GSI PNEG-1510 User Manual

PNEG-1510
Top Dry 24', 30' and 36' Manual Batch
Construction and Owner ’s Manual
PNEG-1510
Date: 02-18-13
2 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch

Contents

Chapter 1 Safety ..................................................................................................................................................... 5
Safety Guidelines .................................................................................................................................. 5
Chapter 2 Decals .................................................................................................................................................... 6
Roof Damage Warning and Disclaimer ................................................................................................. 6
Chapter 3 Foundation Requirements ................................................................................................................... 9
Foundation Requirements for Top Dry Bins (4.00" Top Dry Bin Corrugation) ...................................... 9
Circular Foundation Form ............................................................................................................. ... ... 10
Octagonal Foundation Form ............................... ... ... .... ... ... ... .... ... ... ... ... .......................................... ... 11
Inline Centrifugal Fan Pad ................................................................................................................... 12
Duct and Drying Fan Pad Optional ..................................................................................................... 13
Frost Free Foundation Top Dry Bins ............................. ... ... ... .... ... ... ... ... .... ... ... ... .... ... ......................... 14
Frost Free Pad .......... ....................................... ... ... ... .... ... ... ... ....................................... ............. ... ... ... 15
Anchor Bolt Placement ........................................................................................................................ 16
Chapter 4 Hardware ............................................................................................................................................. 17
Hardware/Bolting Requirements ......................................................................................................... 17
Location of Accessories ...................................................................................................................... 20
Very Important ..................................................................................................................................... 21
Chapter 5 Sidewall Construction ........................................................................................................................ 22
Sidewall Gauges ....... ....................................... ... ... ... .... ... ... ... ....................................... ... .......... ... ... ... 22
Sidewall Erection Instructions ... ... .......................................... .... ......................................... ....... ... ... ... 23
Caulking Detail .................................................................................................................................... 24
Sidewall Construction Instructions ............................................................. ... ...................................... 25
Lifting Jacks and Brackets .................................................................................................................. 26
Lifting Jack Usage ............................... ... ... ... .... ... ... ... .... ... ... ... ....................................... ............. ... ... ... 27
Chapter 6 Stiffener Details .................................................................................................................................. 28
Stiffener Gauges ....... ....................................... ... ... ... .... ... ... ... ....................................... .......... ... ... ... ... 28
Outside Stiffeners ................................................................................................................................ 29
Top Stiffener Starting Location ......................................................................................................... ... 31
Stiffener Installation and Location ....................................................................................................... 32
Bolting Requirements Two (2) Stiffeners per Sidewall Sheet ............................................................. 33
Stiffener and Seam Locations ............................................................................................................. 34
Chapter 7 “C” Channels ...................................................................................................................................... 35
Stiffener to “C” Channel Bracket Installation....................................................................................... 35
“C” Channel Installation ................ .... ... ... ....................................... ... ... ... .... ... ... ... ................................ 36
Center Collar Assembly ...................................................................................................................... 37
Chapter 8 Installation .......................................................................................................................................... 38
Rafter Installation and Floor Support Angle Attachment ..................................................................... 38
Purlin Installation ................................................................................................................................. 39
Dump Hopper Installation ....................... ... ... .... ... ... ... .... ... ... ... .... ......................................... .......... ...... 42
Floor Sheet Installation ....................................................................................................................... 42
24' Leveling Band Post Installation ..................................................................................................... 43
30' Leveling Band Post Installation ..................................................................................................... 44
36' Leveling Band Post Installation ..................................................................................................... 45
Flashing Bolt Installation ..................................................................................................................... 46
Eave Flashing Installation ................................................................................................................... 46
Eave Flashing Splice ........................................................................................................................... 47
Outer Dump Chutes ............................................................................................................................ 48
Intermediate Dump Chutes ................................................................................................................. 49
24' Leveling Band Location ................................................................................................................. 50
30' Leveling Band Location ................................................................................................................. 51
36' Leveling Band Location ................................................................................................................. 53
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 3
Table of Contents
Chapter 9 Assembly ............................................................................................................................................ 55
Center Cone Assembly ....................................................................................................................... 55
Center Cone Installation ...................................................................................................................... 55
Roof Assembly .................................................................................................................................... 56
Pulley Assembly ................... ... ... ... .... ...................................... .... ... ... ... ... .... ........................................ 57
Dump Chute Chain Assembly ............................................................................................................. 58
Winch Assembly .................................................................................................................................. 60
Fan Entrance Sheets .......................................................................................................................... 61
Top Dry Access Door Assembly (TD-100996) .................................................................................... 62
Detailed Layout for Proper Location of Platforms ............................................................................... 63
Access Door Platform (TDP-5012) ...................................................................................................... 64
Large Platform Assembly for 42" Fan ................................................................................................. 65
42" Fan Diffuser Instructions and Installation ...................................................................................... 68
Cross Over Platform Assembly (for use with stairs) (TDP-5013) ........................................................ 70
Perforated Center Band ...................................................................................................................... 71
Optional Rotary Switch Roof Locations ............................................................................................... 72
Optional Rotary Switch Panel Locations ............................................................................................. 72
Optional Installation of Roof Mounted Level Switches ........................................................................ 73
Optional Installation of Wall Mounted Rotary Switches ............................... ............................. ........... 74
Transition Installation (TR-4734) ......................................................................................................... 75
Transition Assembly (TR-4734) .......................................................................................................... 76
Chapter 10 Accessories ...................................................................................................................................... 77
2 Ring Door Installation Instructions .................................................................................................. 77
2 Ring Door Assembly ....................................................................................................................... 78
Optional Bin Step Assembly (WD-042) ............................................................................................. 80
Base Angle ........................................................................................................................................ 81
Base Stiffener Shim ........................................................................................................................... 81
Chapter 11 Warranty ............................................................................................................................................ 83
4 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch

