PNEG-1590
Dryer Final Assembly & Testing Checklist
Customer Name: _____________________________________________________________________________________
Order #: __________________________________________ Serial #: ______________________ MET#: _____________
Model #: ___________________________________________ Date: ___________________________________________
Basket Assembly Checklist
___ ___ Check Order for all Dryer Options
___ ___ Check for loose bolts on dryer (Hit screens and panels and listen for rattles).
___ ___ Check that all screens installed with rough side out.
___ ___ Make sure Plenum Sensor located 36” from rear of Dryer.
___ ___ Check Wet Bin Tie Downs are installed.
___ ___ Check Hair Pins & Wedges are installed.
___ ___ Check that the plastic grommets are installed on the EMT conduit running to the back of the dryer.
___ ___ Check that all lock collars have been installed and the correct rotation applied.
___ ___ Blow off all metal filings from front and rear mounting angles.
___ ___ Check that bottom belt guard is installed correctly and motors are not pushing guards out.
___ ___ Check bottoms of control boxes for foreign material and blow out both if necessary.
___ ___ Check that both doors close without binding and will seal properly (Check weather seal on both doors for contact).
___ ___ Ground cable installed between both door and control box.
___ ___ Check that safety disconnect works properly.
___ ___ Check that hole plugs have been installed and siliconed.
___ ___ Ground lug installed.
___ ___ Check for loose connections by pulling on all control wires and tighten all power wires.
___ ___ Check that each wire has a label in both control boxes.
___ ___ Check and tighten all conduit fittings. Check upper junction box is siliconed.
___ ___ Put weep holes in bottom of white boxes.
___ ___ Make sure burner is centered
___ ___ Make sure grain hi-limits 210 are in grain column & plenum high limits 300 are in plenum
Review Paint Checklist
___ ___ Hand hold rail and grab bar.
___ ___ Shaft ends painted on Motors, Meter rolls, Augers
___ ___ Lock collars painted aluminum.
___ ___ Teflon sprayed on load motor shaft.
___ ___ Hitch
___ ___ Fan Heater blades have aluminum centers painted black for GSI / Aluminum for FFI.
___ ___ Venturi(s) & Grille Guards
___ ___ Pipe train painted black and touch up if necessary.
___ ___ All writing on metal removed.
Review Decal packing list to ensure all decals are on the dryer
___ ___ Two GSI “footballs” on frame (GSI).
___ ___ “Confined Space” decal on rear door (FFI).
___ ___ Auger warning on both sides of rear plenum closure door (GSI/FFI).
___ ___ Auger warning on both sides of access panel, front and rear (GSI).
___ ___ Auger warning on grain discharge. (1 inside and out) (GSI/FFI).
___ ___ Fire danger on rear access door. (1 inside and out) (GSI/FFI).
___ ___ Belt and chain warnings on inside of belt guard (GSI/FFI).
___ ___ Pulley guard has belt and chain warnings installed.
___ ___ Airswitch adjustment decal.
___ ___ Competitor flag installed (2000 series only).
___ ___ GSI decal installed on fan support panel (2000 series only).
___ ___ Error decal inside MCB (2000 series only)
___ ___ Electrical hazard warning installed on fan can lid.
___ ___ Electrical hazard warning beside fan can control box.
___ ___ Warning on meter roll access door (Each Door).
___ ___ Electrical warning decal on Network Fan/Heater box
___ ___ Model # (Single fan, above can in front and above door in rear) (2 fan, below bottom of fan on front panel).
Page 1 of 3
Revision 08
Dryer Pre-fire Checklist
