Carrier 09DK054-084 User Manual

09DK054-084
HEATING & COOLING
Air-Cooled Condenser Units
50/60 Hz
à
Installation, Start-Up and
Service Instructions
Air-Cooled Packages
Page
SAFETY CONSIDERATIONS ...
INSTALLATION .................................................
Step 1 — Complete Pre-Installation
Checks ............................................................................. 1
Step 2 — Rig and Place Unit ..........................................4
• RIGGING
• PLACING THE UNIT
Step 3 — Complete Refrigerant Piping
• GENERAL
• COIL REFRIGERANT PIPING INSTALLATION
• TUBING PACKAGE INSTALLATION
• THREE AND FOUR COIL SPLIT, COIL CIRCUITING APPLICATIONS; 054-084 UNITS
• REFRIGERANT LINE SIZING
• LIQUID SHUTOFF VALVE AND SIGHT GLASS
• PRESSURE RELIEF
• REFRIGERANT RECEIVER
• LIQUID LIFT
Step 4 — Complete Electrical
Connections..................................................................21
• GENERAL
• FIELD CQNNECTIONS
• MAIN POWER WIRING
• CONTROL CIRCUIT POWER WIRING
• GENERAL WIRING NOTES
• DESCRIPTION OF CONTROLS
Step 5 — Add Accessories as Needed
START-UP..........................................................................29
System Evacuation and
Dehydration ..................................................................29
Charging Procedure........................................................29
Check Operation of Condenser Fan Motor
Controls and Rotation of Fans
SERVICE ......................................................................29-31
Cleaning Condenser Coils
Condenser Fans ..............................................................29
Lubrication
Head Pressure Control ..................................................29
• FAN CYCLING
.......................................................................
........................................
.....................
.....................
................................
SAFETY COIVISIDERATIOIMS
Installing, starting up, and servicing air-conditioning equip
ment can be hazardous due to system pressures, electrical components, and equipment location (roofs, elevated struc tures, etc.).
Only trained, qualified installers and service mechanics
should install, start up, and service this equipment (Fig. 1).
Untrained personnel can perform basic maintenance func
tions such as cleaning coils. All other operations should be performed by trained service personnel.
,.. 1
1-28
28
29
29. 29
7
Fig. 1 — Model 09DK (084 Shown)
When working on the equipment, observe precautions in the literature and on tags, stickers, and labels attached to the equipment.
Follow all safety codes. Wear safety glasses and work gloves. Keep quenching cloth and fire extinguisher nearby when brazing. Use care in handling, rigging and setting bulky equipment.
See Tables lA and IB for Physical Data.
ELECTRIC SHOCK HAZARD Separate power sources (main and control cir
cuit power) are used for these units. Be sure both main and control circuit powers are dis connected before servicing.
INSTALLATION
Step 1 — Complete Pre-Installation Checks —
Examine for damage incurred during shipment. File claim immediately with transit company if damage is found. Ver ify that the nameplate electrical requirements match the avail able power supply. Check the shipment for completeness.
Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Book 12 PC 111 Catalog No 530-953 Printed in U.S A Form 09DK-4SI Pg 1 4-93 Replaces: New Tab 4a
Table IA — Physical Data 60 fìz
English
09DK NOMINAL TONS OPERATING WEIGHT-lb
Cu-AI* Cu-Cut
SHIPPING WEIGHT-lb“
Cu-AI‘ Cu-Cut
054
50
1695 1983
2010 2298 2569 2938 3403
REFRIGERANTS NOMINAL HEAT REJECTION
(TONS)tt CONDENSER FANS
No. of Blades No. of Fans Fan Diameter-In. 30 AIrflow-cfm Fan Speed-rpm Fan Motor-hp 1
CONDENSER COILS
Quantity 4 FIns/in. 17 No. of Rows Total Face Area (sq ft)
65.8 78.6 95.4 103.5
4 4 4 4 4 4 6 6
35,000
1140 1140
2
80.5
TD — Temperature Difference = Saturated Condensing Temperature - Entering-Air Temperature
‘Copper tubes and aiuminum fins.
TCopper tubes and copper fins.
“Packaging option includes skid and coil protection.
ttNominal heat rejection based on refrigerant R-22, 15° F subcooling, and a 30° F temperature difference (TD).