1. Safety

DANGER
WARNING
CAUTION
NOTICE
This is the safety alert symbol. It is used to alert you to potential personal injury hazards. Obey all safety messages that follow this symbol to avoid possible injury or death.
WARNING indicates a hazardous situation which, if not
avoided, could result in death or serious injury.
CAUTION, used with the safety alert symbol, indicates a hazardous situation which, if not avoided, could result in minor or moderate injury.
NOTICE is used to address practices not related to personal injury.
DANGER indicates a hazardous situation which, if not avoided, will result in death or serious injury.
Safety Guidelines
This manual contains information that is important for you, the owner/operator, to know and understand. This information relates to protecting personal safety and preventing equipment problems. It is the responsibility of the owner/operator to inform anyone operating or working in the area of this equipment of these safety guidelines. To help you recognize this information, we use the symbols that are defined below. Please read the manual and pay attention to these sections. Failure to read this manual and its safety instructions is a misuse of the equipment and may lead to serious injury or death.
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 5

2. Decals

The manufacturer does not warrant any roof damage caused by excess ive v acuum or internal pressure from fans or other air moving systems. Adequate ventilation and/or “makeup air” devices should be provided for all powered air handling systems. The manufacturer does not recommend the use of downward flow systems (suction). Severe roof damage can result from any blockage of air passages. Running fans durin g high humidity/cold weather conditions can cause air exhaust or intake ports to freeze.
Roof Damage Warning and Disclaimer
CAUTION!
Excessive vacuum (or pressure) may damage roof. Use positive aeration system. Make sure all roof vents are open and unobstructed. Start roof fans when supply fans are started. Do not operate when conditions exist that may cause roof vent icing.
DC-969
6 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
2. Decals
Rotating flighting will
kill or dismember.
Flowing material will
trap and suffocate.
Crusted material will
collapse and suffocate.
Keep clear of all augers. DO NOT ENTER this bin!
Failure to heed these
warnings will result in
serious injury or death.
If you must enter the bin:
1. Shut off and lock out all power.
2. Use a safety harness and safety line.
3. Station another person outside the bin.
4. Avoid the center of the bin.
5. Wear proper breathing equipment or respirator.
DC-GBC-1A
ATTENTION: The decal shown below should be present on the outside of the door cover of the 2 ring, 24" porthole door cover and the roof manway cover. If a decal has been damaged or is missing in any of these locations, contact the manufacturer for a free replacement decal.
GSI Decals
1004 E. Illinois St. Assumption, IL. 62510 Phone: 1-217-226-4421
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 7
2. Decals
Failure to heed these warnings
could result in serious injury, death,
structural damage or collapse of tank.
1. Use CENTER FLOOR OUTLET ONLY until NO grain remains above this outlet.
2. Side floor outlets to be used ONLY when above condition is satisfied.
3. Lock all side floor outlets to avoid accidental premature use.
4. See manufacturers instructions for proper use of factory supplied sidedraw (wall) discharge systems.
UNLOADING INSTRUCTIONS:
DC-GBC-2A
WARNING
DON’T
DO
ATTENTION: The decal shown below should be present on the outside of the door cover of the 2 ring, 24" porthole door cover and the roof manway cover. If a decal has been damaged or is missing in any of these locations, contact the manufacturer for a free replacement decal.
GSI Decals
1004 E. Illinois St. Assumption, IL. 62510 Phone: 1-217-226-4421
8 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch

