ideal NF 230, NF 240, NF 250, NF 260, NF 280 User guide

Page 1

IDEAL ELAN 2 NF 230, NF 240, NF 250, NF 260 & NF 280

Wall Mounted, Fanned, Balanced Flue Gas Boilers. Installation & Servicing.

NOTE TO THE INSTALLER: Leave these instructions adjacent to the gas meter or with the user

Page 2

PERFORMANCE DATA

Settled Land Contract Contract

Table 1- GENERAL DATA

Boiler Size NF 230 NF 240 NF 250 NF 260 NF 280
Main burner bar Aeromatic
AC 19/123 278
Aeromatic AC 19/123 278 AC 19/123 279 AC 19/123 276 Aeromatic
AC 19/123 277
Gas control HONEYWE LL VR 4700 E 1 1042, 240 V
Burner Injector BRAY Cat. 16
size 750
Cat. 16
size 1100
Cat. 16
size 1400
Cat. 16
size 1700
Cat. 10
size 2400
Pilot injector HONEY WELL 459004
STAMPE
21 - 001
D 38 / 36A
ST 45900421 - 002
AMPED 56 / 42
2A
Gas supply connection on (in. BSP) Rc 1/2 (1/2)
Flow connection Compression fi ittings 22 mm 22 mm
Return connection Compression fittings 22 mm 28 mm 28 mm
Maximum static water head m (ft.) 30.5 (100)
Minimum static water head m (ft.) 0.45 (1.5)
Electrical supply 240 V ~ 50 Hz Boiler power consumption; 50 W
Fuse rating External; 3 A Internal; F1 A to BS. 4 BS. 4265
Water content litre (gal.) 1.0 (0 ).22) 1.2 (0 ).27) 1.5 (0.33)
Dry weight k g (lb) 26.3 (58.0) 27.5 (60.6) 35.0 (77.2)
Maximum installation weight kg (lb) 16.0 (35.3) 17.2 (37.9) 37.9) 22.9 (50.5)
Boiler size Height mm (in.) 700 (27.5)
Width mm (in.) 380 (15) 465 (18) 465 (18)
Depth mm (in.) . 300 (12)
Flue duct diameter mm (in.) 100 (4)

Table 2- PERFORMANCE DATA

Boiler Size NF 230 NF 240 NF 250 NF 260 NF 280
Boiler input MINIMUM kW 5.9 11.7 15.2 19.0 23.4
To obtain gas (Btu/h) (20 300) (40 000) (51 900) (64 900) (80 000)
(a) For I/s; divide heat Gas consumption 1/s (ft³/h) 0.15 (19.5) 0.30 (38.5) 0.39 (50.0) 0.49 (62.5) 0.60 (77.1)
input (kW) by C.V. of
the gas (MJ/m 3 ).
MID kW 8.6 13.3 16.9 20.7 26.6
(b) For it 3 /h; divide heat (Btu/h) (29 400) (45 500) (57 700) (70 500) (90 900)
of the gas (Btu/ft 3 ). Gas consumption l/s (ft³/h) 0.22 (28.3) 0.34 (43.8) 0.44 (55.6) 0.53 (67. 9 ) 0.69 (87.6)
Heat inputs are pre-set to the highest nominal MAXIMUM kW 11.1 14.8 18.6 22.2 29.7
rating. (Btu/h) (38 000) (50 600) (63 300) (75 900) (101 300)
Gas Consumption l/s (ft³/h) 0.29 (36.6) 0.38 (48.7) 0.48 (61.0) 0.57 (73.1) 0.77 (97.6)
Boiler output MINIMUM kW 4.4 8.8 11.7 14.7 17.6
(Btu/h) (15 000) (30 000) (40 000) (50 000) (60 000)
MID kW 6.6 10.3 13.2 16.1 20.5
(Btu/h) (22 500) (35 000) (45 000) (55 000) (70 000)
MAXIMUM kW 8.8 11.7 14.7 17.6 23.4
· (Btu/h) (30 000) (40 000) (50 000) (60 000) (80 000)
Burner setting MINIMUM mba ır (in.w.g.) 5.0 (2.0) 9.2 (3.7) 9.7 (3.9) 10.2 (4.1) 9.5 (3.8)
pressure (HOT) MID mbar (in.w.g.) 10.1 (4.0) 11.8 (4.7) 11.9 (4.8) 12.0 (4.8) 12.3 (4.9)
MAXIMUM mba r (in.w.g.) 16.6 (6.7) 14.6 (5.9) 14.0 (5.6) 13.8 (5.5) 15.2 (6 1)
Page 3

INTRODUCTION

The Ideal Elan 2 NF 230, NF 240, NF 250, NF 260 and NF 280 are fully automatically controlled, wall mounted, low water content, balanced flue, fanned gas boilers.

They are range rated to provide central heating outputs of 4.4 kW (15 000 Btu/h) to 23.4 kW (80 000 Btu/h).

The boiler casing is of white enamelled mild steel, with a fascia of satinised white glass. The controls pod, also of white enamalled mild steel, has fixed sides and a removable bottom panel.

The glass fascia slides upwards to reveal the boiler thermostat (in the control box mounted on the gas valve) and the programmer (if fitted).

A Programmer Kit , which fits neatly within the casing, is available as an optional extra. Separate fitting instructions are included with this kit.

The boilers are supplied with a standard flue kit suitable for rear or side outlet applications from 114mm (4 1/2 in.) to 406 mm (16 in.).

Up to 3 optional Flue Extension Duct Kits allowing up to 3 m (118 in.), rear or side outlet, are available.

A Vertex Flue Kit, for vertical flue connection is available as an optional extra.

A 90g Flue Elbow Kit, is also available.

The boilers are suitable for connection to fully pumped, open vented or sealed water systems. Adequate arrangements for completely draining the system by provision of drain cocks, MUST be provided in the installation pipework.

Gas Safety (Installation and Use) Regulations, 1984.

It is the law that all gas appliances are installed by competent persons (e.g. CORGI, identified by 3 ), in accordance with the above Regulations. Failure to install appliances correctly could lead to prosecution. It is in your own interest, and that of safety, to ensure that the law is complied with.

The installation of the boiler MUST also be in accordance with the current I.E.E. Wiring Regulations, the Local Building Regulations, Building Standards (Scotland), the bye laws of the Local Water Undertaking and any relevant requirements of the Local Authority.

Detailed recommendations are contained in the following British Standard Codes of Pratice.

B5. 669 Low pressure installation pit pes.

  • BS. 6798 Installation of gas fired hot water boilers of rated input not exceeding 60kW.
  • BS. 5449 Forced circulation hot water systems.

BS. 5546 Installation of gas hot water supplied for domestic purposes (2nd Family Gases).

  • BS. 5440:1 Flues (for gas appliances of rated input not exceeding 60kW).
  • BS: 5440:2 Ventilation (for gas appliances of rated input not exceeding 60kW).

Manufacturers' notes must not be taken in any way as overriding statutory obligations.

IMPORTANT. These appliances are certificated by the British Standards Institution for safety and performance. It is, therefore, important that no external control devices, e.g. flue dampers, economisers etc., are directly connected to

INTRODUCTION - GAS SUPPLY

Any direct connection of a control device not approved by Caradon Heating Ltd. could invalidate the B.S.I. Certification and the normal appliance warranty. It could also infringe the Gas Safety Regulations and the above regulations.

LOCATION OF BOILER

The boiler MUST be installed on a flat and vertical noncombustile wall, capable of adequately supporting the weight of the boiler and any ancillary equipment.

THE BOILER IS NOT SUITABLE FOR EXTERNAL INSTALLTION

IMPORTANT NOTICE. If the boiler is to be fitted in a timber framed building it should be fitted in accordance, with the British Gas publication 'Guide for Gas Installations in Timber Frame Housing', Reference DM2. If in doubt advice must be sought from the local Gas Region of British Gas.

