Instructions
Pilot-controlled PCVQ
DN 100 - DN 250
PN 16 / PN 25
Table of Contents
1 Safety Notes ...................................................... 2
2 Definition of Application ............................ 2
3 Description .......................................................... 2
3.1 Construction ......................................................... 2
3.2 Mode of Operation ........................................... 2
4 Technical Data .................................................. 3
5 Scope of Delivery ............................................. 3
6 Assembly ............................................................. 4
6.1 Prior to Assembly ............................................... 4
6.2 Installation Position,
Installation Place ................................................ 4
6.3 When Installaling observe ............................. 4
6.4 Impulse Tube Installation ................................ 4
6.5 Insulation .............................................................. 4
6.6 Installation Scheme ........................................... 5
6.7 Assembly Drawings, Dimensions ................ 6
7 Start-up ..................................................................8
7.1 Required static Pressure .................................. 8
7.2 Leak and Pressure Test ...................................... 8
7.3 Filling the System ............................................... 8
7.4 Start-up .................................................................. 8
7.5 Putting out of Operation ................................. 8
7.6 Flow Rate Adjustment ...................................... 9
7.7 Flow Adjusting Curves ................................... 10
7.8 Sealing ................................................................. 12
7.9 Adjustement of the Throttle Valves .......... 12
7.10 Function Test ..................................................... 12
8 Trouble Shooting ......................................... 13
9 Replacement of Valve,
Actuator, Trims .............................................. 14
9.1 Dismounting and
Mounting Actuator Valve ............................. 14
9.2 Replacement of Trim Valve VFQ 21 ........... 16
9.3 Dismounting,
Mounting Actuator AVP-F ............................ 17
9.4 Replacement of Trim Valve AVP-F .............. 17
73696700 DH -SMT/SI VI.JA.G2. 02 © Danfoss 11/2006 1

Pilot controller AVP-F
(Flow Rate)
Adjusting throttle
Throttling element DE
Valve unit PCV-VFQ 21
Throttling valv
e
hrottling valve
only by DN150-250
Instructions Pilot-controlled PCVQ DN 100 - DN 250 (PN 16, PN 25)
1 Safety Notes To avoid injury of persons
and damages to the device,
it is absolutely necessary to
carefully read and observe
these Instructions.
Necessary assembly, start-up, and maintenance
work may be performed only by qualified and
authorized personnel.
Please comply with the instructions of the
system manufacturer or system operator.
2 Definition of
Application
3 Description
The controller is used for flow rate limitation of
water for heating, district heating and cooling
systems.
The admissible medium temperatures depend
on the design and comprise 5 to 140 °C,
5 to 150 °C, 5 to 200 °C.
The technical data on the rating plates
determine the use.
3.1 Construction
Flow Rate Limitation
If the flow rate reaches the adjusted setpoint, the
differential pressure increases at the adjusting
throttle. This differential pressure acts on the
actuator AVP-F via the impulse tubes and the
valve AVP-F closes. Consequently, the valve of
the valve unit is throttled, too, and the flow rate
is restricted.
3.2 Mode of Operation
The control unit consists of the PCV-VFQ21
valve unit, installed in the main pipe and AVP-F
installed as pilot controllers in the bypass. In the
bypass line, a throttle element is installed in front
of the pilot controller.
The controller keeps the differential pressure
across the main valve flow restrictor on a
constant level and restricts the flow rate to the
adjusted setpoints.
The valve and the pilot valves are pressurebalanced.
The setpoint for the flow rate limitation is
adjusted at the adjusting throttle of the valve
unit.
The valve unit in the main pipe is opening on
rising pressure. The pilot controller in the bypass
line is closing on rising pressure.
2 VI.JA.G2. 02 © Danfoss 11/2006 DH-SMT/SI

Instructions Pilot-controlled PCVQ DN 100 - DN 250 (PN 16, PN 25)
4 Technical Data Technical data, see rating plates and the PCV
data sheet.
5 Scope of Delivery
DN 100, DN 125
Assembly kit valve unit PCV-VFQ 21 Pilot controller DN 25
AVP-F
Throttling element
Cu pipe Ø 6 × 1 × 1500 mm
Cu pipe Ø 10 × 1 × 3000 mm
DN 150, DN 250
Assembly kit valve unit PCV-VFQ 21 Pilot controller DN 40
AVP-F
Throttling element
Cu pipe Ø 6 × 1 × 1500 mm
Cu pipe Ø 10 × 1 × 3000 mm
DH-SMT/SI VI.JA.G2. 02 © Danfoss 11/2006 3

pin only
weld
do NOT
weld
Instructions Pilot-controlled PCVQ DN 100 - DN 250 (PN 16, PN 25)
6 Assembly 6.1 Prior to Assembly:
Depressurized system before any
assembly work !
CAUTION!
• Clean pipeline system.
• Install strainer in front of the controller.
• Install shut-off units in front of and behind
the controller.
6.2 Installation Position, Installation Place
• Installation is only permitted in horizontal
pipelines with the actuators hanging in a
downward position.
• The controller may be installed in the
supply as well as in the return line.
6.3 When installing:
• Observe direction of flow.
• Design with welded ends:
6.4 Impulse Tube Installation
See installation scheme, section 6.6.
For CU pipes Ø 10 × 1, insert sockets 1 on both
sides.
1
Care for correct position of the cutting rings 2.
2
6.5 Insulation
The diaphragm actuators must not be insulated
when insulating system parts.
• Loads on the valve body and the throttle
element by the pipes are not permitted.
4 VI.JA.G2. 02 © Danfoss 11/2006 DH-SMT/SI

Bypass controller
PCVQ
Throttling
elemen
t
Throttling valve
Throttling valve
(only
by DN 150 - 250)
Valve unit PCV - VFQ 21
Pilotregler AVP-F
lay impulse tube during mounting
Bypass controller
PCVQ
Throttling
element
Throttling valve
Throttling valve
(only by DN 150 - 250)
Valve unit PCV - VFQ 21
Pilot controller AVP-F
Instructions Pilot-controlled PCVQ DN 100 - DN 250 (PN 16, PN 25)
6 Assembly
6.6 Installation Scheme
Installation in the Return Line
Installation in the Supply Line
DH-SMT/SI VI.JA.G2. 02 © Danfoss 11/2006 5

H1 H2
D2
Cu pipe
Ø 10 × 1
La
y when assembling.
CU pipe Ø 6 ×1
La
y when assembling.
244
160
ca. 1000
A
159
75
L1
DN 25: pipe Ø33.7 × 3.2
Material:
ST 35.8
(not part of the delivery)
DN 25 SW 50
Pilot controller AVP-F
Throttling elemen
t
Instructions Pilot-controlled PCVQ DN 100 - DN 250 (PN 16, PN 25)
6 Assembly 6.7 Assembly Drawings, Dimensions
DN 100 - DN 125
6 VI.JA.G2. 02 © Danfoss 11/2006 DH-SMT/SI