but can be opened
to condition the compartment when service is needed.
Figure 12: Walk-In Service Compartment
Perform Most Refrigerant Service in Comfort, Away
From Compressor Noise
Marine Lights
Exhaust Fan
Optional Unit
Heater
Walk-In Service Compartment
Each unit includes a walk-in service compartment containing
the following:
• Main control panel.See Figure 9, page 12.
• Liquid Line components except the expansion valve.
• Spray pumps, water control valves (except float valves in the
sump) and water supply and sanitary connections. See
Figure 6, page 9.
• Water treatment system (optional).
• Main access door opened from the inside and outside.
• Raised service grate to help protect service personnel against
water and chemical spills.
• Refrigerant Schrader ports are provided on the liquid and
suction lines to allow for easy refrigerant pressure readings,
however, discharge pressure at the compressor must be
measured outside the enclosure.
• Refrigerant charge can be added at the Schrader connections
in the compartment.
• Lights, ventilation fans, manual shutter that can be opened to
allow conditioned air into the plenum and optional unit
heater provide more comfortable servicing.
• An adjustable TC66 thermostat turns on the ventilation fan
when the compartment temperature exceeds 75°F.
• An adjustable integral thermostat runs the unit heater when
Used to compare return air
enthalpy to outside air enthalpy
(used with OAE)
Senses return air temperatureN/A
Initiates unit shutdown if smoke
is detected
Initiates unit shutdown if smoke
is detected
Converts static pressure
signals to voltage signals
Converts static pressure
signals to voltage signals and
sends them to MicroTech II
controller
Converts static pressure
signals to voltage signals.
Controls Wa ter Temp in the
Evap Condenser Sump
Closes liquid line for
pumpdown
Closes hot gas bypass line for
pump-down
Open when sump water level is
low to add water
Opens to drain sumpN/AService
Sensor for freeze and head
pressure control
Shuts off entire control circuit
(except crankcase heaters)
Used to manually switch unit N/A
Sequences the vestibule
exhaust fan
Maintains proper water levelN/ASump Holding
Auto
N/A
N/A
Manual
Manual
N/A
N/A
N/A
N/A
N/A
N/AService
N/ASump Holding
N/A
N/AService
Supply fan
section
Condenser
control box
Economizer
section
Return air
section
Discharge air
section
Return air
section
Main control
box
Main control
box
Main control
box
Sump Holding
Tank
Condenser
section
Condenser
section
Compartment
Compartment
Tank
Main control
box
Main control
box
Compartment
Tank
Tank
.10" wc (25
Pa)
N/AN/AN/A01355000
N/AN/AN/A049262202
N/AN/A060004705
N/AN/AN/A04925001
N/AN/AN/A04925001
N/A
N/A
N/A
N/AN/AN/A
N/AN/AN/A111011001
N/AN/AN/A
N/AN/AN/A
N/AN/AN/ASee parts
N/AN/AN/A001355000
N/AN/AN/A
N/AN/AN/A
N/AN/AN/ASee parts
N/AN/AN/ASee parts
.05-5" wc
(12.5–1245.4
Pa)
0–5" wc
(0–1245.4 Pa)
1–6 VDC out
0–5" wc
(0–1245.4 Pa)
1–6 VDC out
-025–0.25" wc
(-62.3–62.3 Pa)
1–5 VDC out
.05" wc
(12.5 Pa),
fixed
N/A049545007
N/A049545007
N/A049545006
060015801
See parts
See parts
See parts
See parts
See parts
See parts
catalog
catalog
catalog
catalog
catalog
catalog
catalog
catalog
catalog
16McQuay IM 791-2
Mechanical Installation
S
d
p
The installation of this equipment must be in accordance with
the regulations of authorities having jurisdiction and all
applicable codes. It is the responsibility of the installer to
determine and follow the applicable codes.
WARNING
Improper installation, adjustment, alteration se r v ic e or
maintenance can cause personal inju ry or death.
Read and understand this Installation and Maintenance
manual thoroughly before installing or servicing this
equipment.
Note: Low head pressure may lead to poor, erratic refrigerant
feed control at the thermostatic expansion valve. The
units have automatic control of the condenser fans which
should provide adequate head pressure control down to
50°F (10°C). The system designer is responsible for
assuring the condensing section is not exposed to
excessive wind or air recirculation.
