No part of this document may be reproduced or transmitted in any form or by any means without prior written
consent of Huawei Technologies Co., Ltd.
Trademarks and Permissions
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the
customer. All or part of the products, services and features described in this document may not be within the
purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,
and recommendations in this document are provided "AS IS" without warranties, guarantees or
representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Huawei Technologies Co., Ltd.
Address:Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China
Website:http://www.huawei.com
Email:support@huawei.com
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This document describes how to install the modules and cables for the BBU, DCU, RHUB,
pRRU3901, pRRU3902, and pRRU3907 indoors. It also provides checklists for hardware
installation.
NOTE
l Unless otherwise specified, BBU in this document refers to BBU3900 and BBU3910.
l DCU3900 in this document refers to DCU.
l RHUB3908 in this document refers to RHUB.
l Unless otherwise specified, pRRU in this document refers to pRRU3901, pRRU3902, and pRRU3907.
Product Version
The following table lists the product version related to this document.
Product Name
DBS3900 LampSite
Intended Audience
This document is intended for:
lBTS installation personnel
Solution VersionProduct Version
l SRAN10.1 and later versions
l RAN17.1 and later versions
l eRAN8.1 and later versions
l eRAN TDD 8.1 and later
versions
V100R010C10 and later
versions
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
2.2 Preparing Tools and Instruments.................................................................................................................................... 5
2.3 Requirements for Installation Personnel.........................................................................................................................6
3 Unpacking and Checking............................................................................................................ 7
4 Installing a BBU.............................................................................................................................9
5 Installing a DCU.......................................................................................................................... 10
6 Installing an RHUB.....................................................................................................................11
6.1 Information About the Installation............................................................................................................................... 12
6.3 Installing an RHUB...................................................................................................................................................... 22
6.3.1 Installing an RHUB in a 19-Inch Cabinet or Rack....................................................................................................22
6.3.2 Installing an RHUB in a 19-Inch Shelf..................................................................................................................... 25
6.3.3 Installing an RHUB on a Wall................................................................................................................................... 28
6.4.1 Requirements for Cable Layout.................................................................................................................................32
6.4.9 Installing Power Cable...............................................................................................................................................45
6.5 Checking the RHUB Hardware Installation................................................................................................................. 46
6.6 Power-on Check on an RHUB......................................................................................................................................48
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
7 Installing a pRRU3901................................................................................................................ 50
7.1 Information About the Installation............................................................................................................................... 51
7.1.3 Space Requirements.................................................................................................................................................. 55
7.2 Obtaining the MAC Address (Optional) ..................................................................................................................... 57
7.4 Installing a pRRU3901................................................................................................................................................. 58
7.4.2 Installing a pRRU3901 on a Wall.............................................................................................................................. 60
7.4.3 Installing a pRRU3901 on a Ceiling..........................................................................................................................63
7.4.4 Installing a pRRU3901 on a Pole.............................................................................................................................. 66
7.4.5 Installing a pRRU3901 on a Plate............................................................................................................................. 68
7.4.6 Installing a pRRU3901 on a Keel..............................................................................................................................71
7.5.1 Requirements for Cable Layout.................................................................................................................................74
7.5.6 Installing an Ethernet Cable...................................................................................................................................... 81
7.5.7 Installing an RF jumpers (Optional)..........................................................................................................................83
7.6 Checking the pRRU3901 Hardware Installation.......................................................................................................... 85
7.7 Powering on the pRRU3901.........................................................................................................................................86
8 Installing a pRRU3902................................................................................................................ 88
8.1 Information About the Installation............................................................................................................................... 89
8.1.3 Space Requirements.................................................................................................................................................. 93
8.3 Installing a pRRU3902................................................................................................................................................. 96
8.3.2 Installing a pRRU3902 on a Wall.............................................................................................................................. 98
8.3.3 Installing a pRRU3902 on a Ceiling........................................................................................................................102
8.3.4 Installing a pRRU3902 on a Plate........................................................................................................................... 105
8.3.5 Installing a pRRU3902 on a Keel............................................................................................................................ 112
8.3.6 Installing a pRRU3902 on Steel Hangers................................................................................................................ 116
8.4.1 Requirements for Cable Layout...............................................................................................................................120
8.4.5 Installing an Ethernet Cable.................................................................................................................................... 125
8.4.6 Installing an RF Jumpers (Optional)....................................................................................................................... 126
8.5 (Optional) Installing a Combiner................................................................................................................................128
8.6 Checking the pRRU3902 Hardware Installation........................................................................................................ 130
8.7 Powering on the pRRU3902.......................................................................................................................................131
9 Installing a pRRU3907.............................................................................................................. 133
9.1 Information About the Installation............................................................................................................................. 134
9.1.2 Constraints and Limitations.....................................................................................................................................134
9.1.3 Installation Clearance and Space Requirements......................................................................................................137
9.3 Installing a pRRU3907............................................................................................................................................... 141
9.3.2 Installing a pRRU on a Wall.................................................................................................................................... 142
9.3.3 Installing a pRRU on a Pole.................................................................................................................................... 146
9.4.5 Installing a PGND Cable......................................................................................................................................... 152
9.4.6 Installing an RF Jumper...........................................................................................................................................153
9.4.7 Opening the Cover Plate of a pRRU Cabling Cavity.............................................................................................. 157
9.4.8 Installing an Ethernet Cable.................................................................................................................................... 158
9.4.9 Closing the Cover Plate of a pRRU Cabling Cavity............................................................................................... 160
9.5 Checking the pRRU3907 Hardware Installation........................................................................................................ 161
9.6 Powering on the pRRU3907.......................................................................................................................................163
10 Installing the Extender (Optional)....................................................................................... 165
11.1 MAC Collection Template........................................................................................................................................169
Before starting the installation, you must obtain the required reference documents, tools, and
instruments, and familiarize yourself with the skills required.
2 Installation Preparations
2 Installation Preparations
2.1 Reference Documents
Before the installation, you must read the following documents:
2.2 Preparing Tools and Instruments
This section describes the tools and instruments that must be prepared before the installation.
2.3 Requirements for Installation Personnel
This section describes requirements for installation engineers. They must be qualified and
trained, and familiar with correct operation methods and safety precautions before performing
any operations.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes requirements for installation engineers. They must be qualified and
trained, and familiar with correct operation methods and safety precautions before performing
any operations.
Socket wrench (M6)
Before the installation, pay attention to the following items:
lTechnical engineers must take Huawei training and be familiar with proper installation
and operation methods.
lThe number of installation personnel depends on the engineering schedule and
installation environment. Generally, three to five persons are required. Generally, only
three to five onsite personnel are necessary.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Report the problems and causes to the local
Huawei office.
7
DBS3900 LampSite
Installation Guide
Step 3 Check the type and quantity of the equipment in the boxes according to the packing list.
3 Unpacking and Checking
If...Then...
The exterior of each packing box is intactGo to Step 3.
It is damaged or soakedReport the problems and causes to the local
Huawei office.
The collision label is redDo not unpack the packing box and claim for
compensation from the transportation
company.
If...
The type and number are consistent with
the packing list on each packing list
There is any shortage, wrong delivery, or
damaged equipment
Then...
Sign the Packing List with the operator.
Report the problems and causes to the local
Huawei office.
NOTICE
Perform the following operations to protect the components from any damages and help find
out the cause of any damage in future: 1. Store the unpacked equipment and packing materials
indoors. 2. Take photos of the storeroom, rusted or eroded equipment, packing box, and
packing materials. 3. File the photos.