The boiler may be installed in any room or internal space, although particular attention is drawn to the requirements of the current I.E.E. Wiring Regulation and, in Scotland, the electrical provisions of the Building Regulations applicable in Scotland with respect to the installation of the boiler in a room or internal space containing a bath or shower.

Where a room sealed appliance is installed in a room containing a bath or shower thren the appliance and any electrical switch or appliance control utilising mains electricity should be so situated that it cannot be touched by a person using the bath or shower.

Where installation will be in an unusual location, special procedures may be necessary and BS. 6798 gives detailed guidance on this aspect.

A compartment used to enclose the boiler MUST be designed and constructed specially for this purpose. An existing cupboard or compartment may be used, provided it is modified for the purpose. Details of essential features of cupboards / compartment design, including airing cupboards installation are given in BS. 6798.

In siting the boiler, the following limitations MUST be observed:

  • 1. The position selected for installation MUST allow adequate space for servicing in front of the boiler and for air circulation around the boiler. For the minimum clearances required for safety and subsequent service, see the Wall Mounting Template and Frame 4. In addition sufficient space may be required to allow lifting access on to the wall mounting plate.
  • 2. This position MUST also permit the provision of a satisfactory flue termination.

GAS SUPPLY

The Local Gas Region should be consulted, at the installation planning stage, in order to establish the availability of an adequate supply of gas.

An existing service pipe must NOT be used without prior consultation with the Local gas region.

A gas meter can only be connected by the Local Gas Region, or by a local Gas Region Contractor. An existing meter should be checked, preferably by the Gas Region, to ensure the meter is adequate to deal with the rate of gas supply required.

Installation pipes should be fitted in accordance with BS. 6891. Pipework from the meter to the boiler MUST be of an adequate size. Do NOT use pipes of a smaller size than the object interview that content and content interview.

Page 4

FLUE INSTALLATION

The flue MUST be installed in accordance with the recommendations of BS 5440: 1.

The following notes are intended for general guidance.

  • 1. The boiler MUST be installed so that the terminal is exposed to the external air.
  • 2. It is important that the position of the terminal allows the free passage of air across it at all times.
  • 3. The minimum acceptable spacing from the terminal to obstructions and ventilation openings are specified in Table 3.
  • 4. Where the lowest part of the terminal is fitted less than 2 m (6.6 ft.) above a balcony, above ground or above a flat roof to which people have access then the terminal MUST be protected by a purpose designed guard.

Terminal guards are available from:

Quinnel, Barret & Quinnel Ltd., 884 Old Kent Road, London, SE15 (Model 304),

(Model K1)

Telephone No. 071 6391357,

and from,

Tower Flue Components Ltd., Vale Rise, Tonbridge, Kent, TN9 1TB

Telephone No. 0732 351555.

Ensure that the guard is fitted centrally.

  • 5. Where the terminal is fitted within 850 mm (34 in.) of a plastic or painted gutter, or 450 mm (18 in.) of painted eaves then an aluminium shield at least 750 mm (30 in.) long should be fitted to the underside of the gutter or painted surface.
  • The air inlet / products outlet duct and the terminal of the boiler MUST NOT be closer than 25 mm (1 in.) to combustible material. Detailed recommendations on the protection of combustible material are given in BS. 5440:1 1990.
  • 7. If the terminal is fitted less than 2 m (6 ft. 6 in.) above a balcony, above ground or above a flat roof then the minimum spacing in Table 3, No.s 2, 3, 5 and 6 would be 75 mm in order to allow a terminal guard to be fitted.
  • 8. Where it is essential that the terminal wall plate is fitted, i.e. wall thicknesses over 610 mm (24 in.) or with an inaccurately cut hole, the minimum spacing in Table 3, No.s 2, 3, 5 and 6 would be 60 mm in order to allow the terminal wall plate to be fitted.

IMPORTANT. It is absolutely ESSENTIAL to ensure, in practice, that products of combustion discharging from the terminal cannot re-enter the building or any other adjacent building through ventilators, windows, doors, other sources of natural air infiltration, or forced ventilation / air conditioning.

If this should occur, the appliance MUST be turned OFF immediately and the Local Gas Region consulted.

TERMINAL

The flue terminal assembly can be adapted to accomodate various wall thicknesses and flue lengths. Refer to Frame 3.

AIR SUPPLY

Detailed recommendations for air supply are given in BS. 5440: 2. The following notes are for general guidance:

1. It is NOT necessary to have a purpose provided air vent in

FLUE INSTALLATION - AIR SUPPLY

  • 2. If the boiler is to be installed in a cupboard or compartment, permanent air vents are required (for cooling purposes) in the cupboard/ compartment, at both high and low levels. The air vents must either communicate with room/internal space, or be direct to outside air. The minimum effective areas of the permanent air vents, required in the cupboard/ compartment, are specified as follows and are related to maximum rated heat input.
  • 3. Both air vents MUST communicate with the same room or internal space, or MUST be on the same wall to outside air.
  • 4. In siting the air vents care must be taken to avoid the freezing of pipework.

Refer to Tables 4, 5, 6, 7 & 8 for details of air vent position and sizing.

Table 3 - BAI .ANCED FL UE TERMINAL POSITION
Ter minal Position Minimum
Spacing
1. Directly below an openable window, air vent or other ventilation opening. 300 mm (12 in.)
2. Below guttering, drain pipes or soil pipes. 25 mm (1 in.)
3. Below eaves. 25 mm (1 in.)
4. Below balconies or a car port roof. 25 mm (1 in.)
5. From vertical drain pipes or soil pipes. 25 mm (1 in.)
6. From internal or external corners. 25 mm (1 in.)
7. Above adjacent ground, roof or balcony level. 300 mm (12 in.)
8. From a surface facing the terminal. 600 mm (24 in.)
9. From a terminal facing a terminal. 1200 mm (48 in)
10. From an opening in a car port (eg. door or window) into dwelling. 1200 mm (48 in)
11. Vertically from a terminal on the same wall. 1500 mm (60 in)
12. Horizontally from a terminal on the wall. 300 mm (12 in.)

Table 4 - NF 230 AIR SUPPLY

Position of air vent Air from room/
internal space
Air direct
from outside
HIGH LEVEL cm² 100 50
(in²) (16) (8)
LOW LEVEL cm² 100 50
(in²) (16) (8)

Table 5 - NF 240 AIR SUPPLY

Position of air vent Air from room/
internal space
Air direct from outside
HIGH LEVEL cm²
(in²)
133
(21)
67
(11)
LOW LEVEL 0m² 133
(21)
67
(11)
Page 5

Table 6 - NF 250 AIR SUPPLY

Position of air vent Air from room/
internal space
Air direct from outside
HIGH LEVEL cm² 166 83
(in²) (26) (13)
LOW LEVEL cm² 166 83
(in²) (26) (13)

Table 7 - NF 260 AIR SUPPLY

Position of air vent Air from room/
internal space
Air direct from outside
HIGH LEVEL cm² 200 100
(in²) (30) (15)
LOW LEVEL cm² 200 100
(in²) (30) (15)

Table 8 - NF 280 AIR SUPPLY

Position of air vent Air from room/
internal space
Air direct from outside
HIGH LEVEL cm² 264 132
(in²) (40) (20)
LOW LEVEL cm² 264 132
(in²) (40) (20)

Table 9 - WATER FLOW RATE AND PRESSURE LOSS

Boiler Size NF 230 NF 240 NF 250 NF 260 NF 280
Boiler outpu t kW 8.8 11.7 14.7 17.6 23.4
Btu/h 30 000 40 000 50 000 60 000 80 000
Water flow l/min 11.4 15.2 19.0 22.8 30.3
rate gai/h 150 200 250 300 400
Pressure mbar 27 45 - 70 102 92
loss in.w.g. 11 18 28 41 37

WATER CIRCULATION SYSTEM

The boiler must NOT be used for direct hot water supply. The boiler is suitable for connection to fully pumped open

vented or sealed water central heating systems or central heating combined with indirect domestic hot water systems. The central heating system should be in accordance with

BS. 6798 and in addition, for Smallbore and Microbore systems, BS. 5449

The domestic hot water system, if applicable, should be in accordance with relevant recommendations to BS. 5546.