WARNING
Sharp edges and coil surfaces can cause personal
injury. Avoid contact with them.
Installation and maintenance must be performed only by
trained and experienced personnel familiar with local codes
and regulations.
WARNING
Sharp edges on sheet metal, screws and clips can cause
personal injury.
This equipment must be installed and operated only by
experienced trained personnel.
Mechanical Installation
Receiving Inspection
When the equipment is received, check all items against the
bill of lading to be sure all crates and cartons have been
received. If the unit has become dirty during shipment
(winter road chemicals are of particular concern), clean it
when received.
Inspect all units for damage when received. Report all
shipping damage to the carrier and file a claim. In most cases,
equipment is shipped F.O.B. factory and claims for freight
damage should be filed by the receiver.
The unit nameplate should be checked before unloading the
unit to make sure the voltage complies with the power supply
available.
Unit Clearances
Service Clearance
Allow service clearance approximately as indicated in
Figure 13. Also, a roof walkway should be provided to the
rooftop unit and along at least the two sides of the unit that
provide access to most controls and serviceable components.
NOTICE
On units with side discharge, access to plenum mounted
components becomes difficult once ductwork is installed.
Installer must provide access in the ductwork for plenum
mounted controls.
Figure 13: Service Clearances Side Discharge
72"
4 sides except as indicated
ABCDEFG
24"
Roof Walkway
Adjacent to Cooling Coil,
Heat, and Supply
Fan Sections.
ervice Clearance on
Legend:
A = Return Air Section
B = Filter Section
C = Cooling Section
D = Cooling/Supply Fan Section
E = Heat Section
F = Discharge Plenum Section
G = Service Com
artment
72" Clearance to
end of unit or en
of outside hood
McQuay IM 791-217
Mechanical Installation
Maxi
All
Figure 14: Side Discharge
V entilation Clearance
Following are minimum ventilation clearance
recommendations. The system designer must consider each
application and provide adequate ventilation. If this is not
done, the unit will not perform properly.
Unit(s) surrounded by a screen or a fence:
1 The bottom of the screen or fence should be at least 1 ft.
(305 mm) above the roof surface.
2 The distance between the unit and a screen or fence should
be as described in Service Clearance‚ page 17. See also
Figure 13, page 17.
3 The distance between any two units within a screen or
fence should be at least 120" (3048 mm).
Unit(s) surrounded by solid walls:
1 If there are walls on one or two adjacent sides of the unit,
the walls may be any height. If there are walls on more than
two adjacent sides of the unit, the walls should not be
higher than the unit.
2 The distance between the unit and the wall should be at
least 96" (2438 mm) on all sides of the unit.
3 The distance between any two units within the walls should
be at least 120" (3048 mm). Do not locate outside air
intakes near exhaust vents or other sources of contaminated
air.
If the unit is installed where windy conditions are common,
wind screens should be installed around the unit, maintaining
the clearances specified (see Figure 15). This is particularly
important to prevent blowing snow from entering outside air
intakes, and to maintain adequate head pressure control when
mechanical cooling is required at low outdoor air
temperatures.
Overhead clearance
1 Unit(s) surrounded by screens or solid walls must have no
overhead obstructions over any part of the unit.
2 The area above the condenser must be unobstructed in all
installations to allow vertical air discharge.
3 The following restrictions must be observed for overhead
obstructions above the air handler section (see Figure 15):
a There must be no overhead obstructions above the
furnace flue, or within 9" (229 mm) of the flue box.
b Overhead obstructions must be no less than 2" (51 mm)
above the top of the unit.
c There must be no overhead obstructions in the areas
above the outside air and exhaust dampers that are
farther than 24" (610 mm) from the side of the unit.
Figure 15: Overhead Clearance
mum
owable
9" (229mm) Min to Flue Box
Typical All Sides
24" (610 mm)
Maximum
2" (51mm)
Top of Unit
To O verhead
Obstruction
Overhead Canopy Area
Flue Box
18McQuay IM 791-2
Mechanical Installation
Roof Curb Assembly and Installation
The roof curb and unit must be located on a portion of the roof
that can support the weight of the unit. The unit must be
supported to prevent bending or twisting of the machine.
If building construction could allow the transmission of sound
and vibration into the occupied space, the unit should be
located over a non-critical area. It is the responsibility of
the system designer to make adequate provisions for noise
and vibration in the occupied space.
