I N S T A L L A T I O N I N S T R U C T I O N S
nstallation Instruction No.: 1B0161R3 – Updated May 2009
I
IMPORTANT: Please read all instructions before beginning.
OVERVIEW OF SYSTEM:
1. Review and become familiar with all duct components.
2. Keep material and cartons dry.
3. Be careful of sharp edges or burrs when handling any sheet metal parts.
4. All interior duct surfaces that can come into contact with wires shall be smooth.
5. On arrival, check the shipment for shortages or damage. Contact your local Wiremold/Legrand representative
if there are any issues. File freight damage claims directly with your carrier.
Compare and coordinate the architectural and electrical
6.
drawings with Wiremold/Legrand installation drawings.
Contact your local Wiremold/Legrand representative immediately if any details or dimensions are incorrect.
7. Advise all trades that underfloor duct is not to be used as a walkway or crosswalk. Install underfloor
duct system in accordance with Article 390 of the latest National Electric Code.
*40% cable fill is the maximum cable allowed by NEC.
DIAMETERAREA (In2) 40% FILL*
Inches[mm]Inches[mm]DUCTDUCT
DUCT:
1. Duct is manufactured in two sizes and in two styles. 2" IPS round preset and Pro Series rectangular preset duct.
a. No. 2 Duct is 3 1/8" wide x 1 1/4" deep [79mm x 32mm] with a cross sectional area of 3.34 sq. in. [2155 sq. mm].
b. No. 4 Duct is 6 1/2" wide x 1 1/2" deep [165mm x 38mm] with a cross sectional area of 8.72 sq. in. [5626 sq. mm].
2. The largest conductor to be installed in either duct shall be 1/0.
3. Preset duct for distribution runs is standard 10' [3m] length with five presets spaced 12" [305mm] from each end and
on 24" [610mm] centers. (Shown below).
a. Other insert spacing is available.
b. Blank duct (duct without preset inserts) is available for home runs, main system feeds and afterset applications.
2" IPS DUCTPRO SERIES DUCT
2" IPS Preset
Mudcap
#4 Duct
#2 Duct
Mudcap
#2 Duct
2" IPS PRESETS SHOWN
12" [305mm]24" [610mm]
10' [3m]
JUNCTION BOX AND WALKERDUCT INSTALLATION LAYOUT:
1. Secure bench marks at convenient locations on walls or columns wherever the underfloor duct system is to be
installed. This will help establish the level of the finished concrete floor.
Pro Series Preset
Alignment Clip
#4 Duct
STEP 1
STEP 3
First Horizontal
Run of Duct
STEP 4
Vertical Run of Duct
Exterior Wall
2. Obtain the location of the first duct run from the plans.
3. Stretch a base line, at finished floor level, that corresponds with the center of the duct run.
4. In the middle, and at right angles to the line created in Step 3, stretch another line.
5. These two lines should be used as measuring points for laying out the horizontal and vertical runs of duct.
2
FOUR-WAY JUNCTION BOXES:
1. Arrows are located on opposing sides of each box to indicate the entrance for feeder raceways. Cables and conductors
ntering these sides of the junction box will be routed on the lower level to more easily pass through the junction box. To
e
maintain proper segregation, all arrows must point in the same direction. (See Detail A)
STEP 3
Cat. No. 224JS-1
Junction Box
Indicator Arrow
Winged Shaped End
of corner spacer
STEP 1
Detail A
A
STEP 2
Cat. No. 255-3/4
Conduit Adapter
2. Where the plans indicate a conduit feed coming into the corner of the junction box, use a Catalog Number 255 - (3/4", 1",
1 1/4", 1 1/2", 2" trade size) conduit adapter. For plastic conduit, install a threaded rigid steel nipple and plastic adapter.
Install a grounding lug inside the junction box. Ground in accordance with the National Electric Code.
3. The wing shaped end of the plastic spacer at each corner can be removed (except at tunnel locations) to increase wire
pulling area.
CAUTION:
The center duct cannot be fed with conduit from any of the box corners. The center
duct may be fed through the center duct openings in any side of the junction box.
4. Tunnels isolate each service in multiple duct boxes to create a continuous raceway through the box in both directions.
Two Compartment Tunnel
3
LOCATE JUNCTION BOXES:
Junction boxes are used at intersections of duct runs.
Center line
Exterior Wall
1. Locate along the horizontal base line the point where junction boxes are to be centered.
2. Junction boxes must be positioned correctly so that the duct arrangement will conform to the electrical drawings. After the
correct position is established and power and telephone service have been assigned to specific duct runs, the arrow on the
junction box side must be noted. All junction boxes in any interconnecting area must be placed with arrow pointing inthe same direction. This establishes a consistent pattern for all inter-connecting duct runs. When Wiremold/Legrand layout
drawings are provided, the arrows on the installed box must match drawings.
Junction BoxDistance Between Duct Ends
Catalog NumberWithin Junction Box
12JS, JR, HS, or HR7"[178mm]
14JS, JR, HS, or HR11 1/8"[283mm]
222JS, JR, HS, or HR11 1/8"[283mm]
224JS, JR, HS, or HR15 1/4"[387mm]
3222JS, JR, HS, or HR15 1/4"[387mm]
244JS, JR, HS, or HR18 5/8"[473mm]
3224JS, JR, HS, or HR18 5/8"[473mm]
42222JS, JR, HS, or HR19 3/8"[492mm]
3424JS, JR, HS, or HR22"[559mm]
3244JS, JR, HS, or HR22"[559mm]
522222JS, JR, HS, or HR23 1/2"[597mm]
3444JS, JR, HS, or HR25 3/8"[645mm]
3. Proceed with other rows of boxes, making sure that centers are lined up vertical and horizontally with the first row of boxes.
See chart above for dimension to allow for duct length between boxes.
CAUTION:
When field cutting duct to length, always butt factory cut end to factory cut end.
Install field cut end at the end of a given run. Maintains proper insert spacing.