Heat-N-Glo Pier-38HV, ST-38HV Installer's Manual

Page 1
Models:
Pier-38HV ST-38HV
WARNING: IF THE INFORMATION IN THESE INSTRUCTIONS IS NOT FOLLOWED EXACTLY, A FIRE OR EXPLOSION MAY RESULT CAUS­ING PROPERTY DAMAGE, PER­SONAL INJURY, OR DEATH.
- Do not store or use gasoline or other flam­mable vapors and liquids in the vicinity of this or any other appliance.
- What to do if you smell gas  Do not try to light any appliance.  Do not touch any electrical switch.  Do not use any phone in your building.  Immediately call your gas supplier from a
neighbor's phone. Follow the gas supplier's instructions.
 If you cannot reach your gas supplier, call
the fire department.
- Installation and service must be performed by a qualified installer, service agency, or the gas supplier.
Installers Guide
Underwriters
Laboratories Listed
READ THIS MANUAL BEFORE INSTALLING OR OPERATING THIS APPLIANCE. THIS INSTALLERS GUIDE MUST BE LEFT WITH APPLIANCE FOR FUTURE REFERENCE.
WARNING: IMPROPER INSTALLA­TION, ADJUSTMENT, ALTERATION, SERVICE OR MAINTENANCE CAN CAUSE INJURY OR PROPERTY DAM­AGE. REFER TO THIS MANUAL. FOR ASSISTANCE OR ADDITIONAL INFOR­MATION CONSULT A QUALIFIED IN­STALLER, SERVICE AGENCY, OR THE GAS SUPPLIER.
1. This appliance may be installed in an af­termarket, permanently located, manu­factured (mobile) home, where not pro­hibited by local codes.
2. This appliance is only for use with the type of gas indicated on the rating plate. This appliance is not convertible for use with other gases, unless a certified kit is used.
Printed in U.S.A. Copyright 2001,
Heat-N-Glo, a division of Hearth Technologies Inc. 20802 Kensington Boulevard, Lakeville, MN 55044
This product is covered by one or more of the following patents: (United States) 4,112,913; 4,408,594; 4,422,426; 4,424,792; 4,520,791; 4,793,322; 4,852,548; 4,875,464; 5,000,162; 5,016,609; 5,076,254 5,191,877; 5,218,953; 5,328,356; 5,429,495; 5,452,708; 5,542,407; 5,613,487; (Australia) 543790; 586383; (Canada) 1,123,296; 1,297,746; 2,195,264; (Mexico) 97-0457; (New Zealand) 200265; or other U.S. and foreign patents pending.
Please contact your Heat-N-Glo dealer for any questions or concerns. For the number of your nearest Heat-N-Glo dealer, please call 952-985-6000.
285-900D 5/01
1
Page 2
SAFETY AND WARNING INFORMATION
READ and UNDERSTAND all instructions carefully
!
before starting the installation. FAILURE TO FOLLOW these installation instructions may result
in a possible fire hazard and will void the warranty.
Prior to the first firing of the fireplace, READ the
!
Using Your Fireplace section of the Owners Guide.
DO NOT USE this appliance if any part has been
!
under water. Immediately CALL a qualified service technician to inspect the unit and to replace any part of the control system and any gas control which has been under water.
THIS UNIT IS NOT FOR USE WITH SOLID FUEL.
!
Installation and repair should be PERFORMED by a qualified service person. The appliance and venting
!
system should be INSPECTED before initial use and at least annually by a professional service person. More frequent cleaning may be required due to excessive lint from carpeting, bedding material, etc. It is IMPERATIVE that the units control compartment, burners, and circulating air passageways BE KEPT CLEAN to provide for adequate combustion and ventilation air.
These units MUST use one of the vent systems
!
described in the Installing the Fireplace section of the Installers Guide. NO OTHER vent systems or components MAY BE USED.
This gas fireplace and vent assembly MUST be
!
vented directly to the outside and MUST NEVER be attached to a chimney serving a separate solid fuel burning appliance. Each gas appliance MUST USE a separate vent system. Common vent systems are
PROHIBITED.
INSPECT the external vent cap on a regular basis to
!
make sure that no debris is interfering with the air flow.
The glass door assembly MUST be in place and
!
sealed, and the trim door assembly MUST be in place on the fireplace before the unit can be placed into safe operation.
DO NOT OPERATE this appliance with the glass
!
door removed, cracked, or broken. Replacement of the glass door should be performed by a licensed or qualified service person. DO NOT strike or slam the glass door.
Always KEEP the appliance clear and free from
!
combustible materials, gasoline, and other flammable vapors and liquids.
NEVER OBSTRUCT the flow of combustion and
!
ventilation air. Keep the front of the appliance CLEAR of all obstacles and materials for servicing and proper operations.
Due to the high temperature, the appliance should be LOCATED out of traffic areas and away from
!
furniture and draperies. Clothing or flammable material SHOULD NOT BE PLACED on or near the appliance.
Children and adults should be ALERTED to the
!
hazards of high surface temperature and should STAY AWAY to avoid burns or clothing ignition. Young children should be CAREFULLY SUPERVISED when they are in the same room as the appliance.
The glass door assembly SHALL ONLY be
!
replaced as a complete unit, as supplied by the gas fireplace manufacturer. NO SUBSTITUTE material may be used.
DO NOT USE abrasive cleaners on the glass door
!
assembly. DO NOT ATTEMPT to clean the glass door when it is hot.
Turn off the gas before servicing this appliance. It is
!
recommended that a qualified service technician perform an appliance check-up at the beginning of each heating season.
Any safety screen or guard removed for servicing
!
must be replaced before operating this appliance.
DO NOT place furniture or any other combustible
!
household objects within 36 inches of the fireplace front.
2
Page 3
Table of Contents
Safety and Warning Information ..................................... 2
Service Parts Lists .......................................................... 4
u
Section 1: Approvals and Codes .................................... 8
Appliance Certification........................................................ 8
Installation Codes ............................................................... 8
High Altitude Installations .................................................... 8
Section 2: Getting Started .............................................. 9
Introducing the Heat-N-Glo Gas Fireplaces ....................... 9
Pre-installation Preparation ................................................ 9
Section 3: Installing the Fireplace ............................... 12
Constructing the Fireplace Chase ................................... 12
Step 1 Locating the Fireplace ....................................... 12
Step 2 Framing the Fireplace ....................................... 13
u
Step 3 Installing the Vent System ................................. 15
A. Vent System Approvals ................................ 15
u
B. Installing Vent Components ......................... 22
C. Vent Termination .......................................... 25
Step 4 Positioning, Leveling, and
Securing the Fireplace ...................................... 28
Step 5 The Gas Control Systems ................................. 28
Step 6 The Gas Supply Line ......................................... 29
Step 7 Gas Pressure Requirements ............................ 29
Step 8 Wiring the Fireplace .......................................... 30
Step 9 Finishing ............................................................ 31
Step 10 Installing Trim, Logs, and Ember Material ......... 32
Installing the Trim .............................................. 32
Positioning the Logs ..........................................32
Placing the Ember Material ............................... 32
Glass Specifications .......................................... 33
Step 11 Before Lighting the Fireplace .............................33
Step 12 Lighting the Fireplace ........................................33
After the Installation .......................................................... 33
Section 4: Maintaining and Servicing
u = Contains updated information.
