Installing, starting up, and servicing air-conditioning equipment can be hazardous due to system pressures, electrical
components, and equipment location (roofs, elevated structures, etc.).
Only trained, qualified installers and service mechanics
should install, start-up, and service this equipment (Fig. 1).
Untrained personnel can perform basic maintenance functions such as cleaning coils. All other operations should be
performed by trained service personnel.
When working on the equipment, observe precautions in
the literature and on tags, stickers, and labels attached to the
equipment.
Follow allsafetycodes.Wear safetyglassesandworkgloves.
Keep quenching cloth and fire extinguisher nearby when brazing. Use care in handling, rigging, and setting bulky equipment.
ELECTRIC SHOCK HAZARD
Separate power sources (main and control
power circuits) are used for these units. Be
sure both main and control power circuits are
disconnected before servicing.
INSTALLATION
Step 1 — Complete Pre-Installation Checks
UNCRATE UNIT — Remove unit packaging except for the
top skid assembly, which should be left in place until after
the unit is rigged into its final location.
INSPECT SHIPMENT — File claim with shipping company if shipment is damaged or incomplete.
CONSIDER SYSTEM REQUIREMENTS
• Consult local building codes and National Electrical Code
(NEC, U.S.A.) for special installation requirements.
• Allow sufficient space for airflow clearance, wiring,
refrigerant piping, and servicing unit. See Fig. 1. See
Fig. 2 for unit component locations.
• Locate unit so that outdoor coil (condenser) airflow is un-
restricted on all sides and above.
• Unit may be mounted on a level pad directly on the base
channels or mounted on raised pads at support points. See
Tables1A-1Dforunitoperatingweights.See
T able2forweightdistributionbasedonrecommendedsupport points.
NOTE: If vibration isolators are required for a particular
installation, use the data in Table 2 to make the proper
selection.
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 1 4
Tab 3a 2a
PC 111Catalog No. 563-701Printed in U.S.A.Form 38AKS-3SIPg 19-98Replaces: 38AKS-2SI
Page 2
NOTE: Service areas — Allow 3 ft (914 mm) on both sides and 2 ft (610 mm)
on both ends of unit for servicing.
2
Fig. 1 — Dimensions
Page 3
1324567
1291011
LEGEND
1—No. 1 Fan5—No. 2 Fan9—Compressor
2—High-Pressure Switch6—Terminal Block 1 (Unit Power)10 — Low-Pressure Switch
3—Circuit Breaker — Control Circuit7—Terminal Block 2 (Control Power)11 — Hot Gas Bypass Piping Stub (
4—Circuit Breakers — Power Circuits8—Wraparound Coil12 — Muffler
Fig. 2 — Component Locations (Typical)
8
3
⁄8-in. ODM)
3
Page 4
Table 1A — Physical Data (English, 60 Hz)
UNIT 38AKS013014016024
OPERATING WEIGHT (lb)
With Aluminum-Fin Coil732779789900
With Copper-Fin Coil8259199291040
Be sure unit panels are securely in place prior to
rigging.
RIGGING — These units are designed for overhead rigging
only. For this purpose, the transverse base channels extend
beyond the sides of the unit, with holes provided in the end
plates to attach cables or hooks. Rig with top skid packaging
assembly in place to prevent unit damage by the rigging cable.
As further protection for the coil faces, plywood sheets can
be placed against the sides of the unit, behind the cables.
Run the cables to acentral suspension point so that the angle
from the horizontal is not less than 45 degrees. Raise and set
the unit down carefully.
If it is necessary to roll the unit into position, mount
the unit on longitudinal rails, using a minimum of 3 rollers.
Apply force to the rails, not the unit. If the unit is to be skidded into position, place it on a large pad and drag it by the
pad. Do not apply any force to the unit.
Raise from above to lift unit from the rails or pad when
unit is in final position.
COMPRESSOR MOUNTING — As shipped, the compressor is held tightly in place by self-locking bolts. Before start-
ing unit, loosen self-locking bolts until the snubber washer
can be moved sideways with finger pressure. Do not
remove shipping bolts. See Fig. 3.
Step3—CompleteRefrigerantPiping
Connections
IMPORTANT:A refrigerant receiver is not provided with
the unit. Do not install a receiver.
SIZE REFRIGERANT LINES — Consider the length of piping required between outdoor unit and indoor unit (evaporator), the amount of liquid lift, and compressor oil return.
See Tables 3-5B and also refer to Part 3 of Carrier System
Design Manual and E20-IIt software for design details and
line sizing. Refer to indoor unit installation instructions for
additional information.
NOTE: Use the piping data in Tables3-5Bas a general guide
only. For more precise calculations, refer to Carrier System
Design manual or E20-II software.
