Contech Construction A-2026 Installation Manual

A-2000/A-2026
ENGINEERED SOLUTIONS
Unloading, Handling and Installation Guide
Preface
This instruction book is for your crews. Distribute it to help them install Contech® A-2000/A-2026 correctly. They are flexible pipes that must be installed following the trench construction, bedding, haunching, initial backfill, and other requirements of ASTM D 2321,“Standard Recommended Practice for Underground Installation of Flexible Thermoplastic Sewer Pipe.”
Don’t assume experienced workers know all the answers. Review these instructions with your supervisors and crews. It can mean a better job for you and your customer.
We suggest that you adopt a policy of performance testing the first few manhole runs. It will give you an early check that installation procedures are correct.
If you have any questions about these instructions, call your Contech Dealer or your Contech Sales Engineer, or carefully review the installation guide in the Contech A-2000/A-2026 catalogs and ASTM D 2321.
2 3
Contents
Cold Weather Installation .........................5
Unloading and Handling .........................6
Trenching ...............................................8
Installation Tips .......................................9
Assembly of Pipe ..................................10
A. Gasket/Pipe Connection ............. 10
B. Manhole Connection ...................12
C. Field Cutting Pipe .......................14
D. Caps .........................................14
E. Mechanical plugs ........................14
F. Tapping/Saddle Connections ........15
Repairs ................................................18
Installation of Pipe ................................ 20
A. Pipe Zone/Embedment Material....20
B. Deflection Control .......................26
Deep Laterals .......................................27
Special Notes .......................................28
This safety alert symbol indicates important safety messages.
When you see this symbol, be alert to the possibility of personal injury and be sure you understand the message that follows.
Terms You Should Know
Alerts you to
hazards or unsafe practices that CAN result in severe personal injury or property damage.
Messages about procedures
or actions that must be followed for safe handling and installation of A-2000/A-2026 Pipe.
Falling or rolling pipe can cause severe personal injury or death.
Read and follow all safety instructions before unloading pipe.
4 5
Cold Weather Installation
1. Handle the pipe with more care in cold weather. PVC becomes more brittle as temperatures drop. When placing embedment materials in deep trenches and temperatures 0° - 32° F, it is
required to use smaller aggregate (3/4­inch max.) and limit the height of stone dump to 20 feet.
2. Rubber gaskets become harder as the temperature decreases, gaskets tend to compress less, and when combined with PVC bells that become more installation sensitive, jointing becomes less forgiving. Proper bell-spigot alignment, adequate bell and spigot lubrication, and recommended joining procedures (-i.e. bar and block) all become more essential as temperature decreases. In addition, it is recommended to store the gaskets in a warm place prior to use.
Unloading and Handling
The following equipment is recommended for unloading pipe pallets:
Forklift with full-length forks to engage entire
pallet width, front-end loader or backhoe with fork adapters full length to engage entire pallet width.
Nylon lifting slings of sufficient strength and
length to safely handle entire pallet. Do not stand or ride on the pipe load during unloading.
NOTE: Pipes sizes 18” and less are palletized with steel straps around a wood frame. Full trailer width pallets (21” to 36”) are not framed. Only forks of sufficient length to engage entire pallet width are recommended for unloading.
6 7
Failure to follow these instructions can result in serious injury or death and/or damage to pipe.
1. Only trained and authorized equipment operators are to
be permitted to unload the trailer.
2. Wear approved safety hat and shoes, gloves, and
eye protection.
3. Park the truck and trailer on level ground before you
start unloading.
4. Keep all unauthorized persons clear of the area when
the driver releases the binders from the trailer and during unloading.
5. Do not release steel strapping around the wood
frame until the pallets have been placed on level ground and will not be moved again as a unit.
6. Know the capabilities and rated load capacities of
your lifting equipment. Never exceed them.
7. Do not stand or ride on the load of pipe while it is
being unloaded. Do not stand beneath or near the pipe when it’s being unloaded.