Your Fireplace ............................................. 34
3
Page 4
1
Approvals and Codes
Appliance Certification
The Heat-N-Glo fireplace models discussed in this Installers Guide have been tested to certification standards and listed
by the applicable laboratories.
Certification
MODEL: PIER-38HV, ST-38HV LABORATORY: Underwriters Laboratories TYPE: Direct Vent Gas Fireplace STANDARD: ANSI Z21.50CGA2.22UL307B
Installation Codes
The fireplace installation must conform to local codes. Before installing the fireplace, consult the local building code agency to ensure that you are in compliance with all applicable codes, including permits and inspections.
In the absence of local codes, the fireplace installation must conform to the National Fuel Gas Code ANSI Z223.1 (in the United States) or the CAN/CGA-B149 Installation Codes (in Canada). The appliance must be electrically grounded in accordance with local codes or, in the absence of local codes with the National Electric Code ANSI/NFPA No. 70 (in the United States), or to the CSA C22.1 Canadian Electric Code (in Canada).
High Altitude Installations
U.L. Listed gas fireplaces are tested and approved for elevations from 0 to 2,000 feet in the U.S.A. and from 0 to 4,500 feet in Canada.
When installing this fireplace at an elevation above 2,000 feet (in the United States), it may be necessary to decrease the input rating by changing the existing burner orifice to a smaller size. Input should be reduced four percent (4%) for each 1,000 feet above sea level, unless the heating value of the gas has been reduced, in which case this general rule will not apply.
When installing this fireplace at an elevation between 2,000 and 4,500 feet (in Canada), the input rating must be reduced by ten percent (10%).
When installing this fireplace at an elevation above 4,500 feet (in Canada), check with local authorities.
Consult your local gas utility for assistance in determining the proper orifice for your location.
These models may be installed in a bedroom or bed-sitting room in the U.S.A. and Canada.
Heat-N-Glo Quality Systems registered by SGS ICS
8
Page 5
2
Getting Started
Introducing the Heat-N-Glo Gas Fireplaces
Heat-N-Glo direct vent gas fireplaces are designed to oper­ate with all combustion air siphoned from outside of the building and all exhaust gases expelled to the outside.
The information contained in this Installers Guide, unless noted otherwise, applies to all models and gas control systems. Gas fireplace diagrams, including the dimensions, are shown in this section.
Pre-install Preparation
This gas fireplace and its components are tested and safe when installed in accordance with this Installers Guide. Report to your dealer any parts damaged in shipment, particularly the condition of the glass. Do not install any
unit with damaged, incomplete, or substitute parts.
The vent system components are shipped in separate packages. The gas logs are packaged separately and must be field installed.
Read all of the instructions before starting the installation. Follow these instructions carefully during the installation to ensure maximum safety and benefit. Failure to follow these instructions will void the owners warranty and may present a fire hazard.
Warranty
The Heat-N-Glo Warranty will be voided by, and Heat-N-Glo disclaims any responsibility for, the following actions:
 Installation of any damaged fireplace or vent system com-
ponent.
 Modification of the fireplace or direct vent system.
 Installation other than as instructed by Heat-N-Glo.
 Improper positioning of the gas logs or the glass door.
 Installation and/or use of any component part not manu-
factured and approved by Heat-N-Glo, not withstanding any independent testing laboratory or other party approval of such component part or accessory.
ANY SUCH ACTION MAY POSSIBLY CAUSE A FIRE HAZARD.
When planning a fireplace installation, its necessary to determine:
Where the unit is to be installed.
The vent system configuration to be used.
Gas supply piping.
Electrical wiring.
Framing and finishing details.
Whether optional accessories  devices such as a fan,
wall switch, or remote control  are desired.
If the fireplace is to be installed on carpeting or tile, or on any combustible material other than wood flooring, the fireplace must be installed on a metal or wood panel that extends the full width and depth of the fireplace.
9
Page 6
Ø
6 5/8
(168mm)
11 5/ 16
(287mm)
25 7/8
(657mm)
VENT COLLAR
38 5/8
(981mm)
31 3/16
(792mm)
36 1/16
(915mm)
TOP STANDOFFS
TOP
GRILL
SIDE
GLASS
DOOR
28 3/16
(716mm)
35 3/16
(894mm)
2
(52mm)
3 3/8
(85mm)
ELECTRICAL
ACCESS
GAS LINE
ACCESS
22 11/16
(576mm)
VENT COLLAR
2
(52mm)
3 1/16
(79mm)
ELECTRICAL
ACCESS
GAS LINE
ACCESS
Figure 1. Diagram of the PIER-38HV
END GLASS
DOOR
BOTTOM
GRILL
GAS CONTROLS
& LABELS
10
Page 7
Ø6 5/8
(168mm)
11 5/16
(287mm)
25 7/8
(657mm)
VENT COLLAR
38 5/8
(981mm)
35 3/16
(894mm)
31 3/16 (792mm)
38 1/4 (972mm)
TOP STANDOFFS
TOP
GRILL
29 1/8
(739mm)
(52mm)
3 3/8
(85mm)
ELECTRICAL
ACCESS
GAS LINE
2
ACCESS
22 11/16
(576mm)
3 1/16
(79mm)
VENT COLLAR
2
(52MM)
ELECTRICAL
ACCESS
Figure 2. Diagram of the ST-38HV
GAS LINE
ACCESS
GLASS
DOOR
BOTTOM
GRILL
GAS CONTROLS
& LABELS
11
Page 8
3
Installing the Fireplace
36”
PIER-38HV
Constructing the Fireplace Chase
A chase is a vertical box-like structure built to enclose the gas fireplace and/or its vent system. Vertical vents that run on the outside of a building may be, but are not required to be, installed inside a chase.
CAUTION: TREATMENT OF FIRESTOP SPACERS AND CONSTRUCTION OF THE CHASE MAY VARY WITH THE TYPE OF BUILDING. THESE INSTRUCTIONS ARE NOT SUBSTITUTES FOR THE REQUIREMENTS OF LOCAL BUILDING CODES. THEREFORE, YOUR LOCAL BUILD­ING CODES MUST BE CHECKED TO DETERMINE THE REQUIREMENTS FOR THESE STEPS.
Factory-built fireplace chases should be constructed in the manner of all outside walls of the home to prevent cold air drafting problems. The chase should not break the outside building envelope in any manner.
This means that the walls, ceiling, base plate and cantilever floor of the chase should be insulated. Vapor and air infiltra­tion barriers should be installed in the chase as per regional codes for the rest of the home. Additionally, Heat-N-Glo rec­ommends that the inside surfaces be sheetrocked and taped for maximum air tightness.
To further prevent drafts, the firestops should be caulked to seal gaps. Gas line holes and other openings should be caulked or stuffed with insulation. If the unit is being in­stalled on a cement slab, we recommend that a layer of plywood be placed underneath to prevent conducting cold up into the room. Be sure to include spark arrestors for woodburning units if they are required.