Condensing units with multiple-step unloading mayrequire double suction risers to assure proper oil return at
minimum load operating condition. See Tables 4A-5B and
Fig. 4. Reduction of evaporator coil surface should be analyzed to provide sufficient refrigerant velocity to return oil
to the compressor. Liquid line solenoid valves may be used
in certain situations to accomplish this. Hot gas bypass, if
used, should be introduced before the evaporator.
Note that refrigerant suction piping should be insulated.
Table 3 — Liquid Line Data
MAXIMUM
ALLOWABLE
LIQUID LIFT
UNIT
38AKS
01352 (15.8)
01467 (20.4)
01682 (25.0
02487 (26.5) 86 (26)
*Inlet and outlet.
NOTE: Data shown is for units operating at 45 F (7.2 C) saturated
suction and 95 F (35 C) entering air.
ft (m)
60 Hz50 Hz
Maximum
Allowable
Pressure
Drop
psig (kPa)
7 (48.3)2 (1.1)
LIQUID LINE
Maximum
Allowable
Temp.
Loss
F (C)
Filter Drier
and
Sight Glass
Flare Conn.*
in. (mm)
5
⁄8(15.88)
Fig. 3 — Compressor Mounting
8
Page 9
Table 4A — Refrigerant Piping Sizes — 60 Hz Units
Table 5A — Refrigerant Piping Sizes — 50 Hz Units
LENGTH OF INTERCONNECTING PIPING, FT (M)
UNIT
38AKS
0-15
(0-4.5)
15-25
(4.5-7.5)
Line Size (in. OD)
25-50
(7.5-15)
50-75
(15-23)
75-100
(23-30)
LSLSLSLSLS
1
013
0141⁄211⁄
016
0245⁄815⁄
⁄211⁄
1
⁄213⁄
8
8
8
8
1
⁄211⁄
1
⁄213⁄
5
⁄813⁄
5
⁄815⁄
5
8
⁄813⁄
5
8
⁄813⁄
5
8
⁄815⁄
7
8
⁄815⁄
5
8
⁄813⁄
8
5
8
⁄815⁄8*7⁄815⁄8*
7
8
⁄815⁄
8
7
8
⁄821⁄
8
5
⁄815⁄8*
7
⁄821⁄8*
7
⁄821⁄
8
LEGEND
L—Liquid
S—Suction
Close-coupled.
*Requires a double suction riser if 2 unloaders are used and the
evaporator is below the condensing unit. See Table 4B and Fig. 4
for more information.
NOTES:
1. Pipe sizes are based ona2F(1.1 C) loss for liquid lines and a
1.5 F (0.8 C) loss for suction lines.
2. Pipe sizes are based on an equivalent length equal to the maximum lengthof interconnecting pipingplus50% for fittings.Amore
accurate estimate may result in smaller sizes.
3. Line size conversion to mm:
in.mm
1
⁄
2
5
⁄
8
7
⁄
8
11⁄
8
3
1
⁄
8
15⁄
8
21⁄
8
12.7
15.9
22.2
28.6
34.9
41.3
54.0
Table 4B — Refrigerant Piping Sizes,
Double Suction Risers — 60 Hz Units
LENGTH OF INTERCONNECTING PIPING, FT (M)
UNIT
38AKS
50-75
(15-23)
Line Size (in. OD)
ABCABC
013———1
01411⁄
016———1
NOTES:
1. See Fig. 4 for ‘‘A,’’ ‘‘B,’’ and ‘‘C’’ dimensions.
2. No double suction risers are needed for unit size 024.
rator is belowthecondensingunit. See Table 5B andFig.4for more
information.
NOTES:
1. Pipe sizes are based on 2 F (1.1 C) max loss for liquid lines and
2. Pipe sizes are based on an equivalent length equal to the maxi-
3. See Table 4A for line size conversion to mm.
⁄211⁄
5
⁄813⁄
1.5F(0.8 C)maxloss for suctionlines, selected atmaximum length
for each interval and for matched systems at nominal rating conditions, nominal airflow.
mum length ofinterconnectingpipingplus 50% for fittings.Amore
accurate estimate may result in smaller sizes.
1. See Fig. 4 for ‘‘A,’’ ‘‘B,’’ and ‘‘C’’ dimensions.
2. Double suction risers are not required for unit size 024.
3. See Table 4A for line size conversion to mm.
50-75
(15-23)
Line Size (in. OD)
75-100
(23-30)
1
⁄813⁄815⁄
8
8
8
LEGEND
Suction Riser
Suction Riser
Without
With
Trap
Trap
Suction Line to Condensing Unit
Short Vertical Riser Into
Condensing Unit:
38AKS013— 1
38AKS014,016 — 1
38AKS024— 1
1
⁄8in. OD
3
⁄8in. OD
5
⁄8in. OD
Fig. 4 — Suction Line Piping
9
Page 10
INSTALL FILTER DRIER(S) AND MOISTURE INDICATOR(S) — Every unit should have a filter drier and liquidmoisture indicator(sightglass).Insome applications, depending
on space and convenience requirements, it may be desirable
to install 2 filter driers and sight glasses. One filter drier and
sight glass may be installed at A locations in Fig. 5. Or, 2
filter driers and sight glasses may be installed at B locations.
