BEFORE YOU BEGIN
Read these instructions completely and carefully. Save these instructions for future use.
Risk of electrical shock. Disconnect power before servicing or installing product.
Risk of injury or damage. Unit will fall if not installed properly. Follow installation instructions.
LED Area Light
WARNING
WARNING
Installation Guide
GEH-6019
• Best results will be obtained if installed and maintained according to the following recommendations.
CAUTION
Risk of injury. Wear safety glasses and gloves during
installation and servicing.
This device complies with Part 15 of the FCC Rules. Operation is subject to the following two conditions: (1) This device may not cause harmful interference, and (2) this device must accept any interference received, including interference that may cause undesired operation. This Class [A] RFLD complies with the Canadian standard ICES-003. Ce DEFR de la classe [ A ] est conforme à la NMB-003 du Canada.
Note: This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference when the equipment is operated in a commercial environment. This equipment generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio communications. Operation of this equipment in a residential area is likely to cause harmful interference in which case the user will be required to correct the interference at his own expense.
imagination at work
• The luminaire is designed to operate in ambient temperatures ranging from -40°C to +50°C and to be mounted horizontally to a vertical pole with LEDs facing down, as shown.
SPECIFICATIONS
• Weight: Maximum weight 30-37lbs. (14-17kg)
• IP Rating: Optical IP65, Standard Electrical Enclosure: UL 1598 Wet Location Rated
UNPACKING
1
• This luminaire has been properly packed so that no parts should have been damaged during transit.
• Inspect to conrm.
HANDLING
2
• Damage may occur if luminaire is improperly handled outside of pack.
• Do not impact or stack luminaire after removal from packaging.
MOUNTING
3
WARNING
Risk of injury or damage. Unit will fall if not installed
properly. Follow installation instructions.
Step 1 A. Drill pole per Fig. A if a square pole or Fig. B if a round
pole.
• I. 6-inch Arm
Luminaire
Cover
Nut Plate
3/8” bolts
#8-32 Screw
• II. Slip-Fitter “E” mount
Slip-Fitter mounts to 2-inch pipe (2-3/8” OD). Install Luminaire on pipe and tighten each mounting bolt to 10-12 foot-pounds, alternating between bolts.
& Lockwashers
Frame
Power Leads
B. Mount frame and nut plate assembly to pole with (2)
3/8” bolts and lockwashers. If a round pole, install Round Pole Adaptor.
C. Attach luminaire to frame feeding power leads
through Frame tube. Secure with (2) 3/8” bolts a lockwashers.
D. Install cover over Frame and secure with #8-32
Screw.
E. Splice power leads to incoming power. Install pole
cap. Strain relief for incoming power must be provided in the pole top by the customer.
WARNING
DO NOT REMOVE TETHERS FROM UNIT TO PREVENT DAMMAGED TO DOOR ASSEMBLY.
• To open Light Engine Door loosen both fastners CCW.
WARNING
Under no conditions should bolts be torqued to level greater than 12 ft-lbs. (16.3 N•m)
WIRING
4
NOTE: Make all electrical connections in accordance with the National Electrical Code and any applicable local code requirements.
INSTRUCTIONS FOR ROTATING
6
OPTICS
• Remove both hinge bolts (See Fig. 1)
• Take door out of hinge
• Remove Tethers
Do not remove tethers until door is out of hinge!
• Remove four retaining bolts on door (See Fig. 2)
NOTE: Verify that supply voltage is correct by comparing it to nameplate.
• Terminals are readily accessible on terminal board and will accept service leads ranging in size from AWG No. 16 through No. 6.
• Service leads (See xture labeling for supply wire temperature rating) should extend through mounting bracket approximately 7 inches.
• Attach service leads to terminal board as shown on luminaire nameplate.
• See table for screw torques (See Table 1).
• A wiring diagram is provided on a label in luminaire.
TABLE 1. Terminal Board Torque Table
Wire Range Copper Aluminum Torque (in lbs.) 10 - 16 SOL, STR 30 8 - 6 SOL, STR
STR6 SOL, STR
45
• Rotate optic 180 degrees
• Install four Retaining bolts and tethers
• Place door in hinge and bolt to housing
Do not reinstall door without tethers attached rst!
FIGURE 1
PHOTOELECTRIC CONTROL
5
• (If option present) - Photoelectric control receptacle should be oriented before control is installed.
• Loosen the two holding screws and rotate receptacle until “North” is directed as near as possible to true North.
• Tighten holding screws and install control.
• Lower PE receptacle to rmly seat it in this position. Then install PE control.