36”
36”
ST-38HV
36”
Figure 3. Fireplace Dimensions, Locations, and Space Requirements
Minimum Clearances from the Fireplace to
Combustible Materials
Inches mm
Glass Sides or Ends.......... 3 6 ................. 91 4
Floor....................................... 0 .................... 0
Rear Vent............................... 0 .................... 0
Metal Sides or Ends ............ 0 .................... 0
Top ....................................... 3 1/2 ...............8 9
Ceiling*................................. 3 6 ................. 91 4
*The clearance to the ceiling is measured from the top of the unit, excluding the stand-offs (see Figure 34).
THE CHASE SHOULD BE CONSTRUCTED SO THAT ALL CLEARANCES TO THE FIREPLACE ARE MAINTAINED AS SPECIFIED WITHIN THIS INSTALLERS GUIDE.
Step 1. Locating the Fireplace
Space and clearance requirements for locating a fireplace within a room (see Figure 3).
Clearance Requirements
The top, back, and sides of the fireplace are defined by stand-offs. The minimum clearance to a perpendicular wall extending past the face of the fireplace is one inch (25mm). The metal ends of the fireplace may NOT be recessed into combustible construction.
Minimum Clearances from the Vent Pipe to
Combustible Materials
Inches mm
Vertical Sections. ............. 1 ................... 2 5
Horizontal Sections
Top ......................................... 3 ................... 75
Bottom .................................. 1 ................... 25
Sides..................................... 1 ................... 25
At Wall Firestops
Top ...................................... 2 1/2 ...............6 4
Bottom ................................. 1/2 ................. 1 3
Sides..................................... 1 ................... 2 5
For minimum clearances of direct vent termination (see Fig­ures 25 and 26).
12
Page 9
Step 2. Framing the Fireplace
Fireplace framing can be built before or after the fireplace is set in place. Framing should be positioned to accommo­date wall coverings and fireplace facing material. The dia­gram below shows framing reference dimensions.
CAUTION: MEASURE FIREPLACE DIMENSIONS AND VERIFY FRAMING METHODS AND WALL COVERING DETAILS BEFORE FRAMING.
WARNING: FRAMING DIMENSIONS ASSUME
!
USE OF 1/2 INCH THICK WALL COVERING MATERIALS ON EXTERIOR OF FRAMING ONLY AND NO SHEET ROCK ON INTERIOR OF FRAMING.
Shows center of 10 x 10 vent framing holes.
The center of the hole is 1 inch (25.4mm) above the center of the horizontal vent pipe.
37 1/8
(943mm)
Framing should be constructed of 2 X 4 lumber or heavier.
*NOTE: Review details of Figure 5 BEFORE constructing framing. The dimen­sions in Figure 4 do not include po­sitions of venting and firestops.
*35 7/8 (911mm)
1/2 SHEET ROCK
35 3/4
(908mm)
5/8 SHEETROCK
38 1/2
(978mm)
38 3/4
(984mm)
21 11/16
(551mm)
1/2 SHEET ROCK
21 7/16
(545mm)
5/8 SHEET ROCK
38 3/4
(984mm)
21 11/16
(551mm)
1/2 SHEET ROCK
21 7/16
(545mm)
5/8 SHEET ROCK
Figure 4. Framing Dimensions*
13
Page 10
ST-38HV
PIER- 38 HV
Vertical Vent Runs
41 1/2”
(1054mm)
1” (25mm)
PIPE CLEARANCE
”
4
Vertical Vent Runs
1” (25mm)
PIPE CLEARANCE
) m m
2 0
1
(
40 3/8”
(1026mm)
) m
”
m
4
2 0
1
(
Horizontal Vent Runs
3” (75mm)
PIPE CLEARANCE
40”
(1016mm)
FIRESTOP
1 1/2”
(38mm)
36 1/8”
(918mm)
Horizontal Vent Runs
3” (75mm)
PIPE CLEARANCE
37 7/8”
(962mm)
FIRESTOP
1 1/2”
(38mm)
36 1/8”
(918mm)
Figure 5. Vertical and Horizontal Vent Runs for ST-38HV and PIER-38HV.
14
Page 11
Step 3. Installing the Vent System
A. Vent System Approvals
These models are approved to use SL-series direct vent pipe components and terminations. Approved vent system components are labeled for identifica­tion. This pipe is tested and listed as an approved component of the fireplace. The pipe is tested to be run inside an enclosed wall. There is no requirement for inspection openings at each joint within the wall. There is no required pitch for horizontal vent runs.
NO OTHER VENTING SYSTEMS OR COMPO­NENTS MAY BE USED.
Detailed installation instructions are included with each vent termination kit and should be used in conjunction with this Installers Guide. The drawing below shows vent system components and terminations.
The flame and ember appearance may vary based on the type of fuel burned and the venting configura­tion used.
17-24
9 1/4
SL-17/24D
(SL17-24D)
SL-45D
6 1/2
6 5/8
11 3/4
6 5/8
6 3/8
5 3/4
6 3/8
SL-90D
SL-06DSL-12D
6 1/2
6 5/8
6 1/2
9 5/8
9 5/8
47 3/4
Identifying Vent Components
The vent systems installed on this gas fireplace may include one, two, or three 90° elbow assemblies. The relationships of vertical rise to horizontal run in vent configurations using 90° elbows MUST BE strictly adhered to. The rise to run relationships are shown in the venting drawings and tables. Refer to the dia­grams on the next several pages.
NOTE: Two 45° elbows may be used in place of one 90° elbow. Rise to run ratios in the vent system must be followed if 45° elbows are used.
Vent system
termination kits
HORIZONTAL
SLK-01D
SLK-TVCD
TERMINATION
8 3/4
VERTICAL TERMINATION
35 3/4
23 3/4
12-17
SL-09D
SL-12/17D (SL12-17D)
SL-24D
SL-36D
SL-48D
NOTE: PIPES OVERLAP 1-3/8 INCHES (34.93mm) AT EACH JOINT.
Figure 6. SL-Series Direct Vent Component Specifications (4-inch inner pipe / 6 5/8-inch outer pipe)
Vent system components
STORM COLLAR
ROOF FLASHING
HORIZONTAL PIPE SUPPORT
SLK-01TRD
PVK-80
Figure 7. Vent Components and Terminations
WA LL FIRESTOP
90 DEGREE ELBOW
15
CEILING FIRESTOP
PIPE LENGTH
WALL BRACKET
To Unit
Page 12
NOTE: If the vertical vent component is 10 feet or more, you may want to install the vertical baffle to improve flame appearance. Vertical baffle kit (BAF-VERT) is located in the manual bag.Center the vertical baffle on the four inch flue and with self tapping screws secure the baffle to the inside of the firebox (see Figure 8).
CAP
STRAIGHT UP
VERTICAL VENTING
V (FT.)
40' MAX. (12.4 M)
VERTICAL BAFFLE
KIT (BAF-VERT)
Figure 8. Vertical Baffle Kit
V
NOTE: For vertical vent runs of 10 feet or greater the ver­tical baffle kit (BAF-VERT) may be required to improve flame appearance.
Figure 9. Straight Up Vertical Venting
STRAIGHT OUT
HORIZONTAL VENTING
H
Max. Run
24" (610 mm)
Figure 10. Straight Out Horizontal Venting
H
16
Page 13
V
VENTING WITH ONE (1) 90° ELBOW
V (FT.) H (FT.)
