Glow-worm Flexicom 12hx, Flexicom 15hx, Flexicom 18hx, Flexicom 30hx, 35hx Installation And Servicing

...
1
Installation and Servicing
www.glow-worm.co.uk
Flexicom
18hx
High Efciency
Condensing
G.C. No. 41-315-42
12786
15hx
G.C. No. 41-315-29
12hx
G.C. No. 41-315-28
24hx
G.C. No. 41-315-61
30hx
G.C. No. 41-315-67
35hx
G.C. No. 41-315-68
2
Thank you for installing a new Glow-worm appliance in your home.
Glow-worm appliances are manufactured to the very highest standard so we are pleased to offer
our customers a Comprehensive Guarantee.
This product is guaranteed for 24 months from the date of installation or 30 months from the date
of manufacture, whichever is the shorter, for parts and labour.
The second year of the parts guarantee, from the beginning of the 13th month onwards after
installation or manufacture, is conditional upon the boiler having been serviced by a CORGI
registered gas installer,
in accordance with the manufacturer’s recommendations. We strongly recommend regular
servicing of your gas appliance, but where the condition is not met, any chargeable spare parts or
components issued within the applicable guarantee period still benet from a 12 month warranty
from the date of issue by the manufacturer.
We recommend you complete and return as soon as possible your guarantee registration card.
If your guarantee registration card is missing you can obtain a copy or record your registration by
telephoning the Glow-worm Customer Service number 01773 828100.
Guarantee Registration
Customer Service:
01773 828100
Technical Helpline:
01773 828300
General and Sales enquiries:
Tel. 01773 824639
Fax: 01773 820569
To register your Glow-worm appliance
call:
0800 0732142
3
These instructions consist of, Installation, Servicing, Fault Finding, Replacement of Parts
and Spares. The instructions are an integral part of the appliance and must, to comply
with the current issue of the Gas Safety (Installation and Use) Regulations, be handed to
the user on completion of the installation.
CONTENTS DESCRIPTION SECTION PAGE
Warnings 4 Important Information 4 Statutory Requirements 5 Boiler Design 6 Safety Devices 6 Servicing, Maintenance and Spare Parts 6
Boiler Specication 1 7
Boiler Dimensions and Hydraulic Schematic 2 8 Boiler Location, Clearances and Ventilation 3 9 Flue Options and Terminal Clearances 4 10 Water Systems 5 12
• General 5 12
• Open Vented 5 13
• Sealed Systems 5 14 Installation Preparation 6 16 Boiler Fixing 7 17 Gas/Water and Appliance Connection 8 18 Condensate Connections 9 18 Flue Length Preparation and Installation 10 20 Electrical Connection 11 36 Commissioning 12 38
Servicing 13 40 Fault Finding 14 45 Replacement of Parts 15 51 Spare Parts 16 56 Manual Handling 17 57 Declaration of Conformity 18 58
INTRODUCTION
INSTALLATION
MAINTENANCE
4
WARNINGS
Gas Leak or Fault
Turn off the gas emergency control valve immediately. Eliminate all sources of ignition, i.e.smoking, blowlamps, hot
air guns etc. Do not operate electrical lights or switches either on or off. Open all doors and windows,ventilate the
area.
Sheet Metal Parts
This boiler contains metal parts (components) and care should be taken when handling and cleaning, with particular
regard to edges.
Sealed Components
Under no circumstances must the User interfere with or adjust sealed parts.
Gas Category
This boiler is for use only on G20 natural gas.
Gas Safety (Installation and Use)
Regulations
In your own interests and that of safety, it is the Law that ALL gas appliances are installed by a competent person in accordance with the current issue of these regulations.
Control of Substances Hazardous to Health
Under Section 6 of The Health and Safety at Work Act 1974, we are required to provide information on substances hazardous to health. The adhesives and sealants used in this appliance are cured and give no known hazard in this state.
Manual Handling
With regards to the “Manual Handling Operations, 1992 Regulations”, the appliance exceeds the recommended weight for a one man lift, refer to section 17 for more information. The handling of the boiler may involve lifting, pushing and pulling, the use of a sack truck may be required. The following handling techniques and precautions should be considered:
- Grip the boiler at its base
- Be physically capable
- Use safety clothing where appropriate, e.g. gloves, safety footwear. Ensure safe lifting techniques are used
- Keep back straight.
- Avoid twisting at the waist.
- Avoid upper body/top heavy bending.
- Always grip using the palm of the hand.
- Use designated hand holds.
- Keep load as close to body as possible.
- Always use assistance if required.
Electrical Supply
The boiler MUST be earthed.
All system components shall be of an approved type and all wiring to current I.E.E. wiring regulations. External wiring must be correctly earthed, polarised and in accordance with the relevant standards.
In GB, this is BS 7671. In IE, this is the current edition of ETCI rules.
The boiler MUST be connected to a permanent 230V ac, 50Hz supply. Connection of the whole electrical system of the boiler, including any heating controls, to the electrical supply MUST be through one common isolator and must be fused 3 Amp maximum. Isolation should be by a double pole switched fused spur box, with a minimum gap of 3mm for both poles. The fused spur box should be readily accessible and preferably adjacent to
the appliance. It should be identied as to its use.
Alternatively connection can be made through an unswitched shuttered socket and 3A fused 3-pin plug both to the current issue of BS 1363, provided they are not used in a room containing a bath or shower. Wiring to the boiler must be PVC 85OC insulated cable, not less than 0.75mm2 (24/0.20mm).
Testing and Certication
This boiler is tested and certicated for safety and
performance. It is, therefore, important that no alteration is made to the boiler, without permission, in writing, by Glow­worm. Any alteration not approved by Glow-worm, could invalidate
the certication, boiler warranty and may also infringe the
current issue of the statutory requirements.
Important Information
5
CE Mark
This boiler meets the requirements of Statutory Instrument,
No. 3083 The Boiler (Efciency) Regulations, and therefore is
deemed to meet the requirements of Directive 92/42/EEC on
the efciency requirements for new hot water boilers red with
liquid or gaseous fuels.
Type test for purposes of Regulation 5 certied by: Notied
body 0087.
Product/production certied by: Notied body 0086.
The CE mark on this appliance shows compliance with:
1. Directive 90/396/EEC on the approximation of the laws of the Member States relating to appliances burning gaseous fuels.
2. Directive 73/23/EEC on the harmonisation of the Laws of the Member States relating to electrical equipment designed for use within certain voltage limits.
3. Directive 89/336/EEC on the approximation of the Laws of the Member States relating to electromagnetic compatibility.
IMPORTANT
Where no British Standards exists, materials and equipment
should be t for their purpose and of suitable quality and
workmanship. The installation of this boiler must be carried out by a competent person in accordance the rules in force in the countries of destination. Manufacturer’s instructions must not be taken as overriding statutory requirements.
Statutory Requirements
In GB, the installation of the boiler must comply with the requirements of the current issue of BS6798 and be carried out by a competent person as described in the following regulations: The manufacturer’s instructions supplied. The Gas Safety (Installation and Use) Regulations. The appropriate Buildings Regulations either The Building Regulations, The Building Regulations (Scotland),The Building Regulations (Northern Ireland). The Water Fittings Regulations or Water byelaws in Scotland. The Health and Safety at Work Act, Control of Substances Hazardous to Health (COSHH). The Current I.E.E. Wiring Regulations.
Where no specic instructions are given, reference should be
made to the relevant British Standard Code of Practice. In IE, the installation must be carried out by a competent person and installed in accordance with the current edition of I.S.813 “Domestic Gas Installations”, the current Building Regulations and reference should be made to the current ETCI rules for Electrical Installation. GB: the following Codes of Practice apply: BS4814, BS6798, BS5440 Part 1 and 2, BS5546 Part 1, BS5449, BS6891, BS6700, BS7074 Part 1 and 2, BS7593, BS7671.
IE: I.S.813, BS5546, BS 5449, BS 7074, BS 7593. NOTE: For further information, see the current issue of the
Building Regulations, approved document L1 ( in the UK) and the following current issues of:
1) Central heating system specication (CheSS)
and
2) Controls for domestic central heating system and hot water. BRECSU.
Statutory Requirements
Gas Supply
The gas installation must be in accordance with the relevant standards.
In GB, this is BS6891. In IE, this is the current edition of I.S.813 “Domestic Gas
Installations”. The supply from the governed meter must be of adequate size to provide a steady inlet working pressure of 20mbar (8in wg) at the boiler. On completion, test the gas installation for tightness using the
pressure drop method and suitable leak detection uid, purge
in accordance with the above standard.
Domestic Hot Water
All domestic hot water circuits, connections, ttings must be
in accordance with the relevant standards and water supply regulations. GB: Guidance G17 to G24 and recommendation R17 to R24 of the Water Regulations Guide. IE: The current edition of I.S.813 “Domestic Gas Installations”.
Heating System
In GB, it is necessary to comply with the Water Supply (Water Fittings) Regulations 1999 (for Scotland, the Water Byelaws 2000, Scotland). To comply with the Water regulations your attention is drawn to: The Water Regulations guide published by the Water Regulations Advisory Service (WRAS) gives full details of the requirements. In IE, the requirements given in the current edition of I.S.813 “Domestic Gas Installations” and the current Building Regulations must be followed.
6
Boiler Design
Boiler Design
These boilers are designed to provide central heating from a fully pumped open vented or sealed water system and domestic hot water using a fully indirect cylinder. Once the controls are set the boiler operates automatically.
Range Rating
The boilers are fully modulating for central heating, and it is therefore not necessary to range rate the boiler. However, if desired, it is possible to range rate the boiler between 10 and Max. output (according to the model), in 1kW increments, refer to section 12.
Electrical Supply Failure
The boiler will not work without an electrical supply. Normal operation of the boiler should resume when the electrical supply is restored. Reset any external controls, to resume normal operation of the central heating.
If the boiler does not resume normal operation press the reset button. If the boiler does not resume normal operation after this call your Installation/Servicing company or Glow-worm service.
Overheating Safety
The boiler software is designed to recognise the potential for an overheat lockout and will shutdown before this happens. To restart the boiler, press the reset button on the controls fascia.
If the boiler fails to resume normal operation and all external controls are calling for heat, then call your Installation/ Servicing company or Glow-worm service.
Safety Devices
Frost protection
The appliance has a built in frost protection device that protects the boiler from freezing. With the gas and electric supplies ON and irrespective of any room thermostat setting, the frost protection device will operate the pump when the temperature of the boiler water falls below 8oC. A timer is used so that the temperature can be checked periodically. After 10 minutes the pump will be stopped if the temperature is higher than 10oC or has already reached 35oC. The burner will activate if the boiler temperature does not reach 10oC after 30 minutes or at any time if the temperature drops to 5oC. The burner will switch off when the temperature reaches 35oC.
Condensate Drain Blockage
As a safety feature the boiler will stop working if the condensate drain becomes blocked. During freezing conditions this may be due to the forming of ice in the condense drain external to the house. Release an ice blockage by the use of warm cloths on the pipe. The boiler should then restart.
Condensate Drain
A plastic drain pipe must be tted to allow discharge of
condensate to a drain. Condensate should, if possible, be discharged into the internal household draining system. If this is not practical, discharge can be made externally into the household drainage system or a purpose designed soak away, see section 8 for more details.
Pluming from ue terminal
Like all condensing boilers this appliance will produce a plume
of condensation from the ue terminal in cool weather. This is due to the high efciency and hence low ue gas temperature
of the boiler. This is normal and not an indication of a fault.