The curb and unit must be installed level to allow the
condensate drain to flow properly.
Integral supply and return air duct flanges are provided with
the RPE/RDE roof curb, allowing connection of ductwork to
the curb before the unit is set. The gasketed top surface of the
duct flanges seals against the unit when it is set on the curb.
These flanges must not support the total weight of the
ductwork. Refer toInstalling Ductwork‚ page 32 for details on
duct connections. It is critical that the condensate drain side of
the unit be no higher than the opposite side.
Assembly of a typical RPE/RDE roof curb is shown in
Figure 17, page 21. Parts A through K are common to all units
having bottom return openings. Depending on the unit length,
Parts L and M may be included with the roof curb kit to create
the correct overall curb length.
RPE/RDE Assembly instructions
Refer to Figure 17, page 21.
1 Set curbing parts A through K per dimensions shown over
roof opening or on a level surface. Note location of return
and supply air openings.
2 If applicable, set other curbing parts (D, L, M, etc.) in place
making sure that the orientation complies with the
assembly instructions. Check alignment of all mating bolt
holes.
3 Bolt curbing parts together using fasteners provided.
Tighten all bolts finger tight.
4 Square entire curbing assembly and securely tighten all
bolts.
5 Position curb assembly over roof openings. Curb must be
level from side to side and over its length. Check that top
surface of the curb is flat with no bowing or sagging.
6 W eld curbing in place. Caulk all seams watertight. Remove
backing from 0.25" (6 mm) thick x 1.50" (38 mm) wide
gasketing and apply to surfaces shown by notes.
7 Flash curbing into roof as shown in Detail “B”.
8 Parts E and F are not required on units with no return shaft
within the curb perimeter.
9 Parts G and H are not required on units with no supply shaft
within the curb perimeter.
McQuay IM 791-219
Mechanical Installation
Figure 16: RPE/RDE Roof Curb Assembly
RDE & RPE 076-100
D
SA
OPENING
OPENING
N
P
C
RA
SEE FIGURE "A"
G
F
E
F
R
Q
H
J
K
L
K
M
B
RDE & RPE 110-150
G
F
E
C
RA
OPENING
D
SA
OPENING
R
Q
H
K
L
L
K
F
N
P
SEE FIGURE "A"
J
M
B
B
M
Dim076-100C 110-150C
J
100.00100.00
84.0060.00
62.0062.00
38.0046.00
87.0087.00
1.501.50
6.806.80
81.0081.00
7.507.50
5.005.00
8.008.00
2.002.00
4.004.00
1.501.50
78.8078.80
B
C
D
E
F
G
H
K
L
M
N
P
Q
R
20McQuay IM 791-2
Figure 17: RPE/RDE Roof Curb Assembly
Using remaining side supports
in this area, align lengths on
opposite sides of assembly
and install a cross support
at each side.
Equal Length
Side Supports
See Detail "A"
B
Mechanical Installation
Condenser
Section Support
(1 of 2 shown)
A
A
38.8"
B
Return
Air
85"
62.8"
Section B-B
Section A-A
2
1
2
5
4
9
10
6
7
10
3
9
6
8
4
1. Unit Base
2. Curb Gasketing
3. 2 x 4 Nailer Strip
4. Galvanized Curb
5. Duct Support
6. Cant Strip (not furnished)
7. Roofing Material (not furnished)
8. Rigid Insulation (not furnished)
9. Counter flashing (not furnished)
10. Flashing (not furnished)
2
2
3
5
4
1
9
10
6
7
8
McQuay IM 791-221
Mechanical Installation
Post and Rail Mounting
When mounting by post and rail, the structural support should
be run the full length of the unit. Locate the structural member
at the base of the unit as shown in Figure 18 assuring the
shaded area is well supported by the structural member.
CAUTION
The unit must be level side to side and over the entire
length. Equipment damage can result if the unit is not level.
If resilient material is placed between the unit and the rail,
insert a heavy steel plate between the unit and the resilient
material to distribute the load. Properly seal cabinet
penetrations (electrical, piping, etc.) to protect against
moisture and weather.
Figure 18: Post and Rail Mounting
max
4 Provide adequate protection from vandalism, mechanical
contact, etc.