064
60
1845 2200 2278 2617
2136 2521
R-134A, R-22, R-12, R-500, R-502
30 30 30
35,000 52,000 51,000
1 1 1 4 4 4
17 17 17
3 2
80.5 116.7 1167
074
70
1140 1140
084
80
2421 3099
2725
3
SI
09DK NOMINAL kW OPERATING WEIGHT-kg
Cu-AI* Cu-Cut
SHIPPING WEIGHT-kg“
Cu-AI* Cu-Cut
REFRIGERANTS NOMINAL HEAT REJECTION
(kW)tt CONDENSER FANS
No. of Blades No. of Fans Fan DIameter-mm AIrflow-L/s
Fan Speed-r/s Fan Motor-kW
CONDENSER COILS
Quantity
FIns/m No. of Rows Total Face Area (sq m)
TD — Temperature Difference = Saturated Condensing Temperature - Entering-Air Temperature
‘Copper tubes and aluminum fins.
tCopper tubes and copper fins.
“Packaging option includes skid and coil protection
ttNominal heat rejection based on refrigerant R-22, 8.3° C subcooiing, and a 16.7° C temperature difference (TD).
054 064 074
175.7 210.9 246.0 281.2 769
900 912 969 1144
1042 1165 1333 1544
231.3
4 4
762
16 520
19
.746
4
669
2 3 2 3
7.5
837 998
1033
R-134A, R-22, R-12, R-500, R-502
276 2 335.3
4 4
762 762
16 520 24 540
19 19
.746 .746
• 669 669
4 4 4
75 10.84 10.84
1187
4 6
084
1098 1406
1236
363 8
4 6
762
24 070
19
746
669
Table 1B — Physical Data 50 Hz
English
09DK NOMINAL TONS OPERATING WEIGHT-lb
Cu-AI* Cu-Cut
SHIPPING WEIGHT-lb"
Cu-AI* 2010
Cu-Cut REFRIGERANTS NOMINAL HEAT REJECTION (TONS)tt CONDENSER FANS
No. of Blades
No. of Fans
Fan DIameter-ln. 30 30 30 30
AIrflow-cfm
Fan Speed-rpm 950 950 950 950
Fan Motor-hp 1 1 CONDENSER COILS
Quantity
Fins/in.
No. of Rows
Total Face Area (sq ft)
TD — Temperature Difference = Saturated Condensing Temperature - Entering-Air Temperature
'Copper tubes and aluminum fins
tCopper tubes and copper fins.
"Packaging option includes skid and coil protection.
ttNominal heat rejection based on refrigerant R-22, 15° F subcooling, and a 30° F temperature difference (TD).
054 064 074
50 60 70
1695 1845 2200 1983 2278
2298 2569
65.8 78.6
6 6 6 6 4 4 6 6
35,000 35,000 52,000 51,000
4 4 4 4
17 17 17 17
2
80.5 80.5 116.7 1167
2136 2521
R-134A, R-22, R-12, R-500, R-502
3
2617 3099
2938
95 4 103.5
1
2
084
80
2421
2725
3403
1
3
SI
09DK 054 064 074 084 NOMINAL kW OPERATING WEIGHT-kg
Cu-AI* Cu-Cut
SHIPPING WEIGHT-kg"
Cu-AI*
Cu-Cut REFRIGERANTS NOMINAL HEAT REJECTION
(kW)tt CONDENSER FANS
No. of Blades No. of Fans Fan DIameter-mm 762 762 762 762 AIrflow-L/s 16 520 16 520 24 540 24 070 Fan Speed-r/s 15.8 15.8 15.8 15.8 Fan Motor-kW .746
CONDENSER COILS
Quantity Fins/m 669 669 669 669 No. of Rows
Total Face Area (sq m)
TD — Temperature Difference = Saturated Condensing Temperature - Entering-Air Temperature
•Copper tubes and aluminum fins
tCopper tubes and copper fins
"Packaging option includes skid and coil protection.
ttNominal heat rejection based on refrigerant R-22, 8 3° C subcooling.
175 7
769 837 998 900 1033
912 969
1042
231.3 276.2 335.3 363.8
6 4
4 2
7.5
and a 16.7° C temperature difference (TD)
210 9 246 0
1165 1333
R-134A, R-22, R-12,R-500, R-502
6 6 6 4 6 6
746 746
4 4 3 2 3
7.5
281 2
1187 1406 1144
10 84 10 84
1098
1236 1544
.746
4
Step 2 — Rig and Place Unit
RIGGING — These units are designed for overhead rig ging and this method should be used. Lifting holes are pro vided in the frame base rails which are marked for rigging (see rigging label on the unit). It is recommended that field supplied pipes of sufficient length that extend beyond the frame are passed through the holes. Attach cables, chains, or straps to both ends of the pipes. Use spreader bars or a frame to keep the cables, chains, or straps clear of the unit sides. All cables should run to a central suspension point so that the angle from the horizontal is not less than 45 degrees. See Fig. 2 and Table 1 for weight distribution information. Standard coil protection packaging will pro vide some protection to the unit. Raise and set the unit down carefully.