----End
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This chapter describes the process of installing an RHUB. RHUBs are classified into those
with electrical transmission ports and those with no electrical transmission ports. Unless
otherwise specified, this document uses the RHUBs with no electrical transmission ports as an
example.
6 Installing an RHUB
6 Installing an RHUB
6.1 Information About the Installation
This section describes the information to be learnt before RHUB installation, including the
RHUB installation scenarios, clearance, and installation environment.
6.2 Installation Process
The RHUB installation involves installing an RHUB module, installing RHUB cables,
checking the RHUB hardware installation, and powering on the RHUB.
6.3 Installing an RHUB
An RHUB can be installed in a cabinet, rack, shelf, or on a wall.
6.4 Installing RHUB Cables
This section describes how to install cables for an RHUB.
6.5 Checking the RHUB Hardware Installation
After an RHUB is installed, check the installation of hardware including the devices and
related cables.
6.6 Power-on Check on an RHUB
This section describes the power-on check on the RHUB after the RHUB hardware is
installed and checked.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes the information to be learnt before RHUB installation, including the
RHUB installation scenarios, clearance, and installation environment.
6.1.1 Installation Scenarios
An RHUB can be installed in a 19-inch cabinet, rack, shelf, or on a wall.
NOTICE
To prevent the RHUB from water drops, the RHUB panel must not face upwards (shown in
Figure 6-1) in any installation scenarios.
Figure 6-1 Improper installation mode
6 Installing an RHUB
The RHUB mounting ears are installed in standard mode or reverse mode. The reverse mode
is used by default. The two installation modes are defined as follows:
lIn standard mode, the front of the mounting ear is aligned with the RHUB panel, as
shown in Figure 6-2.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Figure 6-4 Installing an RHUB in a 19-inch cabinet or rack in standard mode
Figure 6-5 Installing an RHUB in a 19-inch cabinet in reverse mode
Installing an RHUB in a 19-Inch Shelf
When an RHUB is installed in a 19-inch shelf, the shelf must be installed on a wall. One shelf
can house multiple RHUBs with 1 U space between two RHUBs.
Figure 6-6 and Figure 6-7 show RHUBs installed in a 19-inch shelf.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
When an RHUB is installed in a 19-inch cabinet, rack, shelf, or on a wall, a minimum
clearance is required for easy cabling and operation and maintenance. A recommended
installation clearance is provided based on experience.
NOTICE
l Do not install or place inflammable materials above or under an RHUB.
l A clearance of 350 mm must be reserved in front of the air intake vent of the fan of the
power supply unit (PSU) for maintenance.
Figure 6-9 shows the installation clearance for the RHUB installed in a 19-inch cabinet, rack,
or shelf.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Type C upper-level AC circuit breakers or slow-blow fuses must be used for power cables.
The maximum current must not exceed 16 A. Table 6-2 describes the recommended
specifications.
Table 6-2 Circuit breaker specifications for power cables
6 Installing an RHUB
Power Supply
220 V AC single-phase≥ 6 A
110 V AC dual-live-wire
110 V AC single-phase≥ 12 A
6.2 Installation Process
The RHUB installation involves installing an RHUB module, installing RHUB cables,
checking the RHUB hardware installation, and powering on the RHUB.
Figure 6-12 shows the RHUB installation process.
Upper-level AC Circuit
Breaker (For a single
RHUB)
Cross-Sectional Area of
the Input Power Cable
1.5 mm
2
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
lRotate the mounting ears 90 degrees clockwise, and use a torque screwdriver or Phillips
screwdriver to secure the mounting ear with a torque of 1.4 N•m, as shown in Figure
6-24.
Figure 6-24 Installing mounting ears and screws
Step 2 Determine the position on the wall for installing the RHUB based on the requirements in the
engineering blueprint and 6.1.2 Installation Clearance Requirements. Place the RHUB to
the position to be installed against the wall, and then mark the four anchor points where the
mounting ear screws are fastened using a marker, as shown in Figure 6-25.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Figure 6-26 Drilling holes and installing expansion bolts
(1) M6×60
expansion bolt
(2) Nut(3) Spring washer(4) Flat washer(5) Extension tub
1.Use a hammer drill with bit 8 to drill holes with a diameter of 8 mm and a depth of 45
mm to 50 mm at the marked anchor points. All the holes have the same depth.
2.Use a vacuum cleaner to clear the dust inside and around each hole. If the distance
between two holes is incorrect, mark and drill holes again.
3.Partially tighten an expansion bolt and place it vertically into each hole.
4.Use a rubber mallet to hit the expansion bolt until the entire expansion sleeve is in the
hole.
5.Remove the M6×60 bolt, nut, spring washer, and flat washer from each expansion bolt in
sequence.
NOTICE
After removing an expansion bolt, ensure that the top of the expansion sleeve is level
with the wall. If it is not level, the RHUB cannot be installed on the concrete floor
evenly and securely.
Step 4 Align the mounting holes with the four M6×60 expansion bolts. Install spring washer 6 and
flat washer 6 in sequence on each M6×60 expansion bolt, insert the bolts to each expansion
tub, and then use a torque wrench or socket wrench to tighten the four M6×60 bolts with a
torque of 5 N•m to secure the RHUB to the wall, as shown in Figure 6-27.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
As shown in the preceding figure, when the RHUB is placed against the wall, ensure that the RHUB
panel is vertical to the ground and the PSU is on the lower part of the RHUB panel.
----End
6.4 Installing RHUB Cables
This section describes how to install cables for an RHUB.
6.4.1 Requirements for Cable Layout
Cables must be routed according to the specified cabling requirements to prevent signal
interference.
NOTE
If a cable listed below is not required, skip the requirements for routing the cable.
General Requirements for Cable Layout
National Standards
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
lThe steel pipe or fire-resistant rigid polyvinyl chloride pipe should be used for the cable
duct or for routing cables. The cross-sectional usage of the cable duct should be 30% to
50% and that of the pipe for routing cables should be 25% to 30%.
lCables are placed away from sharp objects or wall burrs. If these positions are inevitable,
protection pipes are required for the cables.
lCables are routed away from heat sources, or heat-insulation materials are added
between cables and heat sources.
lCables are routed away the cooling vents of the RHUB.
lA clearance is reserved at turns of a cable or the position close to a device, facilitating
cable and device maintenance. The recommended clearance is about 0.1 m.
Requirements for Special Cables
Ethernet Cable
lA maximum of 100 Ethernet cables can be bundled if no PVC pipes are used. If pipes are
used, a maximum of 24 Ethernet cables can be led through a pipe. In this case, ensure
that 1/3 space inside the pipes must be vacant.
lThe point at which an Ethernet cable is bundled must be spaced 400 mm or less from the
Ethernet port on an RHUB.
lFor the RHUB used in the elevator engine room on the rooftop, generator set for the
subway engine, and equipment room with central air conditioning, Ethernet cables must
be led through metallic conduits that are reliably grounded at both ends.
6 Installing an RHUB
Power cable
lPositions for routing power cables meet requirements of the engineering design.
lCables are routed only by qualified and trained personnel before all preparations are
made.
lCables are routed in an untangled and orderly fashion.