5 Securely close the doors.
6 If there are isolation dampers, make sure they are properly
installed and fully closed to prevent the entry of animals
and debris through the supply and return air openings.
7 Cover the supply and return air openings on units without
isolation dampers.
Figure 19 shows an example of the rigging instruction label
shipped with each unit.
WARNING
Use all lifting points. Severe personal injury and
property damage can result from improp er lifting
adjustment.
Figure 19: Rigging and Handling Instruction Label
Rigging and Handling Instructions
Unit has either four or six lifting points (four-point shown below).
Caution: All lifting points must be used.
Rigging cables must be at least as long as distance "A".
Note:
*Rail cannot extend beneath the unit more than 5" (127 mm) or it will interfere
with duct and electrical connections.
Rigging and Handling
Lifting brackets with 2" (51 mm) diameter holes are provided
on the sides of the unit.
Use spreader bars, 96" to 100" (2438 to 2540 mm) wide to
prevent damage to the unit cabinet. Avoid twisting or uneven
lifting of the unit. The cable length from the bracket to the
hook should always be longer than the distance between the
outer lifting points.
If the unit must be stored at the construction site for an
intermediate period, these additional precautions should be
taken:
1 Make sure to support the unit well along the length of the
base rail.
2 Make sure to level the unit
(no twists or uneven ground surface).
3 Provide proper drainage around the unit to prevent flooding
of the equipment.
Caution:
Lifting points may not
be symmetrical to center of
gravity of unit. Balast or unequal
Lift Only As Indicated
cable lengths may be required
Lifting Points
Refer to Figure 20 and the following calculations to determine
whether a four or six point lift is required.
X= Distance from the entering air end of the unit (or shipping
section) to the first lifting lug in the direction of air flow.
For all units or shipping sections with outdoor air/return air
options, X= 48"
For shipping sections without outdoor air/return air options,
X= 0
Y= distance from condenser or leaving air end of unit to the
last lifting lug.
For all units or shipping sections with condensers, Y= 21.5
(sizes 76-100) or Y= 60.2 (sizes 110-150).
For all units or shipping sections without condensers, Y=0Z= Total base rail length of the unit. Note: Z excludes hoods
and overhung parts extending past base rails of the unit.
22McQuay IM 791-2
Mechanical Installation
A= Z-X-Y
If A<288", 4-point lift is sufficient
If A>288", 6-point lift is required
B= Distance from first lifting lug to middle lifting lug on units
with 6-point lift.
B= A/2 +/- 48" Note: Middle lifting lug may be installed on
either side of the midpoint to avoid interference with
condensate drains.
Figure 20: Unit Type RPE/RDE Lifting Points
Figure 21: RPE/RDE Factory Split at Supply Fan Section
McQuay IM 791-223
Mechanical Installation
Reassembly of Split Units
Although RoofPak units typically ship from the factory as
complete units, they may be split at the factory.
The RPE/RDE unit may ship from the factory as two pieces,
split at the supply fan bulkhead, to be recoupled together on
the roof. This configuration would be ordered if shipping
length or weight limitation prevented a packaged RPE/RDE
from being ordered. Splitting at the fan has the advantage of
leaving all factory refrigerant piping intact so field evacuation
and charging is not required.
A single nameplate is attached to the air handler section and
power is fed to both sections through the main control box, as
it would be in a non-split RPE/RDE unit.
RPE/RDE Factory Split at Fan
Field reassembly of an RPE/RDE unit that has shipped split at
the fan takes place in two phases:
Phase 1 - Setting the Sections and Cabinet
Reassembly
The steps required to set the unit and reassemble the cabinet
are shown in Figure 22, Figure 23, and Figure 24, page 25.
The following items should be noted:
1 Top cap and plywood covers must be removed before the
sections are set together, but the steel retainer clips must be
left in place to secure the bulkhead. Refer to Step 1 and
Figure 22.
2 Both sections must be carefully lowered into place to make
sure that the roof curb engages the recesses in the unit base.
3 All seams at the split must be caulked watertight after
recoupling the sections, as shown in Step 3 and Figure 23,
page 25.
WARNING
Improper installation can cause severe equipment
damage, personal injury or death.
Connect the power block correctly and maintain proper
phasing.
When reconnection of the power wires is complete, the inner
raceway cover in the blank or heat section must be reinstalled.