Domestic Units With No Overhead Rigging— Standard con denser packaging consists of coil protection only. Skids are not provided as part of the standard packaging. If overhead rigging is not available at the jobsite, place the unit on a skid or pad by using jacks at the rigging points before drag ging or rolling. When rolling, use a minimum of 3 rollers. When dragging, pull the pad or skid. Do not apply pressure
to the unit. Raise from above to lift off the pad or skid
when in final position. See rigging section above for more information.
Export and Domestic Units With Skids— All export units are mounted on skids with vertical coil protection. Leave the unit on the skid until it is in the final position. While on
the skid, the unit can be rolled, dragged or forked; do not
apply force to the unit. Use a minimum of 3 rollers when
rolling, and raise from above to remove the skid when unit is in the final position. See rigging procedure above for more information.
A CAUTION
Do not forklift these units unless attached to a skid de signed for forklifting; damage to unit may occur. If uti lizing a packaging option which includes a skid, the forklift truck must have at least a 60-in. (1524 mm) fork.
PLACING THE UNIT — Locate the condenser where an adequate supply of inlet outdoor air is available. Do not lo cate where the possibility of air recirculation exists, such as under a roof overhang. Also, locate the condenser in an area free from airborne dirt or other foreign material which could clog the condenser coils. Refer to Fig. 3 and 4 for airflow clearances. For multiple units, allow 8 ft (2440 mm) separation between units for airflow and service. Placement area must be level and strong enough to support operating weight of the unit (Fig. 2 and Table 1). It is recommended to bolt unit securely to pad when unit is positioned and lev eled. Fasteners for mounting unit are field supplied. If vi bration isolators are required for a particular installation, refer to the unit weight distribution data table and diagram below to help select the proper isolators.
Y - DIMENSION
UNIT 09DK
054
064
074
084
COIL TYPE*
*Cu-AI — Copper Tubes, Aluminum Fins
Cu-Cu — Copper Tubes, Copper Fins.
UNIT 09DK
054
064
074
084
COIL TYPE*
Cu-AI 1695 (769)
Cu-Cu
Cu-AI
Cu-Cu
Cu-AI
Cu-Cu
Cu-AI
Cu-Cu
TOTAL WEIGHT
1983 (900) 1845 (837)
2278 (1033)
2200 (998)
2617 (1187) 2421 (1098)
3099 (1406) 843 (382) 751 (341)
*Cu-AI — Copper Tubes, Aiuminum Fins.
Cu-Cu — Copper Tubes, Copper Fins.
Cu-AI
Cu-Cu
Cu-AI
Cu-Cu
Cu-AI
Cu-Cu
Cu-AI
Cu-Cu
lb (kg)
X- DIMENSION
CENTER OF GRAVITY In. (mm) X Dimension
48.1 (1222)
48.3 (1227) 48 2 (1224)
44,5 (1232)
56 7 (1440)
57.4 (1458)
57.1 (1450) 581 (1476)
A
452 (205) 425 (193)
524 (238) 497 (225) 489 (222)
598 (271)
618 (280)
722 (328) 673 (305)
Y Dimension
42 7 (1084) 42 9 (1090)
42 8 (1087)
43.1 (1095) 42 5 (1080)
42.8 (1087) 42 6 (1082)
43 0 (1092)
OPERATING CORNER WEIGHTS lb (kg)
B C D
462 (210)
571 (259) 542 (246) 568 (258)
526 (239) 630 (286)
581 (264)
396 (180) 422 (191) 468 (212)
434 (197)
486 (220) 589 (267)
541 (245) 626 (284)
709 (322)
494 (224) 459 (208)
571 (259) 675 (306)
796 (361)

Fig. 2 — Weight Distribution

NOTES:
1. The approximate operating weight of the unit is: 09DK-054—
09DK-054-C 09DK-064— 09DK-064-C
2. Unit must have clearances for airflow as follows: Top — Do not restrict in any way. Ends — 5 ft [1524 mm] Sides — 6 ft [1829 mm]
3. All units are shipped with a capacity split tubing kit. This kit may be used by the field to obtain 100%, 50%/50% and 67%/33% capacity splits. To obtain a 33%/33%/33% capacity split, coils must be manifolded by the field. Coils' are factory circuited for a 33%/33%/17%/17% capacity split.
