Carrier 50PTH, PTV User Manual

AQUAZONE™
50PTH, PTV, PTD026-072
Two-Stage Water Source Heat Pumps
with PURON® Refrigerant (R-410A)
Installation, Start-Up, and Service Instructions
CONTENTS
Page
SAFETY CONSIDERATIONS . . . . . . . . . . . . . . . . . . . . .1,2
GENERAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
INSTALLATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-29
Step 2 — Check Unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
• STORAGE
•PROTECTION
•INSPECT UNIT
Step 3 — Locate Unit. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
• FIELD CONVERSION OF DISCHARGE AIR
• HORIZONTAL UNIT
• VERTICAL UNITS
Step 5 — Check Duct System . . . . . . . . . . . . . . . . . . . . 9
• SO U N D AT T E N U AT I ON
• EXISTING DUCT SYSTEM
Step 6 — Install Condensate Drain . . . . . . . . . . . . . . . 9
• HORIZONTAL UNIT
• VERTICAL UNITS
• VENTING
Step 7 — Pipe Connections . . . . . . . . . . . . . . . . . . . . . 10
• WATER LOOP APPLICATIONS
• GROUND-WATER APPLICATIONS
• GROUND-LOOP APPLICATIONS
• INSTALLATION OF SUPPLY AND RETURN HOSE KIT
• POWER CONNECTION
• SUPPLY VOLTAGE
• 208-VOLT OPERATION
• 460-VOLT OPERATION
• WSHP OPEN WIRING
Step 9 — Wire Field Controls. . . . . . . . . . . . . . . . . . . . 25
• THERMOSTAT CONNECTIONS
• WATER FREEZE PROTECTION
• AIR COIL FREEZE PROTECTION
• ACCESSORY CONNECTIONS
• WATER SOLENOID VALVES
Step 10 — Operate ECM Interface Board . . . . . . . . 27
• STANDALONE — NO DDC CONTROLS
• WSHP OPEN CONTROLS
PRE-START-UP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29,30
System Checkout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
FIELD SELECTABLE INPUTS . . . . . . . . . . . . . . . . . 30-33
Complete C Control Jumper Settings. . . . . . . . . . . . 30
Complete C Control DIP Switches . . . . . . . . . . . . . . . 30
Deluxe D Control DIP Switches. . . . . . . . . . . . . . . . . . 30
Units with Modulating Hot Water Reheat
(HWR) Option . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
• STANDALONE — NO DDC CONTROLS
• WSHP OPEN CONTROLS
• HWR APPLICATION CONSIDERATIONS
• HWR COMPONENT FUNCTIONS
Deluxe D Control Accessory
Relay Configurations. . . . . . . . . . . . . . . . . . . . . . . . . 32
Page
START-UP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33-38
Operating Limits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
Scroll Compressor Rotation. . . . . . . . . . . . . . . . . . . . . 34
Unit Start-Up Cooling Mode . . . . . . . . . . . . . . . . . . . . . 34
Unit Start-Up Heating Mode . . . . . . . . . . . . . . . . . . . . . 34
Unit Start-Up with WSHP Open Controls . . . . . . . . 36
Flow Regulation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Flushing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Antifreeze . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Cooling Tower/Boiler Systems . . . . . . . . . . . . . . . . . . 38
Ground Coupled, Closed Loop and Plateframe
Heat Exchanger Well Systems . . . . . . . . . . . . . . . . 38
OPERATION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38-42
Power Up Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
Units with Aquazone™ Complete C Control . . . . . 39
Units with Aquazone Deluxe D Control. . . . . . . . . . 39
Units with WSHP Open Multiple Protocol. . . . . . . . 39
COMPLETE C AND DELUXE D BOARD
SYSTEM TEST . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .42,43
Test Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
WSHP Open Test Mode. . . . . . . . . . . . . . . . . . . . . . . . . . 43
Retry Mode. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Aquazone Deluxe D Control LED Indicators . . . . . 43
SERVICE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .44,45
Filters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Water Coil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Condensate Drain Pans . . . . . . . . . . . . . . . . . . . . . . . . . 44
Refrigerant System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Compressor. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Fan Motors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Condensate Drain Cleaning . . . . . . . . . . . . . . . . . . . . . 44
Air Coil Cleaning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Condenser Cleaning . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Checking System Charge . . . . . . . . . . . . . . . . . . . . . . . 45
Refrigerant Charging. . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
Air Coil Fan Motor Removal . . . . . . . . . . . . . . . . . . . . . 45
Replacing the WSHP Open Controller’s
Battery . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
TROUBLESHOOTING . . . . . . . . . . . . . . . . . . . . . . . . 45-53
Thermistor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
Control Sensors
WSHP Open Controller. . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
Thermostatic Expansion Valves . . . . . . . . . . . . . . . . . . 46
Stopped or Malfunctioned ECM Motor. . . . . . . . . . . . 50
Moisture Check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
APPENDIX A — WSHP OPEN SCREEN
CONFIGURATION . . . . . . . . . . . . . . . . . . . . . . . . . . 54-59
50PTH,PTV,PTD START-UP
CHECKLIST . . . . . . . . . . . . . . . . . . . . . . . . . . CL-1, CL-2
IMPORTANT: Read the entire instruction manual before starting installation.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
SAFETY CONSIDERATIONS
Installation and servicing of air-conditioning equipment can
be hazardous due to system pressure and electrical
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53500079-01 Printed in U.S.A. Form 50PT-4SI Pg 1 7-10 Replaces: 50PT-3SI
components. Only trained and qualified service personnel should install, repair, or service air-conditioning equipment.
Untrained personnel can perform basic maintenance func­tions such as cleaning coils and filters and replacing filters. All other operations should be performed by trained service personnel. When working on air-conditioning equipment, ob­serve precautions in the literature, tags and labels attached to the unit, and other safety precautions that may apply.
Improper installation, adjustment, alteration, service, main­tenance, or use can cause explosion, fire, electrical shock or other conditions which may cause personal injury or property damage. Consult a qualified installer, service agency, or a local distributor or branch for information or assistance. The qualified installer or agency must use factory-authorized kits or accessories when modifying this product. Refer to the individ­ual instructions packaged with the kits or accessories when installing.
Follow all safety codes. Wear safety glasses and work gloves. Use quenching cloth for brazing operations. Have fire extinguisher available. Read these instructions thoroughly and follow all warnings or cautions attached to the unit. Consult local building codes and the National Electrical Code (NEC) for special installation requirements.
Understand the signal words — DANGER, WARNING, and CAUTION. DANGER identifies the most serious hazards which will result in severe personal injury or death. WARNING signifies hazards that could result in personal inju­ry or death. CAUTION is used to identify unsafe practices, which would result in minor personal injury or product and property damage.
Recognize safety information. This is the safety-alert symbol ( ). When this symbol is displayed on the unit and in instructions or manuals, be alert to the potential for personal injury.
WARNING
Electrical shock can cause personal injury or death. Before installing or servicing system, always turn off main power to system. There may be more than one disconnect switch. Turn off accessory heater power if applicable.
GENERAL
This installation and start-up instructions literature is for Aquazone™ two-stage water source heat pump systems.
Water source heat pumps (WSHPs) are single-package hori­zontally and vertically mounted units with electronic controls designed for year-round cooling and heating. Aquazone WSHPs are available in the following unit configurations:
• 50PTH unit with horizontal airflow and right, left or back
discharge
• 50PTV unit with vertical airflow and top discharge
• 50PTD unit with vertical airflow and bottom discharge
(downflow)
IMPORTANT: The installation of water source heat pump units and all associated components, parts, and accessories which make up the installation shall be in accordance with the regulations of ALL authorities having jurisdiction and MUST conform to all applicable codes. It is the responsi­bility of the installing contractor to determine and comply with ALL applicable codes and regulations.
INSTALLATION
Step 1 — Check Jobsite —
maintenance instructions are provided with each unit. Before
Installation, operation and
unit start-up, read all manuals and become familiar with the unit and its operation. Thoroughly check out the system before operation. Complete the inspections and instructions listed below to prepare a unit for installation. See Table 1 for unit physical data.
IMPORTANT: This equipment is designed for indoor installation ONLY. Extreme variations in temperature, humidity and corrosive water or air will adversely affect the unit performance, reliability and service life.
HORIZONTAL UNIT (50PTH) —
ed for indoor installation only. Be sure to allow adequate space around the unit for servicing. See Fig. 1 for overall unit dimen­sions. Refer to Fig. 2 for an illustration of a typical horizontal installation.
VERTICAL AND DOWNFLOW UNITS (50PTV, PTD) — Vertical units are designed for indoor installations. While verti­cal units are typically installed in a floor-level closet or a small mechanical room, the unit access guidelines for these units are very similar to those described for horizontal units. See Fig. 3 and 4 for overall dimensions. Refer to Fig. 5 for an example of a typical vertical installation. Refer to Fig. 6 for a sample downflow installation.
Horizontal units are design-
CAUTION
To avoid equipment damage, do not use these units as a source of heating or cooling during the construction pro­cess. The mechanical components and filters used in these units quickly become clogged with construction dirt and debris which may cause system damage.
Step 2 — Check Unit — Upon receipt of shipment at
the jobsite, carefully check the shipment against the bill of lading. Make sure all units have been received. Inspect the car­ton or crating of each unit, and inspect each unit for damage. Ensure the shipping company makes proper notation of any shortages or damage on all copies of the freight bill. Concealed damage not discovered during unloading must be reported to the shipping company within 15 days of receipt of shipment.
NOTE: It is the responsibility of the purchaser to file all necessary claims with the shipping company.
1. Be sure that the location chosen for unit installation pro­vides ambient temperatures maintained above freezing. Well water applications are especially susceptible to freezing.
2. Be sure the installation location is isolated from sleeping areas, private offices and other acoustically sensitive spaces.
NOTE: A sound control accessory package may be used to help eliminate sound in sensitive spaces.
3. Check local codes to be sure a secondary drain pan is not required under the unit.
4. Be sure unit is mounted at a height sufficient to provide an adequate slope of the condensate lines. If an appropri­ate slope cannot be achieved, a field-supplied condensate pump may be required.
5. Provide sufficient space for duct connection. Do not allow the weight of the ductwork to rest on the unit.
6. Provide adequate clearance for filter replacement and drain pan cleaning. Do not allow piping, conduit, etc. to block filter access.
7. Provide sufficient access to allow maintenance and servicing of the fan and fan motor, compressor and coils. Removal of the entire unit from the closet should not be necessary.
2
8. Provide an unobstructed path to the unit within the closet or mechanical room. Space should be sufficient to allow removal of unit if necessary.
9. Provide ready access to water valves and fittings, and screwdriver access to unit side panels, discharge collar, and all electrical connections.
10. Where access to side panels is limited, pre-removal of the control box side mounting screws may be necessary for future servicing.
STORAGE — If the equipment is not needed immediately at the jobsite, it should be left in its shipping carton and stored in a clean, dry area of the building or in a warehouse. Units must be stored in an upright position at all times. If carton stacking is necessary, stack units a maximum of 3 high. Do not remove any equipment from its shipping package until it is needed for installation.
PROTECTION — Once the units are properly positioned on the jobsite, cover them with either a shipping carton, vinyl film, or an equivalent protective covering. Cap open ends of pipes stored on the jobsite. This precaution is especially important in areas where painting, plastering, or spraying of fireproof mate­rial, etc. is not yet complete. Foreign material that accumulates within the units can prevent proper start-up and necessitate costly clean-up operations.
Before installing any of the system components, be sure to examine each pipe, fitting, and valve, and remove any dirt or foreign material found in or on these components.
CAUTION
DO NOT store or install units in corrosive environments or in locations subject to temperature or humidity extremes (e.g., attics, garages, rooftops, etc.). Corrosive conditions and high temperature or humidity can significantly reduce performance, reliability, and service life. Always move units in an upright position. Tilting units on their sides may cause equipment damage.
INSPECT UNIT — To prepare the unit for installation, com­plete the procedures listed below:
1. Compare the electrical data on the unit nameplate with ordering and shipping information to verify that the correct unit has been shipped.
2. Do not remove the packaging until the unit is ready for installation.
3. Verify that the unit’s refrigerant tubing is free of kinks or dents, and that it does not touch other unit components.
4. Inspect all electrical connections. Be sure connections are clean and tight at their terminations.
5. Loosen compressor bolts until the compressor rides freely on springs. Remove shipping restraints.
6. Remove the four
1
/4 in. shipping bolts from compressor support plate (two bolts on each side) to maximize vibra­tion and sound alternation.
CAUTION
Failure to remove shipping brackets from spring-mounted compressors will cause excessive noise and could cause component failure due to added vibration.
7. Remove any blower support cardboard from inlet of the blower.
8. Locate and verify any accessory kit located in compressor and/or blower section.
9. Remove any access panel screws that may be difficult to remove once unit is installed.
Table 1 — Physical Data — 50PTH, PTV, PTD026-072 Units
UNIT 50PTH, PTV, PTD 026 038 049 064 072 COMPRESSOR (1 each) Two- St a g e, Sc r oll FACTORY CHARGE R-410A (oz) 58 78 81 144 156 ECM FAN MOTOR AND BLOWER
Fan Motor Type VAR VAR VAR VA R VAR Fan Motor (Hp)
Blower Wheel Size (D x W) (in.) 9 x 7 11 x 10 11x10 11x10 11x10 COAXIAL COIL VOLUME (gal.) .76 .92 1.24 1.56 1.56 WATER CONNECTION SIZE (FPT) (in.) HWG CONNECTION SIZE (FPT) (in.) VERTICAL
Air Coil
Dimensions (H x W) (in.) 28 x 20 28 x 25 32 x 25 36 x 25 36 x 25 Filter Standard — 1-in. Throwaway
(Qty — Size) (in.)
Weight (lb)
Operating 266 327 416 443 443 Packag ed 276 337 426 453 453
HORIZONTAL
Air Coil
Dimensions (H x W) (in.) 18 x 31 20 x 25 20 x 40 20 x 45 20 x 45 Filter Standard — 1-in. Throwaway
(Qty — Size) (in.)
Weight (lb)
Operating 266 327 416 443 443 Packag ed 276 337 426 453 453
LEGEND
ECM — Electronically Commutated Motor HWG — Hot Water Generator VAR — Variable Speed
NOTE: All units have spring compressor mountings, TXV (thermostatic expan­sion valve) expansion devices, and
1
/2 and 3/4-in. electrical knockouts.
1
/
2
3
/
4
1
/
2
1 — 28 x 24 1 — 28 x 30 2 — 16 x 30
2 — 18 x 18
1
/
2
3
/
4
1
/
2
1 — 12 x 20 1 — 20 x 24
111
111
1
/
2
1 — 18 x 20 1 — 20 x 24
1
/
2
1 — 16 x 30 1 — 20 x 30
2 — 20 x 24 2 — 20 x 24
1 — 16 x 30 1 — 20 x 30
1
/
2
3
Y Configuration - Left Return/Back Discharge
W Configuration - Left Return/Right Discharge - Air Coil Opening
W Configuration - Left Return/Right Discharge - Air Coil Opening
P Configuration - Right Return/Back Discharge - Air Coil Opening
N Configuration - Right Return/Left Discharge - Air Coil Opening
N Configuration - Right Return/Left Discharge - Air Coil Opening
Left View
Right View
Size
Right View
ASP
BSP
Q
P
O
R
Blower Outlet
Air Coil Side
C
A
Y
Front
X
Z
C
P
A
R
O
Q
BSP
Left Discharge
Back Discharge
Condensate 3/4” FPT
H
CSP
Front
2 Service Access
Right Return
2 Service Access
3.25”
G
F
E
D
CAP
J
K
L
A
Powe r Supply 3/4” Knockout
1/2”
Knockout
Low Voltage
1/2” Knockout
Front
CSP
ASP
Left Return
Right Discharge
Back Discharge
Condensate 3/4” FPT
H
2 Service Access
2 Service Access
Air Coil Side
Blower Outlet
BSP
P
M
N
O
Blower Outlet
S
U
V
C
T
B
CSP
Front Front
Air Coil
1.1”
C
Air Coil
ASP
S
B
T
Front
CSP
M
BSP
Blower Outlet
O
P
N
3.25”
1.6”
, 072
NOTES:
1. Condensate connection is stainless steel
3
/4 in. female pipe thread (FPT).
2. Unit shipped with top and bottom filter rack and is not suitable for duct connection without additional suppor t.
3. Discharge flange is factory-installed.
4. Hanger kit is factory-installed.
5. Shaded areas are recommended service areas, not required.
6. Discharge can be modified in field. Return cannot be modified.
AIRFLOW CONFIGURATION
50PTH
UNIT
OVERALL CABINET
(in.)
WATER CONNECTIONS (in.)
WATER
CONNEC-
TIONS (in.)
- UNITS
WITH HWR
ELECTRICAL
KNOCKOUTS (in.)
DISCHARGE CONNECTIONS (in.)
DUCT FLANGE INSTALLED
( 0.10 in.)
RETURN CONNECTION
USING AIR COIL
OPENING (in.)
A
WidthBDepthCHeight
123 4 5
Loop
Wate r
FPT (in.)
HWG
FPT (in.)
12
J
1
/2-in.
Cond
K
1
/2-in.
Cond
L
3
/4-in.
Cond
M (LH rtn)
NOSupply
Height
P
Supply
Width
Q (RH rtn)
RSReturn
Width
T Return Height
UV
DInE
Out
F
HWG
In
G
HWG
Out
H Cond­ensate
Loop
in D
Loop out E
Low
Vol ta ge
Ext
Pump
Power
Supply
026 22.4 62.2 19.3 2.1 10.0 13.9 16.9 3.53/
4
1
/22.1 10.0 3.6 6.1 8.6 3.6 2.0 12.5 15.5 3.6 2.0 33.8 16.2 2.3 1.5
038 25.4 71.2 21.3 3.4 10.8 14.6 18.9 3.43/
4
1
/25.96 13.13 3.4 6.1 8.6 3.1 1.2 19.0 17.5 3.1 1.0 34.8 18.2 3.1 1.5
049 25.4 76.2 21.3 3.4 10.8 15.6 18.9 3.4 11/25.96 13.13 3.6 6.1 8.6 3.1 1.2 19.0 17.5 3.1 1.0 39.8 18.2 3.1 1.5
064,072 25.4 81.2 21.3 3.4 10.8 15.6 18.9 3.4 11/25.96 13.13 3.6 6.1 8.6 3.1 1.2 19.0 17.5 3.1 1.0 44.8 18.2 3.1 1.5
CODE RETURN DISCHARGE
N Right Left
P Right Back
W Left Right
Y Left Back
LEGEND
ASP — Alternate Service Panel BSP — Blower Service Panel CAP — Control Access Panel CSP — Compressor Service Panel FPT — Female Pipe Thread HWG — Hot Water Generator HWR — Hot Water Reheat
Fig. 1 — 50PTH026-072 Dimensional Data
4
Field-Supplied Electric Heat (if applicable)
Filter Access
Integral hanger support­pre-attached in factory
Field-supplied transition to minimize pressure loss
3/8” threaded rods
(by others)
Return Air (Ductwork not shown)
Thermostat
Wiring
Power Wiring
Balancing Valve (field­installed accessory)
Stainless steel braid hose with integral “J” swivel
3/8” Threaded
Rod (by others)
Supply Air
Insulated supply duct with at least one 90 degree elbow to reduce air noise (field-supplied)
Flexible Connection
Vibration Isolator
(white-compressor end
and red-blower end)
Washer
(by others)
Double Hex Nuts
(by others)
Unit Power
Unit Power Disconnect (by others)
Unit Hanger (factory­supplied)
Low Pressure Drop Water Control Valve (optional) (field-installed accessory)
Ball Valve with optional integral P/T plug (typical for supply and return piping)
(field-installed accessory)
(field-installed accessory)
Aux Electric Heat Disconnect
Water In
Water Out
Building
Loop
Fig. 2 — Typical Installation — 50PTH Unit
UNIT HANGER ISOLATION DETAIL
5
Filter Bracket
NOTES:
1. Condensate connection is stainless steel 3/4 in. female pipe thread (FPT).
2. Unit shipped with top and bottom filter rack and is not suitable for duct connection without additional support.
3. Discharge flange is field-installed.
4. Shaded areas are recommended service areas, not required.
AIRFLOW CONFIGURATION
50PTV
UNIT
OVERALL CABINET
(in.)
WATER CONNECTIONS (in.)
WATER
CONNEC-
TIONS (in.)
- UNITS
WITH HWR
ELECTRICAL
KNOCKOUTS (in.)
DISCHARGE CONNECTIONS (in.)
DUCT FLANGE INSTALLED
( 0.10 in.)
RETURN CONNECTION
USING AIR COIL OPENING
(in.)
A
WidthBDepthCHeight
123 4 5
Loop
Wate r
FPT (in.)
HWG
FPT (in.)
12
J
1
/2-in.
Cond
K
1
/2-in.
Cond
L
3
/4-in.
Cond
M (LH rtn)
NOSupply
Width
P
Supply
Depth
Q (RH rtn)
RSReturn
Depth
T Return Height
U
DInE
Out
F
HWG
In
G
HWG
Out
H Cond­ensate
Loop
in D
Loop out E
Low
Vol ta ge
Ext
Pump
Power
Supply
026 22.4 25.6 48.5 2.1 10.0 13.9 16.9 7.8
3
/
4
1
/22.1 10.0 3.6 6.1 8.6 7.2 5.8 14.0 14.0 4.9 2.2 21.1 27.2 1.0
038 25.4 30.6 50.5 3.4 10.8 15.6 18.9 7.83/
4
1
/25.96 13.13 3.6 6.1 8.6 6.4 6.3 18.0 18.0 5.3 2.2 26.1 27.2 1.0
049 25.4 30.6 54.5 3.4 10.8 15.6 18.9 7.8 11/25.96 13.13 3.6 6.1 8.6 6.4 6.3 18.0 18.0 5.3 2.2 26.1 31.2 1.0
064, 072
25.4 30.6 58.5 3.4 10.8 15.6 18.9 7.8 11/25.96 13.13 3.6 6.1 8.6 6.4 6.3 18.0 18.0 5.3 2.2 26.1 35.2 1.0
CODE RETURN DISCHARGE
J Left Top
K Right Top
LEGEND
ASP — Alternate Service Panel BSP — Blower Service Panel CAP — Control Access Panel CSP — Compressor Service Panel FPT — Female Pipe Thread HV — High Voltage HWG — Hot Water Generator HWR — Hot Water Reheat LV Low Voltage
Fig. 3 — 50PTV Dimensional Data
Field-Installed Discharge Flange (shipped loose inside blower section)
Access Panels
Front
O
Q
K - Configuration - Right Return
/Top Discharge
U
T
C
Front
K - Configuration - Right Return -
Air Coil Opening
(Right Side View)
P
Air Coil Side
(Top View)
S
ASP
B
N
R
N
J - Configuration - Left Return
R
P
Air Coil Side
/Top Discharge
(Top View)
S
Front
U
Air Coil
T
C
1.18”
CSP
Back Back Front
J - Configuration - Left Return -
Air Coil Opening
(Left Side View)
O
M
A
Air Coil
Air Coil
Power Supply 3/4” HV Knockout
1/2” Knockout
Low Voltage 1/2” LV Knockout
CSP
2ʼ Service Access
CSP
BSP
CAP
1.63”
J
K
Front View
Isometric View
CAP
L
ASP
ASP
1.00”
1.68”
D
Condensate 3/4” FPT
H
2ʼ Service Access
G
F
E
6
NOTES:
1. Condensate connection is stainless steel 3/4 in. female pipe thread (FPT).
2. Unit shipped with top and bottom filter rack and is not suitable for duct connection without additional support.
3. Downflow unit does not have discharge flange, and is rated for zero clearance installation.
4. Shaded areas are recommended service areas, not required.
AIRFLOW CONFIGURATION
50PTD
UNIT
OVERALL CABINET
(in.)
WATER CONNECTIONS (in.)
WATER
CONNEC-
TIONS (in.)
- UNITS
WITH HWR
ELECTRICAL
KNOCKOUTS (in.)
DISCHARGE CONNECTIONS (in.)
DUCT FLANGE INSTALLED
( 0.10 in.)
RETURN CONNECTION (in.)
USING AIR COIL OPENING
A
WidthBDepthCHeight
12 3 4 5
Loop
Wate r
FPT (in.)
HWG
FPT (in.)
12
J
1
/2-in.
Cond
K
1
/2-in.
Cond
L
3
/4-in.
Cond
M (LH rtn)
NOSupply
Width
P
Supply
Depth
Q (RH rtn)
RSReturn
Depth
T Return Height
U
DInE
Out
F
HWG
In
G
HWG
Out
H
Cond-
ensate
Loop
in D
Loop out E
Low
Vol t ag e
Ext
Pump
Power
Supply
026 22.4 25.6 52.5 2.1 10.0 13.9 16.9 3.63/
4
1
/22.1 10.0 3.6 6.1 8.6 6.7 8.4 10.1 9.1 10.8 2.2 21.1 27.2 1.0
038 25.4 30.6 54.5 3.4 10.8 15.6 18.9 3.63/
4
1
/25.96 13.13 3.6 6.1 8.6 7.2 9.0 13.4 12.9 10.4 2.2 26.1 27.2 1.0
049 25.4 30.6 58.5 3.4 10.8 15.6 18.9 3.6 11/25.96 13.13 3.6 6.1 8.6 7.2 9.0 13.4 12.9 10.4 2.2 26.1 31.4 1.0
064,072 25.4 30.6 62.5 3.4 10.8 15.6 18.9 3.6 11/25.96 13.13 3.6 6.1 8.6 7.2 9.0 13.4 12.9 10.4 2.2 26.1 35.2 1.0
CODE RETURN DISCHARGE
J Left Bottom
K Right Bottom
LEGEND
ASP — Alternate Service Panel BSP — Blower Service Panel CAP — Control Access Panel CSP — Compressor Service Panel FPT — Female Pipe Thread HWG — Hot Water Generator HWR — Hot Water Reheat
Fig. 4 — 50PTD Dimensional Data
7
• Provide adequate clearance for filter replacement and
Return
Air
Power
Thermostat Wiring
Compressor Access Panel
Balancing Valve (field-installed accessory)
Low Pressure
Drop Water Control Valve (optional) (field-installed accessory)
Ball Valve with optional integral P/T plug (typical for supply and return piping) (field-Installed accessory)
Water Out
Water In
Building
Loop
Supply Air
Flexible Connection
Stainless steel braid hose with integral “J” swivel (field-installed accessory)
Return
Air
Power
Thermostat
Wiring
Compressor Access Panel
Balancing Valve
(field-installed
accessory)
Low Pressure Drop Water Control Valve (optional) (field-installed accessory)
Ball Valve with optional integral
P/T plug (typical for supply and return piping)(field-installed accessory)
Water Out
Water In
Building Loop
Supply Air
Flexible Connection
Flexible
Connection
Stainless steel braid hose with integral ”J” swivel(field­installed accessory)
NOTE: Ball valve with integral pressure temperature plug recommended.
Fig. 5 — Typical Vertical Installation — 50PTV Unit
NOTE: Ball valve with integral pressure temperature plug recommended.
Fig. 6 — Typical Downflow Installation —
50PTD Unit
Water
Connection End
Supply Duct
Return Air
Water
Connection End
Drain
Return Air
Discharge Air
Side Discharge
Back Discharge
Fig. 7 — Conversion Right Return, Side Discharge to Back Discharge
drain pan cleaning. Do not block filter access with pip­ing, conduit or other materials. Refer to Fig. 1, 3, and 4 for dimensional data.
• Provide access for fan and fan motor maintenance and for servicing the compressor and coils without removing the unit.
• Provide an unobstructed path to the unit within the closet or mechanical room. Space should be sufficient to allow removal of the unit, if necessary.
• In limited side access installations, pre-removal of the control box side mounting screws will allow control box removal for future servicing.
• Provide access to water valves and fittings and screw­driver access to the unit side panels, discharge collar and all electrical connections.
NOTE: Correct placement of the horizontal unit can play an important part in minimizing sound problems. Since duct­work is normally applied to these units, the unit can be placed so that the principal sound emission is outside the oc­cupied space in sound-critical applications. A fire damper may be required by the local code if a fire wall is penetrated.
FIELD CONVERSION OF DISCHARGE AIR — The dis­charge air of the 50PTH horizontal units can be converted between side and back discharge in the field. The conversion process is the same for right and left return configurations. See Fig. 7 and 8.
NOTE: It is not possible to convert return air between left or right return models in the field due to refrigerant piping changes.
Step 3 — Locate Unit — The following guidelines
should be considered when choosing a location for a WSHP:
• Units are for indoor use only.
