Electro Industries EMB-4, EMB-W-9, EMB-5, EMB-2, EMB-9 User Manual

Electro-HELPS XV
Electro-HELPS XV
Made in USA
ELECTRO-BOILER SPECIFICATIONS
A complete product line to fi t all your application needs
The Electro-Boiler™ has been heating America’s homes and businesses since 1980. We take pride in our craftsmanship and we use only the best materials to ensure a high quality product. We are commited to you and we are confi dent that you will be completely satisfi ed with the Electro-Boiler.
Submittal Sheets are available for each model at
www.electromn.com in the Dealer Support section.
Electro
Providing Comfort Through Efficient Energy Solutions
MINI-BOILER* MECHANICAL
Pressure Relief
Valve (30 PSIG)
Supply Pressure &
Temperature Gauge
Return Pressure &
Temperature Gauge
WarmFlo Sensor
Return
From
Radiation
Boiler Indicator Lights
Air Eliminator
Expansion Tank
Circulator Pump
Supply to Radiation
Manifold or Other Radiant Heat Application
*This plumbing arrangement also
applies to the Midsize boiler.
MINI-BOILER ELECTRICAL
BOILER
SOURCE
POWER
L1 L2
PUMP
NEUTRAL
120VAC
PUMP
POWER
L2L1 G
LMC
SHOWN WITH
COVER REMOVED
NO INTERNAL
WIRING SHOWN
2
BLUE
BLUE
R W C
T-STAT CABLE
1
2
STATUS INDICATOR LIGHTS
C
W
R
1
SLAB SENSOR
ANY 2-WIRE STAT OR END SWITCH CONTACT CAN BE USED TO OPERATE R & W, ELECTRO-STAT SHOWN AS EXAMPLE ONLY
TRANSFORMER FOR INTERNAL CIRCUITS ONLY. ZONE VALVES, ETC. MUST HAVE THEIR OWN 24V SOURCE
%LECTRO3TAT
%LECTRO3TAT

#
2
/
%
/
-
,
2
%
!
2
7


&
&,//24%-0
'2./. 2%$/&&
!24

Built-in
Electrical
Disconnect
Air Eliminator
Pressure Relief Valve (30PSIG)
Fill Drain
Return From
Radiation
ELECTRO-BOILER MECHANICAL
Return Pressure & Temperature Gauge
Supply to Radiation
Manifold or Other Radiant Heat Application
ELECTRO-BOILER ELECTRICAL
MINI-BOILER SERIES
STANDARD EQUIPMENT
▪ Controls and control wiring terminals
▪ LED indicator lights
▪ DC Power Relays
▪ Hi-limits: 1st - automatic reset at 160° F
2nd - manual reset at 205° F
▪ Circulator switching relay - 10-amp maximum
▪ Thermostat or end switch connection (R and W)
▪ Load management control provisions
▪ Heavy duty sheet metal enclosure
▪ 1 gl. Steel vessel ASME “H” Stamp (20-year
warranty)
▪ Pressure/temperature gauge
▪ Safety relief valve (30 PSI)
▪ Heating elements (20-year warranty)
▪ 2-year parts warranty
▪ EMB-W-9 senses target supply temperature and
modulates electric element
WATER FLOW REQUIREMENTS
Water Temperature Rise
Model
EMB-2 1.7 6.43 .01 .006 .85 3.21 .02 .006 .56 2.11 .004 .001
EMB-4 3.41 12.88 .08 .024 1.70 6.42 .04 .012 1.13 4.27 .02 .006
EMB-5 3.07 11.60 .06 .018 1.53 5.78 .02 .006 1.02 3.85 .02 .006
EMB-9 6.14 23.20 .23 .07 3.07 11.60 .10 .03 2.04 7.71 .06 .018
EMB-W-9 6.14 23.20 .23 .07 3.07 11.60 .10 .03 2.04 7.71 .06 .018
Note: Head Loss based on 110° F return temperature.