________
-------------
-------------
-------------
► 1695 lb [769 kg]
»■ 1983 lb [900 kg]
»• 1845 lb [837 kg]
»-2278 lb [1033 kg]
CONTROL BOX
END
UNIT
09DK-054—
09DK-054-C
09DK-064—
09DK-064-C
DIMENSION Y DIMENSION X
3'-6 11/16”
[1084 mm]
3'-6 7/8"
[1090 mm]
3'-6 3/4"
[1087 mm]
3’-7 1/8"
[1095 mm]
4'-1/8"
[1222 mm]
4'-5/16"
[1227 mm]
4'-3/16"
[1224 mm]
4'-1/2"
[1232 mm]
OPERATING CORNER WEIGHTS A B
452 lb
[205 kg]
524 lb
[238 kg]
489 lb
[222 kg]
598 lb
[271 kg]
425 lb
[193 kg]
497 lb
[225 kg]
462 lb
[210 kg]
571 lb
[259 kg]
C
396 lb
[180 kg]
468 lb
[212 kg]
434 lb
[197 kg]
542 lb
[246 kg]
D
422 lb
[191 kg]
494 lb
[224 kg]
459 lb
[208 kg]
568 lb
[258 kg]
CAPACITY SPLIT
100% 50%/50% 67%/33%
33%/33%/33%
33%/33%/17%/17%
HOT GAS
LIQUID
HOT GAS
LIQUID
HOT GAS
LIQUID
HOT GAS 1
LIQUID
HOT GAS 1 7
LIQUID
TYPE
T-A 1/2'-
C224 7rain3
BASE OVERALL
CONNECTIONS
N0.5
1/3.5,7 2,4.6,8
5,7
1/3
2.4
6.8 7/8 I.D.
1.3,5 7
2.4.5 8 7
2 a 4.5
3 5 4
2 8
SIZE
1 1/8’ I.D.
7/8 I.D.
1 1/8' I.D. 1 1/8' I.D.
7/8 1.0.
3,51 1/8' I.D.
7/8 I.D.
1 1/8' I.D.
6 7/8 I.D.
Fig. 3 — Dimensions; 054 and 064 Units
NOTES.
1. The approximate operating weight of the unit is: 09DK-074—
09DK-074-C 09DK-084 09DK-084--C
2. Unit must have clearances for airflow as follows: Top — Do nof restrict in any way. Ends — 5 ft [1524 mm] Sides — 6 ft [1829 mm]
3. All units are shipped with a capacity split tubing kit. This kit may be used by
the field to obtain 100%, 50%/50% and 67%/33% capacity splits. To obtain a 33%/33%/33% capacity split, coils must be manifolded by fhe field. Coils are factory circuited for a 33%/33%/17%/17% capacity split.
_________
----------------
-----------------
--------------
2200 ib [998 kg]
»2617 ib [1187 kg]
»• 2421 ib [1098 kg]
»-3099 Ib [1406 kg]
09DK-074—
09DK-074-C
09DK-084—
09DK-084-C
Ov
DIMENSION Y
3’-6 1/2"
[1080 mm] 3'-6 13/16"
[1087 mm]
3'-6 5/8"
[1082 mm]
3'-7"
[1092 mm]
П6) MTG HOLES
17/32' DIA.—V
C13.5bb3
r-4 7/8'-
С42В.5в>т:
HT6. HOLES
DIMENSION X
Г-5 1/2'-
C444m}
HTG. HOLES
4'-8 11/16" [1440 mm]
4'-9 3/8"
[1458 mm]
4'-9 1/8"
[1450 mm]
4'-10 1/8"
[1476 mm]
С22531ПЛ1
Г-4 3/4'-
L425cnir>3
MTG. HOLES
-?'-4 11/16'-
OPERATING CORNER WEIGHTS
A В
618 Ib
[280 kg]
722 Ib
[328 kg]
673 Ib
[305 kg]
843 Ib
[382 kg]
HINGED ACCESS
PANEL
(CONTROL BOX)
526 Ib
[239 kg]
630 Ib
[286 kg]
581 Ib
[264 kg]
751 Ib
[341 kg]
-Г-5 1/2'
C444nti3
MTG. HOLES
C
486 Ib
[220 kg]
589 Ib
[267 kg]
541 Ib
[245 kg]
709 Ib
[322 kg]
»-1 1/2'
[Se.Snnl
MTG. HOLES
• 7/8'
[428.Siw]
MTG. HOLES
D
571 Ib
[259 kg]
675 Ib
[306 kg]
6261b
[284 kg]
796 Ib
[361 kg]
base overall
(4) RIG HOLES
2 5/8' DIA.
СбТтт]
CAPACITY SPLIT
100%
50%/50%
67%/33%
33%/33%/33%
33%/33%/17%/17%
TYPE
HOT GAS 1,3.5.7
LIQUID 2.4.6,8 7/8 I.D.
HOT GAS
LIQUID
HOT GAS
LIQUID 2.4,5 8 7/8 I.D.
HOT GAS 1 7
LIQUID
HOT GAS17
LIQUID 2
CONNECTIONS
N0.5 SIZE
5,7
1.3 2,4 6,8 7/8 I.D.
7
1.3.S
3.5
2
8 4,6 7/8 I.D.