• Locate in areas where ambient temperatures are between 39 F and 102 F and relative humidity is no greater than 75%.
• Provide sufficient space for water, electrical and duct
• Locate unit in an area that allows easy access and removal
• Allow enough space for service personnel to perform
• Return air must be able to freely enter the space if unit needs
• Install the unit on a piece of rubber, neoprene or other
connections.
of filter and access panels.
maintenance.
to be installed in a confined area such as a closet.
mounting pad material for sound isolation. The pad should be at least
3
/8 in. [10 mm] to 1/2 in. [13 mm] in
thickness. Extend the pad beyond all four edges of the unit.
Preparation
— The unit should be on the ground in a well lit area. Hung units should be taken down to ground level before converting.
Side to Back Discharge Conversion
1. Remove screws to free the top and discharge panels. Set screws aside for later use. See Fig. 8.
2. Remove the access panel and set aside.
3. Lift the discharge panel from side of unit and rotate it to back using care not to damage blower wiring.
4. Check blower wire routing and connections for undue tension or contact with sheet metal edges. Re-route if necessary.
8
Fig. 9 — 50PTV Units Mounted With
Vibration Absorption Pad
Return Air
Remove Screws
Return Air
Rotate
Move to Side
Side Discharge
Return Air
Discharge Air
Drain
Back Discharge
Replace Screws
Water
Connection End
Water
Connection End
Water
Connection End
Fig. 8 — Conversion Left Return,
Side Discharge to Back Discharge
5. Check refrigerant tubing for contact with other compo­nents. Adjust if necessary.
6. Reinstall top panel using screws set aside in Step 1. NOTE: Location for some screws at bottom of discharge
panel may have to be changed.
7. Manually spin fan wheel to check for obstructions. Adjust for any obstruction found.
8. Replace access panel.
Back to Side Discharge Conversion above for Side to Back Discharge Conversion, noting the panels would be reversed.
— Follow instructions
Step 4 — Mount the Unit
HORIZONTAL UNIT (50PTH) — Horizontal units should be mounted using the factory-installed hangers. Proper attach­ment of hanging rods to building structure is critical for safety. See Fig. 1. Rod attachments must be able to support the weight of the unit. See Table 1 for unit operating weights.
VERTICAL UNITS (50PTV,PTD) — Vertical and downflow units are available in left or right return air configurations. See Fig. 3 and 4. Mount the unit (except 50PTD) on a vibration absorption pad slightly larger than the entire base to minimize vibration transmission. It is not necessary to mount the unit on the floor. See Fig. 9.
NOTE: Some codes require the use of a secondary drain pan under vertical units. Check local codes for more information.
Step 5 — Check Duct System — Size the duct sys-
tem to handle the design airflow quietly.
NOTE: Depending on the unit, the fan wheel may have a ship­ping support installed at the factory. This must be removed before operating unit.
SOUND ATTENUATION — To eliminate the transfer of vibration to the duct system, a flexible connector is recom­mended for both discharge and return air duct connections on metal duct systems. The supply and return plenums should in­clude internal duct liner of fiberglass or be made of duct board construction to maximize sound attenuation of the blower. Installing the WSHP unit to uninsulated ductwork in an uncon­ditioned space is not recommended since it will sweat and adversely affect the unit’s performance.
To reduce air noise, at least one 90-degree elbow could be included in the supply and return air ducts, provided system performance is not adversely impacted. The blower speed can also be changed in the field to reduce air noise or excessive air­flow, provided system performance is not adversely impacted.
EXISTING DUCT SYSTEM — If the unit is connected to existing ductwork, consider the following:
• Verify that the existing ducts have the proper capacity to
handle the unit airflow. If the ductwork is too small, install
larger ductwork.
• Check existing ductwork for leaks and repair as necessary.
NOTE: Local codes may require ventilation air to enter the
space for proper indoor air quality. Hard-duct ventilation
may be required for the ventilating air supply. If hard
ducted ventilation is not required, be sure that a proper air
path is provided for ventilation air to unit to meet ventila-
tion requirement of the space.
Step 6 — Install Condensate Drain
HORIZONTAL UNIT (50PTH) — Slope the unit toward the drain at quired pitch, install a condensate at the unit to pump conden­sate to building drain.
ternal trap is necessary. Install each unit with its own individual trap and means to flush or blow out the condensate drain line. Do not install units with a common trap or vent. See Fig. 11 for typical condensate connections.
NOTE: Never use a pipe size smaller than the connection.
VERTICAL UNITS (50PTV,PTD) — Each unit uses a con­densate hose inside all cabinets as a trapping loop, therefore an external trap is not necessary. See Fig. 12.
1
/4 in. See Fig. 10. If it is not possible to meet the re-
Horizontal units are not internally trapped, therefore an ex-
9
Each unit must be installed with its own individual vent and
NOTE: Trap should be deep enough to offset maximum unit static difference. A 4-in. trap is recommended.
Fig. 11 — Trap Condensate Drain
Alternate Condensate Location
Vent
1/4 per foot slope to drain
3/4 Copper FPT/PVC
Water Connections
1/2
1/2
3/4 PVC
NOTE: Unit does not need to be sloped toward drain.
Fig. 12 — Vertical Condensate Connection
1/4 Pitch for Drainage
Drain Connection
Pitch Toward Drain
Fig. 10 — Horizontal Unit Pitch
means to flush or blow out the condensate drain line. Do not in­stall units with a common trap or vent.
VENTING — Install a vent in the condensate line of any application that may allow dirt or air to collect in the line. Con­sider the following:
• Always install a vent where an application requires a long horizontal run.
• Always install a vent where large units are working against higher external static pressure and to allow proper drainage for multiple units connected to the same condensate main.
• Be sure to support the line where anticipated sagging from the condensate or when “double trapping” may occur.
• If condensate pump is present on unit, be sure drain connec­tions have a check valve to prevent back flow of condensate into other units.
Step 7 — Pipe Connections — Depending on the
application, there are 3 types of WSHP piping systems to choose from: water loop, ground-water and ground loop. Refer to Piping Section of Carrier System Design Manual for addi­tional information.
All WSHP units use low temperature soldered female pipe
thread fittings for water connections to prevent annealing and out-of-round leak problems which are typically associated with high temperature brazed connections. Refer to Table 1 for con­nection sizes. When making piping connections, consider the following:
• Use a backup wrench when making screw connections to unit to prevent internal damage to piping.
• Insulation may be required on piping to avoid condensation in the case where fluid in loop piping operates at tempera­tures below dew point of adjacent air.
• Piping systems that contain steel pipes or fittings may be subject to galvanic corrosion. Dielectric fittings may be used to isolate the steel parts of the system to avoid galvanic corrosion.
WATER LOOP APPLICATIONS — Water loop applications usually include a number of units plumbed to a common pip­ing system. Maintenance to any of these units can introduce air into the piping system. Therefore, air elimination equipment comprises a major portion of the mechanical room plumbing.
The flow rate is usually set between 2.25 and 3.5 gpm per
ton of cooling capacity. For proper maintenance and servicing, pressure-temperature (P/T) ports are necessary for temperature and flow verification.
Cooling tower/boiler systems typically utilize a common
loop maintained at 60 to 95 F. The use of a closed circuit evap­orative cooling tower with a secondary heat exchange between the tower and the water loop is recommended. If an open type cooling tower is used continuously, chemical treatment and fil­tering will be necessary.
In addition to complying with any applicable codes, consid-
er the following for system piping:
• Piping systems using water temperatures below 50 F
• Avoid all plastic to metal threaded fittings due to the poten-
• Teflon tape thread sealant is recommended to minimize
• Use backup wrench. Do not overtighten connections.
• Route piping to avoid service access areas to unit.
• Flush the piping system prior to operation to remove dirt
GROUND-WATER APPLICATIONS — Typical ground­water piping is shown in Fig. 13. In addition to complying with any applicable codes, consider the following for sys­tem piping:
• Install shut-off valves for servicing.
• Install pressure-temperature plugs to measure flow and
• Connect boiler drains and other valves using a “T” connec-
• Do not overtighten connections.
• Route piping to avoid service access areas to unit.
• Use PVC SCH80 or copper piping material.
NOTE: PVC SCH40 should not be used due to system high pressure and temperature extremes.
10
1
require
/2-in. closed cell insulation on all piping surfaces to
eliminate condensation.
tial to leak. Use a flange fitted substitute.
internal fouling of the heat exchanger.
and foreign materials from the system.
temperature.
tor to allow acid flushing for the heat exchanger.
Water Supply and Quantity
Boiler Drains (field-installed)
Strainer (field-installed accessory) (16 to 20 mesh recommended for filter sediment)
Shut-Off Valve (field-installed accessory)
Water Control Valve (field-installed accessory)
Flow Regulator (field-installed accessory)
Pressure
Ta nk
Water Out
Water In From Pump
Fig. 13 — Typical Ground-Water Piping Installation
— Check water supply. Water supply should be plentiful and of good quality. See Table 2 for water quality guidelines.
IMPORTANT: Failure to comply with the above required water quality and quantity limitations and the closed­system application design requirements may cause damage to the tube-in-tube heat exchanger. This damage is not the responsibility of the manufacturer.
In all applications, the quality of the water circulated through the heat exchanger must fall within the ranges listed in the Water Quality Guidelines table. Consult a local water treat­ment firm, independent testing facility, or local water authority for specific recommendations to maintain water quality within the published limits.
GROUND-LOOP APPLICATIONS — Temperatures between 25 and 110 F and a cooling capacity of 2.25 to 3 gpm of flow per ton is recommended. In addition to complying with any applicable codes, consider the following for system piping:
• Limit piping materials to only polyethylene fusion in the
buried sections of the loop.
• Do not use galvanized or steel fittings at any time due to
corrosion.
• Avoid all plastic to metal threaded fittings due to the poten-
tial to leak. Use a flange fitted substitute.
• Do not overtighten connections.
• Route piping to avoid service access areas to unit.
• Use pressure-temperature (P/T) plugs to measure flow of
pressure drop. INSTALLATION OF SUPPLY AND RETURN HOSE
KIT — Follow these piping guidelines.
1. Install a drain valve at the base of each supply and return riser to facilitate system flushing.
2. Install shutoff/balancing valves and unions at each unit to permit unit removal for servicing.
3. Place strainers at the inlet of each system circulating pump.
4. Select the proper hose length to allow slack between con­nection points. Hoses may vary in length by +2% to –4% under pressure.
5. Refer to Table 3. Do not exceed the minimum bend radius for the hose selected. Exceeding the minimum bend radi­us may cause the hose to collapse, which reduces water flow rate. Install an angle adapter to avoid sharp bends in the hose when the radius falls below the required minimum.
NOTE: Piping must comply with all applicable codes.
Insulation is not required on loop water piping except where the piping runs through unheated areas or outside the building or when the loop water temperature is below the minimum ex­pected dew point of the pipe ambient. Insulation is required if loop water temperature drops below the dew point.
Do not bend or kink supply lines or hoses.
Pipe joint compound is not necessary when Teflon threaded tape is pre-applied to hose assemblies or when flared-end connections are used. If pipe joint compound is preferred, use compound only in small amounts on the male pipe threads of the fitting adapters. Prevent sealant from reaching the flared surfaces of the joint.
NOTE: When anti-freeze is used in the loop, assure that it is compatible with Teflon tape or pipe joint compound employed.
Maximum allowable torque for brass fittings is 30 ft-lb. If a torque wrench is not available, tighten finger-tight plus one quarter turn. Tighten steel fittings as necessary.
Optional pressure-rated hose assemblies designed specifi­cally for use with Carrier units are available. Similar hoses can be obtained from alternate suppliers. Supply and return hoses are fitted with swivel-joint fittings at one end to prevent kink­ing during installation.
Backup wrench is required when tightening water connec­tions to prevent water line damage.
Refer to Fig. 14 for an illustration of a supply/return hose kit. Male adapters secure hose assemblies to the unit and risers. Install hose assemblies properly and check them regularly to avoid system failure and reduced service life.
CAUTION
CAUTION
11
Table 2 — Water Quality Guidelines
Rib Crimped
Length
(2 ft Length Standard)
Swivel Brass Fitting
Brass Fitting
MPT
Fig. 14 — Supply/Return Hose Kit
CONDITION
Scaling Potential — Primary Measurement
Above the given limits, scaling is likely to occur. Scaling indexes should be calculated using the limits below.
pH/Calcium Hardness Method
Index Limits for Probable Scaling Situations (Operation outside these limits is not recommended.)
Scaling indexes should be calculated at 150 F for direct use and HWG applications, and at 90 F for indirect HX use. A monitoring plan should be implemented.
Ryznar Stability Index
Langelier Saturation Index
Iron Fouling
2+
(Ferrous)
Iron Fe (Bacterial Iron Potential)
Iron Fouling
Corrosion Prevention††
pH
Hydrogen Sulfide (H
Ammonia Ion as Hydroxide, Chloride, Nitrate and Sulfate Compounds
Maximum Chloride Levels Maximum allowable at maximum water temperature.
Erosion and Clogging
Particulate Size and Erosion
Brackish
HWG — Hot Water Generator HX Heat Exchanger N/A — Design Limits Not Applicable Considering Recirculating
NR Application Not Recommended SS Stainless Steel
*Heat exchanger materials considered are copper, cupronickel, 304 SS
(stainless steel), 316 SS, titanium.
†Closed recirculating system is identified by a closed pressurized piping
system.
**Recirculating open wells should observe the open recirculating design
considerations.
Pota ble Wate r
S)
2
LEGEND
HX
MATERIAL*
All N/A pH < 7.5 and Ca Hardness, <100 ppm
All N/A
All N/A
All N/A
All N/A
All
All N/A
All N/A
Copper N/A
Cupronickel N/A <150 ppm
304 SS N/A <400 ppm 316 SS N/A <1000 ppm
Titanium N/A >1000 ppm
All
All N/A
CLOSED RECIRCULATING† OPEN LOOP AND RECIRCULATING WELL**
6.0 - 7.5
–0.5 to +0.5
<0.2 ppm (Ferrous)
<0.5 ppm of Oxygen
6 - 8.5
<0.5 ppm
<0.5 ppm
75 F (24 C) 100 F (38 C)
NR NR
NR NR <250 ppm <150 ppm <550 ppm <375 ppm >550 ppm >375 ppm
6 - 8.5
Monitor/treat as needed.
<10 ppm of particles and a
maximum velocity of 6 fps.
Filtered for maximum
800 micron size.
If >7.5 minimize steel pipe use.
Based upon 150 F HWG and direct well, 85 F indirect well HX.
2+
If Fe
(ferrous) >0.2 ppm with pH 6 - 8, O2<5 ppm check for iron bacteria.
Minimize steel pipe below 7 and no open tanks with pH <8.
At H
S>0.2 ppm, avoid use of copper and cupronickel piping or HXs.
2
Copper alloy (bronze or brass) cast components are okay to <0.5 ppm.
50 F (10 C)
<20 ppm
<10 ppm (<1 ppm “sandfree for reinjection) of particles and a maximum velocity of 6 fps. Filtered for maximum 800 micron size. Any particulate that is not removed can potentially clog components.
Use cupronickel heat exchanger when concentrations of calcium or sodium chlo­ride are greater than 125 ppm are present. (Seawater is approximately 25,000 ppm.)
††If the concentration of these corrosives exceeds the maximum allowable
level, then the potential for serious corrosion problems exists. Sulfides in the water quickly oxidize when exposed to air, requiring that no agitation occur as the sample is taken. Unless tested immediately at the site, the sample will require stabilization with a few drops of one Molar zinc acetate solution, allowing accurate sulfide determination up to 24 hours after sampling. A low pH and high alkalinity cause system problems, even when both values are within ranges shown. The term pH refers to the acid­ity, basicity, or neutrality of the water supply. Below 7.0, the water is consid­ered to be acidic. Above 7.0, water is considered to be basic. Neutral water contains a pH of 7.0. To convert ppm to grains per gallon, divide by 17. Hardness in mg/l is equivalent to ppm.
If <–0.5 minimize steel pipe use.
Above this level deposition will occur.
Rotten egg smell appears at 0.5 ppm level.
Table 3 — Metal Hose Minimum Bend Radii
HOSE DIAMETER (in.) MINIMUM BEND RADII (in.)
1
/
2
3
/
4
15
21/
4
1
2
/
2
Step 8 — Wire Field Power Supply
WARNING
To avoid possible injury or death due to electrical shock, open the power supply disconnect switch and secure it in an open position during installation.
CAUTION
Use only copper conductors for field-installed electrical wiring. Unit terminals are not designed to accept other types of conductors.
All field-installed wiring, including the electrical ground, MUST comply with the National Electrical Code (NEC) as well as applicable local codes. In addition, all field wiring must
12
conform to the Class II temperature limitations described in the NEC.
Refer to unit wiring diagrams Fig. 15-24 for a schematic of the field connections, which must be made by the installing (or electrical) contractor. For Deluxe D with WSHP Open controls 3-phase units and Complete C with Open controls single-phase and 3-phase units contact Application Engineering. Refer to Table 4 for fuse sizes.
Consult the unit wiring diagram located on the inside of the compressor access panel to ensure proper electrical hookup. The installing (or electrical) contractor must make the field connections when using field-supplied disconnect.
Operating voltage must be the same voltage and phase as shown in electrical data shown in Table 4.
Make all final electrical connections with a length of flexi­ble conduit to minimize vibration and sound transmission to the building.
POWER CONNECTION — Make line voltage connection by connecting the incoming line voltage wires to the line side of the compressor contactor terminal as shown in Fig. 25. See Table 4 for amperage ratings to provide correct wire and maximum overcurrent protection sizing.
SUPPLY VOLTAGE — Operating voltage to unit must be within voltage range indicated on unit nameplate.
On 3-phase units, voltages under load between phases must be balanced within 2%. Use the following formula to deter­mine the percentage voltage imbalance:
% Voltage Imbalance
= 100 x
max voltage deviation from average voltage
average voltage
Example: Supply voltage is 460-3-60.
AB = 452 volts BC = 464 volts AC = 455 volts
Average Voltage =
452 + 464 + 455
3
1371
=
3
= 457
Determine maximum deviation from average voltage: (AB) 457 – 452 = 5 v
(BC) 464 – 457 = 7 v (AC) 457 – 455 = 2 v
Maximum deviation is 7 v. Determine percent voltage imbalance.
% Voltage Imbalance = 100 x
7
457
= 1.53%
This amount of phase imbalance is satisfactory as it is
below the maximum allowable 2%.
Operation on improper line voltage or excessive phase imbalance constitutes abuse and may cause damage to electri­cal components.
NOTE: If more than 2% voltage imbalance is present, contact your local electric utility.
208-VOLT OPERATION — All 208-230 volt units are factory wired for 208 volts. The transformers may be switched to 230-volt operation by switching the red (208 volt) wire with the orange (230 volt) wire at the L1 terminal.
460-VOLT OPERATION — Units using 460-v and an ECM (electronically commutated motor) fan motor, modulating HWR, and/or internal secondary pump will require a neutral wire from the supply side in order to feed accessory with 265-v.
Table 4 — 50PTH,PTV,PTD Electrical Data
50PTH,
PTV, PTD
UNITS
026 208/230-1-60 197/254 10.3 52.0 4.3 14.6 17.2 25 0.8 15.4 18.0 25
038
049
064
072 208/230-1-60 197/254 27.2 150.0 7.0 34.2 41.0 60 1.07 35.3 42.1 60
FLA Full Load Amps HACR — Heating, Air Conditioning and Refrigeration LRA Locked Rotor Amps RLA Rated Load Amps HWR — Hot Water Reheat
V-P H- Hz *
208/230-1-60 197/254 16.7 82.0 4.3 21.0 25.2 40 0.8 21.8 26.0 40 208/230-3-60 197/254 11.2 58.0 4.3 15.5 18.3 25 0.8 16.3 19.1 30
460-3-60 414/506 4.5 29.0 4.1 8.6 9.7 15 0.7 9.3 10.4 15 208/230-1-60 197/254 21.2 96.0 7.0 28.2 33.5 50 1.07 29.3 34.6 50 208/230-3-60 197/254 13.5 88.0 7.0 20.5 23.9 35 1.07 21.6 24.9 35
460-3-60 414/506 6.4 41.0 6.9 13.3 14.9 20 1.07 14.4 16.0 20 208/230-1-60 197/254 25.6 118.0 7.0 32.6 39.0 60 1.07 33.7 40.1 60 208/230-3-60 197/254 17.6 123.0 7.0 24.6 29.0 45 1.07 25.7 30.1 45
460-3-60 414/506 9.0 62.0 6.9 15.9 18.2 25 1.07 17.7 19.2 25
LEGEND *The 460-v units using an ECM (electronically commutated motor) fan
VO LTAGE
MIN/MAX
COMPRESSOR
RLA LRA
FAN
MOTOR
FLA
TOTAL
UNIT FLA
MIN
CIRCUIT
AMPS
motor, modulating HWR, and/or an internal secondary pump will require a neutral wire from the supply side in order to feed the accessory with 265-v.
MAX FUSE/ HACR
REHEAT
PUMP
FLA
UNITS WITH HWR
TOTAL
UNIT
FLA
MIN
CIRCUIT
AMP
MAX FUSE/ HACR
13
ECM
Y
GGGGR
W
O
Y
2
Y
1
G
R
C
Y
2
Y
1
G
O
W
C
R
D
H
A
L
1
A
A
A
L
1
S
W1
S
W2
S
W3
S
W4
S
W5
S
W6
S
W7
S
W8
S
W9
OF
F
ON
G
D
E
HUM
C
F
M
T
B
1
J1
S
1
BM ECM
ECM
INTERFACE
BOARD
S
W
1
S
W
2
S
W
3
S
W
4
S
W
5
S
W
6
S
W
7
S
W
8
S
W
9
OF
F
ON
S
1
J1
BM ECM
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
BR Blower Relay
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
DTS Discharge Temp Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HWG Hot Water Generator
JW1 Jumper, Alarm
LOC Loss of Charge Pressure Switch
MV Motorized Valve
NEC National Electrical Code
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS Transformer
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. Transformer for 208/230 v will be connected for 208 v operation. For 230 v operation, dis-
connect RED lead at L1 and attach ORN lead to L1. Insulate open end of RED lead. Trans-
former for 220/240 v will be connected for 220 v operation. For 240 v operation, disconnect
RED lead at L1 and attach ORN lead to L1. Transformer is energy limiting or may have cir-
cuit breaker.
4. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut
JW3 jumper.
5. Typical Aquazone™ thermostat wiring shown. Refer to thermostat installation instructions
for wiring to the unit. Thermostat wiring must be Class 1 and voltage rating equal to or
greater than unit supply voltage.
6. 24-v alarm signal shown. For dry alarm contact, cut JW1 jumper and dry contact will be
available between AL1 and AL2.
7. Transformer secondary ground via Complete C board standoffs and screws to control box.
(Ground available from top two standoffs as shown.)
8. Aquastat is field-supplied and must be wired in series with the hot leg to the pump. Aqua-
stat is rated for voltage up to 277 v.
9. Place jumpers on 2 and 3, ECM board, when dehumidification mode is used.
LEGEND
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Optional Wiring
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Temperature Switch
Thermistor
Ground
Wire Nut
Fig. 15 — Wiring of 50PTH,PTV,PTD026-072 Units with Complete C Controller, Single Phase (208/230 V)
14
ECM INTERFACE BOARD LAYOUT
Y
GGGGR
W
O
Y2
Y1
G
R
C
Y2
Y1
G
O
W
C
R
DH
AL
1
A
A
AL
1
SW
1
SW
2
SW
3
SW
4
SW
5
SW
6
SW
7
SW
8
SW
9
OFF
ON
G
DEH
UM
C
FM
T
B1
J
1
S
1
BM (ECM)
ECM
INTERFACE
BOARD
SW1
S
W2
S
W3
S
W4
S
W5
S
W6
S
W7
S
W8
S
W9
OFF
O
N
BM
(ECM)
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
CAP Capacitor
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
COMPR — Compressor
DDC Direct Digital Control
DTS Discharge Temp Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HWG Hot Water Generator
JW1 Jumper, Alarm
NSB Digital Night Setback
LOC Loss of Charge Pressure Switch
MV Motorized Valve
NEC National Electrical Code
LEGEND
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. Transformer for 208/230 v will be connected for 208 v operation. For 230 v operation, discon-
nect RED lead at L1 and attach ORN lead to L1. Insulate open end of RED lead. Transformer
for 220/240 v will be connected for 220 v operation. For 240 v operation, disconnect RED
lead at L1 and attach ORN lead to L1. Transformer is energy limiting or may have circuit
breaker.
4. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut
JW3 jumper.
5. Typical Aquazone™ thermostat wiring shown. Refer to thermostat installation instructions for
wiring to the unit. Thermostat wiring must be Class 1 and voltage rating equal to or greater
than unit supply voltage.
6. 24-v alarm signal shown. For dry alarm contact, cut AL2 dr y jumper and dry contact will be
available between AL1 and AL2.
7. Transformer secondary ground via Deluxe D board standoffs and screws to control box.
(Ground available from top two standoffs as shown.)
8. Aquastat is field-supplied and must be wired in series with the hot leg to the pump. Aquastat
is rated for voltage up to 277 v.
9. Place jumpers on 2 and 3, ECM board, when dehumidification mode is used.
Fig. 16 — Wiring of 50PTH,PTV,PTD026-072 Units with Deluxe D Controller, Single Phase (208/230 V)
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS Transformer
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Thermistor
Ground
Wire Nut
15
BM (ECM)
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
BR Blower Relay
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
DTS Discharge Temp Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HWG Hot Water Generator
JW1 Jumper, Alarm
LOC Loss of Charge Pressure Switch
MV Motorized Valve
NEC National Electrical Code
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS Transformer
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. Transformer for 208/230 v will be connected for 208 v operation. For 230 v operation, disconnect
RED lead at L1 and attach ORN lead to L1. Insulate open end of RED lead. Transformer for 220/
240 v will be connected for 220 v operation. For 240 v operation, disconnect RED lead at L1 and
attach ORN lead to L1. Transformer is energy limiting or may have circuit breaker.
4. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut JW3
jumper.
5. Typical Aquazone™ thermostat wiring shown. Refer to thermostat installation instructions for wir-
ing to the unit. Thermostat wiring must be Class 1 and voltage rating equal to or greater than unit
supply voltage.
6. 24-v alarm signal shown. For dry alarm contact, cut JW1 jumper and dr y contact will be available
between AL1 and AL2.
7. Transformer secondary ground via Complete C board standoffs and screws to control box.
(Ground available from top two standoffs as shown.)
8. Aquastat is field-supplied and must be wired in series with the hot leg to the pump. Aquastat is
rated for voltage up to 277 v.
9. Place jumpers on 2 and 3, ECM board, when dehumidification mode is used.
LEGEND
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Optional Wiring
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Temperature Switch
Thermistor
Ground
Wire Nut
Fig. 17 — Wiring of 50PTH,PTV,PTD026-072 Units with Complete C Controller, Three Phase (208/230 V)
ON 1 S
J1
Y
W8
W6
W9
W7
W4
W5
W3
W2
W1
S
S
S
S
S
S
S
S
S
M F C
2
O
W
Y
L1 A
F
HUM E
OF
D
A
G
A 1
L A
H D
R
C
W
O
G 1
Y 2
Y
1 B T
C
GGGGR
1
R
G
Y
ECM INTERFACE BOARD LAYOUT
BM
(ECM)
N O
F OF
W7
W9
W4
W6
W3
W5
W2
W8
SW1
S
S
S
S
S
S
S
S
ECM
INTERFACE
BOARD
16
ECM INTERFACE BOARD LAYOUT
Y
GGGGR
W
O
Y2
Y1
G
R
C
Y2
Y1
G
O
W
C
R
DH
AL
1
A
A
AL
1
SW
1
SW
2
SW
3
SW
4
SW
5
SW
6
SW
7
SW
8
SW
9
OFF
ON
G
DEH
UM
C
FM
T
B1
J
1
S
1
BM (ECM)
ECM
INTERFACE
BOARD
SW1
S
W2
S
W3
S
W4
S
W5
S
W6
S
W7
S
W8
S
W9
OFF
O
N
BM
(ECM)
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
COMPR — Compressor
DDC Direct Digital Control
DTS Discharge Temp Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HWG Hot Water Generator
JW1 Jumper, Alarm
NSB Digital Night Setback
LOC Loss of Charge Pressure Switch
MV Motorized Valve
NEC National Electrical Code
LEGEND
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. Transformer for 208/230 v will be connected for 208 v operation. For 230 v operation, dis-
connect RED lead at L1 and attach ORN lead to L1. Insulate open end of RED lead. Trans-
former for 220/240 v will be connected for 220 v operation. For 240 v operation, disconnect
RED lead at L1 and attach ORN lead to L1. Transformer is energy limiting or may have cir-
cuit breaker.
4. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut
JW3 jumper.
5. Typical Aquazone™ thermostat wiring shown. Refer to thermostat installation instructions
for wiring to the unit. Thermostat wiring must be Class 1 and voltage rating equal to or
greater than unit supply voltage.
6. 24-v alarm signal shown. For dry alarm contact, cut AL2 dry jumper and dry contact will be
available between AL1 and AL2.
7. Transformer secondary ground via Deluxe D board standoffs and screws to control box.
(Ground available from top two standoffs as shown.)
8. Aquastat is field-supplied and must be wired in series with the hot leg to the pump.
Aquastat is rated for voltage up to 277 v.
9. Place jumpers on 2 and 3, ECM board, when dehumidification mode is used.
Fig. 18 — Wiring of 50PTH,PTV,PTD026-072 Units with Deluxe D Controller, Three Phase (208/230 V)
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS Transformer
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Thermistor
Ground
Wire Nut
17
ECM INTERFACE BOARD LAYOUT
Y
GGGGR
W
O
Y
2
Y
1
G
R
C
Y
2
Y
1
G
O
W
C
R
D
H
A
L
1
A
A
A
L
1
S
W1
S
W2
S
W3
S
W4
S
W5
S
W6
S
W7
S
W8
S
W9
OF
F
ON
G
D
E
HUM
C
F
M
T
B
1
J1
S
1
BM (ECM)
ECM
INTERFACE
BOARD
BM
(ECM)
SW1
S
W2
S
W3
S
W4
S
W5
S
W6
S
W7
S
W8
S
W9
OF
F
O
N
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
BR Blower Relay
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
COMPR — Compressor
DTS Discharge Temp Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HWG Hot Water Generator
JW1 Jumper, Alarm
LOC Loss of Charge Pressure Switch
MV Motorized Valve
NEC National Electrical Code
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS Transformer
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut JW3
jumper.
4. Typical Aquazone™ thermostat wiring shown. Refer to thermostat installation instructions for wir-
ing to the unit. Thermostat wiring must be Class 1 and voltage rating equal to or greater than unit
supply voltage.
5. 24-v alarm signal shown. For dry alarm contact, cut JW1 jumper and dry contact will be available
between AL1 and AL2.
6. Transformer secondary ground via Complete C board standoffs and screws to control box.
(Ground available from top two standoffs as shown.)
7. Aquastat is field-supplied and must be wired in series with the hot leg to the pump. Aquastat is
rated for voltage up to 277 v.
8. Place jumpers on 2 and 3, ECM board, when dehumidification mode is used.
LEGEND
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Optional Wiring
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Temperature Switch
Thermistor
Ground
Wire Nut
Fig. 19 — Wiring of 50PTH,PTV,PTD026-072 Units with Complete C Controller, Three Phase (460 V)
18
ECM INTERFACE BOARD LAYOUT
Y
GGGGR
W
O
Y2
Y1
G
R
C
Y2
Y1
G
O
W
C
R
DH
AL
1
A
A
AL
1
SW
1
SW
2
SW
3
SW
4
SW
5
SW
6
SW
7
SW
8
SW
9
OFF
ON
G
DEH
UM
C
FM
T
B1
J
1
S
1
BM
(ECM)
ECM
INTERFACE
BOARD
BM
(ECM)
SW1
S
W2
S
W3
S
W4
S
W5
S
W6
S
W7
S
W8
S
W9
OFF
O
N
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
BR Blower Relay
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
DDC Direct Digital Control
DTS Discharge Temp Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HWG Hot Water Generator
JW1 Jumper, Alarm
NSB Digital Night Setback
LOC Loss of Charge Pressure Switch
MV Motorized Valve
NEC National Electrical Code
LEGEND
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS — Transformer
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Thermistor
Ground
Wire Nut
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut JW3
jumper.
4. Typical Aquazone™ thermostat wiring shown. Refer to thermostat installation instructions for wiring
to the unit. Thermostat wiring must be Class 1 and voltage rating equal to or greater than unit supply
voltage.
5. 24-v alarm signal shown. For dry alarm contact, cut AL2 dry jumper and dry contact will be available
between AL1 and AL2.
6. Transformer secondary ground via Deluxe D board standoffs and screws to control box. (Ground
available from top two standoffs as shown.)
7. Fan motors are factory wired for medium speed. For high or low speed, remove BLU wire from fan
motor speed tap “M or “3 and connect to “H or “2 for high speed or “L” or “4” for low speed.
8. Place jumpers on 2 and 3, ECM board, when dehumidification mode is used.
Fig. 20 — Wiring of 50PTH,PTV,PTD026-072 Units with Deluxe D Controller, Three Phase (460 V)
19
*Optional Wiring.
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
BMC Blower Motor Capacitor
BR Blower Relay
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
DTS Discharge Temperature Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HPWS High-Pressure Water Switch
HWG Hot Water Generator
JW1 Clippable Field Selection Jumper
LOC Loss of Charge Pressure Switch
LON Local Operating Network
MV Motorized Valve
MVES Motorized Valve End Switch
NEC National Electrical Code
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS Transformer
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. Transformer is wired to 460 v (BLK/RED) lead for 460/3/60 units. Transformer is energy limiting or may
have circuit breaker.
4. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut JW3 jumper.
5. Typical thermostat wiring shown. Refer to thermostat installation instructions for wiring to the unit. Ther-
mostat wiring must be Class 1 and voltage rating equal to or greater than unit supply voltage.
6. Factory cut JW1 jumper. Dry contact will be available between AL1 and AL2.
7. Transformer secondary ground via Complete C board standoffs and screws to control box. (Ground
available from top two standoffs as shown.)
8. Aquastat is supplied with unit and must be wired in series with the hot leg to the pump. Aquastat is rated
for voltages up to 277-v.
9. Optional LON wires. Only connect if LON connection is desired at the wall sensor.
10. Fan motors are factory wired for medium speed. For high or low speed, remove BLU wire from fan motor
speed tap “M and connect to “H for high speed or “L” for low speed.
11. For low speed, remove BLK wire from BR “6 and replace with RED. Connect BLK and BRN wires
together.
12. For blower motors with leads. For medium or low speed, disconnect BLK wire from BR “6. Connect BLK
and ORG/PUR wire together. Connect RED for low or BLU for medium to BR “6”.
13. The 460-v units using an ECM (electronically commutated motor) fan motor, modulating HWR, and/or an
internal secondary pump will require a neutral wire from the supply side in order to feed the accessory
with 265-v.
Complete C
a50-8363
LEGEND
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Optional Wiring
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Temperature Switch
Thermistor
Ground
Wire Nut
Relay Contacts - N.C.
Relay Contacts - N.O.
Low Pressure Switch
High Pressure Switch
Splice Cap
Circuit Breaker
Fig. 21 — Wiring of 50PTH,PTV,PTD026-072 Units with Complete C and LON Controller, Three Phase (460 V)
20
*Optional Wiring.
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
BMC Blower Motor Capacitor
BR Blower Relay
CB Circuit Breaker
CC Compressor Contactor
CO Sensor, Condensate Overflow
DTS Discharge Temperature Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HPWS High-Pressure Water Switch
HWG Hot Water Generator
JW1 Clippable Field Selection Jumper
LOC Loss of Charge Pressure Switch
LON Local Operating Network
MV Motorized Valve
NEC National Electrical Code
P1 Field Wiring Terminal Block
RVS Reversing Valve Solenoid
TRANS Transformer
LEGEND
Field Line Voltage Wiring
Field Low Voltage Wiring
Printed Circuit Trace
Optional Wiring
Relay/Contactor Coil
Condensate Pan
Solenoid Coil
Temperature Switch
Thermistor
Ground
Wire Nut
Relay Contacts - N.C.
Relay Contacts - N.O.
Low Pressure Switch
High Pressure Switch
Splice Cap
Circuit Breaker
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. Transformer is wired to 460 v (BLK/RED) lead for 460/3/60 units. Transformer is energy limiting or may
have circuit breaker.
4. FP1 thermistor provides freeze protection for water. When using antifreeze solutions, cut JW3 jumper.
5. Typical thermostat wiring shown. Refer to thermostat installation instructions for wiring to the unit. Ther-
mostat wiring must be Class 1 and voltage rating equal to or greater than unit supply voltage.
6. Factory cut JW1 jumper. Dry contact will be available between AL1 and AL2.
7. Transformer secondary ground via Deluxe D board standoffs and screws to control box. (Ground avail-
able from top two standoffs as shown.)
8. Aquastat is supplied with unit and must be wired in series with the hot leg to the pump. Aquastat is rated
for voltages up to 277-v.
9. Place jumpers on 2 and 3, ICM board, when dehumidification mode is used.
10. Optional LON wires. Only connect if LON connection is desired at the wall sensor.
11. Blower motor is factory wired for medium and high speeds. For any other combination of speeds, at the
motor attach the BLK wire to the higher of the two desired speed taps and the BLU wire to the lower of
the two desired speed taps.
12. Blower motor is factory wired for high and low speeds. No other combination is available.
13. The 460-v units using an ECM (electronically commutated motor) fan motor, modulating HWR, and/or an
internal secondary pump will require a neutral wire from the supply side in order to feed the accessory
with 265-v.
Fig. 22 — Wiring of 50PTH,PTV,PTD026-072 Units with Deluxe D and LON Controller, Three Phase (460 V)
Deluxe D
HP
LOC
FP1
FP2
RVS
CO
SEE NOTE 4
a50-8364
21
LEGEND
AL Alarm Relay Contacts
ASTAT Aquastat
BM Blower Motor
BMC Blower Motor Capacitor
BR Blower Relay
CB Circuit Breaker
CC Compressor Contactor
DTS Discharge Temperature Switch
ECM Electronically Commutated Motor
FP1 Sensor, Water Coil Freeze Protection
FP2 Sensor, Air Coil Freeze Protection
HP High-Pressure Switch
HPWS High-Pressure Water Switch
HWG Hot Water Generator
JW Jumper Wire
LOC Loss of Charge Pressure Switch
LWT Leaving Water Temperature
MV Motorized Valve
MVES Motorized Valve End Switch
NEC National Electrical Code
P1 Field Wiring Terminal Block
RH Relative Humidity
RVS Reversing Valve Solenoid
SPT Space Temperature Sensor
TRANS Transformer
Deluxe D
Field Line Voltage Wiring
Relay Contacts - N.C.
Field Low Voltage Wiring
Relay Contacts - N.O.
Printed Circuit Trace
Low Pressure Switch
Optional Wiring
High Pressure Switch
Relay/Contactor Coil Circuit Breaker
Condensate Float Switch Splice Cap
Solenoid Coil
Temperature Switch
Thermistor
Ground
Wire Nut
* Optional wiring.
NOTES:
1. Compressor and blower motor thermally protected internally.
2. All wiring to the unit must comply with NEC and local codes.
3. 208-240 60 Hz units are wired for 208v operation. For 240v 60 Hz
operation switch RED wire to ORG wire. 2240240v 50 Hz units are
wired for 240v operation. For 220v 50 Hz operation switch ORG
wire to RED. Transformer is energy limiting or may have circuit
breaker.
4. FP1 thermistor provides low temperature protection for water.
When using antifreeze solutions, cut JW3 jumper.
5. Refer to thermostat installation, application and operation manual
for control wiring to the unit. Wire from ECM to “Y CXM when a
motorized valve is not used. Thermostat wiring must be “Class 1
and volatage rating equal to or greater than unit supply voltage.
6. 24v alarm signal shown. For dry alarm contact, cut JW1 jumper.
Dry contact will be available between AL1 and AL2.
7. Transformer secondary ground via green wire with yellow stripe
from “C terminal to control box
8. Aquastat is supplied with unit and must be wired in series with the
hot leg to the pump. Aquastat is rated for voltages up to 277v.
9. For field-installed two-position hot water reheat coils disconnect
wire from terminal W1 and connect to field-supplied hot water
valve.
Fig. 23 — Wiring of 50PTH,PTV,PTD026-072 with Deluxe D and WSHP Open Multiple Protocol Controls (Single-Phase 208-230 V)
a50-8570
22
012207-1BT485BT
LED1
DB
Install BT485 where device is
located at the end of network
segment only.
+ 24vac
(If not installed, it must be connected to DO-5)
DEHUMIDIFY OUTPUT CONTACT (DO-6) (FACTORY OPTION)
FAN SPEED (DO-7) (MED OR LOW)
OA DAMPER (AO-2)
FAN SPEED (DO-8) (HIGH OR FAN ON )
LWT (Input 6)
SAT (LAT) (Input 7)
SPACE CO2
SENSOR
+24vac
4-20mA
+
-
AO1 – Aux Reheat or Cond.
WTR. Loop Econ. (AO 1)
-Gnd
Fan (DO-1) (Fan On or Low Speed)
Aux Heat (DO-2)
Reversing Valve (DO-3)
Comp #2 (DO-4)
Comp #1 (DO-5)
Comp Status (DI-5)
SPT PLUS Sensor
Shown
+12V
Rnet-
Rnet+
Gnd
RED
BLACK
WHITE
GREEN
To WSHP Controller
Rnet Terminals (J13)
FIELD INSTALLED
0
5
1
6
2
7
3
8
4
9
0
5
1
6
2
7
3
8
4
9
12
3 45
6
7 8
O
N
1
2 3
4
5
67
8
12
1
2
3
4
123 4
1
2 3
123 45678
GREEN
WHITE
BLACK
RED
Field Installed
J5
J12
J13
J20
J19
J22
J17
J11
J14
To
SPT PLUS
1
2
3
45
6
1
1
10
7
J4
J1 J2
SW3
MSB
LSB
MSTP Baud
9600 19.2k 38.4k 76.8k
SPACE RH
SENSOR
+24vac
4-20mA
+
-
Local Access Port
(FIELD-INSTALLED)
PRIMARY
PRIMARY
CONDENSATE
OVERFLOW SWITCH
REMOTE OCCUPANCY/
FAN STATUS SWITCH
(FIELD-INSTALLED)
NC FIRE/SMOKE
DETECTOR CONTACT
(FIELD-INSTALLED)
Fig. 24 — WSHP Open Control
WSHP Open Inputs and Outputs Table
*These inputs are configurable.
INPUT/OUTPUT TYPE PART NUMBERS TYPE OF I/O
CONNECTION
PIN NUMBERS
CHANNEL
DESIGNATION
Inputs
Space Temperature Sensor SPS, SPPL, SPP Communicating J13, 1 - 4 Local Access Port
Space Relative Humidity 33ZCSENSRH-01 AI (4 - 20mA) J4, 5 and 6 Analog Input 1
Indoor Air Quality 33ZCSENCO2 AI (4 -20mA) J4, 2 and 3 Analog Input 2
Condensate Switch N/A BI (Dry Contacts) J1, 2 Binary Input 3
Stage 1 Compressor Status N/A BI (Dry Contacts) J1, 10 Binary Input 5
Leaving Condenser Water Temperature 10K Type II AI (10K Thermistor) J2, 1 and 2 Analog Input 6
Supply Air Temperature 33ZCSENSAT AI (10K Thermistor) J2, 3 and 4 Analog Input 7
Outputs
Modulating Valve (Auxiliary Heat/Water
Economizer)
N/A AO (0-10Vdc/2 - 10Vdc) J2 4 and 5* Analog Output 1
Outside Air Damper N/A AO (0-10Vdc/2 - 10Vdc) J22 1 and 2* Analog Output 2
Supply Fan On/Low Speed
(3 Speed Only)
N/A BO Relay (24VAC, 1A) J1, 4* Binary Output 1 (G)
Auxiliary Heat or 2-Position Water Loop
Economizer
N/A BO Relay (24VAC, 1A) J1, 5* Binary Output 2
Reversing Valve (B or O Operation) N/A BO Relay (24VAC, 1A) J1, 6* Binary Output 3 (RV)
Compressor 2nd Stage N/A BO Relay (24VAC, 1A) J1, 7 Binary Output 4 (Y2)
Compressor 1st Stage N/A BO Relay (24VAC, 1A) J1, 8 Binary Output 5 (Y1)
Dehumidification Relay N/A BO Relay (24VAC, 1A) J11, 7 and 8 (NO) Binar y Output 6
Fan Speed Medium/Low (3 Speed Only) N/A BO Relay (24VAC, 1A) J11, 5 and 6 (NO)* Binary Output 7
Fan Speed High/Low (3 Speed Only) N/A BO Relay (24VAC, 1A) J11, 2 and 3 (NO)* Binary Output 8
LEGEND
NOTES:
10. Mount the water source heat pump controller in the equipment controls enclosure
with at least two #6 x 1 in. self-tapping screws. Allow adequate clearance for wiring.
11. Verify sensor power and wiring requirements prior to making any terminations. Sen-
sors requiring a separate isolated 24 vac power source will not utilize WSHP termi-
nals J4-1, or 4.
AI Analog Input
AO Analog Output
BI Binary Input
BO Binary Output
SPT Space Temperature
Factory Wiring
Field Wiring
a50-8571
23
COMPRESSOR CONTACTOR
Fig. 25 — 50PTH,PTV,PTD Typical Single-Phase Line Voltage Power Connection
LINE
LOAD
CAPACITOR
COMPLETE C CONTROL
TRANSFORMER
WSHP OPEN WIRING — The WSHP Open controller will be factory mounted to the unit control panel and wired to the Complete C or Deluxe D control board, however, the system wiring will need to be completed utilizing WSHP Open con­troller wiring diagrams and the Third Party Integration (TPI) Guide. Factory installation includes harness, LWT (leaving water temperature), supply air, and condensate sensor.
WARNING
Disconnect all power to the unit before performing mainte­nance or service. Unit may automatically start if power is not disconnected. Failure to follow this warning could cause personal injury, death, and/or equipment damage.
Wiring Sensors to Inputs WSHP Open controller’s inputs. See Table 5.
All field control wiring that connects to the WSHP Open con­troller must be routed through the raceway built into the corner post. The raceway provides the UL required clearance between high and low-voltage wiring.
1. Pass control wires through the hole provided in the corner post.
2. Feed the wires through the raceway to the WSHP Open controller.
3. Connect the wires to the removable Phoenix connectors.
4. Reconnect the connectors to the board.
Field-Supplied Sensor Hardware troller is configurable with the following field-supplied sen­sors. See Table 5.
Table 5 — Field-Supplied Sensors for
WSHP Open Controller
SENSOR NOTES
Space Temperature Sensor
Indoor Air Quality Sensor
NOTE: BACview6 Handheld or Virtual BACview can be used as the user interface.
(SPT)
Outdoor Air
Temperature Sensor
(Separate Sensor)
Space Relative
Humidity Sensor
For specific details about sensors, refer to the literature sup-
plied with the sensor. Wiring a SPT Sensor
ed to a wall-mounted space temperature (SPT) sensor to moni­tor room temperature using a Molex plug.
The WSHP Open system offers the following SPT sensors.
See Table 6.
— Sensors can be wired to the
— The WSHP Open con-
Field Installed (Must be used with
WSHP Open controller.)
Network Sensor
Required only for demand
control ventilation.
Separate Sensor
— A WSHP Open controller is connect-
ECM CONTROL
BOARD
Table 6 — SPT Sensors
SENSOR
SPT
Standard
SPT Plus SPPL
SPT Pro SPP
SPT Pro
Plus
*The SPT Pro Plus fan speed adjustment has no effect in this application.
PA RT
NUMBER
SPS
SPPF
FEATURES
• Local access port
• No operator control
• Slide potentiometer to adjust set point
• Manual on button to override schedule
• LED to show occupied status
• Local access port
• LCD display
• Manual on button to override schedule
• Warmer and cooler buttons to adjust set point
• Info button to cycle through zone and outside air temperatures, set points, and local override time
• Local access port
• LCD display
• Manual on button to override schedule
• Warmer and cooler buttons to adjust set point
• Info button to cycle through zone and outside air temperatures, set points, and local override time
• Local access port
• Fan speed*
Wire SPT sensors to the WSHP Open controller’s Rnet port. An Rnetbus can consist of any of the following combina­tions of devices wired in a daisy-chain configuration:
• 1 SPT Plus, SPT Pro, or SPT Pro Plus sensor
• 1 to 4 SPT Standard sensors
• 1 to 4 SPT Standard sensors and 1 SPT Plus, SPT Pro, or
SPT Pro Plus sensor
• Any of the above combinations, plus up to 2 BACview
Handheld but no more than 6 total devices NOTE: If the Rnetbus has multiple SPT Standard sensors, each
sensor must be given a unique address on the Rnetbus. See the Carrier Open Sensor Installation Guide.
Use the specified type of wire and cable for maximum signal integrity. See Table 7.
Table 7 — Rnet Wiring Specifications
RNET WIRING SPECIFICATIONS
Description
Conductor 18 AWG
Maximum Length 500 ft
Recommended Coloring
UL Temperature 32 to 167 F
Vo lta ge 300-vac, power limited
Listing UL: NEC CL2P, or better
AWG — American Wire Gage CMP — Communications Plenum Cable NEC — National Electrical Code UL Underwriters Laboratories
LEGEND
4 conductor, unshielded, CMP,
plenum rated cable
Jacket: white
Wiring: black, white, green, red
6
24
To wire the SPT sensor to the controller:
Fig. 26 — Rnet Cable Wire
a50-8443
1. Partially cut , then bend and pull off the outer jacket of the Rnet cable(s), being careful not to nick the inner insulation.
2. Strip about
1
/4 in. of the inner insulation from each wire.
See Fig. 26.
OUTER JACKET
.25 IN.
INNER INSULATION
3. Wire each terminal on the sensor to the same terminal on the controller. See Fig. 15-24. Table 8 shows the recom­mended Rnet wiring scheme.
Table 8 — Rnet Wiring
WIRE TERMINAL
Red +12-v Black .Rnet White Rnet+ Green Gnd
NOTE: The wire should be connected to the terminal shown.
Wiring a Supply Air Temperature (SAT) Sensor — The SAT sensor is required for reheat applications.
If the cable used to wire the SAT sensor to the controller will be less than 100 ft, an unshielded 22 AWG (American Wire Gage) cable should be used. If the cable will be greater than 100 ft, a shield 22 AWG cable should be used. The cable should have a maximum length of 500 ft.
To wire the SAT sensor to the controller:
1. Wire the sensor to the controller. See Fig. 15-24.
2. Verify that the Enable SAT jumper is on.
3. Verify that the Enable SAT and Remote jumper is in the left position.
Wiring an Indoor Air Quality (IAQ) Sensor
— An IAQ sensor monitors CO2 levels. The WSHP Open controller uses this information to adjust the outside-air dampers to provide proper ventilation. An IAQ sensor can be wall-mounted or mounted in a return air duct. (Duct installation requires an aspi­rator box assembly.)
The sensor has a range of 0 to 2000 ppm and a linear 4 to
20 mA output. This is converted to 1 to 5 vdc by a 250-ohm,
1
/4 watt, 2% tolerance resistor connected across the zone con-
troller’s IAQ input terminals. NOTE: Do not use a relative humidity sensor and CO
on the same zone controller if both sensors are powered off the
sensor
2
board. If sensors are externally powered, both sensors may be used on the same zone controller.
If the cable used to wire the IAQ sensor to the controller will be less than 100 ft, an unshielded 22 AWG (American Wire Gage) cable should be used. If the cable will be greater than 100 ft, a shield 22 AWG cable should be used. The cable should have a maximum length of 500 ft.
To wire the IAQ sensor to the controller:
1. Wire the sensor to the controller. See Fig. 15-24.
2. Install a field-supplied 250-ohm,
1
/4 watt, 2% tolerance resistor across the controller’s RH/IAQ and Gnd terminals.
3. Verify the the RH/IAQ jumper is set to 0 to 5 vdc.
Wiring a Relative Humidity (RH) Sensor
— The RH sensor is used for zone humidity control (dehumidification) if the WSHP unit has a dehumidification device. If not, the sensor only monitors humidity.
NOTE: Do not use a relative humidity sensor and CO on the same zone controller if both sensors are powered off the
sensor
2
board. If sensors are externally powered, both sensors may be used on the same zone controller.
If the cable used to wire the RH sensor to the controller will be less than 100 ft, an unshielded 22 AWG (American Wire Gage) cable should be used. If the cable will be greater than 100 ft, a shield 22 AWG cable should be used. The cable should have a maximum length of 500 ft.
To wire the RH sensor to the controller:
1. Strip the outer jacket from the cable for at least 4 inches.
2. Strip
1
/4 in. of insulation from each wire.
3. Wire the sensor to the controller.
Step 9 — Wire Field Controls
THERMOSTAT CONNECTIONS — The thermostat should be wired directly to the ECM control board. See Fig. 27.
WATER FREEZE PROTECTION — The Aquazone™ con­trol allows the field selection of source fluid freeze protection points through jumpers. The factory setting of jumper JW3 (FP1) is set for water at 30 F. In earth loop applications, jumper JW3 should be clipped to change the setting to 10 F when using antifreeze in colder earth loop applications. See Fig. 28.
NOTE: The extended range option should be selected with water temperatures below 60 F to prevent internal condensation.
AIR COIL FREEZE PROTECTION — The air coil freeze protection jumper JW2 (FP2) is factory set for 30 F and should not need adjusting.
ACCESSORY CONNECTIONS — Terminal A on the control is provided to control accessory devices such as water valves, electronic air cleaners, humidifiers, etc. This signal operates with the compressor terminal. See Fig. 29. Refer to the specific unit wiring schematic for details.
NOTE: The A terminal should only be used with 24-volt signals — not line voltage signals.
WATER SOLENOID VALVES — An external solenoid valve(s) should be used on ground water installations to shut off flow to the unit when the compressor is not operating. A slow closing valve may be required to help reduce water hammer. Figure 29 shows typical wiring for a 24-vac external solenoid valve. Figures 30 and 31 illustrate typical slow closing water control valve wiring for Taco 500 Series and Taco ESP Series valves. Slow closing valves take approximately 60 sec. to open (very little water will flow before 45 sec.). Once fully open, an end switch allows the compressor to be energized (on­ly on valves with end switches). Only relay or triac based elec­tronic thermostats should be used with slow closing valves. When wired as shown, the slow closing valve will operate properly with the following notations:
1. The valve will remain open during a unit lockout.
2. The valve will draw approximately 25 to 35 VA through the “Y” signal of the thermostat.
IMPORTANT: Connecting a water solenoid valve can overheat the anticipators of electromechanical thermo­stats. Only use relay based electronic thermostats.
25
TYPICAL WATER VALVE
C
A
24 VAC
TERMINAL STRIP P2
Fig. 27 — Low Voltage Field Wiring
AQUAZONE CONTROL (Complete C Shown)
Fig. 28 — Typical Aquazone™ Control Board
Jumper Locations
Fig. 29 — Typical Accessory Wiring
a50-8141
a50-7764tf
Fig. 30 — AMV Valve Wiring
C
C
THERMOSTAT
1Y
1
2
3
1Y
AMV
TACO VALVE
HEATER SWITCH
a50-8441
Fig. 31 — Taco SBV Valve Wiring
a50-8442
COMPRESSOR CONTACTOR
LINE
TRANSFORMER
CAPACITOR
LOAD
COMPLETE C CONTROL
W
O
Y2
Y1
G
GGGGR
TB1
CFM
J1
Y
SW1 SW2 SW3 SW4 SW5 SW6 SW7 SW8 SW9
OFF
DEHUM
G
S1
ON
Y2
R
C
Y1
THERMOSTAT CONNECTION
DH
R
C
W
G
O
A
A
AL1
AL1
26
+
Y
GGGGR
W
O
Y2
Y1
G
R
C
Y2
Y1
G
O
W
C
R DH
AL1
A
A
AL1
SW1
SW2
SW3
SW4
SW5
SW6
SW7
SW8
SW9
OFF
ON
G
DEHUM
CFM
TB1
J1
S1
THERMOSTAT INPUT LEDS
CFM COUNTER 1 FLASH PER 100 CFM
ECM MOTOR LOW VOLTAGE CONNECTOR
1/4" SPADE
CONNECTIONS
TO COMPLETE C OR
DELUXE D BOARD
THERMOSTAT
CONNECTIONS
DEHUMIDIFICATION
LED
FAN SPEED SELECTION DIP SWITCH
Fig. 32 — ECM Interface Board Physical Layout
Step 10 — Operate ECM Interface Board
STANDALONE — NO DDC CONTROLS — The ECM fan is controlled by an interface board that converts thermostat inputs and field selectable cfm settings to signals used by the ECM (electronically commutated motor) controller. See Fig. 32.
