Huawei PRU01B04 Host Manual

LampSite

Installation Guide

Issue 08

Date 2014-12-30

HUAWEI TECHNOLOGIES CO., LTD.

Copyright © Huawei Technologies Co., Ltd. 2014. All rights reserved.

No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.

All other trademarks and trade names mentioned in this document are the property of their respective holders.

Notice

The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS" without warranties, guarantees or representations of any kind, either express or implied.

The information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.

Address: Huawei Industrial Base

Bantian, Longgang

Shenzhen 518129

People's Republic of China

Website: http://www.huawei.com

Email: support@huawei.com

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

i

Copyright © Huawei Technologies Co., Ltd.

 

 

LampSite

 

Installation Guide

About This Document

About This Document

Overview

This document describes how to install the modules and cables for the RHUB3908, pRRU3901 indoors. It also provides checklists for hardware installation.

Product Version

The following table lists the product version related to this document.

Product Name

Solution Version

Product Version

 

 

 

 

DBS3900

SRAN9.0 and later versions

V100R009C00 and later

 

RAN16.0 and later versions

versions

 

eRAN7.0 and later versions

 

 

eRAN TDD 7.0 and later

 

 

 

versions

 

 

 

 

 

Intended Audience

This document is intended for:

BTS installation personnel

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

ii

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

Contents

Contents

About This Document....................................................................................................................

ii

1 Changes in LampSite Installation Guide .................................................................................

1

2 Installation Preparations .............................................................................................................

6

2.1

Reference Documents ......................................................................................................................................

6

2.2 Preparing Tools and Instruments ......................................................................................................................

6

2.3

Requirements for Installation Personnel ..........................................................................................................

7

3 Unpacking and Checking ............................................................................................................

9

4 Installing a BBU ..........................................................................................................................

11

5 Installing an RHUB3908 ............................................................................................................

12

5.1

Information About the Installation .................................................................................................................

12

 

5.1.1 RHUB3908 Installation Scenarios ........................................................................................................

12

 

5.1.2 Installation Clearance Requirements of an RHUB3908........................................................................

17

 

5.1.3 Installation Environment of an RHUB3908..........................................................................................

19

5.2

Installation Process.........................................................................................................................................

21

5.3

Installing an RHUB3908 ................................................................................................................................

21

 

5.3.1 Installing an RHUB3908 in a 19-Inch Cabinet or Rack........................................................................

21

 

5.3.2 Installing an RHUB3908 in a 19-Inch Shelf .........................................................................................

24

 

5.3.3 Installing an RHUB3908 on a Wall.......................................................................................................

27

5.4

Installing RHUB3908 Cables .........................................................................................................................

31

 

5.4.1 Requirements for Cable Layout ............................................................................................................

31

 

5.4.2 RHUB3908 Cable List ..........................................................................................................................

34

 

5.4.3 Cable Connections ................................................................................................................................

35

 

5.4.4 RHUB3908 Cable Installation Process .................................................................................................

35

 

5.4.5 Installing an RHUB3908 PGND Cable.................................................................................................

36

 

5.4.6 Installing an Ethernet Cable ..................................................................................................................

38

 

5.4.7 Installing CRPI Optical Cables .............................................................................................................

40

 

5.4.8 Installing an RHUB3908 Alarm Cable (Optional) ................................................................................

42

 

5.4.9 Installing an RHUB3908 Power Cable .................................................................................................

43

5.5

Checking the RHUB3908 Hardware Installation ...........................................................................................

44

5.6 Power-on Check on an RHUB3908 ...............................................................................................................

46

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

iii

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

 

Installation Guide

Contents

6 Installing a pRRU3901................................................................................................................

48

6.1

Information About the Installation .................................................................................................................

49

 

6.1.1 pRRU3901 Product Family...................................................................................................................

49

 

6.1.2 pRRU3901 Installation Scenario...........................................................................................................

49

 

6.1.3 Space Requirements ..............................................................................................................................

53

 

6.1.4 pRRU3901 Installation Environment Requirements.............................................................................

54

6.2

Obtaining the MAC Address (Optional).........................................................................................................

55

6.3

Installation Process.........................................................................................................................................

56

6.4

Installing a pRRU3901...................................................................................................................................