3 5 4
8
• 7'-4 1/2'
[224?готЗ
BASE Overall
1 3/8' I.D.
1 3/8' I.D.
1 3/8' I.D.
1 3/8' I.D.
1 3/8' I.D.
5 7/8 I.D.
Fig. 4 — Dimensions; 074 and 084 Units
Step 3 — Complete Refrigerant Piping
GENERAL — All field leak and pressure testing should be in accordance with local code requirements. If a local code does not exist, use ASHRAE (American Society of Heat ing, Refrigeration and Air Conditioning Engineers) Stan dard 15, Safety Code for Mechanical Refrigeration.
For leak testing procedures, refer to the Carrier’s
“Refrigerant Service Techniques” Book, Form SM-IA.
For any parts that need to be removed, use a mini tubing cutter. Perform phos-copper brazing on all field-made con nections while protecting adjacent joints from heat.
Install or replace filter-drier(s). BEFORE CHARGING THE SYSTEM, INSTALL OR REPLACE THE FILTER­DRIER(S) CONNECTED TO THE LIQUID LINE WITHIN THE INDOOR UNIT(S) TO PREVENT CONTAMINA TION WITHIN THE SYSTEM.
COIL REFRIGERANT PIPING INSTALLATION - Hot gas and liquid connections are located on the same end and are capped from the factory with a heat shrink-type cap, which provides a clean joint for field piping. The coil cir cuiting is designed to provide several selections of coil splits to satisfy various applications (See Table 2), with piping connections made in the field. In all cases where circuits are field connected, the piping connections should be made within the unit cabinet. The hot gas lines should enter and the liquid lines should leave the condenser at the header end of the unit.
As a standard item, a tubing package for headering, in cluding two fan cycle pressure switches (FCPSs) and hard ware is provided for the 100, 50/50, and 67/33% typical condenser coil circuiting options. The tubing also provides the ports for easy FCPS installations. The ports come with a 1/4 in. male flare fitting and check valve for each FCPS replacement. Tubing and FCPSs are field installed regard less of circuiting. Tubing packages are not offered for the
33/33/33% and 33/33/17/17% coil circuiting options; tub ing for these coil circuit options must be field fabricated and installed. See Fig. 5 and 6 for tubing package contents.
NOTE: 67/33, 33/33/33 and 33/33/17/17 represent average coil split combinations. Refer to sections below for actual values for your particular coil split combination.
IMPORTANT: With the 67/33, 33/33/33, and 33/33/
17/17% capacity split options, 3 or 4 FCPSs are used. For these applications, an accessory fan control kit is required. See accessory installation instructions for more information.
Figure 7 shows a typical piping application for a condenser with a multiple-split system. Figure 8 shows the typical field piping arrangements for the 09DK units. See Fig. 9 for coil connection details. Figures 10 and 11 show typical factory supplied coil circuiting and typical field installed 67/33% coil split circuiting respectively.
TUBING PACKAGE INSTALLATION - Before install ing, inspect the package contents. If any parts are missing or damaged, file a claim with the shipping company and notify your Carrier representative. A field supplied 3/8-in.
conduit (Greenfield conduit recommended) is required
according to UL/CSA (Underwriters’ Laboratories/ Canadian Standards Association) code for the FCPS field wiring. Field supplied 3/8-in. conduit connectors are re quired for connection to the junction box.
100% Coil Circuiting Applications: 054. 064 Units
1. Piping — Refer to Fig. 9 and 12 for field piping details
for 100% coil circuiting. Note that tubes 15 and 22 require cut on the longer leg of the tube. Two 7/8-in. OD tubes, approximately 3 in. (76.2 mm) long, must be cut from the remaining tubes (tubes 21, 23, or 25) and brazed between the tees (item 8) and coil header stubs. The remaining tubes are not used in this application and may be discarded.
2. Install Fan Cycle Pressure Switches and Clamps — Braze 2 valve core bodies (item 5) to designated hole locations on tubes 19 and 22. Insert valve cores (item 6), into valve core bodies by threading into place and tightening to 1.5 to 3 in.-lb (169.5 to 339 mN-m). Install FCPSl and FCPS2 (item 7) at designated locations on tubes 19 and 22. Cut the 3/8-in. field-supplied FCPS conduit at a desired length to fit between each FCPS location and the junction box on the unit. Figure 11 shows a typical installation of the conduit. Feed FCPS wires through each conduit and secure at the switch by utilizing each conduit connector. See Fig. 13. Secure the conduit at the junction box with 3/8-in. field­supplied conduit connectors. Wire FCPSl and FCPS2 according to Fig. 14. Clamp hot gas line, tube 27, at the location specified in Fig. 12 using the 1 5/8-in. clamp (item 4) and the 2 screws supplied. Clamp the liquid line, tube 24, using the 1 1/8-in. clamp (item 2) and the 2 screws provided.