NOTE: Power must be off to the unit for at least three seconds before the ECM will recognize a speed change. The motor will recognize a change in the CFM Adjust or Dehumidification mode settings while the unit is powered.
There are four different airflow settings from lowest airflow rate (speed tap 1) to the highest airflow rate (speed tap 4). Tables 9-13 indicate settings for the ECM interface board, fol­lowed by detailed information for each setting.
CAUTION
When the disconnect switch is closed, high voltage is pres­ent in some areas of the electrical panel. Exercise caution when working with energized equipment.
Cooling mal) cfm for all units with ECM motor. Cooling (normal) set­ting is used when the unit is not in Dehumidification mode. Tap 1 is the lowest cfm setting, while tap 4 is the highest cfm set­ting. To avoid air coil freeze-up, tap 1 may not be used if the Dehumidification mode is selected. See Table 9.
Heating for 50PTH,PTV,PTD units. Tap 1 is the lowest cfm setting, while tap 4 is the highest cfm setting. See Table 10.
CFM Adjust tions. The NORM setting is the factory default position. The + or – settings adjust the airflow by ±15%. The + or – settings are used to “fine tune” airflow adjustments. The TEST setting runs the ECM at 70% torque, which causes the motor to operate like a standard PSC motor, and disables the cfm counter. See Tab le 11.
— The cooling setting determines the cooling (nor-
Table 9 — Cooling Settings
TAP SETTING
1 ON ON 2 ON OFF 3 OFF ON 4 OFF OFF
DIP SWITCH
SW1 SW2
— The heating setting determines the heating cfm
Table 10 — Heating Settings
TAP SETTING
1 ON ON 2 ON OFF 3 OFF ON 4 OFF OFF
DIP SWITCH
SW3 SW4
— The CFM Adjust setting allows four selec-
Table 11 — CFM Adjust Settings
TAP SETTING
TEST ON ON
NORM OFF OFF
DIP SWITCH
SW7 SW8
ON OFF
OFF ON
Dehumidification Mode
— The dehumidification mode setting provides field selection of humidity control. When op­erating in the normal mode, the cooling airflow settings are de­termined by the cooling tap setting in Table 12.
Table 12 — Dehumidificaton Mode Settings
TAP SETTING
NORM ON
Dehumid OFF
DIP SWITCH
SW9
When dehumidification is enabled, there is a reduction in airflow in cooling to increase the moisture removal of the heat pump. The Dehumidification mode can be enabled in two ways:
1. Constant Dehumidification mode: When the Dehumidifi­cation mode is selected via DIP switch, the ECM will operate with a multiplier applied to the cooling CFM settings (approximately 20 to 25% lower airflow). Any time the unit is running in the Cooling mode, it will oper­ate at the lower airflow to improve latent capacity. The “DEHUM” LED will be illuminated at all times. Heating airflow is not affected.
NOTE: Do not select Dehumidification mode if cooling setting is tap 1.
2. Automatic (humidistat-controlled) Dehumidification mode: When the Dehumidification mode is selected via DIP switch AND a humidistat is connected to termi­nal DH, the cooling airflow will only be reduced when the humidistat senses that additional dehumidification is required. The DH terminal is reverse logic. Therefore, a humidistat (not dehumidistat) is required. The “DEHUM” LED will be illuminated only when the hu­midistat is calling for Dehumidification mode. Heat­ing airflow is not affected.
NOTE: Do not select Dehumidification mode if cooling setting is tap 1.
27
Table 13 — Blower Performance Data
50PT
UNIT SIZE
026 0.50
038 0.50
049 0.75 1
064 0.75 1
072 0.75 1
MAX ESP
(in. wg)
FAN
MOTOR
(hp)
1
/
2
1
/
2
TAP
SETTING
4 810 950 475 630 740 475 920 1060 475 3 725 850 425 560 660 425 825 950 425 2 620 730 370 490 570 370 710 820 370 1 520 610 300 600 690 300 4 1120 1400 700 870 1090 700 1120 1400 700 3 1000 1250 630 780 980 630 1000 1250 630 2 860 1080 540 670 840 540 860 1080 540 1 730 900 450 730 900 450 4 1460 1730 870 1140 1350 870 1560 1850 870 3 1300 1550 780 1020 1210 780 1400 1650 780 2 1120 1330 670 870 1040 670 1200 1430 670 1 940 1120 560 1010 1200 560 4 1670 2050 1020 1300 1600 1020 1860 2280 1020 3 1500 1825 920 1160 1430 920 1650 2050 920 2 1280 1580 790 1000 1230 790 1430 1750 790 1 1080 1320 660 1200 1470 660 4 1620 2190 1050 1270 1650 1050 1690 2230 1050 3 1500 1950 980 1170 1520 980 1600 2100 980 2 1400 1830 910 1100 1420 910 1400 1850 910 1 1320 1700 850 1240 1620 850
COOLING MODE (cfm) DEHUMIDIFICATION MODE (cfm) HEATING MODE (cfm)
Stage 1 Stage 2 Fan Stage 1 Stage 2 Fan Stage 1 Stage 2 Fan
WSHP OPEN CONTROLS — The ECM fan is controlled by an interface board that converts the fan speed outputs from the WSHP Open control board to the signal used by the ECM mo­tor (see Fig 35). The indicator LEDs allow the service techni­cian to view the airflow mode that the WSHP Open control is commanding. The table below indicates the illuminated LEDs for each fan mode.
ECM INDICATORS LEDs SPEED
G Fan Only
G + Y1 Low Fan
G + Y1 + Y2 Med Fan
G + Y1 +W High Fan
NOTE: Power must be off to the unit for at least three seconds before the ECM will recognize a speed change. The motor will recognize a change in the CFM Adjust setting (SW7 and SW8) while the unit is powered.
The WSHP Open controller provides four different airflow settings which can be set between the lowest airflow (tap 1) to the highest airflow (tap 4). The lowest three airflow settings (Fan Only, Low, and Medium) are set using SW3 and SW 4 while the highest airflow (High) is set independently using SW5 and SW6. This provides the ability to better adjust the fan performance of the unit to meet the required load conditions.
Cooling and Heating
— The SW3 and SW4 DIP switch set­tings determine the fan airflow (cfm) to be used during normal Fan Only, Cooling, Heating, and Dehumidification modes (see
Table 14A). The fan speed and airflow is independent from the compressor capacity control. During Fan Only operation, the fan will operate at the Fan Only airflow value specified in the table for the appropriate tap setting. Once either cooling or heating is required and the compressor is energized, the fan will increase the minimum airflow across the coil to the value defined by the low fan selection. Coil freeze protection and ex­cessive discharge air temperature protection are integral parts of the WSHP Open controller function so the fan airflow can increase to medium or high airflow as required and indepen­dent of compressor capacity to prevent excessively hot or cold supply air temperature and coil freeze-up. The selection of the high fan airflow setting is independent of the other fan airflow settings and is defined in Table 14B. The high airflow must be chosen so that it is equal to or greater than the medium fan air­flow. Therefore the tap setting for high fan (SW5 and SW6) MUST equal or exceed the tap chosen for the SW3 and SW4.
Dehumidification
— When Dehumidification is used, the fan operates at the airflow setting defined by the Medium Fan air­flow setting and the tap position of SW3 and SW4.
CFM Adjust
— The CFM Adjust setting allows the balancer to fine tune the actual airflow. SW7 and SW8 are used to set the CFM Adjustment if necessary. The NORM setting is the factory default. The (+) or (-) settings provide the ability to ad­just the airflow by either +15% or -15% as needed. A test posi­tion is also provided but should not be used (see Table 11).
28
Table 14A — WSHP Open — Fan Only / Low Fan and Med Fan Airflow
50PT UNIT
SIZE
26 0.5 0.5
38 0.5 0.5
49 0.75 1
64 0.75 1
72 0.75 1
NOTE: Factory default setting shown bold. IMPORTANT: The tap setting for high fan MUST equal or exceed the
MAX
ESP
FAN MOTOR
HP
TAP SETTING
4 OFF OFF 475 920 1050 3 OFF ON 425 825 950
2 ON OFF 370 710 820
1 ON ON 300 600 690 4 OFF OFF 700 1120 1400 3 OFF ON 630 1000 1250
2 ON OFF 540 860 1080
1 ON ON 450 730 900 4 OFF OFF 870 1560 1850 3 OFF ON 780 1400 1650
2 ON OFF 670 1200 1430
1 ON ON 560 1010 1200 4 OFF OFF 1020 1860 2280 3 OFF ON 920 1650 2040
2 ON OFF 780 1430 1750
1 ON ON 660 1200 1470 4 OFF OFF 1050 1600 2230 3 OFF ON 980 1600 2100
2 ON OFF 910 1400 1850
1 ON ON 850 1240 1620
SW 3
(SW 1)
SW 4
(SW 2)
FAN ONLY
tap setting for fan only/low/med fan
COOLING AND
HEATING LOW FAN
COOLING AND
HEATING MED FAN
Table 14B — WSHP Open — High Fan Airflow
50PT UNIT SIZE MAX ESP FAN MOTOR HP TAP SETTING SW 5 SW 6 COOLING AND HEATING HIGH FAN
4 OFF OFF 1060
26 0.5 0.5
38 0.5 0.5
49 0.75 1
64 0.75 1
72 0.75 1
NOTE: Factory default setting shown bold. IMPORTANT: The tap setting for high fan MUST equal or exceed the tap setting for fan only/low/med fan
3 OFF ON 950 2 ON OFF 820 1 ON ON 690
4 OFF OFF 1400
3 OFF ON 1350 2 ON OFF 1350 1 ON ON 1350
4 OFF OFF 1850
3 OFF ON 1660 2 ON OFF 1430 1 ON ON 1350
4 OFF OFF 2280
3 OFF ON 2050 2 ON OFF 1750 1 ON ON 1470
4 OFF OFF 2230
3 OFF ON 2100 2 ON OFF 1870 1 ON ON 1670
5. Air is purged from closed loop system.
6. System is balanced as required. Monitor if necessary.
7. Isolation valves are open.
PRE-START-UP
System Checkout —
follow the system checkout procedure outlined below before starting up the system. Be sure:
1. Voltage is within the utilization range specifications of the unit compressor and fan motor and voltage is balanced for 3-phase units.
2. Fuses, breakers and wire are correct size.
3. Low voltage wiring is complete.
4. Piping and system flushing is complete.
When the installation is complete,
8. Water control valves or loop pumps are wired.
9. Condensate line is open and correctly pitched.
10. Transformer switched to lower voltage tap if necessary.
11. Blower rotates freely — shipping support is removed.
12. Blower speed is on correct setting.
13. Air filter is clean and in position.
14. Service/access panels are in place.
15. Return-air temperature is between 40 to 80 F heating and 50 to 110 F cooling.
29
16. Air coil is clean.
17. Control field-selected settings are correct.
AIR COIL — To obtain maximum performance, clean the air coil before starting the unit. A 10% solution of dishwasher detergent and water is recommended for both sides of the coil. Rinse thoroughly with water.
FIELD SELECTABLE INPUTS
Jumpers and DIP (dual in-line package) switches on the control board are used to customize unit operation and can be configured in the field.
IMPORTANT: Jumpers and DIP switches should only be clipped when power to control board has been turned off.
Complete C Control Jumper Settings
WATER COIL FREEZE PROTECTION (FP1) LIMIT SETTING — Select jumper 3 (JW3-FP1 Low Temp) to choose FP1 limit of either 30 F or 10 F. To select 30 F as the limit, DO NOT clip the jumper. To select 10 F as the limit, clip the jumper.
AIR COIL FREEZE PROTECTION (FP2) LIMIT SET­TING — Select jumper 2 (JW2-FP2 Low Temp) to choose FP2 limit of either 30 F or 10 F. To select 30 F as the limit, DO NOT clip the jumper. To select 10 F as the limit, clip the jumper.
ALARM RELAY SETTING — Select jumper 1 (JW1-AL2 Dry) to either connect alarm relay terminal (AL2) to 24 vac (R) or to remain as a dry contact (no connection). To connect AL2 to R, DO NOT clip the jumper. To set as dry contact, clip the jumper.
Deluxe D Control Jumper Settings
WATER COIL FREEZE PROTECTION (FP1) LIMIT SETTING — Select jumper 3 (JW3-FP1 Low Temp) to choose FP1 limit of either 30 F or 10 F. To select 30 F as the limit, DO NOT clip the jumper. To select 10 F as the limit, clip the jumper.
AIR COIL FREEZE PROTECTION (FP2) LIMIT SET­TING — Select jumper 2 (JW2-FP2 Low Temp) to choose FP2 limit of either 30 F or 10 F. To select 30 F as the limit, DO NOT clip the jumper. To select 10 F as the limit, clip the jumper.
ALARM RELAY SETTING — Select jumper 4 (JW4-AL2 Dry) to either connect alarm relay terminal (AL2) to 24 vac (R) or to remain as a dry contact (no connection). To connect AL2 to R, DO NOT clip the jumper. To set as dry contact, clip the jumper.
LOW PRESSURE SETTING — The Deluxe D control can be configured for Low Pressure Setting (LP). Select jumper 1 (JW1-LP Norm Open) for choosing between low pressure input normally opened or closed. To configure for normally closed operation, DO NOT clip the jumper. To configure for normally open operation, clip the jumper.
Complete C Control DIP Switches — The Com-
plete C control has 1 DIP (dual in-line package) switch bank with five switches labeled SW1. See Fig. 15, 17 , 19, and 21.
PERFORMANCE MONITOR (PM) — The PM is a unique feature that monitors water temperature and will display a warn­ing when heat pump is beyond typical operating range. Refer to Control Operation section for detailed information. DIP switch 1 will enable or disable this feature. To enable the PM, set the switch to ON. To disable the PM, set the switch to OFF.
STAGE 2 — DIP switch 2 will enable or disable compressor delay. Set DIP switch to OFF for stage 2 in which the compres­sor will have a 3-second delay before energizing.
NOTE: The alarm relay will not cycle during Test mode if switch is set to OFF, stage 2.
SWITCH 3 — Not used. DDC OUTPUT AT EH2 — Switch 4 provides a selection for
Direct Digital Control (DDC) operation. If set to DDC output at EH2, the EH2 terminal will continuously output the last fault code of the controller. If the control is set to EH2 Normal, then EH2 will operate as standard electric heat output. Set the switch to ON to set the EH2 to normal. Set the switch to OFF to set the DDC output at EH2.
FACTORY SETTING — Switch 5 is set to ON. Do not change the switch to OFF unless instructed to do so by the factory.
Deluxe D Control DIP Switches — The Deluxe D
control has 2 DIP (dual in-line package) switch banks. Each bank has 8 switches and is labeled either S1 or S2 on the cir­cuit board. See Fig. 16, 18, 20, 22, and 23.
DIP SWITCH BANK 1 (S1) — This set of switches offers the following options for Deluxe D control configuration:
Performance Monitor (PM) that monitors water temperature and will display a warning when heat pump is beyond typical operating range. Set switch 1 to enable or disable performance monitor. To enable the PM, set the switch to ON. To disable the PM, set the switch to OFF.
Compressor Relay Staging Operation able or disable compressor relay staging operation. The com­pressor relay can be set to turn on with stage 1 or stage 2 call from the thermostat. This setting is used with dual stage units (units with 2 compressors and 2 Deluxe D controls) or in mas­ter/slave applications. In master/slave applications, each com­pressor and fan will stage according to its switch 2 setting. If switch is set to stage 2, the compressor will have a 3-second delay before energizing during stage 2 demand.
NOTE: If DIP switch is set for stage 2, the alarm relay will not cycle during Test mode.
Heating/Cooling Thermostat Type lection of thermostat type. Heat pump or heat/cool thermostats can be selected. Select OFF for heat/cool thermostats. When in heat/cool mode, Y1 is used for cooling stage 1, Y2 is used for cooling stage 2, W1 is used for heating stage 1 and O/W2 is used for heating stage 2. Select ON for heat pump thermostats. In heat pump mode, Y1 used is for compressor stage 1, Y2 is used for compressor stage 2, W1 is used for heating stage 3 or emergency heat, and O/W2 is used for reversing valve (heating or cooling) depending upon switch 4 setting.
O/B Thermostat Type pump O/B thermostats. O is cooling output. B is heating out­put. Select ON for thermostats with O output. Select OFF for thermostats with B output.
Dehumidification Fan Mode of normal or dehumidification fan mode. Select OFF for dehumidification mode. The fan speed relay will remain OFF during cooling stage 2. Select ON for normal mode. The fan speed relay will turn on during cooling stage 2 in normal mode.
Output
— Switch 6 provides selection for DDC operation. If set to DDC output at EH2, the EH2 terminal will continuously output the last fault code of the controller. If the control is set to EH2 normal, then the EH2 will operate as standard electric heat output. Set the switch to ON to set the EH2 to normal. Set the switch to OFF to set the DDC output at EH2.
Boilerless Operation erless operation and works in conjunction with switch 8. In boilerless operation mode, only the compressor is used for heating when FP1 is above the boilerless changeover tempera­ture set by switch 8 below. Select ON for normal operation or select OFF for boilerless operation.
— The PM is a unique feature
— Switch 2 will en-
— Switch 3 provides se-
— Switch 4 provides selection for heat
— Switch 5 provides selection
— Switch 7 provides selection of boil-
30
Boilerless Changeover Temperature
— Switch 8 on S1 provides selection of boilerless changeover temperature set point. Select OFF for set point of 50 F or select ON for set point of 40 F.
If switch 8 is set for 50 F, then the compressor will be used for heating as long as the FP1 is above 50 F. The compressor will not be used for heating when the FP1 is below 50 F and the compressor will operates in emergency heat mode, staging on EH1 and EH2 to provide heat. If a thermal switch is being used instead of the FP1 thermistor, only the compressor will be used for heating mode when the FP1 terminals are closed. If the FP1 terminals are open, the compressor is not used and the control goes into emergency heat mode.
DIP SWITCH BANK 2 (S2) — This set of DIP switches is used to configure accessory relay options. See Fig. 16, 18, 20, 22, and 23.
Switches 1 to 3
— These DIP switches provide selection of Accessory 1 relay options. See Table 15A for DIP switch combinations.
Switches 4 to 6
— These DIP switches provide selection of Accessory 2 relay options. See Table 15B for DIP switch combinations.
Table 15A — DIP Switch Block S2 —
Accessory 1 Relay Options
ACCESSORY 1
RELAY OPTIONS
Cycle with Fan On On On
Digital NSB Off On On
Water Valve — Slow Opening On Off On
Reheat — Dehumidistat Off On Off
NSB — Night Setback OAD — Outside Air Damper
NOTE: All other DIP switch combinations are invalid.
OAD On On Off
Reheat — Humidistat Off Off Off
LEGEND
DIP SWITCH POSITION
123
Table 15B — DIP Switch Block S2 —
Accessory 2 Relay Options
ACCESSORY 2
RELAY OPTIONS
Cycle with Compressor On On On
Digital NSB Off On On
Water Valve — Slow Opening On Off On
NSB — Night Setback OAD — Outside Air Damper
NOTE: All other switch combinations are invalid.
OAD On On Off
LEGEND
DIP SWITCH POSITION
456
Auto Dehumidification Mode or High Fan Mode — Switch 7 provides selection of auto dehumidification fan mode or high fan mode. In auto dehumidification fan mode, the fan speed relay will remain off during cooling stage 2 if terminal H is active. In high fan mode, the fan enable and fan speed relays will turn on when terminal H is active. Set the switch to ON for auto dehumidification fan mode or to OFF for high fan mode.
Factory Setting
— Switch 8 is set to ON. Do not change the switch to OFF unless instructed to do so by the factory.
Units with Modulating Hot Water Reheat (HWR) Option
STANDALONE — NO DDC CONTROLS — A heat pump equipped with hot water reheat (HWR) can operate in three modes: cooling, cooling with reheat, and heating. The cooling and heating modes are like any other water source heat
pump. The reversing valve ("O" signal) is energized in cool­ing, along with the compressor contactor(s) and blower relay. In the heating mode, the reversing valve is deenergized. Almost any thermostat will activate the heat pump in heating or cooling modes. The Deluxe D microprocessor board, which is standard with the HWR option, will accept either heat pump (Y,O) thermostats or non-heat pump (Y,W) thermostats.
The reheat mode requires either a separate humidistat/ dehumidistat or a thermostat that has an integrated dehumidifi­cation function for activation. The Deluxe D board is config­ured to work with either a humidistat or dehumidistat input to terminal “H” (DIP switch settings for the Deluxe D board are shown in Table 16). Upon receiving an “H” input, the Deluxe D board will activate the cooling mode and engage reheat.
Table 16 — Humidistat/Dehumidistat Logic and
Deluxe D DIP Switch Settings
Sensor 2.1
Humidistat
Dehumidistat Off On Off Standard 24 VAC 0 VAC
2.2 2.3 Logic
Of f O ff O ff Re ve rs e 0 VA C 24 VAC
Reheat
(ON) - H
Reheat
(OFF) - H
Table 17 shows the relationship between thermostat input signals and unit operation. There are four operational inputs for single-stage units and six operational inputs for dual-stage units:
•Fan Only
• Cooling Stage 1
• Cooling Stage 2
• Heating Stage 1
• Heating Stage 2
• Reheat Mode WSHP OPEN CONTROLS — A heat pump equipped with
the hot water reheat option and the WSHP Open controller, operates in three modes: Cooling, Heating and Dehumidifica­tion. Cooling and Heating modes follow the standard water source heat pump operation with the reversing valve control­ling the operating mode (Heating or Cooling) and the compres­sor.
The hot water reheat option uses the Deluxe D board and the optional humidity sensor to provide dehumidification oper­ation that is separate from the standard heating or cooling cy­cle. The Dehumidification mode is active when the value of the humidity sensor exceeds the appropriate (occupied or unoccu­pied) humidity setpoint in the WSHP Open controller. When this occurs, the WSHP Open controller outputs a signal to the H terminal of the Deluxe D board which starts dehumidifica­tion with hot water reheat. The WSHP Open controller also sets the fan to operate at the airflow defined by the medium fan speed and the tap setting of SW3 and SW4. Dehumidification is ONLY active when neither cooling nor heating is required and the humidity sensor value exceeds the humidity setpoint. Also, both the HWR option and the Optional RH sensor must be set to Enable in the WSHP Open control for dehumidifica­tion.
HWR APPLICATION CONSIDERATIONS — Unlike most hot gas reheat options, the HWR option will operate over a wide range of entering-water temperatures (EWTs). Special flow regulation (water regulating valve) is not required for low EWT conditions. However, below 55 F, supply-air temperatures cannot be maintained at 72 F because the cooling capacity exceeds the reheat coil capac­ity at low water temperatures. Below 55 F, essentially all water is diverted to the reheat coil (no heat of rejection to the building loop). Although the HWR option will work fine with low EWTs, overcooling of the space may result with well water systems or, on rare occasions, with ground loop (geothermal) systems (NOTE: Extended range units are required for well water and ground loop systems). Since dehumidification is generally only required in cooling, most
31
ground loop systems will not experience overcooling of the supply-air temperature. If overcooling of the space is a con­cern (e.g., computer room well water application), auxiliary heating may be required to maintain space temperature when the unit is operating in the dehumidification mode. Water source heat pumps with HWR should not be used as makeup air units. These applications should use equipment specifically designed for makeup air.
HWR COMPONENT FUNCTIONS — The proportional controller operates on 24 VAC power supply and automatically adjusts the water valve based on the supply-air sensor. The supply-air sensor senses supply-air temperature at the blower inlet, providing the input signal necessary for the proportional control to drive the motorized valve during the reheat mode of operation. The motorized valve is a proportional actuator/three­way valve combination used to divert the condenser water from the coax to the hydronic reheat coil during the reheat mode of operation. The proportional controller sends a signal to the motorized valve based on the supply-air temperature reading from the supply air sensor.
The loop pump circulates condenser water through the hy­dronic reheat coil during the reheat mode of operation (refer to Fig. 33). In this application, the loop pump is only energized during the reheat mode of operation. The hydronic coil is uti­lized during the reheat mode of operation to reheat the air to the set point of the proportional controller. Condenser water is di­verted by the motorized valve and pumped through the hydron­ic coil by the loop pump in proportion to the control set point. The amount of reheating is dependent on the set point and how far from the set point the supply air temperature is. The factory set point is 70 to 75 F, generally considered "neutral" air.
Deluxe D Control Accessory Relay Configura­tions — The following accessory relay settings are applica-
ble for Deluxe D control:
CYCLE WITH FAN — In this configuration, the accessory relay 1 will be ON any time the Fan Enable relay is on.
CYCLE WITH COMPRESSOR — In this configuration, the accessory relay 2 will be ON any time the Compressor relay is on.
DIGITAL NIGHT SET BACK (NSB) — In this configura­tion, the relay will be ON if the NSB input is connected to ground C.
NOTE: If there are no relays configured for digital NSB, then the NSB and override (OVR) inputs are automatically config­ured for mechanical operation.
MECHANICAL NIGHT SET BACK — When NSB input is connected to ground C, all thermostat inputs are ignored. A thermostat set back heating call will then be connected to the OVR input. If OVR input becomes active, then the Deluxe D control will enter night low limit (NLL) staged heating mode. The NLL staged heating mode will then provide heating dur­ing the NSB period.
WATER VALVE (SLOW OPENING) — If relay is configured for Water Valve (slow opening), the relay will start 60 seconds prior to starting compressor relay.
OUTSIDE AIR DAMPER (OAD) — If relay is configured for OAD, the relay will normally be ON any time the Fan Enable relay is energized. The relay will not start for 30 minutes fol­lowing a return to normal mode from NSB, when NSB is no longer connected to ground C. After 30 minutes, the relay will start if the Fan Enable is set to ON.
CAUTION
To avoid equipment damage, DO NOT leave system filled in a building without heat during the winter unless anti­freeze is added to system water. Condenser coils never fully drain by themselves and will freeze unless winterized with antifreeze.
Table 17 — HWR Operating Modes
MODE
No Demand On/Off Off Off Off Off On/Off Off Off Off Off Fan Only On/Off On Off Off Off On/Off On Off Off Off Cooling Stage 1 On On On Off Off On On On Off Off Cooling Stage 2 On On On On Off On On On On Off Cooling and Dehumidistat Dehumidistat Only On/Off Off Off Off On On On On On On Heating Stage 1 Off On On Off Off Off On On Off Off Heating Stage 2 Off OnOnOnOffOffOnOnOnOff Heating and Dehumidistat** Off On On On/Off On Off On On On/Off Off
*Not applicable for single stage units; Full load operation for dual capacity units. †Cooling input takes priority over dehumidify input.
O G Y1 Y2* H O G Y1 Y2* Reheat
On On On On/Off On On On On On/Off Off
INPUT OUTPUT
**Deluxe D is programmed to ignore the H demand when the unit is in heating mode. NOTE: On/Off is either on or off.
32
START-UP
Fig. 33 — HWR Schematic
a50-8145
Water Out (To Water Loop)
Water In (From Water Loop)
Mixing Valve
COAX
Evaporator Coil
Reheat
Coil
Refrigerant Out
(Cooling)
Refrigerant In
(Cooling)
Entering Air
Leaving
Air
Internal Pump
NOTE: All components shown are internal to the heat pump unit.
Use the procedure outlined below to initiate proper unit
start-up. NOTE: This equipment is designed for indoor installation only.
Operating Limits
ENVIRONMENT — This equipment is designed for indoor installation ONLY. Extreme variations in temperature, humidi­ty and corrosive water or air will adversely affect the unit per­formance, reliability and service life.
POWER SUPPLY — A voltage variation of ± 10% of name­plate utilization voltage is acceptable.
UNIT STARTING CONDITIONS — Units start and operate in an ambient temperature of 45 F with entering-air tempera­ture at 50 F, entering-water temperature at 60 F and with both air and water at the flow rates used.
NOTE: These operating limits are not normal or continuous operating conditions. Assume that such a start-up is for the purpose of bringing the building space up to occupancy tem­perature. See Table 18 for operating limits.
WARNING
When the disconnect switch is closed, high voltage is pres­ent in some areas of the electrical panel. Exercise caution when working with the energized equipment.
1. Restore power to system.
2. Turn thermostat fan position to ON. Blower should start.
3. Balance airflow at registers.
4. Adjust all valves to the full open position and turn on the line power to all heat pump units.
5. Operate unit in the cooling cycle first, then the heating cycle. Refer to Table 18 for unit operating limits. Al­low 15 minutes between cooling and heating tests for pressure to equalize.
NOTE: Two factors determine the operating limits of a unit: entering-air temperature and water temperature. Whenever any of these factors are at a minimum or maximum level, the other two factors must be at a normal level to ensure proper unit operation. See Table 18.