Servicing, Maintenance and Spare Parts
Servicing and Maintenance
To ensure the continued efcient and safe operation of the
boiler it is recommended that it is checked and serviced as necessary at regular intervals. The frequency of servicing will depend upon the particular installation conditions and usage. If this appliance is installed in a rented property there is a duty of care imposed on the owner of the property by the current issue of the Gas Safety (Installation and Use) Regulations, Section 35. Servicing/maintenance should be carried out by a competent person in accordance with the rules in force in the countries of destination. To obtain service, please call your installer or Glow-worm’s own service organisation using the telephone number on the inside front cover of this literature.
“Benchmark” scheme
Glow-worm support the Benchmark initiative. It is very important that the Installation, Commissioning and Service Record is completed by the installation engineer and handed over to the user.
Spare Parts
Remember, when replacing a part on this appliance, use only spare parts that you can be assured conform to the
safety and performance specication that we require. Do not
use reconditioned or copy parts that have not been clearly authorised by Glow-worm. If a part is required contact Glow-worm’s own service organisation using the telephone number on the inside front cover of this booklet. Please quote the name of the appliance, this infomation will be on the name badge on the front of the appliance. If in doubt seek advice from the local gas company or Glow­worm’s own service organisation using the telephone number on the inside front cover of this booklet.
7
1 Boiler Specication
14730
Diagram 1.2
BOILER SPECIFICATION
Lift weight
12hx
to
30hx
25kg (55Ib)
35hx
26.5kg (58.4Ib)
Total weight (installed)
12hx
to
30hx
28kg (62Ib)
35hx
29.5kg (65Ib)
Gas connection Ø O.D. 15mm. copper
Heating Flow and Return connection Ø O.D. 22mm. copper
Condensate connection Ø I.D. 21.5mm. plastic
Electrical supply 230V~50Hz
Electrical rating 60W fused 3A
IP clasification IPX4D
Internal fuse rating on main PCB 2A
Gas supply (governed meter only) and cat. G20 natural gas
Gas Category I
2H
natural gas
Inlet gas working pressure 20mbar
Burner % CO2 case on 9.3 nominal
Burner % CO2 case off 9.3 nominal
12hx 15hx 18hx 24hx 30hx 35hx
m3/h 1.28 1.60 1.93 2.58 3.26 3.8
ft3/h 45 56.5 68.1 90.9 115 134
m3/h 0.99 0.99 0.99 0.99 0.99 0.99
ft3/h 35.1 35.1 35.1 35.1 35.1 35.1
PLEASE REFER TO THE COMMISSIONING SECTION
max. 12.1 15.1 18.2 24.4 30.8 35.8
min. 9.4 9.4 9.4 9.4 9.4 9.4
max. 12 15 18 24 30 35.0
min. 9.3 9.3 9.3 9.3 9.3 9.3
90.7 90.5 90.4 90.3 90.3 90.0
Approximate max. gas rate after 10 mins. from cold
Heat input NETT Q = kW
Heat output P = kW
Approximate min. gas rate after 10 mins. from cold
Approximate gas rate at part load.
SEDBUK rating
Band A
Flue type (all models) C13, C33, C53
NOx (all models) Class 5
8
2 Boiler Dimensions and Hydraulic Schematic
13938
Diagram 2.2
2.1 Boiler Dimensions and Hydraulic Schematic
All dimensions are given in millimetres (except as noted).
The general arrangment of the boiler is shown in diagram 2.1. and the hydraulic and gas schematic, diagram 2.2.
The data label is positioned on the front of the inner casing panel.
13937
Diagram 2.1
9
3 Boiler Location, Clearances and Ventilation
3.1 Location
This boiler is not suitable for outdoor installation. This boiler may be installed in any room, although particular attention is drawn to the installation of a boiler in a room containing a bath or shower where reference must be made to the relevant requirements. This boiler is suitable for installation in bathroom zones 2 and
3. In GB this is the current I.E.E. WIRING REGULATIONS and BUILDING REGULATIONS. In IE reference should be made to the current edition of I.S.813 “Domestic Gas Installations” and the current ETCI rules.
3.2 Clearances
The boiler should be positioned so that at least the minimum operational and servicing clearances are provided, see diagram
3.1.
Increased clearances would be benecial for the installation. Where external access is not practicable, for ue installations
consideration should be given for the space required to insert
the ue internally, which may necessitate the clearance to be greater than those specied in diagram 3.1.
3.3 Timber Frame Buildings
If the boiler is to be installed in a timber frame building it should
be tted in accordance with the Institute of Gas Engineers
document IGE/UP/7/1998. If in doubt seek advice from the local gas undertaking or Glow-worm.
3.4 Combustible Material
The boiler and ue are suitable for installation onto and
through combustible materials provided that:-
1) Minimum 5mm clearance is maintained around the
circumference of the ue (air intake).
2) The combustible surface and xings are suitable for
supporting the load.
3) The minimum clearances from the boiler case are maintained.
3.5 Room Ventilation
The boiler is room sealed so a permanent air vent is not required.
3.6 Cupboard or Compartment Ventilation
Due to the high efciency and hence low casing temperature
of this boiler, cupboard or compartment ventilation is not necessary. Leave existing air vents.
12792
Diagram 3.1
10
4 Flue Options and Terminal Clearances
Top horizontal telescopic ue (Ø60/100) Part No. A2043600 - Section 10, page 20
Top horizontal standard ue (Ø60/100) Part No. A2043400 - Section 10, page 24
Twin Flue
Twin Flue Adapter, concentric ue (Ø80)
Part No. A2011000 - Section 10, page 32
Diagram 4.1
Plume Management Kit
basic set, white, concentric ue
(Ø60/100) - Part No. A2044100 for use with Part No. A2043400 and Part No. A2043600 - Section 10, page 35
Vertical Flue
Vertical Flue Adapter, concentric ue (Ø60/100)
Part. No. A2024600 - Section 10, page 29
Vertical ue terminal kit, concentric ue (Ø60/100)
Part. No. 2000460480 - Section 10, page 29
Direct rear telescopic ue (Ø60/100) Part No. A2043500 - Section 10, page 28
11
HORIZONTAL FLUES
A DIRECTLY BELOW AN OPENING, AIR BRICK, OPENING WINDOWS 300 B ABOVE AN OPENING, AIR BRICK, OPENING WINDOWS 300 C HORIZONTALLY TO AN OPENING, AIR BRICK, OPENING WINDOWS 300 D BELOW GUTTER, DRAIN/SOIL PIPE 25 E BELOW EAVES 25 F BELOW A BALCONY OR CAR PORT 25 G FROM VERTICAL DRAIN PIPES AND SOIL PIPES 25 H FROM INTERNAL/EXTERNAL CORNERS 25
H* TO A BOUNDARY ALONGSIDE THE TERMINAL 300 I ABOVE ADJACENT GROUND OR BALCONY LEVEL 300
J* FROM SURFACE OR A BOUNDARY FACING THE TERMINAL 600 K FACING TERMINALS 1200 L FROM OPENING (DOOR/WINDOW) IN CAR PORT INTO DWELLING 1200 M VERTICAL FROM A TERMINAL 1500 N HORIZONTALLY FROM A TERMINAL 300
VERTICAL FLUES
P FROM ANOTHER TERMINAL 600 Q ABOVE ROOF LEVEL 300 R FROM ADJACENT OPENING WINDOW 1000 S FROM ADJACENT WALL TO FLUE 300
H* and J* These dimensions comply with the building regulations, but they may need to be increased to avoid wall staining and nuisance from pluming depending on site conditions.
Diagram 4.2
4 Flue Options and Terminal Clearances
Diagram 4.3
4.1 Flue Options
There are various ue options to choose from as illustrated in diagram 4.1. The ue lengths and installation are described in
section 10.
4.2 Flue Terminal Position
In GB the minimum acceptable siting dimensions for the
terminal from obstructions, other terminals and ventilation openings are shown in diagram 4.2.
In IE the minimum distances for ue terminal positioning must
be those detailed in I.S.813 “Domestic Gas Installations”.
The terminal must be exposed to the external air, allowing free passage of air across it at all times.
Being a condensing boiler some pluming may occur from
the ue outlet. This should be taken into consideration when
selecting the position for the terminal.
Carports or similar extensions of a roof only, or a roof and one wall, require special consideration with respect to any openings, doors, vents or windows under the roof. Care is required to protect the roof if made of plastic sheeting. If the carport comprises of a roof and two or more walls, seek advice from the local gas supply company before installing the boiler.
4.3 Terminal Guard
A terminal guard is required if persons could come into contact with the terminal or the terminal could be subject to damage. If a terminal guard is required, it must be positioned to provide minimum of 50mm clearance from any part of the terminal and be central over the terminal. The guard should be similar to that shown in diagram 4.3. A suitable guard is manufactured by: ­Tower Flue Components Morley Rd. Tonbridge Kent TN9 1RA. Size: 280mm x 280mm x 270mm.
12
0
5
10
15 20
25
30
Flow Rate (litres/min)
24kW
30kW
Pressure Loss (metres)
15kW
35kW
5 Water Systems - General
5.1 General
This boiler is designed to provide central heating from a fully pumped open vented or sealed water system and domestic hot water using a fully indirect cylinder.
5.2 Draining Points
Draining taps must be provided at all low points of the system, which will allow the entire system to be drained. Draining taps shall be to the current issue of BS2879.
5.3 Pump
The pump should be tted on the ow pipe from the boiler and
have isolating valves each side. A variable duty pump should be set to give a temperature
difference of no greater than 200C between the ow and
return, with the thermostat set at “MAX”, which is about 800C,
to give a ow rate as given in the table.
See chart for pressure loss of the boiler, diagram 5.1. High resistance microbore systems may require a higher duty pump.
5.4 Flow Rate
If it is necessary to alter the ow rate, the system can be tted with a lockable balancing valve in the main ow or return pipes shown in diagram 5.2. The ow rate through the boiler
must not be allowed to fall below that given in diagram 5.1.
5.5 Bypass
A system bypass is required and should be tted at least 1.5
metres away from the boiler, refer to the current issue of the
central heating system specications (CHeSS).
5.6 Unvented DHW System
Where a storage system will not have a vent to atmosphere the installation must comply with the building regulations and local Water Company bylaws, see also the current issue of BS5546 and BS6700.
If tting to an existing system the local authority should be
informed.
General - All domestic hot water circuits, connections, ttings
must be in accordance with the relevant standards and water supply regulations.
For GB: Guidance G17 to G24 and recommendation R17 to R24 of the Water Regulations Guide.
For IE: The current edition of I.S.813 “Domestic Gas Installations”.
Diagram 5.1
14401
5.7 Water Treatment
Existing system- It is ESSENTIAL that prior to installing the
new boiler the system is thoroughly ushed.
New system- For optimum performance after installation, the boiler and its associated central heating system should also
be ushed.
Flushing should be carried out in accordance with BS7593: 1992 using a cleanser such as Sentinel X300 or X400, Fernox Restorer or Salamander corrosion guard cleaner.
IMPORTANT: Ensure all cleanser is removed from the whole system before adding an inhibitor.
For long-term corrosion protection, after ushing, an inhibitor
should be used, refer to the current issue of BS 5449 and BS 7593 on the use of inhibitors in central heating systems. Examples are Sentinel X100 Fernox Protector or Salamander corrosion guard inhibitor.