Select the filter drier for maximum unit capacity andminimum pressure drop. Complete the refrigerant piping from
indoor unit to outdoor unit before opening the liquid and suction lines at the outdoor unit.
2. Remove
1
⁄4-in. flare cap from liquid valve Schrader port.
3. Attach refrigerant recovery device and recover holding
charge.
4. Remove runaround loop.
5. Install a field-supplied liquid moisture indicator in the piping immediately leaving outdoor unit.
6. If necessary, install field-supplied thermostatic expansion valve(s) (TXVs) in air handler.
If 2 TXVs are installed and two-step cooling is desired,
install field-supplied liquid line solenoid valve ahead of the
upper TXV (see Fig. 5).
PROVIDE SAFETY RELIEF — A fusible plug is located
on the compressor crankcase or in the liquid line (Fig. 6).
Do not cap this plug. If local code requires additional safety
devices, install them as directed.
TXV — Thermostatic Expansion Valve
Fig. 5 — Location of Sight Glass(es)
and Filter Drier(s)
INSTALL LIQUID LINE SOLENOID VALVE — SOLENOID DROP — It is recommended that a solenoid valve be
placed in the main liquid line (see Fig. 5) between condensing unit (38AKS) and fan coil (40RM, 39 Series). (A liquid
line solenoid valve is required when the liquid line length
exceeds 100 ft [30.5 m] or when the condensing unit is connected to a chiller barrel in a built-up chiller system.) This
valve prevents refrigerant migration (which causes oil dilution) to the compressor during the off cycle at low outdoor
ambient temperatures. The solenoid should be wired in parallel with the compressor contactor coil. This means of electrical control is referred to as solenoid drop control.
INSTALL LIQUID LINE SOLENOID VALVE (Optional)
— CAPACITY CONTROL — If 2-step cooling is desired,
place a solenoid valve in the location shown in Fig. 5.
MAKE PIPING CONNECTIONS — Do not remove runaround loop from suction and liquid line stubs in the compressor compartment until piping connections are ready to
be made. Pass nitrogen or other inert gas through piping while
brazing to prevent formation of copper oxide.
Recover holding charge prior to removal of runaround
piping loop.
NOTE: 38AKS024 has a fusible plug in the liquid line.
Fig. 6 — Location of Fusible Plug (38AKS)
Step 4 — Install Accessories — Field install
accessories such as winter start control or low-ambient control before proceeding with wiring. Refer to the instructions
shipped with the accessory.
Step 5 — Complete Electrical Connections
POWER WIRING — Unit is factory wired for voltage shown
on nameplate. Provideadequatefuseddisconnectswitchwithin
sight from unit and readily accessible from unit, but out of
the reach of children. Lock switch open (off)topreventpower
from being turned on while unit is being serviced. Disconnect switch, fuses, and field wiring must comply with
national and local code requirements. SeeTables 6A and 6B.
Route power wires through opening in unit end panel to
connection in unit control box as shown on unit label diagram and in Fig. 7. Unit must be grounded.
Affix crankcase heater warning sticker to unit disconnect
switch.
CONTROL CIRCUIT WIRING — Control voltage is 24 v.
See Fig. 8 and unit label diagram for field-supplied wiring
details. Route control wires through opening in unit end panel
to connection in unit control box.
1. Open service valves:
a. Discharge service valve on compressor.
b. Suction service valve on compressor.
c. Liquid line valve.
10
Page 11
LEGEND
EQUIP GND — Equipment Ground
NEC— National Electrical Code
Factory Wiring
Field Wiring
Fig. 7 — Main Power Supply Wiring
Table 6A — Electrical Data (3 Ph/60 Hz)
UNITCOMPRFAN MOTORS (Single Phase)
LEGEND
Volts
Supplied*
MinMax12
MCAICF
UNIT
38AKS
013
014
016
024
FLA— Full Load Amps (Fan Motors)
ICF— Maximum Instantaneous Current Flow during start-up
kW— Total Fan Motor Input (kilowatts)
LRA— Locked Rotor Amps
MCA— Minimum Circuit Amps per NEC (U.S.A.),
LLSV2 — Liquid Line Solenoid Valve 2 — Capacity Control
R—Relay
NOTES:
1. Combination LLSV plus IFC va should not exceed 30 va.
2. Do not exceed 5 va (24 vac) per coil.
3. If va values shown in Notes 1 and 2 must be exceeded, use
accessory relay transformer package 38AE900001 (60 Hz) or
38AD900003 (50 Hz and 380-3-60).