Table 18 — Operating Limits —
50PTH, PTV, PTD Units
Min. Ambient Air 45 40 Rated Ambient Air 80 70 Max. Ambient Air 100 85 Min. Entering Air 50 40 Rated Entering Air db/wb 80/67 70 Max. Entering Air db/wb 110/83 80
Min. Entering Water 30 20 Normal Entering Water 50-110 30-70 Max. Entering Water 120 90
db — Dry Bulb wb — Wet Bulb
NOTE: Value in heating column is dry bulb only. Any wet bulb reading is acceptable.
AIR LIMITS COOLING (F) HEATING (F)
WATER LIMITS
LEGEND
33
Scroll Compressor Rotation — It is important to be
certain compressor is rotating in the proper direction. To determine whether or not compressor is rotating in the proper direction:
1. Connect service gages to suction and discharge pressure fittings.
2. Energize the compressor.
3. The suction pressure should drop and the discharge pressure should rise, as is normal on any start-up.
If the suction pressure does not drop and the discharge
pressure does not rise to normal levels:
1. Turn off power to the unit. Install disconnect tag.
2. Reverse any two of the unit power leads.
3. Reapply power to the unit and verify pressures are correct.
The suction and discharge pressure levels should now move
to their normal start-up levels.
When the compressor is rotating in the wrong direction, the
unit makes more noise and does not provide cooling.
After a few minutes of reverse operation, the scroll com­pressor internal overload protection will open, thus activating the unit lockout. This requires a manual reset. To reset, turn the thermostat on and then off.
NOTE: There is a 5-minute time delay before the compressor will start.
Unit Start-Up Cooling Mode
1. Adjust the unit thermostat to the warmest position. Slowly reduce the thermostat position until the compres­sor activates.
2. Check for cool air delivery at unit grille a few minutes after the unit has begun to operate.
3. Verify that the compressor is on and that the water flow rate is correct by measuring pressure drop through the heat exchanger using P/T plugs. See Table 19. Check the elevation and cleanliness of the condensate lines; any dripping could be a sign of a blocked line. Be sure the condensate trap includes a water seal.
4. Check the temperature of both supply and discharge water. Compare to Tables 20-23. If temperature is within range, proceed. If temperature is outside the range, check the cooling refrigerant pressures in Tables 20-23.
5. Check air temperature drop across the coil when com­pressor is operating. Air temperature drop should be between 15 and 25 F.
Unit Start-Up Heating Mode
NOTE: Operate the unit in heating cycle after checking the cooling cycle. Allow 5 minutes between tests for the pressure or reversing valve to equalize.
1. Turn thermostat to lowest setting and set thermostat switch to HEAT position.
2. Slowly turn the thermostat to a higher temperature until the compressor activates.
3. Check for warm air delivery at the unit grille within a few minutes after the unit has begun to operate.
4. Check the temperature of both supply and discharge water. Compare to Tables 20-23. If temperature is within range, proceed. If temperature is outside the range, check the heating refrigerant pressures in Tables 20-23.
5. Once the unit has begun to run, check for warm air deliv­ery at the unit grille.
6. Check air temperature rise across the coil when compres­sor is operating. Air temperature rise should be between 20 and 30 F after 15 minutes at load.
7. Check for vibration, noise and water leaks.
Table 19 — Water Temperature Change
WATER FLOW RATE (GPM)
For Closed Loop: Ground Source or Cooling/Boiler Systems at 3 gpm/ton
For Open Loop: Ground Water Systems at
1.5 gpm/ton
Through Heat Exchanger
COOLING
RISE (F)
Min Max Min Max
91248
20 26 10 17
HEATING DROP (F)
Table 20 — Typical 50PTH,PTV,PTD026 Unit Operating Pressures and Temperatures
ENTERING
WATER
TEMP (F)
(EWT)
30
50
70
90
110
DB Dry Bulb HWG — Hot Water Generator ——No heating operation in this temperature range
WATER
FLOW
(Gpm/Ton)
1.5 118-128 159-179 25-30 9-14 16.7-18.7 19-25 73- 83 273-293 6-11 3- 8 5.9- 7.9 16-22
2.25 118-128 146-166 25-30 7-12 12.3-14.3 20-26 75- 85 275-295 6-11 3- 8 4.2- 6.2 17-23 3 118-128 132-152 25-30 7-12 7.9- 9.9 20-26 78- 88 277-297 6-11 3- 8 2.7- 4.7 18-24
1.5 128-138 186-206 18-23 8-13 16.3-18.3 19-25 102-112 302-322 8-12 6-11 8.9-10.9 22-28
2.25 128-138 172-192 18-23 6-11 12.1-14.1 20-26 106-116 303-323 8-12 6-11 6.7- 8.7 23-29 3 128-138 158-178 18-23 6-11 7.8- 9.8 20-26 110-120 305-325 8-12 6-11 4.5- 6.5 23-29
1.5 136-146 281-301 7-12 7-12 15.7-17.7 19-25 128-138 330-350 10-15 8-13 11.3-13.3 27-34
2.25 136-146 267-287 7-12 5-10 11.6-13.6 19-25 134-144 332-352 10-15 8-13 8.5-10.5 28-35 3 136-146 253-273 7-12 4- 9 7.6- 9.6 19-25 141-151 334-354 10-15 8-13 5.8- 7.8 28-35
1.5 139-149 368-388 6-11 7-12 14.9-16.9 18-24 162-172 367-387 14-19 10-15 14.4-16.4 33-41
2.25 139-149 354-374 6-11 5-10 11.0-13.0 18-24 166-176 372-392 15-20 10-15 10.8-12.8 34-42 3 139-149 340-360 6-11 5-10 7.2- 9.2 18-24 171-181 377-397 17-22 10-15 7.1- 9.1 34-42
1.5 143-153 465-485 6-11 7-12 13.9-15.9 17-23
2.25 143-153 450-470 6-11 5-10 10.2-12.2 17-23 — 3 143-153 433-453 6-11 5-10 6.5- 8.5 17-23
FULL LOAD COOLING WITHOUT HWG ACTIVE FULL LOAD HEATING WITHOUT HWG ACTIVE
Suction
Pressure
LEGEND
(psig)
Discharge
Pressure
(psig)
Super-
heat
(F)
Sub-
cooling
(F)
Water
Tem p
Rise
(F)
Air
Tem p
Drop (F)
DB
Suction
Pressure
(psig)
Discharge
Pressure
(psig)
Super-
heat
(F)
Sub-
cooling
(F)
Wate r Tem p
Drop
(F)
Air
Tem p
Rise (F)
DB
34
Table 21 — Typical 50PTH,PTV,PTD038 Unit Operating Pressures and Temperatures
ENTERING
WATER
TEMP (F)
(EWT)
30
50
70
90
110
DB Dry Bulb HWG — Hot Water Generator ——No heating operation in this temperature range
WATER
FLOW
(Gpm/Ton)
1.5 120-130 156-176 25-30 9-14 22.1-24.1 18-24 69- 79 293-313 7-12 14-19 8.9-10.9 17-23
2.25 119-129 148-168 25-30 8-13 16.8-18.8 19-25 73- 83 297-317 7-12 14-19 6.7- 8.7 18-24 3 119-129 138-158 25-30 8-13 10.5-12.5 19-25 76- 86 300-320 7-12 14-19 4.5- 6.5 19-25
1.5 129-139 225-245 15-20 10-15 21.9-23.9 18-24 96-106 322-342 10-15 17-22 12.2-14.2 23-29
2.25 128-138 211-231 15-20 9-14 16.1-18.1 19-25 100-110 326-346 10-15 17-22 9.3-11.3 24-30 3 128-138 197-217 15-20 9-14 10.3-12.3 19-25 105-115 331-351 10-15 17-22 6.4- 8.4 24-30
1.5 136-146 302-322 9-14 13-18 21.5-23.5 18-24 123-133 352-372 11-16 19-24 15-17 28-35
2.25 135-145 283-303 9-14 12-17 15.8-17.8 19-25 129-139 358-378 11-16 19-24 11.6-13.6 29-36 3 135-145 265-285 9-14 12-17 10.0-12.0 19-25 135-145 364-384 11-16 19-24 8.2-10.2 30-37
1.5 140-150 390-410 7-12 13-18 20.5-22.5 17-23 157-167 390-410 13-18 18-23 21-23 36-44
2.25 140-150 369-389 8-13 8-13 14.9-16.9 17-23 169-179 399-419 13-18 16.5-21.5 15.5-17.5 37-45 3 140-150 349-369 8-13 8-13 9.3-11.3 17-23 181-191 408-428 14-19 15-20 10.5-12.5 39-47
1.5 145-155 488-508 7-12 13-18 19.0-21.0 17-23
2.25 145-155 467-487 8-13 8-13 14.0-16.0 17-23 — 3 145-155 447-467 8-13 8-13 9.0-11.0 17-23
FULL LOAD COOLING WITHOUT HWG ACTIVE FULL LOAD HEATING WITHOUT HWG ACTIVE
Suction
Pressure
(psig)
Discharge
Pressure
(psig)
Super-
heat
(F)
LEGEND
Table 22 — Typical 50PTH,PTV,PTD049 Unit Operating Pressures and Temperatures
ENTERING
WATER
TEMP (F)
(EWT)
30
50
70
90
110
DB Dry Bulb HWG — Hot Water Generator ——No heating operation in this temperature range
WATER
FLOW
(Gpm/Ton)
1.5 112-122 187-207 22-27 14-19 20.7-22.7 18-24 66- 76 286-306 7-12 8-13 8-10 18-24
2.25 111-121 167-187 22-27 12-17 15.5-17.5 18-24 69- 79 289-309 7-12 9-14 6- 8 19-25 3 111-121 147-167 23-28 11-16 10.2-12.2 18-24 72- 82 292-312 7-12 9-14 4- 6 19-25
1.5 125-135 242-262 13-18 10-15 20.9-22.9 19-25 93-103 314-334 8-13 10-15 11.5-13.5 23-29
2.25 123-133 224-244 13-18 9-14 15.6-17.6 19-25 98-108 320-340 8-13 10-15 8.7-10.7 24-30 3 122-132 205-225 14-19 7-12 10.2-12.2 19-25 103-113 326-346 8-13 10-15 5.9- 7.9 25-31
1.5 133-143 310-330 8-13 8-13 20.5-22.5 19-25 123-133 344-364 9-14 9-14 15-17 28-35
2.25 132-142 290-310 8-13 7-12 15.2-17.2 19-25 130-140 354-374 9-14 9-14 11.5-13.5 29-36 3 131-141 270-290 9-14 5-10 9.9-11.9 19-25 137-147 361-381 9-14 9-14 7.9- 9.9 30-37
1.5 138-148 396-416 7-12 7-12 19.2-21.2 18-24 165-175 390-410 13-18 8-13 19.6-21.6 37-45
2.25 137-147 374-394 7-12 6-11 14.3-16.3 18-24 175-185 401-421 15-20 8-13 15-17 38-46 3 136-146 352-372 7-12 4- 9 9.3-11.3 18-24 185-195 413-433 17-22 8-13 10.3-12.3 39-47
1.5 144-154 497-517 7-12 5-10 18.0-20.0 17-23
2.25 143-153 472-492 7-12 4- 9 13.3-15.3 17-23 — 3 142-152 447-467 7-12 3- 8 8.5-10.5 17-23
FULL LOAD COOLING WITHOUT HWG ACTIVE FULL LOAD HEATING WITHOUT HWG ACTIVE
Suction
Pressure
(psig)
Discharge
Pressure
(psig)
Super-
heat
(F)
LEGEND
Sub-
cooling
(F)
Sub-
cooling
(F)
Water
Tem p
Rise
(F)
Water
Tem p
Rise
(F)
Air
Tem p
Drop (F)
DB
Air
Tem p
Drop (F)
DB
Suction
Pressure
(psig)
Suction
Pressure
(psig)
Discharge
Pressure
(psig)
Discharge
Pressure
(psig)
Super-
heat
(F)
Super-
heat
(F)
Sub-
cooling
(F)
Sub-
cooling
(F)
Wate r
Tem p Drop
(F)
Wate r
Tem p Drop
(F)
Air
Tem p
Rise (F)
DB
Air
Tem p
Rise (F)
DB
Table 23 — Typical 50PTH,PTV,PTD064,072 Unit Operating Pressures and Temperatures
ENTERING
WATER
TEMP (F)
(EWT)
30
50
70
90
110
DB Dry Bulb HWG — Hot Water Generator ——No heating operation in this temperature range
WATER
FLOW
(Gpm/Ton)
1.5 117-127 170-190 27-32 15-20 18.2-20.2 17-23 66- 76 282-302 10-16 9-14 8-10 19-25
2.25 116-126 143-163 28-33 13-18 12.6-14.6 17-23 69- 79 285-305 10-16 9-14 6- 8 19-25 3 115-125 135-155 29-34 12-17 7.0- 9.0 17-23 72- 82 289-309 10-16 10-15 4- 6 20-26
1.5 128-138 238-258 16-21 14-19 20.5-22.5 21-27 90-100 310-330 11-17 12-17 11.3-13.3 24-30
2.25 126-136 222-242 21-26 13-18 14.9-16.9 21-27 95-105 313-333 11-17 12-17 8.5-10.5 25-31 3 125-135 205-225 26-31 12-17 9.2-11.2 21-27 99-109 316-336 11-17 12-17 5.7- 7.7 26-32
1.5 135-145 315-335 10-15 14-19 21.0-23.0 22-28 115-125 337-357 12-18 14-19 14-16 28-35
2.25 134-144 296-316 12-17 13-18 15.5-17.5 22-28 120-130 341-361 12-18 14-19 10.6-12.6 29-36 3 133-143 276-296 15-20 11-16 10.0-12.0 22-28 126-136 345-365 12-18 15-20 7.3- 9.3 30-37
1.5 139-149 408-428 10-15 15-20 20.1-22.1 21-27 157-167 390-410 15-20 14-19 18.2-20.2 37-45
2.25 138-148 386-406 10-15 13-18 14.8-16.8 21-27 161-171 394-414 15-20 14-19 13.9-15.9 38-46 3 138-148 364-384 10-15 11-16 9.5-11.5 21-27 166-176 398-418 15-20 15-20 9.6-11.6 39-47
1.5 144-154 515-535 8-13 14-19 19.0-21.0 20-26
2.25 143-153 493-513 8-13 13-18 14.0-16.0 20-26 — 3 142-152 469-489 8-13 12-17 9.0-11.0 20-26
FULL LOAD COOLING WITHOUT HWG ACTIVE FULL LOAD HEATING WITHOUT HWG ACTIVE
Suction
Pressure
(psig)
Discharge
Pressure
(psig)
Super-
heat
(F)
LEGEND
Sub-
cooling
(F)
Water
Tem p
Rise
(F)
35
Air
Tem p
Drop (F)
DB
Suction
Pressure
(psig)
Discharge
Pressure
(psig)
Super-
heat
(F)
Sub-
cooling
(F)
Wate r
Tem p Drop
(F)
Air
Tem p
Rise (F)
DB
Unit Start-Up with WSHP Open Controls —
Fig. 34 — BACview6 Display Interface
a50-8444
*Sponsored by ASHRAE (American Society of Heating, Refrigerat­ing and Air Conditioning Engineers).
The WSHP Open is a multi-protocol (default BACnet*) con­troller with extensive features, flexible options and powerful capabilities. The unit comes from the factory pre-programmed and needs minimal set up to function in a BAS (Building Automation System) system or provide additional capabilities to Carrier's WSHP product line. Most settings on the controller have factory defaults set for ease of installation. There are a few settings that must be configured in the field and several settings that can be adjusted if required by unique job condi­tions. Refer to Appendix A — WSHP Open Screen Configura­tion. In order to configure the unit, a BACview required. See Fig. 34.
NOTE: If the WSHP Open control has lost its programming, all display pixels will be displayed on the SPT sensor. See the WSHP Third Party Integration Guide.
When the unit is OFF, the SPT sensor will indicate OFF. When power is applied, the SPT sensor will indicate tempera­ture in the space at 78 F.
To start-up a unit with WSHP Open controls:
1. To plug in the BACview
6
handheld display into a SPT sensor, point the two ears on the connector up and tilt the bottom of the plug toward you. Insert the plug up into the SPT sensor while pushing the bottom of the plug away from you.
2. BACview
6
should respond with "Establishing Connec­tion." The Home screen will then appear on the display showing operating mode and space temperature. Press any button to continue.
See Appendix A — WSHP Open Screen Configuration for the hierarchal structure of the WSHP Open controller. All functions of the controller can be set from the Home screen.
3. When the Login is requested, type 1111 and push the OK softkey. The Logout will then be displayed to indicate the password was accepted.
4. To set the Clock if it is not already displayed:
a. Select System Settings from the Home screen, then
press Clockset.
b. Scroll to hour, minute and second using the arrow
keys. Use the number keypad to set actual time.
c. Scroll to day, month and year using arrow keys.
Use number keypad to set date.
5. To set Daylight Savings Time (DST):
a. Push the DST softkey. The display will indicate
02:00:060 which is equal to 2:00AM.
6
display is
b. To program the beginning and end dates, scroll
down to the beginning month and press the enter key. The softkeys (INCR and DECR) will activate to increment the month in either direction, Jan, Feb, March, etc.
c. Use number keys to select the day of month and
year.
d. Push the OK softkey to finalize the data.
6. To view configuration settings: a. Select the Config softkey. b. Select the Service Config softkey. Scroll through
the factory settings by using the up and down arrow keys. See below for factory settings.
Only the following settings will need to be checked.
• # of Fan Speeds — This should be set to "1" for units with PSC motors and set to "3" for units with ECM motors.
• Compressor Stages — This should be set to "1."
• Factory Dehumidification Reheat Coil — This should be set to "none" unless the modulating hot water reheat option is supplied in the unit, then set to "installed."
• The condenser water limit needs to be verified depending on design parameters and application, whether geothermal or boiler/tower.
7. To view unit configuration settings: a. Select the Unit Configuration softkey, then select
Unit.
b. Scroll through the unit settings by using the up and
down arrow keys. Unit settings include:
• Fan Mode: Default Continuous
• Fan Delay:
• Minimum SAT Cooling: Default 50 F
• Maximum SAT Heating: Default 110 F
• Filter Service Alarm: Must be set from 0 to 9999 hr
8. To set local schedules: a. Select the Schedule softkey from the Configuration
screen, then press enter.
b. Select Weekly, then press enter (7 schedules
available). c. Select day and press enter. d. Press enter again and select ADD or DEL (DECR
or INCR) set schedule. e. Enter ON/OFF time, then press continue.
36
f. Press OK to apply and save to a particular day of
the week.
g. Continue to add the same or different schedule spe-
cific days of the week. To add exceptions to the schedule: i. Press Add softkey. ii. Select exception type from following:
• Date
• Date Range
• Week-N-Day
• Calender Reference
9. Go back to Home Screen.
10. Remove BACview
6
cable from SPT sensor by reversing
the process in Step 1.
11. Perform system test.
Flow Regulation — Flow regulation can be accom-
plished by two methods. Most water control valves have a flow adjustment built into the valve. By measuring the pressure drop through the unit heat exchanger, the flow rate can be deter­mined. See Table 24. Adjust the water control valve until the flow of 1.5 to 2 gpm is achieved. Since the pressure constantly varies, two pressure gages may be needed in some applications.
Table 24 — Coaxial Water Pressure Drop
UNIT 50PTH, PTV,
PTD
026
038
049
064,072
GPM
4.0 1.5 1.3 1.1 1.0
6.0 3.1 2.6 2.3 2.1
7.0 4.1 3.4 3.0 2.7
8.0 5.1 4.3 3.8 3.4
4.0 1.2 1.0 0.8 0.6
6.0 2.6 2.5 2.3 2.1
8.0 4.5 4.2 4.0 3.7
9.0 5.7 5.2 4.8 4.4
5.5 1.1 0.9 0.8 0.7
8.3 2.2 2.1 2.0 1.8
11.0 3.9 3.6 3.2 3.1
12.0 4.5 4.2 3.8 3.5
7.0 0.5 0.3 0.2 0.1
10.5 1.9 1.8 1.7 1.6
14.0 3.9 3.5 3.2 2.9
15.0 4.8 4.3 3.9 3.5
WATER TEMPERATURE (F)
30 F 50 F 70 F 90 F
Pressure Drop (psi)
An alternative method is to install a flow control device. These devices are typically an orifice of plastic material de­signed to allow a specified flow rate that are mounted on the outlet of the water control valve. Occasionally these valves produce a velocity noise that can be reduced by applying some back pressure. To accomplish this, slightly close the leaving isolation valve of the well water setup.
WARNING
the water level in the flush cart tank to drop below the pump inlet line in order to prevent air from filling the line.
3. Maintain a fluid level in the tank above the return tee in order to avoid air entering back into the fluid.
4. Shutting off the return valve that connects into the flush cart reservoir will allow 50 psig surges to help purge air pockets. This maintains the pump at 50 psig.
5. To purge, keep the pump at 50 psig until maximum pumping pressure is reached.
6. Open the return valve to send a pressure surge through the loop to purge any air pockets in the piping system.
7. A noticeable drop in fluid level will be seen in the flush cart tank. This is the only indication of air in the loop.
NOTE: If air is purged from the system while using a 10 in. PVC flush tank, the level drop will only be 1 to 2 in. since liquids are incompressible. If the level drops more than this, flushing should continue since air is still being compressed in the loop. If level is less than 1 to 2 in., reverse the flow.
8. Repeat this procedure until all air is purged.
9. Restore power.
Antifreeze may be added before, during, or after the flush­ing process. However, depending on when it is added in the process, it can be wasted. Refer to the Antifreeze section for more detail.
Loop static pressure will fluctuate with the seasons. Pres­sures will be higher in the winter months than during the warm­er months. This fluctuation is normal and should be considered when charging the system initially. Run the unit in either heating or cooling for several minutes to condition the loop to a homogenous temperature.
When complete, perform a final flush and pressurize the loop to a static pressure of 40 to 50 psig for winter months or 15 to 20 psig for summer months.
After pressurization, be sure to remove the plug from the end of the loop pump motor(s) to allow trapped air to be discharged and to ensure the motor housing has been flooded. Be sure the loop flow center provides adequate flow through the unit by checking pressure drop across the heat exchanger. Compare the results to the data in Table 24.
Antifreeze — In areas where entering loop temperatures
drop below 40 F or where piping will be routed through areas subject to freezing, antifreeze is needed.
Alcohols and glycols are commonly used as antifreeze agents. Freeze protection should be maintained to 15 F below the lowest expected entering loop temperature. For example, if the lowest expected entering loop temperature is 30 F, the leaving loop temperature would be 22 to 25 F. Therefore, the freeze protection should be at 15 F (30 F – 15 F = 15 F).
IMPORTANT: All alcohols should be pre-mixed and pumped from a reservoir outside of the building or introduced under water level to prevent fuming.
To avoid possible injury or death due to electrical shock, open the power supply disconnect switch and secure it in an open position before flushing system.
Flushing — Once the piping is complete, units require final
purging and loop charging. A flush cart pump of at least 1.5 hp is needed to achieve adequate flow velocity in the loop to purge air and dirt particles from the loop. Flush the loop in both direc­tions with a high volume of water at a high velocity. Follow the steps below to properly flush the loop:
1. Verify power is off.
2. Fill loop with water from hose through flush cart before using flush cart pump to ensure an even fill. Do not allow
Calculate the total volume of fluid in the piping system. See Table 25. Use the percentage by volume in Table 26 to deter­mine the amount of antifreeze to use. Antifreeze concentration should be checked from a well-mixed sample using a hydrom­eter to measure specific gravity.
FREEZE PROTECTION SELECTION — The 30 F FP1 factory setting (water) should be used to avoid freeze damage to the unit.
Once antifreeze is selected, the JW3 jumper (FP1) should be clipped on the control to select the low temperature (anti­freeze 13 F) set point to avoid nuisance faults.
37
Table 25 — Approximate Fluid Volume (gal.)
per 100 Ft of Pipe
PIPE DIAMETER (in.) VOLUME (gal.)
Copper 14.1
Rubber Hose 13.9 Polyethylene
LEGEND
IPS Internal Pipe Size SCH — Schedule SDR — Standard Dimensional Ratio
NOTE: Volume of heat exchanger is approximately 1.0 gallon.
1.25 6.4
1.5 9.2
3
/4 IPS SDR11 2.8 1 IPS SDR11 4.5 11/4 IPS SDR11 8.0
1
/2 IPS SDR11 10.9 2 IPS SDR11 18.0 11/4 IPS SCH40 8.3 11/2 IPS SCH40 10.9 2 IPS SCH40 17.0
Table 26 — Antifreeze Percentages by Volume
MINIMUM TEMPERATURE FOR
ANTIFREEZE
Methanol (%) 25 21 16 10 100% USP Food Grade
Propylene Glycol (%) Ethenol 29 25 20 14
FREEZE PROTECTION (F)
10 15 20 25
38 30 22 15
Cooling Tower/Boiler Systems — These systems
typically use a common loop temperature maintained at 60 to 95 F. Carrier recommends using a closed circuit evaporative cooling tower with a secondary heat exchanger between the tower and the water loop. If an open type cooling tower is used continuously, chemical treatment and filtering will be necessary.
Ground Coupled, Closed Loop and Plateframe Heat Exchanger Well Systems — These systems al-
low water temperatures from 30 to 110 F. The external loop field is divided up into 2 in. polyethylene supply and return lines. Each line has valves connected in such a way that upon system start-up, each line can be isolated for flushing using only the system pumps. Locate air separation in the piping sys­tem prior to the fluid re-entering the loop field.
OPERATION
Power Up Mode —
inputs, terminals and safety controls are checked for normal operation.
NOTE: The compressor will have a 5-minute anti-short cycle upon power up.
The unit will not operate until all the
Units with Aquazone™ Complete C Control
STANDBY — Y and W terminals are not active in Standby mode, however the O and G terminals may be active, depend­ing on the application. The compressor will be off.
COOLING — Y and O terminals are active in Cooling mode. After power up, the first call to the compressor will initiate a 5 to 80 second random start delay and a 5-minute anti-short cycle protection time delay. After both delays are complete, the compressor is energized.
NOTE: On all subsequent compressor calls the random start delay is omitted.
HEATING STAGE 1 — Terminal Y is active in heating stage 1. After power up, the first call to the compressor will initiate a 5 to 80 second random start delay and a 5-minute anti-short cycle protection time delay. After both delays are complete, the compressor is energized.
NOTE: On all subsequent compressor calls the random start delay is omitted.
HEATING STAGE 2 — To enter Stage 2 mode, terminal W is active (Y is already active). Also, the G terminal must be active or the W terminal is disregarded. The compressor relay will remain on and EH1 is immediately turned on. EH2 will turn on after 10 minutes of continual stage 2 demand.
NOTE: EH2 will not turn on (or if on, will turn off) if FP1 tem­perature is greater than 45 F and FP2 is greater than 110 F.
LOCKOUT MODE — The status LED will flash fast in Lockout mode and the compressor relay will be turned off immediately. Lockout mode can be “soft” reset via the Y input or can be “hard” reset via the disconnect. The last fault causing the lockout is stored in memory and can be viewed by entering test mode.
LOCKOUT WITH EMERGENCY HEAT — While in Lock­out mode, if W becomes active, then Emergency Heat mode will occur.
EMERGENCY HEAT — In Emergency Heat mode, terminal W is active while terminal Y is not. Terminal G must be active or the W terminal is disregarded. EH1 is immediately turned on. EH2 will turn on after 5 minutes of continual emergency heat demand.
Units with Aquazone Deluxe D Control
EXTENDED COMPRESSOR OPERATION MONITOR — If the compressor has been on for 4 continuous hours the con­trol will automatically turn off the compressor relay and wait the short cycle time protection time. All appropriate safeties, including the low-pressure switch, will be monitored. If all operations are normal and the compressor demand is still pres­ent, the control will turn the compressor back on.
STANDBY/FAN ONLY — The compressor will be off. The Fan Enable, Fan Speed, and reversing valve (RV) relays will be on if inputs are present. If there is a Fan 1 demand, the Fan Enable will immediately turn on. If there is a Fan 2 demand, the Fan Enable and Fan Speed will immediately turn on.
NOTE: DIP switch 5 on S1 does not have an effect upon Fan 1 and Fan 2 outputs.
HEATING STAGE 1 — In Heating Stage 1 mode, the Fan Enable and Compressor relays are turned on immediately. Once the demand is removed, the relays are turned off and the control reverts to Standby mode. If there is a master/slave or dual compressor application, all compressor relays and related functions will operate per their associated DIP switch 2 setting on S1.