57

 

6.4.1 pRRU3901 Installation Kits..................................................................................................................

58

 

6.4.2 pRRU3901 Installed on a Wall..............................................................................................................

59

 

6.4.3 pRRU3901 Installed on a Ceiling .........................................................................................................

62

 

6.4.4 pRRU3901 Installed on a Pole..............................................................................................................

66

 

6.4.5 pRRU3901 Installed on a Plate .............................................................................................................

68

 

6.4.6 pRRU3901 Installed on a Keel .............................................................................................................

71

6.5

Installing pRRU3901 Cables..........................................................................................................................

74

 

6.5.1 Requirements for Cable Layout ............................................................................................................

74

 

6.5.2 pRRU3901 Cable List ...........................................................................................................................

76

 

6.5.3 Cable Connections ................................................................................................................................

76

 

6.5.4 Cable Connections (LTE TDD).............................................................................................................

79

 

6.5.5 pRRU3901 cable installation process ...................................................................................................

80

 

6.5.6 Installing an Ethernet Cable ..................................................................................................................

81

 

6.5.7 Installing pRRU3901 Jumpers (Optional).............................................................................................

82

6.6

Checking the pRRU3901 Hardware Installation ............................................................................................

84

6.7

Powering on the pRRU3901...........................................................................................................................

85

7 Installing the Extender (Optional)...........................................................................................

87

8 Appendix ......................................................................................................................................

90

8.1

MAC Collection Template .............................................................................................................................

90

8.2

LampSite Engineering Label..........................................................................................................................

91

8.3 Attaching an L-Shaped Label .........................................................................................................................

94

8.4

Installing RF Daughter Boards on a pRRU3901 (in Capacity Expansion Scenarios) ....................................

96

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

iv

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

1 Changes in LampSite Installation Guide

1 Changes in LampSite Installation Guide

This chapter describes the changes in the LampSite Installation Guide.

08 (2015-01-15)

This is the eighth commercial release.

Compared with 07 (2014-11-15), this issue includes the following new topics:

4 Installing a BBU

Compared with 07 (2014-11-15), this issue incorporates the following changes:

Content

Change Description

 

 

 

Entire document

Changed RHUB, and pRRU to

 

 

RHUB3908, and pRRU3901,

 

 

respectively.

 

Added the pRRU3901 with three

 

 

transmission ports plus no PWR port (or

 

 

the pRRU3901 AWS+PCS+WIFI for

 

 

use in North America) .

 

 

6.7 Powering on the pRRU3901

Deleted the description that the pRRU3901

 

supports AC/DC power supply.

 

 

 

Compared with 07 (2014-11-15), no information is deleted.

07 (2014-11-15)

This is the seventh commercial release.

Compared with 06 (2014-09-30), no information is added.

Compared with 06 (2014-09-30), this issue incorporates the following change:

 

Content

 

Change Description

 

 

 

 

 

 

Space Requirements

Added the requirements on the installation space

 

 

 

 

when the pRRU3901 working on the 2.6 GHz

 

 

 

 

 

 

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

1

 

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

1 Changes in LampSite Installation Guide

 

 

 

 

Content

Change Description

 

 

 

 

 

band and the Wi-Fi module need to process

 

 

services concurrently.

 

 

 

Compared with 06 (2014-09-30), this issue excludes the following topic:

Installing RF Daughter Boards on a pRRU3901 (in Capacity Expansion Scenarios)

06 (2014-09-30)

This is the sixth commercial release.

Compared with 05 (2014-08-30), no information is added.

Compared with 05 (2014-08-30), this issue incorporates the following changes:

 

Content

 

 

Change Description

 

 

 

 

 

 

 

 

pRRU Installation Environment

 

 

Changed the operating temperature of

 

 

Requirements

 

 

pRRU3901s to a range from - 5°C to +

 

 

 

 

 

40°C.

 

 

 

 

 

 

 

 

Requirements for Cable Layout

 

 

Added the cabling requirements for Ethernet

 

 

 

 

 

cables.

 

 

Requirements for Cable Layout

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Compared with 05 (2014-08-30), no information is deleted.

05 (2014-08-30)

This is the fifth commercial release.

Compared with 04 (2014-07-30), no information is added.