Copper tubing to BS. 2871: 1 is recommended for water carrying pipework.

The hot water storage cylinder MUST be of the indirect type and should be, preferably, manufactured of copper.

Single-feed indirect cylinders are not recommended and

AIR SUPPLY - ELECTRICALSUPPLY

The hot water cylinder and ancillary pipework, not forming part of the useful heating surface, should be lagged to prevent heat loss and any possible freezing, particularly where pipes run through roof spaces and ventilated under floor spaces.

Draining taps MUST be located in accessible positions, which permit the draining of the whole system, including the boiler and hot water storage vessel.

Draining taps should be at least 1/2 in. nominal size and be in accordance with BS. 2879.

The hydraulic resistances of the boilers, at MAXIMUM OUTPUT with an 11°C (20°F) temperature differential, are shown in Table 9.

ELECTRICAL SUPPLY

Wiring external to the appliance MUST be in accordance with the current I.E.E. Wiring Regulations and any Local Regulations which apply.

The boiler is supplied for 240 V ~ 50 Hz

Single Phase

Fuse Rating is 3 A

The method of connection to the mains electricity supply MUST facilitate complete electrical isolation of the boiler, preferably by the use of a fused, unswitched three pin plug and a shuttered socket outlet, both complying with the requirements of BS. 1363.

Alternatively, a fused double pole switch, having at least a 3 mm (1/8 in.) contact separation in both poles and servicing only the boiler, may be used.

The point of connection to the mains should be readily accessible and adjacent to the boiler, except that for bathroom installations, the point of connection to the mains MUST be situated outside of the bathroom.

Note. Where a room sealed appliance is installed in a room containing a bath or shower then the appliance and any electrical switch or apppliance control utilising mains electricity should be so situated that it cannot be touched by a person using the bath or shower.

Page 6

16. Flue outlet sealing plate

UNPACKING

13

Page 7

WALL MOUNTING PLATE - BOILER CASING REMOVAL

4 BOILER DIMENSIONS & CLEARANCES

The following minimum clearances must be maintained for operation and servicing. Additional space will be required for installation depending upon site conditions. In addition a minimum of 450 mm MUST be available at the front of the boiler for servicing. Side and Rear Flue Installations.

  • 1. Provided that the flue hole is cut accurately, e.g. wih a core drill the flue can be installed from inside but for flue lengths greater than the width / depth of the boiler then the space in which the boiler is to be installed must be at least equal to the flue length plus the length of the terminal grill, (inside installation up to 610 mm wall thickness only).
  • 2. If a core boring tool is to be used from inside the building, the space in which the boiler is to be installed must be at least wide enough to accomodate the tool.

Side Flue Installations ONLY.

3. Once the boiler has been installed, the clearance on the non-flue side may be

Release the 2 bottom captive screws and lift the casing off the boiler. Place the casing safely to one side, taking care not to damage the glass fascia panel. (Slide the glass panel down in the casing for safe keeping.)

Page 8

FLUE ASSEMBLY - PREPARING THE WALL

5 in. diameter

flue hole

SECTION SHOWING

Note. Check all of the hole

positions BEFORE drilling.

WALL THICKNESS, 'X'

Note. If the terminal is to

be sited within 25 to 40 mm

of a corner or vertical pipe

(refer to Table 3.) then the

hole MUST be accurately

cut and the rubber weather

seal trimmed around the

The terminal wall plate

aroove provided.

need not be fitted.

8 PREPARING THE WALL

IMPORTANT. Ensure that, during the cutting operation, masonry falling outside of the building does not cause damage or personal injury.

  • 1. Cut the flue hole (preferably with a 5 in. core boring tool) ensuring that the hole is square to the wall. If the hole has been quite accurately cut with a drill, then making good the wall faces is not essential- as seals are provided at both ends of the flue. However, both wall faces immediately around the cut hole should be flat; make good if necessary. For less accurate holes make good to approximatly 125 mm diameter at the two wall faces. If the flue hole is longer than 610 mm this must be done from the outside for the outer face, as access to outside is needed to fit the terminal plate anyway.
  • 2. Measure and note the wall thickness 'X'.
  • 3. Drill the 5 fixing holes with an 8 mm (5/16 in.) masonry drill.
  • 4. Insert the plastic plugs provided.

5. Cooste two No. 10 x 2 in. screws in the wall mounting plate top fixing holes and screw home to within 6 mm (1/4 in.) of the wall sur face.

Page 9

CUTTING THE DUCT ASSEMBLY - TERMINAL WALL PLATE

Check with a spirit level that the plate is vertical.

Align the holes in the sliding collar flange with the 3 cut-outs in the wall plate. Insert 3 of the self-tappers and rectangular washers to retain the ascence

  • Using the sliding collar as a template at the duct join, mark the positions of the 3 fixing screws. Note. If the duct join is too close to the rubber weather seal to permit access for drilling, mark the hole positions at the mid-point of the duct
  • 4. Slide the collar back to the boiler end of the duct and mark the positions for a further 3 fixing screws.

  • tapping screws in order to fix the collar in position and lock the duct assembly. DO NOT DRILL THE INNER FLUE DUCT.
  • 6. Seal the air duct joint with the aluminium tape provided in the Hardware Pack.

FOR WALL THICKNESSES ABOVE 406 mm, REFER TO FRAMES 27 & 28 - FLUE EXTENSION DUCTS.

13 TERMINAL WALL PLATE

This plate is provided to allow the neat concealment and full compression of the rubber seal. If the flue hole and flue ducts have been accurately cut and the outside wall face is flat then its use is not essential except that this plate must be used on wall thicknesses over 610 mm (24 in.) .

ane 9

Page 10

BOILER MOUNTING - SEALING THE FLUE

APPLIANCES FITTED WITH A REAR OUTLET FLUE: PROCEED DIRECT TO FRAME 29

Page 11

18 PREPARING THE WALL

IMPORTANT. Ensure that, during the cutting operation, masonry failing outside of the building does not cause damage or, personal injury.

  • 1. Cut the flue hole (preferably using a 5 in. core boring tool), ensuring that the hole is square to the wall. If the hole has been quite accurately cut will a drill then making good the wall faces is not essential - as seals are provided at both ends of the flue. However, both wall faces immediately around the cut hole should be flat; make good if necessary. For less accurate holes make good to approximately 125 mm diameter at the two wall faces. For holes longer than 610 mm this must be done from outside for the outer face- as access to outside is needed to fit the terminal wall plate anyway.
  • Measure the wall thickness 'X' and calculate dimension 'Y' (i.e. Boiler spacing plus 'X'). Refer to Frame 3.
  • 3. Drill the all 9 fixing holes with an 8 mm (5/16 in.) masonry drill and insert the plastic plugs provided.
  • 4. Locate two No. 10 x 2 in. screws in the terminal mounting plate top fixing holes and screw home to within 6mm (1/4 in.) of wall surface. Note. If the terminal is to be sited 25 to 40 mm from a corner or vertical pipe (refer to Table 3) the hole must be accurately cut and the rubber weather seal trimmed around the groove provided. The terminal wall plate need not be fitted.

Page 12

FLUE ASSEMBLY - TERMINAL MOUNTING PLATE

plus 50 mm (2 in

position

washers, provided, to retain the flue assembly

rectangular washers, provided, to retain the assembly

Refer to the detail in Frame 22

____Self tapping screws. 6 off The flue assembly is shown locked in plate, insert 3 of the self tapping screws and rectangular

Page 13

WALL MOUNTING PLATE - MOUNTING THE BOILER

  • 1. Locate two No. 10 x 2 in. screws in the plate top fixing holes and screw home to within 6 mm (1/4 in.) of the wall surface.
  • 2. Engage the plate on the top two fixing screws.