HEATING STAGE 2 — In Heating Stage 2 mode, the Fan Enable and Compressor relays are remain on. The Fan Speed relay is turned on immediately and turned off immediately once the demand is removed. The control reverts to Heating Stage 1 mode. If there is a master/slave or dual compressor application, all compressor relays and related functions will operate per their associated DIP switch 2 setting on S1.
HEATING STAGE 3 — In Heating Stage 3 mode, the Fan Enable, Fan Speed and Compressor relays remain on. The EH1 output is turned on immediately. With continuing Heat Stage 3 demand, EH2 will turn on after 10 minutes. EH1 and EH2 are turned off immediately when the Heating Stage 3 demand is re­moved. The control reverts to Heating Stage 2 mode.
The output signal EH2 will be off if FP1 is greater than 45 F AND FP2 (when shorted) is greater than 110 F during Heating Stage 3 mode. This condition will have a 30-second recogni­tion time. Also, during Heating Stage 3 mode, EH1, EH2, Fan Enable, and Fan Speed will be ON if G input is not active.
EMERGENCY HEAT — In Emergency Heat mode, the Fan Enable and Fan Speed relays are turned on. The EH1 output is turned on immediately. With continuing Emergency Heat de­mand, EH2 will turn on after 5 minutes. Fan Enable and Fan Speed relays are turned off after a 60-second delay. The control reverts to Standby mode.
38
Output EH1, EH2, Fan Enable, and Fan Speed will be ON if
the G input is not active during Emergency Heat mode. COOLING STAGE 1 — In Cooling Stage 1 mode, the Fan
Enable, compressor and RV relays are turned on immediately. If configured as stage 2 (DIP switch set to OFF) then the com­pressor and fan will not turn on until there is a stage 2 demand. The Fan Enable and compressor relays are turned off immedi­ately when the Cooling Stage 1 demand is removed. The con­trol reverts to Standby mode. The RV relay remains on until there is a heating demand. If there is a master/slave or dual compressor application, all compressor relays and related func­tions will track with their associated DIP switch 2 on S1.
COOLING STAGE 2 — In Cooling Stage 2 mode, the Fan Enable, compressor and RV relays remain on. The Fan Speed relay is turned on immediately and turned off immediately once the Cooling Stage 2 demand is removed. The control reverts to Cooling Stage 1 mode. If there is a master/slave or dual compressor application, all compressor relays and related functions will track with their associated DIP switch 2 on S1.
NIGHT LOW LIMIT (NLL) STAGED HEATING — In NLL staged Heating mode, the override (OVR) input becomes ac­tive and is recognized as a call for heating and the control will immediately go into a Heating Stage 1 mode. With an addition­al 30 minutes of NLL demand, the control will go into Heating Stage 2 mode. With another additional 30 minutes of NLL demand, the control will go into Heating Stage 3 mode.
Units with WSHP Open Multiple Protocol —
The WSHP Open multi-protocol controller will control me­chanical cooling, heating and waterside economizer outputs based on its own space temperature input and set points. An optional CO space can maximize the occupant comfort. The WSHP Open controller has its own hardware clock that is automatically set when the heat pump software is downloaded to the board. Oc­cupancy types are described in the scheduling section below. The following sections describe the functionality of the WSHP Open multi-protocol controller. All point objects referred to in this sequence of operation will be referenced to the objects as viewed in the BACview
SCHEDULING — Scheduling is used to start/stop the unit based on a time period to control the space temperature to spec­ified occupied heating and cooling set points. The controller is defaulted to control by occupied set points all the time, until ei­ther a time schedule is configured with BACview tant, i-Vu able the BAS (Building Automation System) on/off point. The local time and date must be set for these functions to operate properly. The occupancy source can be changed to one of the following:
Occupancy Schedules until a time schedule has been configured using either Field Assistant, i-Vu Open, BACview tem to enable/disable the BAS on/off point. The BAS point can be disabled by going to Config, then Unit, then Occupancy Schedules and changing the point from enable to disable then clicking OK.
NOTE: This point must be enabled in order for the i-Vu Open, Field Assistant, or BACview schedule to the controller.
Schedule_schedule schedule configured and stored in the unit. The schedule is accessible via the BACview Field Assistant control system. The daily schedule consists of a start/stop time (standard or 24-hour mode) and seven days of the week, starting with Monday and ending on Sunday. To enter a daily schedule, navigate to Config, then Sched, then enter BACview schedule_schedule. From here, enter either a Weekly or Excep­tion schedule for the unit.
IAQ (indoor air quality) sensor mounted in the
2
6
handheld user interface.
6
®
Open, or a third party control system to enable/dis-
, Field Assis-
— The controller will be occupied 24/7
6
or a third party control sys-
6
control system to assign a time
— The unit will operate according to the
6
Handheld tool, i-Vu Open, or
6
Admin Password (1111), then go to
Occupancy Input Contact
— The WSHP Open controller has the capability to use an external dry contact closure to deter­mine the occupancy status of the unit. The Occupancy Sched­ules will need to be disabled in order to utilize the occupancy contact input.
NOTE: Scheduling can only be controlled from one source. BAS (Building Automation System) On/Off
— A BAS system that supports network scheduling can control the unit through a network communication and the BAS scheduling function once the Occupancy Schedules have been disabled.
NOTE: Scheduling can either be controlled via the unit or the BAS, but not both.
INDOOR FAN — The indoor fan will operate in any one of three modes depending on the user configuration selected.
Fan mode can be selected as Auto, Continuous, or Always On. In Auto mode, the fan is in intermittent operation during both occupied and unoccupied periods. Continuous fan mode is intermittent during unoccupied periods and continuous dur­ing occupied periods. Always On mode operates the fan con­tinuously during both occupied and unoccupied periods. In the default mode, Continuous, the fan will be turned on whenever any one of the following is true:
• The unit is in occupied mode as determined by its occu-
pancy status.
• There is a demand for cooling or heating in the unoccu-
pied mode.
• There is a call for dehumidification (optional).
When power is reapplied after a power outage, there will be a configured time delay of 5 to 600 seconds before starting the fan. There are also configured fan delays for Fan On and Fan Off. The Fan On delay defines the delay time (0 to 30 seconds; default 10) before the fan begins to operate after heating or cooling is started while the Fan Off delay defines the delay time (0 to 180 seconds; default 45) the fan will continue to op­erate after heating or cooling is stopped. The fan will continue to run as long as the compressors, heating stages, or the dehu­midification relays are on. If the SPT failure alarm or conden­sate overflow alarm is active; the fan will be shut down imme­diately regardless of occupancy state or demand.
Automatic Fan Speed Control
— The WSHP Open controller is capable of controlling up to three fan speeds using the ECM (electronically commutated motor). The motor will operate at the lowest speed possible to provide quiet and efficient fan op­eration with the best latent capability. The motor will increase speed if additional cooling or heating is required to obtain the desired space temperature set point. The control increases the motor's speed as the space temperature rises above the cooling or below the heating set point. The amount of space tempera­ture increase above or below the set point required to increase the fan speed is user configurable in the set point.
The Low Fan speed range is configured by the width of the Yellow (for cooling) and Light Blue (for heating) setpoint bands. The fan will operate at low speed as long as the space temperature remains within the yellow or light blue band range. The Medium Fan speed range is determined by the Or­ange and Dark Blue setpoint band. The fan will operate at me­dium speed when the space temperature enters this range. If the space temperature rises or falls into the red range, the fan will operate at High Fan speed.
As the temperature returns toward setpoint, a configurable hysteresis is used to prevent the fan from changing speeds er­ratically. The default value is 0.5° F (shown above).
Also, the control will increase the fan speed as the Supply Air Temperature approaches the configured Minimum or Max­imum SAT limits.
Fan Speed Control (During Heating)
— Whenever heat is re­quired and active, the control continuously monitors the sup­ply-air temperature to verify it does not rise above the config-
39
ured maximum heating SAT limit (110 F default). As the SAT
approaches this value, the control will increase the fan speed as required to ensure the SAT will remain within the limit. This feature provides the most quiet and efficient operation by oper­ating the fan at the lowest speed possible.
Fan Speed Control (During Cooling) cal cooling is required and active, the control continuously monitors the supply-air temperature to verify it does not fall be­low the configured minimum cooling SAT limit (50 F default). As the SAT approaches this value, the control will increase the fan speed as required to ensure the SAT will remain within the limit. The fan will operate at lowest speed to maximize latent capacity during cooling.
COOLING — The WSHP Open controller will operate one or two stages of compression to maintain the desired cooling set point. The compressor outputs are controlled by the PI (propor­tional-integral) cooling loop and cooling stages capacity algo­rithm. They will be used to calculate the desired number of stages needed to satisfy the space by comparing the space tem­perature (SPT) to the appropriate cooling set point. The water side economizer, if applicable, will be used for first stage cool­ing in addition to the compressor(s). The following conditions must be true in order for the cooling algorithm to run:
• Cooling is set to Enable.
• Heating mode is not active and the compressor time guard has expired.
• Condensate overflow input is normal.
• If occupied, the SPT is greater than the occupied cooling set point.
• Space temperature reading is valid.
• If unoccupied, the SPT is greater than the unoccupied cooling set point.
• If economizer cooling is available and active and the economizer alone is insufficient to provide enough cool­ing.
• OAT (if available) is greater than the cooling lockout temperature.
If all the above conditions are met, the compressors will be
energized as required, otherwise they will be deenergized. If cooling is active and should the SAT approach the minimum SAT limit, the fan will be indexed to the next higher speed. Should this be insufficient and if the SAT falls further (equal to the minimum SAT limit), the fan will be indexed to the maxi­mum speed. If the SAT continues to fall 5 F below the mini­mum SAT limit, all cooling stages will be disabled.
During Cooling mode, the reversing valve output will be
held in the cooling position (either B or O type as configured) even after the compressor is stopped. The valve will not switch position until the Heating mode is required.
The configuration screens contain the minimum SAT
parameter as well as cooling lockout based on outdoor-air temperature (OAT) Both can be adjusted to meet various specifications.
There is a 5-minute off time for the compressor as well as a
5-minute time delay when staging up to allow the SAT to achieve a stable temperature before energizing a second stage of capacity. Likewise, a 45-second delay is used when staging down.
After a compressor is staged off, it may be restarted again
after a normal time-guard period of 5 minutes and if the sup­ply-air temperature has increased above the minimum supply­air temperature limit.
The WSHP Open controller provides a status input to moni-
tor the compressor operation. The status is monitored to deter­mine if the compressor status matches the commanded state. This input is used to determine if a refrigerant safety switch or other safety device has tripped and caused the compressor to stop operating normally. If this should occur, an alarm will be generated to indicate the faulted compressor condition.
— Whenever mechani-
HEATING — The WSHP Open controller will operate one or two stages of compression to maintain the desired heating set point. The compressor outputs are controlled by the heating PI (proportional-integral) loop and heating stages capacity algo­rithm. They will be used to calculate the desired number of stages needed to satisfy the space by comparing the space tem­perature (SPT) to the appropriate heating set point. The follow­ing conditions must be true in order for the heating algorithm to run:
• Heating is set to Enable.
• Cooling mode is not active and the compressor time guard has expired.
• Condensate overflow input is normal.
• If occupied, the SPT is less than the occupied heating set point.
• Space temperature reading is valid.
• If unoccupied, the SPT is less than the unoccupied heat­ing set point.
• OAT (if available) is less than the heating lockout temperature.
If all the above conditions are met, the heating outputs will
be energized as required, otherwise they will be deenergized. If the heating is active and should the SAT approach the maxi­mum SAT limit, the fan will be indexed to the next higher speed. Should this be insufficient, and the SAT rises further reaching the maximum heating SAT limit, the fan will be indexed to the maximum speed. If the SAT still continues to rise 5 F above the maximum limit, all heating stages will be disabled.
During Heating mode, the reversing valve output will be
held in the heating position (either B or O type as configured) even after the compressor is stopped. The valve will not switch position until the Cooling mode is required.
The configuration screens contain the maximum SAT
parameter as well as heating lockout based on outdoor-air temperature (OAT); both can be adjusted to meet various specifications.
There is a 5-minute off time for the compressor as well as a
5-minute time delay when staging up to allow the SAT to achieve a stable temperature before energizing a second stage of capacity. Likewise, a 45-second delay is used when staging down.
After a compressor is staged off, it may be restarted again
after a normal time-guard period of 5 minutes and if the sup­ply-air temperature has fallen below the maximum supply air temperature limit.
The WSHP Open controller provides a status input to moni-
tor the compressor operation. The status is monitored to deter­mine if the compressor status matches the commanded state. This input is used to determine if a refrigerant safety switch or other safety device has tripped and caused the compressor to stop operating normally. If this should occur, an alarm will be generated to indicate the faulted compressor condition. Also, if auxiliary heat is available (see below), the auxiliary heat will operate to replace the reverse cycle heating and maintain the space temperature as required.
AUXILIARY HEAT — The WSHP Open controller can con­trol a two-position, modulating water, or steam valve connect­ed to a coil on the discharge side of the unit and supplied by a boiler or a single-stage ducted electric heater in order to main­tain the desired heating set point. Should the compressor capac­ity be insufficient or a compressor failure occurs, the auxiliary heat will be used. Unless the compressor fails, the auxiliary heat will only operate to supplement the heat provided by the compressor if the space temperature falls more than one degree below the desired heating set point (the amount is configu­rable). The heat will be controlled so the SAT will not exceed the maximum heating SAT limit.
40
Auxiliary Modulating Hot Water/Steam Heating Reheat
— The control can modulate a hot water or steam valve con­nected to a coil on the discharge side of the unit and supplied by a boiler in order to maintain the desired heating set point should the compressor capacity be insufficient or a compressor failure occurs. Unless a compressor fault condition exists, the valve will only operate to supplement the heat provided by the compressor if the space temperature falls more than one degree below the desired heating set point. The valve will be con­trolled so the SAT will not exceed the maximum heating SAT limit.
Two-Position Hot Water/Steam Heating Reheat
The con-
trol can operate a two-position, NO or NC, hot water or steam valve connected to a coil on the discharge side of the unit and supplied by a boiler in order to maintain the desired heating set point should the compressor capacity be insufficient or a com­pressor failure occurs. Unless a compressor fault condition ex­ists, the valve will only open to supplement the heat provided by the compressor if the space temperature falls more than one degree below the desired heating set point. The valve will be controlled so the SAT will not exceed the maximum heating SAT limit. The heat stage will also be subject to a 2-minute minimum OFF time to prevent excessive valve cycling.
Single Stage Electric Auxiliary Heat
— The control can op­erate a field-installed single stage of electric heat installed on the discharge side of the unit in order to maintain the desired heating set point should the compressor capacity be insufficient or a compressor failure occurs. Unless a compressor fault con­dition exists, the heat stage will only operate to supplement the heat provided by the compressor if the space temperature falls more than one degree below the desired heating set point. The heat stage will be controlled so the SAT will not exceed the maximum heating SAT limit. The heat stage will also be sub­ject to a 2-minute minimum OFF time to prevent excessive cycling.
INDOOR AIR QUALITY (IAQ) AND DEMAND CON­TROLLED VENTILATION (DCV) — If the optional in­door air quality sensor is installed, the WSHP Open controller can maintain indoor air quality via a modulating OA damper providing demand controlled ventilation. The control operates the modulating OA damper during occupied periods. The con­trol monitors the CO set points, adjusting the ventilation rate as required. The control
level and compares it to the configured
2
provides proportional ventilation to meet the requirements of ASHRAE (American Society of Heating, Refrigerating and Air Conditioning Engineers) specifications by providing a base ventilation rate and then increasing the rate as the CO
level in-
2
creases. The control will begin to proportionally increase venti­lation when the CO point and will reach the full ventilation rate when the CO
level rises above the start ventilation set
2
level
2
is at or above the maximum set point. A user-configurable min­imum damper position ensures that proper base ventilation is delivered when occupants are not present. The IAQ configura­tions can be accessed through the configuration screen. The following conditions must be true in order for this algorithm to run:
• Damper control is configured for DCV.
• The unit is in an occupied mode.
• The IAQ sensor reading is greater than the DCV start
control set point.
The control has four user adjustable set points: DCV start control set point, DCV maximum control set point, minimum damper position, and DCV maximum damper position.
Two-Position OA Damper
— The control can be configured to operate a ventilation damper in a two-position ventilation mode to provide the minimum ventilation requirements during occupied periods.
DEHUMIDIFCATION — The WSHP Open controller will provide occupied and unoccupied dehumidification only on
units that are equipped with the modulating hot water reheat (HWR) option. This function requires an accessory space rela­tive humidity sensor. When using a relative humidity sensor to control dehumidification during occupied or unoccupied times, the dehumidification set points are used accordingly. When the indoor relative humidity becomes greater than the dehumidifi­cation set point, a dehumidification demand will be acknowl­edged. Once acknowledged, the dehumidification output will be energized, bringing on the supply fan (medium speed), me­chanical cooling, and the integral hot water reheat coil. The controls will engage Cooling mode and waste heat from the compressor cooling cycle will be returned to the reheat coil si­multaneously, meaning that the reversing valve is causing the compressor to operate in the Cooling mode. During Cooling mode, the unit cools, dehumidifies, and disables the HWR coil; however, once the call for cooling has been satisfied and there is still a call for dehumidification, the unit will continue to op­erate using the reheat mode and HWR coil.
WATERSIDE ECONOMIZER — The WSHP Open control­ler has the capability of providing modulating or two-position water economizer operation (for a field-installed economizer coil mounted to the entering air side of the unit and connected to the condenser water loop) in order to provide free cooling (or preheating) when water conditions are optimal. Water econ­omizer settings can be accessed through the equipment status screen. The following conditions must be true for economizer operation:
• SAT reading is available.
• LWT reading is available.
• If occupied, the SPT is greater than the occupied cooling set point or less than the occupied heating set point and the condenser water is suitable.
• Space temperature reading is valid.
• If unoccupied, the SPT is greater than the unoccupied cooling set point or less than the unoccupied heating set point and the condenser water is suitable.
Modulating Water Economizer Control
— The control has the capability to modulate a water valve to control condenser water flowing through a coil on the entering air side of the unit.
Cooling — The purpose is to provide an economizer cooling function by using the water loop when the entering water loop temperature is suitable (at least 5 F below space temperature). If the water loop conditions are suitable, then the valve will modulate open as required to maintain a supply-air temperature that meets the load conditions. Should the economizer coil ca­pacity alone be insufficient for a period greater than 5 minutes, or should a high humidity condition occur, then the compressor will also be started to satisfy the load. Should the SAT ap­proach the minimum cooling SAT limit, the economizer valve will modulate closed during compressor operation.
Heating — Additionally, the control will modulate the water valve should the entering water loop temperature be suitable for heating (at least 5 F above space temperature) and heat is required. The valve will be controlled in a similar manner ex­cept to satisfy the heating requirement. Should the economizer coil capacity alone be insufficient to satisfy the space load con­ditions for more than 5 minutes, then the compressor will be started to satisfy the load. Should the SAT approach the maxi­mum heating SAT limit, the economizer valve will modulate closed during compressor operation.
Two-Position Water Economizer Control
— The control has the capability to control a NO or NC, two-position water valve to control condenser water flow through a coil on the entering air side of the unit.
Cooling — The purpose is to provide a cooling economizer function directly from the condenser water loop when the en­tering water loop temperature is suitable (at least 5 F below space temperature). If the optional coil is provided and the wa­ter loop conditions are suitable, then the valve will open to pro-
41
vide cooling to the space when required. Should the capacity
be insufficient for a period greater than 5 minutes, or should a high humidity condition occur, then the compressor will be started to satisfy the load. Should the SAT reach the minimum cooling SAT limit, the economizer valve will close during compressor operation.
Heating — Additionally, the economizer control will open the water valve should the entering water loop temperature be suit­able for heating (at least 5 F above space temperature) and heat is required. The valve will be controlled in a similar man­ner except to satisfy the heating requirement. Should the coil capacity be insufficient to satisfy the space load for more than 5 minutes, then the compressor will be started to satisfy the load. Should the SAT reach the maximum heating SAT limit, the economizer valve will close during compressor operation.
DEMAND LIMIT — The WSHP Open controller has the ability to accept three levels of demand limit from the network. In response to a demand limit, the unit will decrease its heating set point and increase its cooling set point to widen the range in order to immediately lower the electrical demand. The amount of temperature adjustment in response is user adjustable for both heating and cooling and for each demand level. The re­sponse to a particular demand level may also be set to zero.
CONDENSER WATER LINKAGE — The control pro­vides optimized water loop operation using an universal con­troller (UC) open loop controller. Loop pump operation is auto­matically controlled by WSHP equipment occupancy sched­ules, unoccupied demand and tenant override conditions. Positive pump status feedback prevents nuisance fault trips. The condenser water linkage operates when a request for con­denser water pump operation is sent from each WSHP to the loop controller. This request is generated whenever any WSHP is scheduled to be occupied, is starting during optimal start (for warm-up or pull down prior to occupancy), there is an unoccu­pied heating or cooling demand, or a tenant pushbutton over­ride. At each WSHP, the water loop temperature and the loop pump status is given. The WSHP will NOT start a compressor until the loop pumps are running or will shutdown the com­pressors should the pumps stop. This prevents the WSHP from operating without water flow and thus tripping out on refriger­ant pressure, causing a lockout condition. The WSHP Open controller control will prevent this from occurring. Also, the loop controller can be configured to start the pumps only after a configurable number of WSHPs are requesting operation (from 1-"N"). This can be used to prevent starting the entire loop op­eration for only one WSHP. Meanwhile, the WSHPs will not operate if the loop pump status is off and therefore the WSHP compressor will not run.
COMPLETE C AND DELUXE D BOARD
SYSTEM TEST
Test mode provides the ability to check the control opera­tion in a timely manner. The control enters a 20-minute test mode by momentarily shorting the test terminals. All time de­lays are sped up 15 times. The following operations are com­mon to both Complete C and Deluxe D controls.
Test Mode — To enter Test mode, cycle the fan 3 times
within 60 seconds. The LED will flash a code representing the last fault when entering the Test mode. The alarm relay will also power on and off during Test mode. See Tables 27 and 28. To exit Test mode, short the terminals for 3 seconds or cycle the fan 3 times within 60 seconds.
NOTE: The flashing code and alarm relay cycling code will both have the same numerical label. For example, flashing code 1 will have an alarm relay cycling code 1. Code 1 indi­cates the control has not faulted since the last power off to power on sequence.
Table 27 — Complete C Control Current LED
Status and Alarm Relay Operations
LED STATUS DESCRIPTION OF OPERATION ALARM RELAY
On
Off
Slow Flash Fault Retry Open
Fast Flash Lockout Closed
Slow Flash Over/Under Voltage Shutdown
Flashing Code 1 Test Mode — No fault in memory Cycling Code 1
Flashing Code 2
Flashing Code 3
Flashing Code 4
Flashing Code 5
Flashing Code 6
Flashing Code 7
Flashing Code 8 Test Mode — PM in memory Cycling Code 8
Flashing Code 9
LEGEND
CO Condensate Overflow FP Freeze Protection HP High Pressure LED — Light-Emitting Diode LP Low Pressure PM Performance Monitor
NOTES:
1. Slow flash is 1 flash every 2 seconds.
2. Fast flash is 2 flashes every 1 second.
3. EXAMPLE: “Flashing Code 2 is represented by 2 fast flashes followed by a 10-second pause. This sequence will repeat continually until the fault is cleared.
Normal Mode Open
Normal Mode with
PM Warning
Complete C Control is
non-functional
Test Mode —
HP Fault in memory
Test Mode —
LP Fault in memory
Test Mode —
FP1 Fault in memory
Test Mode —
FP2 Fault in memory
Test Mode —
CO Fault in memory
Test Mode — Over/Under
shutdown in memory
Test Mode — FP1/FP2
Swapped Fault in memory
Cycle
(closed 5 sec.,
open 25 sec.)
Open
Open,
(Closed after
15 minutes)
Cycling Code 2
Cycling Code 3
Cycling Code 4
Cycling Code 5
Cycling Code 6
Cycling Code 7
Cycling Code 9
Table 28 — Complete C Control LED Code and
Fault Descriptions
LED
CODE
1 No fault in memory There has been no fault since
2 High-Pressure Switch HP switch opens instantly 3 Low-Pressure Switch LP switch opens for
4 Freeze Protection Coax
— FP1
5 Freeze Protection Air Coil —
FP2
6 Condensate overflow Sense overflow (grounded) for
7
(Autoreset)
FP Freeze Protection HP High Pressure LED — Light-Emitting Diode LP Low Pressure PM Performance Monitor
Over/Under Voltage Shutdown
8 PM Warning Performance Monitor Warning
9 FP1 and FP2
Thermistors are swapped
LEGEND
FAULT DESCRIPTION
the last power-down to power­up sequence
30 continuous seconds before or during a call (bypassed for first 60 seconds)
FP1 below Temp limit for 30 continuous seconds (bypassed for first 60 seconds of operation)
FP2 below Temp limit for 30 continuous seconds (bypassed for first 60 seconds of operation)
30 continuous seconds "R" power supply is <19VAC or
>30VAC
has occurred. FP1 temperature is higher than
FP2 in heating/test mode, or FP2 temperature is higher than FP1 in cooling/test mode.
42
WSHP Open Test Mode — To enter WSHP Open test
mode, navigate from the BACview
6
home screen to the config­uration screen. Choose the service screen and enable unit test. The controller will then test the following:
FAN TEST — Tests all fan speeds, sequences fan from low to high, and operates each speed for one minute. Resets to disable on completion.
COMPRESSOR TEST — Tests compressor cooling and heating operation. Sequences cooling stage 1 then cooling stage 2 followed by heating stage 2 then reduces capacity to heating stage 1. Operates for 1 minute per step.
DEHUMIDIFICATION TEST — Tests dehumidification mode. Operates for 2 minutes.
AUXILIARY HEATING TEST — Tests auxiliary heat. Sequences fan on and enables heating coil for 1 minute.
H
O ECONOMIZER TEST — Tests entering/returning
2
water loop economizer operation. Sequences fan and opens economizer water valve for one minute.
OPEN VENT DAMPER 100% TEST — Tests outside air (OA) damper operation.
PREPOSITION OA DAMPER — Prepositions OA damper actuator to set proper preload.
NOTE: The auxiliary heating test, H vent damper 100% test, and preposition OA damper features
O economizer test, open
2
will not be visible on the screen unless configured.
Once tests are complete, set unit test back to disable. Unit will automatically reset to disable after 1 hour.
Retry Mode — In Retry mode, the status LED will start to
flash slowly to signal that the control is trying to recover from an input fault. The control will stage off the outputs and try to again satisfy the thermostat used to terminal Y. Once the ther­mostat input calls are satisfied, the control will continue normal operation.
NOTE: If 3 consecutive faults occur without satisfying the thermostat input call to terminal Y, the control will go into lockout mode. The last fault causing the lockout is stored in memory and can be viewed by entering Test mode.
Aquazone™ Deluxe D Control LED Indica­tors —
STATUS LED — Status LED indicates the current status or mode of the D control. The Status LED light is green.
TEST LED — Test LED will be activated any time the D control is in test mode. The Test LED light is yellow.
FAULT LED — Fault LED light is red. The fault LED will always flash a code representing the last fault in memory. If there is no fault in memory, the fault LED will flash code 1 and appear as one fast flash alternating with a 10-second pause. See Table 29.
There are 3 LED indicators on the Deluxe D control:
Table 29 — Aquazone Deluxe D Control Current LED Status and Alarm Relay Operations
DESCRIPTION
Normal Mode On Off Flash Last Fault Code in Memory Open
Normal Mode with PM On Off Flashing Code 8
Deluxe D Control is non-functional
Tes t M od e On Flash Last Fault Code in Memory Cycling Appropriate Code
Night Setback Flashing Code 2 Flash Last Fault Code in Memory
ESD Flashing Code 3 Flash Last Fault Code in Memory Invalid T-stat Inputs Flashing Code 4 Flash Last Fault Code in Memory No Fault in Memory On Off Flashing Code 1 Open
HP Fault Slow Flash Off Flashing Code 2 Open
LP Fault Slow Flash Off Flashing Code 3 Open FP1 Fault Slow Flash Off Flashing Code 4 Open FP2 Fault Slow Flash Off Flashing Code 5 Open
CO Fault Slow Flash Off Flashing Code 6 Open
Over/Under Voltage Slow Flash Off Flashing Code 7 Open (closed after 15 minutes)
HP Lockout Fast Flash Off Flashing Code 2 Closed
LP Lockout Fast Flash Off Flashing Code 3 Closed FP1 Lockout Fast Flash Off Flashing Code 4 Closed FP2 Lockout Fast Flash Off Flashing Code 5 Closed
CO Lockout Fast Flash Off Flashing Code 6 Closed
CO — Condensate Overflow HP High Pressure ESD — Emergency Shutdown LP Low Pressure FP Freeze Protection PM Performance Monitor
STATUS LED
(Green)
Off Off Off Open
LEGEND NOTES:
TEST LED
(Yellow)
FAULT LED (Red) ALARM RELAY
Cycle (closed 5 sec,
open 25 sec, …)
1. If there is no fault in memory, the Fault LED will flash code 1.
2. Codes will be displayed with a 10-second Fault LED pause.
3. Slow flash is 1 flash every 2 seconds.
4. Fast flash is 2 flashes every 1 second.
5. EXAMPLE: “Flashing Code 2 is represented by 2 fast flashes followed by a 10-second pause. This sequence will repeat con­tinually until the fault is cleared.