13
5.8 Vented (Open) Water System
The boiler must be supplied from an unrestricted water supply taken from a feed and expansion cistern situated at a maximum height of 27 metres (90ft) above the boiler.
The cold feed must be 15mm minimum size.
The vent must rise continuously and be unrestricted.
It is important that the relative positions of the pump, cold feed and open vent are as shown in diagram 5.2.
5.9 Combined Feed and Vent
For combined feed and vent, a 22mm pipe must be tted in
accordance with BS 5449.
5.10 Domestic Hot Water Cylinder
SINGLE FEED INDIRECT CYLINDERS ARE NOT SUITABLE The domestic hot water cylinder must be of the double feed fully indirect coil type.
5.11 Draining Points
Draining taps must be provided at the lowest points of the system, which will allow the entire system to be drained. A draining point for the appliance is provided at the position shown in diagram 5.3.
Diagram 5.3
14506
5 Water Systems - Open Vented
Diagram 5.2
13147
DRAIN POINT
14
5 Water Systems - Sealed
5.12 Sealed Water Systems
The installation must comply with the appropriate requirements of the current issue of BS4814, BS5449, BS6759, BS6798 and BS7074 Part 1 and 2. See diagram 5.4 for a suggested layout.
5.13 Safety Valve
A safety valve must be tted to a sealed system.
It shall be preset, non-adjustable with a lift pressure of 3 bar, incorporating seating of a resilient material, a test device and a connection for drain. The drain from the safety valve must be routed outside the building, must not discharge above an entrance or window or any type of public access area, be clear of any electrical
ttings and positioned so that any discharge can be seen.
5.14 Expansion Vessel
A diaphragm type expansion vessel, conforming to the current issue of BS4814 (see also BS7074 Part 1 and 2) must be connected at a point close to the inlet side of the circulating pump, see the diagrammatic layout, diagram 5.4. The expansion vessel volume depends on the total water system volume and the initial system design pressure. For any system an accurate calculation of vessel size is given in the current issue of BS5449 and BS7074 Part 1. Example: For an initial design pressure of 0.7 bar, the mini­mum total vessel volume required is 0.063 x Total System Volume. NOTE: A higher initial design pressure requires a larger vol­ume expansion vessel. Guidance on vessel sizing is also given in the current issue of BS5449 and BS7074 Part 1, for IE refer to the current edition of I.S.813 “Domestic Gas Installations”. The charge pressure must not be less than the static head of the system, that is, the height of the highest point of the system above the expansion vessel.
Diagram 5.4
14017
5.15 Pressure Gauge
A pressure gauge with a set pointer and covering at least 0 to
4 bar (0 to 60 lb/in2) shall be tted permanently to the system in a position where it can be seen when lling the system.
5.16 Domestic Hot Water Cylinder
SINGLE FEED INDIRECT CYLINDERS ARE NOT SUITABLE The domestic hot water cylinder must be of the double feed fully indirect coil type. It must be suitable for working at a gauge pressure of 0.35 bar above the safety valve setting.
15
TEMPORARY CONNECTION
HOSE UNION
HOSE
UNION
SUPPLY
PIPE
CONTROL VALVE
CONTROL
VALVE
DOUBLE CHECK VALVE
HEATING CIRCUIT
DRAIN POINT
SUPPLY
PIPE
AIR GAP
TUNDISH
CONTROL
VALVE
CONTROL
VALVE
TYPE CA BACKFLOW
PREVENTION DEVICE
BOILER
RETURNFLOW
BOILER
RETURNFLOW
HEATING CIRCUIT
DRAIN POINT
Method 1
Method 2
Diagram 5.5
11680
5 Water Systems - Sealed
5.17 Water Makeup
Provision should be made for replacing water loss from the system using a make up bottle mounted in a position higher than the top point of the system, connected through a non-re­turn valve to the return side of either the heating circuit or the hot water cylinder. Alternatively, provision for make up can be made using a
lling loop.
5.18 Filling a Sealed Water System
Provision for lling the system at low level must be made, see
diagram 5.5. There must be no permanent connection to the mains water supply, even through a non-return valve.
16
6 Installation Preparation
6.1 Appliance Pack
Please check the contents of packs as shown in diagram 6.1.
The packs are located in the top polystyrene packing.
Remove the carton sleeve and top pack then lift the boiler and its polystyrene base support out of the lower pack.
6.2 Site Requirements
The boiler mounting wall should be suitable for the weight of
the appliance and be true and at.
NOTE: Due to the varied site conditions we do not supply
xings and advise that the installer should supply those which
are suitable.
6.3 Wall Template
Take the wall template from the document pack located within the top polystyrene packing and place in the desired position
on the wall, giving due consideration to the required boiler clearances, see section 3, and the ue you are tting.
Mark the position of the ue centre, if tting a side ue, extend the ue centre line into the corner then 149mm along the
adjacent wall, see diagram 6.2.
For extended side ues, the ue hole centre should be
determined by extending the dashed inclined line on the template to the side wall, then 149mm along the adjacent wall, see diagram 6.2. This dashed line is drawn at 44mm/ metre (2.5°) rise from the boiler.
To allow for the ue passing through the wall at this angle
a 125mm hole should be drilled irrespective of internal or external installation.
Remove the wall template whilst drilling the ue hole.
6.4 Flue Hole Cutting
External access ue installation can use a 105mm diameter
core drill.
Internal access only ue installation will need a 125mm
diameter core drill.
NOTE: The ue is designed with an internal fall of 44mm/
metre (2.5°), therefore the hole can be drilled horizontally.
If ue extension pipes are to be used then a core drill size of
125mm is required. This will allow the extension pieces to slope at 44mm/metre (2.5°) towards the boiler.
14020
Diagram 6.2
Diagram 6.1
14016
Documentation Pack (not illustrated) Wall Template, User Instructions, Installation and Servicing Instructions.
17
Diagram 7.1
12965
7 Boiler Fixing
7.1 Wall Hanging Bracket
The Wall Hanging Bracket is supplied in the main boiler packaging.
Reposition the wall template over the ue hole and mark the position of the xing holes for the hanging bracket, see
diagram 7.1.
NOTE: Due to the varied site conditions we do not supply
xings and advise that the installer should supply those which
are suitable.
Drill xing holes and insert suitable wall plugs.
Direct Rear Flue only - If external access is not available the
ue to be used should be assembled as described in sections
10.11 to 10.13 and inserted through the hole in the wall before
tting the wall hanging bracket.
7.2 Boiler Hanging
IMPORTANT: With regards to the Manual Handling
Operations, 1992 Regulations, the following lift operation is deemed to be a one man lift, refer to section 17 Manual Handling.
IMPORTANT: Direct Rear Flue only - The direct rear ue must be tted before hanging the boiler, refer to sections
10.11 to 10.13, and the rear outlet cover plate should be removed.
Lifting the boiler into position, lean the top of the boiler slightly to the wall and position just above the hanging bracket. Lower the boiler slowly push back and engage onto the hanging bracket making sure the boiler is located over the retaining bosses, see diagram 7.2.
Diagram 7.2
12959
18
8 Gas / Water and Appliance Connection
Diagram 8.1
8.1 Gas Connection
Before connection check the supply of local gas. The gas supply connection is below the boiler, see diagram
8.1. The whole of the gas installation, including the meter, should be inspected, tested for tghtness and purged in accordance with the current issue of BS6891 and in IE the current edition of I.S.813 “Domestic Gas Installations”.
RETURN
FLOW
22mm compression is the recommended fixing for servicing (not supplied)
Gas Connection
Water Connections
12799
14507
9.1 Condensate Drain Connection
The condensate drain connection, is positioned below the boiler as shown in diagram 9.1. To discharge condensate to a drain, the drain pipe should have a fall of a least 44mm/metre (2.5°) away from the boiler. Condensate should, if possible be discharged into the household internal drainage system. If this is not practicable, discharge can be allowed into the external household drains or a purpose designed soak away, refer to diagram 9.2. It is recommended that any external condensate drain pipe is insulated and also preferably of 32mm diameter, to prevent freezing in adverse weather conditions. The condensate is discharged periodically in ‘slugs’ by siphonic action. It is not necessary to provide air breaks or extra traps in the discharge pipe as there is already a trap inside the boiler. Fitting an extra trap may cause the boiler siphon to work incorrectly. Refer to BS5546 or BS6798 for advice on disposal of boiler condensate.
14508
Diagram 9.1
CONDENSATE DRAIN CONNECTION
8.2 Water Connections
Provision is made for the water connections to be made from above the boiler, see diagram 8.1. The position is shown on the wall template. Flush out the domestic hot water and the heating systems before connecting to the boiler.
9 Condensate Connections
GAS SERVICE ISOLATION VALVE
GAS SUPPLY PIPE IN
PRESSURE TEST POINT
19
9 Condensate Connections
13000
Diagram 9.2
20
10 Telescopic Flue - Length, Preparation and Installation
14014
Horizontal Telescopic Flue
Diagram 10.1
14004
10.1 Flue Length
The maximum permissable horizontal ue length is 8 metres plus the ue terminal assembly, this can be achieved by use
of the accessories, see diagram 10.3.
However should an additional 90º or 2 x 45º elbows be used then the length MUST be reduced by 1metre.
The diagram 10.1 shows the length achievable by using the kit A2043600.
When extension pipes are used the ue system must be
designed to have a continuous fall to the boiler of at least 2.5º 44mm/metre to allow condensate to run back into the boiler and out via the condensate drain.
The ue can be installed from inside the building, when
access to the outside wall face is not practicable.
21
14005
Diagram 10.3
13765
10 Telescopic Flue - Length, Preparation and Installation
Diagram 10.2
22
10.2 Horizontal Telescopic Flue - A2043600
Refer to diagram 10.2 for kit contents.
10.3 REAR Flue
If a wall thickness is between 231mm min. to 441mm max.
then the ue can be used without extensions.
Remove the top ue outlet cover secured with four screws,
see diagram 10.4.
Using these screws inserted into the same holes on the boiler,
temporarily secure the ue elbow, measure the distance from the outside wall to the butt joint, see diagram 10.5. If the measurement ‘Y’ exceeds 525mm, then the appropriate length of extension pipe is required.
If the dimension is less than 315mm DO NOT cut the ue, it
can project to a maximum of 600mm, refer to diagram 10.6. If
this is not desirable then a Standard ue MUST be used and
cut to length.
10.4 SIDE Flue
Remove the top ue outlet cover secured with four screws,
see diagram 10.4.
Using these screws inserted into the same holes on the boiler,
temporarily secure the ue elbow, measure the distance from the outside wall to the butt joint, see diagram 10.7. If the measurement ‘Y’ exceeds 525mm, then the appropriate length of extension pipe is required.
If the dimension is less than 315mm DO NOT cut the ue, it
can project to a maximum of 600mm, refer to diagram 10.6. If
this is not desirable then a Standard ue MUST be used and
cut to length.
Diagram 10.6
12979
10 Telescopic Flue - Length, Preparation and Installation
Diagram 10.4
12978
Diagram 10.5
12806
Diagram 10.7
13224
23
Diagram 10.8
12929
Diagram 10.9
12977
Diagram 10.10
12930
10 Telescopic Flue - Length, Preparation and Installation
10.5 Flue Fitting
With the air duct seams aligned and the ue set to the
required length ‘Y’, mark the securing hole position in the air duct. Drill a 3mm diameter hole at this position, take care not
to pierce the inner ue duct. Secure with screw provided and
tape the joint, see diagram 10.8.