Compared with 04 (2014-07-30), this issue incorporates the following changes:

 

Content

 

 

Change Description

 

 

 

 

 

 

 

 

Installation Clearance Requirements of an

 

 

Added the security precautions for the

 

 

RHUB

 

 

RHUB3908 installation environment.

 

 

 

 

 

 

 

 

Requirements for Cable Layout

 

 

 

 

 

 

 

 

 

 

 

Installing an Ethernet Cable

 

 

Added the Ethernet cable specifications and

 

 

 

 

 

requirements on flame spread rating.

 

 

Installing an Ethernet Cable

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Compared with 04 (2014-07-30), no information is deleted.

04 (2014-07-30)

This is the fourth commercial release.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

2

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

1 Changes in LampSite Installation Guide

Compared with 03

(2014-06-30), no information is added.

Compared with 03

(2014-06-30), this issue incorporates the following change:

 

 

 

Content

 

Change Description

 

 

7 Installing the Extender (Optional)

Added the descriptions about installing a

 

 

Extender on a Ceiling.

 

 

 

Compared with 03 (2014-06-30), no information is deleted.

03 (2014-06-30)

This is the third commercial release.

Compared with 02 (2014-05-30), this issue includes the following new topics:

8.2 LampSite Engineering Label

8.3 Attaching an L-Shaped Label

Compared with 02 (2014-05-30), this issue incorporates the following changes:

 

Content

 

 

Change Description

 

 

 

 

 

 

 

 

Cable Connections

 

 

Modified the description about cable

 

 

 

 

 

connections of the RHUB3908.

 

 

 

 

 

 

 

 

Installing RHUB Cables

 

 

Added the steps for attaching labels to

 

 

 

 

 

cables.

 

 

Installing pRRU Cables

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Installing an Ethernet Cable

 

 

Added the steps for making Ethernet cables.

 

 

 

 

 

 

 

 

Installing an Ethernet Cable

 

 

 

 

 

 

 

 

 

 

 

Installing RF Daughter Boards on a

 

 

Added the descriptions about the supported

 

 

pRRU3901 (in Capacity Expansion

 

 

block type.

 

 

Scenarios)

 

 

 

 

 

 

 

 

 

 

Compared with 02 (2014-05-30), no information is deleted.

02 (2014-05-30)

This is the second commercial release.

Compared with 01 (2014-04-26), no information is added.

Compared with 01 (2014-04-26), this issue incorporates the following change:

Content

Change Description

 

 

Entire document

Added the descriptions about the LTE

 

FDD+LTE FDD mode.

 

 

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

3

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

1 Changes in LampSite Installation Guide

Compared with 01 (2014-04-26),

no information is deleted.

01 (2014-04-26)

This is the first commercial release.

Compared with Draft C (2014-03-26), no information is added.

Compared with Draft C (2014-03-26), this issue incorporates the following change:

Content

Change Description

 

 

Entire document

Changed the pRRU3901 name from

 

pRRU3901 with two Ethernet ports to

 

pRRU3901 with two transmission ports, and

 

pRRU3901 with three Ethernet ports to

 

pRRU3901 with three transmission ports.

 

 

Compared with Draft C (2014-03-26), no information is deleted.

Draft C (2014-03-26)

This is a draft release.

Compared with Draft B (2014-02-28), no information is added.

Compared with Draft B (2014-02-28), this issue incorporates the following changes:

Content

Change Description

 

 

Installing CRPI Optical Cables

Added the description of connecting the

 

CPRI cable to the TX and RX ports of the

 

optical module crossly.

 

 

pRRU Installation Environment

The operating temperature of pRRU3901 is

Requirements

updated.

 

 

Compared with Draft B (2014-02-28), no information is deleted.

Draft B (2014-02-28)

This is a draft release.

Compared with draft A (2013-11-30), this issue includes the following new topics:

Obtaining the MAC Address (Optional)

Cable Connections

MAC Collection Template

Compared with draft A (2013-11-30), this issue incorporates the following changes:

 

Content

 

Change Description

 

 

 

 

 

 

 

Entire document

 

Added descriptions about pRRU3901s with

 

 

 

 

 

 

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

4

Copyright © Huawei Technologies Co., Ltd.