43
SERVICE
Perform the procedures outlined below periodically, as
indicated.
WARNING
To prevent injury or death due to electrical shock or contact with moving parts, open unit disconnect switch before ser­vicing unit.
IMPORTANT: When a compressor is removed from this unit, system refrigerant circuit oil will remain in the com­pressor. To avoid leakage of compressor oil, the refrigerant lines of the compressor must be sealed after it is removed.
IMPORTANT: All refrigerant discharged from this unit must be recovered without exception. Technicians must fol­low industry accepted guidelines and all local, state and fed­eral statutes for the recovery and disposal of refrigerants.
IMPORTANT: To avoid the release of refrigerant into the atmosphere, the refrigerant circuit of this unit must only be serviced by technicians who meet local, state and federal proficiency requirements.
Filters — Filters must be clean for maximum performance.
Inspect filters every month under normal operating conditions. Replace when necessary.
IMPORTANT: Units should never be operated without a filter.
Water Coil — Keep all air out of the water coil. Check
open loop systems to be sure the well head is not allowing air to infiltrate the water line. Always keep lines airtight.
Inspect heat exchangers regularly, and clean more frequent­ly if the unit is located in a “dirty” environment. Keep the heat exchanger full of water at all times. Open loop systems should have an inverted P trap placed in the discharge line to keep water in the heat exchanger during off cycles. Closed loop systems must have a minimum of 15 psig during the summer and 40 psig during the winter.
Check P trap frequently for proper operation.
CAUTION
To avoid fouled machinery and extensive unit clean-up, DO NOT operate units without filters in place. DO NOT use equipment as a temporary heat source during construction.
Condensate Drain Pans — Check condensate drain
pans for algae growth twice a year. If algae growth is apparent, consult a water treatment specialist for proper chemical treat­ment. Applying an algaecide every three months will typically eliminate algae problems in most locations.
Refrigerant System — Verify air and water flow rates
are at proper levels before servicing. To maintain sealed circuit­ry integrity, do not install service gages unless unit operation appears abnormal.
Check to see that unit is within the superheat and subcool­ing temperature ranges shown in Tables 20-23. If the unit is not within these ranges, recover and reweigh in refrigerant charge.
Compressor — Conduct annual amperage checks to en-
sure that amp draw is no more than 10% greater than indicated on the serial plate data.
Fan Motors — All units have lubricated fan motors. Fan
motors should never be lubricated unless obvious, dry operation is suspected. Periodic maintenance oiling is NOT recommended as it will result in dirt accumulating in the excess oil and cause eventual motor failure. Conduct annual dry oper­ation check and amperage check to ensure amp draw is no more than 10% greater than indicated on serial plate data.
Condensate Drain Cleaning — Clean the drain line
and unit drain pan at the start of each cooling season. Check flow by pouring water into drain. Be sure trap is filled to main­tain an air seal.
Air Coil Cleaning — Remove dirt and debris from evap-
orator coil as required by condition of the coil. Clean coil with a stiff brush, vacuum cleaner, or compressed air. Use a fin comb of the correct tooth spacing when straightening mashed or bent coil fins.
Condenser Cleaning — Water-cooled condensers may
require cleaning of scale (water deposits) due to improperly maintained closed-loop water systems. Sludge build-up may need to be cleaned in an open water tower system due to induced contaminants.
Local water conditions may cause excessive fouling or pitting of tubes. Condenser tubes should therefore be cleaned at least once a year, or more often if the water is contaminated.
Proper water treatment can minimize tube fouling and pitting. If such conditions are anticipated, water treatment analysis is recommended. Refer to the Carrier System Design Manual, Part 5, for general water conditioning information.
CAUTION
Follow all safety codes. Wear safety glasses and rubber gloves when using inhibited hydrochloric acid solution. Observe and follow acid manufacturer’s instructions.
Clean condensers with an inhibited hydrochloric acid solu­tion. The acid can stain hands and clothing, damage concrete, and, without inhibitor, damage steel. Cover surroundings to guard against splashing. Vapors from vent pipe are not harmful, but take care to prevent liquid from being carried over by the gases.
Warm solution acts faster, but cold solution is just as effec­tive if applied for a longer period.
GRAVITY FLOW METHOD — Do not add solution faster than vent can exhaust the generated gases.
When condenser is full, allow solution to remain overnight, then drain condenser and flush with clean water. Follow acid manufacturer’s instructions. See Fig. 35.
FORCED CIRCULATION METHOD — Fully open vent pipe when filling condenser. The vent may be closed when condenser is full and pump is operating. See Fig. 36.
Regulate flow to condenser with a supply line valve. If pump is a nonoverloading type, the valve may be fully closed while pump is running.
For average scale deposit, allow solution to remain in con­denser overnight. For heavy scale deposit, allow 24 hours. Drain condenser and flush with clean water. Follow acid manu­facturer’s instructions.
44
Checking System Charge — Units are shipped with
Fig. 35 — Gravity Flow Method
FILL CONDENSER WITH CLEANING SOLUTION. DO NOT ADD SOLUTION MORE RAPIDLY THAN VENT CAN EXHAUST GASES CAUSED BY CHEMICAL ACTION.
PAIL
FUNNEL
CONDENSER
PAIL
3’ TO 4’
VENT PIPE
5’ APPROX
1 PIPE
SUCTION
PUMP SUPPORT
TANK
FINE MESH SCREEN
RETURN
GAS VENT
PUMP
PRIMING CONN.
GLOBE VALV ES
SUPPLY
1 PIPE
CONDENSER
REMOVE WATER REGULATING VALVE
Fig. 36 — Forced Circulation Method
full operating charge. If recharging is necessary:
1. Insert thermometer bulb in insulating rubber sleeve on
2. Connect pressure gage to discharge line near compressor.
3. After unit conditions have stabilized, read head pressure
4. From standard field-supplied Pressure-Temperature chart
5. Read liquid line temperature on thermometer; then
6. Compare the subcooling temperature with the normal
liquid line near filter drier. Use a digital thermometer for all temperature measurements. DO NOT use a mercury or dial-type thermometer.
on discharge line gage. NOTE: Operate unit a minimum of 15 minutes before
checking charge.
for R-410A refrigerant, find equivalent saturated con­densing temperature.
subtract from saturated condensing temperature. The dif­ference equals subcooling temperature.
temperature listed in Tables 20-23. If the measured liquid line temperature does not agree with the required liquid line temperature, ADD refrigerant to raise the tempera­ture or REMOVE refrigerant (using standard practices) to lower the temperature (allow a tolerance of ± 3° F).
Refrigerant Charging
WARNING
To prevent personal injury, wear safety glasses and gloves when handling refrigerant. Do not overcharge system — this can cause compressor flooding.
NOTE: Do not vent or depressurize unit refrigerant to atmo­sphere. Remove and recover refrigerant following accepted practices.
Air Coil Fan Motor Removal
CAUTION
Before attempting to remove fan motors or motor mounts, place a piece of plywood over evaporator coils to prevent coil damage.
Disconnect motor power wires from motor terminals before
motor is removed from unit.
1. Shut off unit main power supply.
2. Loosen bolts on mounting bracket so that fan belt can be removed.
3. Loosen and remove the 2 motor mounting bracket bolts on left side of bracket.
Slide motor/bracket assembly to extreme right and lift out through space between fan scroll and side frame. Rest motor on a high platform such as a step ladder. Do not allow motor to hang by its power wires.
Replacing the WSHP Open Controller’s Bat­tery — The WSHP Open controller’s 10-year lithium
CR2032 battery provides a minimum of 10,000 hours of data retention during power outages.
NOTE: Power must be ON to the WSHP Open controller when replacing the battery, or the date, time and trend data will be lost.
1. Remove the battery from the controller, making note of the battery's polarity.
2. Insert the new battery, matching the battery's polarity with the polarity indicated on the WSHP Open controller.
TROUBLESHOOTING
When troubleshooting problems with a WSHP, consider the
following:
Thermistor — A thermistor may be required for single-
Control Sensors — The control system employs 2 nom-
inal 10,000 ohm thermistors (FP1 and FP2) that are used for freeze protection. Be sure FP1 is located in the discharge fluid and FP2 is located in the air discharge. See Fig. 38.
45
WSHP Open Controller — With the WSHP Open con-
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0
Temperature (degF)
Resistance (kOhm)
Fig. 37 — Thermistor Nominal Resistance
SUCTION
COMPRESSOR
DISCHARGE
COAX
EXPANSION
VALV E
FP2
FP1
LIQUID LINE
WATER IN
WATER OUT
CONDENSATE
OVERFLOW
(CO)
AIR COIL FREEZE PROTECTION
WATER COIL PROTECTION
THERMISTOR
(°F)
(°F)
AIR
COIL
AIRFLOW
AIRFLOW
LEGEND
Fig. 38 — FP1 and FP2 Thermistor Location
COAX — Coaxial Heat Exchanger
Airflow Refrigerant Liquid Line Flow
troller option, the 100 most recent alarms can be viewed using the BACview
To view the alarms:
1. Navigate to the Alarm Status screen from the Home screen using the arrow softkeys. The screen will display the current alarm status, either normal or Alarm, and al­low for scrolling through the unit’s alarm status.
2. From the Alarm Status screen, press the Alarm softkey to view the 100 most recent alarms which are labeled with date and time for easy reference.
NOTE: Active faults can be viewed by scrolling down, these faults indicate a possible bad sensor or some condi­tion which may not merit an alarm.
3. To view alarms which have been corrected, scroll down through the Alarm screen to Return Top Normal screen.
NOTE: Alarms are automatically reset once alarm con­dition has been corrected.
See Table 32 for possible alarm cause and solution.
6
alarm status and alarm history.
Thermostatic Expansion Valves — Thermostat-
ic expansion valves (TXV) are used as a means of metering the refrigerant through the evaporator to achieve a preset superheat at the TXV sensing bulb. Correct superheat of the refrigerant is
important for the most efficient operation of the unit and for the life of the compressor.
Packaged heat pumps typically use one bi-flow TXV to me­ter refrigerant in both modes of operation. When diagnosing possible TXV problems it may be helpful to reverse the refrig­erant flow to assist with the diagnosis.
Geothermal and water source heat pumps are designed to operate through a wide range of entering-water temperatures that will have a direct effect on the unit refrigerant oper­ating pressures. Therefore, diagnosing TXV problems can be difficult.
TXV FAILURE — The most common failure mode of a TXV is when the valve fails while closed. Typically, a TXV uses spring pressure to close the valve and an opposing pressure, usually from a diaphragm, to open the valve. The amount of pressure exerted by the diaphragm will vary, depending on the pressure inside of the sensing bulb. As the temperature of and pressure within the bulb decreases, the valve will modulate closed and restrict the refrigerant flow through the valve. The result is less refrigerant in the evaporator and an increase in the superheat. As the temperature at the bulb increases the dia­phragm pressure will increase, which opens the valve and allows more refrigerant flow and a reduction in the superheat.
If the sensing bulb, connecting capillary, or diaphragm assembly are damaged, pressure is lost and the spring will force the valve to a closed position. Often, the TXV will not close completely so some refrigerant flow will remain, even if inade­quate flow for the heat pump to operate.
The TXV sensing bulb must be properly located, secured, and insulated as it will attempt to control the temperature of the line to which it is connected. The sensing bulb must be located on a dedicated suction line close to the compressor. On a pack­aged heat pump, the bulb may be located almost any place on the tube running from the compressor suction inlet to the reversing valve. If the bulb is located on a horizontal section, it should be placed in the 10:00 or 2:00 position for optimal performance.
CAUTION
Use caution when tightening the strap. The strap must be tight enough to hold the bulb securely but caution must be taken not to over-tighten the strap, which could dent, bend, collapse or otherwise damage the bulb.
46
The bulb must be secured to the pipe using a copper strap. The use of heat transfer paste between the bulb and the pipe will also help ensure optimum performance.
The bulb must also be properly insulated to eliminate any influence on valve operation by the surrounding conditions. Cork tape is the recommended insulation as it can be molded tight to the bulb to prevent air infiltration.
Causes of TXV Failure failure are:
1. A cracked, broken, or damaged sensing bulb or capillary can be caused by excessive vibration of the capillary dur­ing shipping or unit operation.
If the sensing bulb is damaged or if the capillary is cracked or broken, the valve will be considered failed and must be replaced. Replacement of the TXV “power head” or sensing bulb, capillary, diaphragm assembly is possi­ble on some TXVs. The power head assembly screws onto most valves, but not all are intended to be replace­able. If the assembly is not replaceable, replace the entire valve.
2. Particulate debris within the system can be caused by sev­eral sources including contaminated components, tubing, and service tools, or improper techniques used during brazing operations and component replacement.
Problems associated with particulate debris can be com­pounded by refrigerant systems that use POE (polyol es­ter oil). POE oil has solvent-like properties that will clean the interior surfaces of tubing and components. Particu­lates can be released from interior surfaces and may mi­grate to the TXV strainer, which can lead to plugging of the strainer.
3. Corrosive debris within the system may happen after a failure, such as a compressor burn out, if system was not properly cleaned.
4. Noncondensables may be present in the system. Non­condensables includes any substance other than the refrigerant or oil such as air, nitrogen, or water. Contami­nation can be the result of improper service techniques, use of contaminated components, and/or improper evacu­ation of the system.
Symptoms and will include one or more of the following:
• Low refrigerant suction pressure
• High refrigerant superheat
• High refrigerant subcooling
• TXV and/or low pressure tubing frosting
• Equalizer line condensing and at a lower temperature than the suction line or the equalizer line frosting
• FP1 faults in the heating mode in combination with any of the symptoms listed above
• FP2 faults in the cooling mode in combination with any of the symptoms listed above. Some symptoms can mimic a failed TXV but may actually be caused be another problem.
Before conducting an analysis for a failed TXV the follow-
ing must be verified:
• Confirm that there is proper water flow and water tempera­ture in the heating mode.
• Confirm that there is proper airflow and temperature in the cooling mode.
• Ensure coaxial water coil is clean on the inside; this applies to the heating mode and may require a scale check.
• Refrigerant may be undercharged. To verify, subcooling and superheat calculations may be required.
— The symptoms of a failed TXV can be varied
— The most common causes of TXV
Diagnostics a TXV has failed. The following tools may be required for testing:
1. Refrigerant gage manifold compatible with the refriger-
2. Digital thermometer, preferably insulated, with wire leads
3. Refrigerant pressure-temperature chart for the refrigerant
To determine that a TXV has failed, verify the following:
• The suction pressure is low and the valve is non-responsive. The TXV sensing bulb can be removed from the suction line and warmed by holding the bulb in your hand. This
action should result in an increase in the suction pressure while the compressor is operating. The sensing bulb can also be chilled by immersion in ice water, which should result in a decrease in the suction pressure while the compressor is operating. No change in the suction pres­sure would indicate a nonresponsive valve.
• Simultaneous LOW suction pressure, HIGH refrigerant subcooling and HIGH superheat.
• LOW suction pressure, LOW subcooling and HIGH super­heat may indicate an undercharge of refrigerant. HIGH sub­cooling and LOW superheat may indicate an overcharge of refrigerant. The suction pressure will usually be normal or high if there is an overcharge of refrigerant.
• LOW suction pressure and frosting of the valve and/or equalizer line may indicate a failed valve. However, these symptoms may also indicate an undercharge of refrigerant. Calculate the subcooling and superheat to verify a failed valve or refrigerant charge issue.
Repair
—Several tests may be required to determine if
ant in the system
that can be connected directly to the tubing
used
WARNING
Puron® refrigerant (R-410A) operates at higher pressure than R-22, which is found in other WSHPs. Tools such as manifold gages must be rated to withstand the higher pres­sures. Failure to use approved tools may result in a failure of tools, which can lead to severe damage to the unit, injury or death.
WARNING
Most TXVs are designed for a fixed superheat setting and are therefore considered non-adjustable. Removal of the bottom cap will not provide access for adjustment and can lead to damage to the valve or equipment, unintended vent­ing of refrigerant, personal injury, or possibly death.
CAUTION
Always recover the refrigerant from the system with suit­able approved tools, recovery equipment, and practices prior to attempting to remove or repair any TXV.
CAUTION
Use caution when tightening the strap. The strap must be tight enough to hold the bulb securely but caution must be taken not to over-tighten the strap, which could dent, bend, collapse or otherwise damage the bulb.
47
CAUTION
Puron® refrigerant (R-410A) requires the use of synthetic lubricant (POE oil). Do not use common tools on systems that contain R-22 refrigerants or mineral oil. Contamina­tion and failure of this equipment may result.
IMPORTANT: Repair of any sealed refrigerant system requires training in the use of refrigeration tools and proce­dures. Repair should only be attempted by a qualified ser­vice technician. A universal refrigerant handling certificate will be required. Local and/or state license or certificate may also be required.
See Tables 30-32 for additional troubleshooting
IMPORTANT: Due to the hygroscopic nature of the
information. POE oil in Puron refrigerant (R-410A) and other envi­ronmentally sound refrigerants, any component replace-
ment must be conducted in a timely manner using caution and proper service procedure for these types of refrigerants. A complete installation instruction will be included with each replacement TXV/filter drier assem­bly. It is of critical importance these instructions are
Disconnect power from unit before removing or replacing connectors, or servicing motor. Wait 5 minutes after dis­connecting power before opening motor.
carefully understood and followed. Failure to follow these instructions can result in a system that is contami­nated with moisture to the extent that several filter drier replacements may be required to properly dry the system.
Table 30 — ECM Troubleshooting
FAULT DESCRIPTION SOLUTION
Motor rocks slightly when starting
Motor will not start No movement Check power at motor.
Motor rocks Check for loose or non-compliant motor mount.
Motor oscillates up and down while being tested off of blower
Motor starts, but runs erratically Varies up and down or intermittent Check line voltage for variation or “sag.
“Hunts or “puffs at high cfm (speed)
Stays at low cfm despite system call for cool or heat cfm
Stays at high cfm Check to see if “R is missing/not connected at motor.
Blower will not shut off Check to see if there is current leakage from controls into G, Y, or W. Check for Triac switched
Excessive noise Noisy blower or cabinet Determine if it’s air, cabinet, duct, or motor noise.
“Hunts or “puffs at high cfm
Evidence of moisture Motor failure or malfunction has
(speed)
occurred and moisture is present Evidence of moisture present
inside air mover
This is normal start-up for ECM.
Check low voltage (24-vac R to C) at motor. Check low voltage connections (G,Y, W, R, C) at motor. Check for unseated pins in connectors on motor harness. See Fig. 39. Test with a temporary jumper between R and G. Check motor for tight shaft. Perform motor/control replacement check. Run moisture check. See Moisture Check section in Troubleshooting.
Make sure blower wheel is tight on shaft. Perform motor/control replacement check. It is normal for motor to oscillate with no load on shaft.
Check low voltage connections (G,Y, W, R, C) at motor, unseated pins in motor harness connectors. See Fig. 39.
Check “Bk for erratic cfm command (in variable speed applications). Check system controls, thermostat. Perform moisture check. See Moisture Check section in Troubleshooting. If removing panel or filter reduces “puffing, reduce restriction or reduce maximum airflow.
Check low voltage (thermostat) wires and connections.
Verify fan is not in delay mode. Wait until delay is complete. Check to see if “R is missing/not connected at motor. Perform motor/control replacement check.
Verify fan is not in delay mode. Wait until delay is complete. Perform motor/control replacement check.
thermostat or solid state relay.
Check for loose blower housing, panels, etc. If high static is creating high blower speed, check for air whistling through seams in ducts,
cabinets, or panels. If high static is creating high blower speed, check for cabinet/duct deformaton. If removing panel or filter reduces “puffing, reduce restriction or reduce maximum airflow.
Replace motor and perform moisture check. See Moisture Check section in Troubleshooting.
Perform moisture check. See Moisture Check section in Troubleshooting.
CAUTION
48
Fig. 39 — ECM Pin Connectors
a50-8448
49
Stopped or Malfunctioned ECM Motor — Refer
Fig. 40 — ECM Troubleshooting Flow Diagram
a50-8447
to Fig. 40 to determine the possible cause of a stopped or mal­functioned ECM motor. Follow the instructions in the boxes.
50
Moisture Check — To perform moisture check:
• Check that connectors are orientated “down” (or as recom­mended by equipment manufacturer).
• Arrange harnesses with “drip loop” under motor.
• Check if condensate drain is plugged.
• Check for low airflow (too much latent capacity).
• Check for undercharged condition.
• Check and plug leaks in return ducts, cabinet.
Table 31 — Good Practices
DO DO NOT
Check motor, controls wiring, and connections thoroughly before replac-
Automatically assume the motor is bad.
ing motor. Orient connectors down so water cannot get in. Install “drip loops. Locate connectors above 7 and 4 o’clock positions. Use authorized motor and control model numbers for replacement. Replace one motor or control model number with another (unless
replacement is authorized).
Keep static pressure to a minimum by:
• Using high efficiency, low-static filters.
• Keeping filters clean.
• Designing ductwork for minimum static and maximum comfort.
• Improving ductwork when replacement is necessary.
Use high pressure drop filters. Use restricted returns.
Size equipment wisely. Oversize system then compensate with low airflow. Check orientation before inserting motor connectors. Plug in power connector backwards.
Force plugs.
Table 32 — WSHP Troubleshooting
Main Power Problems X X Green Status LED Off Check line voltage circuit breaker and disconnect.
HP Fault — Code 2 High Pressure
LP/LOC Fault — Code 3 Low Pressure/Loss of Charge
FP1 Fault — Code 4 Water Freeze Protection
FP2 Fault — Code 5 Air Coil Freeze Protection
Condensate Fault — Code 6
LED — Light-Emitting Diode RV Reversing Valve TXV — Thermostatic Expansion Valve
FAULT HEATING COOLING POSSIBLE CAUSE SOLUTION
Check for line voltage between L1 and L2 on the contactor. Check for 24 vac between R and C on controller. Check primary/secondary voltage on transformer.
Check water flow adjust to proper flow rate. Bring water temperature within design parameters.
Check fan motor operation and airflow restrictions. Dirty air coil — construction dust etc. External static too high. Check blower performance per Tables 9-13.
Tables 20-23.
Plugged strainer or filter. Clean or replace. Check water flow adjust to proper flow rate.
Clip JW2 jumper for antifreeze (10F) use.
Check fan motor operation and airflow restrictions. External static too high. Check blower performance per Tables 9-13.
parameters. Normal airside applications will require 30 F only.
Check slope of unit toward outlet. Poor venting. Check vent location.
LEGEND
X Reduced or no water flow in cooling Check pump operation or valve operation/setting.
X Water temperature out of range in
X Reduced or no airflow in heating Check for dirty air filter and clean or replace.
X Air temperature out of range in heating Bring return-air temperature within design parameters. X X Overcharged with refrigerant Check superheat/subcooling vs typical operating condition per
X X Bad HP switch Check switch continuity and operation. Replace. X X Insufficient charge Check for refrigerant leaks. X Compressor pump down at start-up Check charge and start-up water flow.
X Reduced or no water flow in heating Check pump operation or water valve operation/setting.
X Inadequate antifreeze level Check antifreeze density with hydrometer. X Improper freeze protect setting (30F
X Water temperature out of range Bring water temperature within design parameters. X X Bad thermistor Check temperature and impedance correlation.
X X Bad thermistor Check temperature and impedance correlation. X X Blocked drain Check for blockage and clean drain. X X Improper trap Check trap dimensions and location ahead of vent.
cooling
vs 10F)
X Reduced or no airflow in cooling Check for dirty air filter and clean or replace.
X Air temperature out of range Too much cold vent air. Bring entering air temperature within design
X Improper freeze protect setting (30F
vs 10F)
X Poor drainage Check for piping slope away from unit.
X Moisture on sensor Check for moisture shorting to air coil.
51
Table 32 — WSHP Troubleshooting (cont)
FAULT HEATING COOLING POSSIBLE CAUSE SOLUTION
Over/Under Voltage — Code 7 (Auto Resetting)
Performance Monitor — Code 8
FP1 and FP2 Thermistors — Code 9
No Fault Code Shown X X No compressor operation See Scroll Compressor Rotation section.
Swapped Thermistor — Code 9
Unit Short Cycles X X Dirty air filter Check and clean air filter.
Only Fan Runs X X Thermostat position Ensure thermostat set for heating or cooling operation.
Only Compressor Runs X X Thermostat wiring Check G wiring at heat pump. Jumper G and R for fan operation.
Unit Does Not Operate in Cooling
Insufficient Capacity/ Not Cooling or Heating Properly
LEGEND
LED — Light-Emitting Diode RV Reversing Valve TXV — Thermostatic Expansion Valve
X X Under voltage Check power supply and 24 vac voltage before and during operation.
Check power supply wire size. Check compressor starting. Check 24 vac and unit transformer tap for correct power supply voltage.
X X Over voltage Check power supply voltage and 24 vac before and during operation.
X Heating mode FP2>125F Check for poor airflow or overcharged unit.
X Cooling mode FP1>125F OR
FP2<40F
X FP1 temperature is higher
X X Compressor overload Check and replace if necessary. X X Control board Reset power and check operation. X X FP1 and FP2 swapped Reverse position of thermistors.
X X Unit in 'Test Mode' Reset power or wait 20 minutes for auto exit. X X Unit selection Unit may be oversized for space. Check sizing for actual load of space. X X Compressor overload Check and replace if necessary.
X X Unit locked out Check for lockout codes. Reset power. X X Compressor overload Check compressor overload. Replace if necessary. X X Thermostat wiring Check Y and W wiring at heat pump. Jumper Y and R for compressor
X X Fan motor relay Jumper G and R for fan operation. Check for line voltage across BR
X X Fan motor Check for line voltage at motor. Check capacitor.
X X Dirty filter Replace or clean. X Reduced or no airflow in heating Check for dirty air filter and clean or replace.
X X Leaky ductwork Check supply and return air temperatures at the unit and at distant duct
X X Low refrigerant charge Check superheat and subcooling per Tables 20-23. X X Restricted metering device Check superheat and subcooling per Tables 20-23. Replace.
X X Thermostat improperly located Check location and for air drafts behind thermostat. X X Unit undersized Recheck loads and sizing check sensible cooling load and heat pump
X X Scaling in water heat exchanger Perform condenser cleaning. X X Inlet water too hot or cold Check load, loop sizing, loop backfill, ground moisture.
than FP2 temperature.
X FP2 temperature is higher
than FP1 temperature.
X Reversing valve Set for cooling demand and check 24 vac on RV coil and at control.
X Thermostat setup Check for 'O' RV setup not 'B'. X Thermostat wiring Check O wiring at heat pump. Jumper O and R for RV coil 'Click'.
X Reduced or no airflow in cooling Check for dirty air filter and clean or replace.
X Defective reversing valve Set for cooling demand and check 24 vac on RV coil and at control.
Check 24 vac and unit transformer tap for correct power supply voltage.
Check for poor water flow or airflow.
Swap FP1 and FP2 thermistors.
Swap FP1 and FP2 thermistors.
operation in Test mode.
Check Y and W wiring at heat pump. Jumper Y and R for compressor operation in test mode.
contacts. Check fan power enable relay operation (if present).
If RV is stuck, run high pressure up by reducing water flow and while operating, engage and disengage RV coil voltage to push valve.
Check fan motor operation and airflow restrictions. External static too high. Check blower performance per Tables 9-13.
Check fan motor operation and airflow restrictions. External static too high. Check blower performance per Tables 9-13.
registers if significantly different, duct leaks are present.
If RV is stuck, run high pressure up by reducing water flow and while operating, engage and disengage RV coil voltage to push valve.
capacity.
52
Table 32 — WSHP Troubleshooting (cont)
FAULT HEATING COOLING POSSIBLE CAUSE SOLUTION
High Head Pressure X Reduced or no airflow in heating Check for dirty air filter and clean or replace.
Check fan motor operation and airflow restrictions. External static too high. Check blower performance per Tables 9-13.
X Reduced or no water flow in
cooling
X Inlet water too hot Check load, loop sizing, loop backfill, ground moisture.