PGND cable
lPGND cables are buried in the ground or routed indoors. They cannot be routed
overhead before they are routed into the equipment room.
lOuter conductors of coaxial cables and both ends of the shield layers on shielded cables
are in proper electrical contact with the metal surface of the equipment to which they are
connected.
lPGND cables and signal cables are installed in an untangled and orderly fashion. A
certain distance is reserved between them to prevent interference from each other.
lFuses or switches are not allowed on PGND cables.
lOther devices cannot be used for electrical connections of PGND cables.
lAll the metal parts in the equipment are reliably connected to the ground terminal.
Optical cable
lCables are routed in an untangled and orderly fashion.
lOptical fibers cannot be bound at turns.
lOptical fibers cannot be stretched with too much force or stepped on, and they are far
away from sharp objects. Heavy objects cannot be placed on optical cables.
lWhen optical cables are routed, the extra length of the cables is coiled around special
devices, such as a fiber coiler.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
l If one end of the CPRI cable is connected to the DLC connector, the other end connects the BBU,
DCU or RHUB through the DLC connector. If one end of the CPRI cable is connected to the ODF
adapter, the other end connects the BBU or RHUB through a connector corresponding to the adapter.
The connectors include the FC connector, SC connector, and LC connector.
l The Extender can be used to lengthen the distance between the RHUB and the pRRU connected
using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one
between the RHUB and the Extender and the other between the Extender and the pRRU.
6.4.3 Cable Connections
This section describes the cable connections for an RHUB.
Figure 6-28 shows the cable connections for an RHUB. The port of ETH are reserved.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
The Extender can be used to lengthen the distance between the RHUB and the pRRU connected using
the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one between the
RHUB and the Extender and the other between the Extender and the pRRU.
6.4.4 Cable Installation Process
This section describes the process of installing RHUB cables.
Figure 6-29 shows the RHUB cable installation process.
Figure 6-29 RHUB cable installation process
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
An RHUB PGND cable ensures proper grounding of an RHUB.
Prerequisites
The OT terminals at both ends of the PGND cable are prepared.
Context
The yellow and green or green PGND cable is a single cable. The cross-sectional area of the
PGND cable is 6 mm2 (0.009 in.2). Both ends of the cable are OT terminals, as shown in
Figure 1.
Figure 6-30 Exterior of a PGND cable
6 Installing an RHUB
(1) OT terminal (6 mm
NOTE
l If the PGND cable is provided by the customer, a copper-core cable with a minimum cross-sectional
area of 6 mm2 (0.009 in.2) or 10 AWG is recommended.
l The OT terminals at both ends of the PGND cable are assembled at the site.
l The M6 OT terminal has the default size. You can replace it with another OT terminal of the
expected size based on the site requirement.
2
[0.009 in.2], M4)(2) OT terminal (6 mm2 [0.009 in.2], M6)
NOTICE
l Ensure proper grounding of the RHUB using a PGND cable.
l When installing the PGND cable, tightly press the OT terminal in the correct direction, as
shown in Figure 6-31.
Figure 6-31 Correct direction of an OT terminal for the PGND cable
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Step 1 Route the PGND cable by referring to 6.4.1 Requirements for Cable Layout.
Step 2 Use a torque screwdriver or Phillips screwdriver to secure the M4 OT terminal at one end of
6 Installing an RHUB
the PGND cable to the ground screw on the RHUB panel with a torque of 1.4 N•m. If the OT
terminal is a one-hole OT terminal, connect it to the ground screw on the lower part of the
RHUB panel, as shown in Figure 6-32.
Figure 6-32 Installing an RHUB PGND cable
Step 3 Use a torque screwdriver or Phillips screwdriver to secure the M8 OT terminal at one end of
the PGND cable to the wiring terminal on the ground bar at the site with a torque of 1.4 N•m.
----End
Follow-up Procedure
1.Route the cable, and then use a cable tie to bind the cable. For details, see 6.4.1
Requirements for Cable Layout.
2.Label the installed cable. For details, see section 11.3 Attaching an L-Shaped Label.
6.4.6 Installing Ethernet Cable
This section describes how to install an Ethernet cable.
Prerequisites
lThe Ethernet cable must be of Category 5e (enhanced) or higher. In addition, its cross-
sectional area must be 24 AWG or larger and frame spread rating must be CM or higher.
lThe Ethernet cables can be straight-through cables or crossover cables.
lWith the internal PoE module providing power, the maximum length of an Ethernet
cable is 100 m. With the Extender, the distance of the pRRU and RHUB can be extended
by the Extender up to a total distance of 200 m.
lEthernet cables are not delivered, and they must be prepared onsite. You need to use a
network cable tester to test the Ethernet cable connection.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
lProvides power supply for the pRRU when connected to the CPRI_E0 port on the
pRRU.
lTransmits CPRI signals between an RHUB and a pRRU.
Using the CPRI_E1 port on the pRRU3901 has the same Ethernet cable connection to the
RHUB as using the CPRI_E0 port. The following section describes the connection using the
CPRI_E0 port.
1.Assemble an RJ45 connector and an Ethernet cable by following instructions in
Assembling the Unshielded RJ45 Connector and the Ethernet Cable of InstallationReference.
NOTE
Follow pin assignment instructions described in section Ethernet Cable in DBS3900 LampSite
Hardware Description to assemble the unshielded RJ45 connector and the Ethernet cable. Otherwise,
the transmission signal quality deteriorates and CPRI links may be disconnected.
2.Check whether the made RJ45 connector is qualified by following instructions in
Checking the Appearance of Metal Contact Strips.
3.To complete the assembly of the other end, repeat Step 1.1 and Step 1.2.
4.Check whether the touch points on the connectors at both ends are normally conducted
and well contacted and whether the connections are correct by following instructions in
Testing the Connection of Assembled Cables of Installation Reference.
Step 2 Connect the RJ45 connector at the other end of the Ethernet cable to any port ranging from
CPRI_E0 to CPRI_E7 on the RHUB panel based on the engineering design.
Step 3 Optional: Connect the RJ45 connector at the other end of the Ethernet cable to the output
port of the Extender. Then, connect the RJ45 connector at one end of another Ethernet cable
to the input port of the Extender.
If the Extender is used, the Ethernet cable is divided into two parts, one between the RHUB
and the Extender and the other between the Extender and the pRRU.
Step 4 Remove the dustproof cap of the CPRI_E0 port on the pRRU.
Step 5 Connect the RJ45 connector at one end of the Ethernet cable to the CPRI_E0 port on the
pRRU panel, as shown in Figure 6-33, Figure 6-34.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Step 1 Install an optical module, as shown in Figure 6-35 and Figure 6-36.
6 Installing an RHUB
lFor details about the connection of CPRI optical cables, see CPRI Topology in
DBS3900 LampSite Technical Description.
lAn optical module to be installed must match the rate of its corresponding port.
NOTE
The performance of an optical module that is exposed to the air for more than 20 minutes may be abnormal.
Therefore, you must insert a fiber optic cable into an unpacked optical module within 20 minutes.
1.Remove the dust-proof cap from the CPRI port on the RHUB panel.
2.Remove the dust-proof cap on the optical module.
3.Lower the puller of the optical module.
4.Insert the optical module into the CPRI port on the RHUB, DCU, BBU or ODF.
5.Raise the puller of the optical module.
Figure 6-35 Removing the dust-proof cap from a port
Figure 6-36 Installing an optical module
Step 2 Install a CPRI optical cable, as shown in Figure 6-37.
1.Remove the dust-proof cap from the optical cable connector.