Figure 24, page 25 shows a typical installation of the raceway
cover. If the unit is equipped with a fan diffuser, install as
shown in Figure 24.
Control harnesses can be run by removing the external
raceway covers on either side of the unit split. The excess
harness length can be removed from the external raceway on
the DX side of the split, routed along the raceway through the
bushed hole in the fan section and into the junction box where
control wiring terminal blocks are provided for reconnection.
All electrical connections should be made per the unit's
electrical schematics. Reinstall the external raceway covers
after routing of the control wires is complete.
1 Prepare the units for reassembly as shown in Figure 22.
Figure 22: RPE/RDE Split at Fan Reassembly - Step 1
R e m o v e p l y w o o d a n d r e t a i n i n g
R e m o v e t o p c a p a n d
s a v e f o r s t e p 3
a n g l e s f r o m u n i t a n d d i s c a r d
D i s c h a r g e e n
d o f U n i t
Phase 2 - Reconnecting Power and Control Wiring
The DX coil/condenser section contains power and control
harnesses which have their excess length in the blank or heat
section that is normally immediately downstream of the fan.
Once the sections are physically reconnected, the ends of the
F a n e n d o f U n i t
power harness are fed back through the unit base into the
junction box, per the unit’s electrical schematics.
24McQuay IM 791-2
2
Set fan end of unit and discharge end of unit in place.
3 Caulk and install parts as shown in Figure 23.
R e m o v e s c r e w s o n f a n p a n e l , b u t
l e a v e r e t a i n e r c l i p s i n p l a c e ;
s a v e s c r e w s f o r
S t e p 3 .
Mechanical Installation
ovided
Figure 23: Split at Fan Reassembly - Step 3
Reinstall Top Cap
Saved from Step 1
Caulk Ends of
Splice Cap
Splice Cover
Provided
Install
#10 Screws
Provided
Figure 24: RPE Split at Fan Reassembly - Step 4
Install Screws (.250-20 x .75)
Saved from Step 1
Nut
Clip-on
Pr
4
Make electrical connections and reinstall Inner Raceway
Cover as shown in Figure 24.
McQuay IM 791-225
Mechanical Installation
Condensate Drain Connection
The unit is provided with a 1.5" male NPT condensate drain
connection. Refer to certified drawings for the exact location.
The unit and drain pan must be level side to side and a P-trap
must be installed for proper drainage.
RPE units may have positive or negative pressure sections.
Traps should be used in both cases, with care given to negative
pressure sections. In Figure 25, page 26, dimension “A”
should be a minimum of 8" (203 mm). So the cabinet static
pressure does not blow or draw the water out of the trap and
cause air leakage, dimension A should be two times the
maximum static pressure encountered in the coil section in
inches w.c.
Drainage of condensate directly onto the roof may be
acceptable; refer to local codes. A small drip pad of stone,
mortar, wood or metal be should be provided to protect the
roof against possible damage.
If condensate is to be piped into the building drainage system,
the drain line should be pitched away from the unit at a
minimum of 1/8" per foot. The drain line must penetrate the
roof external to the unit. Refer to local codes for additional
requirements. Sealed drain lines require venting to provide
proper condensate flow.
Where the cooling coils have intermediate condensate pans on
the face of the evaporator coil, copper tubes near both ends of
the coil provide drainage to the main drain pan. Check that the
copper tubes are in place and open before the unit is put into
operation.
Because drain pans in any air conditioning unit will have some
moisture in them, algae, etc. will grow. Periodic cleaning is
necessary to prevent this buildup from plugging the drain and
causing the drain pan to overflow. Also, the drain pans should
be kept clean to prevent the spread of disease. Cleaning must
be performed by qualified personnel.
WARNING
Clean drain pans regularly. Growth in uncleaned drain
pans can cause disease.
Cleaning must be done by trained, experienced personnel.
Figure 25: Condensate Drain Connection
S e e V i e w " A "
C o p p e r T u b e
( o n e e a c h e n d o f c o i l )
S t a t i c P r e s s u r e " P "
4 " ( 1 0 2 m m )
M i n i m u m
" A "
8 " ( 2 0 3 m m )
M i n . o r 2 x " P "
( i n . w . o . )
D r a i n P a n
N o t e : D r a i n l i n e m u s t
n o t b e r u n h i g h e r
t h a n t h i s l e v e l
M i n i m i z e T h i s
e n s i o n
D i m
Unit Piping
Gas Piping
See the “Installation” section of the gas-fired furnace
installation manual, Bulletin No. IM684 or IM685.