4.5' MIN. (1.37m) 3' MAX. (.914m) 6' MIN. (1.86m) 4' MAX. (1.22m) 8' MIN. (2.4m) 5' MAX. (1.5m)
5' MAX. (1.5m)
V + H = 37 MAX. (11.3m)
H
H
V
VENTING WITH ONE (1) 90° ELBOW
V (FT.) H (FT.) 1' MIN. (305mm) 2' MAX. (610mm) 2' MIN. (610mm) 4' MAX. (1.22m) 3' MIN. (914mm) 6' MAX. (1.86m) 4' MIN. (1.22m) 8' MAX. (2.44m)
5 MIN. (1.5m) 10 MAX. (3.05m) 6 MIN. (1.86m) 12 MAX. (3.6m) 7 MIN. (2.13m) 14' MAX. (4.27m)
14' MAX. (4.27m)
V + H = 37 MAX. (11.3m)
NOTE: For vertical vent runs of 10 feet or greater the vertical baffle kit (BAF-VERT) may be required to improve flame appearance.
Figure 11. Venting with One 90° Elbow
17
Page 14
H
11
VENTING WITH TWO (2) 90° ELBOWS
V (FT.) H + H1 (FT.) 1' MIN. (305mm) 2' MAX. (610mm) 2' MIN. (610mm) 4' MAX. (1.22m) 3' MIN. (914mm) 6' MAX. (1.86m) 4' MIN. (1.22m) 8' MAX. (2.44m) 5 MIN. (1.5m) 10 MAX. (3.04m) 6 MIN. (1.86m) 12 MAX. (3.6m) 7 MIN. (2.13m) 14' MAX. (4.27m)
14' MAX. (4.27m)
V + H = 37 MAX. (11.3m)
V
H
H
NOTE: For vertical vent runs of 10 feet or greater the vertical baffle kit (BAF-VERT) may be required to improve flame appearance.
Figure 12. Venting with Two 90° Elbows
V
11
18
V
Page 15
VENTING WITH TWO (2) 90° ELBOWS
V H H + H
1´ MIN. (305 mm) 2´ MAX. (610 mm) 2´ MAX. (610 mm) 2´ MIN. (610 mm) 2´ MAX. (610 mm) 4´ MAX. (1.22 m) 3´ MIN. (914 mm) 2´ MAX. (610 mm) 6´ MAX. (1.86 m) 4´ MIN. (1.22 m) 2´ MAX. (610 mm) 8´ MAX. (2.4 m) 5´ MIN. (1.52 m) 2´ MAX. (610 mm) 10´ MAX. (3.04 m) 6´ MIN. (1.86 m) 2´ MAX. (610 mm) 12´ MAX. (3.65 m) 7´ MIN. (2.13 m) 2´ MAX. (610 mm) 14´ MAX. (4.26 m)
14´ MAX. (4.26 m)
H
11
V + H + H
= 37 MAX. (11.3 m)
1
1
H
V
NOTE: For vertical vent runs of 10 feet or greater the vertical baffle kit (BAF-VERT) may be required to improve flame appearance.
Figure 13. Venting with Two (2) 90° Elbows
19
Page 16
V
H
22
V
H
11
H
11
V
H
11
NOTE: For vertical vent runs of 10 feet or greater the vertical baffle kit (BAF-VERT) may be required to improve flame appearance.
Figure 14. Venting with Three 90° Elbows
H
VENTING WITH THREE (3) 90° ELBOWS
V H H + H
1´ MIN. (305 mm) 2´ MAX. (610 mm) 2´ MAX. (610 mm) 2´ MIN. (610 mm) 2´ MAX. (610 mm) 4´ MAX. (1.22 m) 3´ MIN. (914 mm) 2´ MAX. (610 mm) 6´ MAX. (1.86 m) 4´ MIN. (1.22 m) 2´ MAX. (610 mm) 8´ MAX. (2.4 m) 5´ MIN. (1.52 m) 2´ MAX. (610 mm) 10´ MAX. (3.04 m) 6´ MIN. (1.86 m) 2´ MAX. (610 mm) 12´ MAX. (3.65 m)
7´ MIN. (2.13 m) 2´ MAX. (610 mm) 14´ MAX. (4.26 m)
V + H + H
= 37 MAX. (11.3 m)
1
20
1
14´ MAX. (4.26 m)
Page 17
H
H
11
V
11
V
VENTING WITH THREE (3) 90° ELBOWS
V (FT.) H + H1 (FT.) 1' MIN. (305mm) 2' MAX. (610mm) 2' MIN. (610mm) 4' MAX. (1.22m) 3' MIN. (914mm) 6' MAX. (1.86m) 4' MIN. (1.22m) 8' MAX. (2.44m) 5 MIN. (1.5m) 10 MAX. (3.04m) 6 MIN. (1.86m) 12 MAX. (3.6m) 7 MIN. (2.13m) 14' MAX. (4.27m)
14' MAX. (4.27m)
V
11
V + H = 37 MAX. (11.3m)
H
11
NOTE: For vertical vent runs of 10 feet or greater the vertical baffle kit (BAF-VERT) may be required to improve flame appearance.
Figure 15. Venting with Three 90° Elbows
21
H
V
Page 18
B. Installing Vent Components
1. Attach the First Vent Component to the Starting Collars
To attach the first vent component to the starting collars of the fireplace:
 Apply a 3/8 inch (9.5mm) bead of stove cement around
the 5 inch (127mm) fireplace starting collar.
WARNING: ENSURE THAT THE FIBERGLASS
!
ROPE GASKET SUPPLIED WITH THE FIREPLACE SEALS BETWEEN THE FIRST VENT COMPONENT AND THE OUTER FIREPLACE WRAP.
If the installation is for a termination cap attached directly to the fireplace, skip to the sections, Install Firestops and Vent Termination.
 Make sure that the fireplace rope gasket supplied with
the fireplace seals between the first 8-5/8 inch (219mm) vent component and the outer fireplace wrap.
 Lock the vent components into place by sliding the con-
centric pipe sections with four (4) equally spaced interi­or beads into the fireplace collar or previously installed com­ponent end with four (4) equally spaced indented sections.
 When the internal beads of each 6-5/8 inch (168mm)
outer pipe line up, rotate the pipe section clockwise about one-quarter (1/4) turn. The vent pipe is now locked together.
STARTING
COLLAR
STOVE
SEALANT
BEAD
2. Continue Adding Vent Components
To continue adding vent components in accordance with the pre-planned vent system configuration:
 Ensure that each succeeding vent component is securely
fitted and locked into the preceding component in the vent system.
 90° elbows may be installed and rotated to any point
around the preceding components vertical axis. If an elbow does not end up in a locked position with the pre­ceding component, attach with a minimum of two (2) sheet metal screws. Continue adding vent components, locking each succeeding component into place (see Figure 17).
FIRST VENT
COMPONENT
1 INCH
(25.4mm)
Figure 16. Attaching the First Vent Component to the Starting Collars
WARNING: A 3/8 INCH (9.5 MM) BEAD OF
!