2.Install the optical cables by referring to Table 6-4.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
l In sharing BBUs with Macro Networks scenario, RHUBs share only main control boards with with
RF modules on macro base stations, not baseband processing units.
l If one end of the CPRI cable is connected to the DLC connector, the other end connects the BBU or
RHUB through the DLC connector. If one end of the CPRI cable is connected to the ODF adapter,
the other end connects the BBU/DCU or RHUB through a connector corresponding to the adapter.
The connectors include the FC connector, SC connector, and LC connector.
l When connecting the CPRI cable to the TX and RX ports of the optical module through connectors
in a cross manner, ensure that one end of a core of the CPRI cable is connected to the TX port and
the other end is connected to the RX port. Figure 6-37 shows how to install a CPRI optical cable for
connecting the BBU and RHUBs.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
8The distance between the bundled fiber tails and the RHUB panel is less than
70 mm.
Table 6-9 lists the checking items for other cable connections.
Table 6-9 Checklist for other cable connections
No.
1The connectors of the other cables must securely connected.
2Labels on the cables are legible and bound based on the engineering
3Positions for routing the cables must meet requirements of the engineering
Item
requirements. The cables must be bound tightly and neatly. The sheaths of the
cables must not be damaged.
design.
6.6 Power-on Check on an RHUB
This section describes the power-on check on the RHUB after the RHUB hardware is
installed and checked.
Context
DANGER
Power-on check involves high-voltage operation. Be cautious when conducting the power-on
check. Any direct contact with the input voltage or indirect contact through damp objects
might endanger your life.
Procedure
Step 1 Measure the RHUB earth resistance.
If...
The RHUB earth resistance is less than
10 ohms
The RHUB earth resistance is equal to
or larger than 10 ohms
Step 2 Measure the voltage of the RHUB.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Find out the cause and ensure that the resistance
meets requirement. Then, go to Step 2.
48
DBS3900 LampSite
Installation Guide
6 Installing an RHUB
If...Then...
The external power supply ranges from
Go to Step 3.
100 V AC to 240 V AC
The external power supply does not
range from 100 V AC to 240 V AC
Find out the cause and ensure that the resistance
meets requirement. Then, go to Step 3.
Step 3 Power on the RHUB. Wait 3 to 5 minutes, check the status of the RUN indicator of the RHUB
after the RHUB runs properly.
If the Status of
It Indicates that...Then...
the RUN
Indicator...
Steady onThe power supply is
normal while the board
Power off the RHUB, and power on it again
after rectifying the board fault.
is faulty.
Steady offThere is no power input
or the board is faulty.
Power off the RHUB, and check the power
input again. Rectify the board faulty and
power on the RHUB again if the power
input is normal.
On for 1s and off
for 1s
The devices work
properly.
End the operation.
On for 0.125s
and off for 0.125s
----End
The board software is
being uploaded.
Power off the RHUB if the uploading is not
finished in 5 minutes, and check whether
the configuration file is correct. Power on
the RHUB again after the fault is rectified.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This chapter describes the pRRU3901 installation process. The pRRU3901 can have two
transmission ports (plus PWR port) or three transmission ports (plus PWR port or no PWR
port). Unless otherwise specified, this document uses the pRRU3901 with three transmission
ports plus no PWR port as an example.
7 Installing a pRRU3901
7 Installing a pRRU3901
7.1 Information About the Installation
This section describes the information that you must be familiar with before installing a
pRRU3901, including the pRRU3901 product family, installation scenarios, installation space
and environment requirements.
7.2 Obtaining the MAC Address (Optional)
Before installing a pRRU3901, record the media access control (MAC) address, which will be
used during pRRU3901 commissioning. This section applies only when a pRRU3901 with
three transmission ports is configured with a Wi-Fi daughter board.
7.3 Installation Process
This section describes the pRRU3901 installation process, which involves installing a
pRRU3901, and cables, checking the pRRU3901 hardware installation, and powering on the
pRRU3901.
7.4 Installing a pRRU3901
This section describes the pRRU3901 installation process. A pRRU3901 can be installed on a
wall, ceiling, indoor metal pole, or standard keel, but not on an aluminum panel or a nonstandard keel.
7.5 Installing pRRU3901 Cables
This section describes the procedure of installing the pRRU3901 cables.
7.6 Checking the pRRU3901 Hardware Installation
pRRU3901 hardware installation checking includes hardware and cable installation checking.
7.7 Powering on the pRRU3901
This section describes the power-on check on the pRRU3901 after the pRRU3901 hardware is
installed and checked.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes the information that you must be familiar with before installing a
pRRU3901, including the pRRU3901 product family, installation scenarios, installation space
and environment requirements.
7.1.1 Product Family
This chapter describes the configurations and functions of the pRRU3901 components.
Table 7-1 lists the pRRU3901 product family.
Table 7-1 pRRU3901 product family
7 Installing a pRRU3901
Category
Main
equipment
Auxiliary
device
Equip
ment
pRRU
3901
Extern
al
antenn
a
Mounti
ng kits
ExtenderOptional1 or 2
Optional or
Mandatory
Mandatory1Processes the radio
Optional2Provides external
Mandatory1Supports the pRRU3901
QuantityFunction
NOTE
The quantity depends
on the number of
Ethernet cables in use.
frequency signals.
antennas for the
pRRU3901.
NOTE
Configure two external
antennas for each RF
daughter board.
installation on a wall,
pole, ceiling, or keel.
The mounting kits vary
with the pRRU3901
installation mode.
Extends the distance
between the pRRU3901
and RHUB.
7.1.2 Installation Scenario
The pRRU3901 can be installed on a wall, ceiling, pole, or keel. The following table describes
the installation in different scenarios.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
A keel under the
ceiling can bear a
load at least four
times the weight of
the pRRU3901.
Installing the pRRU3901 on a pole
When a pRRU3901 is installed on a pole, installation modes vary with the diameter of the
pole, as shown in Table 7-4.
Table 7-4 Pole-mounted suggestion
Installation
Mode
RequirementsMounting BracketsInstallation
For details, see Table
7-5.
Diagram
For details, see Table
7-5.
Diagram
Installing the
pRRU3901 on
a pole
For details, see
7.4.4
Installing a
pRRU3901 on
a Pole.
The diameter of the
pole ranges from 30
mm to 70 mm.
The diameter of the
pole ranges from 70
mm to 110 mm.
Installing the pRRU3901 on a keel
1. Plate
2. V clamp
3. Bolt (M6X80)
1. Plate
2. Hose clamp, which is
prepared by the
customer
The pRRU3901 can be installed on a keel of U-shape, T-shape, or H-shape. For the keels of
other shapes, they are determined based on the onsite requirements.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
The keel is in Ushape, T-shape, Hshape, or other
shapes.
7.4.6
Installing a
pRRU3901 on
a Keel.
7.1.3 Space Requirements
This chapter describes the space requirements of the pRRU3901.
When the pRRU3901 is installed on a wall, ceiling, pole or keel, the minimum space is
required for easy cabling and O&M. Based on the engineering practice, the recommendation
for the installation space is provided.
NOTE
During installation, a minimum clearance of 2 m must be reserved between the pRRU3901 working on
the 2.6 GHz band and the Wi-Fi module if they need to process services concurrently.
Diagram
1. Plate
2. V clamp
3. Bolt (M6X80)
shows the pRRU
installed on a Ushaped keel.
Figure 7-1 shows the recommended space requirements of the pRRU3901.