3. Foundation Requirements

Foundation Requirements for Top Dry Bins (4.00" Top Dry Bin Corrugation)
Requirements
The following foundation recommendations are a revision to earlier manuals distributed by the GSI Group.
NOTE: There are changes in founda tion dimensions from past publications. These dimensions are critical
to the proper installation and function of each foundation.
Selecting the Proper Site
The selected site should be level, firm and free from underlying debris. The bin can be installed satisfactorily on slopes, but as the slope increases, additional labor and materials are required for the foundation. The concrete foundation surface must be level. If some fill is required, it should be watered and tamped thoroughly to prevent uneven settling from the weight of th e bin. Naturally, the site must allow convenient access for easy loading and unloading, plus provide additional space for future units. Also consider the positioning of handling equipment, availability of electricity and the placement of fans, heaters and gas tanks.
Scribe the Diameter
Having determined the center of the site, drive a small 2 x 4 in the ground to mark the center point of the foundation. The top of the stake should be the same height as the finished foundation will be. Using one large spike, nail a straight 2 x 4 (approximately 2' longer than the radius of the bin) to the top of the center spike. The swiveling 2 x 4 will act as a compass, enabling you to scribe the correct diameter of the foundation and later locate the anchor and stiffener bolt locations. (NOTE: Making the 2 x 4 2' longer than the radius allow the 2 x 4 to also be used as a leveling device and for pulling concrete.) (See Figure 3A.)
Figure 3A
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 9
3. Foundation Requirements
Circular Foundation Form
Footing trench
Carpenter’s level
Figure 3B
Prepare the Foundation
Having scribed the diameter of the foundation, proceed by digging the footing of the foundation. This consists of a large circular trench dug just inside the foundation line. (Refer to foundation details for necessary information.) Once the footing has been dug, you are ready to build the forms. It is important that the form be rigid enough to hold its shape against the poured concrete. Also, the foundation must be flat. Sloped floors cannot be used in drying bins. A carpenter’s level placed on t op of the 2 x 4 will enable you to set the top of the forms to match the top of the center stake. Check the form work with a transit to ensure a uniform elevation for the entire foundation. (See Figure 3B.)
10 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
3. Foundation Requirements
Octagonal Foundation Form
There are two (2) styles of foundation forms commonly used. The first is the circular form depicted in
Figure 3B on Page 10. The second style can be made of 2" x 8" boards set into a square with corners
blocked off to form an octagon. (See Figure 3C.) This eight (8) sided form will approximate a circle and can be constructed quite easily.
When the foundation form is completed install reinforcement rods by either welding or wiring in place. Place 2" of compacted sand on the inside level of the foundation. The sand is then covered with a 4 mil plastic moisture barrier. 6" x 6" Wire mesh (two (2) mats), covering the entire area of the foundation, completes the preparation of the bin’s foundation. You are now ready to begin pouring concrete.
NOTE: All concrete is to have a minimum compressive strength of 3000 PSI at 28 days.
Figure 3C
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 11
3. Foundation Requirements
Inline Centrifugal Fan Pad
Placement of the Fan Pad: GSI Transitions/Fans only.
If a fan is to be installed, refer to Figure 3D to determine the concrete pad size.
1. The top of this pad should be level with the top of the bin’s foundation.
2. Recommended pad thickness is 4" minimum.
3. Front of pad should be perpendicular to bin wall.
4. Pad for heater not required.
IMPORTANT: Fan pad and fan must be leveled an d smooth for proper operation. Vibration problems can