Fit the sealing collar onto the locating ring on the ue terminal,
see diagram 10.9.
With the ue elbow removed, push the ue assembly into
the wall, externally or internally, until the end of the assembly protrudes a short way from the inside face of the wall. This will enable the internal trim ring (if required) to be positioned
and allow the ue assembly to be drawn back up to the ue
elbow.
Secure the ue elbow in position on top of the boiler with the
four screws supplied.
Draw the ue assembly from wall and engage the ue duct into the elbow and butt t between the air duct and ue elbow.
Check the correct alignment of the ue.
Fit the securing collar in position, mark through two of the pre drilled holes in the securing collar. Remove securing collar and drill two 3mm diameter holes one in the elbow and one in
the air duct, take care not to pierce the inner ue duct. Fit the
securing collar and secure with screws provided, see diagram
10.10.
Slide the internal trim ring back against the wall, securing in place with a small amount of sealant if required.
The cut ducts must be de-burred and all lings and debris
removed.
Insert the ue duct into the air duct terminal assembly,
remembering to engage the catch within the terminal.
NOTE: If the seals require lubricant to ease installation, do not use mineral oils or grease, only silicon grease or water is recommended.
24
10.6 Flue Length
The maximum permissable horizontal ue length is 8 metres plus the ue terminal assembly, this can be achieved by use
of the accessories, see diagram 10.13.
However should additional 90º or 2 x 45º elbows be used then the length MUST be reduced by 1metre.
The diagram 10.11 shows the length achievable by using the kit A2043400.
When extension pipes are used the ue system must be
designed to have a continuous fall to the boiler of at least 2.5º 44mm/metre to allow condensate to run back into the boiler and out via the condensate drain.
The ue can be installed from inside the building, when
access to the outside wall face is not practicable.
10 Standard Flue - Length, Preparation and Installation
Diagram 10.11
14015
14006
Standard Horizontal Flue
25
10 Standard Flue - Length, Preparation and Installation
Diagram 10.12
13222 13765
Diagram 10.13
26
10 Standard Flue - Length, Preparation and Installation
10.7 Standard Horizontal Flue - A2043400
Refer to diagram 10.12 for kit contents.
10.8 REAR Flue
Remove the top ue outlet cover secured with four screws,
see diagram 10.4.
Using these screws inserted into the same holes on the boiler,
temporarily secure the ue elbow, measure the distance from the outside wall to the butt joint, see diagram 10.14. If the measurement ‘Y’ exceeds 665mm, then the appropriate length of extension pipe is required. The minimum dimension
is 187mm to suit a 75mm min wall thickness. The ue can
project to a maximum of 600mm, refer to diagram 10.15.
10.9 SIDE Flue
Remove the top ue outlet cover secured with four screws,
see diagram 10.4.
Using these screws inserted into the same holes on the boiler,
temporarily secure the ue elbow, measure the distance from the outside wall to the butt joint, see diagram 10.16. If the measurement ‘Y’ exceeds 665mm, then the appropriate length of extension pipe is required. The minimum dimension for Lhd is 227.5 and Rhd 177.5 to suit a minimum wall
thickness of 75mm. The ue can project to a maximum of
600mm, refer to diagram 10.15.
13224
Diagram 10.16
Left Hand illustrated
Diagram 10.14
13223
Diagram 10.15
12979
27
10.10 Flue Fitting
Remove the ue elbow.
Separate the ue duct from the terminal by twisting to release
the terminal catch, then pull out of the retaining seal, refer to diagram 10.17.
The ue duct cutting length (L + 11mm.) is shown in diagram
10.17.
The air duct should be cut at the opposite end to the terminal
The plastic ue duct MUST be cut at the opposite end to the
terminal catch.
The plastic ue duct extensions MUST be cut at the opposite
end to seal.
The cut ducts must be de-burred and all lings and debris
removed.
Insert the ue duct into the air duct terminal assembly,
remembering to engage the catch within the terminal.
NOTE: If the seals require lubricant to ease installation, do not use mineral oils or grease, only silicon grease or water is recommended.
Fit the sealing collar behind the locating lugs on the ue
terminal, see diagram 10.18.
Push the ue assembly into the wall, externally or internally,
initially until the end of the assembly protrudes a short way from the inside face of the wall. This will enable the internal
trim ring (if required) to be positioned and allow the ue assembly to be drawn back into the ue elbow.
Secure the ue elbow in position on top of the boiler with four
torque headed screws supplied.
Draw the ue assembly from wall and engage the ue duct into the elbow and butt t between the air duct and ue elbow.
Ensuring the correct alignment of the terminal.
Fit the securing collar into position, mark through two of the pre drilled holes in the securing collar. Remove securing collar and drill two 3mm diameter holes one in the elbow and
one in the air duct, take care not to pierce the inner ue duct.
Fit the securing collar and secure with screws provided, see diagram 10.18.
Slide the internal trim ring back against the wall, securing in place with a small amount of sealant if required.
NOTE: If the air and ue ducts have been correctly cut to the instructions the sealing collar should t ush with the outside
wall, check this.
Diagram 10.17
12847
10 Standard Flue - Length, Preparation and Installation
Diagram 10.18
12658
28
10 Direct Rear Flue - Length, Preparation and Installation
28mm MAX 24mm MIN
10.11 Direct Rear ue - Telescopic
Part No. A2043500.
Refer to diagram 10.19 for kit contents.
10.12 Flue Length
Measure the distance from the outside wall to the inside wall face. This measurement must not exceed 512mm (465mm if the upward piping kit is used). If the dimension is less than
291mm DO NOT cut the ue, it can project to a maximum of
600mm, see diagram 10.15.
10.13 Flue Fitting
Set the ue to the required length ‘Y’ plus 24mm min to 28mm
max, see diagram 10.20, ensure the air duct seams line up. Mark the securing hole position in the air duct. Drill a 3mm diameter hole at this position, take care not to pierce the
inner ue duct. Secure with screw provided and tape the joint,
see diagrams 10.19.
Fit the sealing collar onto the locating ring on the ue terminal,
see diagram 10.19.
Push the telescopic terminal assembly into the wall, externally or internally, initially.
Draw the telescopic ue through the wall and engage the
telescopic terminal assembly into the clamping band grips. The telescopic terminal assembly must be pulled forward of the clamping band grips by the dimension shown in diagram
10.21 to ensure a good seal when the boiler is located onto
the xing plate.
Ensuring the correct alignment of the terminal.
Secure the telescopic terminal assembly using the clamping band supplied. The position of the clamping band securing screw is important, refer to label and wall template.
IMPORTANT: CHECK THE CLAMPING BAND IS SUFFICIENTLY TIGHTENED TO AVOID ANY MOVEMENT OF THE FLUE WHEN FITTING THE BOILER.
Continue at the appropriate paragraph of section 7.
Diagram 10.20
12966
Diagram 10.21
12958
13203
Diagram 10.19
29
10 Vertical Flue - Length, Preparation and Installation
Diagram 10.22
12984
10.14 Vertical ue
The vertical ue system is available as an option where the
boiler position does not permit the use of the top horizontal
ue system.
The system is made up from accessories. The accessories
include terminal assembly, bends 45º and 90º, ue extensions, xing bracket and appropriate weather collar, see
diagram 10.23.
The maximum permitted straight ue length is 8 metres plus the terminal. for each 90º or 2x45º bends tted, the maximum
length must be reduced by 1 metre, see diagram 10.22.
NOTE: 2x45º bends can replace 1x90º bend if necessary. When using 90º bends any horizontal extension pipe should be inclined by a minimum of 44mm/metre (2.5º) towards the boiler to facilitate condense removal, see (a) in diagram
10.22.
Alternatively use 45º bends to avoid horizontal runs, see (b) in diagram 10.22.
The terminal siting should be as shown in diagram 4.2.
Measure the distance of ue length required for the
installation.
The ue must be designed with a continuous fall towards the
boiler.
30
10 Vertical - Flue Length, Preparation and Installation
Flue Installation
Remove the top ue outlet cover secured with four screws,
see diagram 10.4.
Refer to diagram 10.24 and secure the ue adapter in
position on top of the boiler with four screws supplied, making
sure the nib ts into the locating slot in the boiler casing to
ensure correct orientation.
NOTE: The rubber ‘O’ rings of each section should be lubricated prior to assembly. Do not use mineral oils or grease, silicon grease or water is recommended.
Secure the rst extension pipe to the ue adapter with the
securing collar supplied by positioning the collar centrally over the joint, then tighten the two screws on the securing collar, see diagram 10.25.
Fit more extension pipes as required using the collar and
screws supplied with each extension pipe. To t position the
collar centrally over the joint, tighten the two screws on the securing collar. Using the holes provided in the securing collar drill and insert the two self tapping srews supplied, see diagram 10.26.
The rubber ‘O’ rings of each section should be lubricated prior to assembly.
NOTE: Do not use mineral oils or grease, silicon grease or water is recommended.
When installing the ue it is recommended that it is supported every 2 metres and at every bend by a xing bracket.
Project the rise of the ue pipe to roof level and cut a 150mm
hole in the roof.
Flue Terminal Installation
(a) Pitched Roof
Fit the required pitched roof weather collar over the 150mm hole in the roof. Make good the tiling or slating around the
collar incorporating the ashing of the weather collar. Position
the angle cap over the weather collar in the correct orientation to attain the correct angle for your roof.
(b) Flat Roof
Fit the aluminium weather collar over the 150mm hole in the roof ensuring a weather tight seal.
From above carefully place the ue terminal through the
weather collar.
Flue Terminal to Boiler Connection
Should the clearances above the boiler to roof not allow for
extensions, it is permitted to cut the ue terminal ensuring the relationship of ue and air duct lengths are retained.
12969
Diagram 10.23
31
10 Vertical Flue Length, Preparation and Installation
Completion of Installation
With the ue terminal positioned in the roof the length of the nal pipe can be determined. If a telescopic length cannot be used, then a standard ue length can be cut to make the correct length. Cut the ue to the desired length measuring
from the ‘O’ ring end and discard the plain end of the tube. The cuts must be square and made free of burrs to allow correct assembly.
NOTE: The ue pipe is 10mm longer than the air pipe, see
diagram 10.27.
Carefully push the terminal assembly upwards to allow room
for tting the nal ue piece. Fit a xing bracket to the terminal assembly. Pull the terminal assembly down and join to the ue
system. Ensure that the terminal is making a weather tight
seal on the weather collar. Secure the xing bracket tted to the terminal to the roong struts or a purpose made batton.
Diagram 10.24
12980
Diagram 10.25
12981
Diagram 10.26
12982
Diagram 10.27
12983
32
10 Twin Flue - Length, Preparation and Installation
Diagram 10.28
12987
33
10 Twin Flue - Length, Preparation and Installation
10.15 Twin ue
The twin ue system is available as an option when the top horizontal or vertical ue system is not appropriate.
The system can provide an independent horizontal air inlet
and ue outlet, horizontal air inlet and vertical ue outlet or vertical air inlet and ue outlet via a concentric terminal.
The system is made up from accessories, see diagram 10.29.
NOTE: The air and ue outlets do not have to be equal
lengths. 2x45º bends can replace 1x90º bend if necessary.
The maximum permitted combined (air inlet + ue outlet) ue length is 40 metres plus terminal assemblies. For each 90° or 45º x 2 bends tted, the maximum ue length must be
reduced by 1 metre, see diagram 10.28.