ELECTRIC SUPPLY
Model Volts Watts Amps kW Phase Btu/h
EMB-2 120 2,500 20.83 2.5 1-60 8,532
EMB-4 120 5,000 41.66 5 1-60 17,065
EMB-5 240 4,500 18.75 4.5 1-60 15,358
EMB-9 240 9,000 37.5 9 1-60 30,717
EMB-W-9 240 9,000 37.5 9 1-60 30,717
Flow - 10° F/6° C Head Loss Flow - 20° F/11° C Head Loss Flow - 30° F/16° C Head Loss
gpm lpm ft m gpm lpm ft m gpm lpm ft m
CLEARANCES
MINIMUM CLEARANCE FROM SUGGESTED MINIMUM COMBUSTIBLE SURFACES SERVICE CLEARANCE BACK 0 INCH 0 MM 0 INCH 0 MM LEFT 1 INCH 25 MM 6 INCHES 152 MM RIGHT 1 INCH 25 MM 6 INCHES 152 MM FRONT 1 INCH 25 MM 24 INCHES 610 MM TOP 1 INCH 25 MM 24 INCHES 610 MM BOTTOM REQUIRED CLEARANCE - 10 INCHES/254 MM
STANDARD EQUIPMENT
Staging - EB-MS-**
▪ Supply water sensing ▪ Regulates to front panel selected temperature ▪ Staging indicator lights ▪ DC Power Relays ▪ Hi-limits: 1 2nd - manual reset at 205° F ▪ Circulator switching relay - 10-amp maximum ▪ Thermostat or end switch connection (R and W) ▪ Utility load control provisions ▪ 2.2 gl. Steel vessel ASME “H” Stamp (20-year
warranty) ▪ Supply temperature/pressure gauge ▪ Safety relief valve (30 PSI) ▪ Optional standby boiler control kit, plug-in ▪ Standby switch and boiler contact
Modulating - EB-MA-**
▪ Same as EB-MS-** ▪ Modulates at a tighter temperature control ▪ Standby control package
Modulating - EB-MO-**
▪ Same as EB-MA-** ▪ Outdoor sensing with outdoor reset capability.
The target supply temperature ramps up as it is colder outside.
st
- automatic reset at 190° F
PLUS
PLUS
MIDSIZE SERIES
WATER FLOW REQUIREMENTS
Water Temperature Rise
Model
EB-M*-10 6.82 25.82 .01 .003 3.41 12.91 .004 .001 2.27 8.59 .001 .001
EB-M*-15 10.23 38.73 .03 .009 5.11 19.34 .01 .003 3.41 12.91 .004 .001
EB-M*-20 13.65 51.66 .07 .02 6.82 25.01 .02 .006 4.55 17.22 .01 .003
* = S, A, or O
Note: Head Loss based on 110° F return temperature.
ELECTRIC SUPPLY
Model Volts Watts Amps kW Phase Btu/h CB
EB-M*-10 240 10,000 41.66 10 1-60 34,130 60
EB-M*-15 240 15,000 62.50 15 1-60 51,195 60 + 30
EB-M*-20 240 20,000 83.33 20 1-60 68,260 60 + 60
* = S, A, or O
Flow - 10° F/6° C Head Loss Flow - 20° F/11° C Head Loss Flow - 30° F/16° C Head Loss
gpm lpm ft m gpm lpm ft m gpm lpm ft m
CLEARANCES
MINIMUM CLEARANCE FROM SUGGESTED MINIMUM COMBUSTIBLE SURFACES SERVICE CLEARANCE BACK 0 INCH 0 MM 0 INCH 0 MM LEFT 1 INCH 25 MM 12 INCHES 305 MM RIGHT 1 INCH 25 MM 6 INCHES 152 MM FRONT 1 INCH 25 MM 24 INCHES 610 MM TOP 1 INCH 25 MM 24 INCHES 610 MM BOTTOM REQUIRED CLEARANCE - 18 INCHES/457 MM
TS SERIES
STANDARD EQUIPMENT
Staging - EB-S-**
▪ Supply water sensing ▪ Regulates to front panel selected temperature ▪ Staging indicator lights ▪ DC Power Relays ▪ Hi-limits: 1st - automatic reset at 190° F 2nd - manual reset at 205° F ▪ Circulator switching relay - 10-amp maximum ▪ Thermostat or end switch connection (R and W) ▪ Utility load control provisions ▪ 6.5 gl. Steel vessel ASME “H” Stamp (20-year
warranty) ▪ Supply temperature/pressure gauge ▪ Safety relief valve (30 PSI) ▪ Optional standby boiler control kit, plug-in ▪ Standby switch and boiler contact
Modulating - EB-WA-**
▪ Same as EB-S-** ▪ Modulates at a tighter temperature control ▪ Standby control package
Modulating - EB-WO-**
▪ Same as EB-WA-** ▪ Outdoor sensing with outdoor reset capability.