Control
Factory Wiring
Field Wiring
LEGEND
Fig. 8 — Remote Thermostat Wiring
MOCP
(Fuse
Only)
RLALRA
*Units are suitable for use on electrical systems where voltage sup-
plied to the unit terminals is not below or above the listed limits.
NOTES:
1. The MCA and MOCP values are calculated in accordance
with the National Electrical Code (NEC) article 440 (U.S.A.
standard).
2. Motor RLA and LRA values are established in accordance
with Underwriters’ Laboratories (UL) Standard 1995 (U.S.A.
standard).
Total
Fans
2
2
2
2
FLA (ea)
Fan No.
4.33.7
4.33.7
4.33.7
4.33.7
kW
1.41
1.41
1.41
1.41
11
Page 12
Table 6B — Electrical Data (3 Ph/50 Hz)
UNITCOMPRFAN MOTORS 230 v (Single Phase)
UNIT
38AKS
013
014
016
024
FLA— Full Load Amps (Fan Motors)
ICF— Maximum Instantaneous Current Flow during start-up
kW— Total Fan Motor Input (kilowatts)
LRA— Locked Rotor Amps
MCA— Minimum Circuit Amps per NEC (U.S.A.),
*Units are suitable for use on electrical systems where voltage sup-
plied to the unit terminals is not below or above the listed limits.
NOTES:
1. The MCA and MOCP values are calculated in accordance
with the National Electrical Code (NEC) article 440 (U.S.A.
standard).
2. Motor RLA and LRA values are established in accordance
with Underwriters’ Laboratories (UL) Standard 1995 (U.S.A.
standard).
Total
Fans
22.93.51.20
22.93.51.20
22.93.51.20
22.93.51.2030334631138051.51218033.3115
FLA (ea)
Fan No.
kW
PRE-START-UP
IMPORTANT: Before beginning Pre-Start-Up or
Start-Up, review Start-Up Checklist at the back of this
book. The Checklist assures proper start-up of a unit
and provides a record of unit condition,application requirements, system information, and operation at initial start-up.
Do not attempt to start the condensing unit, even
momentarily, until the following steps have been completed. Compressor damage may result.
System Check
1. Check all air handler(s) andotherequipmentauxiliarycomponents. Consult the manufacturer’s instructions regarding any other equipment connected to the condensing unit.
If unit has field-installed accessories, be sure all are properly installed and correctly wired. If used, airflow switch
must be properly installed.
2. Backseat (open) compressor suction and discharge valves.
Now close valves one turn to allow refrigerant pressure
to reach test gages.
3. Open liquid line service valve.
4. Check tightness of all electrical connections.
5. Compressor oil level should be visible in sight glass. See
Fig. 9. Adjust the oil level as required. Refer to Preliminary Oil Charge section. No oil should be removed
unless the crankcase heater has been energized for at least
24 hours.
6. Be sure unit is properly leak checked, dehydrated, and
charged. See Preliminary Charge, this page.
7. Electrical power source must agree with nameplate
rating.
8. Crankcase heater must be firmly locked into compressor
crankcase. Be sure crankcase is warm (heater mustbe on
for 24 hours before starting compressor).
9. Be sure compressor floats freely on the mounting springs
and that snubber washers can be moved with finger pressure. See Compressor Mounting, page 8, and Fig. 3 for
loosening compressor bolts.
Leak Test and Dehydration — Leak test the entire
refrigerant system using soap bubbles and/or an electronic
leak detector. Evacuate and dehydrate entire refrigerant system by use of methods described in GTAC II, Module 4,
System Dehydration.
T urnOn Crankcase Heater — Turnoncrankcaseheater
for 24 hours before starting the unit to be sure all the
refrigerantis out of the oil. Toenergizethecrankcase heater,
proceed as follows:
1. Set the space thermostat set point above the space temperature so there is no demand for cooling.
2. Close the field disconnect.
3. Turn the fan circuit breaker on. Leave the compressor circuit breakers off. The crankcase heater is now
energized.
Preliminary Charge — Refer to GTAC II, Module 5,
Charging, Recovery, Recycling, and Reclamation for charging methods and procedures. Charge each system with R-22
by the liquid charging method (through liquid service valve)
on the high side. Charge according to the values in the
Charging Chart, Fig. 10, 11, or 12.
12
Page 13
START-UP
Compressor crankcase heater must be on for 24 hours
before start-up. After the heater has been on for 24 hours,
the unit can be started. If no time has elapsed since the preliminary charge step has been completed, it is unnecessary
to wait the 24-hour period.
Preliminary Checks
1. Ensure that compressor service valves are backseated.
2. Verify that each compressor floats freely on its mounting
springs.
3. Check that electric power supply agrees with unit name-
plate data.
4. Verify that compressor crankcase heater is securely in place.
5. Check that compressor crankcase heater has been on at
least 24 hours.