Figure 7-1 Recommended space requirements of the pRRU3901
The recommended space for installing a single pRRU3901 is described as follows:
lAt least 300 mm above the pRRU3901 is reserved for maintenance.
lAt least 300 mm under the pRRU3901 is reserved for cabling.
lAt least 300 mm on the left of the pRRU3901 is reserved for maintenance.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Before installing a pRRU3901, record the media access control (MAC) address, which will be
used during pRRU3901 commissioning. This section applies only when a pRRU3901 with
three transmission ports is configured with a Wi-Fi daughter board.
Context
The MAC address indicates the IP address through which a device can be reached.
Procedure
Step 1 Remove the backup WIFI MAC label from the front housing of the pRRU3901 and keep
them secure, as shown in Figure 7-2.
NOTE
l Do not remove the WIFI MAC label on the side of the pRRU3901 housing.
l Before removing the backup WIFI MAC label, photograph it.
7 Installing a pRRU3901
Figure 7-2 Removing backup WIFI MAC label
Step 2 Save the MAC according to 11.1 MAC Collection Template, and report it to the pRRU3901
commissioning personnel.
----End
7.3 Installation Process
This section describes the pRRU3901 installation process, which involves installing a
pRRU3901, and cables, checking the pRRU3901 hardware installation, and powering on the
pRRU3901.
Figure 7-3 shows the pRRU3901 installation process.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes the pRRU3901 installation process. A pRRU3901 can be installed on a
wall, ceiling, indoor metal pole, or standard keel, but not on an aluminum panel or a nonstandard keel.
NOTE
Note the following when installing the pRRU3901:
l The pRRU3901 cannot be grounded. If the pRRU3901 is grounded but the RHUB connected to this
pRRU3901 is not, the pRRU3901 may fail to be powered on.
l A minimum distance of 50 cm must be reserved between the pRRU3901 and the incandescent lamp.
l The installation spacing between the pRRU3901 and the temperature sensor must be greater than 50
cm.
l It is good practice to install the pRRU3901 on materials that can tolerate a temperature higher than
65°C and have an ignition point higher than 70°C.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes how to install a pRRU3901 on an indoor wall. If a wall indoors has
adequate load bearing capacity and installation space, it is good practice to install the
pRRU3901 on the wall. If the wall does not have adequate load bearing capacity, choose an
installation mode based on site requirements.
Context
NOTICE
This section describes only the wall-mounted installation in which mounting kits are directly
installed on the wall without auxiliary devices. The procedure for other wall-mounted
installation modes is similar.
Procedure
7 Installing a pRRU3901
Step 1 Determine the position for installing the pRRU3901 based on the construction blueprint and
the clearance requirements.
NOTE
For details about the clearance requirements, see 7.1.3 Space Requirements.
Step 2 Place the mounting bracket in the installation position against the wall. Then, level the
mounting bracket and use a marker to mark two anchor points. See Figure 7-6.
Figure 7-6 Anchor points on the pRRU3901 mounting bracket (unit: mm)
(1) Wall(2) Mounting bracket(3) Anchor point
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Step 3 Use a hammer drill with φ8 bore to drill holes at the marked anchor points, as shown in
7 Installing a pRRU3901
CAUTION
To prevent inhalation or eye contact with dust, take adequate preventive measures when
drilling holes.
Figure 7-7. Use a vacuum cleaner to clean the dust inside and around the holes and measure
the distance between them. If they are inaccurately positioned, re-measure and re-drill the
holes. Then, use a rubber mallet to hit a plastic expansion sleeve into each hole.
Figure 7-7 Drilling holes and installing expansion bolts
Step 4 Lead the M6x50 screws through the washers, and then through the drilling holes on the
mounting bracket to the plastic expansion sleeves, and torque the screws to 5 N•m, as shown
in Figure 7-8.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes how to install a pRRU3901 on the ceiling, such as the concrete ceiling,
when the ceiling has adequate load bearing capacity and installation space.
Context
NOTICE
If the pRRU3901 is installed on a ceiling, the temperature of the ceiling may increase by a
maximum of 30 degrees. Therefore, whether a pRRU3901 can be installed on a ceiling
depends on the ceiling material.
Procedure
Step 1 Determine the position for installing the pRRU3901 based on the construction blueprint and
the clearance requirements.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Step 2 Place the mounting bracket in the installation position against the ceiling. Then, level the
7 Installing a pRRU3901
NOTE
For details about the clearance requirements, see 7.1.3 Space Requirements.
mounting bracket and use a marker to mark two anchor points. See Figure 7-10.
Figure 7-10 Anchor points on the pRRU3901 mounting bracket (unit: mm)
(1) Ceiling(2) Mounting bracket(3) Anchor point
CAUTION
To prevent inhalation or eye contact with dust, take adequate preventive measures when
drilling holes.
Step 3 Use a hammer drill with φ8 bore to drill holes at the marked anchor points, as shown in
Figure 7-11. Use a vacuum cleaner to clean the dust inside and around the holes and measure
the distance between them. If they are inaccurately positioned, re-measure and re-drill the
holes. Then, use a rubber mallet to hit a plastic expansion sleeve into each hole.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes how to install a pRRU3901 on a metal pole indoors.
Procedure
Step 1 Determine the position for installing the pRRU3901 based on the construction blueprint and
the clearance requirements.
NOTE
For details about the clearance requirements, see 7.1.3 Space Requirements.
Step 2 If the diameter of the pole ranges from 30 mm to 70 mm, use the delivered V clamp,
mounting bracket, and bolts to install the pRRU3901 on the pole. Lead the M6x80 bolts
through the mounting bracket, and torque the bolts to 5 N•m, as shown in Figure 7-14.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Figure 7-14 Securing the pRRU3901 mounting bracket on the metal pole
If the diameter of the pole is greater than 70 mm, use the hose clamp to install the mounting
bracket on the pole. The hose clamp is prepared by customers. Torque the bolts to 5 N•m, as
shown in Figure 7-15.
Figure 7-15 Securing the pRRU3901 mounting bracket on the metal pole
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Step 3 Fit the four hooks of the pRRU3901 into the mounting holes on the mounting bracket and
7 Installing a pRRU3901
then press the pRRU3901 downwards until a click is heard. See Figure 7-16.
NOTE
It is good practice to perform the installation from the side view to promptly align the hooks with the
mounting holes.
Figure 7-16 Installing a pRRU3901 on a pole
----End
7.4.5 Installing a pRRU3901 on a Plate
This section describes how to install a pRRU3901 on a plate. If a suspended ceiling plate has
adequate load bearing capacity and installation space, the pRRU3901 can be installed on the
plate. However, it is good practice not to install a pRRU3901 on an aluminum plate.
Procedure
Step 1 Determine the position for installing the pRRU3901 based on the construction blueprint and
the clearance requirements.
NOTE
For details about the clearance requirements, see 7.1.3 Space Requirements.
Step 2 Place the mounting bracket in the installation position against the wall. Then, level the
mounting bracket and use a marker to mark two anchor points. See Figure 7-17.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes how to install a pRRU3901 on a keel. If a suspended ceiling plate
cannot bear the pRRU3901, the pRRU3901 can be installed on the keel on the ceiling.