LampSite

 

 

 

Installation Guide

 

 

1 Changes in LampSite Installation Guide

 

 

 

 

 

 

 

 

Content

 

 

Change Description

 

 

 

 

 

 

 

 

 

 

 

three transmission ports. Such pRRU3901s

 

 

 

 

 

support integrated Wi-Fi services.

 

 

 

 

 

 

 

 

 

 

 

Added the descriptions about the UMTS,

 

 

 

 

 

LTE FDD and UMTS+LTE FDD mode.

 

 

 

 

 

 

 

 

LampSite Installation Guide

 

 

Optimized descriptions about matching

 

 

 

 

 

product versions.

 

 

 

 

 

 

 

 

Installing an Ethernet Cable

 

 

Changed the cable name from

 

 

 

 

 

RHUB3908-pRRU3901 Ethernet cable to

 

 

Installing an Ethernet Cable

 

 

 

 

 

 

Ethernet cable.

 

 

 

 

 

 

 

 

 

 

 

Compared with draft A (2013-11-30), this issue excludes the following topics:

Installing External Antennas (Optional)

RHUB3908 Exterior

RHUB3908 Ports and Indicators

pRRU3901 Exterior

pRRU3901 Ports and Indicators

Draft A (2013-11-30)

This is a draft release.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

5

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

2 Installation Preparations

2 Installation Preparations

About This Chapter

Before starting the installation, you must obtain the required reference documents, tools, and instruments, and familiarize yourself with the skills required.

2.1 Reference Documents

Before the installation, you must read the following documents:

2.2 Preparing Tools and Instruments

This section describes the tools and instruments that must be prepared before the installation.

2.3 Requirements for Installation Personnel

This section describes requirements for installation engineers. They must be qualified and trained, and familiar with correct operation methods and safety precautions before performing any operations.

2.1 Reference Documents

Before the installation, you must read the following documents:

LampSite Hardware Description

Installation Reference

For details about how to install a baseband unit (BBU), see DBS3900 Installation Guide.

2.2 Preparing Tools and Instruments

This section describes the tools and instruments that must be prepared before the installation.

 

Marker

 

Torque screwdriver

Diagonal pliers

 

Level

 

 

 

 

 

 

(M4 to M6)

 

 

 

 

 

 

 

 

 

 

 

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

6

 

 

Copyright © Huawei Technologies Co., Ltd.

 

Huawei PRU01B04 Host Manual

LampSite

 

 

Installation Guide

 

2 Installation Preparations

 

 

 

 

 

Power cable crimping tool

RJ11 crimping tool

Cable cutter

 

 

 

 

 

Rubber mallet

T20 torque torx screwdriver

Wire stripper

 

 

 

 

 

Hammer drill (Ø6, Ø8 and

Torque wrench (Ø10 mm)

Protective gloves

 

Ø12)

 

 

 

 

 

 

 

Guarded blade utility knife

ESD gloves

Long measuring tape

 

 

 

 

 

Multimeter

Network cable tester

Vacuum cleaner

 

 

 

 

 

Ladder

Torque wrench for SMA

Socket wrench (M6)

 

 

connector

 

 

 

 

 

2.3 Requirements for Installation Personnel

This section describes requirements for installation engineers. They must be qualified and trained, and familiar with correct operation methods and safety precautions before performing any operations.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

7

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

2 Installation Preparations

Before the installation, pay attention to the following items:

Technical engineers must take Huawei training and be familiar with proper installation and operation methods.

The number of installation personnel depends on the engineering schedule and installation environment. Generally, three to five persons are required. Generally, only three to five onsite personnel are necessary.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

8

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

3 Unpacking and Checking

3 Unpacking and Checking

This section describes how to unpack and check the delivered equipment to ensure that the materials are complete and intact.

Context

The following lists important notes when you are transporting, lifting, or installing the equipment or components:

Protect them from colliding with doors, walls, shelves, or other objects.

Wear clean gloves and do not touch them with bare hands, sweat-soaked gloves, or dirty gloves.

You must power on the RHUB3908 or pRRU within 7 days after it is unpacked.

Procedure

1.Count the total number of the shipments.

 

If...

Then...

 

 

 

 

The total number of the components is

Go to Step 2.

 

consistent with that recorded in the

 

 

packing lists on all packing boxes

 

 

 

 

 

The total number of the components is

Report the problems and causes to the local

 

inconsistent with that recorded in the

Huawei office.

