Number One
Air(3onditoning
Maker
e
Division of Carrier Corporation
Carrier Parkway • Syracuse NY 13201
Air-Cooled Condensing Units
Table 1 — Physical Data
INTRODUCTION
The 38GK condensing units are designed for
use with Carrier approved evaporator coils or fan
coils which have capillary tube or AccuRater
refrigerant control. They may also be used with
evaporators which have expansion valves that
equalize pressure during the off cycle. If an
expansion valve without pressure equalization fea
ture is used, add an accessory start capacitor kit to
condensing unit.
Install these condensing units either thru-thewall, outdoors on a slab or on the roof. When
installing units, allow sufficient space for air-flow
clearance, wiring, refrigerant piping and servicing
units. Consult local building codes and National
Electrical Code (NEC) for special installation re
quirements. See Fig. 1 and Tables 1 and 2 for
detailed unit installation data.
COND UNIT
OPER WT (lb)
R-22 CHG (Ib-oz)
COND FAN
D i scharge
Motor Hp
Rpm
Diom + Width (in.)
DIM. (ft-in.)
Length
Width
Height _
CONN.* (in.)
Suction (ODF)
Liquid (ODF)
*Units are equipped with Carrier Compatible Fittings for refrig
erant connections
SS^GKOOl 38GK002 38GK003
144 __ 162
____
186
2j3 _ .3^5 ~ 4Ì3
Twin Centrifugal Biowers —
Direct Drive
Hori zontal
V4
1550
6^6+514
2-2Va
1- 4%
2- 4%
%
Table 2 — Installation Data (ft-in.)
COND UNIT ! 38GK001 | 38GK002 ] 38GK003
THRU-THE-WALL
CLEARANCE DIM.
AIR CLEARANCE
CONCRETE MOUNTING
PAD DIMENSIONS
SERVICE
CLEARANCE
"Units are serviced from rear access panel Therefore, units can be
installed with 0-in end clearance
1/ A I I
Ends
Bock
2-2% X 2-5
3-0
2-3 X 1-5 X 0-5
0*
1-6*
%
%
Certified aimensionarawlngs available oh request ..................................
..............................................
..
Fig. 1 — Dimensions and Connections
© Carrier Corporation 1976 Foim 38GK-4SI
INSTALLATION
Mounting Thru-The-Wall
An opening approximately 26-1/2 x 29 in. shall
be made in a wall as close to a nearby cooling coil
as possible. Refer to Fig. 2 to build a frame in a
manner to support the condensing unit.
1. Locate unit with frame into the opening until
the unit extends approximately 1 in. beyond
the outside (finished) wall.
2.
Tilt to the front to allow the water to drain off.
See Fig. 3.
3.
Fasten the unit to the frame with metal straps.
4.
Use flashing under the unit and caulk all edges
to provide a weathertight seal (Fig. 3).
Fig. 3 — Flush or Recess Mounting
Fig. 2 — Roughing-ln Supporting Frame
REFRIGERANT LINE SIZING
Selection of Correct Liquid Line — See Table 3 for
maximum allowable vertical and horizontal dis
tance between condensing unit and evaporator
using recommended 3/8-in. liquid line.
Selection of the Correct Suction Line Diameter —
To keep line losses at a minimum, refer to Table 4
to select the correct suction line diameters.
Table 3 — Recommended Liquid Line Sizes
MAX COND*
COND
UNIT
38GK001 40
38GK002 40
38GK003
*Decrease maximum allowable vertical separation by 20% for
every 10 ft of refrigerant line length over 100 feet At 150 ft of
line length, 0 ft vertical separation is allowed
UNIT HT (ft)
40
Below
Evap
50
70
60
Above
Evap
Crankcase heater required
REFF
0-49
Liqu
%
Table 4 — Recommended Suction Line Diameters
UNIT
38GK001 (All)
38GK002 (All)
38GK003 201
38GK003
*Field-supplied 7/8-in to 3/4-in adapter is required
NOTE
The above table is based on a line loss of 2 F Longer lengths can
be used in each diameter listed, but the result will be larger line
losses Refer to Carrier, Syracuse Engineering Office for specific
details
MODEL
301
SUCTION LINE
LENGTH (ft)
0
46
47 - 120
150
121 -
0 - 28
29 - 72
150
73 -
19
0 -
52
20 -
116
53 -
0 - 18
48
19 -
107
49 -
SUCTION LINE
DIAMETER (in.)