  • Locate two No. 10 x 2 in. screws in the bottom fixing holes and drive home all four screws.
  • 4. Check with a spirit level that the plate is vertical.

24 TERMINAL WALL PLATE This plate allows the neat concealment and full compression of

the rubber seal. Its use is not essential if the flue hole and flue ducts have been accurately cut and the outside wall face is flat except that this plate must be used on wall thickness over 610 mm (24 in.).

  • 1. Position the terminal wall plate over the terminal.
  • Drill 4 fixing holes with an 8 mm (5/16 in.) masonry drill.
  • 3. Insert the four plastic plugs provided

Secure the plate with four of the No. 10 x 2in. screws provided.

Note. If the terminal is less than 2 m (6.6 ft.) above ground level, an approved terminal guard should be fitted. Refer to Page 4.

Page 14

(d) Reconnect the electrical leads and the pressure sensing tube to the fan.

PROCEED TO FRAME 29

Page 15

Note. If the flue duct assembly locking screws restrict the sliding collar then use the collar locking screws to lock the whole assembly.

APPLIANCES FITTED WITH A REAR OUTLET FLUE: PLEASE REFER TO FRAME 11 (PAGE 9). APPLIANCES FITTED WITH A SIDE OUTLET FLUE: PLEASE REFER TO FRAME 21 (PAGE 12).

6. Using the sliding collar as a template at the joins of any ducts

mark the positions the fixing screws (3 screws for each joint).

Page 15

Page 16

SERVICE CONNECTIONS - SYSTEM REQUIREMENTS

29 GAS CONNECTION

  • 1. A MINIMUM working gas pressure of 20 mbar (8
  • in.wg) MUST be available at the boiler inlet.
  • 2. Extend a gas supply pipe NOT LESS THAN 15 mm O.D. to the boiler and connect to the gas service cock situated at the bottom left hand side of the boiler. Note. If the pipe run from

the meter to the boiler is greater than 3 m (10 ft.), it is recommended that 22 mm O.D. pipe is used.

3. To facilitate connection, it

is recommended that the

das service cock is not

removed from the gas

control valve. A 1/2 in. BSP x 15 mm connector prefitted with a short stub connection should be screwed into the cock using a suitable sealant. Ensure that the gas supply pipe does not foul the boiler casing when fitted.

IMPORTANT. The gas service cock contains a non-metallic seal, so must not be overheated when making capillary connections.

4. Test the gas installation for soundness and purge in accordance with BS. 6891.

30 WATER CONNECTIONS

1. Connect the system flow and return pipework to the two water connections at the top of the boiler.

Note. When the required output exceeds 16.1kW (55 000 Btu/h) 28mm (1in.) flow and return pipes should be used, both to and from the boiler. On the NF 260 boiler only connect to the boiler in 22mm (4/,in.) pipe and increase to 28 mm (1in.) as soon as is practicable.

2. Ensure that all valves are open, fill and vent the system and check for water soundness. Note:- This appliance is NOT suitable for use with a direct hot water cylinder.

IDEAL ELAN NF 280 ONLY

When venting the heat exchanger using the manual ar vent on the flow header, protect the electrical controls with a waterproof sheet or similar.

Page 17

SYSTEM REQUIREMENTS

33 SCHEMATIC PIPEWORK AND BY-PASS ADJUSTMENT - OPEN VENT

Boiler size NF 230 NF 240 NF 250 NF 260 NF 280
Boiler output kW (Btu/h) 8.8 (30 000) 11.7 (40 000) 14.7 (50 000) 17.6 (60 000) 23.4 (80 000)
Water flow rate for 11 C differential l/min. (gal./h) 11.4 (150) 15.2 (200) 19.0 (250) 22.8 (300) 30.3 (400)
Pressure loss for 11° C differential mbar (in.w.g) 27 (11) 45 (18) 70 (28) 102 (41) 92 (37)
Water flow rate for 9 C differential l/min. (gal./h) 13.8 (183) 18.5 (244) 23.2 (306) 27.8 (367) 37.0 (488)
Pressure loss for 9° C differential mbar (in.w.g) 40 (16.4) 67 (26.9) 105 (41.8) 152 (61.2) 138 (55)

T NOT be more th

When the NF 260 (with output above 16.1kW [55 000 Btu/h]) and NF 280 units are used, 28mm (1in.) flow and return pipes MUST be used - both to and from the boiler.

The control system used with the boiler MUST provide a load in circuit with the boiler of at least 10% of the boiler output whenever the boiler fires. In order to achieve this load it may be necessary to provide 'uncontrolled' radiator(s) which cannot be manually turned off by the use

A by-pass MUST be fitted as far from the boiler as possible, consisting of the following:

(a) 15 mm pipe not more than 1 metre long for boilers up to 50 000 Btu/h output. (b) 22 mm pipe for boilers of over 60 000 Btu/h output. The by-pass should incorporate a balancing valve which CANNOT be adjusted by the househ

ξ

5. The circulating pump used should have adequate performance to give a maximum temperature differential across the boiler of 9°C when the by-pass & the 'uncontrolled' radiator(s) (when fitted) are closed, with either the heating or the dom etic bot water controls call

BY-PASS ADJUSTMENT

  • 6. With the heating circuit OPEN and the by-pass and 'uncontrolled' radiator(s) (if fitted) CLOSED, set the pump to give a maximum of 9° C differential across the boiler and system. The system should be at full mperature for this operation and this is a convenient point to balance the system flows
  • 7. Open the valve on the 'uncontrolled' radiator(s) (if fitted) and set its temperature differential to approximately 10° C.
  • 8. Open the by-pass until the differential across the boiler is 11° C.
  • 9. Check that the water flow through the boiler is equate when the heating controls are satisfied and the domestic hot water controls are calling for heat.

Thermostatic Radiator Valves

Caradon Heating Ltd. support the recommendations made in BS. 5449 and by leading manufacturers of domestic heating controls that heating systems utilising the full thermostatic radiator valve control of temperature in individual rooms should also be fitted with a roor thermostat controlling the temperature in a space served by radiators not fitted with such a valve.

Such an arrangement will provide for a potentially more efficient control of the environment and will also avoid the continuous running of the circulation pump during programmed heating 'ON' periods - thus saving electrical energy. It is therefore strongly recommended that, when thermostatic radiator valves are used, space heating temperature control over a living / dining area or a hallway having a heating requirement of at least 10 % of the boiler heat output is achieved using a room thermostat whilst other rooms are individually controlled by thermostatic radiator valves. If a rcom thermostat is not fitted as described above then it is recommended that the system includes in concerce of radiator has seen a melon in heat (see of 10% of the boiler heat output under design conditions.

Page 18

Notes.

  • A. Any connection for filling or replenishing of a sealed primary circuit from a supply pipe is conditional upon a water undertaking seeking and obtaining consent for a relaxation of its Byelaws 38.8 (1), from the Secretary of State.
  • B. The method of filling, re-filling, topping up or flushing sealed primary hot water circuits from the mains via a temporary hose connection is only allowed if acceptable to the Local Water Authority.

1. General.

  • (a) The installation must comply with the requirements of BS. 6798 and BS. 5449.
  • (b) The installation should be designed to work with flow temperatures of up to 82° C.
  • (c) All components of the system, including the heat exchanger of the indirect cylinder, must be suitable for a working pressure of 3 bar (45 lb.ft. / in2) and temperature of 110° C. Care should be taken in making all connections so that the risk of leakage is minimised.