NOTE: When using 90º bends any horizontal run should be inclined by a minimum of 44mm/metre (2.5º) towards the boiler to facilitate condense removal.
Alternatively use 45º bends to avoid horizontal runs in the ue
pipe.
Terminal Position
The clearances for a ue outlet are given in the "Flue Location and Ventilation" section.
In addition the horizontal air inlet must not be closer than 300
mm from a ue outlet on the same wall or 1200mm from an opposing ue outlet.
Diagram 10.29
12970
34
10 Twin Flue - Length, Preparation and Installation
Installation Details
The parts available for a twin ue system installation are
shown in diagram 10.29.
Boiler Connection
Remove the top ue outlet cover secured with four screws,
see diagram 10.4.
Place the twin ue adaptor onto the outlet of the boiler with
the air inlet to the left hand side, see diagram 10.30. Secure the adaptor to the top panel with the screws provided. Care should be taken when inserting the screw through the hole in adaptor top.
To facilitate engagement, it is recommended that the rubber ‘O’ rings are lubricated with silicone grease or water prior to assembly.
Air and Flue Pipe Installation
The air and ue pipes can now be built up from the boiler.
The ue must be designed with a continuous fall towards the boiler. If using the horizontal ue pipe or 90° bends the pipe
must be inclined at 44mm/metre (2.5°) minimum, see diagram
10.28.
Alternatively if space allows, use 45° bends in place of 90º bends.
The rubber ‘O’ rings of each section should be lubricated prior to assembly with silicone grease.
When building the ue up it is recommended that it is supported every 2 metres and at every bend by a xing
bracket.
Horizontal Terminal Installation
With due consideration to terminal clearances mentioned in section 4.2 drill the one or two holes as required with a 90mm core drill.
Push the horizontal terminal through the wall allowing approx. 100mm to protrude outside.
Push a grey rubber wall seal onto either side of the wall ensuring that both wall seals are pushed up to the wall surface, see examples (b) and (c) diagram 10.28.
Vertical Terminal Installation
With due consideration to terminal clearances mentioned in
Section 4.2, project the rise of the ue pipe to roof level and
cut 150mm hole in the roof.
(a) Pitched Roof
Fit the required pitched roof weather collar over the 150mm hole in the roof. Make good the tiling or slating around the
collar incorporating the ashing of the weather collar. Position
the angle cap over the weather collar in the correct orientation to attain the correct angle for your roof. One way round gives a pitch of 25°-38° and the other gives 37°- 50°.
(b) Flat Roof
Fit the aluminium weather collar over the 150mm hole in the roof ensuring a weather tight seal.
Diagram 10.30
12985
Horizontal Pipes-Completion of Installation
Having built the pipe(s) from the boiler to the terminal(s), the
length of the nal pipe piece can be determined. Cut pipes at
the opposite end to the ‘O’ ring seal making square and free from burrs. Push the horizontal terminal through the wall to
engage the nal pipe piece and pull back ensuring the grey
wall seals are fully pulled up to the outside and inside wall faces.
Vertical Pipes-Completion of Installation
Refer to diagram 10.28.
For installation of (a), attach the twin pipe to concentric
ue adaptor, part number A2011600, to the base of vertical
terminal assembly. For installation of (b), attach the single pipe to concentric adaptor, part number A2011500, to the base of vertical terminal assembly.
With the vertical terminal assembly positioned in the roof,
the length of the nal pipe can be determined. Cut the ue
to the desired length measuring from the ‘O’ ring seal end and discard the plain end of the tube. The cut end should be square and free from burrs. Carefully push the terminal
assembly upwards to allow room for tting the nal ue piece(s). Fit a 100mm xing bracket to the terminal assembly
Part No2000460486. Pull the terminal assembly down and
join to the ue system. Ensure that the terminal is making a weather tight seal on the weather collar. Secure the xing bracket tted to the terminal to the roong struts or a purpose
made batton.
35
10 Plume Management Kit
10.16 Plume Management Kit
The Plume Management Kit: Part No. A2044100 (white) or A2044000 (black) can be used to overcome many site issues.
The Plume Management Kit will t to the Top Horizontal
Telescopic, Rear Horizontal Telescopic and Standard
Horizontal Flue. This enables the ue products to exhaust
further away from the boiler, thereby reducing the impact of pluming.
NOTE: The ue air inlet can be sited closer to doors, opening
windows and air bricks, than stated in section 4.2, see diagram 10.31.
The maximum length of the Plume Management Kit must NOT
exceed 6m with a horizontal concentric ue length of 2m max.
For each 90o bend or 2 x 45o bends the maximum length of the Plume Management Kit must be reduced by 1m.
For more information contact Glow-worm, refer to page 2.
The Plume Management Kit is supplied with installation instructions.
Refer to BS5546 or BS6798 for advice on disposal of boiler condensate.
Diagram 10.31
12997
36
11 Electrical Connection
WARNING: This appliance must be earthed.
This appliance must be wired in accordance with these instructions. Any fault arising from incorrect wiring cannot be put right under the terms of the Glow-worm guarantee. All system components must be of an approved type. Electrical components have been tested to meet the equivalent requirements of the BEAB. Do not interrupt the mains supply with a time switch or programmer. Connection of the whole electrical system and any heating system controls to the electrical supply must be through a common isolator. Isolation should preferably be by a double pole switched fused spur box having a minimum contact separation of 3mm on each pole. The fused spur box should be readily accessible and preferably adjacent to the boiler. It should be
identied as to its use.
A fused three pin plug and shuttered socket outlet may be used instead of a fused spur box provided that both the plug and socket comply with the current issue of BS1363. This boiler is suitable for installation in bathroom zones 2 and 3.
11.1 Electrical Wiring
Remove the electrical cartridge from the ttings pack.
Remove the securing screw to open the cartridge, see diagram 11.1. NOTE: There are two screws supplied loose in the electrical cartridge, these will be required to secure the cartridge into the electrical interface housing. Slacken the cable strain relief screws in the electrical cartridge, see diagram 11.1. Route the mains supply and system cables through the strain relief and connect to the relevant plug, see diagram 11.2.
11.2 Pump Wiring
Ensure that a seperate pump supply cable is routed through the strain relief and connected to the relevant plug, see diagram 11.2. Slacken the cable strain relief and route the pump electrical supply cable and connect as shown in diagrams 11.1 and
11.2.
ELECTRICAL CARTRIDGE
CABLE STRAIN RELIEF
SECURING SCREW
Diagram 11.1
13905
Diagram 11.2
13457
37
13906
11 Electrical Connection
ELECTRICAL CARTRIDGE
FIXING SCREWS
Diagram 11.3
11.3 Electrical Cartridge Securing
Close the cartridge and secure with the previously removed screw. Push the electrical cartridge into the interface housing on completion of the wiring, see diagram 11.3. Secure with the two cartridge retaining screws provided in the cartridge body.
11.4 Electrical Connections - Testing
Carry out preliminary electrical system checks as below:
1. Test insulation resistance to earth of mains cables.
2. Test the earth continuity and short circuit of cables.
3. Test the polarity of the mains.
NOTE: If you require to test the appliance refer to section 14.
12 Commissioning
12.1 Preliminaries - All Systems
The commissioning should be carried out by a competent person in accordance with the current issue of BS6798. DO NOT operate the boiler without water.
Make sure that the system has been thoroughly ushed
out with cold water and that all cleanser, if used, has been removed. Isolate the boiler from the mains electrical supply. Test for gas tightness and purge air from the gas supply.
12.2 Filling the Heating Circuit
With the gas service isolation valve closed and with no demand from any external controls.
1. Fill the heating system.
Sealed system only - ll the system to a pressure of
1.0bar.
2. Vent all air from the system - repeat as neccessary until the system is full and all the air has been vented.
12.3 Gas Supply
The gas valve is factory set for natural gas (G20) and should need no adjustment. Turn on the gas supply at the isolation valve, see diagram 12.1. Check the supply pressure at the pressure test point is 20mbar.
Diagram 12.1
14507
GAS SERVICE ISOLATION VALVE
GAS SUPPLY PIPE IN
PRESSURE TEST POINT
38
12 Commissioning
12.3 Initial Lighting
DO NOT operate the boiler without water.
The lighting procedure of the boiler is fully automated. Refer to diagram 12.2.
1. With no demand from any external controls, switch on the electrical supply to the boiler. Open the gas service isolation valve, see diagram 12.1.
2. Press and hold the “ Mode “ button of the boiler user
controls for 2 seconds, the Central Heating symbol,
will ash. Use the “SELECTOR” buttons to adjust CH
temperature. After 10 seconds of inactivity the display will reset to indicate the water temperature.
3. Turn ON your external controls and select the room temperature required. The boiler will operate automatically. NOTE: The display will indicate the Heating system water temperature or a fault code if in a fault condition. NOTE: After ignition the boiler will ramp slowly to full rate rather than going immediately to full rate. This is an adaptive feature to cope with small system requirements. After a period of 10 minutes, check that the supply inlet pressure of the boiler is still 20mbar, disconnect the pressure gauge. NOTE: The burner pressure cannot be measured at the gas valve as it is altered by the suction of the fan and modulated according to demand.
14249
APPROXIMATE GAS RATES
MODEL NATURAL GAS G20 m3/h ft3/h 12hx 1.28 45 15hx 1.60 56.5 18hx 1.93 68 24hx 2.58 91 30hx 3.26 115 35hx 3.8 134
Diagram 12.2
14513
12.4 Gas Rates
Should any doubt exist about the gas rate, check it using the gas meter test dial and stop watch. Make sure that all other gas burning appliances and pilot lights are off. It should be noted that this appliance will modulate the heat input according to demand. This may affect the gas rates measured if the appliance reaches its operating temperature during the measurement. The approximate gas rates:
In the unlikely event that the gas valve needs adjusting, refer to section 13.9.
MODE
MODE
39
12 Commissioning
12.5 Range Rating
These boilers are fully modulating, therefore it is not necessary to range rate them, however, if desired, you can adjust the boiler in 1kW increments between 10 and maximun output of your appliance, as follows:
a) Press and hold the ‘MODE’ and “+” button for 5
seconds. The display will change to ashing ‘0’. b) Use the ‘+’ or ‘-’ button to scroll to 96. c) Press and hold ‘MODE’ 5 seconds to conrm. d) The display now shows a ashing ‘d. 0’.
e) The part load setting is displayed in kW. Press ‘MODE’ the max rate will be indicated, to
change the value to the desired setting, use the ‘+’
or ‘-’ button.
f) Press ‘MODE’ for 5 sec to conrm the new setting
has been saved.
g) Press and hold ‘MODE’ and “+” to exit.
12.7 Completion
Adjust the boiler temperature control and any system controls to their required settings. GB: It is a requirement that the “Benchmark” Installation Commissioning and Service Record is completed and left wth the user. IE: it is necessary to complete a “Declaration of Conformity” to indicate compliance to I.S.813. An example of this is given in the current edition of I.S.813.
Testing Flue Gases: If any doubt exists that the ue products
are not exhausting correctly, investigate by use of a gas analyser (FGA).
12.8 Instruct the User
Demonstrate, then instruct the User about the lighting procedure and heating system controls operation. Advise the user on the use and maintenance of any scale reducer and pass on any relevant instructional documents.