STOVE CEMENT MUST BE PLACED AROUND THE 4 INCH (102MM) FIREPLACE STARTING COL­LAR BEFORE ATTACHING THE FIRST VENT COM­PONENT. FAILURE TO SEAL THIS JOINT MAY CAUSE THE FIREPLACE TO OPERATE IMPROPER­LY. SEE FIGURE 16.
Figure 17. Adding Venting Components
22
Page 19
3. Install Support Brackets
For Horizontal Runs - The vent system must be sup-
ported every five (5) feet of horizontal run by a horizontal pipe support.
To install support brackets for horizontal runs:
 Place the pipe supports around the vent pipe.
 Nail the pipe supports to the framing members.
For Vertical Runs - The vent system must be supported
every eight (8) feet (2.4m) above the fireplace flue outlet by wall brackets.
To install support brackets for vertical runs:
 Attach wall brackets to the vent pipe and secure the wall
bracket to the framing members with nails or screws.
WALL BRACKET
WALL STUD
To install firestops for horizontal runs that pass through either interior or exterior walls:
 Cut a 10-inch by 10-inch (254mm X 254mm) hole through
the wall. The center of the hole is one (1) inch (25.4mm) above the center of the horizontal vent pipe.
 Position the firestops on both sides of the hole previ-
ously cut and secure the firestops with nails or screws.
 The heat shields of the firestops MUST BE placed to-
wards the top of the hole.
 Continue the vent run through the firestops.
NOTE: There must be NO INSULATION or other combustibles inside the framed firestop opening.
10"
(254mm)
1" (25.4 mm)
10"
(254mm)
8 FT.
(2.4mm)
FLUE
OUTLET
1 INCH MIN.
(25.4mm)
Figure 18. Installing Support Brackets
4. Install Firestops
For Horizontal Runs - Firestops are REQUIRED on both sides of a combustible wall through which the vent passes.
VENT PIPE
Figure 19. 10" x 10" Hole and Vent Pipe
HEAT SHIELD
INTERIOR FIRESTOP
TRIM HEAT SHIELD IF TOO LONG, ADD TO SHIELD IF TOO SHORT
EXTERIOR FIRESTOP
NOTE: Model SLK-01TRD does not need an exterior firestop on an exterior combustible wall. The firestop is built into the cap.
Figure 20. Heat Shield, Interior & Exterior Firestops
23
Page 20
For Vertical Runs - One ceiling firestop is REQUIRED
at the hole in each ceiling through which the vent passes. To install firestops for vertical runs that pass through ceilings:
 Position a plumb bob directly over the center of the verti-
cal vent component.
If the area above the ceiling is NOT an attic, position and secure the ceiling firestop on the ceiling side of the previously cut and framed hole.
 Mark the ceiling to establish the centerpoint of the vent.
 Drill a hole or drive a nail through this centerpoint.
 Check the floor above for any obstructions, such as wir-
ing or plumbing runs.
 Reposition the fireplace and vent system, if necessary,
to accommodate the ceiling joists and/or obstructions.
CEILING
 Cut an 10-inch x 10-inch (254mm x 254mm) hole through
the ceiling, using the centerpoint previously marked.
NAILS (4 REQUIRED)
 Frame the hole with framing lumber the same size as the
ceiling joists.
Figure 22. Ceiling Firestop (Ceiling Side)
NOTE: There must be NO INSULATION or other combustibles inside the framed firestop opening.
If the area above the ceiling IS an attic, position and secure the firestop on top of the previously framed hole.
Figure 23 shows an attic installation. Keep insulation away from the vent pipe at least 1 inch (25mm).
10" (254mm) 10" (254mm)
While it is not mandatory, it is strongly recommended that an attic insulation shield be used whenever insulation can come in contact with the vent pipe. Follow your local building codes.
CHIMNEY HOLE
JOIST
CEILING FIRESTOP
EXISTING CEILING JOISTS
CEILING
NEW FRAMING MEMBERS
Figure 21. 10" x 10" Hole & New Framing Members
NAILS (4 REQUIRED)
RAFTER
CEILING
CEILING FIRESTOP
Figure 23. Attic Firestop
24
Page 21
C. Vent Termination
For Horizontal Terminations - To attach and secure
the termination to the last section of horizontal vent:  Rotate and interlock the ends as described at the begin-
ning of the Installing Vent Components section.
 The termination kit should pass through the wall firestops
from the exterior of the building.
 Adjust the termination cap to its final exterior position on
the building.
WARNING: THE TERMINATION CAP MUST BE POSITIONED SO THAT THE ARROW IS POINT-
!
ING UP.
ROUND CAP TERMINATION
PERFORATION CANNOT BE
INSIDE THE WALL
For roundcap termination kits:
 Use the exterior pipelock hole provided on the round
flange of the wall firestop to secure the vent pipe in place.
For trapezoidal cap termination kits:
 Using screws, secure the cap to the exterior wall
through the flanges built into the cap.
WARNING: THE BOTTOM OF THE VENT
!
TERMINATION CAP MUST BE A MINIMUM OF 12 INCHES (305 MM) ABOVE GROUND LEVEL (GRADE). THE TOP OF THE CAP MUST BE A MIN­IMUM OF 24 INCHES (690 MM) BELOW COMBUS­TIBLE MATERIAL, SUCH AS A DECK, AND THE SIDE OF THE CAP MUST BE A MINIMUM OF 6 INCHES (152 MM) AWAY FROM A PARALLEL OUT­SIDE WALL. VENTING TERMINALS SHALL NOT BE RECESSED INTO A WALL OR SIDING. SEE FIG­URE 25 FOR VENT TERMINATION CLEARANCES.
7 1/2"
(191mm)
MINIMUM
TRAPEZOID CAP TERMINATION
7 1/4"
(184mm)
Figure 24. Round & Trapezoid Termination Caps
25
Page 22
4
4
D
E
v
L
B
v
=VENT TERMINAL X =AIR SUPPLY INLET
V
C
v
F
v
B
openable
v
B
G
v
A
fixed closed
v
23
23
B
A
=AREA WHERE TERMINAL IS NOT PERMITTED
H
M
I
v
X
J or K
A = 12" .................... clearances above grade, veran-
da, porch, deck or balcony
B = 12" .................... clearances to window or door
that may be opened
C = 9" (U.S.A.)
12" (Canada) ..... clearance to permanently
closed window.
D = 24" .................... vertical clearance to ventilated
soffit located above the termi­nal within a horizontal distance of 2 feet (60 cm) from the cen­ter-line of the terminal
E = 24" .................... clearance to unventilated soffit
F = 9" ..................... clearance to outside corner
G = 6" ...................... clearance to inside corner
H = 3 ft. (Canada) .... not to be installed above a gas
meter/regulator assembly with­in 3 feet (90cm) horizontally from the center-line of the regulator
I = 3 ft. (U.S.A.)
6 ft. (Canada) ..... clearance to service regu-
lator vent outlet.
J = 9" (U.S.A.)
12" (Canada) ..... clearance to non-mechan-
ical air supply inlet to building or the combustion air inlet to any other ap­pliance
K = 3 ft. (U.S.A.)
6 ft. (Canada) ..... clearance to a mechanical
air supply inlet
*L = 7 ft. ................... clearance above paved
sidewalk or a paved drive­way located on public property
**M = 24" .................... clearance under veranda,
porch, deck or balcony
* a vent shall not terminate directly above a sidewalk or paved driveway which is
located between two single family dwellings and serves both dwellings.