 

packing lists on all packing boxes

 

 

 

 

Step 2 Check the exterior of each packing box.

 

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

9

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

3 Unpacking and Checking

 

 

 

 

 

 

If...

Then...

 

 

 

 

 

 

The exterior of each packing box is

Go to Step 3.

 

 

intact

 

 

 

 

 

 

 

It is damaged or soaked

Report the problems and causes to the local

 

 

 

Huawei office.

 

 

 

 

 

 

The collision label is red

Do not unpack the packing box and claim

 

 

 

for compensation from the transportation

 

 

 

company.

 

 

 

 

Step 3 Check the type and quantity of the equipment in the boxes according to the packing list.

 

 

 

 

 

 

If...

Then...

 

 

 

 

 

 

The type and number are consistent

Sign the Packing List with the operator.

 

 

with the packing list on each packing

 

 

 

list

 

 

 

 

 

 

 

There is any shortage, wrong delivery,

Report the problems and causes to the local

 

 

or damaged equipment

Huawei office.

 

 

 

 

 

 

 

 

Perform the following operations to protect the components from any damages and help find out the cause of any damage in future: 1. Store the unpacked equipment and packing materials indoors. 2. Take photos of the storeroom, rusted or eroded equipment, packing box, and packing materials. 3. File the photos.

----End

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

10

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

4 Installing a BBU

4 Installing a BBU

This chapter describes the process of installing a BBU.

The BBU can have BBU3900 and BBU3910. Unless otherwise specified, the BBU refers to both the BBU3900 and BBU3910 in this document.

For details about the installation of the BBU, see DBS3900 Installation Guide.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

11

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

5 Installing an RHUB3908

About This Chapter

This chapter describes the process of installing an RHUB3908.

5.1 Information About the Installation

This section describes the information to be learnt before RHUB3908 installation, including the RHUB3908 installation scenarios, clearance, and installation environment.

5.2 Installation Process

The RHUB3908 installation involves installing an RHUB3908 module, installing RHUB3908 cables, checking the RHUB3908 hardware installation, and powering on the RHUB3908.

5.3 Installing an RHUB3908

An RHUB3908 can be installed in a cabinet, rack, shelf, or on a wall.

5.4 Installing RHUB3908 Cables

This section describes how to install cables for an RHUB3908.

5.5 Checking the RHUB3908 Hardware Installation

After an RHUB3908 is installed, check the installation of hardware including the devices and related cables.

5.6 Power-on Check on an RHUB3908

This section describes the power-on check on the RHUB3908 after the RHUB3908 hardware is installed and checked.

5.1 Information About the Installation

This section describes the information to be learnt before RHUB3908 installation, including the RHUB3908 installation scenarios, clearance, and installation environment.

5.1.1 RHUB3908 Installation Scenarios

An RHUB3908 can be installed in a 19-inch cabinet, rack, shelf, or on a wall.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

12

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

The RHUB3908 supports that mounting ears are installed in standard mode or reverse mode. The reverse mode is used by default. The two installation modes are defined as follows:

In standard mode, the front of the mounting ear is aligned with the RHUB3908 panel, as shown in Figure 5-1.

Figure 5-1 Installing mounting ears in standard mode

In reverse mode, the front of the mounting ear is 31 mm away from the RHUB3908 panel, as shown in Figure 5-2.

Figure 5-2 Installing mounting ears in reverse mode

Installing an RHUB3908 in a 19-Inch Cabinet or Rack

Installing an RHUB3908 in a 19-inch cabinet or rack: Secure the mounting ear to the mounting bracket by using M6 screws.

If there is no other modules installed in the 1 U space near the RHUB3908, install the RHUB3908 directly. Otherwise, remove the modules before installing the RHUB3908.

Before installation, you need to check the installation mode supported by the rack and adjust the position of the mounting ear.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

13

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

 

Figure 5-3 and Figure 5-4 show RHUB3908s installed in a cabinet or rack, respectively.

 

Figure 5-3 Installing an RHUB3908 in a 19-inch cabinet or rack in standard mode

Figure 5-4 Installing an RHUB3908 in a 19-inch cabinet in reverse mode

Installing an RHUB3908 in a 19-Inch Shelf

When an RHUB3908 is installed in a 19-inch shelf, the shelf must be installed on a wall. One shelf can house multiple RHUB3908s with 1 U space between two RHUB3908s.