X Air temperature out of range in
X X Unit overcharged Check superheat and subcooling. Reweigh in charge. X X Noncondensables in system Remove refrigerant, evacuate system and charge unit. X X Restricted metering device Check superheat and subcooling per Tables 20-23. Replace.
Low Suction Pressure X Reduced water flow in heating Check pump operation or water valve operation/setting.
X Water temperature out of range Bring water temperature within design parameters.
X X Insufficient charge Check for refrigerant leaks.
Low Discharge Air Temperature in Heating
High Humidity X Too high airflow Check blower performance per Tables 9-13
Low Refrigerant Suction Pressure
High Refrigerant Superheat X X Insufficient refrigerant charge Locate and repair leak.
High Refrigerant Subcooling
TXV and/or Low Pressure Tubing Frosting
Equalizer Line Condensing or Frosting
X Too high airflow Check blower performance per Tables 9-13. X Poor performance See “Insufficient Capacity.
X Normal operation Check/compare with unit Installation Manual for typical operating temper-
X Reduced water flow Check pump operation.
X Water temperature out of range Bring water temperature within proper range. X Scaling in water to refrigerant
X X Return air temperature below
X X Insufficient refrigerant charge Locate and repair leak. X X Improperly located TXV sensing
X X Failed or restricted metering
X X Improperly located TXV sensing
X X Failed or restricted metering
X X Excessive refrigerant charge Remove refrigerant as needed. X X Failed or restricted metering
X Normal operation May occur when entering water temperature is close to minimum. X X Insufficient refrigerant charge Locate and repair leak. X X Failed or restricted metering
X X Failed or restricted metering
heating
X Scaling in water heat exchanger Perform condenser cleaning.
X Reduced airflow in cooling Check for dirty air filter and clean or replace.
X Air temperature out of range Too much cold vent air. Bring entering air temperature within design
X Unit oversized Recheck loads and sizing check sensible cooling load and heat pump
heat exchanger
X Reduced airflow Check for dirty air filter.
minimum
X Supply air bypassing to return air
stream (zone systems).
bulb
device
bulb
device
device
device
device
LEGEND
LED — Light-Emitting Diode RV Reversing Valve TXV — Thermostatic Expansion Valve
Check pump operation or valve operation/setting. Check water flow adjust to proper flow rate. See Tables 19 and 24.
Bring return-air temperature within design parameters.
Plugged strainer or filter. Clean or replace. Check water flow adjust to proper flow rate.
Check fan motor operation and airflow restrictions. External static too high. Check blower performance per Tables 9-13.
parameters.
capacity.
atures and pressures chart.
Check strainer or filter. Improper flow regulator.
Conduct water quality analysis.
Check for dirty air coil. Check fan motor operation. External static pressure exceeds fan operating parameters. Space temperature too cold.
Excessive fresh air. Check for leaking ductwork.
Locate bulb on suction line between reversing valve and compressor.
Failed TXV power head, capillary or sensing bulb. Plugged TXV strainer.
Locate bulb on suction line between reversing valve and compressor.
Failed TXV power head, capillary or sensing bulb. Plugged TXV strainer.
Failed TXV power head, capillary or sensing bulb. Plugged TXV strainer.
Failed TXV power head, capillary or sensing bulb. Plugged TXV strainer. Failed TXV power head, capillary or sensing bulb. Plugged TXV strainer.
53
APPENDIX A — WSHP OPEN SCREEN CONFIGURATION


SCREEN NAME POINT NAME
Operating Mode
SPT F Displays SPT SAT F Displays SAT
Condenser Leaving
Temperature
Condenser Entering
Temperature
Fan
Equipment
Status
Alarm Status
Sensor
Calibration
BAS — Building Automation System DCV — Demand Controlled Ventilation IAQ — Indoor Air Quality OAT — Outdoor Air Temperature RH Relative Humidity SAT — Supply Air Temperature SPT — Space Temperature TPI Third Party Integration
Compressor Capacity 0 - 100% Displays compressor capacity
Damper Position 0 - 100%
O Economizer 0 - 100% Displays position of economizer valve
H
2
Auxiliary Heat 0 - 100%
Space RH 0 - 100%
Dehumidification Inactive/Active
IAQ CO
2
SPT Alarm Status
Alarming SPT F
SPT Alarm Limit F
SPT Sensor Alarm
Status
IAQ Alarm Status Normal/Alarm Current IAQ/ventilation condition
Compressor Alarm
Status
SAT Alarm Status Normal/Alarm Current SAT condition
Condensate Overflow
Alarm Status
Condenser Water Tem-
perature Alarm Status
Filter Alarm Status Normal/Alarm Current filter condition
Space RH Alarm Status Normal/Alarm Current space RH condition
OAT Alarm Status Normal/Alarm
Airside Linkage Status Normal/Alarm Current linkage status if enabled
Condenser Water
Linkage
SAT
SAT Offset X -9.9 - 10.0 F 0 F Used to correct sensor reading
Leaving Condenser Water Temperature
Leaving CW Offset X -9.9 - 10.0 F 0 F Used to correct sensor reading
Rnet Sensor
Temperature
Rnet Offset X -9.9 - 10.0 F 0 F Used to correct sensor reading
RH % Displays Space RH value
RH Sensor Offset X -15% - 15% 0 % Used to correct sensor reading
LEGEND
PASSWO RD
LEVEL
No Password
Required
No Password
Required
Admin Password level access only
EDITABLE RANGE DEFAULT NOTES
Off, Fan Only, Economize,
Cooling, Heating, Cont Fan,
Test, Start Delay, Dehumidify
F
F
Off/Low Speed/
Medium Speed
High Speed/On
0 - 9999 ppm Displays the space CO2 level
Normal/Alarm
Normal/Alarm
Normal/Alarm Current compressor condition
Normal/Alarm
Normal/Alarm
Normal/Alarm Current linkage status if enabled
F Display SAT
F
F Displays SPT
Displays unit operating mode
Displays leaving condenser
water temperature
Displays entering condenser
water temperature (Value
will not update when compressor
Displays current damper position (Viewable only if Ventilation DMP
reheat valve (Viewable only if Leaving
Air Auxiliary Heat Type = 2 position,
Displays space RH% (Viewable only if
Displays if dehumidification is active
Dehumidification Reheat = Installed)
exceeded the alarm limit (when SPT
Displays the SPT alarm limit that was
exceeded; causing the alarm condition
(when SPT alarm above is in Alarm)
SPT sensor - ALARM is displayed
should the sensor fail to communicate
Current status of the condensate
is operating)
Displays fan speed status
Type = 2 position or DCV)
Displays position of auxiliary
1 stage Elect or Modulating)
Humidity Sensor = Installed)
(Viewable only if Factory
Displays current space
temperature condition Displays the SPT that
alarm above is in Alarm)
Displays the status of the Rnet
with the control module
drain (overflow switch)
Current status of the
condenser water
Current status of the OAT
broadcast function
Displays Leaving Condenser
Water Temperature
54
APPENDIX A — WSHP OPEN SCREEN CONFIGURATION (cont)

SCREEN NAME POINT NAME
Operating Mode
Fan Operating Mode Auto/Continuous/Always On
Occupancy Status Unoccupied/Occupied Displays the current occupancy status
Occupancy Control
Outside Air
Temperature
SPT F Displays SPT
SPT Status
SPT Sensor Status Inactive/Connected
Condensate Overflow Normal/Alarm
Cooling Set Point F
Unit
Maintenance
System Settings
Occupancy
Maintenance
Schedule
Configuration
BAS — Building Automation System DCV — Demand Controlled Ventilation IAQ — Indoor Air Quality OAT — Outdoor Air Temperature RH Relative Humidity SAT — Supply Air Temperature SPT — Space Temperature TPI Third Party Integration
Heating Set Point F
Set Point Adjustment F
Auxiliary Heat Control
Set Point
O Economizer
H
2
Control Set Point
Calculated IAQ/
Ventilation Damper
position
Active Compressor
Stages
SAT F Displays SAT
Reset Filter Alarm X No/Yes
Overflow Contact Closed/Open
Occupancy Contact Closed/Open
BAS/Keypad Override X
OAT Input N/A / Network
BACnet X See TPI
Keypad Configuration X Mapping
Password X Changes password
Network X See TPI
BACnet Time Master X See TPI
Clock Set X Changes clock/time setting
Override Schedules
Pushbutton Override Inactive/Active Occupied
Keypad Override
Schedules Inactive/Active Occupied
Occupancy Contact Inactive/Active Occupied
BAS on/off Inactive/Active Occupied
Local Occupancy
Schedules
Local Holiday
Schedules
Local Override
Schedules
BACnet Occupancy
Schedules
LEGEND
PASSWORD
LEVEL
No Password
required
No Password
required
User/Admin
Password level
access
EDITABLE RANGE DEFAULT NOTES
Off, Fan Only,Economize,
Cooling, Heating, Cont Fan, Test,
Start Delay, Dehumidify
Always Occupied/Local Schedule/
BACnet Schedule/BAS Keypad/
Occupied Contact/Holiday Schedule/
Override Schedule/Pushbutton
Override/Unoccupied None
F
Normal/Above Limit/Below
Limit/Sensor Failure
F
F
%
0/1/2
Inactive/Occupied/
Unoccupied
Inactive/Active Occupied
Inactive/Active Occupied/Active
Unoccupied
X Disable/Enable Enable
X Disable/Enable Disable
X Disable/Enable Disable
X Disable/Enable Disable
Inactive
Displays unit operating mode
Displays how the fan is configured
Displays OAT (Viewable only if OAT
Displays the connection status
being used for heating control
Displays the offset values from the Rnet
user set point adjustment that is being
applied to the configured set points
Displays the calculated set point being
used for auxiliary heating control
Displays the calculated set point being
Displays the ventilation damper
position calculated by the DCV control
Displays the actual number of
Used to reset the filter alarm timer after
the filter has been cleaned or replaced
Displays the state of the condensate
Displays the state of the external/
remote occupancy input switch contact
Provides capability to force the
occupied or unoccupied mode
Displays if an OAT value is being
Used to display the active and
inactive occupancy control inputs
Used to define which occupancy inputs
to operate
Displays the origin of the
occupancy control
is a network broadcast)
Displays the SPT status
of the Rnet sensor
Displays the status of the
condensate overflow
Displays the actual set point
being used for cooling control
Displays the actual set point
used for economizer control
compressor stages operating
overflow switch contact
equipment to operate in an
received from the Network
are used to determine
occupancy mode.
55
APPENDIX A — WSHP OPEN SCREEN CONFIGURATION (cont)



SCREEN NAME POINT NAME
Occupied Heating
Occupied Cooling X 55 - 99 F 76 F
Unoccupied Heating X 40 - 90 F 55 F
Unoccupied Cooling X 55 - 99 F 90 F
Effective Heating
Set Point
Effective Cooling
Set Point
Optimal Start
Configuration
Occupied RH
Set Points
Configuration
Schedule
Weekly Schedule
Configuration
Schedule
Exception
Schedules 1 - 12
LEGEND
BAS — Building Automation System DCV — Demand Controlled Ventilation IAQ — Indoor Air Quality OAT — Outdoor Air Temperature RH Relative Humidity SAT — Supply Air Temperature SPT — Space Temperature TPI Third Party Integration
Set Point
Unoccupied RH
Set Point
DCV CTRL Start
Set Point
DCV Max CTRL
Set Point
Start Time
End Time X 00:00 - 24:00 18:00
Mon X No/Yes Yes
Tu e X N o /Ye s Ye s
Wed X No/Yes Yes
Thur X No/Yes Yes
Fri X No/Yes Yes
Sat X No/Yes No
Sun X No/Yes No
Start Month
Start Day X 0 - 31 0
Start Time X 00:00 - 23:59 0:00
End Month X 0 - 12 0
End Day X 0 - 31 0
End Time X 00:00 - 24:00 0:00
PASSWORD
LEVEL
User/Admin
Password level
access
User/Admin
Password level
access
User/Admin
Password level
access
EDITABLE RANGE DEFAULT NOTES
X 40 - 90 F 72 F
X0 - 10 F
X0 - 10 F
X 0 - 100% 65%
X 0 - 100% 90%
X 0 - 9999 ppm 500 ppm
X 0 - 9999 ppm 1050 ppm
X 00:00 - 23:59 06:00
X0 - 120
Defines the Occupied
Heating Set Point
Defines the Occupied
Cooling Set Point
Defines the Unoccupied
Heating Set Point
Defines the Unoccupied
Cooling Set Point
Takes into effect bias (maximum
allowable set point deviation)
Takes into effect bias (maximum
allowable set point deviation)
Uses historical data to calculate
ramp up time so as to be at set point
at occupied/unoccupied time
Defines the control set point used
during occupied periods (Viewable
only if Humidity Sensor = Installed/
Determines when to start
Dehumidification when occupied)
Defines the control set point used
during unoccupied periods
(Viewable only if Humidity Sensor =
Installed/Determines when to start
Dehumidification when unoccupied)
Defines the control set point used to
start increasing ventilation during
occupied periods (Viewable only if
Ventilation DMP Type = DCV)
Defines the control set point
used to define where the ventilation
will reach its maximum limit during
occupied periods (Viewable only if
Ventilation DMP Type = DCV/Used
to determine DCV ending control
Defines the start time for an
Defines the ending time of an
Determines if this day is included
Determines if this day is included
Determines if this day is included
Determines if this day is included
Determines if this day is included
Determines if this day is included
Determines if this day is included
Defines the start month of this
Defines the start day of this holiday
Determines the start time for this
Defines the month to end this
Defines the day to end this holiday
Determines the time to end this
point)
occupied period
occupied period
in this schedule
in this schedule
in this schedule
in this schedule
in this schedule
in this schedule
in this schedule
hoilday schedule
schedule
schedule
hoilday schedule
schedule
schedule
56
APPENDIX A — WSHP SCREEN OPEN CONFIGURATION (cont)

SCREEN NAME POINT NAME
Fan Mode
Fan On Delay X 0 - 30 sec 10 sec
Fan Off Delay X 0 - 180 sec 45 sec
Heating Enable X Disable/Enable Enable
Cooling Enable X Disable/Enable Enable
Minimum SAT in
Configuration
Unit
Configuration
Configuration
Service
Test
LEGEND
BAS — Building Automation System DCV — Demand Controlled Ventilation IAQ — Indoor Air Quality OAT — Outdoor Air Temperature RH Relative Humidity SAT — Supply Air Temperature SPT — Space Temperature TPI Third Party Integration
Cooling
Maximum SAT in
Heating
Damper Ventilation
Positio n
DCV Maximum Vent
Positio n
Filter Alarm Timer X 0 - 9999 hrs 0 hrs Disables Filter Alarm if set to 0
Pushbutton Override X Disable/Enable Enable Enables Override Feature on Rnet sensor
SPT Sensor Set Point
Adjustment
Lockout Cooling if
OAT <
Lockout Heating if
OAT >
Power Fail Restart
Delay
Occupancy Schedules X Disable/Enable Enable Enables unit occupied
Set Point Separation X 2 - 9 F 4 F
Test Mode
Fan Test X Disable/Enable Disable
Fan Speed
Compressor Test X Disable/Enable Disable
Dehumidification Test X Disable/Enable Disable
Testing Compressor
Aux Heating Test X Disable/Enable Disable
O Economizer Test X Disable/Enable Disable
H
2
Preposition OA
Damper
Open Vent
Damper 100%
SAT F Displays SAT
LCWT F
PASSWORD
LEVEL
Admin Password
level access only
Admin Password
level access only
EDITABLE RANGE DEFAULT NOTES
Auto= Intermittant operation during both
occupied and unoccupied periods/
X
X40 - 60 F50 F
X 80 - 140 F 110 F
X 0 - 100% 100%
X 0 - 100% 100%
X Disable/Enable Enable
X -65 - 80 F -65 F
X 35 - 150 F 150 F
X 0 - 600 sec 60 sec Delay before equipment starts
X Disable/Enable Disable
X Disable/Enable Disable
X Disable/Enable Disable Used to test OA damper operation
Auto/Continuous/
Always On
Off/Low Speed/Medium
Speed/High Speed/On
Inactive/Heating/Cooling/
Dehumidify/TimeGard
Wait
Continuous
Continuous = Intermittant during unoccupied
periods and continuous during occupied
periods/Always on = fan operates
continuously during both occupied and
unoccupied periods
Defines the delay time before the fan begins
to operate after heating or cooling is started
Defines the amount of time the fan will
continue to operate after heating or
cooling is stopped
Provides capability to manually
disable heating operation
Provides capability to manually
disable cooling operation
Defines the minimum acceptable operating
temperature for the Supply Air
Defines the maximum acceptable operating
temperature for the Supply Air
Normally set to 100% if 2 position damper
type or set to minimum ventilation position if
Usually set at 100% - Used to limit maximum
Enables Set Point adjustment capability
Cooling is locked out when OAT is less than
configured value and OAT is actively being
Heating is locked out when OAT is greater
than configured value and OAT is actively
Used to enable test mode. Will automatically
Used to test all fan speeds. Sequences fan
from low to high and operates each speed for
1 minute. Resets to disable on completion
Used to test compressor cooling and heating
operation. Sequences cooling stage 1, then
stage 2, then heating stage 2 and reduces
capacity to stage 1. Operates for 1 minute per
Used to test entering/return air water loop
economizer coil operation. Sequences fan on
and opens economizer coil water valve for 1
minute. Resets to disable on completion
damper type = DCV
damper opening in DCV mode
on Rnet Sensor
broadcast
being broadcast
Used to enforce minimum
set point separation
reset to disable after 1 hour
Displays current fan operation
step. Resets to disable on completion.
Used to test dehumification mode -
Operates for 2 minutes. Resets to
disable on completion.
Displays compressor test mode
Used to test auxiliary heat.
Sequences fan on and enables
heating coil for 1 minute. Resets to
disable on completion
Used to preposition OA damper
actuator to set proper preload
Displays Leaving Condenser
Water Temperature
57
APPENDIX A — WSHP SCREEN OPEN CONFIGURATION (cont)

SCREEN NAME POINT NAME
# of Fan Speeds
G Output Type X Fan On/Fan Low Fan On
Compressor Stages X One Stage/Two Stages One Stage
Reversing Valve Type X O type output/B type output O type
Leaving Air Auxiliary
Heat Type
Entering Air Water
Economizer Type
2-Position Water
Val ve Type
Modulating Water
Val ve Type
Ventilation Damper
Ty pe
Damper Actuator Type X (0-10 volt)/(2-10 volt) 0-10 volt
Configuration
Service
Configuration
LEGEND
BAS — Building Automation System DCV — Demand Controlled Ventilation IAQ — Indoor Air Quality OAT — Outdoor Air Temperature RH Relative Humidity SAT — Supply Air Temperature SPT — Space Temperature TPI Third Party Integration
Humidity Sensor X None/Installed None
Factory Dehumidifica-
tion Reheat Coil
Occupancy Input Logic
Condensate Switch
Alarm Delay
Condensate Switch
Alarm State
Minimum Condenser
Water Temperature in
Heating
Maximum Condenser
Water Temperature in
Heating
Minimum Condenser
Water Temperature in
Cooling
Maximum Condenser
Water Temperature in
Cooling
IAQ sensor
minimum input
IAQ sensor
maximum input
IAQ sensor
minimum output
IAQ sensor
maximum output
PASSWORD
LEVEL
Admin Password
level access only
EDITABLE RANGE DEFAULT NOTES
X 1,2,3 3
X
X None/2-Position/Modulating None
X Normally Closed/Normally Open
X Normally Closed/Normally Open
X None/2-Position/DCV None
X None/Installed None
X Occupied Open/Occupied Closed
X 5 - 600 seconds 10 sec
X Alarm OPEN/Alarm CLOSED
X25 - 60 F60 F
X 65 - 100 F 90 F
X30 - 60 F60 F
X 85 - 120 F 95 F
X 0 - 5 ma 4 ma
X 5 - 20 ma 20 ma
X 0 - 9999 ppm 0 ppm
X 0 - 9999 ppm 2000 ppm
None/2-Position HW/1 Stage
Electric/Modulating HW
None
Normally
Closed
Normally
Closed
Occupied CLOSED
Alarm
CLOSED
Used to set number of
fan motor speeds
When set to Fan On, G output is energized when ever any fan speed is active (required for ECM and Fan
control board). When set to Fan
Low, output is only energized for
Set to Installed if factory-installed
Used to determine external occu-
pancy switch contact occupied state
Delay before equipment alarms on
acceptable water loop temperature
acceptable water loop temperature
acceptable water loop temperature
acceptable water loop temperature
Maximum output current (mA) for
Corresponding value in ppm for
Corresponding value in ppm for
Low Speed
Defines the number of stages of compression
Determines reversing valve
signal output type
Determines Auxiliary
Reheat Coil Type
Determines Entering Air
Economizer Coil Type
Determines type of 2-position
water valve used
Determines type of modulating
water valve used
Determines type of ventilation
damper control to be used
Used to determine ventilation
damper output signal range
(closed - open)
Set to Installed if humidity
sensor is present
dehumidification reheat coil
is present
high condensate level
Determine Alarm state of
condensate switch input
Determines the minimum
to start heating
Determines the maximum
to start heating
Determines the minimum
to start cooling
Determines the maximum
to start cooling
Minimum output current (mA)
for IAQ sensor
IAQ sensor
minimum output current
maximum output current
58
APPENDIX A — WSHP SCREEN OPEN CONFIGURATION (cont)

SCREEN NAME POINT NAME
SPT Occupied Alarm
Hysteresis
SPT Alarm Delay X 0 - 30 min per degree 10 min
SPT Unoccupied Low
Alarm Temperature
SPT Unoccupied High
Alarm Temperature
SAT Low SAT
Alarm Limit
SAT High SAT
Alarm Limit
Condensate Overflow
Alarm Delay
Space Humidity Occupied
High Alarm Limit
Configuration
Alarm
Configuration
Configuration
Linkage
BAS — Building Automation System DCV — Demand Controlled Ventilation IAQ — Indoor Air Quality OAT — Outdoor Air Temperature RH Relative Humidity SAT — Supply Air Temperature SPT — Space Temperature TPI Third Party Integration
Space Humidity Alarm
Delay
Space Humidity Unoccu-
pied High Alarm Limit
IAQ/Ventilation Occupied
High Alarm Limit
IAQ/Ventilation
Alarm Delay
Rnet Sensor SPT Alarm X Ignore/Display Ignore
Rnet Sensor SAT Alarm X Ignore/Display Ignore
Rnet Sensor Compressor
Lockout Alarm
Rnet Sensor Condenser
Water Temperature Alarm
Rnet Sensor Condensate
Overflow Alarm
Rnet Sensor Dirty
Filter Alarm
Rnet Sensor Space
High Humidity Alarm
Loop Control Network
Number
Loop Control Network
Address
Number of Linked Heat
Pumps
LEGEND
PASSWO RD
LEVEL
Admin Password level access only
EDITABLE RANGE DEFAULT NOTES
Defines the hysteresis applied above
X2 - 20 F5 F
X 35 - 90 F 45 F
X 45 - 100 F 95 F
X 15 - 90 F 45 F
X 90 - 175 F 120 F
X 5 - 600 sec 10 sec
X 45% - 100% 100%
X 0 - 30 min per % RH 5 min
X 45% - 100% 100%
X 0 - 9999 ppm 1100 ppm
X 0.1 - 1.0 min per ppm 0.25 min
X Ignore/Display Display
X Ignore/Display Display
X Ignore/Display Display
X Ignore/Display Display
X Ignore/Display Ignore
the cooling and below the heating set
points before an alarm condition will
Used to calculate the delay time before
an alarm is generated after the alarm
Defines the fixed unoccupied
Defines the fixed unoccupied
Defines the fixed minimum
Defines the fixed maximum
Defines the delay time before an alarm
is generated after the alarm condition
Defines the fixed occupied
high space RH alarm limit
Used to calculate the delay time before
an alarm is generated after the alarm
Defines the fixed unnoccupied
high space RH alarm limit
Defines the fixed occupied high
space IAQ/Ventilation alarm limit
Used to calculate the delay time before
an alarm is generated after the alarm
Determines if the SPT alarm is
displayed on the local Rnet sensor
Determines if the SAT alarm is
displayed on the local Rnet sensor
Determines if the Compressor Lockout
alarm is displayed on the local Rnet
Determines if the Condenser Water
Temperature alarm is displayed on the
Determines if the Condensate
Overflow alarm is displayed on the
Determines if the Dirty Filter alarm is
displayed on the local Rnet sensor
Determines if the High Space
RH alarm is displayed on the
occur
condition occurs
ow SPT alarm limit
high SPT alarm limit
SAT alarm limit
SAT alarm limit
occurs
condition occurs
condition occurs
sensor
local Rnet sensor
local Rnet sensor
local Rnet sensor
See TPI
See TPI
See TPI
59
Copyright 2010 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53500079-01 Printed in U.S.A. Form 50PT-4SI Pg 62 7-10 Replaces: 50PT-3SI
50PTH,PTV,PTD
START-UP CHECKLIST
CUSTOMER:___________________________ JOB NAME: _______________________________________
MODEL NO.:___________________________ SERIAL NO.:____________________ DATE:_________
I. PRE-START-UP
DOES THE UNIT VOLTAGE CORRESPOND WITH THE SUPPLY VOLTAGE AVAILABLE? (Y/N)
HAVE THE POWER AND CONTROL WIRING CONNECTIONS BEEN MADE AND TERMINALS TIGHT? (Y/N)
HAVE WATER CONNECTIONS BEEN MADE AND IS FLUID AVAILABLE AT HEAT EXCHANGER? (Y/N)
HAS PUMP BEEN TURNED ON AND ARE ISOLATION VALVES OPEN? (Y/N)
HAS CONDENSATE CONNECTION BEEN MADE AND IS A TRAP INSTALLED? (Y/N)
IS AN AIR FILTER INSTALLED? (Y/N)
II. START-UP
IS FAN OPERATING WHEN COMPRESSOR OPERATES? (Y/N)
IF 3-PHASE SCROLL COMPRESSOR IS PRESENT, VERIFY PROPER ROTATION PER INSTRUCTIONS. (Y/N)
UNIT VOLTAGE — COOLING OPERATION
PHASE AB VOLTS PHASE BC VOLTS PHASE CA VOLTS
(if 3 phase) (if 3 phase)
PHASE AB AMPS
PHASE BC AMPS PHASE CA AMPS
(if 3 phase) (if 3 phase)
CONTROL VOLTAGE
IS CONTROL VOLTAGE ABOVE 21.6 VOLTS? (Y/N) . IF NOT, CHECK FOR PROPER TRANSFORMER CONNECTION.
TEMPERATURES
FILL IN THE ANALYSIS CHART ATTACHED.
COAXIAL HEAT EXCHANGER
COOLING CYCLE: FLUID IN
FFLUID OUT F PSI FLOW
HEATING CYCLE: FLUID IN
FFLUID OUT F PSI FLOW
AIR COIL COOLING CYCLE:
AIR IN
HEATING CYCLE: AIR IN
FAIR OUT F
FAIR OUT F
CL-1
HEATING CYCLE ANALYSIS
a50-8449
SUCTION
COMPRESSOR
DISCHARGE
COAX
EXPANSION
VALVE
°F
°F
AIR
COIL
°F
PSI
FLUID OUT
FLUID IN
°F
PSI
°F
LIQUID LINE
PSI
°F
SAT
LOOK UP PRESSURE DROP IN TABLES 20-23 TO DETERMINE FLOW RATE
a50-8450
PSI
SAT
°F
AIR
COIL
°F
°F
LIQUID LINE
COOLING CYCLE ANALYSIS
EXPANSION
VALVE
°F
FLUID IN
°F
PSI
COAX
FLUID OUT
°F
PSI
LOOK UP PRESSURE DROP IN TABLES 20-23 TO DETERMINE FLOW RATE
SUCTION
COMPRESSOR
DISCHARGE
HEAT OF EXTRACTION (ABSORPTION) OR HEAT OF REJECTION =
FLOW RATE (GPM) x TEMP. DIFF. (DEG. F) x FLUID FACTOR* =
(Btu/hr)
SUPERHEAT = SUCTION TEMPERATURE – SUCTION SATURATION TEMPERATURE
=
(DEG F)
SUBCOOLING = DISCHARGE SATURATION TEMPERATURE – LIQUID LINE TEMPERATURE
=
*Use 500 for water, 485 for antifreeze.
Copyright 2010 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53500079-01 Printed in U.S.A. Form 50PT-4SI Pg CL-2 7-10 Replaces: 50PT-3SI
(DEG F)
CUT ALONG DOTTED LINE CUT ALONG DOTTED LINE
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - -
Loading...