___ Check wiring in control boxes (Jumpers, loose wires, and strands).
___ Check wiring to the main power supply.
___ Check location of 1FI and 2FI wires, make sure 1 is on L1 and 2 is on L3.
___ Capacitor is installed on moisture control light (2000 series only).
___ Check all overloads are set at the rated amperage listed on motors rating plate.
___ Check wiring in fan boxes
___ Check fan overloads are set at the rated amperage listed on the motors rating plate.
___ Check direction of flow on all solenoids and regulators.
___ Perform a Dielectric Strength (Hi-Pot) test in accordance with work instruction QSD-000152.R00. ___ Pass, ___ Fail
___ Perform a Grounding Continuity test in accordance with work instruction QSD-000151.R00. ___ Pass, ___ Fail
___ Apply required power.
___ Install newest version of software into the computer. Version #_______
___ Check switch wiring using feature in program (Vision).
___ Check switch lights for correct colors.
___ Set dip switches on back of display I/O. 2 & 3 on for GSI, 2 on for FFI.
___ Put correct model number of dryer into computer.
___ Check LCD for backlighting.
___ Do all operating lights work?
___ Overload amp range: Load _______, Unload _______, Fan #1 _______, #2 _______, #3 _______, #4 _______, #5 _______, #6 _______.
___ Auxiliary overload amp range: Unload _________ Load _________.
___ Check 12 volt output. _________ Volts.
___ Check that grain and plenum temperature read out is correct.
___ Check the SCR drive resistor for the proper size.
___ Check outside light.
___ Check motor rotation: Unload (CCW) _________Load (CW) _________ Metering rolls (CW) _________ Load CCW for FF _________.
___ Ensure Aux contactor engages when load is on
___ Ensure Aux contactor engages when unload is on
___ Check Unload Auger for Excessive Vibration.
___ Metering roll RPM and BPH are displayed and counting.
___ Check 2 speed operation with moisture control on for low speed and off for high speed.
___ Turn pots on main I/O board fully to the right.
___ Set SCR board pots IR to 10 o’clock and CL to 4 o’clock.
___ Adjust minimum voltage for SCR drive to 9 volts @ 0 on pot display for vision set 9 volts @ 50 for (2000 series)
___ Adjust maximum voltage for SCR drive to 180 volts @ 1000 on pot display
___ Check for unload auger clean out time delay after SCR has shut off meter rolls.
___ Check load motor on and off operation with the mercury switch with delay.
___ Check the out of grain timer is working.
___ Check motor running amps: Unload ___________amps. Load _____________amps.
___ Run fans with airswitch on to make sure it is wired correctly.
___ Check the fan motor(s) running amps: Fan #1 _______ Fan #2 _______Fan #3 _______Fan #4 _______Fan #5 _______Fan #6 _______
___ Check total running amps of the dryer: _______amps.
___ Is there a 5 second time delay between each fan start-up.
___ Check 20 second safety on burners with burner on but with no gas attached. #1 ____ #2 ____ #3 ____ #4 ____ #5 ____ #6 _____
Dryer Burner Operation Checklist
___ Adjust the vaporizer coil (LP units only). Burner #1 ______ #2 ______ #3 ______ #4 ______ #5 ______ #6______
___ Operate dryer in continuous flow mode.
___ Do all burners light: Burner #1 ______ #2 ______ #3 ______ #4 ______ #5 ______ #6 ______
___ Adjust gas pressure ______ 3 & 10 lbs. for LP, ______ 2 & 6 lbs. for natural gas.
___ Check burner pipe trains for gas leaks: Burner #1 ______ #2 ______ #3 ______ #4 ______ #5 ______ #6 ______
___ Do all burners cycle from high to low: Burner #1 ______ #2 ______ #3 ______ #4 ______ #5 ______ #6 ______
___ Cycle burner six times by using the burner control switch
___ Cycle burner six times by setting the computer to on/off fire
___ Operate dryer in staged batch mode 2 times.
___ Does moisture control hold at the end of the dry cycle?
___ Video dryer with all motors and burners on.
___ Burn all gas out of pipe train.
Safety Shutdown Checklist
___ Housing high limit for fan #1 ______ #2 ______ #3 ______ #4 ______ #5 ______ #6 ______
___ Vapor high limit for each fan (On LP units only) #1 ______ #2 ______ #3 ______ #4 ______ #5 ______ #6 ______
___ Fixed grain high limits: Lower ____ Middle ____ Upper ____.
___ Check discharge switch with unload running to check discharge vibration and ensure proper shut down
___ Remove grain sensor wires to ensure proper wiring
___ Auxiliary user safety.
___ Plenum high limit for each plenum chamber.
___ Motor overload.
___ Make sure all covers are on boxes and housing high limits
Page 2 of 3