Figure 5-5 and Figure 5-6 show RHUB3908s installed in a 19-inch shelf.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

14

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

Figure 5-5 RHUB3908 installed in a 19-inch shelf in standard mode

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

15

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

Figure 5-6 RHUB3908 installed in a 19-inch shelf in reverse mode

Installing an RHUB3908 on a Wall

An RHUB3908 can be installed on a wall.

The wall on which an RHUB3908 is installed must meet the following requirements:

When a single RHUB3908 is installed, the wall must have a capacity of bearing at least four times the weight of the RHUB3908.

Expansion bolts must be tightened to 10 N·m (88.507 bf·in.) to ensure the bolts work properly and the wall remains intact without cracks in it.

Figure 5-7 shows an RHUB3908 installed on a wall.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

16

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

Figure 5-7 RHUB3908 installed on a wall

5.1.2 Installation Clearance Requirements of an RHUB3908

When an RHUB3908 is installed in a 19-inch cabinet, rack, shelf, or on a wall, a minimum clearance is required for easy cabling and operation and maintenance. A recommended installation clearance is provided based on experience.

Do not install or place inflammable materials above or under an RHUB3908.

A clearance of 350 mm must be reserved in front of the air intake vent of the fan of the power supply unit (PSU) for maintenance.

Figure 5-8 shows the installation clearance for the RHUB3908 installed in a 19-inch cabinet, rack, or shelf.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

17

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

 

Figure 5-8 Installation clearance for an RHUB3908 installed in a 19-inch cabinet, rack, or shelf

Figure 5-9 and Figure 5-10 shows the recommended and minimum installation clearance respectively when the RHUB3908 is installed on a wall.

Figure 5-9 Recommended installation clearance for a wall-mounted RHUB3908 (unit: mm)

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

18

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

Figure 5-10 Minimum installation clearance for a wall-mounted RHUB3908 (unit: mm)

5.1.3 Installation Environment of an RHUB3908

The installation environment of an RHUB3908 involves the running environment specifications for the RHUB3908 and other specifications.

RHUB3908 Running Environment Specifications

Table 5-1 shows the environment specifications for the RHUB3908 installed indoors.

The temperature and humidity of the installation position must ensure normal operation. A cool and ventilated place is recommended.

The heat dissipation holes on the RHUB3908 cannot be blocked.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

19

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

 

 

 

 

 

 

 

 

 

 

 

Installation Guide

 

 

 

 

 

 

 

 

 

 

 

5 Installing an RHUB3908

 

Table 5-1 RHUB3908 environment specifications

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Specifi

 

 

Installation

 

 

RHUB3908

 

 

Condition

 

 

Remarks

 

 

cations

 

 

Scenario

 

 

Quantity

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operati

 

 

Installed on a

 

 

N/A

 

 

-5°C to

 

 

N/A

 

 

ng

 

 

wall or in a

 

 

 

 

 

+50°C

 

 

 

 

 

tempera

 

 

19-inch rack.

 

 

 

 

 

 

 

 

 

 

 

ture

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Installed in a

 

1

 

 

-5°C to

 

 

N/A

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

shelf.

 

 

 

 

 

+45°C

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2

 

 

-5°C to

 

 

N/A

 

 

 

 

 

 

 

 

 

 

 

+43°C

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3

 

 

-5°C to

 

 

N/A

 

 

 

 

 

 

 

 

 

 

 

+40°C

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Relativ

 

 

Installed in all

 

 

N/A

 

 

5% RH to

 

 

N/A

 

 

e

 

 

scenarios.

 

 

 

 

 

95% RH

 

 

 

 

 

humidit

 

 

 

 

 

 

 

 

 

 

 

 

 

 

y

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Altitude

 

 

N/A

 

 

N/A

 

 

-60 m to

 

 

Works properly.

 

 

 

 

 

 

 

 

 

 

 

+1800 m

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1800 m to

 

 

Above the 1800 m altitude,

 

 

 

 

 

 

 

 

 

 

 

4000 m

 

 

the maximum operating

 

 

 

 

 

 

 

 

 

 

 

 

 

 

temperature decreases by

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1°C each time the altitude

 

 

 

 

 

 

 

 

 

 

 

 

 

 

increases by 220 m.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Installing more than one RHUB3908, 1 U space is required between two RHUB3908s.