Advise that to ensure the continued efcient and safe
operation of the boiler it is recommended that it is checked and serviced at regular intervals. The frequency of servicing will depend upon the installation conditions and usage, but in general, once a year should be enough. Draw attention, if applicable, to the current issue of the Gas Safety (Installation and Use) Regulations, Section 35, which imposes a duty of care on all persons who let out any property containing a gas appliance in the UK. The user shall not interfere with or adjust sealed components. It is the Law that any servicing is carried out by a competent
person.
Advise the user that, like all condensing boilers this appliance
will produce a plume of condensation from the ue terminal in cool weather. This is due to the high efciency and hence low ue gas temperature of the boiler.
Advise the user of the precautions necessary to prevent damage to the system, boiler and the building, in the event of the heating system being out of use during frost or freezing conditions. Advise the user that the permanent mains electrical supply SHOULD NOT be switched off, as the built in frost protection and pump/valve saver program will not operate. Advise the User if the mains electricity and gas are to be turned off for any long periods during severe weather, it is recommended that the whole system, including the boiler, should be drained to avoid the risk of freezing. NOTE: Contact your installation/servicing company as draining, relling and pressurising MUST be carried out by a competent person. Leave these instructions and the ‘Benchmark’ Installation, Commissioning and Service Record with the user.
kW m3/hr ft3/hr kW m3/hr ft3/hr
35 3.7 131 22 2.3 81.2 34 3.6 127 21 2.2 77.7 33 3.5 124 20 2.1 74.2 32 3.4 120 19 2.0 70.6 31
3.3 117 18 1.9 67.1 30 3.2 113 17 1.8 63.6 29 3.1 109.5 16 1.7 60.0 28 3.0 106 15 1.6 56.5 27 2.9 102.4 14 1.5 53.0 26 2.8 98.9 13 1.4 49.5 25 2.6 91.8 12 1.3 45.9 24 2.5 88.3 11 1.2 42.4 23 2.4 84.8 10 1.12 38.9
12.6 Testing - Heating System
Check that all external controls are calling for heat. The boiler
will re automatically. Fully open all radiator valves, ow control valve and bypass valve if tted. Balance the radiators as required and if tted adjust ow
control valve to give the required system differential. Turn off all radiators that can be shut off by the user and check to see if less than the maximum differential allowed of 200C can be
achieved across ow and return.
Allow the system to reach maximum temperature then switch off the boiler by isolating from the electrical supply. Drain the entire system rapidly whilst hot, using the drain tap at the lowest part of the system. Fill and vent the system as described previously in section 12.2
Lock or remove the handle from controls valve, if tted.
40
13 Servicing
Diagram 13.2
13.1 General Inspection
Before servicing the appliance inspect the following and then carry out the functional checks:
1. Condition of case and ue.
2. Flue terminal for obstructions.
3. Electrical supply connections.
4. Water connections.
5. Gas connection.
6. System pressure. Correct any fault before continuing.
13.2 Functional Checks
With the appliance operational carry out the following:
COMBUSTION CHECK - with a ue gas analyser as
described in section 13.9.
GAS RATE CHECK - the gas rates, refer to section
12.4. If the gas rate requires adjustment you
MUST NOT adjust the gas valve without a gas analyser, refer to section 13.9.
If you cannot measure the gas rate it is acceptable to measure the combustion rate as described in section 13.9, however, if you do not have either facility then the appliance MUST be turned off and disconnected until such equipment is available.
If the Combustion and Gas rate checks did not require adjustment then it will not be necessary to service the Combustion Chamber, Burner, Heat Exchanger or Spark Electrode, proceed to section 13.11.
If the combustion or gas rate requires adjustment you must complete the servicing as described in sections 13.3 to
13.8, then repeat the functional checks before proceeding to section 13.11 to complete the servicing.
13.3 Servicing the Appliance
On completion of paragraphs 13.1 and 13.2, proceed with the following.All routine servicing requirements can be achieved by the removal of the front panel, see diagram 13.1.
Before commencing with a service or replacement of parts the boiler should be isolated from the electrical and gas supplies, see diagram 13.2 for the position of the gas service isolation valve.
14381
Diagram 13.1
14291
GAS SERVICE ISOLATION VALVE
IMPORTANT NOTES:
1. To ensure the continued efcient and safe operation of the boiler it is recommended that it is checked and
serviced at regular intervals. The frequency of servicing will depend upon the particular installation and usage, but in general once a year should be enough.
2. It is the Law that any servicing is carried out by a competent person.
3. Before commencing with a service or replacement of parts the boiler should be isolated from the electrical supply and the gas supply should be turned off at the gas service isolation valve.
4. When replacing a part on this appliance, use only spare parts that you can be assured conform to the safety
and performance specication that we require. Do not use reconditioned or copy parts that have not been
clearly authorised by Glow-worm.
5. If any electrical connections have been disconnected and after their connection, checks to the earth continuity, polarity, short circuit and resistance to earth must be repeated using a suitable multimeter, as described in section 14.
6. On completion the “Benchmark” Service Record should be completed.
41
13 Servicing
13.4 Spark Electrode
NOTE: If the functional checks did not indicate poor
combustion then it is not necessary to service this
component.
Ease the securing clips away from the sump to release the
retaining catch then push the ue hood up to disengage from
the sump, see diagram 13.3.
To remove, swivel ue hood 90o and pull down and out, see
diagram 13.3.
Check seal for wear or damage and replace if necessary.
IMPORTANT: Do not allow xings, nuts, screws, etc. to fall into the open ue hood sump, use a temporary cover whilst
removing any parts.
Disconnect the spark electrode plug and earth lead. Remove the two securing screws and withdraw the spark electrode carefully from the combustion chamber, see diagram 13.4.
Inspect the tips for damage.
Clean away any debris and check the spark gap is 4mm.
Check the electrode gasket for signs of damage and replace if necessary.
13.5 Burner
NOTE: If the functional checks did not indicate poor
combustion then it is not necessary to service this
component.
Disconnect the gas supply at the gas valve and electrical connections, see diagram 13.5.
The Silencer (front) is a push t, so there is no need for tools to remove or t, see diagram 13.6.
Release the igniter unit support bracket, see diagram 13.7.
Remove the fan retaining bracket.
To ease removal of the securing nut from the fan retaining
bracket, a at bladed screwdriver can be used in the position
shown and gently levered down as indicated, see diagram
13.8.
Remove the fan and gas valve assembly.
The silencer (rear) is a push t so no tools are required for its removal or tting, see diagram 13.9.
Check the spark electrode gap is 4mm. Clean and adjust as necessary, see diagram 13.4.
It should not be necessary to remove the spark electrode from the burner during servicing.
Remove the anged nuts and studs that secure the burner,
note that two studs at the rear also hold the fan clamping bracket, see diagram 13.10.
Clean the burner with a soft brush taking great care not to damage the surface of the burner. DO NOT use wire or sharp instruments to clean the mesh of the burner.
NOTE: The burner gasket should be inspected but will not need replacing unless there are signs of wear or damage.
Follow the tightening sequence when re-tting the burner, see
diagram 13.10.
14406
14407
Diagram 13.3
Diagram 13.4
14408
42
GAS VALVE
GAS PIPE
ELECTRICAL CONNECTION (removed)
SECURING SCREW (3)
TUBING NUT
Diagram 13.5
14079
Diagram 13.6
13128
FAN
SECURING NUT
FAN RETAINING BRACKET
Diagram 13.9
14288
Diagram 13.8
14081
Diagram 13.7
14409
13 Servicing
SECURING NUT
SUPPORT
BRACKET IGNITION LEAD
SPADE CONNECTOR
IGNITER UNIT
EARTH CONNECTION
ELECTRICAL CONNECTIONS
43
13 Servicing
13.6. Heat Exchanger
NOTE: If the functional checks did not indicate poor
combustion then it is not necessary to service this
component.
Remove loose debris from inside the heat exchanger using a soft brush and vacuum cleaner.
Carefully ush by spraying water into the heat exchanger, any
remaining debris should pass through the condensate trap (Ensure the water is kept away from electrical components).
13.7 Condense Trap and Siphonic Drain
The condensate trap and siphonic drain does not normally need servicing unless material deposits exceed beyond the
service ll level, see diagram 13.11.
To clean the condense trap remove the sump and rinse with water.
Diagram 13.11
14089
LOCATING SCREW
SERVICE FILL LEVEL
CONDENSE TRAP AND SIPHONIC DRAIN
SUMP
Turn anti-clockwise to remove
SECURING NUTS (6)
BURNER
FAN CLAMPING BRACKET
Diagram 13.10
14410 14397
13.8 Casing panel seal check
NOTE: If the functional checks did not indicate poor
combustion then it is not necessary to service this
component.
Check the condition of the seal and replace if worn or damaged.
To replace remove the old seal and thoroughly clean the casing surfaces. Fit the new seals, these are supplied to the correct lengths and are in four pieces, for use on the sides, top and bottom.
14460
44
13 Servicing
13.9 Combustion Check
With the appliance operational connect the CO2 combustion
analyser to the ue elbow test point or if direct rear ue tted,
the test point shown in diagram 13.12.
IMPORTANT: Remember to replace the cap on completion of the test.
A competent person only should carry out any adjustment to
the gas valve, refer to diagram 13.13.
Monitor the combustion reading and at max rate the reading should be 9.3% ± 0.5.
Check the burner %CO2 at maximum rate (open a hot water tap fully) is as shown in the “CHECK” column of the table and if the reading falls within the tolerance, disconnect the
analyser, t the test point cap and return to functional checks
- gas rate.
If adjustment is required remove the front casing panel, see diagram 13.1. Taking care not to touch any internal components, proceed as follows:
Press the “reset” button on the controls fascia, release
and immediately press and hold in the “+” button. After
approximately 5 seconds “Hi” will be displayed. Pressing the mode button when “Hi” is selected will force the boiler
to maximum rate, the display will ash between “Hi” and the
“default display” this will indicate the boiler has been forced to maximum.
Adjust the maximum rate CO2 with the throttle to 9.3%. (Rotate anti-clockwise to increase).
To exit the check sequences press the “mode” and “+” buttons
simultaneously, this will reset the boiler to the default display.
Monitor the combustion reading and at min rate the reading should be 9.3% ± 0.5.
If adjustment proves necessary then proceed as follows:
Press the “reset” button on the controls fascia, release
and immediately press and hold in the “+” button. After
approximately 5 seconds “Hi” will be displayed. Pressing the
“+” or “-” buttons will cycle between “Hi” and “Lo”. Pressing
the mode button when “Lo” is selected will force the boiler
to minimum rate, the display will ash between “Lo” and the
“default display” this will indicate the boiler has been forced to minimum.
Refer to diagram 13.13, remove the offset screw cover.
Adjustment of the CO2 at minimum rate is very coarse so carefully adjust the CO2 with the offset adjustment to 9.3%. (Rotate clockwise to increase).
Ret the offset cover and the cap on the test point.
To exit the check sequences press the “mode” and “+” buttons
simultaneously, this will reset the boiler to the default display.
NOTE: Check the casing panel is tted correctly giving an air
tight seal.
13.10 Gas Rate Adjustment
This appliance incorporates a pre-mix burner. The gas rate should be correct if the combustion measured in section 13.9 is correct.
13.11 Service Completion
On completion of the service the “Benchmark” Service Record should be completed.
Diagram 13.12
13028
Diagram 13.13
12776
14290
45
14 Fault Finding
14.1 Preliminary fault nding
The following checks should be performed before proceeding
onto specic diagnostics:
Check the external electrical supply to the boiler is on and a supply of 230V is present at the ‘L’ and ‘N’ terminals at the installer interface.