The target supply temperature ramps up as it is colder outside.
PLUS
PLUS
WATER FLOW REQUIREMENTS
Water Temperature Rise
Model
EB-**-13 9.21 34.86 .03 .009 4.60 17.41 .01 .003 3.07 11.62 .004 .001
EB-**-18 12.28 46.49 .06 .018 6.14 23.24 .02 .006 4.09 15.48 .01 .003
EB-**-23 15.35 58.11 .09 .027 7.67 29.03 .02 .006 5.11 19.34 .01 .003
EB-**-27 18.43 69.77 .13 .039 9.21 34.86 .03 .009 6.14 23.24 .02 .006
EB-W*-13-2 9.21 34.86 .03 .009 4.60 17.41 .01 .003 3.07 11.62 .004 .001
EB-W*-27-2 18.43 69.77 .13 .039 9.21 34.86 .03 .009 6.14 23.24 .02 .006
** = S, WA, or WO Note: Head Loss based on 110° F return temperature.
ELECTRIC SUPPLY
Model Volts Watts Amps kW Phase Btu/h CB
EB-**-13 240 13,500 56 13.5 1-60 46,075 60 + 30
EB-**-18 240 18,000 75 18 1-60 61,434 60 + 60
EB-**-23 240 22,500 94 22.5 1-60 76,792 60 + 60 + 30
EB-**-27 240 27,000 113 27 1-60 92,151 60 + 60 + 60
EB-W*-13-2 208 13,500 37.5 13.5 3-60 46,075 50
EB-W*-27-2 208 27,000 75 27 3-60 92,151 100
Flow - 10° F/6° C Head Loss Flow - 20° F/11° C Head Loss Flow - 30° F/16° C Head Loss
gpm lpm ft m gpm lpm ft m gpm lpm ft m
CLEARANCES
MINIMUM CLEARANCE FROM SUGGESTED MINIMUM COMBUSTIBLE SURFACES SERVICE CLEARANCE BACK 0 INCH 0 MM 0 INCH 0 MM LEFT 1 INCH 25 MM 12 INCHES 305 MM RIGHT 1 INCH 25 MM 6 INCHES 152 MM FRONT 1 INCH 25 MM 24 INCHES 610 MM TOP 1 INCH 25 MM 24 INCHES 610 MM BOTTOM REQUIRED CLEARANCE - 16 INCHES/406 MM
** = S, WA, or WO
STANDARD EQUIPMENT
Staging - EB-CA-**
▪ Supply water sensing ▪ Regulates to front panel selected temperature ▪ Staging indicator lights ▪ Heavy duty contactors ▪ Hi-limits: 1st - automatic reset at 190° F 2nd - manual reset at 205° F
▪ Circulator switching relay - 10-amp maximum
▪ Thermostat or end switch connection (R and W)
▪ Utility load control provisions ▪ 13.1 gl. Steel vessel ASME “H” Stamp (20-year
warranty)
▪ Supply temperature/pressure gauge ▪ Safety relief valve (30 PSI) ▪ Optional standby boiler control kit, plug-in ▪ Standby switch and boiler contact
Staging - EB-CO-**
▪ Same as EB-CA-** ▪ Adds outdoor reset capability
PLUS
COMMERCIAL SERIES
WATER FLOW REQUIREMENTS
Water Temperature Rise
Model
Flow - 20° F/6° C
Head Loss
gpm lpm ft m gpm lpm ft m gpm lpm ft m
EB-C-18-48 6.14 23.24 .002 .0006 4.09 15.48 .001 .0003 3.07 11.62 .0008 .0002
EB-C-36-48 12.28 46.49 .01 .003 8.19 31.00 .004 .001 6.14 23.24 .002 .0006
EB-C-54-48 18.43 69.77 .02 .006 12.28 46.49 .01 .003 9.21 34.86 .01 .003
EB-C-27-20 9.21 34.86 .01 .003 6.14 23.24 .002 .0006 4.60 17.41 .001 .0003
EB-C-40-20 13.82 52.32 .01 .003 9.21 34.86 .01 .003 6.91 26.16 .003 .0009
EB-C-27-24 9.21 34.86 .01 .003 6.14 23.24 .002 .0006 4.60 17.41 .001 .0003
EB-C-40-24 13.82 52.32 .01 .003 9.21 34.86 .01 .003 6.91 26.16 .003 .0009
EB-C-31 10.75 40.69 .06 .018 7.16 27.10 .07 .021 5.37 20.33 .07 .021
EB-C-36 12.28 46.49 .06 .018 8.19 31.00 .06 .018 6.14 23.24 .07 .021
Note: Head Loss based on 110° F return temperature.