Context
Before installing the pRRU3901 on a keel, ensure that the keel is strong enough to bear the
pRRU3901.
lThe mounting bracket of the pRRU3901 can be installed on the keel of the following
specifications: GBT 11981-2008, JIS A6517-2002, and ASTM C635 C635M-2007. The
installation mode depends on onsite requirements because there are various keels.
lThis section describes the procedure of installing a pRRU3901 on the keel of JIS
standard used in Japan. The procedure of installing a pRRU3901 on other keels is the
same as that of installing a pRRU3901 on the keel of JIS standard.
Procedure
Step 1 Determine the position for installing the pRRU3901 based on the construction blueprint and
the clearance requirements.
NOTE
For details about the clearance requirements, see 7.1.3 Space Requirements.
Step 2 Place the V clamp across the keel, and use a marker to mark the projective positions of the
mounting holes on the suspended ceiling plate, as shown in Figure 7-20.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
lCode for Quality Acceptance of Electric Engineering Construction in Building (GB
50303-2002)
lTechnical Specification for Construction and Acceptance of Telecommunication Conduit
Engineering (GB 50374-2006)
International Standards
lGeneric Cabling for Customer Premises (ISO/IEC 11801)
lCommercial Building Telecommunications Cabling Standard (EIA/TIA 568)
lCommercial Building Standard for Telecommunication Pathways and Spaces (EIA/TIA
569)
lAdministration Standard for Commercial Telecommunications Infrastructure (EIA/TIA
606)
lGrounding and Bonding Requirements for Telecommunications in Commercial
Buildings (EIA/TIA 607)
lGeneric Cabling Systems for Information Technology (EN 50173)
lCabling Installation for Information Technology (EN 50174)
Bending radius
lThe bending radius of a 1/4'' jumper, a 1/2'' softer jumper, and a 1/2'' common jumper
must be longer than 35 mm, 50 mm, and 127 mm, respectively.
lThe bending radius of a power cable is at least three times the diameter of the cable.
lThe bending radius of a signal cable must be at least five times of the diameter of the
cable.
Cable binding
lCables of the same type are bound together.
lDifferent types of cables must be separately routed with a minimum spacing of 30 mm
and cannot be entangled.
lThe cables are bound tightly and neatly and the sheaths of the cables is intact.
lThe cable ties face the same direction and all cable ties bound at similar positions must
be in a straight line.
lThe extra length of each indoor cable tie must be cut off. A slack of 5 mm is reserved for
each outdoor cable tie before the extra length is cut off. All cut surfaces are without
sharp edges.
lLabels or nameplates are attached to both ends, joints, or turns of cables after they are
installed.
Safety
lThe steel pipe or fire-resistant rigid polyvinyl chloride pipe should be used for the cable
duct or for routing cables. The cross-sectional usage of the cable duct should be 30% to
50% and that of the pipe for routing cables should be 25% to 30%.
lCables are placed away from sharp objects or wall burrs. If these positions are inevitable,
protection pipes are required for the cables.
lCables are routed away from heat sources, or heat-insulation materials are added
between cables and heat sources.
lA clearance is reserved at turns of a cable or the position close to a device, facilitating
cable and device maintenance. The recommended clearance is about 0.1 m.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
lA maximum of 100 Ethernet cables can be bundled if no PVC pipes are used. If pipes are
used, a maximum of 24 Ethernet cables can be led through a pipe. In this case, ensure
that 1/3 space inside the pipes must be vacant.
lThe point at which an Ethernet cable is bundled must be spaced 400 mm or less from the
Ethernet port on a pRRU.
lFor the pRRU3901 used in the elevator engine room on the rooftop, generator set for the
subway engine, and equipment room with central air conditioning, Ethernet cables must
be led through metallic conduits that are reliably grounded at both ends.
7.5.2 pRRU3901 Cable List
This section describes pRRU3901 cable connections.
Table 7-7 lists pRRU3901 cables.
Table 7-7 List of pRRU3901 cables
7 Installing a pRRU3901
Cable
One EndThe Other End
ConnectorConnected
ConnectorConnected to ...
to ...
Ethernet
Cable
RJ45 connectorCPRI_E0~CP
RI_E7 port on
RHUB
RJ45 connectorTransmission
port on Access
RJ45 connectorCPRI_E0~CPRI_
E1 port on
pRRU3901
RJ45 connectorGE port on
pRRU3901
Control(AC)
(Optional)
RF Jumper
SMA straight
male connector
External
antenna
TX/RX RF
port on
Based on the
port model of
the antenna
system.
Antenna system
pRRU3901
NOTE
l The Extender can be used to lengthen the distance between the RHUB and the pRRU3901 connected
using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one
between the RHUB and the Extender and the other between the Extender and the pRRU3901.
l The Ethernet cable used for connecting the GE port on the pRRU3901 to the transmission port on
the AC is required only when the pRRU3901 have three transmission ports and is configured with
the Wi-Fi daughter board.
7.5.3 Cable Connections
This section describes the cable connections for a single pRRU3901 and multiple pRRU3901s
in UMTS, LTE FDD, UMTS+LTE FDD, LTE FDD+LTE FDD mode.
Before installing the pRRU3901 cables, you must be aware of the following information:
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
lThe pRRU3901 can obtain power supply through the power over Ethernet (PoE).
lFor external antennas corresponding to RF daughter board 1, the TX port and RX port
are ANT0 and ANT1, respectively. For external antennas corresponding to RF daughter
board 2, the TX port and RX port are ANT2 and ANT3, respectively. For external
antennas corresponding to RF daughter board 3, the TX port and RX port are ANT4 and
ANT5, respectively.
lThe external antenna system is optional, and the pRRU3901 jumpers are not delivered.
By default, the pRRU3901s are configured with built-in antennas. If the external antenna
system is connected, the antenna system automatically switches to the external one. One
end of the pRRU3901 RF jumper is the SMA male connector, which is connected to the
external antenna TX/RX RF port on the pRRU3901. The other end of the pRRU3901 RF
jumper is the type N male connector, which is connected to the antenna system. For the
standard of the pRRU3901 RF jumper, see (Optional) RF Jumper of the DBS3900LampSite Hardware Description.
Figure 7-23 shows the cable connection when the pRRU3901 is configured with only one RF
Daughter Board.
Figure 7-23 pRRU3901 cable connection (1)
(1) Ethernet cable(2) RF jumper
NOTE
l The Extender can be used to lengthen the distance between the RHUB and the pRRU3901 connected
using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one
between the RHUB and the Extender and the other between the Extender and the pRRU3901.
l When two Ethernet cables are used to transmit CPRI signals, connect one end of the cables to the
CPRI_E0 and CPRI_E1 ports on the pRRU panel and the other end to any two ports of CPRI_E0 to
CPRI_E7 on the RHUB panel. On the RHUB panel, CPRI_E0 and CPRI_E1, CPRI_E2 and
CPRI_E3, CPRI_E4 and CPRI_E5, and CPRI_E6 and CPRI_E7 are used in pairs. CPRI_E0 on the
pRRU panel connects to the even-numbered CPRI port (for example, CPRI_E0, CPRI_E2,
CPRI_E4, or CPRI_E6) on the RHUB panel, and CPRI_E1 on the pRRU panel connects to the oddnumbered CPRI port (for example, CPRI_E1, CPRI_E3, CPRI_E5, or CPRI_E7). This document
describes signal transmission using one Ethernet cable as an example.