50/50% Coil Circuiting Applications: 054 and 064 units
1. Piping — Refer to Fig. 9 and 15 for field piping details
for 50/50% coil circuiting. Note that tubes 21 and 22 require cuts on the longer leg of the tubes. Two 7/8-in. OD tubes, approximately 3 in. (72.6 mm) long, must be cut from the remaining tubes (21, 25, 26, or 29) and brazed between the tees (item 8) and coil header stubs. The re maining tubes are not used in this application and may be discarded.
2. Install Fan Cycle Pressure Switches and Clamps — Braze 2 valve core bodies (item 5) to designated hole locations on tubes 19 and 22. Insert valve cores (item 6) into valve core bodies by threading into place and tightening to 1.5 to
3 in.-lb (169.5 to 339 mN-m). Install FCPSl and FCPS2
(item 7) at designated locations on tubes 19 and 22. Cut the field-supplied 3/8-in. FCPS conduit at a desired length to fit between each FCPS location and the junction box on the unit. Figure 11 shows a typical installation of the conduit. Feed FCPS wires through each conduit and secure at the
switch using each conduit connector. See Fig. 13. Secure
the conduit at the junction box with 3/8-in. field-supplied
conduit connectors. Wire FCPSl and FCPS2 according to
Fig. 14. Clamp hot gas lines, tube 15 at the location spec
ified in Fig. 15 using the two 1 3/8-in. clamps (item 3)
and 4 screws provided. Clamp the liquid lines, tubes 21
and 23, using the two 7/8-in. clamps (item 1) and the
4 screws provided.
09DK
054 064 100% 074 100% 084 100%
100% 50/50%
Table 2 — Coil Circuiting Options
09DK CIRCUITING OPTIONS
66/34 50/50% 50/50% 50/50%
66/34
68/32
67/33
34/34/32 34/34/32 32/32/36 33/33/33
34/34/16/16 34/34/16/16 32/32/18/18 33/33/17/17
ITEM
QUANTITY NAME 1 2 a 3 4 5 6 7 8 9
10 11 12 13 14 15 16 17 2 18 19 20 21 22 23 24 25 1 26 27 28 29 30
Tube Clamp 1 2 1 Tube Clamp 2 2 2 2 1 1 1 1 2 1 2 Discharge Tuba 2
1 1 1
1
1 Liquid Tube 1 Liquid Tube 1
1 1
8 1 1
Tube Clamp Tube Clamp 1 3/8 in.
Valve Body Valve Core
Switch Fan cycle pressure switch Tee Tee
Tee Solder Coupling 1 1/8 in.
Elbow, 90 Degree 1 1/8 in
Tee
Tee
Discharge Tube’ 1 1/8 in. CD X 32 11/32 in. Lx 5 1/16 in. W Discharge Tube Discharge Tube 1 3/8 in CD Liquid Tube 7/8 in. CD X 16 13/16 in. L X 3 7/16 in. W Discharge Tube Liquid Tube 7/8 in. CD X 17 11/16 in. L
Straight Tube
Straight Tube 7/8 in. CD X 7 3/4 in. L Straight Tube 7/8 in. OD X 18 1/4 in. L Straight Tube 1 5/8 in. OD X 34 in. L
Screw 1/4 - 14 X 5/8 in long
Straight Tube 7/8 in OD X 3 7/8 in long Discharge Tube
DESCRIPTION
7/8 in.
1 1/8 in.
1 5/8 in. 1/4 in. male flare fitting
-
7/8 in. X 7/8 in. X 7/8 in.
1 1/8 in X 1 1/8 in. X 1 1/8 in. 7/8 in. X 7/8 in. X 1 1/8 in.