For access remove and open the electrical cartridge, see diagrams 11.3. and 11.1.
Test at the ‘L’ and ‘N’ terminals on the installer interface, refer to diagrams 11.1 and 14.4.
Check the electrical installation and appliance, carry out tests for earth continuity, polarity, short circuit and resistance to earth, using a suitable multimeter.
An aid to test
Remove the front casing panel, see diagram 14.1 and hinge down the control box.
Unclip the rear cover to gain access to the main PCB.
Carry out the tests at connector plug X17, see diagram 14.2. Check chassis earth at a bare metal point on the boiler.
Check that there is a gas supply to the boiler and the gas service isolation valve is turned on, see diagram 12.1.
Check pressure at the gas service isolation valve, refer to section 12.4.
Check that the heating system pressure indicates at least
1mb, if not, ll and vent the system as described in section
12.2.
Check that all external controls are on.
Check the functional ow diagram, 14.5.
14.2 Fault Codes
Fault codes take priority over all other display functions in the event of a fault occuring, refer to diagram 14.6.
If multiple faults occur the codes will be displayed for approx. 2 seconds, alternatively.
14.3 Fault Memory
The Fault memory stores details of the ten most recent faults.
To access this menu, refer to diagram 14.3:
a) Press and hold ‘MODE’ and ‘-’ buttons for 5 seconds.
b) The display will stop ashing and alternate between the
fault memory number and the fault code.
c) Press ‘+’ button to scroll through the fault memory
(Position 1 is most recent), see fault codes.
To exit this menu, press the ‘MODE’ button.
14.4 Diagnostic Menu
The Diagnostic Menu provides the ability to view and change certain parameters. See diagram 14.8 for available parameters.
14028
Diagram 14.3
Diagram 14.2
13845
14291
Diagram 14.1
14.5 Status Codes
The status codes provide information about the current operating condition of the boiler and can be accessed through the diagnostic display, refer to diagram 14.7.
46
14 Fault Finding
13917
Diagram 14.4
GAS CONTROL VALVE
HEATING FLOW THERMISTOR
HEATING
RETURN
THERMISTOR
FAN
IGNITION ELECTRODE
IGNITER UNIT
MAIN CONTROL BOARD
APPLIANCE INTERFACE BOARD
FLEXICOM HX
g/y
r
bk
gy
w
bk
bk
b
r
w
y
b
br
b
g/y
w
bk
b
r
g/y
br
g/y
b
r
r
br
b
gy
w
r
g/y
br BROWN b BLUE g/y GREEN/YELLOW
g GREEN
gy GREY
bk BLACK y YELLOW
pk PINK
p PURPLE
or ORANGE
w WHITE
r RED
KEY
47
13012
Diagram 14.5
14 Fault Finding
48
14 Fault Finding
Diagram 14.6
14029
FAULT CODES
In all circumstances press the reset button to clear the fault. If the fault persists, consult the table below.
49
14 Fault Finding
Diagram 14.7
13131
STATE LISTS
State list - To access the state lists the ‘-’ button must be pressed for longer than 5 seconds until it
begins to ash ‘S’ and then a number to indicate the state. The state numbers are given below.
50
14 Fault Finding
DIAGNOSTIC CODES - LEVEL 1
Installer Access
14725
Diagram 14.8
d.99 State List (see diagram 14.7)
d.28 Option Relay 2
d.27 Option Relay 1
d.91 Internal Programmer type (for use with Options board kit) 0:24 hour (default) 1:7 day
N/A
Flow temperature setpoint
Description Range
intelligent control
Status additional heating pump (option)
Status central heating pump
> 8 no flame < 4 good flame
Minutes
Digital regulator status
Quantity (in hundreds)
N/A
Reserved for future use
To enter the diagnostics menu follow the procedure below:-
Press and hold the ‘MODE’ and ‘+’ buttons for approx 5 seconds until the screen changes. Use the ‘+’ or ‘-’ button to select the
number 96, this is the password. Hold the ‘MODE’ for approx 5 seconds when 96 is selected, when the screen changes release
the button. The screen will ash between ‘L1’ and a number. ‘L1’ indicates you have level 1 access, the number indicates the diagnostic number below. Use the ‘+’ and ‘-’ to cycle through the selections below. To select a diagnostic number press
the ‘MODE’ button when the correct number is selected. The display will show the parameter value of the diagnostic number
selected. To return to the diagnostic number selector simply press the ‘MODE’ button. To change the parameter use the + or
- buttons. Once the value has been changed it must be saved by holding the ‘MODE’ button for approximately 5 seconds. This will return to the diagnostic number selector.
Indicates read and write function - all other diagnostics are read only
51
15 Replacement of Parts
Diagram 15.1
15.1 General
Replacement of parts must be carried out by a competent person.
Replacement parts that have associated components that need replacing on removal, ie. ‘O’ ring seals, gasket, etc; will
be supplied and should be tted.
Before replacing any parts the boiler should be isolated from the mains electric supply and the gas should be turned off at the gas service isolation valve on the boiler, see diagram
15.1.
Ensure that components with electrical connections are disconnected before removal.
Unless stated otherwise parts are replaced in the reverse order to removal.
After replacing any parts always test for gas tightness and if necessary carry out functional test of the controls.
For replacement of parts the front casing of the boiler will need to be removed. To remove undo the two screws on the underside of the front casing and lift off.
The side panels can be removed to aid replacement of parts.
To hinge a side panel undo and remove the four screws securing each side panel to the boiler, two below and two at the top.
15.2 Igniter Unit
For access, refer to section 15.1.
Remove ignition lead and electrical connections then remove igniter unit by removing two securing screws, see diagram
13.7.
15.3 Ignition Lead
For access, refer to section 15.1.
Pull the spark plug style connector off the spark electrode and the spade connector connected to the igniter unit, see diagrams 13.4 and 13.7.
15.4 Silencer Assembly (front)
For access, refer to section 15.1.
Pull forwards to remove.
The silencer is a push t so no tools or xings are required for its removal or tting, see diagram 13.6.
15.5 Gas Valve
Remove the three securing screws, holding the gas valve to the fan, see diagram 13.5.
Remove the gas valve.
After re-tting check the combustion CO2 and adjust if
necessary, refer to section 13.9, Combustion Check.
After assembly test for gas tightness and purge in accordance with the current issue of BS6891or in IE, the current edition of I.S.813 “Domestic Gas Installations”.
15.6 Flue Hood
For access, refer to section 15.1.
Pull the ue hood securing clips away from the ue hood sump and push ue hood up slightly towards ue hood top,
see diagram 13.3.
To remove swivel ue hood 900 and pull down and out
towards front of boiler.
14383
15.7 Fan/Gas valve assembly
For access, refer to section 15.1.
Undo the tubing nut to remove the gas valve from the gas pipe and any electrical connections, see diagram 13.5.
Remove the securing nut holding the fan retaining bracket, press down on burner to ease removal of securing nut. Slide out the fan retaining bracket.
Lift front of bracket away from stud and pull forward to release the fan, see diagram 13.8.
Lift fan/gas valve assembly up and forward away from locating studs.
Remove fan gasket and replace.
To replace the fan and retaining bracket correctly, insert into slots on fan clamping bracket and locate onto lugs on the burner, see diagram 13.10.
15.8 Silencer assembly (rear)
For access, refer to section 15.1.
Remove the fan/gas valve assembly, see section 15.7.
Pull Silencer rear away from fan/gas valve assembly.
The rear silencer is a push t so no tools or xings are required for its removal or tting, see diagram 13.9.
15.9 Spark Electrode
For access, refer to section 15.1.
Remove the spark plug lead and earth lead.
Remove the two securing nuts.
Withdraw the spark electrode by slowly pulling up and leaning it forward towards the centre of the heat exchanger to ensure that the electrode does not foul on the hole in the burner casing.
Check spark gap, see diagram 13.4.
PRESSURE TEST POINT
GAS SERVICE ISOLATION VALVE
GAS SUPPLY IN
CONDENSATE
52
15 Replacement of Parts
15.10 Burner
For access, refer to section 15.1.
Remove igniter unit, ue hood, fan and gas valve assembly
and spark electrode lead, refer to relevant sections.
Remove the anged nuts and studs that secure the burner,
note that two studs at the rear also hold the fan clamping bracket, see diagram 13.10.
NOTE: The burner gasket should be inspected but will not need replacing unless there are signs of wear or damage.
IMPORTANT: Do not allow xings, nuts, screws, etc. to fall into the open ue hood sump, use a temporary cover whilst
removing any parts.
15.11 Condensate Trap
For access, refer to section 15.1.
Remove securing screw, see diagram 13.11.
Disconnect the exible condense drain pipe from the external
plastic drain pipe beneath the boiler.
Carefully pull the condensate trap down and forward so as not to spill its contents. The trap shoud be removed complete with
the sealing grommet and exible condensate drain pipe.
15.12 Heating Flow Thermistor
For access refer to section 15.1
Remove the silencer front, fan/gas valve assembly and ue
hood for access. See relevant sections.
Refer to diagram 15.2.
15.15 Casing Seal
Refer to Section 13.8
15.16 Access to User interface and Main PCB
For access, refer to section 15.1.
Hinge down the control box and unclip the rear cover to gain access.
Remove electrical connections from main PCB noting their positions for replacement.
Unclip main PCB and remove, see diagram 15.5.
Unclip user interface and remove.
For replacement, see diagram 15.6 and ensure that the user
interface connection cable is retted.
NOTE: When re-tting any of the control boards make sure
you support the control box to avoid straining hinges as you push down and clip back into place.
Remove the electrical connections from the thermistor.
Remove the retaining clip from the ow pipe.
Remove the thermistor from the retaining clip.
Note that the polarity of the wiring to thermistors is unimportant.
HEATING FLOW THERMISTOR
FLOW PIPE
Diagram 15.2
12964
53
Diagram 15.3
14379
15 Replacement of Parts
Diagram 15.4
14384
Diagram 15.5
14278
HEATING RETURN THERMISTOR
RETURN PIPE
DRAIN POINT
RETAINING CLIP
RETURN PIPE
FLANGED ELBOW
15.13 Heating Return Thermistor
For access, refer to section 15.1.
Refer to diagram 15.3.
Remove the electrical connections from the thermistor.
Remove the retaining clip from the return pipe.
Remove the thermistor from the retaining clip.
Note that the polarity of the wiring to thermistor is unimportant.
15.14 Heat Exchanger
For access, refer to section 15.1.
Drain down the boiler heating circuit
Remove the silencer front
Pull forwards to remove.
The silencer is a push t so no tools or xings are required for its removal or tting, see diagram 13.6.
Remove the ue hood front
Ease the securing clips away from the sump to release the
retaining catch then push the ue hood up to disengage from
the sump, see diagram 13.3.
To remove, swivel ue hood 90° and pull down and out, see
diagram 13.3.
Remove the igniter unit with support bracket
Disconnect the electrical connections and ignition lead.
Release the igniter unit support bracket.
Remove the igniter unit assembly, see diagram 13.7.
Remove the gas valve/fan
Disconnect the tubing nut at the gas valve, see diagram 13.5.
Remove the fan retaining bracket, see diagram 13.8.
To ease removal of the securing nut from the fan retaining
bracket, a at bladed screwdriver can be used in the position
shown and gently levered down as indicated.
Remove the spark electrode plug and earth connection.
Remove the fan and gas valve electrical connections.
