Duro-Last Duro-Guard Sopravap'r User Manual

DURO-GUARD® SOPRAVAP’R
DESCRIPTION:
Duro-Guard
®
Sopravap’r is a self-adhesive vapor barrier membrane composed of SBS modified bitumen adhesive on the bottom surface and a tri­laminated woven polyethylene on the top surface. A silicone release film covers the self-adhesive on the bottom surface.
Sopravap’r can be used within a Duro-Last
®
roof system to minimize vapor transmission. Duro-Last recommends the use of vapor barriers, however it is the responsibility of the Duro-Last contractor of record to ensure that all applicable specifications, building codes, regulations and ordinances are complied with and followed. A roofing professional, such as a consultant or architect, should be utilized for correct roof system design prior to installing any roof system.
Sopravap’r can provide a durable, walkable, temporary surface that protects the decking for up to 4 months until a Duro-Last system can be installed (See Figure 1). Temporary roofs do not carry any type of warranty and must only be used at the discretion of a roofing consultant or architect.
The installing contractor is responsible for following applicable building, plumbing and electrical codes.
Sopravap’r may be installed on steel decks without a primer. The following substrates will require the use of Elastocol Stick primer prior to installing the Sopravap’r:
Structural Concrete (poured in place or precast)
Gypsum (poured in place or precast)
Lightweight Concrete (insulating or cellular)
Wood (Plywood, OSB or Lumber)
Cement Block/Masonry
PRECAUTIONS:
1. Read Safety Data Sheets (SDS) prior to using.
2. Wear proper personal protective equipment, such as gloves and eye protection, per the SDS.
ORDERING:
Rolls may be ordered individually. Each roll measures 3.75 ft. by 133 ft. and will cover 465 square feet with a 3-inch overlap.
BENEFITS
Meets IECC air barrier requirements for
mechanically fastened roof systems
Quick release film
Self-sealing
Temporarily protects against inclement weather
Slip resistant
Substrate board not required for most
applications.
100% UV protection for up to 4 months
Puncture resistant
No primer required on steel decks
Ideal for mechanically fastened or adhered
systems
Highly resistant to work crew traffic
ACCEPTABLE SUBSTRATES:
Prior to installation of the Sopravap’r, the substrate must be smooth and level without significant surface irregularities or depressions. It must be clean, dry and free of grease, dust and loose debris. Do not apply to wet or damp surfaces. Concrete and gypsum decks must be cured prior to installation.
Figure 1. Duro-Guard Sopravap’r as temporary roof
Duro-Last, Duro-Guard and “World’s Best Roof” are registered marks owned by Duro-Last, Inc.
1 of 2www.duro-last.com 800-248-0280
Created: 01/15/2014
1
DURO-GUARD® SOPRAVAP’R
INSTALLATION:
1. Limitations
a. The minimum ambient and surface
temperature before application should be 14 F and rising.
b. Do not use during wet weather. c. Do not use on wet substrates. d. Do not use on dirty or greasy substrates. e. Do not use on substrates that show signs of
deterioration or loss of structural integrity.
f. Do not use product after expiration date.
2. Vapor barrier (immediately covered by a roof system)
a. Install according to the 6 steps shown in the
pictures below.
3. Temporary roof (not immediately covered by a roof system)
a. Install according to the 6 steps shown below. b. Cover and seal all T joints, transitions and
any other openings with Sopramastic.
TABLE 1. PHYSICAL PROPERTIES
Standards Results
Thickness - 31.5 mils
Weight - 0.16 lb/sqft
Tensile Strength ASTM D 5147 64 lbf/in x 88 lbf/in
Elongation ASTM D 5147 52% x 24%1
Cold Bending ASTM D 5147 -31° F
Static Puncture ASTM D 5602 90 lbf
Tear Resistance ASTM D 5601 84 lbf x 90 lbf
Lap Adhesion ASTM D 1876 138 lbf
Water Absorption ASTM D 5147 0.1% maximum
Peel Resistance ASTM D 903 83 lbf/ft
Water Vapor Permeance
Air Permeability
Values are shown for both machine and cross machine
directions. The machine direction results are listed first.
2
All values are nominal.
ASTM E 96
(Pro. B)
ASTM E 283
(75 Pa)
2
.017 perm
< 0.007 L/sec
1
1
.m2
1. Roll out the Sopravap’r over a clean, dry
deck.
4. On steel decks, at the end of a roll, install
a metal plate (6 in. by 42 in.) to support the membrane end lap between the metal flutes ensuring a complete end lap seal. End laps must overlap by 6 inches.
2. Once the membrane is in place, while holding the membrane tight, peel off the silicone release film by pulling diagonally.
5. The membrane’s superior strength offers extra protection from heavy foot traffic during installation. The slip-resistant surface allows for safe movement across the roof.
3. Install subsequent rolls of membrane in the same way, taking care to overlap the longitudinal joints by 3 inches.
6. Once installation is complete, the Sopravap’r membrane temporarily protects against inclement weather. If not immediately covered, follow extra steps per 3a and 3b in the instructions above.
Duro-Last, Duro-Guard and “World’s Best Roof” are registered marks owned by Duro-Last, Inc.
2 of 2www.duro-last.com 800-248-0280
Created: 01/15/2014
Loading...