Supply Water
City water must be piped into the service section of the unit.
Install a manual shutoff valve to facilitate service of the unit.
Provisions have been made to pipe through the floor of the
service section within the curb. If the unit will be exposed to
low outdoor air conditions, care must be taken to prevent
freeze damage to this piping.
The service section has an optional heater to minimize freeze
problems during cold weather. Verify that this heater functions
before filling the unit. A sump heater option is also offered that
includes heat tape on the pressure side of the float controlled
fill valve, plus an extra 8 feet of heat tape to protect field
connections inside the service compartment.
If the unit is mounted on post and rail structure, pipe will be
exposed to outdoor conditions and will need to be heat taped
or drained manually during the winter season.
26McQuay IM 791-2
Mechanical Installation
Drain Water
A drain and bleed off connection is also located in the service
section of the unit. Since this water will contain water
treatment chemicals, local codes may require connection to the
sanitary sewer. The freeze warning for supply water also
applies to drain water piping.
Figure 26: Unit Piping Knockout Locations
Discharge
Air
Opening
A
7.87
6.88
9.26
DETAIL A
SCALE 1 : 9
4.75
2.25
6.75
4.75
Note: Make sure that a service compartment heater and
especially a sump heater or some type of freeze
protection have been provided if freezing conditions are
expected.
Walk-in
Vestibule
CONTROL
WIRING
.88" KNOCKOUT
(3)
B
C ondensing
SUPPLY
WATER
3.0" KNOCKOUT
(.75" COPPER
CONN ECTION)
Unit
7.87
26.50
DETAIL B
SCALE 1 : 9
21.50
3.0" KNOCKOUT
(2)
Water Treatment
WARNING
Failure to maintain and continually provide water
treatment will result in severe equipment damage and
may create biologically hazardous conditions.
Water treatment, whether ordered as an option on the unit or
purchased separately, must be properly installed and started
before starting the unit. Failure to do so will result in scale
build up on the condenser tubes with a resulting loss in heat
rejection capacity. In severe cases, it may become impossible
to operate the compressors. In addition, untreated cooling
tower water can be a source for airborne disease.
Proper water treatment must include the following minimum
features:
• Bleed Off
• Scale and corrosion inhibitor chemical treatment
• Biocide chemical treatment
See Catalog 219 for information on the optional McQuay
supplied water treatment systems.
POWER WIRES
72.00
(REFERENCE)
DRAIN
WATER
3.0" KNOCKOUT
(2.0" PVC C ONNEC TION)
Hot Water Coil Piping
Hot water coils either are provided without valves for field
piping or are piped with three-way valves and actuator motors.
Note: If the unit is equipped with an iron valve, connecting to a
copper piping system will likely cause galvanic corrosion to
occur and the valve will not last. All coils have vents and
drains factory installed.
Hot water coils are not normally recommended for use with
entering air temperatures below 40°F (4°C). No control system
can guarantee a 100% safeguard against coil freeze-up. Glycol
solutions or brines are the only freeze-safe media for operation
of water coils at low entering air temperature conditions.
When no factory piping or valve is included, the coil
connections are 2-1/8" copper (two supply and two return).
With the factory piping and valve package, field piping
connections are the same NPT size as the valve with female
threading (see Figure 27, page 28).
Refer to the certified drawings for the recommended piping
entrance locations. All piping penetrations must be sealed to
prevent air and water leakage.
Note: The valve actuator spring returns to a stem down
position upon power failure. This allows full flow through
the coil.
McQuay IM 791-227
Mechanical Installation
CAUTION
Coil freeze possible. Possible equipment damage.
Carefully read and follow instructions for mixing antifreeze
solution. Some products will have higher freezing points in
their natural state than when mixed with water. The freezing
of coils is not the responsibility of McQuay International.
Figure 27: Hot Water Valve Package
R e t u r n
Figure 28: Hot Water Heat Section (Factory Valve/Piping)
B y p a s s
S u p p l y
Refer to the certified drawings for the recommended piping
entrance locations. All piping penetrations must be sealed to
prevent air and water leakage.