2. Safety Valve.

A spring loaded safety valve complying with the relevant requirements of BS. 6759 must be fitted in the flow pipe as close to the boiler as possible and with no intervening valve or restriction. The valve should have the following features:

  • (a) A non-adjustable pre-set lift pressure not exceeding 3 bar (45 lb.ft. / in2).
  • (b) A manual testing device.
  • (c) Provision for connection of a discharge pipe. The valve or discharge pipe should be positioned such that the discharge of water or steam cannot create a hazard to the occupants of the premises, or cause damage to electrical components and wiring.

3. Pressure Gauge.

A pressure gauge covering at least the range 0 - 4 bar (0 - 60 lb.ft. / in2) must be fitted to the system. The gauge should be easily seen from the fitting point and should preferably be connected at the same point as the expansion vessel.

4. Expansion Vesse

  • (a) A diaphragm type expansion vessel must be connected at a point close to the inlet side of the pump, the connecting pipe being not less than 15 mm (1/2 in. nominal) size and not incorporating valves of any sort.
  • (b) The vessel capacity must be adequate to accept the expansion of the system water when heated to 110° C (230° F).
  • (c) The charge pressure must not be less than the static water head above the vessel. The pressure attained in the system when heated to 110° C (230° F) should be at least 0.35 bar (5 lb.ft. / in²) less than the lift pressure of the safety valve. For guidance on vessel sizing refer to the Table in Frame 35. For further details refer to BS. 5449, BS. 7074:1 & the British Gas Corporation publication - 'Material and Installation Specifications for Domestic Central Heating & Hot Water'.

5. Cylinder.

The cylinder must be either of the indirect coil type or a direct cylinder fitted with an immersion calorifier, which is suitable for operating on a gauge pressure of 0.35 bar (5 lb.ft. / in2) in excess of the safety valve setting. Single feed indirect cylinders are not suitable for sealed systems.

6. Make-up Water.

Provision must be made for replacing water loss from the system either,

  • (a) From a manually filled make-up vessel with a readily visible water level. The vessel should be mounted at least 150 mm (6 in.) above the highest point of the system, and be connected through a non-return valve to the system, fitted at least 300 mm (12 in.) below the make-up vessel on the
  • return side of the domestic hot water cylinder or radiators.
  • (b) Where access to a make-up vessel would be difficult, by pre-pressurisation of the system. Refer to 'Filling'.

7. Mains Connection.

There must be no direct connection to the mains water supply or to the water storage tank supplying domestic water, even through a non-return valve, without the approval of the Local Water Authority.

Page 19

35 SEALED SYSTEM REQUIREMENTS

8. Filling.

The system may be filled by one of the following methods:

(a) Through a cistern, used for no other purposes, via a ball valve permanently connected directly to a service pipe and / or a cold water distributing pipe.

The static head available from the cistern should be adequate to provide the desired initial system design pressure. The cold feed pipe from the cistern should include a non-return valve & a stop valve with an automatic air vent connected between them, the stop valve being located between the system & the automatic air vent. The stop valve may remain open during normal operation of the system if automatic water make-up is required.

(b) Through a self-contained unit comprising a cistem, pressure booster pump if required, and if necessary, an automatic pressure reducing valve and flow restrictor. The cistern should be supplied through a temporary connection from a service pipe or cold water distributing pipe.

This unit may remain permanently connected to the heating system to provide limited automatic water make-up. Where the temporary connection is supplied from a service pipe or distributing pipe which also supplies other 'draw-off' points at a lower level then a double check valve shall be installed upstream of the draw off point.

(c) Through a temporary hose connection from a draw off tap supplied from a service pipe under mains pressure. Where the mains pressure is excessive a pressure reducing valve shall be used to facilitate filling.

The following fittings shall form a permanent part of the system and shall be fitted in the order stated.

A stop valve complying with the requirements of BS. 1010 Part 2 (the hose from the draw off tap shall be connected to this fitting). A test cock.

A double check valve of an approved type.

  • Thoroughly flush out the whole of the system with cold water without the pump in position.
  • With the pump fitted, fill & vent the system until the pressure gauge registers 1.5 bar (21.5 lb.ft. / in2), Examine for leaks.
  • Check the operation of the safety valve by manually raising the water pressure until the valve lifts. This should occur within ± 0.3 bar (± 4.3 lb.ft. / in²) of the pre-set lift pressure.
  • Release water from the system until the initial system design pressure is reached.
  • Light the boiller and heat the system to the maximum working temperature. Examine for leaks.
  • Turn off the boiler and drain the system while still hot.
  • Refill and vent the system
  • Adjust the initial pressure to the required value.

Sizing procedure for expansion vessels: The volume of the expansion vessel (litres) fitted to a sealed system shall not be less than that given by the table below multiplied by a factor of 0.8 (for flow temperatures of less than 88° C).

Safety valve setting 3.0 bar 3.5 bar 3.5 bar
Vessel charge and initial system pressure 0.5
bar
1.0
bar
1.5
bar
0.5
bar
1.0
bar
1.5
bar
0.5
bar
1.0
bar
Total water content of sy ystem Exp ansion vesse l volume (litr res) r
25 ( (litres) 2.1 2.7 3.9 2.3 3.3 5.9 2.8 5.0
50 4.2 5.4 7.8 4.7 6.7 11.8 5.6 10.0
75 6.3 8.2 11.7 7.0 10.0 17.7 8.4 15.0
100 8.3 10.9 15.6 9.4 13.4 23.7 11.3 20.0
125 10.4 13.6 19.5 11.7 16.7 29.6 14.1 25.0
150 12.5 16.3 23.4 14.1 20.1 35.5 16.9 30.0
175 14.6 19.1 27.3 16.4 23.4 41.4 19.7 35.0
200 16.7 21.8 31.2 18.8 26.8 47.4 22.6 40.0
225 18.7 24.5 35.1 21.1 30.1 53.3 25.4 45.0
250 20.8 27.2 39.0 23.5 33.5 59.2 28.2 50.0
275 22.9 30.0 42.9 25.8 36.8 65.1 31.0 55.0
300 25.0 32.7 46.8 28.2 40.2 71.1 33.9 60.0
Multiplying factors for o
system volumes
ther 0.0833 0.109 0.156 0.094 0.134 0.237 0.113 0.20

36 ELECTRICAL CONNECTIONS

WARNING. This appliance MUST be efficiently earthed

A mains supply of 240V ~ 50 Hz is required.

All external controls & wiring MUST be suitable for mains voltage. Wiring should (Green/yellow) be 3-core PVC insulated cable, NOT LESS than 0.75 mm2 (24 x 0.2 mm) and to BS. 6500, Table 16. Wiring external to the boiler MUST be in accordance with the current I.E.E. Wiring Regulations and any Local Regulations.

The supply connection may be made via a removable plug to an unswitched shuttered socket/ outlet, preferably adjacent to the boiler, & should such a plug be used for connection to the mains, it must be of the 3-pin type-wired as shown, fused at 3A & comply with the requirements of BS. 1363. Alternatively, a fused double-pole switch, having a 3mm contact separation in both coles, parving poly the boiler & its external controls may be used.

Page 20

ELECTRICAL CONNECTIONS - WIRING DIAGRAMS

38 EXTERNAL WIRING

External wiring MUST be in accordance with the current I.E.E. Wiring Regulations.

The wiring diagrams illustrated in Frames 40 to 42 cover the systems most likely to be used with this appliance.

For wiring external controls to the Ideal Elan 2 NF boiler, reference should be made to the systems wiring diagram supplied by the relevant Manufacturer in conjunction with the wiring diagrams shown in Frame 39.

Difficulty in wiring should not arise, providing the following directions are observed:

  • 1. Controls that switch the system ON & OFF, e.g. a time switch, MUST be wired in series, in the live mains lead to the boiler.
  • 2. Controls that over-ride an ON / OFF control, e.g. a frost thermostat, MUST be wired into the mains lead in parallel with the controls to be over-ridden. Refer to Frame 43.