result from improper fan leveling.
Figure 3D
12 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
3. Foundation Requirements
Duct and Drying Fan Pad Optional
Placement of the Duct Fan Pad: GSI Top Dry Duct System only.
Refer to Figure 3E to determine the duct pad size.
1. The top of this pad should be level with the top of the bin’s foundation.
2. Recommended pad thickness is 4" minimum.
3. Front of pad should be perpendicular to bin wall.
Figure 3E
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 13
3. Foundation Requirements
Frost Free Foundation Top Dry Bins
Diameter of Bin: 24' Corrugation : 4.00"
Ring # B N
6 1'-1" 2 12'-9" 900 600 200 13
7, 8 1'-9" 2 12'-9" 900 600 200 15
9, 10 2'-6" 3 13'-2" 900 600 400 18
Diameter of Bin: 30' Corrugation : 4.00"
Ring # B N
6 1'-2" 2 15'-9" 1400 900 200 19
7, 8 1'-10" 2 15'-10" 1400 900 200 21
9, 10 2'-8" 3 16'-1" 1400 900 500 25
11 3'-8" 4 16'-5" 1400 900 700 29
Outside
Radius
Outside
Radius
Sq. Ft. Mesh
6 x 6 - 6/6
Sq. Ft. Mesh
6 x 6 - 6/6
Optional #4
18" x 18" Grid (Ft.)
Optional #4
18" x 18" Grid (Ft.)
Length #6
Bar (Ft.)
Length #6
Bar (Ft.)
To tal Cu. Yds.
Concrete
Total Cu. Yds.
Concrete
Diameter of Bin: 36' Corrugation : 4.00"
Ring # B N
6 1'-3" 2 18'-9" 2000 1300 300 26
7, 8 2'-0" 2 18'-11" 2000 1300 400 30
9, 10 2'-10" 3 19'-0" 2000 1300 600 33
11, 12 3'-11" 4 19'-6" 2000 1300 900 39
Outside
Radius
Sq. Ft. Mesh
6 x 6 - 6/6
Optional #4
18" x 18" Grid (Ft.)
Length #6
Bar (Ft.)
Total Cu. Yds.
Concrete
14 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
3. Foundation Requirements
Frost Free Pad
NOTES:
1. Foundation site should be well drained and free of vegetation or debris.
2
2. Foundation design is based on a minimum soil bearing capacity of 3000 lbs/ft capacity is in doubt, contact a local soil testing engineer.
3. Concrete shall have a minimum compressive strength of 3000 PSI at 28 days.
4. Requirements for reinforcement do not include overlap.
5. Lap all circumferential bars 35 bar diameters and stagger all laps in plan 3'-0".
6. All material used for backfill inside the ring wall should be a clean, well graded, crushed stone or
sand-gravel mixture. Backfill should be placed in 6" lifts and well compacted.
. If soil bearing
Figure 3F
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 15
3. Foundation Requirements
Anchor Bolt Placement
Having poured and leveled the concrete, use the center stake and straight 2" x 4" again to find the bolt circle radius for the outside hold-down brackets. Select a starting point and stretch a pre-measured chord along the imaginary circle formed by the bolt circle radius. Take into consideration the placement o f these bolts so as not to interfere with the positions of bin doors and transitions. (Refer to below Chart for necessary radius and chord lengths.) Take the time and work carefully since accuracy is important.
Work both directions from first anchor bolt location, this will help eliminate possible error in laying out anchor bolts. On larger bins sight across starting anchor bolt and center pin and place anchor bolt on opposite side of anchor bolt radius. From this point you can work both directions from both anchor bolts.
NOTE: Top edge of slab where the bin wall sets must be held to within 1/8" of level.
Bin
Diameter
24' 12' - 2-7/8" 16 4' - 9-5/16" 30' 15' - 2-11/16" 20 4' - 9-1/8" 36' 18' - 2-1/2" 24 4' - 9-1/16"
“B” Bolt
Circle Radius
# of
Anchors
“E” Chord
Distance
Figure 3G Anchor Bolt
16 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
Hardware/Bolting Requirements
NOTE: Grade 2 bolts are designated with a plain head.
NOTE: Grade 5 bolts are designated by three (3) slash marks on the head.
All 5/16" diameter bolts are to be grade 5 or higher.
NOTE: Grade 8 bolts are designated by six (6) slash marks on the head.
NOTE: Grade 8.2 bolts are designated by six (6) slash marks on the head in a
sunrise pattern. All 3/8" diameter bolts are to be grade 8 or 8.2.
Under no condition shall any other bolts be substituted for those supplied by GSI Group.

