This equipment will store up-to six pounds of whole bean coffee in each of two hoppers and grind it to a preset
grind and amount into an awaiting funnel and filter from most commercial drip coffee brewers. The equipment is only
for indoor use on a sturdy counter or shelf. Adequate space must be available above the grinder to raise the lids when
adding beans. Use only with whole bean coffee.
The grind is preset at the factory to drip specifications as set forth by the United States Department of Commerce
and adopted by the Coffee Brewing Center of the Pan American Coffee Bureau. Adjustments may be made to alter both
the amount and grind from the factory setting.
WARRANTY
Bunn-O-Matic Corp. (“Bunn”) warrants the equipment manufactured by it to be commercially free from
defects in material and workmanship existing at the time of manufacture and appearing within one year from the
date of installation. In addition:
1.) Bunn warrants electronic circuit and/or control boards to be commercially free from defects in material
and workmanship for two years from the date of installation.
2.) Bunn warrants the compressor on refrigeration equipment to be commercially free from defects in mate-
rial and workmanship for two years from the date of installation.
3.) Bunn warrants that the grinding burrs on coffee grinding equipment will grind coffee to meet original
factory screen sieve analysis for three years from date of installation or for 30,000 pounds of coffee, whichever
comes first.
This warranty does not apply to any equipment, component or part that was not manufactured by Bunn or
that, in Bunn’s judgement, has been affected by misuse, neglect, alteration, improper installation or operation,
improper maintenance or repair, damage or casualty.
THE FOREGOING WARRANTY IS EXCLUSIVE AND IS IN LIEU OF ANY OTHER WARRANTY, WRITTEN OR
ORAL, EXPRESS OR IMPLIED, INCLUDING, BUT NOT LIMITED TO, ANY IMPLIED WARRANTY OF EITHER MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. The agents, dealers or employees of Bunn are not
authorized to make modifications to this warranty or to make additional warranties that are binding on Bunn.
Accordingly, statements by such individuals, whether oral or written, do not constitute warranties and should not
be relied upon.
The Buyer shall give Bunn prompt notice of any claim to be made under this warranty by telephone at (217)
529-6601 or by writing to Post Office Box 3227, Springfield, Illinois, 62708-3227. If requested by Bunn, the
Buyer shall ship the defective equipment prepaid to an authorized Bunn service location. If Bunn determines, in
its sole discretion, that the equipment does not conform to the warranty, Bunn shall repair the equipment with no
charge for parts during the warranty period and no charge for labor by a Bunn Authorized Service Representative
during the warranty period. If Bunn determines that repair is not feasible, Bunn shall, at its sole option, replace
the equipment or refund the purchase price for the equipment.
THE BUYER’S REMEDY AGAINST BUNN FOR THE BREACH OF ANY OBLIGATION ARISING OUT OF THE
SALE OF THIS EQUIPMENT, WHETHER DERIVED FROM WARRANTY OR OTHERWISE, SHALL BE LIMITED, AS
SPECIFIED HEREIN, TO REPAIR OR, AT BUNN’S SOLE OPTION, REPLACEMENT OR REFUND.
In no event shall Bunn be liable for any other damage or loss, including, but not limited to, lost profits, lost
sales, loss of use of equipment, claims of Buyer’s customers, cost of capital, cost of down time, cost of substitute equipment, facilities or services, or any other special, incidental or consequential damages.
2
10854 030300
USER NOTICES
Carefully read and follow all notices on the grinder and in this manual. They were written for your protection. All notices on the
grinder are to be kept in good condition. Replace any unreadable or damaged labels.
#05876.0000
#24237.0000
#20545.0000
#05942.0000
DG-2 ONLY
3
10854 030300
ELECTRICAL REQUIREMENTS
This grinder has an attached cordset and requires 2-wire, grounded service rated 120 volts ac, 15 amp,
single phase, 60 Hz.
OPERATING CONTROLS
Off/On/Start Switch
OFF - (upper position) Switching to this position stops all operation of the grinder.
ON - (middle position) The switch will return to this position after a grind cycle has begun and
will remain in this position after grinding has ceased.
START - (lower, momentary position) Pressing the switch to this position and releasing initiates
a grind cycle.
Hopper Selector Switch
LEFT - Switching to this position allows beans to be ground from the left
hopper.
RIGHT - Switching to this position allows beans to be ground from the
right hopper.
P734
Dispense Timer - DG-2
The dispense timer controls the amount of beans that will be ground in a cycle. The timer can be adjusted
to dispense a different amount from each hopper. The scale is from 0.1 to 60.0 seconds. Refer to the
Adjustments section for timer setting chart. See page 7.
+/Increase - (left momentary push-button)
DISPENSE TIME (Seconds)
I 0.0
DISPLAY
IncreaseDecrease
+
Readout will be displayed for 5 minutes.
Timer can only be adjusted
while readout is displayed.
WARNING
HAZARDOUS VOLTAGE
Pressing this button will increase the dispense interval on the timer while
the readout is displayed. The interval will change slowly for the first second’s
indication, then speed-up for the next fifteen second’s indication, and increase
very fast after that until it reaches the limit on the scale.
DISPLAY - (center momentary push-button)
Pressing this button will display the current timer readout. The timer can
only be adjusted while the readout is displayed. The indication on the display
will last for five minutes.
UNPLUG GRINDER
BEFORE REMOVING!