Note: The valve actuator spring returns to a stem up position
upon power failure. This allows full flow through the coil.
Steam Piping Recommendations
1 Be certain that adequate piping flexibility is provided.
Stresses resulting from expansion of closely coupled piping
and coil arrangement can cause serious damage.
2 Do not reduce pipe size at the coil return connection. Carry
return connection size through the dirt pocket, making the
reduction at the branch leading to the trap.
3 Install vacuum breakers on all applications to prevent
retaining condensate in the coil. Generally, connect the
vacuum breaker between the coil inlet and the return main.
However, if the system has a flooded return main, the
vacuum breaker should be open to the atmosphere and the
trap design should allow venting of large quantities of air.
4 Do not drain steam mains or takeoffs through coils. Drain
mains ahead of coils through a steam trap to the return line.
5 Do not attempt to lift condensate.
6 Pitch all supply and return steam piping down a minimum
of 1" (25 mm) per 10 feet (3 m) of direction of flow.
Steam Coil Piping
Steam coils either are provided without valves for field piping,
or are piped with two-way valves and actuator motors.
The steam coil is pitched at 1/8" (3 mm) per foot (305 mm) to
provide positive condensate removal. When no factory piping
or valve is included, the coil connections are 2.5" male NPT
iron pipe.
With the factory piping and valve package, the field supply
connection is the same NPT size as the valve with female
threading (see Figure 30, page 29).
Steam Trap Recommendations
1 Size traps in accordance with manufacturers'
recommendations. Be certain that the required pressure
differential will always be available. Do not undersize.
2 Float and thermostatic or bucket traps are recommended for
low pressure steam. Use bucket traps on systems with onoff control only.
3 Locate traps at least 12" (305 mm) below the coil return
connection.
4 Always install strainers as closely as possible to the inlet
side of the trap.
5 A single tap may generally be used for coils piped in
parallel, but an individual trap for each coil is preferred.
Steam Coil Freeze Conditions
If the air entering the steam coil is below 35°F (2°C), note the
following recommendations:
1 1.5 psi (34.5 kPa) steam must be supplied to coils at all
times.
2 Do not use modulating valves. Control should be by means
of face and bypass dampers.
3 As additional protection against freeze-up, the tap should
be installed sufficiently far below the coil to provide an
adequate hydrostatic head to provide removal of
condensate during an interruption on the steam pressure.
Estimate 3 ft. (914 mm) for each 1 psi (7 kPa) of trap
differential required.
28McQuay IM 791-2
Mechanical Installation
4 If the unit is to be operated in environments with possible
freezing temperatures, an optional freezestat is
recommended. See Freeze Protection‚ page 68 for
additional information.
The optional damper assemblies described in this section are
provided with manually adjustable linkages, or may be shipped
with factory installed actuators and linkages.
Economizer Dampers
Outside air intake is provided on both sides of the unit, and the
return air path is at the center of the damper set. As the single
actuator modulates the outside air dampers open, the return air
dampers close. Exhaust air exits the unit through the gravity
relief dampers provided at the end of the economizer section.
The outside air return air damper assembly (economizer)
comes with manually adjustable linkage. This adjustable
linkage can also be used for connection of a damper operator.
The damper is set so that the crankarm moves through a 90degree angle to bring the economizer dampers from full open
to full close. Mechanical stops have been placed in the
crankarm mounting bracket. Do not remove stops. If the
crankarm is driven past the stops, damage to the linkage or
damper will result. The unit will ship with a shipping bolt
securing the linkage crankarm. Remove shipping bolt before
use.
Figure 32: Damper Adjustment
O u t s i d e
O u t s i d e
O p t i o n a l R e t u r n A i r F a n
A i r
A i r
E c o n o m i z e r
S h a f t . 5 0 0 D i a .
x 1 . 5 0 L o n g
O A
O p e n
9 0 °
S t r o k e
. 7 5
. 2 5
3 . 0 0
O A
C l o s e d
Note: For good airflow control, adjust linkages so damper
blades do not open beyond 70 degrees. Opening a
damper blade beyond 70 degrees has little effect on its
airflow.
Do not “overclose” low leak damper blades. The edge
seal should just lightly contact the adjoining blade. The
blades will lock up if they are closed so far the seal goes
over center.
30McQuay IM 791-2
Loading...
+ 76 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.