Other Running Environment Specifications

The RHUB3908 cannot be installed at an air outlet of the heat dissipation box of an air conditioner or other heat-generating appliances.

The RHUB3908 cannot be installed near a strong heat source.

The RHUB3908 cannot be installed in a position with water dripping, such as outdoor equipment of air conditioners, pipe, and leaking or dripping roofs.

The installation position must be far from rains. If the RHUB3908 is installed on a wall, there must be no window on either side of the wall.

The installation position must be far away from high voltage, highly corrosive devices, flammable or explosive substances, and electromagnetic interference.

The RHUB3908 must be installed in a dry, ventilating, and dust-proof place.

If the RHUB3908 is installed in parking areas or basements, the installation position must be well-ventilated.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

20

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

5.2 Installation Process

The RHUB3908 installation involves installing an RHUB3908 module, installing RHUB3908 cables, checking the RHUB3908 hardware installation, and powering on the RHUB3908.

Figure 5-11 shows the RHUB3908 installation process.

Figure 5-11 RHUB3908 installation process

5.3 Installing an RHUB3908

An RHUB3908 can be installed in a cabinet, rack, shelf, or on a wall.

5.3.1 Installing an RHUB3908 in a 19-Inch Cabinet or Rack

This section describes how to install an RHUB3908 in a 19-inch cabinet.

Procedure

The following describes how to install an RHUB3908 with mounting ears in reverse mode:

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

21

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

If necessary, request one more person for assistance.

1.With one hand holding it, align the mounting holes with the installation holes, slowly push the RHUB3908 into the required position in the cabinet, as shown in Figure 5-12.

Figure 5-12 Pushing an RHUB3908 into a cabinet

2.Use a torque screwdriver or Phillips screwdriver to tighten the four M6×16 screws with a torque of 2 N•m, as shown in Figure 5-13.

Figure 5-13 Tightening screws

The following describes how to install an RHUB3908 with mounting ears aligned with the RHUB3908 panel:

If necessary, request one more person for assistance.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

22

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

1.Remove the mounting ears on both sides of the RHUB3908 by removing the four M4×8 screws, as shown in Figure 5-14.

Figure 5-14 Removing mounting ears and screws

2.Use a torque screwdriver or Phillips screwdriver to tighten the four M4×8 screws with a torque of 1.4 N•m to install the removed mounting ears again, as shown in Figure 5-15. The mounting ears must be aligned with the RHUB3908 panel.

Figure 5-15 Installing mounting ears in standard mode

3.With one hand holding it, align the mounting holes with the installation holes, slowly push the RHUB3908 into the required position in the cabinet, as shown in Figure 5-16.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

23

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

Figure 5-16 Pushing an RHUB3908 into a cabinet

4.Use a torque screwdriver or Phillips screwdriver to tighten the four M6×16 screws with a torque of 2 N•m, as shown in Figure 5-17.

Figure 5-17 Tightening screws

----End

5.3.2 Installing an RHUB3908 in a 19-Inch Shelf

If a shelf houses more than one RHUB3908, 1 U space is required between two RHUB3908s. The PSU must be installed at the bottom of the cabinet.

Issue 08 (2014-12-30)

Huawei Proprietary and Confidential

24

 

Copyright © Huawei Technologies Co., Ltd.

 

LampSite

 

Installation Guide

5 Installing an RHUB3908

Procedure

The following describes how to install an RHUB3908 with mounting ears installed in reverse mode:

If necessary, request one more person for assistance.

1.With one hand holding it, align the mounting holes with the installation holes, slowly push the RHUB3908 into the required position in the shelf.

2.Use a torque screwdriver or Phillips screwdriver to tighten the four M6×16 screws with a torque of 2 N•m, as shown in Figure 5-18.

Figure 5-18 Tightening screws

The following describes how to install an RHUB3908 with mounting ears installed in standard mode:

If necessary, request one more person for assistance.

1.Remove the mounting ears on both sides of the RHUB by removing the four M4×8 screws, as shown in Figure 5-19.