  • 3. If a proprietary system is used, follow the instructions supplied by the Manufacturers.
  • 4. The pump must always be wired in 'parallel' with the boiler.
  • 5. SYSTEM DESIGNS FEATURING CONTROLS OR WIRING ARRANGEMENTS WHICH ALLOW THE BOILER TO FIRE WHEN THERE IS NO PUMPED CIRCULATION TAKING PLACE SHOULD NOT BE FITTED.

Advice on required modifications to wiring may be obtained from the component Manufacturers.

Notes.

1. Connections between a frost thermostat and the time control should be made without disturbing other wiring.

.......................................

2. A frost thermostat should be sited in a cool place in the house, but where it can sense heat from the system.

Page 21

WIRING DIAGRAMS

Page 22

WIRING DIAGRAMS

Page 22

Page 23

FROST PROTECTION - COMMISSIONING AND TESTING

43 FROST PROTECTION

  • 1. The frost thermostat should be wired to the programmer as shown, without disturbing the existing wiring
  • 2 The frost thermostat should be sited in a cool place in the house, but where it can sense heat from the system.
  • 3. The occupier should be advised that, during frosty weather, the system should be turned OFF at the programmer switches ONLY. All other controls should be left in the normal running position.

COMMISSIONING AND TESTING

44 COMMISSIONING AND TESTING

(a) Electrical Installation

  • 1. Checks to ensure electrical safety should be carried out by a competent person.
  • 2. ALWAYS carry out the preliminary electrical system checks i.e. earth continuity, polarity, resistance to earth and short circuit using a suitable test meter.

(b) Gas Installation

  • 1. The whole of the cas installation, including the meter, should be inspected & te for soundness & purged in accordance with the recommendations of BS. 6891.
  • 2. Purge air from the gas installation by loosening the four extended nuts securing the gas service cock and purging until gas is smelled.
  • 3. Retighten the outs and test for gas soundness.

WARNING. Whilst effecting the required gas soundness test & purging air from the gas installation, open all windows & doors, extinguish naked lights & DO NOT SMOKE.

45 INITIAL LIGHTING BOILER CONTROLS

  • A Sightglass. B Thermostat knob
    • G Inlet pressure test nipple

F Gas sevice cock.

  • C Thermostat ON / OFF switch.
  • H Main burner pressure adjuster.
  • I Main burner pressure test nipple.
  • D Overheat thermostat reset button.
  • 1. Check that the electricity supply is OFF.
  • 2. Check that the gas service cock (F) is ON and the boiler thermostat switch (C) is OFF
  • 3. Slacken the screw in the burner pressure test nipple (I) and connect a das pressure dauge via a flexible tube
  • 4. Switch the electricity supply ON and check that all external controls are calling for heat
  • 5. Set the boiler thermostat knob (B) to position '6' and the thermostat switch (C) to ON. The pilot solenoid valve should open and the intermittent spark commence - continuing until the pilot is established. The main burner will then light

FITTING THE BOILER CASING

IMPORTANT. This appliance MUST NOT be operated with the casing removed.

Slide the fascia up until it locates in the retaining

Secure the bottom two captive screws.

The casing MUST seat correctly and compress the sealing strip to make an airtight joint. If side the clearance is limited then this may be checked by ensuring that the top and bottom edges of the casing are correctly located

Check that the pilot flame envelops the igintion / detection electrode. If the pilot flame appears incorrect then refer to Frame 8 'Servicing', Note. The pilot flame is factory set and no adjustment is possible

  • 6. Test for gas soundness around ALL boiler gas components, particularly valve & manifold flanges, using leak detection fluid.
  • 7 Set the boiler thermostat switch (C) to OFF and switch OFF the electricity supply.
  • 8. If the boiler output is to be set to MID or MINIMUM. affix the appropriate indicator label to the Data Plate, located on the bottom 8 H. side of the back panel.
Page 24

46 INITIAL LIGHTING

Continued from Frame 45.

  • 1. Switch the electricity supply ON -
  • 2. Set the boiler thermostat knob (B) to position '6' and the thermost switch (C) to ON and the fan will start.
  • Once the pilot is established the main gas will come on. Check that the main burner cross lights smoothly. If this sequence does not occur then refer to the 'Fault Finding' section.
  • 4. Operate the boiler for 10 minutes to stabilise the burner temperature.

COMMISSIONING AND TESTING

  • The boiler is pre-set at the factory to its highest nominal rating, but can be range rated to suit the system design requirements. Refer to Table 2 on page 2. Turn the adjusting screw (H) clockwise to decrease the pressure
  • 6. Set the boiler thermostat switch (C) to OFF.
  • Remove the pressure gauge and tube. Retighten the sealing screw in the pressure test nipple. Ensure a gas tight seal is made.
  • 8. Re-fit the casing bottom panel.

47 GENERAL CHECKS

Make the following checks for correct operation:

  • 1. Set the boiler thermostat knob to position '6' and operate the thermostaat ON / OFF switch. Check that the main burner lights and extinguishes in response.
  • The correct operation of ANY programmer and all other system controls should be proved. Operate each control separately and check that the main

burner or circulating pump, as the case may be, responds.

  • Check that the casing is sealed correctly and compressing the sealing strip all around the casing.
  • 4. Water Circulation System
    • (a) With the system HOT, examine all water connections for soundness.
    • (b) With the system still hot, turn off the gas, water and electricity supplies to the boiler and drain down in order to complete the flushing process.
    • (c) Re-fill and vent the system, clear all air locks and again check for water soundness.
    • (d) Balance the system and set the by-pass.

  • 5. Finally set the controls to the User's requirements and slide the glass fascia down into the closed position.
  • If an optional Programmer Kit is fitted then refer to the instructions supplied with the kit.
  • The temperatures quoted below are approximate and vary between installations.
Knob Setting Flow Te mperature
°C ۴
1 54 130
2 60 140
3 66 150
4 71 160
5 77 170
6 82 180

WARNING. The boiler MUST NOT be operated with the casing removed.

48 HANDING OVER

After completing the installation and commissioning of the system, then the installer should hand over to the householder by the following actions:

  • 1. Hand the User's Instructions to the Householder and explain his or her responsibilities under the Gas Safety (Installation and Use) Regulations 1984.
  • Draw attention to the Lighting Instruction label affixed to the casing front and visible through the observation window in the glass fascia when in the raised position.
  • Explain and demonstrate the lighting and shutting down procedures.
  • 4. The operation of the boiler and the use and adjustment of ALL system controls should be fully explained to the Householder, to ensure the greatest possible fuel economy, consistant with household requirements of both heating and hot water consumption.

Advise the User of the precautions necessary to prevent damage to the system and to the building, in the event of the system remaining inoperative during frosty conditions.

  • 5. Explain the function and the use of the boiler thermostat and external controls.
  • 6. Explain the function of the boiler over-heat thermostat and emphasise that if cut-out persists, the boiler should be turned off and the local Heating Installer consulted.
  • 7. Explain and demonstrate the function of time and temperature controls, radiator valves, etc for the economic use of the system.
  • 8. If any Programmer Kit is fitted, then draw attention to the Programmer Kit User's instructions and hand them to the Householder.
  • Stress the importance of regular servicing by the Local Gas Region or by a qualified Heating Engineer and that a comprehensive service should be carried out AT LEAST ONCE A YEAR.
Page 25

1 SCHEDULE

To ensure the continued safe and efficient operation of the appliance, it is recommended that it is checked at regular intervals and serviced as necessary. The frequency of servicing will depend upon the installation condition and usage, but should be carried out at least annually. It is the law that any service work must be carried out by a competent person.

  • (a) Light the boiler and carry out a pre-service check, noting any operational faults.
  • (b) Clean the main burner.
  • (c) Clean the heat exchanger.
  • (d) Clean the main and pilot injectors.
  • (e) Check that the flue terminal is unobstructed and that the flue system is sealed correctly.
  • (f) if the appliance has been installed in a compartment, check that the ventilation areas are clear.

