Lithium Battery Indicator
Color
Status
Meaning
Run indicator (RUN)
Green Off
The lithium battery has no power input or is faulty.
Steady on
The lithium battery is powered on.
Blinking slowly (0.5 Hz)
The lithium battery is communicating properly with upstream monitoring equipment.
Blinking fast (4 Hz)
The lithium battery fails to communicate with upstream monitoring equipment. Alarm
indicator (ALM)
Red
Off
There is no alarm. Steady on
The lithium battery has generated a fault alarm and needs to be replaced.
Blinking slowly (0.5 Hz)
The lithium battery has generated a protection alarm, which can be cleared.
Function Module Indicator
Color
Status
Meaning
Run indicator
Green Off
The function module has no power input or is faulty.
Blinking slowly (0.5 Hz)
The function module is communicating properly with upstream monitoring equipment.
Blinking fast (4 Hz)
The function module fails to communicate with upstream monitoring equipment.
Alarm indicator
Yellow Off
There is no alarm. Blinking slowly
The function module has generated an alarm, which can be cleared.
Steady on
The function module has generated an AC power failure or PV array fault alarm, which can be cleared.
Fault indicator
Red
Off
The function module is normal.
Blinking slowly
The function module has an external fault, which can be cleared.
Steady on
The function module has an internal fault, which cannot be cleared.
NOTE
(PC500-300H1, PC500-300G1)
Issue: 03 Date: 2018-03-22
Copyright © Huawei Technologies Co., Ltd. 2018. All rights reserved.
Overview
1
Appearance Grid Hybrid Scenario Solar Hybrid Scenario
PC500-300G1
PMP
microwave
Lightning rod
Lightning rod
Cantilever
PV modules
Lithium battery: CBM20E-N14A1
Pole
mounting kit
Pole
mounting kit
Function
module
Bullet
cameras
Lithium battery
Lithium battery
Pole
Dome
camera
PMP
microwave
Pole
mounting kit
Pole
mounting kit
Function
module
Cantilever
Bullet
cameras
Lithium battery
Lithium battery
Pole
PV module
support
Dome camera
The three indicators are steady on when the power unit of the function module is upgrading. They return to normal status after the upgrade is complete.
1
2
NOTE
Tools
Routing Cables Through the Pole
3
1. Place the pole on a wooden case or a similar object.
2. Route a pull wire.
3. Route cables.
Routing Cables Through
the Grid Hybrid Pole
Mains AC cable and optical fiber
Module ground cable
Mains AC cable, module ground cable, optical fiber, camera cable, and PMP microwave cables
Routing Cables Through
the Solar Hybrid Pole
Mains AC cable and optical fiber
Module ground cable
Mains AC cable, module ground cable, optical fiber, camera cable, PMP microwave cables, and PV cable
Routing Cables Through
the Cantilever
Camera ground cable
PMP microwave cables
Camera signal cable, power cable, and alarm cable
PMP microwave cables
PV DC input cable
Camera signal cable, power cable, and alarm cable
Dome camera signal cable, power cable, alarm cable, and ground cable
Bullet camera signal cable, power cable, and ground cable
2
PMP microwave cables can be used only in scenarios where the PMP microwave is adopted.
The cables routed from the pole cable hole have a length of 1.5 m reserved. The cables routed from the cantilever cable hole have a length of 0.5 m reserved.
The object where the pole is placed should be able to bear a load above 700 kg.
Installing a Cantilever
NOTICE
Site Latitude
PV Module Tilt Angle
0–15°
15°
16–25° 25°
26–30° 35°
31–45° 45°
4
Installing Cameras and Cables
5
Installing Cameras
5.1
For the camera installation method, see the camera document.
Installing Camera Cables
5.2
For the cable connections at the camera side, see the camera document. Reserve the other ends of cables.
(Optional) Installing the PMP Microwave
6
For the PMP microwave installation method, see the PMP microwave product document.
Installing PV Modules and Cables (Solar Hybrid Scenario)
7
In the northern hemisphere, PV modules face due south. In the southern hemisphere, PV modules face due north.
1. Remove the connective kit, adjust the PV module direction based on the PV module direction principles, and then reinstall the connective kit.
2. Install the PV module support.
3. Adjust the tilt angle of the PV module support based on the site latitude.
or
or
or
4. Loosen the bolt at the base of the PV module support.
3
5. Install the angle adjustment bracket and tighten the bolt at the base of the PV module support.
6. Install horizontal beams.
NOTE
NOTE
NOTE
Keep the slots of horizontal beams facing inwards for installing PV modules.
Partially tighten the bolts so that PV modules can be adjusted during installation.
Spacing shim
7. Install two PV modules.
Ensure that the junction boxes on the rear of PV modules are positioned consistently.
8. Install raking strut beams for the PV modules.
9. Install spacing shims for the PV modules.
Ensure that the openings of the raking strut beams face outwards.
Partially tighten the bolts to prevent the PV modules from sliding.
Raking
strut beam
Spacing shim
11.Install raking struts for the PV modules. 12.Install PV cables.
10.Tighten the bolts at the horizontal beams and raking strut beams.
Adhesive
tape
4
Installing an Antenna Fastener and Lightning Rod
Site Latitude
Lightning Rod Tilt Angle
0–15°
15°
16–25° 25°
26–30° 35°
31–45° 45°
NOTICE
NOTE
8
Grid Hybrid Scenario
Solar Hybrid Scenario
Adjust the tilt angle of the lightning rod based on the site latitude.
Installing the Function Module and Lithium Battery
9
Wear gloves during installation.
Do not place a module with its bottom against the ground.
Never install a module with power on. Ensure that the angle between a module and the line vertical to the ground is within 10 degrees.
The paint on the module exterior should be intact. If paint has flaked off, repaint the area to avoid corrosion.
Installing the Function Module and Lithium Battery on a Pole
9.1
1. Use a positioning sticker to mark the installation position for the pole mounting kit.
Positioning sticker
2. Install the pole mounting kit.
Ensure that the arrow on the top of the pole mounting kit points exactly to the middle point on the top of the positioning sticker.
There are three types of bolts available for installing the pole mounting kit. Choose the appropriate type of bolts based on the pole diameter.
Pole Diameter (105–140 mm)
Bolt (120 mm)
Pole Diameter
(140–175 mm)
Bolt (160 mm)
Pole Diameter (175–210 mm)
Bolt
(190 mm)
Cable hole