8. If unloading at multiple points,
secure pallets between drop off points. For each unit of four pallets, always unload the top pallets first. (See diagram)
9. Never attach chains or wire
rope to the pipe. They could damage the pipe.
10. Do not push pallets off the trailer or permit
pipe to drop to the ground.
11. Do not drag A-2000/A-2026 Pipe across
the ground.
12. Do not stack A-2000/A-2026 Pipe over two
pallets high. Stacks of three or more pallets can damage bottom pipes and can become unstable.
13. Handle A-2000/A-2026 Pipe with extra
care in freezing or cold weather. Plastic pipe is more brittle when cold.
Trenching
Trenching practice and bedding materials shall be in accordance with ASTM D2321 and OSHA rules.
1. The excavation needs to be wide enough and be supported adequately to allow a person to work safely.
2. Where trench walls are unstable, the contractor may elect to use tight sheeting, stay bracing, or a trench box for stabilization during pipe laying. If the conditions are severe, sheeting may be left in place.
3. Excessive groundwater may necessitate dewatering.
4. An unstable trench bottom must be stabilized at the engineer’s direction. In such cases, install special foundation and bedding materials in 6-inch layers and compact.
5. Excavation from 6 inches to 12 inches below the pipe should be filled with acceptable bedding material and compacted to a minimum 90% Standard Proctor Density. Fill areas of over excavation beyond 12 inches with processed stone or gravel following standard bedding practices.
6. Before installing the pipe, bring bedding material to grade along the entire length of the pipe.
7. When excavating in Class IV materials (silt, silty clays, and clays), provide a uniform, undisturbed foundation.
8 9
Installation Tips
1. At manholes, flexible manhole connections like
rubber boots, A-Loks, etc. are recommended. With rubber boot manhole connectors, install either a standard A-2000/A-2026 double gasket (8”-10”) or an A-2000 manhole gasket (12”-36”) on the pipe spigot under the stainless steel strap (See manhole connection detail.) Where manholes are manufactured with A-Lok connections, use a Contech PVC manhole sleeve.
2. Do not probe for the pipe with rods, shovels, or
other sharp objects when excavating down to install laterals, etc. Instead, mark the elevation of the pipe with stakes or other markers to help locate it.
3. When haunching the pipe or digging down to
install laterals, take care not to damage the pipe with shovels, or other construction equipment.
4. String only enough pipe to use during the day’s
laying operations.
5. A full line of adapters to other pipes is available. See
Contech A-2000/A-2026 Fittings Catalogs.
6. After proper assembly, the first load of backfill
should be placed over the middle of the pipe. While the first load is being placed, the free bell end should be held on line by the pipe layer (either by placing a foot inside the bell or by straddling the bell with both ankles.) This technique will minimiz e pipe mo v ement during backfilling. Subsequent loads of backfill may be placed in a normal fashion.
7. Handle A-2000/A-2026 pipe with
extra care in freezing or cold weather. Plastic pipe is more brittle when cold.
8. Rubber gaskets become har der as temperature
decreases, gaskets tend to compress less, and when combined with PVC bells that become more brittle, jointing becomes less forgiving.
Assembly of Pipe
A. Gasket/Pipe Connection
1. The double sealing surface A-2000/A-2026 gaskets are fitted to the first two full corrugations on the spigot end of the pipe as shown in the drawing. (Note A-2000 gaskets are black while A-2026 are gray)
The single sealing surface A-2000 Drainage gaskets are fitted in the first corrugation valley as shown in the drawing.
Gaskets are shipped loose and require field installation on the pipe spigot. The leading (lower) edge of the gasket is marked with the Contech logo and wording to distinguish it from the seating (higher) edge.
The low height seal is fitted into the first corrugation. The double sealing gasket is fitted into the first two full corrugation valleys.
Spigot
Gasket location on 4”to 36” diameter A-2000/A-2026
Bell (Plant­formed)
Gasket location on D-2000/ A-2000 Drainage
Pipe end
10 11