Danfoss ECmat Aqua is a hot-water oor heating
mat with low construction height (approximately
10mm), which makes it especially suitable for
renovation jobs in existing buildings.
The capacity of your Danfoss ECmat Aqua installation is strongly dependent on the capacity of the
1�1 Potential application examples
Substrate
Surface
Floor leveling compound
Anhydride screed
Substrate
Surface
Floor leveling compound Primer
Anhydride screedPrimer
Timber ooring (parquet, boarding) or on existing thermal insulation
Load distribution mat,
min. 9mm, glued (not
screwed)
Load distribution mat,
min. 9mm, glued (not
screwed)
circulation pump. Please consult your plumber to
determine the capacity of your heating system.
Each room with oor heating should be
equipped with its own thermostatic room temperature control, such as a Danfoss RTL valve
with TH function (not included).
Construction height
min. 13mm, including
pipe
Construction height
min. 28mm, including
pipe
Screed, concrete, stone, etc�
Construction height
min. 13mm, including
pipe
Construction height
min. 28mm, including
pipe
Laid in staggered
sections
Laid in staggered
sections
Laid in staggered
sections
Laid in staggered
sections
UK
Please note!
• Consult your plumber for any work on your
existing heating system. They have the
necessary experience and will be pleased to
assist you
• Remember to t expansion joints at the junctions of heated and unheated areas
Congratulations on the purchase of your new
Danfoss product
2�1 Initial planning
Please take the manufacturer’s data into consideration with regard to subsequent covering of
the heating mat with oor levelling compound,
screed or the like. The selected materials must be
suitable for use on top of a oor heating system
and should have a certain degree of elasticity
Installation is considerably simplied if the tting
location for control is specied in the planning
stage. The control and accessories, such as the
manifold, should remain easily accessible after
installation.
Please observe the following installation guidelines in order to obtain good results and longterm trouble-free operation.
Plan: Follow the Danfoss installation instructions
step by step. This will avoid any problems during
mat installation and adjustment. Sketch the oor
plan of your room on the mat sheet (Figure1)
Draw your Danfoss ECmat Aqua mat (width
48mm) on the oor plan with a separation of
2cm between the runs. The woven glass net
can be cut as necessary to change directions
(Figure2).
Figure 2
UK
Figure 1
2�2 Preparation and cleaning
Before installing the heating mat, you must prepare the oor surface (Figure3).
Transfer the markings from your drawing to the
oor so you can see exactly where you should
start and stop
The substrate must be level, structurally sound,
and free from dust, grease and oil.
5
Installation Guide Danfoss ECmat Aqua
You should preferably start laying the heating mat
close to the connection point.
All connections should remain readily accessible
afterwards.
Always connect the RTL valve (not included) to
the end of the hose (supply line), not to the start.
If you use an RTL control with TH function to
Figure 3
It may be necessary to apply a bonding agent
(primer), depending on the substrate. This ensures
proper bonding of the heating mat.
2�3 Laying the mat
Remove the protective lm from the mat and roll
it out according to your oor plan, with the self-
adhesive side facing down (Figure4).
adjust the room temperature, install the RTL valve
(not included) ahead of the heating mat (see the
installation instructions for Danfoss controls).
Figure 5a
The length of the pipe attached to woven mat has
been selected to match the required connection
Figure 4
When you encounter an obstacle (wall, cabinet,
toilet, end of the room, etc.), cut the woven glass
net (but not the pipe) and continue laying in
another direction (Figures5a & 5b).
length.
The pipe length is calculated to ensure that in the
worst case, you can always return the pipe along
the same path as you used when rolling out the
mat.
You can use the pipe couplings and angle connectors available as accessories to replace a damaged
pipe section or extend a pipe that is too short, if
necessary.
Before lengthening the pipe, you should obtain
the approval of your plumber.
Figure 5b
If you intend to install several Danfoss ECmat
Aqua mats in the same room, you must select the
right distributor in advance.
Distributors are available for installation of a
single mat as well as for installation of two or
three mats.
2�4 Intermediate test
After completing all the installation steps, you
should recheck the entire procedure.
Note that when more than one mat is installed,
all mats must be the same size�
Examples:
5m² = 2 x 2.5m², corresponding to 2 x 3m² (mats
must be shortened)
6m² = 2 x 3m², corresponding to 2 x 3m² (packing unit)
7m² = 3 x 2.33m², corresponding to 3 x 3m²
(mats must be shortened)
At this point you should have arrived at the manifold with the ends of the connecting lines. Cut the
pipes to length with straight, unchamfered and
burr-free edges. This is necessary to ensure secure
tting of the connector components.
Note: Push the ends of the connecting lines into
the manifold until they reach the stop.
Attached pipes can be disconnected by slightly
lifting the locking ring. This intelligent technology
eliminates the need for tools.
The piping of the Danfoss ECmat Aqua mat should
now become warm.
UK
Check that all parts have been installed or
connected properly. Are all connectors rmly
secured?
Start up your heating system again with the RTL
valve (not included) closed.
After slowly lling the system with water, check
all connections and joints for leaks (visually or by
touch).
Danfoss can accept no responsibility for possible errors in catalogues, brochures and other printed material. Danfoss reserves
already on order provided that such alterations can be made without subsequential changes being necessary in specications alre
companies. DEVI and the DEVI logotype are trademarks of Danfoss A/S. All rights reserved.
Electric Heating Systems
Ulvehavevej 61
7100 Vejle
Denmark