** only permitted if veranda, porch, deck or balcony is fully open on a minimum of
2 sides beneath the floor.
NOTE: Local Codes or Regulations may require different clearances.
Figure 25. Vent Termination Minimum Clearances
CAUTION: IF EXTERIOR WALLS ARE FINISHED WITH VINYL SIDING, IT IS NECESSARY TO INSTALL THE VINYL PROTECTOR KIT TO THE TOP OF THE EXTERIOR FIRESTOP (FOR ALL ROUND TERMINATION CAPS).
26
Page 23
For Vertical Terminations - To locate the vent and
install the vent sections:  Locate and mark the vent centerpoint on the underside
of the roof, and drive a nail through the centerpoint.
 Make the outline of the roof hole around the centerpoint
nail.
 The size of the roof hole framing dimensions depend on the
pitch of the roof. There MUST BE a 1-inch (25.4mm) clear­ance from the vertical vent pipe to combustible materials.
 Mark the roof hole accordingly.
 Cover the opening of the installed vent pipes.
 Cut and frame the roof hole.
To seal the roof hole, and to divert rain and snow from the vent system:
 Attach a flashing to the roof using nails, and use a non-
hardening mastic around the edges of the flashing base where it meets the roof.
 Attach a storm collar over the flashing joint to form a
water-tight seal. Place non-hardening mastic around the joint, between the storm collar and the vertical pipe.
 Slide the termination cap over the end of the vent pipe
and rotate the pipe clockwise 1/4 turn.
HORIZONTAL
OVERHANG
 Use framing lumber the same size as the roof rafters
and install the frame securely. Flashing anchored to the frame must withstand heavy winds.
 Continue to install concentric vent sections up through
the roof hole (for inside vent installations) or up past the roof line until you reach the appropriate distance above the roof (for outside terminations).
WARNING: MAJOR U.S. BUILDING CODES
!
SPECIFY MINIMUM CHIMNEY AND/OR VENT HEIGHT ABOVE THE ROOF TOP. THESE MIN­IMUM HEIGHTS ARE NECESSARY IN THE INTER­EST OF SAFETY. SEE THE FOLLOWING DIAGRAM FOR MINIMUM HEIGHTS, PROVIDED THE TERMI­NATION CAP IS AT LEAST TWO (2) FEET FROM A VERTICAL WALL AND 2-FEET BELOW A HORIZON­TAL OVERHANG.
NOTE: This also pertains to vertical vent systems in­stalled on the outside of the building.
2 FT. MIN.
TERMINAT ION
CAP
2 FT. MIN.
LOWEST
DISCHARGE
OPENING
H (MIN.) - MINIMUM HEIGHT FROM ROOF TO LOWEST DISCHARGE OPENING
X
12
ROOF PITCH
VERTICAL
WALL
IS X/ 12
Roof Pitch H (min.) ft.
flat to 6/12 1.0 6/12 to 7/12 1.25 over 7/12 to 8/12 1.5 over 8/12 to 9/12 2.0 over 9/12 to 10/12 2.5 over 10/12 to 11/12 3.25 over 11/12 to 12/12 4.0 over 12/12 to 14/12 5.0 over 14/12 to 16/12 6.0 over 16/12 to 18/12 7.0 over 18/12 to 20/12 7.5 over 20/12 to 21/12 8.0
Figure 26. Minimum Height from Roof to Lowest Discharge Opening
27
Page 24
Step 4. Positioning, Leveling, and Securing the Fireplace
The diagram below shows how to properly position, level, and secure the fireplace.
PIER-38H V
Step 5. The Gas Control Systems
WARNING: THIS UNIT IS NOT FOR USE WITH
!
SOLID FUEL.
Two types of gas control systems are used with these mod­els: Standing Pilot Ignition and Direct Spark Ignition (DSI).
Standing Pilot Ignition System
This system includes millivolt control valve, standing pilot, thermopile/thermocouple flame sensor, and piezo ignitor.
WARNING: 110-120 VAC MUST NEVER BE
!
CONNECTED TO A CONTROL VALVE IN A MILLIVOLT SYSTEM.
ST-38HV
Figure 27. Proper Positioning, Leveling, and Securing of a Fireplace
 Place the fireplace into position.
 Level the fireplace from side to side and from front to
back.
 Shim the fireplace with non-combustible material, such
as sheet metal, as necessary.
 Secure the fireplace to the framing by nailing or screwing.
Figure 28. Standing Pilot Ignition
Direct Spark Ignition (DSI) System
This system includes a 120VAC control valve, electronic module and spark ignitor/flame sensor (see Figure 29).
WARNING: CONTINUOUS 110-120 VAC SERVICE
!
MUST BE WIRED DIRECTLY TO THE FIREPLACE JUNCTION BOX IN A DSI SYSTEM.
WARNING: DIRECT VENT PROPANE MODELS
!
WITH DSI CONTROL SYSTEMS CANNOT BE USED IN CANADA.
3/8”
(10mm)
Figure 29. Direct Spark Ignition
28
Page 25
Step 6. The Gas Supply Line
NOTE: Have the gas supply line installed in accordance with local building codes by a qualified installer approved and/or licensed as required by the locality.
NOTE: Before the first firing of the fireplace, the gas supply line should be purged of any trapped air.
NOTE: Consult local building codes to properly size the gas supply line leading to the 1/2 inch (13mm) hook-up at the unit.
This gas fireplace is designed to accept a 1/2 inch (13mm) gas supply line.
To install the gas supply line:  A listed (and State of Massachusetts approved) 1/2 inch
(13mm) tee-handle manual shut-off valve and a listed flexible gas connector are connected to the 1/2 inch (13mm) inlet of the control valve. NOTE: If substituting for these components, please consult local codes for compliance.
 Locate the gas line access hole in the outer casing of
the fireplace.
 The gap between the supply piping and gas access hole
can be plugged with non-combustible insulation to pre­vent cold air infiltration.
 Open the fireplace lower grille, insert the gas supply line
through the gas line hole, and connect it to the shut-off valve.
 When attaching the pipe, support the control so that the
lines are not bent or torn.
 After the gas line installation is complete, use a soap
solution to carefully check all gas connections for leaks.
Step 7. Gas Pressure Requirements
Pressure requirements for Heat-N-Glo gas fireplaces are shown in the table below.
Pressure Natural Gas Propane
Minimum 5.0 inches 11.0 inches Inlet Pressure w.c. w.c.
Maximum Inlet 14.0 inches 14.0 inches Gas Pressure w.c. w.c.
Manifold 3.5 inches 10.0 inches Pressure w.c. w.c.
A one-eighth (1/8) inch (3 mm) N.P.T. plugged tapping is provided on the inlet and outlet side of the gas control for a test gauge connection to measure the manifold pressure.
The fireplace and its individual shut-off valve must be disconnected from the gas supply piping system during any pressure testing of the system at test pressures in excess of one-half (1/2) psig (3.5 kPa).
The fireplace must be isolated from the gas supply piping system by closing its individual shut-off valve during any pressure testing of the gas supply piping system at test pressures equal to or less than one-half (1/2) psig (3.5 kPa).