4. Hardware

IMPORTANT: Do not tighten bolts to exceed the torque specifications listed below.
Torque (Ft. lbs.)
CAUTION
IMPORTANT:
Bolt Size
Minimum Maximum
5/16"-18 15 20 3/8"-16 35 42 7/16"-14 65 72 1/2"-13 95 105
Hardware Usage - 20 Gauge - 15 gauge sidewall sheets, use 5/16" x 3/4" bolts and
nuts (S-275). 14 Gauge and 13 gauge sidewall sheets, use 5/16" x 3/4" bolts and
nuts (S-275).
Use 5/16" x 1-1/4" (S-277) for attaching floor flashing to the sidewall.
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 17
4. Hardware
0.3125" x 0.750" Pre-assembled with a steel backed neoprene washer.
This bolt is used to connect horizontal and vertical seams for 13 gauge and thinner sidewall sheets to each other and to bolt the stiffeners to the sidewall sheets. It is also used in attaching roof panels to the top sidewall sheet and attaching roof panels and flashing to the center collar.
0.3125" x 1.250" Pre-assembled with a steel backed neoprene washer.
This bolt is primarily used to connect roof panels together where they overlap. It is also used at the bottom of the flat bottomed bins to attach the base angle to the sidewall sheet. A small number of these are provided for joints and FC-42076 splice plates for the stiffeners to sidewall connection.
Refer to Top Dry Tank Bolting Requirements for Complete Bolt Usage
18 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
Refer to Top Dry Tank Bolting Requirements for Complete Bolt
0.375" x 1.000" Hex flanged head without a plastic sealing washer.
This bolt is used to splice the stiffeners together on the flanges. A steel flat washer is used on the nut side of the connection. They are also used on “C” channel splices and mounting “C” channel to wall bracket.
0.375" x 1.500" Hex flanged head without a plastic sealing washer.
This bolt is used to attach the wall bracket to the sidewall and stiffener. A steel flat washer is used on the nut side of the connection.
Usage (Continued)
4. Hardware
NOTE: The only washers shipped loose with the bins are the steel flat washers. The 5/16" steel flat washer
(S-845) is used where the base angle attaches to the sheet and some are used at the main e ave clips. The 3/8" steel flat washers (S-248) are used at the stiffener splices and some are used in
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 19
the roof rafter splices.
4. Hardware
Location of Accessories
Below is a typical Top Dry bin layout showing suggested locations of Top Dry accessories. When locating the manway be sure the outside ladder will not interfere with other accessories below. Roof vents sh ould be spaced evenly around the roof. (Quantity will vary with individual systems.) (See Figure 4A.)
NOTE: The Top Dry system should be provided with a dependable equipment ground.
Figure 4A
20 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
Very Important
4. Hardware
Figure 4B Sheet Shown as Viewed from the Inside of Bin
All 4.00" corrugated sidewall sheets must be placed correctly.
4.00" corrugated sidewall sheets have a top and bottom.
All
Failure to observe this will not allow the door to fit properly. Carefully review the erection manual and place sidewall sheets as shown in Figure 4B.
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 21