1 3/8 in. X 1 1/8 in. X 1 1/8 in. 1 5/8 in X 1 3/8 in X 1 3/8 in. 1 3/8 in. CD X 44 23/32 in L x 10 1/16 in. W
1 1/8 in. CD X 24 5/32 in L x 5 1/16 in W
1 1/8 in. CD X 24 1/2 in. L
7/8 in CD X 18 13/16 in L X 3 7/16 in. W 7/8 in. CD x8 11/16 in. Lx 5 1/16 in. W 1 1/8 in. OD X 7 3/4 in. L
1 1/8 in OD X 44 19/32 in. L x 11 9/16 in. W

Fig. 5 — 09DK054,064 Tubing Package Contents

8
16
ITEM
QUANTITY NAME
1 2
Tube Clamp
2 1 Tube Clamp 3 4 5 6 7 8 9
1 Tube Clamp 2 1 2 2 2 Siwitch 2
Tube Clamp Tube Clamp Valve Body Valve Core -
Tee
10 1 Coupling 11 1 Tee 12 1 Tee 13 2 Tee 14 1 Tee 15 16 17 2 18 19
1
2
2 1
Discharge Tube Discharge Tube Discharge Tube Discharge Tube Discharge Tube
20 1 Liquid Tube 21 1
Discharge Tube
22 1 Liquid Tube 23 24 25 26
1 Liquid Tube 1 1 Straight Tube 1 1/8 in OD X 7 3/4 in L 1 Straight Tube 7/8 in. OD X 8 1/4 in. L
Liquid Tube 7/8 in. OD X 14 13/16 in. L X 3 7/16 in W
27 1 Straight Tube 28 29 8
1 Straight Tube 2 1/8 in OD X 40 in. L
Screw
DESCRIPTION
7/8 in
1 1/8 in. 1 3/8 in 1 5/8 in
2 1/8 in
1/4 in. male flare fitting
Fan cycle pressure switch
7/8 in. X 7/8 in X 7/8 in.
1 3/8 in. X 1 3/8 in.
7/8 in. X 7/8 in. X 1 1/8 in.
1 3/8 in. X 1 3/8 in X 1 3/8 in. 1 5/8 in. X 1 3/8 in. X 1 3/8 in
2 1/8 in X 1 5/8 in X 1 5/8 in
1 3/8 in CD X 50 25/32 in. L x 14 1/8 in. W 1 5/8 in CD X 50 29/32 in. L x 12 1/16 in. W 1 3/8 in CD X 34 1/2 in L X 4 3/4 in. W 1 3/8 in CD X 19 7/8 in. L X 4 3/4 in. W 1 5/8 in CD
7/8 in. OD X 23 13/16 in L X 3 7/16 in. W 1 3/8 in OD X 28 3/8 in. L 7/8 in OD X 23 1/4 in. L (074 Units only) 7/8 in. OD X 18 1/4 in L
7/8 in. OD X 17 7/8 in. L
1/4 in.-14 X 5/8 in long

Fig. 6 — 09DK074,084 Tubing Package Contents

66/34% Coil Circuiting Applications: 054 and 064 Units
NOTE: To operate the 054 and 064 condenser units with 66/34% coil circuiting, an accessory fan control kit is required. Refer to fan control kit installation instruc tions for more information.
1. Piping — Refer to Fig. 9 and 16 for field piping details
for 66/34% coil circuiting. Note that tube 16 will require cuts on the longer leg of the tube. Tube 16 will be used in the two specified locations. A 7/8-in. OD tube, approxi mately 3 in. (72.6 mm) long, must be cut from the remain ing tubes (23 or 26) and brazed between the tee (item 8) and coil header stub. The remaining tubes are not used in this application and may be discarded.
2. Install Fan-Cycle Pressure Switches and Clamps — Braze 3 valve core bodies (item 5) to designated hole locations on tubes 19, 21, and 22. Insert valve cores (item 6) into valve core bodies by threading into place and tightening to 1.5 to 3 in.-lb (169.5 to 339 mN-m). Note that the accessory fan control kit is required for this coil circuiting. An extra FCPS and valve assembly is provided with the kit. Install FCPSl, FCPS2, and FCPS4 (item 7) at designated locations on tubes
19, 21, and 22. Cut the field-supplied 3/8-in. FCPS conduit at a desired length to fit between each FCPS location and the junction box on the unit. See Fig. 11 for typical conduit installation. Feed FCPS wires through each conduit and se cure at the switch by utilizing each conduit connector. See Fig. 13. Secure the conduit at the junction box with 3/8-in., field-supplied conduit connectors. Wire FCPSl, FCPS2, and FCPS4 according to Fig. 14 Note that FCPS2 and FCPS4 are wired in parallel. Fan 4 is shared by the 34% and 66% refrigeration circuit. If either circuit needs the fan to be on, it will be on. At the location specified in Fig. 16, clamp hot gas lines, tubes 15 and 30, using a 1 3/8-in. clamp (item 3) and a 1 1/8-in. clamp (item 2) with the 4 screws supplied. Clamp the liquid lines, tubes 21 and 25, with 7/8-in. clamps (item 1) and 4 screws provided.
100% Coil Circuiting Applications: 074 Units
1. Piping — Refer to Fig. 9 and 17 for field piping details
for 100% coil circuiting. Note that tube 16 requires a cut on the longer leg of the tube. Two 7/8-in. OD tubes approxi mately 3 in. (72.6 mm) long, must be cut from the remain ing tubes (22 or 23) and brazed between the tees (item 9)
and coil header stubs. The remaining tubes are not used and may be discarded.