The servicing procedures are covered more fully in Frames 2 to 8 and must be carried out in sequence.

WARNING. Always turn off the gas supply at the gas service cock and and switch off & disconnect the electricity supply to the appliance before servicing.

IMPORTANT. After completing the servicing or exchange of components always test for gas soundness and carry out functional checks as appropriate.

Note. In order to carry out either servicing or replacement of components, the boiler casing must be removed (Frame 2). IMPORTANT. When work is complete the casing MUST be

correctly refitted, ensuring that a good seal is made. DO NOT OPERATE THE BOILER IF THE CASING IS NOT FITTED.

3 BURNER AND AIR BOX REMOVAL

1. Remove the wing nut securing the burner front support bracket. Remove the M5 pozi screw situated at the left hand, bottom rear of the burner & pull the burner downwards in

GENERAL - CLEANING AND ADJUSTMENT

2 BOILER CASING REMOVAL

  • 1. Release the top two captive screws.
  • 2. Slide the glass fascia upwards until it locates in the retaining catch.

3. Remove the two securing screws, slide the bottom panel forward slightly, and then sideways to remove from the casing.

  • 4. Release the two bottom captive screws and lift the casing off the boiler. Place the casing safely to one side, taking care not to damage the glass fascia panel. Slide the glass panel down in the casing for safe keeping.
  • 2. Remove the control box lid fixing screws. Pull the lid forwards and upwards to disengage the catches and remove the lid.
  • 3. Pull the H.T. lead connection off the printed circuit board and pull the lead through the bottom panel grommet.

Page 26

CLEANING AND ADJUSTMENT - REPLACEMENT OF PARTS

5 CLEANING THE FLUEWAYS

1. Stacken the 4 wing nuts, disengage the tie rods and remove the flue collector hood.

Place a plastic sheet, or similar, beneath the boiler and remove all loose deposits from the heat exchanger finned block and copper skirt using a suitable brush and / or clearing rod - brushing from above and below.

7 RE-ASSEMBLY

Re-assemble the boiler in the following order:

1. Refit the flue collector hood - renewing any damaged or deteriorating sealing gasket.

Note. Enter the horizontal tie rods, with the hooks vertical, through the collector hood slots and engage in the holes in the retention angle.

  • 2. Reconnect the pressure switch sensing pipe.
  • 3. Refit the fan mounting plate assembly, taking care to reconnect the pressure sensing pipe.

  • B CLEANING THE BURNER AND PILOT ASSEMBLY
  • Brush off any deposits that may have fallen on to the burner head, ensuring the flame ports are un-obstructed and remove any debris that may have collected. Note. Brushes with metallic bristles MUST NOT be used.
  • 2. Remove the main burner injector and ensure there is no blockage or damage. Clean or renew as necessary.
  • 3. Refit the injector using an approved jointing compound sparingly.
  • 4. Inspect the pilot burner & ignition / detection electrode. Ensure that they are clean & in good condition. Check that:
    • (a) The pilot burner injector is not blocked or damaged. Refer to Frame 13 for removal details.
    • (b) The pilot burner is clean and unobstructed.
    • (c) The ignition/detection electrode is clean and undamaged.
    • (d) The ignition / detection lead is in good condition.
    • (e) The spark gap is correct (Frame 13). Clean or renew as necessary.
  • 4. Refit the air box assembly and burner.
  • 5. Refit the control box cover.
  • 6. Turn on the gas supply at the gas service cock.
  • 7. Re-connect the electricity supply.
  • 8. Check the sightglass in the boiler casing. Clean or renew as necessary. Refer to Frame 10.
  • 9. Refit the boiler casing.

IMPORTANT. When work is complete the casing MUST be correctly re-fitted. Ensure that a good seal is made.

B GAS PRESSURE ADJUSTMENT

PILOT Light the boiler and check that the pilot flame envelopes the ignition / detection electrode.

The pilot is factory set to maximum and no further adjustment is possible. However, if the pilot flame length is incorrect then remove and inspect the pilot injector. Refer to Frame 13. Relight in accordance with 'Initial Lighting'. Refer to Frame 46 'Installation'.

MAIN BURNER

After any servicing, reference should be made to Table 2 which quotes details of the rated output with the related burner setting pressure and the heat input. Any required adjustments should be made by using the pressure adjustment screw. Refer to 'Initial Lighting', Frame 46 'Installation'.

REPLACEMENT OF PARTS

9 GENERAL When replacing any component: Note. In ore er to assist fault finding the control box printed circuit board is
1. Isolate the electricity supply. fitted with 4 indicator lights which represent the following boiler conditions:
2. Turn OFF the gas supply Neon i1. Air pressure switch made.
3. Remove the boiler casing. Refer to Frame 2. Neon 12. Boiler thermostat calling for heat.
IMPORTANT. When work is complete the casing MUST be
correctly refitted, ensuring that a good seal is made.
Neon 13. Mains electricity ON.
Neon SG1 Flashes to indicate spark operation (stops after detection).
τ he boiler MUST NOT be operated if the casing is not fitted.
Page 27

REPLACEMENT OF PARTS

Page 28

REPLACEMENT OF PARTS

15 MAIN BURNER AND MAIN BURNER INJECTOR REPLACEMENT

  • 1. Refer to Frame 9.
  • 2. Remove the wing nut retaining the front burner support bracket. Refer to Frame 3.
  • 3. Remove the M5 pozi screw and washer, situated at the left hand bottom rear of the burner. Pull the burner downwards to disengage the retention tab and remove the burner.
  • 4. Withdraw the burner from the boiler.
  • 5. At this stage the main burner injector can be removed, checked, cleaned or replaced as required. Ensure that an approved jointing compound is used sparingly.
  • 6. Transfer the front support bracket to the new burner.
  • Fit the new burner, ensuring that the retention tab is correctly located in the air box slot.
  • 8. Refit M5 retaining screw and washer.
  • 9. Refit the boiler casing. Refer to Frame 7.
  • 10. Check the burner for cross-lighting and flame stability.

Page 29

SERVICING -

18 GAS CONTROL VALVE REPLACEMENT

ate. Also refer to Frame 26 of 'Exploded Views' for illustration of the procedure detailed below.

  • . Refer to Frame 9.
  • 2. Remove the control box as follows
    • (a) Remove the lid and unclip the front panel. Refer to Frame 11.
    • (b) Pull off the connections at the printed circuit board. Refer to Frame 39 'Installation'
    • (c) Release the central fixing screw. Refer to Frame 27. Withdraw and suspend the control box.
    • (d) Pull off the solenoid electrical connections and unscrew the earth lead at the gas control valve. Refer to Frame 39 'Installation'.
    • (e) Suspend the control box from the incomming mains lead.
  • 3. Remove the four M4 extended nuts securing the gas service cock to the das valve.

17 GAS CONTROL VALVE SOLENOID REPIACEMENT

  • 1. Refer to Frame 9.
  • 2. Remove the control box from the das control valve. Refer to Frame 16
  • 3. Slide out the spring clip and remove the solenoid from the gas control valve.
  • 4. Fit the new solenoid and re-assemble in reverse order.