5. Sidewall Construction

Sidewall Gauges
Tank
Diameter
(Ft.)
24 5 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga.
24 6 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga.
24 7 18 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga.
24 8 18 Ga. 18 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga.
24 9 17 Ga. 18 Ga. 18 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga.
24 10 17 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga. 20 Ga.
30 5 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
30 6 18 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
30 7 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
30 8 17 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
30 9 17 Ga. 17 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
30 10 16 Ga. 17 Ga. 17 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
30 11 16 Ga. 17 Ga. 17 Ga. 17 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
36 5 17 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
# of Rings
of Sidewall
Sidewall
Base Ring
Sidewall
Ring #2
Sidewall
Ring #3
Sidewall
Ring #4
Sidewall
Ring #5
Sidewall
Ring #6
Sidewall
Ring #7
Sidewall
Ring #8
Sidewall
Ring #9
Sidewall Ring #10
Sidewall Ring #11
36 6 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
36 7 16 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
36 8 16 Ga. 16 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
36 9 16 Ga. 16 Ga. 16 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
36 10 15 Ga. 16 Ga. 16 Ga. 16 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
36 11 14 Ga. 15 Ga. 15 Ga. 16 Ga. 16 Ga. 17 Ga. 18 Ga. 18 Ga. 18 Ga. 18 Ga. 20 Ga.
NOTE: Fan entrance sheets and plenum access door sheets are located in the second ring fr om the top
of the bin, just below the upper drying floor.
22 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
5. Sidewall Construction
Sidewall Erection Instructions
Before bolting the sidewall sheets together, check that you have the proper gauge steel for the first ring. The higher gauge numbers denote the thinner materials. (For example, 22 gauge material is thinner than 14 gauge.) In erecting most grain bins the thinnest material usually goes on top, therefore the first sid ewall ring you assemble will be the top ring of the bin. Check the various gauges of the bin with the color code
chart and begin building accordingly. REMEMBER...... Assemble the top ring first.
Color Code Chart
Gauge Color Code Gauge Color Code
22 White 14 Green 20 Red 19 Black/Yellow 12 Black 18 Orange 17 Pink/Light Blue 10 Light Blue 16 Blue 15 Brown/Red 8 Yellow
13 Yellow/Blue
11 Pink
9 Blue/Orange
Once you have selected the proper gauge material, begin assembling all sidewall sheets in the following manner: Standing on the inside the bin, place the left panel to the inside with the right panel to the outside.
(See Figure 5A.) Check to see that the sidewall shee t is “Right side up”. Refer to Page 26 for details.
Figure 5A
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 23
5. Sidewall Construction
Caulking Detail
NOTE: The rope caulking is installed before each sheet is assembled. Apply rope caulking between the
last vertical row of bolts and edge of outside sheet. There is sufficient caulking for all vertical seams on storage and drying bins. Wipe sheet clean where caulking is to be applied.
Using correct size bin bolts throughout, begin assembling sidewall sheets end to end (overlapping the same way throughout) until the ring is completed. All body sheet bolts are to be installed with the bolt head and its neoprene washer to the outside and the nut on the inside. Do not tighten bolts until all sheets are assembled and form a complete ring. Attach lifting brackets to stiffener bolt holes. These straps, coupled to the jacks will enable you to later elevate the bin. Now, tighten the bolts in sequence, starting from the center and working to the edge in both directions. This permits the sidewall sheets to draw-up evenly. Complete 1 ring and stop. You are now ready to assemble the roof. Refer to roof erection manual for roof assembly instructions located in roof hardware box. (See Figure 5B.)
Figure 5B Standard Sidewall Sheet as Viewed from Inside
24 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
5. Sidewall Construction
Sidewall Construction Instructions
Figure 5C
Using correct size bin bolts throughout, begin assembling sidewall sheets end to end (overlapping the same way throughout) until the ring is complete. All body sheet bolts are to be installed with the bolt head and its neoprene washer to the outside and the nut on the inside. Do n ot tighten bolts u ntil all sh eets are assembled and form a complete ring. Tighten the bolts in sequence, starting from the center and work to the edge in both directions. This permits the sidewall sheets to draw-up evenly.
After assembling the second ring, lift the top ring sheets in place, add top stiffeners, build the Top Dry floor, then the roof.
NOTE: The sidewall sheets used for the top ring are punched to accommodate the eave flashing bolts. NOTE: The fan entrance sheet and access door are located in the second ring. Attach the top stiffe ners,
leaving out the seven (7) bolts indicated in Figure 5D at each stiffener location. Install the flashing bolts from the outside.
Figure 5D Top 2 Rings
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch 25
5. Sidewall Construction
Lifting Jacks and Brackets
NOTE: The number of lifting jacks required is best determined by personal experience. Factors such as
bin size, soil compaction, wind velocity, jack design, etc., are all to be considered when deciding how many to use. If in doubt, use one jack on every other stiffener. GSI recommends heavy duty jacks rated at 6000 lbs. or more. (See Figure 5E.)
Figure 5E
26 PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
Loading...
+ 58 hidden pages