6. Note that compressor oil level isvisible in the sight glass.
7. Recheck for leaks using same procedure as pre-
viously outlined in Pre-Start-Up section, Leak Test and
Dehydration.
8. If any leaks are detected, evacuate and dehydrate as pre-
viously outlined in Pre-Start-Up section, Leak Test and
Dehydration.
9. All internal wiring connections must be tight, and all bar-
riers and covers must be in place.
Preliminary Oil Charge — Compressor is factory
charged with oil (see Tables 1A-1D). When oil is checked at
start-up, it may be necessary to add or remove oil to bring
it to the proper level. One recommended oil level adjustment method follows:
ADD OIL — Close suction service valve and pump down
crankcase to 2 psig (14 kPag). (Low-pressure switch must
be jumpered.) Wait a few minutes and repeat until pressure
remains steady at 2 psig (14 kPag). Remove oil fill plug above
the oil level sight glass, add oil through plug hole, and
replace plug. Run compressor for 20 minutes and check oil
level. See Fig. 9.
NOTE: Use only Carrier approved compressor oil. Approved sources are:
Petroleum Specialties Inc. ................Cryol 150A
Texaco, Inc. .........................Capella WF-32
Witco Chemical Co. .....................Suniso 3GS
Do not use oil that has been drained out, or oil that has
been exposed to atmosphere.
REMOVE OIL — Pump down compressor to 2 psig
(14 kPag). Loosen the
pressor base and allow the oil to seep out past the threads
of the plug.
NOTE: The crankcase will be slightly pressurized. Do not
remove the plug, or the entire oil charge will be lost.
Small amounts of oil can be removed through the oil pump
discharge connection while the compressor is running.
1
⁄4-in. (6.4 mm) pipe plug at the com-
Never charge liquid into the low-pressure side of system. Do not overcharge. During charging or removal of
refrigerant, be sure indoor-fan system is operating.
Adjust Refrigerant Charge
NOTE: Actual start-up and all refrigerant charge modifications should be done only under supervision of a qualified
refrigeration mechanic.
With all fans operating, adjust the refrigerant charge in
accordance with the unit charging charts located on the
inside of the control box doors and in Fig. 10-12.
Measure pressure at the liquid line service valve, being
sure Schrader depressor is used if required. Also, measure
liquid line temperature as close to the liquid service valve as
possible.Add chargeuntil the pressure and temperature conditions of the charging chart curve are met. If liquid pressure
and temperature point fall above curve, add charge. If liquid
pressure and temperature point fall below curve, reduce the
charge until the conditions match the curve.
If the sight glass is cloudy, check refrigerantchargeagain.
Ensure all fans are operating. Also ensure maximum
allowable liquid lift has not been exceeded. If charged per
chart and if the sight glass is stillcloudy, check fora plugged
filter drier or a partially closed solenoid valve. Replace or
repair, as needed.
Check Compressor Oil Level— After adjusting the
refrigerant charge, allow the compressor to run fully loaded
for 20 minutes. Running oil level should be within view of
the crankcase sight glass. Stop the compressor at the field
power supply disconnect and check the crankcase oil level.
Add oil only if necessary to bring the oil into view in the
sight glass. If oil is added, run the compressor for an additional 10 minutes, then stop and check oil level. If the level
remains low, check the piping system for proper design for
oil return; also, check the system for leaks.
If the initial check shows too much oil (too high in the
sight glass) remove oil to proper level. See Preliminary Oil
Charge, this page, for proper procedure for adding and
removing oil. See Fig. 9.
When the above checks are complete, repeat the procedure with the unit operating at minimum load conditions.
Unload the compressor by turning the control set point
adjustment nut counterclockwiseuntiltheadjustmentnutstops.
The unloader is now at 0 psig (0 kPag) set point. If electric
actuated unloaders are installed, energize the solenoid to unload the compressor.
Return unloader to original setting after checks are
complete.
Start Unit — The field disconnect is closed, the fan cir-
cuit breaker is closed, and the space thermostat is set above
ambient so that there is no demand for cooling. Only the
crankcase heater will be energized.
Next, close the compressor circuit breaker and then reset
space thermostat below ambient so that a call for cooling is
ensured. If compressor does not start, set thermostat lower.
NOTE: Do not use circuit breaker to start and stop the compressor except in an emergency.
After starting, there is a delay of at least 3 seconds before
compressor starts.
38AKS02438AKS013,014,016
(06E COMPRESSOR)(06D COMPRESSOR)
Fig. 9 — Operating Oil Levels
Final Checks — Ensure all safety controls are operat-
ing, control panel covers are on, and the service panels are
in place.