=/b
%
Vb*
%
Vb
Vb*
V
/4
V
'A
7/*
%
%
Vb*
INSTALLING REFRIGERANT LINES
General — The condensing unit is fully charged at
the factory. Be sure both service valves are frontseated (turned clockwise) to avoid loss of the
charge. Do not remove refrigerant line connection
seals from the condensing unit, the matching coil,
nor the refrigerant tubing, until ready to make the
actual connection at the point of seal.
If accessory tubing package or evaporator coil
has been open for more than 15 seconds per
connection, evacuate or purge evaporator coil and
tubing system (use field-supplied refrigerant, not
unit refrigerant). Always evacuate or purge if
field-supplied tubing is used. See Purging.
Ensure field-supplied tubing is of refrigerant
grade. Insulate the suction line with insulation that
has an adequate vapor barrier (Armaflex or
Ensolex). Evacuate tubing.
When a complete Carrier system is used, a
filter-drier is not required. However, if other than
Carrier accessory tubing package or evaporator is
used, or if refrigerant tubing or coil is exposed to
atmospheric conditions for longer than 10 minutes,
install a filter-drier in the system near evaporator
coil. Additional refrigerant must be added to the
system to compensate for the additional volume of
the filter-drier.
Installation
1. Run refrigerant lines as directly as possible,
avoiding all unnecessary turns and bends.
2. Tape the liquid line to the top of the insulated
suction line for support.
3. Suspend the refrigerant lines so that they do
not damage the insulation on the suction line
and do not transmit vibration to the structure.
4. If the refrigerant lines are too long, the lines
should be rolled into a loop and placed in a
horizontal plane, or the excess may be cut off.
5. Check to be sure both service valves are
frontseated (turned clockwise). It is necessary
to remove the valve stem caps to check.
6. Connect tubing to the condensing unit. The
refrigerant tubing and evaporator coil should be
leak tested upon completion.
Connection Procedure — When making piping
connections, be sure to provide clearance at unit
for electrical connections.
Connect refrigerant liquid and suction lines to
condensing unit. Fig. 1 (page 1). Unit Compatible
Fittings permit 2 methods of refrigerant line
connection: mechanical (quick connect) or sweat
connection. Make suction line connection first.
MECHANICAL CONNECTION (Mate one set of
connections at a time.)
1. Loosen nut on Compatible Fitting one turn. Do
not remove.
2. Remove plug and be sure 0-ring is in the groove
inside the Compatible Fitting.
3. Cut tubing to correct length.
4. Insert tube into Compatible Fitting until it
bottoms. Be sure tube is bottomed while nut is
being tightened.
5. Tighten nut until it bottoms on back coupling
flange.
SWEAT CONNECTION (Use refrigerant grade
tubing.)
1. Remove locking nut, rubber 0-ring and
Schrader core from valve.
2. Cut tubing to correct length.
3. Insert tube into Compatible Fitting. Wrap top
and bottom of service valves in wet cloth to
prevent damage by heat. Solder with lowtemperature (450 F) silver alloy solder.
4. Replace Schrader core.
5. Evacuate or purge system with field-supplied
refrigerant.
Leak Testing
No installation is complete until all field and
factory joints have been checked for leaks.
1. Remove the valve stem caps from both service
valves and check to be sure the valves are
frontseated (turned clockwise). Remove the
service port caps.
2. Attach a gage manifold to service ports of the
service valves and purge the hoses.
3. Pressurize the evaporator coil and the inter
connecting refrigerant tubing with vapor from
an external refrigerant cylinder of R-22 until
the system and cylinder pressures are equalized.
NOTE: NEVER USE A UNIT CHARGE FOR
LEAK TESTING.
4. Leak test with an electronic detector, a halide
torch, or a liquid soap solution.
5. Release the pressure and repair any leaks found.
6. If the system is to be purged or evacuated, leave
the service valves in the frontseated position.
7. If the system is free of leaks, you may then
prepare the unit for operation by:
a. Backseating (turn counterclockwise) both
service valves.
b. Removing the gage manifold.
c. Replacing the caps on the service port and
valve stem.
Purging — To purge unit, do not use the unit
charge Proceed as follows:
1. Remove the valve stem caps from both service
valves and check the valve stems to be sure they
are frontseated (clockwise).
2. Remove the service port caps from both service
valves and connect a refrigerant cylinder of
R-22 to the service port of the liquid line
service valve.
3. Open the refrigerant cylinder valve and allow
approximately 1/2 to 1 pound of refrigerant to
flow thru the system and out the service port
on the suction line service valve.