WARNING: DO NOT USE AN OPEN FLAME
!
TO CHECK FOR GAS LEAKS.
 At the gas line access hole, use insulation to re-pack
the space around the gas pipe.
 Insert insulation from the outside of the fireplace and
pack the insulation tightly to totally seal between the pipe and the outer casing.
USE A WRENCH ON
SHUT-OFF VALVE WHEN
TIGHTENING GAS LINE
MANUAL
SHUT-OFF VALVE
GAS VALVE
FLEX
CONNECTOR
GAS LINE
ACCESS
CONTROL
VALVE
Figure 30. Gas Supply Line
29
Page 26
3/16” PIG GYBACK CONNECTOR
WHITE T2
GAS V ALU E
THERMOCOUPLE
RED T1
THERMOPILE
Figure 31. Standing Pilot Ignition Wiring Diagram
BLACK S2
ON
OFF
BLACK S1
ON/OFF SWITCH
REMOTE SWITCH
PIGTAIL
OPTIONAL WALL SWITCH,
THERMOSTAT OR REMOTE
Step 8. Wiring the Fireplace
NOTE: Electrical wiring must be installed by a licensed electrician.
CAUTION: DISCONNECT REMOTE CONTROLS IF YOU ARE ABSENT FOR EXTENDED TIME PERIODS. THIS WILL PREVENT ACCIDENTAL FIREPLACE OPERATION.
For Standing Pilot Ignition Wiring
Appliance Requirements  This appliance DOES NOT require 110-120 VAC to operate.
WARNING: DO NOT CONNECT 110-120 VAC
!
TO THE GAS CONTROL VALVE OR WALL SWITCH OR THE APPLIANCE WILL MALFUNCTION AND THE VALVE WILL BE DESTROYED.
Optional Accessories
Optional fan and remote control kits require that 110-120 VAC be wired to the factory installed junction box before the fireplace is permanently installed.
Wall Switch
Position the wall switch in the desired position on a wall. Run a maximum of 25 feet (7.8 m) continuous wire or less length of 18 A.W.G. minimum wire and connect it to the fireplace ON/OFF switch pigtails.
CAUTION: LABEL ALL WIRES PRIOR TO DISCONNEC­TION WHEN SERVICING CONTROLS. WIRING ERRORS CAN CAUSE IMPROPER AND DANGEROUS OPERA­TION. VERIFY PROPER OPERATION AFTER SERVICING.
For Direct Spark Ignition (DSI) Wiring
Appliance Requirements
This appliance requires that 110-120 VAC be wired to the factory installed junction box. Maintain correct polarity when wiring the junction box.
Optional Accessories
Optional fan and remote control kits require that 110-120 VAC be wired to the fireplace junction box.
Wall Switch
Position the wall switch in the desired position on a wall. Run a maximum of 25 feet (7.8 m) or less of 16 A.W.G. minimum wire and connect it to the fireplace ON/OFF switch pigtails.
CAUTION: LABEL ALL WIRES PRIOR TO DISCONNEC­TION WHEN SERVICING CONTROLS. WIRING ERRORS CAN CAUSE IMPROPER AND DANGEROUS OPERATION. VERIFY PROPER OPERATION AFTER SERVICING.
VARIABLE SPEED CONTROL
BLK
BLK
BLK
TEMPERATURE
SENSOR SWITCH
BLK
JUNCTION BOX
BLK
BLK
BLK
BLK
GROUND
Figure 32. Fan Wiring Diagram
110-120 VAC
GRN
WHT
NOTE: IF ANY OF THE ORIGINAL WIRE AS SUPPLIED WITH THE APPLIANCE MUST BE REPLACED, IT MUST BE REPLACED WITH TYPE 105 C RATED WIRE.
BLK
WHT
WHT
BLOWER RECEPTACLE
30
JUNCTION BOX
O
FAN
BLOWER
TEMPERATURE
SENSOR SWITCH
SPEED CONTROL
(RHEOSTAT)
Page 27
OPTIONAL REMOTE,
WALL SWITCH
OR THERMOSTAT
(ON CERTIFIED UNITS ON LY)
100-254A
JUNCTION
BOX
120 VAC
BLACK
L2
(NEUTRAL)
L1
(HOT)
OPTIONAL
FAN
SWITCHES
476-500
DSI CONTROL VALVE
459-591
IGNITOR
ON/OFF
FLAME SENSOR/SPARKER
IGNITION
MODULE
GAS
VALVE
120 VAC
POWER CORD
REMOTE OUTLET
REM
FAN
GROUND
TO
FIREPLACE
CHASSIS
GROUND
WHITE
BLACK
ON/OFF SWITCH
WHITE
YELLOW
GREEN
BLUE
WHITE
BLUE
E G N
A R O
501-592
DSI
MODULE
FAN OUTLET
NEUTRAL
Figure 33. Direct Spark Ignition (DSI) Wiring Diagram
Step 9. Finishing
Figure 34 shows the minimum vertical and corresponding maximum horizontal dimensions of fireplace mantels or other combustible projections above the top front edge of the fireplace. See Figures 3 and 4 for other fireplace clearances.
Only non-combustible materials may be used to cover the black fireplace front.
WARNING: WHEN FINISHING THE FIREPLACE,
!
NEVER OBSTRUCT OR MODIFY THE AIR IN­LET/OUTLET GRILLES IN ANY MANNER.
NOTE: Sheetrock can be placed on the top edge and sides
of the fireplace (see Figure 35).
CONNECTORS
Figure 34. Minimum Vertical and Maximum Horizontal Dimensions of Combustibles above Fireplace
HOTGROUND
CEILING
12"
11"
10"
9"
8"
7"
6"
5"
4"
3"
2"
1”
3”
2”
1”
TOP FRONT EDGE
OF FIREPLACE
6”
5”
4"
10”
9”
8”
7”
11”
36”
12”
31
Page 28
CAUTION: IF JOINTS BETWEEN THE FINISHED WALLS AND THE FIREPLACE SURROUND (TOP AND SIDES) ARE SEALED, A 300° F. MINIMUM SEALANT MATE­RIAL MUST BE USED. THESE JOINTS ARE NOT RE­QUIRED TO BE SEALED. ONLY NON-COMBUSTIBLE MATERIAL (USING 300° F. MINIMUM ADHESIVE, IF NEEDED) CAN BE APPLIED AS FACING TO THE FIRE­PLACE SURROUND. SEE THE DIAGRAM BELOW.
ST-38HV
TOP EDGE
SIDE EDGE
0” GAP
Placing the Ember Material
See two separate bags of ember material. The bag labeled Golden Ember (GE-93) is flame colorant material. The bag labeled Glowing Ember (050-721) is standard glowing ember material. To place the ember material:
 Remove the wing nuts, glass clips and spring clips around
the glass door. Remove the glass door.
 Ember material is to be placed on burner with caution. Do
NOT place ember material over burner port holes. Place only dime size pieces along outer edges of port trails (see Figure 37). The bag is for (4) ember applications. Failure to apply ember material as directed could result in poor light­ing conditions and sooting problems. After placing ember material sprinkle GE-93 on top of the burner. Save the re­maining ember materials for use during fireplace servicing.