13
Page 14
14
Fig. 10 — 38AKS013 and 38AKS024 Charging Chart
Page 15
15
Fig. 11 — 38AKS014 Charging Chart
Page 16
16
Fig. 12 — 38AKS016 Charging Chart
Page 17
OPERATING SEQUENCE
Cooling—
mostat closes, the timer starts. After approximately
3 seconds, the timer expires, energizing the compressor and
fan motor no. 1. When the liquid pressure builds to approximately 257 psig (1772 kPa), fan motor no. 2 is energized.
On demand for additional cooling capacity, the second stage
(TC2) of the cooling thermostat closes, energizing a fieldsupplied liquid line solenoid (LLS) valve, whichopens.This
increases the suction pressure, causing the compressor to
operate at higher capacity.
When fan switch is set at AUTO,theindoor unit fan cycles
with the compressor. When the switch is set at ON, the
indoor unit fan runs continuously.
At shutdown, the Time Guardt II timer prevents the compressor from restarting for approximately 5 minutes.
When installed, a field-supplied solenoid valve (wired in
parallel with the compressor contactor coil), shuts off the liquid line to prevent refrigerant migration back to the compressor during the off cycle.
When the first stage (TC1) of the cooling ther-
Heating— The heating thermostat (TH) energizes a field-
supplied relay which operates heating controls and energizes the indoorunitrelay. When the fan switch issetatAUTO,
the indoor unit fan cycles with the heating control. The
indoor unit fan runs continuously when the fan switch is set
at ON.
Causes of complete unit shutdown are: interruption of supplied power, open compressor internal protector (IP), open
control circuit breaker,oranopenhigh-orlow-pressuresafety
switch.
PRESSURE DIFFERENTIAL (difference between cylinder
load and unload points) is adjustable from 6 to 22 psig
(41.4 to 152 kPag). To adjust, turn pressure differential adjustment screw (Fig. 13) counterclockwise to its back stop
position. In this position, differential is 6 psig (41.4 kPag).
Next, turn adjustment clockwise to desired pressure differential setting. Every full turn clockwise increases differential by 1.5 psig (10.3 kPag).
Head Pressure Control — Fan cycling is a standard
feature. The no. 2 fan cycles in response to changes in liquid
pressure. The switch cycles the fan off at 160 ± 10 psig
(1103 ± 69 kPa) as pressure decreases, and cycles it back on
at 255 ± 10 psig (1758 ± 69 kPa).
Fan Cycling — Head pressure control is accomplished
by cycling the fans. The no. 2 fan responds to liquid line
pressure, cycling on at approximately 255 psig (1758 kPa)
and off at approximately 160 psig (1103 kPa).
WinterStart Control (If Installed) — When thecom-
pressor starts, the control’s bypass timer contacts close for
150 seconds, thereby bypassing the low-pressure switch during start-up. After 150 seconds, the bypass timer contacts
open and the low-pressure switch is restored to the safety
circuit.
SERVICE
Capacity Control —
unloader controls 2 cylinders and provides capacity control.
Unloaders are factory set (see Tables 1A-1D), but can be
field adjusted as described in the 2 following sections.
CONTROL SET POINT (cylinder load point) is adjustable
from 0 to 85 psig (586 kPa). To adjust, turn control set point
adjustment nut (Fig. 13) clockwise to its bottom stop. In this
position, set point is 85 psig (586 kPa). Next, turn adjustment counterclockwise to desired control set point. Every
full turn counterclockwise decreases set point by 7.5 psig
(51.7 kPa).
A suction pressure-actuated
Fig. 13 — Compressor Capacity Control Unloader
Time Guard II Circuit — Circuit prevents short-
cycling by providing a delay of approximately 5 minutes
before restarting compressor after shutdown from safety
device action.
On start-up, the Time Guard II timer causes a delay of
approximately 3 seconds after thermostat closes.
On compressor shutdown, the timer recycles for approximately 5 minutes. During this time, the compressor cannot
restart.
Refer to Fig. 14 and to label diagram on unit.
Fig. 14 — Timer Sequence Chart
17
Page 18
Winter Start Control (If Required) — Install Ac-
cessory Package 38AE900021.
Crankcase Heater — The heater prevents refrigerant
migration and compressor oil dilution during shutdown whenever compressor is not operating. It is wired to cycle with
the compressor; the heater is off when compressor is running, and on when compressor is off.
Both compressor service valves must be closed whenever
the crankcase heater is deenergized for more than 6 hours.
The crankcase heater is operable as long as the control circuit is energized.
Compressor Protection
CIRCUIT BREAKER — Calibrated trip manual reset, ambient compensated, magnetic breaker protects against motor
overload and locked rotor conditions.
COMPRESSOR OVER TEMPERATUREPROTECTION(IP)
— A thermostat installed on compressor motor winding
reacts to excessively high winding temperatures and shuts
off the compressor.
TIME GUARDt II CONTROL — Control prevents compressor from short cycling. See Operating Sequence.