Figure 7-24 shows the cable connection when the pRRU3901 is configured with two RF
Daughter Boards.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
l The Extender can be used to lengthen the distance between the RHUB and the pRRU3901 connected
using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one
between the RHUB and the Extender and the other between the Extender and the pRRU3901.
l When two Ethernet cables are used to transmit CPRI signals, connect one end of the cables to the
CPRI_E0 and CPRI_E1 ports on the pRRU panel and the other end to any two ports of CPRI_E0 to
CPRI_E7 on the RHUB panel. On the RHUB panel, CPRI_E0 and CPRI_E1, CPRI_E2 and
CPRI_E3, CPRI_E4 and CPRI_E5, and CPRI_E6 and CPRI_E7 are used in pairs. CPRI_E0 on the
pRRU panel connects to the even-numbered CPRI port (for example, CPRI_E0, CPRI_E2,
CPRI_E4, or CPRI_E6) on the RHUB panel, and CPRI_E1 on the pRRU panel connects to the oddnumbered CPRI port (for example, CPRI_E1, CPRI_E3, CPRI_E5, or CPRI_E7). This document
describes signal transmission using one Ethernet cable as an example.
Figure 7-24 shows the cable connection when the pRRU3901 is configured with two RF
Daughter Boards and one Wi-Fi daughter board.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
l The Extender can be used to lengthen the distance between the RHUB and the pRRU3901 connected
using the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one
between the RHUB and the Extender and the other between the Extender and the pRRU3901.
l When two Ethernet cables are used to transmit CPRI signals, connect one end of the cables to the
CPRI_E0 and CPRI_E1 ports on the pRRU panel and the other end to any two ports of CPRI_E0 to
CPRI_E7 on the RHUB panel. On the RHUB panel, CPRI_E0 and CPRI_E1, CPRI_E2 and
CPRI_E3, CPRI_E4 and CPRI_E5, and CPRI_E6 and CPRI_E7 are used in pairs. CPRI_E0 on the
pRRU panel connects to the even-numbered CPRI port (for example, CPRI_E0, CPRI_E2,
CPRI_E4, or CPRI_E6) on the RHUB panel, and CPRI_E1 on the pRRU panel connects to the oddnumbered CPRI port (for example, CPRI_E1, CPRI_E3, CPRI_E5, or CPRI_E7). This document
describes signal transmission using one Ethernet cable as an example.
7.5.4 Cable Connections (LTE TDD)
This section describes the cable connections for a single pRRU3901 and multiple pRRU3901s
in LTE TDD mode.
Before installing the pRRU3901 cables, you must be aware of the following information:
lThe pRRU3901 can obtain power supply through the power over Ethernet (PoE).
lFor external antennas corresponding to RF daughter board 1, the TX port and RX port
are ANT0 and ANT1, respectively. For external antennas corresponding to RF daughter
board 2, the TX port and RX port are ANT2 and ANT3, respectively. For external
antennas corresponding to RF daughter board 3, the TX port and RX port are ANT4 and
ANT5, respectively.
lThe external antenna system is optional, and the pRRU3901 jumpers are not delivered.
By default, the pRRU3901s are configured with built-in antennas. If the external antenna
system is connected, the antenna system automatically switches to the external one. One
end of the pRRU3901 RF jumper is the SMA male connector, which is connected to the
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
external antenna TX/RX RF port on the pRRU3901. The other end of the pRRU3901 RF
jumper is the type N male connector, which is connected to the antenna system. For the
standard of the pRRU3901 RF jumper, please see (Optional) RF Jumper of the DBS3900LampSite Hardware Description.
Figure 7-26 shows the cable connection when the pRRU3901 is configured with only one RF
Daughter Board.
Figure 7-26 pRRU3901 cable connection (1)
(1) Ethernet cable(2) RF jumper
NOTE
The Extender can be used to lengthen the distance between the RHUB and the pRRU connected using
the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one between the
RHUB and the Extender and the other between the Extender and the pRRU.
Figure 7-27 shows the cable connection when the pRRU3901 is configured with one RF
Daughter Boards and one Wi-Fi daughter board.
Figure 7-27 pRRU3901 cable connection (2)
(1) Ethernet cable(2) RF jumper
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
The Extender can be used to lengthen the distance between the RHUB and the pRRU connected using
the Ethernet cable. If the Extender is used, the Ethernet cable is divided into two parts, one between the
RHUB and the Extender and the other between the Extender and the pRRU.
7.5.5 pRRU3901 cable installation process
This section describes the process of installing pRRU3901 cables.
Figure 7-28 shows the process of installing pRRU3901 cables.
Figure 7-28 pRRU3901 cable installation process
7 Installing a pRRU3901
7.5.6 Installing an Ethernet Cable
This section describes how to install an Ethernet cable.
Prerequisites
lThe Ethernet cable must be of Category 5e (enhanced) or higher. In addition, its cross-
sectional area must be 24 AWG or larger and frame spread rating must be CM or higher.
lThe Ethernet cables can be straight-through cables or crossover cables.
lWith the internal PoE module providing power, the maximum length of an Ethernet
cable is 100 m. With the Extender, the distance of the pRRU3901 and RHUB can be
extended by the Extender up to a total distance of 200 m.
lEthernet cables are not delivered, and they must be prepared onsite. You need to use a
network cable tester to test the Ethernet cable connection.
Context
The Ethernet cable has the following functions:
lProvides power supply for the pRRU3901 when the cable connects the CPRI_E0 port on
the pRRU3901 to the RHUB.
lTransmits CPRI signals between an RHUB and a pRRU3901.
lProvides Wi-Fi services for the pRRU3901 when the cable connects the GE port on the
pRRU3901 with three transmission ports to the AC.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Using the CPRI_E1 port on the pRRU3901 has the same Ethernet cable connection to the
RHUB as using the CPRI_E0 port. The following section describes the connection using the
CPRI_E0 port.
1.Assemble an RJ45 connector and an Ethernet cable by following instructions in
Assembling the Unshielded RJ45 Connector and the Ethernet Cable of InstallationReference.
NOTE
Follow pin assignment instructions described in section Ethernet Cable in DBS3900 LampSite
Hardware Description to assemble the unshielded RJ45 connector and the Ethernet cable.
Otherwise, the transmission signal quality deteriorates and CPRI links may be disconnected.
2.Check whether the made RJ45 connector is qualified by following instructions in
Checking the Appearance of Metal Contact Strips.
3.To complete the assembly of the other end, repeat Step 1.1 and Step 1.2.
4.Check whether the touch points on the connectors at both ends are normally conducted
and well contacted and whether the connections are correct by following instructions in
Testing the Connection of Assembled Cables of Installation Reference.
Step 2 Install an Ethernet cable between an RHUB and a pRRU3901.
1.Remove the dustproof cap of the CPRI_E0 port on the pRRU3901.
2.Connect the RJ45 connector at one end of the Ethernet cable to the CPRI_E0 port on the
pRRU3901 panel.
3.Optional: Connect the RJ45 connector at the other end of the Ethernet cable to the
output port of the Extender. Then, connect the RJ45 connector at one end of another
Ethernet cable to the input port of the Extender.
4.Connect the RJ45 connector at the other end of the Ethernet cable to any port ranging
from CPRI_E0 to CPRI_E7 on the RHUB panel based on the engineering design, as
shown in Figure 7-29.
Step 3 Optional: Install the Ethernet cable between the pRRU3901 and the AC. This operation is
required when the pRRU3901 with three transmission ports is configured with a Wi-Fi
daughter board.
1.Remove the dustproof cap of the GE port on the pRRU3901.