FIRST
GRATE BAR
Figure 35. Sealant Material
Hearth Extensions
A hearth extension may be desirable for aesthetic reasons. However, ANSI or CAN/CGA testing standards do not require hearth extensions for gas fireplace appliances.
Step 10. Installing Trim, Logs & Ember Material
Installing the Trim
Combustible materials may be brought up to the specified clearances on the side and top front edges of the fireplace, but MUST NEVER overlap onto the front face. The joints between the finished wall and the fireplace top and sides can only be sealed with a 300° F. (149° C) minimum sealant.
Install optional marble and brass trim surround kits as desired. Marble, brass, brick, tile, or other non-combustible materials can be used to cover up the gap between the sheet rock and the fireplace.
Do not obstruct or modify the air inlet/outlet grilles. When overlapping on both sides, leave enough space so that the bottom grille can be raised and the trim door removed.
Positioning the Logs
The gas logs have been factory installed and should not need to be positioned. After removing the stretch wrapping, reinstall the logs and grate (see Figure 37). Make sure the end of the grate with the incomplete cross bar is on the pilot end of the firebox.
If sooting occurs, the logs might need to be repositioned slightly to avoid excessive flame impingement.
PIER-38HV
TOP EDGE
SIDE EDGE
0” GAP
EMBER
MATERIAL
DO NOT PLACE EMBER
INCORRECT
EMBER PLACEMENT
CORRECT
EMBER
PLACEMENT
MATERIAL ON FIRST SECTION OF PORTS BETWEEN THE PILOT ASSEMBL Y AND THE FIRST GRATE BAR.
Figure 37. Placement of the Ember Material
 Replace the wing nut, glass clips and spring clips.  If using the optional mesh doors, attach to fireplace glass
doors using the mesh clips provided in the manual bag. See Figure 38.
Figure 38.
MESH
CLIP
CAUTION: IT IS STRONGLY RECOMMENDED THAT TRIM DOORS WITH OPTIONAL MESH SCREENS BE IN­STALLED ON PROPANE MODELS.
 Replace the glass door and a front trim door on the unit.
Pull out and latch the glass clips into the groove on the glass frame. Hand tighten the wing nuts.
32
PILOT
ASSEMBL Y
Page 29
GLASS SPECIFICATIONS:
LARGE SMALL GLASS
MODEL GLASS GLASS TYPE
PIER-38HV 34 X 20 20 X 20 TEMPERED ST-38HV 34 X 20 N/A TEMPERED
Heat-N-Glo fireplaces manufactured with tempered glass may be installed in hazardous locations such as bathtub enclosures as defined by the CPSC. The tempered glass has been tested and certified to the requirements of ANSI Z97.1-1984 and CPSC 16 CFR 1202. (Safety Glazing Certification Council SGCC # 1595 and 1597. Architectural Testing, Inc. Reports 02-31919.01 and 02-31917.01.)
This statement is in compliance with CPSC 16 CFR Section
1201.5 Certification and labeling requirements which refers to 15 USC 2063 stating Such certificate shall accompany the product or shall otherwise be furnished to any distributor or retailer to whom the product is delivered.
Some local building codes require the use of tempered glass with permanent marking in such locations. Glass meeting this requirement is available from the factory. Please contact your dealer or distributor to order.
A small amount of air will be in the gas supply lines. When first lighting the fireplace, it will take a few minutes for the lines to purge themselves of this air. Once the purging is complete, the fireplace will light and will operate normally.
Subsequent lightings of the fireplace will not require this purging of air from the gas supply lines, unless the gas valve has been turned to the OFF position, in which case the air would have to be purged.
NOTE: The fireplace should be run 3 to 4 hours on the initial start-up. Turn it off and let it cool completely. Remove and clean the glass. Replace the glass and run the fireplace for an additional 8 hours. This will help to cure the chemicals used in the paint and logs.
Step 12. Lighting the Fireplace
Youve reviewed all safety warnings, youve checked the fireplace for gas leaks, you know the vent system is unobstructed, and youve checked for faulty components. Now youre ready to light the fireplace.
Step 11. Before Lighting the Fireplace
Before lighting the fireplace, be sure to do the following: Remove all paperwork from underneath the fireplace. Review safety warnings and cautions
 Read the Safety and Warning Information section at
the beginning of this Installers Guide.
Double-check for gas leaks
 Before lighting the fireplace, double-check the unit for
possible gas leaks.
Double-check vent terminations and front grilles for
obstructions.
 Before lighting the fireplace, double-check the unit for
possible obstructions that could be blocking the vent ter­minations or the front grilles.
Double-check for faulty components
 Any component that is found to be faulty MUST BE re-
placed with an approved component. Tampering with the fireplace components is DANGEROUS and voids all war­ranties.
WARNING: PLEASE REFER TO THE USERS
!
MANUAL FOR ALL CAUTIONS, SAFETY, AND WARNING INFORMATION PERTAINING TO THE LIGHTING AND OPERATION OF THE FIREPLACE.
After the Installation
LEAVE THIS INSTALLATION MANUAL WITH
!
THE APPLIANCE FOR FUTURE REFERENCE.
33
Page 30
Maintaining and Servicing Your Fireplace
4
Fireplace Maintenance
Although the frequency of your fireplace servicing and main­tenance will depend on use and the type of installation, you should have a qualified service technician perform an appli­ance check-up at the beginning of each heating season. See the table below for specific guidelines regarding each fireplace maintenance task.
IMPORTANT: TURN OFF THE GAS BEFORE SERVICING YOUR FIREPLACE.
Replacing old ember material Frequency: Once annually, during the checkup. By: Qualified service technician. Task: Brush away loose ember material near the burner.
Replace old ember material with new dime-size and shape pieces of Golden Ember (DE-93) and Glowing Ember (050-
721). New ember material should be placed alternately on top of the burner - a layer of Golden Ember, a layer of Glowing Ember, and so on. Save the remaining ember material and repeat this procedure at your next servicing. For more information, see Placing Ember Material.
Cleaning Burner and Controls Frequency: Once annually. By: Qualified service technician. Task: Brush or vacuum the control compartment, fireplace
logs and burner areas surrounding the logs.
Checking Flame Patterns, Flame Height Frequency: Periodically. By: Qualified service technician/Home owner. Task: Make a visual check of your fireplaces flame patterns.
Figure 39. Burner Flame Patterns
Make sure the flames are steady - not lifting or floating. See Figure 39. The flame sensor (DSI) or thermopile/ thermocouple (standing pilot) tips should be covered with flame. See Figures 28 and 29.
Checking Vent System Frequency: Before initial use and at least annually
thereafter, more frequently if possible.
By: Qualified service technician/Home owner. Task: Inspect the external vent cap on a regular basis to
ensure that no debris is interfering with the flow of air. Inspect entire vent system for proper function.
Cleaning Glass Door Frequency: After the first 3 to 4 hours of use. As neces-
sary after initial cleaning.
By: Home owner. Task: Remove and clean glass after the first 3 to 4 hours of
use. After the initial cleaning, clean as necessary, particu­larly after adding new ember (flame colorant) material. Film deposits on the inside of the glass door should be cleaned off using a household glass cleaner. NOTE: DO NOT handle
or attempt to clean the door when it is hot and DO NOT use abrasive cleaners.
34