CRANKCASE HEATER — Heater minimizes absorptionof
liquid refrigerant by oil in crankcase during brief or extended shutdown periods. The control circuit is maintained
if compressor fan motor circuit breakers are turned off. The
main disconnect must be on to energize crankcase heater.
IMPORTANT: Never open any switch or disconnect
that energizes the crankcase heater unless unit is being
serviced or is to be shut down for a prolonged period.
After a prolonged shutdown on a service job, energize
the crankcase heater for 24 hours before starting the
compressor.
High-Pressure Switches — Switches have fixed,
nonadjustable settings. Switches are mounted on the
compressors.
Low-Pressure Switches — Switches have fixed,
nonadjustable settings. Switches are mounted on the
compressors.
TO CHECK — Slowly close liquid shutoff valve and allow
compressor to pump down. Do not allow compressor
pump-down below 2 psig (13.8 kPa). Compressor should shut
down when suction pressure drops to cutout pressure in
Tables 1A-1D, and should restart when pressure builds up to
cut-in pressure shown.
Outdoor Fans — Each fan is supported by a formed-
wire mount bolted to the fan deck and covered with a wire
guard. The exposed end of the motor shaft is covered with
a rubber boot. In case a fan motor must be repaired or replaced, be sure the rubber boot is put back on when the fan
is reinstalled and be sure the fan guard is in place before
starting the unit. Figure 15 shows the proper position of the
mounted fan. Fan motors have permanently lubricated
bearings.
Lubrication
F ANMOTORS have sealed bearings. No provisions are made
for lubrication.
COMPRESSOR has its own oil supply. Loss of oil due to a
leak in the system should be the only reason for adding oil
after the system has been in operation. See Preliminary Oil
Charge section.
CleaningCoils— Thecoilscanbecleanedwithavacuum
cleaner, washed out with low velocity water, blown out with
low-pressure compressed air, or brushed (do not use wirebrush). Fan motors are drip-proof but not waterproof. Do
NOT use acid cleaners.
Clean outdoor coil annually or as required by location or
outdoor air conditions. Inspect coil monthly, and clean as
required. Fins are not continuous through coil sections; dirt
and debris may pass through first section, become trapped
between the 2 rows of fins (38AKS013) or 3 rows of fins
(38AKS014-024) and restrict outdoor airflow. Use a flashlight to determine if dirt or debris has collected between coil
sections. Clean coil as follows:
1. Turn off unit power.
2. Remove screws holding rear corner posts and top
cover in place. Pivot top cover up 12 to 18 in. (305 to
457 mm) and support with a rigid support. See Fig. 16.
3. Remove clips securing tube sheets together at the return
bend end of the coil. Carefully spread the ends of the coil
rows apart by moving the outer sections. See Fig. 17.
4. Using a water hose, orothersuitableequipment,flushdown
between the sections of coil to remove dirt and debris.
5. Clean the remaining surfaces in the normal manner.
6. Reposition outer coil sections.
7. Reinstall clips which secure tube sheets.
8. Replace top cover and rear corner posts.
18
Page 19
Fig. 15 — Outdoor Fan
Fig. 17 — Coil Cleaning (Typical)
Fig. 16 — Pivot and Support Top Cover
19
Page 20
TROUBLESHOOTING
PROBLEMSOLUTION
COMPRESSOR DOES NOT RUN
Contactor Open
1. Power off.1. Restore power.
2. Fuses blown in field power circuit.2. After finding cause and correcting, replace with correct size fuse.
3. No control power.3. Check control circuit breaker; reset if tripped or replace if defective.
1. Shortage of refrigerant due to leak.1. Repair leak and recharge.
2. Expansion valve opens too wide.2. Adjust expansion valve.
FROSTED LIQUID LINE
1. Restricted filter drier.1. Remove restriction or replace.
2. Liquid line solenoid valve partially closed.2. Replace valve.
COMPRESSOR WILL NOT UNLOAD
1. Defective unloader.1. Replace unloader.
2. Defective capacity control solenoid valve (if used).2. Replace valve.
3. Miswired capacity control liquid line solenoid (if used).3. Rewire correctly.
4. Weak, broken, or wrong valve body spring.4. Replace spring.
COMPRESSOR WILL NOT LOAD
1. Miswired capacity control liquid line solenoid (if used).1. Rewire correctly.
2. Defective capacity control solenoid valve (if used).2. Replace valve.
3. Plugged strainer (high side).3. Clean or replace strainer.
4. Stuck or damaged unloader piston or piston ring(s).4. Clean or replace the necessary parts.
1. Tighten all connections.
1. Add refrigerant.
Check outdoor-air fan thermostat settings.
Check unloader setting.
bearings are worn.
defective.