2.Connect the RJ45 connector at one end of the Ethernet cable to the GE port on the
pRRU3901 panel.
3.Connect the RJ45 connector at the other end of the Ethernet cable to the transmission
port of the AC based on the engineering design, as shown in Figure 7-29.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
(1) Ethernet cable(2) GE port on the pRRU3901(3) CPRI_E0 port on the pRRU3901
NOTE
The pRRU3901 can have two transmission ports plus one PWR port or three transmission ports (plus
one PWR port or no PWR port), requiring the same installation operations. This section uses the
pRRU3901 with three transmission ports no PWR port as an example.
----End
Follow-up Procedure
1.Route the cable, and then use a cable tie to bind the cable. For details, see 7.5.1
Requirements for Cable Layout.
2.Label the installed cable. For details, see section 11.3 Attaching an L-Shaped Label.
7.5.7 Installing an RF jumpers (Optional)
The RF jumpers transmit radio frequency signals. One end of the RF jumpers is the SMA
straight male connector, and the other end is the type N connector.
Context
lIf the RF jumper is provided by the customer, the jumper must not be lower than the
RG316 specifications. In addition, the jumpers can be used after they are checked by
Huawei engineers.
lpRRU3901s can be connected to external whip antennas or external remote antennas
(through pRRU3901 RF jumpers). Whip antennas are delivered optionally. RF jumpers
are not delivered.
Procedure
Step 1 Expose the SMA female connector by removing the pRRU3901 antenna housing, as shown in
Figure 7-30.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Step 2 Use a torque wrench with a torque of 0.6 N•m to connect the SMA straight male connector on
a jumper to the ANT port on the pRRU3901 panel.
NOTICE
Tighten it with hands, and then use a torque wrench to tighten it with a rotational speed of less
than or equal to 2.4 rpm to tighten it.
Step 3 Connect the type N female connector of the jumper to the type N male connector of the RF
feeder connected to the built-in antenna.
NOTICE
Tighten the feeder close to the type N connector to ensure that the jumper is not tightened. In
this way, the connectors on both ends of a jumper are not affected by the external force.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Power off the power supply,
rectify the fault, and power on
the pRRU3901.
86
DBS3900 LampSite
Installation Guide
7 Installing a pRRU3901
If the RUN Indicator...Because...Then...
Steady offThere is no power input, or an
alarm is reported on the
board.
Power off the power supply
and check the power input. If
no fault is found after the
pRRU3901 is powered off,
clear the fault on the board,
and power on the pRRU3901.
On for 1s and off for 1sThe device works properly.End this operation.
On for 0.125s and off for
0.125s
The software of the board is
loading.
Wait five minutes for the
software to be successfully
loaded. If the software is
loading five minutes later,
shut off the power supply.
Check whether the data
configuration file is correct.
After the fault is rectify,
power on the pRRU3901
again.
----End
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This chapter describes the pRRU3902 installation process.
8 Installing a pRRU3902
8 Installing a pRRU3902
8.1 Information About the Installation
This section describes the information that you must be familiar with before installing a
pRRU3902, including the pRRU3902 product family, installation scenarios, installation space
and environment requirements.
8.2 Installation Process
This section describes the pRRU3902 installation process, which involves installing a
pRRU3902, and cables, checking the pRRU3902 hardware installation, and powering on the
pRRU3902.
8.3 Installing a pRRU3902
This section describes the pRRU3902 installation process. A pRRU3902 can be installed on a
wall, ceiling, indoor metal pole, or keel, but not on an aluminum panel or a non-standard keel.
8.4 Installing pRRU3902 Cables
This section describes the procedure of installing the pRRU3902 cables.
8.5 (Optional) Installing a Combiner
This section describes how to install a combiner.
8.6 Checking the pRRU3902 Hardware Installation
pRRU3902 hardware installation checking includes hardware and cable installation checking.
8.7 Powering on the pRRU3902
This section describes the power-on check on the pRRU3902 after the pRRU3902 hardware is
installed and checked.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
This section describes the information that you must be familiar with before installing a
pRRU3902, including the pRRU3902 product family, installation scenarios, installation space
and environment requirements.
8.1.1 pRRU3902 Product Family
This chapter describes the configurations and functions of the pRRU3902 components.
Table 8-1 lists the pRRU3902 product family.
Table 8-1 pRRU3902 product family
8 Installing a pRRU3902
Category
Main equipmentpRRU3902
EquipmentOptional or
with internal
antennas
pRRU3902
supporting
external
antennas
CombinerOptional2Combines
QuantityFunction
Mandatory
Mandatory1Functions as a
remote radio
unit that
processes RF
signals.
Mandatory1Functions as a
remote radio
unit that
processes RF
signals. It has
no internal
antennas and
must connect
to external
antennas.
signals of RF
units
operating in
different
frequency
bands.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
Installing the
pRRU3902
on a ceiling
by drilling
holes
For details,
see 8.3.3
Installing a
pRRU3902
on a Ceiling.
Installing the
pRRU3902
on a ceiling
using a clamp
through an
attachment
plate
For details,
see 8.3.4
Installing a
pRRU3902
on a Plate.
RequirementsMounting BracketsInstallation
Diagram
l The ceiling, such
as a concrete
ceiling, can bear a
load at least four
times the weight
of the pRRU3902.
1. Plate
2. Screw (M3.5 x 35)
3. Plastic expansion
sleeve
4. Flat washer
l The screws must
be tightened with
a torque of 1.5
N·m. This ensures
the screws work
properly and the
ceiling remains
intact without
cracks in it.
l The ceiling, such
as a concrete
ceiling, can bear a
load at least four
times the weight
1. Plate
2. U-shaped metal plate
3. Bolt (M4 x 35)
4. Bolt (M4 x 60)
of the pRRU3902.
l The thickness of
the ceiling is less
than 45 mm.
Installing the
pRRU3902
on a keel
For details,
see 8.3.5
A keel under the
ceiling can bear a
load at least four
times the weight of
the pRRU3902.
For details, see Table
8-4.
Installing a
pRRU3902
on a Keel.
Installing the pRRU3902 on a keel
The pRRU3902 can be installed on a keel of U-shape, T-shape, or H-shape. For the keels of
other shapes, they are determined based on the onsite requirements.
Issue 06 (2015-10-30)Huawei Proprietary and Confidential
The keel is in Ushape, T-shape, Hshape, or other
shapes.
1. Plate
2. U-shaped metal plate
3. Bolt (M4 x 35)
4. Bolt (M4 x 60)
Installing the pRRU3902 on a on steel hangers
Either M6 or M8 steel hangers can be used for installation.
Table 8-5 Steel hangers installation suggestion
Diagram
shows the pRRU3902
installed on a Ushaped keel.
Installation
Mode
Installing the
pRRU3902
on a steel
hangers
For details,
see 8.3.6
Installing a
pRRU3902
on Steel
Hangers.
RequirementsMounting BracketsInstallation
Either M6 or M8
steel hangers can be
used for installation.
8.1.3 Space Requirements
This chapter describes the space requirements of the pRRU3902.
When the pRRU3902 is installed on a wall, ceiling, pole or keel, the minimum space is
required for easy cabling and O&M. Based on the engineering practice, the recommendation
for the installation space is provided.
Diagram
1. Plate
2. U-shaped metal plate
3. Bolt (M4 x 35)
4. Bolt (M4 x 60)
Figure 8-1 shows the recommended space requirements of the pRRU3902 when the external
antenna is required.