2. Install Fan Cycle Pressure Switches and Clamps — Braze 2 valve core bodies (item 6) to designated hole locations on tubes 20 and 24. Insert valve cores (item 7) into valve core bodies by threading into place and tightening to 1.5 to
3 in.-lb (169 to 339 mN-m). Install FCPSl and FCPS2
(item 8) at designated locations on tubes 20 and 24. Cut the
3/8-in. field-supplied FCPS conduit at a desired length to
fit between each FCPS location and the junction box on the
unit. See Fig. 11 for typical conduit installation. Feed FCPS
wires through each conduit and secure at the switch by uti
lizing each conduit connector. See Fig. 13. Secure the con
duit at the junction box with 3/8-in. field-supplied conduit
connectors. Wire FCPSl and FCPS2 according to Fig. 18.
Clamp hot gas line, tube 28, using 2 1/8-in. clamp (item 5)
at the location specified in Fig. 17 with the 2 screws sup
plied. Clamp the liquid line, tube 25, using 1 1/8-in. clamp
(item 2) and the 2 screws provided.
50/50% Coil Circuiting Applications: 074 Units
1. Piping — Refer to Fig. 9 and 19 for field piping details
for 50/50% coil circuiting. Note that tube 23 will require a cut, located exactly at the location of the hole in the tube. Tube 23 will be used in the two locations specified. Two 7/8-in. OD tubes, approximately 3 in. (72.6 mm) long, must be cut from the remaining tubes (22, 26, or 27) and brazed between the tees (item 9) and coil header stubs. The re
maining tubes are not used in this application and may be
discarded.
2. Install Fan Cycle Pressure Switches and Clamps — Braze 2 valve core bodies (item 6) to designated hole locations on tubes 20 and 24. Insert valve cores (item 7) into valve core bodies by threading into place and tightening to 1.5 to
3 in.-lb (169.5 to 339 mN-m). Install FCPSl and FCPS2 (item 8) at designated location on tubes 20 and 24. Cut the 3/8-in. field-supplied FCPS conduit at a desired length to fit between each FCPS location and the junction box on the unit. See Fig. 11 for typical conduit installation. Feed FCPS wires through each conduit and secure at the switch by us
ing each conduit connector. See Fig. 13. Secure the con
duit at the junction box with 3/8-in. field-supplied conduit connectors. Wire FCPSl and FCPS2 according to Fig. 18. Clamp hot gas line, tube 16, at the location specified in Fig. 19 using two 1 5/8-in. clamps (item 4) and 4 screws supplied. Clamp the liquid lines, tubes 23, using the two
7/8-in. clamps (item 1) and the 4 screws provided.
68/32% Coil Circuiting Applications: 074 Units
NOTE: To operate the 074 condenser units with 68/32% coil circuiting, an accessory fan control kit is required. See accessory installation instructions for more infor mation.
1. Piping — Refer to Fig. 9 and 20 for field piping details
for 68/32% coil circuiting. Note that tubes 17 and 20 re quire euts on the longer leg of the tubes. Tube 17 will be used in the two locations specified. Also, a 7/8-in. OD tube, approximately 3 in. (72.6 mm) long, must be cut from the remaining tubes (23 or 27) and brazed between the tee (item 9) and eoil header stub. The remaining tubes are not used in this application and may be discarded.
2. Install Fan Cycle Pressure Switches and Clamps — Braze 3 core bodies (item 6) to designated hole locations on tubes 20, 22, and 24. Insert valve cores (item 7) into valve core bodies by threading into place and tightening to 1.5 to 3 in.-lb (169.5 to 339 mN-m). Note that the accessory fan control kit is required for this coil circuiting. An extra FCPS and valve assembly is provided with the kit. Install FCPSl, FCPS2, and FCPS4 (item 8) at designated locations on tubes 20, 22, and 24. Cut the 3/8-in. field-supplied FCPS conduit at a desired length to fit between each FCPS location and the junction box on the unit. See Fig. 11 for typical conduit installation. Feed FCPS wires through each conduit and se cure at the switch by utilizing each conduit connector. See Fig. 13. Secure the conduit at the junction box with 3/8-in. field-supplied conduit connectors. Wire FCPSl, FCPS2 and FCPS4 according to Fig. 18. Note that FCPS2 and FCPS4 are wired in parallel. Fan 4 is being shared by the 32% and 68% refrigeration circuit. If either circuit needs the fan to be on, it will be on. At the location specified in Fig. 20, clamp hot gas lines, tube 15 with a 1 3/8 in. clamp (item 3) and tube 16 with a 1 5/8 in. clamp (item 4) with the 4 screws supplied. Clamp the liquid lines, tube 22 with a 7/8 in. clamp (item 1) and tube 25 with a 1 1/8 in. clamp (item 2) with the 4 screws supplied.
10
Loading...
+ 22 hidden pages