21
Page 22
Copyright 1998 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 1 4
Tab 3a 2a
PC 111Catalog No. 563-701Printed in U.S.A.Form 38AKS-3SIPg 229-98Replaces: 38AKS-2SI
Page 23
START-UP CHECKLIST
A. Preliminary Information
OUTDOOR: MODEL NO.SERIAL NO.
INDOOR: AIR HANDLER MANUFACTURER
MODEL NO.SERIAL NO.
ADDITIONAL ACCESSORIES
B. Pre-Start-Up
OUTDOOR UNIT
IS THERE ANY SHIPPING DAMAGE?
IF SO, WHERE:
WILL THIS DAMAGE PREVENT UNIT START-UP?(Y/N)
CHECK POWER SUPPLY. DOES IT AGREE WITH UNIT?(Y/N)
HAS THE GROUND WIRE BEEN CONNECTED?(Y/N)
HAS THE CIRCUIT PROTECTION BEEN SIZED AND INSTALLED PROPERLY?(Y/N)
ARE THE POWER WIRES TO THE UNIT SIZED AND INSTALLED PROPERLY?(Y/N)
HAVE COMPRESSOR HOLDDOWN BOLTS BEEN LOOSENED (Snubber washers are snug, but not tight)?
(Y/N)
(Y/N)
CONTROLS
ARE THERMOSTAT AND INDOOR FAN CONTROL WIRING
CONNECTIONS MADE AND CHECKED?(Y/N)
ARE ALL WIRING TERMINALS (including main power supply) TIGHT?(Y/N)
HAS CRANKCASE HEATER BEEN ENERGIZED FOR 24 HOURS?(Y/N)
INDOOR UNIT
HAS WATER BEEN PLACED IN DRAIN PAN TO CONFIRM PROPER DRAINAGE?(Y/N)
ARE PROPER AIR FILTERS IN PLACE?(Y/N)
HAVE FAN AND MOTOR PULLEYS BEEN CHECKED FOR PROPER ALIGNMENT?(Y/N)
DO THE FAN BELTS HAVE PROPER TENSION?(Y/N)
HAS CORRECT FAN ROTATION BEEN CONFIRMED?(Y/N)
PIPING
ARE LIQUID LINE SOLENOID VALVES LOCATED AT THE INDOOR COILS AS REQUIRED?(Y/N)
HAVE LEAK CHECKS BEEN MADE AT COMPRESSOR, OUTDOOR AND INDOOR COILS,
WITH A LEAK DETECTOR?(Y/N)
LOCATE, REPAIR, AND REPORT ANY LEAKS.
HAVEALL COMPRESSOR SERVICE VALVES BEEN FULLY OPENED (BACKSEATED)?(Y/N)
HAVE LIQUID LINE SERVICE VALVES BEEN OPENED?(Y/N)
IS THE OIL LEVEL IN EACH COMPRESSOR CRANKCASE VISIBLE IN THE COMPRESSOR SIGHT GLASSES?
(Y/N)
CHECK VOLTAGE IMBALANCE
LINE-TO-LINE VOLTS:AB
(AB + AC + BC)/3 = AVERAGE VOLTAGE =
MAXIMUM DEVIATION FROM AVERAGE VOLTAGE =
VOLTAGE IMBALANCE = 100 X (MAX DEVIATION)/(AVERAGE VOLTAGE) =
IF OVER 2% VOLTAGE IMBALANCE, DO NOT ATTEMPT TO START SYSTEM!
CALL LOCAL POWER COMPANY FOR ASSISTANCE.
VAC VBC V
V
V
CL-1
%
Page 24
C. Start-Up
CHECK INDOOR UNIT FAN SPEED AND RECORD.
CHECK OUTDOOR UNIT FAN SPEED AND RECORD.
AFTER AT LEAST 10 MINUTES RUNNING TIME, RECORD THE FOLLOWING MEASUREMENTS:
OIL PRESSURE
SUCTION PRESSURE
SUCTION LINE TEMP
DISCHARGE PRESSURE
DISCHARGE LINE TEMP
ENTERING OUTDOOR UNIT AIR TEMP
LEAVING OUTDOOR UNIT AIR TEMP
INDOOR UNIT ENTERING-AIR DB (dry bulb) TEMP
INDOOR UNIT ENTERING-AIR WB (wet bulb) TEMP
INDOOR UNIT LEAVING-AIR DB TEMP
INDOOR UNIT LEAVING-AIR WB TEMP
COMPRESSOR AMPS (L1/L2/L3)//
CHECK THE COMPRESSOR OIL LEVEL SIGHT GLASSES; ARE THE SIGHT GLASSES SHOWING
OIL LEVEL IN VIEW?(Y/N)
NOTES:
Copyright 1998 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 1 4
Tab 3a 2a
PC 111Catalog No. 563-701Printed in U.S.A.Form 38AKS-3SICL-29-98Replaces: 38AKS-2SI