ELECTRIC SUPPLY
Model Volts Watts Amps kW Phase Btu/h CB
EB-C-18-48 480 18,000 22 18
EB-C-36-48 480 36,000 44 36
EB-C-54-48 480 54,000 65 54
EB-C-27-20 208 27,000 75 27
EB-C-40-20 208 40,500 113 40.5
EB-C-27-24 240 27,000 65 27
EB-C-40-24 240 40,500 98 40.5
EB-C-31 240 31,500 131 31.5
EB-C-36 240 36,000 150 36
Flow - 30° F/11° C
3-60
3-60
3-60
3-60
3-60
3-60
3-60
1-60
1-60
61,434 30
122,868 60
184,302 80
92,151 100
138,226 150
92,151 80
138,226 125
107,509 100 + 80
122,868 100 + 100
Head Loss
CLEARANCES
MINIMUM CLEARANCE FROM SUGGESTED MINIMUM COMBUSTIBLE SURFACES SERVICE CLEARANCE BACK 0 INCH 0 MM 0 INCH 0 MM LEFT 1 INCH 25 MM 16 INCHES 406 MM RIGHT 1 INCH 25 MM 6 INCHES 152 MM FRONT 1 INCH 25 MM 24 INCHES 610 MM TOP 1 INCH 25 MM 24 INCHES 610 MM BOTTOM REQUIRED CLEARANCE - 16 INCHES/406 MM
Flow - 40° F/16° C
Head Loss
ZONE CONTROLLER
This will simplify your wiring and make zoning applications much easier. In addition, enhanced communicating features have the ability to stage the electric boiler based upon the connected zone capacity.
Standard Features
• Terminal block wiring, visual wiring layout
• Indicator lights showing zone operation
• 24-volt, 40VA transformer
120/208/240 connection
• Fuse protection
• Priority option
• Dual temperature operation
• Applies to digital or
standard thermostats
• Dial switch, select each zone capacity
All Others
EB-ZXA-1 - universal, pumps or valves, non-communicating, for any boiler EB-ZS-4 - automatic staging system for Brand X boilers or dual EB-R, -L, -E Series EB-ZC-4 - wiring and convenience interface, isolated boiler end switch EB-5415A - low cost, 2 or 3 zones, sheds one boiler stage (Mini-Boiler enhancement)
Pumps, Actuators, Valves
EB-ZTA-1 - install within boiler cabinet EB-ZEA-1 - with enclosure and 40VA transformer EB-ZEA-2 - add additional 4, enclosure and 40VA
Pumps
EB-Z2P - two pumps with priority and dual temp.
Zone Valves
EB-ZTS-1 - install within boiler cabinet, encl. option EB-ZTS-2 - add additional 4, enclosure and 40VA
SLAB STAT
Sensing and controlling the system based upon radiant fl oor surface temperature or the concrete mass has very positive benefi ts. Radiant fl oor air stat in the same area as a forced air roomstat presents serious control problems. A remote sensing slab stat for the radiant fl oor removes this issue.
Remote sensing slab stat is required for storage applications.
ES-24-BR
SWITCHING RELAY - EE-5051 MULTI-BOILER - EB-C-STG5
This DPDT 24-volt switching relay provides a convenient solution to any AC or DC application.
OTHER OPTIONS
Ideal for zone pumps
24V coil
120V, 10A, contact sets
Easy to wire and nicely packaged
CIRCULATING PUMPS INSTALLATION PLUMBING KITS
Electro stock includes three pumps sizes and three fl ange kit (with valve) sizes.
Electrically connects between 2nd and 3rd, 3rd and 4th, etc.
SOT-1 Switchover to standby, total run time
5701 Single feed bus for 2 CB’s (SQ-D CB)
5702 Single feed bus for 3 CB’s (SQ-D CB)
EB-S-SB Dual boiler option for EB-S Series
WF-ANZ5 WarmFlo Analyzer, now applicable to WO and
WA Series
For convenience of installation, Electro has plumbing kits tailored for each boiler series. See price sheet for various models and confi guration.
Specifi cations subject to change without notice, all rights reserved.
Loading...