Danfoss 145H3665, 145H3666, 145H3667 Installation guide [de]

Installation Guide

Service Kit 145H3665 / 145H3666 / 145H3667 for exchange of HEX on EvoFlat substation

Service Kit 145H3665 / 145H3666 / 145H3667 für Austausch von HEX auf EvoFlat station

TPC-M valve 003L3952

HEX 26 145H3020 / HEX 40 145H3021 / HEX 60 145H3019

Hairpin 307.011* O-ring 145.083* Washer 326.266* Filter 145H3554*

Hairpin 307.012*

* Also available in spare part set 145H3018 / Auch in Ersatzset 14BH3018 erhältlich

English - GB:

Shut off all energy sources to the unit - including electrical connections before performing maintenance work, - i.e. make sure that all ball valves on the substation and connection to the household piping are closed before performing maintenance work.

Remember to turn on all energy sources/open ball valves again after completion of maintenance work.

German - DE:

Die gesamte Energieversorgung der Station, hierunter auch die gegebenenfalls vorhandene Stromzufuhr, muss vor den Wartungsarbeiten unterbrochen werden. Es ist daher sicher zu stellen, dass alle Kugelhähne geschlossen sind. Der elektrische Anschluss und der erforderliche Schutz müssen durch einen Fachmann in Übereinstimmung mit den örtlichen Vorschriften vorgenommen werden.

Nach dem Abschluss der Wartungsarbeiten ist die Energieversorgung der Station wieder herzustellen.

Danfoss District Energy

VI.JV.N1.5B

DKDHR 1

Installation Guide

Service kit HEX for EvoFlat

 

 

1

1a

1b

1c

~

2 DKDHR

VI.JV.N1.5B

Danfoss District Energy

Danfoss 145H3665, 145H3666, 145H3667 Installation guide

Installation Guide

Service kit HEX for EvoFlat

 

 

2

 

2a

 

 

 

2b

 

 

 

145H3554

 

 

 

2c

 

 

Danfoss District Energy

VI.JV.N1.5B

DKDHR

3

Loading...
+ 5 hidden pages