Gas control val Spring clip noid mounting c

4. Whilst supporting the gas control valve, remove the two screws retaining the manifold to the back panel.

  • 6. Remove the four screws securing the manifold extension to the gas control valve and withdraw the valve.
  • 7. Fit the new gas control valve, ensuring that:
    • (a) The valve is fitted the correct way round (an arrow engraved on the back indicates the direction of flow).
    • (b) The sealing gasket and 'O' ring supplied with the valve are correctly fitted.
  • 8. Re-assemble in reverse order.
  • 9. Replace the burner / air box assembly.
  • 10. Replace the boiler casing. Refer to Frame 7.
  • 11. Check the gas valve operation

18 FAN UNIT REPLACEMENT

  • 1. Refer to Frame 9
  • 2. Disconnect the pressure sensing tube from the fan
  • 3. Disconnect the fan electical leads and unclip the harness from the fan mounting plate, A Remove the four screws securing the fan assembly.
  • 5. Slide the fan assembly clear of the boiler, disengaging the fan outlet elbow from the flue. Note, Always take care when handling the fan in order to preserve the balance of the impeller
  • 6. Transfer the pressure sensing pipe connector to the n

9. Check the boiler operation.

Pressure switch

REPLACEMENT OF PARTS

Page 30

REPLACEMENT OF PARTS

Front nanel

ol box lid

21 THERMOSTAT SWITCH REPLACEMENT

  • 1. Refer to Frame 9.
  • 2. Remove the control box lid. Refer to Frame 11.
  • 3. Disconnect the two electrical leads from the switch.
  • 4. Compress the retaining clips and prise the defective switch out of the front panel.
  • 5. Fit the new switch and re-assemble in reverse order. Ensure that the switch is the correct way round, i.e. with the terminals towards the right, as shown. Polarity is immaterial.
  • 6. Refit the boiler casing. Refer to Frame 7.
  • 7. Check the operation of the thermostat.

Thermostat switch

Page 30

Page 31

1. Refer to Frame 9.

2. Drain down the system and heat exchanger.

23 HEAT EXCHANGER REPLACEMENT IMPORTANT. Before starting the removal procedure, protect the gas electrical controls with a waterproof sheet or plastic bag. 24 CASING SEAL REPLACEMENT 1. Refer to Frame 9.

  • Remove the boiler control box lid and release the terminal strip from its slide retention. Disconnect the 'L', 'N' & ' * connections from the terminal strip and release the cable clamps.
  • 3. Remove the 2 screws retaining the programmer mounting bracket to the back panel mounting bracket.

. Daar ar

Remove the old seals from the channel in the casing, and press in the new seals (4 pieces). Replace the boiler casing. Refer to Frame 7. Note. Ensure that the casing is correctly seated -compressing the sealing strip to make an airtight joint. If side clearances are

Note. Ensure that the casing is correctly sealed -compressing the sealing strip to make an airtight joint. If side clearances are limited, then this can be checked by ensuring that top and bottom edges of the casing are correctly located.

  • 4. Pull the programmer mounting bracket downward and forward in order to disengage the terminal strip connection.
  • 5. Remove the 2 screws fastening the stainless steel lid to the programmer mounting bracket and remove the lid.
  • 6. Slide the programmer upwards in order to clear the mounting bracket.
  • 7. Remove the strain relief bush retaining the control box feed cable and remove the earth lead from the earth post.
  • 8. Remove the 3 screws retaining the terminal strip to the programmer mounting bracket.
  • 9. Remove the programmer, complete with its terminal strip and wiring harness.
  • 10. Fit the new programmer, terminal strip and wiring harness in reverse order.

11. Sat the ornorammer to the desired occoramme & test its indigits

REPLACEMENT OF PARTS

Page 32

EXPLODED VIEWS

Page 33

_____

Page 34

SHORT LIST OF PARTS

Ideal Elan 2 NF 230, NF 240, NF 250, NF 260 and NF 280 Gas Boilers

The following list comprises parts commonly required as replacement components due to damage, expendability, or such that their failure or absence is likely to affect safety or performance. The list is extracted from the British Gas List of Parts, which contains all available spare parts.

Details of the British Gas Lists are held by Gas regions, CARADON Distributors and by Merchants.

When ordering spares please quote:

  • 1. Boiler Model
  • 2. Appliance G.C. Number
  • 3. Description
  • 4. Maker's Part Number
  • 5. Quantity
Key No. G.C. Part No. Description No. Off Product Code No.
З 319 493 Sightglass assembly kit. 1 079 333
5 Main burner.
386 235 386 235 AEROMATIC No. AC 19/123 278; NF 230 113 207
386 236 AEROMATIC No. AC 19/123 279; NF 240 1 113 208
386 233 AEROMATIC No. AC 19/123 276; NF 250 & NF 260 1 113 209
386 234 AEROMATIC No. AC 19/123 277; NF 280 1 113 210
6 Main burner injector.
398 315 BRAY Cat. 16 - size 750; NF 230 1 002 773
398 339 BRAY Cat. 16 - size 1100; NF 240 1 003 279
398 329 BRAY Cat. 16 - size 1400; NF 250 1 003 962
398 332 BRAY Cat. 16 - size 1700; NF 260 1 003 213
398 066 BRAY Cat. 10 - size 2400; NF 280 1 004 444
8 308 347 Pilot burner. HONEYWELL Q 359 A 1124 1. 079 599
9 Pilot burner injector.
386 131 HONEYWELL 45900421 - 001; NF 230 & NF 240 1 004 981
386 150 HONEYWELL 45900421 - 002; NF 250, NF 260 & NF 280 1 004 982
10 308 359 Gas control valve.
HONEYWELL VR 4700 E 1042, 240 V 1 079 600
11 308 281 Control box, including control thermostat potentiometer,
control thermostat, sensor lead, control thermostat knob
40 and mains ON / OFF switch. 1 137 656
12 308 317 Ignition electrode. VERNITRON No. 1414 1 113 172
15 386 149 Automatic ignition printed circuit board.
PACTROL P.C.B. No. 25B 1 079 716
16 386 802 Control thermostat ON / OFF switch. 1 004 882
17 308 285 Pressure switch, BECK 911.81 L 1 137 990
18 397 910 Control thermostat potentiometer. 1 137 661
. 18 A 308 357 Control thermostat sensor lead. 1 137 658
18 B 308 283 Control thermostat knob. 1 079 601
20 386 675 Overheat thermostat, RANCO LM 7. 589 930 056
21 386 686 Fan assembly. 009 930 036
SIFAN FFB 0224 - 004 or SEL RL 108/0034 - 3030 L H 1 126 729
26 Boiler casing assembly - white stove enamel with · 1 130720
sightglass, foil insulation & bottom panel (less glass fascia). ·
308 372 Ideal Elan 2 NF 230, NF 240, NF 250 & NF 260. 198 934 035
308 408 ideal Elan 2 NF 280. 1 137,989
27 Controls casing bottom panel.
308 373 Ideal Elan 2 NF 230, NF 240, NF 250 & NF 260. 1 079.612
308 409 Ideal Elan 2 NF 280. 1 079 613
28 308 374 Glass fascia. Ideal Elan 2 NF 230, NF 240, NF 250 & NF 260. 1 137 900
· 308 383 Ideal Elan 2 NF 280. 1 137 904
30 308 058 Casing seal. Ideal Elan 2 NF 230 NF 240 NF 250 2 NF 260 070 520
308 059 Ideal Elan 2 NF 280. 079 532
1 019 233
Page 35

SHORT LIST OF PARTS - COMPONENT DIAGRAMS

Page 36

THIS SYMBOL IS YOUR ASSURANCE OF QUALITY

These appliances are designed for use with Natural Gas only. They have been tested and conform with the provisions of BS. 6332 and BS. 5258.

Products bearing this Kitemark are made to a safety and performance standard under a stringent scheme of supervision and control monitored by the British Standards Institute.

CARADON IDEAL Ltd. pursues a policy of continuing improvement in the design and performance of its products. The right is therefore reserved to vary specification without notice.

CARADON IDEAL Ltd.

P.O. Box 103, National Avenue,

Registration No. London 322 137.

Kingston upon Hull.

North Humberside. HU5 4JN.

Telephone: 01482 492 251

Fax: 01482 448 858

Registered Office; National Avenue, Kingston upon Hull, North Humberside. HU5 4JN.

A subsidiary of Caradon p.I.c

August 1994 116 799 A07

Customer Care & Technical Support

Please use the following numbers for speedy assistance.

Spares Tel: 01482 498 643
Customer Care &
Technical Support Tel: 01482 498 610
Publications/literature Tel: 01482 498 467
Loading...