Remove the fan and gas valve assembly.
Remove the condensate trap
Remove the drain outlet pipe from the base of the trap, see diagram 15.1. Remove the condensate drain securing screw and carefully pull the trap forward, see diagram 13.11.
Drain the heat exchanger
Drain the heat exchanger using the drain point on the right hand side of the heat exchanger, see diagram 15.4.
54
15 Replacement of Parts
Diagram 15.6
14385
Diagram 15.7
14402
SECURING SCREW
SECURING SCREW
DRAIN POINT
HEAT EXCHANGER (with the burner and flow pipe removed for clarity)
Remove the heat exchanger
Undo the screws securing the anged elbow on the top right
hand side of the heat exchanger and remove the retaining clip
from the anged elbow, see diagram 15 5.
Remove retaining clip from the anged elbow on the bottom of
the heat exchanger, see diagram 15.4.
Remove screws securing the heat exchanger, one on top and one underneath the heat exchanger, see diagram 15.6.
Lift up heat exchanger slightly to disengage it from its hanging bracket.
Remove the heat exchanger by pulling forward, then pulling to the right to disengage the return pipe and tilting backwards to ease removal complete with sump. Discard the heat
exchanger and anged elbows.
Remove the burner
Remove the six anged nuts and two studs that secure the
burner, note that the two studs also hold the fan clamping bracket, see diagram 15.7.
Taking great care not to damage the surface of the burner.
NOTE: Replace the burner gasket and follow the tightening
sequence when re-tting the burner, see diagram 15.7.
NOTE: Fit all replacement gaskets and seals when re-tting
parts.
Refer to Section 12.
Fill the boiler heating system.
Re-pressurise (sealed sysem only)
Check for any leaks.
Vent all air from the system.
Test for gas tightness, earth continuity, polarity, short circuit and resistance to earth.
Light the boiler and carry out functional checks.
55
Diagram 15.8
13003
15 Replacement of Parts
Diagram 15.9
13003
Diagram 15.10
13004
15.15 Casing Seal
Refer to Section 13.8.
15.16 Access to User interface and Main PCB
For access, refer to section 15.1.
Hinge down the control box and unclip the rear cover to gain access.
Remove electrical connections from main PCB noting their positions for replacement.
Unclip main PCB and remove, see diagram 15.8.
Unclip user interface and remove.
For replacement, see diagram 15.9 and ensure that the user
interface connection cable is retted.
NOTE: When re-tting any of the control boards make sure
you support the control box to avoid straining hinges as you push down and clip back into place.
15.17 Control Box
For access, refer to section 15.1.
Hinge down the control box and unclip the rear cover to gain access.
Remove relevant electrical connections from main PCB and grommets from the control box.
MPORTANT: Support the control box whilst undoing the hinges.
Remove the hinge securing screws accessed from beneath the boiler and remove the control box, see diagram 15.10.
15.18 Fuse - Main PCB - Control Box
For access, refer to section 15.16.
The fuse is located at the top left hand corner of the main PCB, see diagram 15.8.
15.19 Installer Interface Electrical Cartridge
Remove the Installer Interface securing screw accessed from beneath the boiler.
Carefully pull down the electrical cartridge, disconnect the cables.
56
16 Spare Parts
Diagram 16.1
13013
1
2
3
4
5
6
7
8
Key No. Part No. Description GC No
1 0020020734 Fan *********
2 0020020763 Igniter unit *********
3 0020020781 Heating ow & return thermistor (2) *********
4 0020020735 Gas valve 12hx - 30hx *********
4 0020059600 Gas valve 35hx *********
5 0020020731 Spark Electrode *********
6 0020020728 Burner 12hx - 30hx *********
6 0020059601 Burner 35hx *********
7 0020023826 User interface *********
8 0020023825 Main P.C.B. *********
57
IMPORTANT. With regards to the Manual Handling Opera-
tions, 1992 Regulations, the following lift operation exceeds the recommended weight for a one man lift.
General recommendations when handling
Clear the route before attempting the lift. Ensure safe lifting techniques are used – keep back straight – bend us­ing legs. Keep load as close to body as possible. Do not twist – repo­sition feet instead. If 2 persons performing lift, ensure co-ordinated movements during lift. Avoid upper body/top heavy bending - do not lean forward/sideways. Recommend wear suitable cut resistant gloves with good grip to protect against sharp edges and ensure good grip. Always use assistance if required.
Removal of carton from delivery van
Recommend 2 person lift or 1 person with use of sack truck. If 1 person is performing lift, straddle the load, tilt and place carton into po­sition on truck. Recommend secure appliance onto truck with suitable straps. Ensure safe lifting techniques are used – keep back straight – bend using legs. Keep load as close to body as possible. If 2 persons performing lift, ensure co-ordinated movements during lift. Always use assistance if required.
Carriage of carton from point of delivery to point of installation – ground oor.
Recommend 2 person lift or 1 person with use of sack truck. If 1 person is performing lift, straddle the load, tilt and place carton into position on truck. Recommend secure appliance onto truck with suitable straps. Ensure safe lifting techniques are used – keep back straight – bend using legs. Keep load as close to body as possible. If 2 persons per­forming lift, ensure co-ordinated movements during lift. Clear the route before attempting the lift. If removing boiler from truck straddle the load and tilt forwards to facilitate secure grip. Ensure safe lifting techniques are used – keep back straight – bend using legs. Do not twist – repo­sition feet instead. Take care to avoid trip hazards, slippery or wet surfaces and when climbing steps and stairs. Always use assistance if
required.
Carriage of carton from point of delivery to point of installation – rst or higher oor, cellar.
Recommend 2-person lift or 1 person with use of sack truck. If 1 person is performing lift, straddle the load, tilt and place carton into position on truck. Recommend secure appliance onto truck with suitable straps. Ensure safe lifting techniques are used – keep back straight – bend us­ing legs. Keep load as close to body as possible. If 2 persons perform­ing lift, ensure co-ordinated movements during lift. Avoid upper body/top heavy bending - do not lean forward/sideways. Clear the route before attempting the lift. If removing boiler from truck straddle the load and tilt forwards to facilitate secure grip. Ensure safe lifting techniques are used – keep back straight – bend using legs. Do not twist – reposition feet instead. Take care to avoid trip hazards, slippery or wet surfaces and when climbing steps and stairs. Always use assistance if required.
Carriage of carton from point of delivery to point
of installation – roofspace.
Recommend 2-person lift. Ensure co-ordinated movements during lift. Avoid upper body/top heavy bending - do not lean forward/side­ways. Clear the route before attempting the lift. Take care to avoid trip hazards, slippery or wet surfaces and when climbing steps and stairs. When transferring appliance into roofspace, recommend 1 person to be in roofspace to receive the appliance and other person to be below to pass up and support appliance. Ensure safe lifting techniques are used – keep back straight – bend using legs. Keep load as close to body as possible. Always use assistance if required. It is assumed safe access,
ooring and adequate lighting are provided in the roof space. It is
recommended a risk assessment of the roof space area be carried out before moving the appliance into the area to take into account access,
stability of ooring, lighting and other factors, and appropriate measures
taken.
Unpacking of appliance from carton.
Recommend 2 persons unpack appliance from carton. Always keep working area clear. Recommend cut base end of carton and open
carton aps, then tilt boiler forwards from its side onto its base and
remove carton by sliding up over the boiler. Ensure safe lifting tech­niques are used – keep back straight – bend using legs. Keep load as close to body as possible. Always use assistance if required. Dispose
17 Manual Handling
of packaging in a responsible manner. Recommend wear suitable cut resistant gloves with good grip to protect against sharp edges and ensure good grip when handling appliance outside packaging.
Positioning of Appliance for Final Installation
– no obstructions.
This appliance is deemed to be a one person lift when removed from the carton. Fit bracket securely onto wall before lifting appliance into
position. Obtain rm grip on front and sides of appliance, lift upwards,
ensure stable balance achieved and lift upwards to position in place on bracket. Ensure safe lifting techniques are used – keep back
straight – bend using legs - when lifting load from oor level. Do not
twist – reposition feet instead. Keep boiler as close as possible to body throughout lift to minimise strain on back. Ensure co-ordinated movements to ensure equal spread of weight of load. Always use assistance if required. Recommend wear suitable cut resistant gloves with good grip to protect against sharp edges and ensure good grip when handling appliance.
Positioning of Appliance for Final Installation
– above worktop, foreseeable obstructions etc.
This appliance is deemed to be a one person lift when removed from the carton. Fit bracket securely onto wall before lifting appliance into
position. Obtain rm grip on front and sides of appliance, lift upwards,
onto worktop if practicable. Ensure stable balance achieved and lift upwards to position in place on bracket. If 2 persons positioning onto
bracket obtain rm grip at front and sides/base of boiler. Ensure co-
ordinated movements during 2 person lifts to ensure equal spread of weight of load. Ensure safe lifting techniques are used – keep back
straight – bend using legs - when lifting load from oor level. Do not
twist – reposition feet instead. Keep boiler as close as possible to body throughout lift to minimise strain on back. Avoid upper body/top heavy bending - do not lean forward/sideways. Always use assistance if re­quired. Recommend wear suitable cut resistant gloves with good grip to protect against sharp edges and ensure good grip when handling appliance.
Positioning of Appliance for Final Installation –
within compartment etc. restricting installation.
This appliance is deemed to be a one person lift when removed from the carton. Fit bracket securely onto wall before lifting appliance into
position. Obtain rm grip on front and sides of appliance, lift upwards,
onto worktop if practicable. Ensure stable balance achieved and lift upwards to drop into place onto bracket. If 2 persons positioning onto
bracket obtain rm grip at front and sides/base of boiler. Ensure co-
ordinated movements during 2 person lifts to ensure equal spread of weight of load. If 1 person positioning onto bracket recommend obtain
rm grip supporting base of boiler. Ensure safe lifting techniques are
used – keep back straight – bend using legs - when lifting load from
oor level. Do not twist – reposition feet instead. Keep boiler as close
as possible to body throughout lift to minimise strain on back. Always use assistance if required. Recommend wear suitable cut resistant gloves with good grip to protect against sharp edges and ensure good
grip when handling appliance.
Positioning of Appliance for Final Installation – in roof space restricting installation.
This appliance is deemed to be a one person lift when removed from the carton. Obtain rm grip on front and sides of appliance, lift up­wards, ensure stable balance achieved and lift upwards to drop into
place onto bracket. If 2 persons positioning onto bracket obtain rm
grip at front and sides/base of boiler. Ensure co-ordinated movements during 2 person lifts to ensure equal spread of weight of load. If 1 person positioning onto bracket recommend obtain rm grip support­ing base of boiler. Ensure safe lifting techniques are used - keep back
straight – bend using legs - when lifting load from oor level. Do not
twist – reposition feet instead. Keep boiler as close as possible to body throughout lift to minimise strain on back. Always use assistance if re­quired. Recommend wear suitable cut resistant gloves with good grip to protect against sharp edges and ensure good grip when handling appliance. It is recommended a risk assessment of the roof space area be carried out before moving the appliance into the area to take
into account access, stability of ooring, lighting and other factors, and
appropriate measures taken.
58
18 Declaration of Conformity
14506
59
Notes
60
Because of our constant endeavour for improvement, details may vary slightly from those shown in these instructions.
0020057279-02 02.08
Glow-worm, Nottingham Road, Belper, Derbyshire. DE56 1JT
0020057279
Loading...