–/Decrease - (right momentary push-button)
P595
Pressing this button will decrease the dispense interval on the timer while
the readout is displayed. The interval will change slowly for the first second’s
indication, then speed-up for the next fifteen second’s indication, and increase very fast after that until it reaches
the limit on the scale.
4
10854 030300
NOTICE
DG-2 INITIAL SET-UP
1.WARNING - Unplug grinder before removal of any panel.
2.Read NOTICE attached to upper front inspection panel.
3.Remove upper front inspection panel located below control switches and
the rear panel.
4.Remove shipping bracket, materials and discard.
5.Reinstall upper front inspection panel and rear panel.
6.Open the top lid(s). Clear all foreign objects and shipping material from the
hopper compartments and the entrance to the grind chambers.
7.Remove the lower front inspection panel.
8.Plug-in the grinder.
9.Select either the left or right hopper with the selector switch. Do not press
the start switch.
10.The dispense timer panel readout will indicate the present timer setting in
seconds and will remain displayed for five minutes.
11.Increase or decrease the timer setting to obtain the desired amount of coffee for the hopper selected by pressing the appropriate button (+ or –).
12.Repeat steps 9 thru 11 for the other hopper. The display will go out on its
own. Reinstall lower front inspection panel.
13.Fill the hopper compartments with whole bean coffee. (Capacity 6 pounds
each). The grinder is now ready for use.
DISPENSE TIME (Seconds)
I 0.0
DISPLAY
IncreaseDecrease
+
Readout will be displayed for 5 minutes.
Timer can only be adjusted
while readout is displayed.
WARNING
HAZARDOUS VOLTAGE
UNPLUG GRINDER
BEFORE REMOVING!
P734
WDG-2 INITIAL SET-UP
1.WARNING - Unplug grinder before removal of any panel.
2.Read NOTICE attached to the upper front inspection panel.
3.Remove upper front inspection panel located below control switches and
the rear panel.
4.Remove shipping bracket, materials and discard.
5.Reinstall upper front inspection panel and rear panel.
6.Open the top lid(s). Clear all foreign objects and shipping material from the
hopper compartments and the entrance to the grind chambers.
7.Remove the four screws securing the lower front inspection panel and carefully pull out far enough to view and operate the digital control display
assembly.
8.Plug-in the grinder.
9.Select either the left or right hopper with the selector switch. Do not press
the start switch.
10.The digital control display assembly screen displays selected weight when
idle. When grinding - display resets to 0.00 and shows increasing weight.
Display shows final weight for ten seconds and returns to selected weight.
11.Use (+) or (-) buttons and left or right hopper selector switch to set selected
weights, .50 oz minimum - 16 oz maximum.
NOTE: Refer to function list on page 8 for recalibration of weigh control
assembly if necessary.
NOTICE
The Shipping Bracket and
All Packing Material
Behind This Panel
MUST be Discarded
Before Using Grinder!
(Refer to the Operating & Service Manual for
Additional Set-up Information.)
NOTICE
For connection to Bunn-Omatic
Coffee Brewer Models:
Dual, OT, Single, & System III only.
(24 volt N.E.C. Class 2 circuit only.)
B
U
N
N
N
IO
T
A
R
O
P
R
O
C
IC
T
A
-M
-O
N
N
U
B
Y
B
D
E
R
U
T
C
A
F
U
N
A
M
.
.A
.S
, U
IS
O
IN
L
, IL
D
L
IE
F
G
IN
R
P
S
/N
S
L
E
M
D
O
S
T
T
A
W
M
P
. A
.C
A
S
T
L
O
V
Z
T
R
E
H
E
IR
W
E
S
A
H
P
:
S
T
N
E
T
A
P
G
IN
W
O
L
L
O
F
E
H
T
F
O
E
R
O
M
R
O
E
N
O
R
E
D
N
U
D
E
R
E
V
O
C
G
IN
D
N
E
P
E
B
Y
A
M
S
T
N
E
T
A
P
R
E
H
T
O
E
R
O
M
R
O
E
N
O
P928
-
+
+
F
F
U
U
N
N
C
C
+
F
U
N
C
PP927
P927
5
10854 030300
SPECIAL SET-UP FOR FLAVORED COFFEE BEANS
1.WARNING - Unplug grinder before removal of
any panel.
2.Select the hopper to be used for flavored coffee
beans.
3.Remove upper front inspection panel located
below control switches.
4.Locate dechaffer blade lever for hopper(s) selected in step #2.
5.Rotate lever clockwise approximately 90°.
6.Remove clip(s) from bag inside of grinder housing and clip to the right of the lever. This will
hold the dechaffer open.
7.Reinstall upper front inspection panel.
25705.0000
02311.0000(4)
S
S
R
R
A
A
O
O
C
C
T
H
E
M
O
P
R
T
O
Y
U
O
H
N
G
O
P
H
R
P
O
E
F
L
R
E
B
Y
C
L
D
E
N
I
A
R
N
G
01384.0000
E
E
IN
IN
F
F
E
E
S
S
R
R
A
A
Y
O
O
L
C
C
B
.
R
S
A
O
M
C
R
E
E
S
V
S
O
A
C
U
E
E
E
B
R
S
IN
IN
I
E
H
T
F
F
E
E
C
I
T
E
R
E
M
A
H
C
R
O
G
T
F
H
N
E
E
I
E
M
O
V
B
Y
C
P
R
O
I
L
T
R
O
M
Y
T
E
B
E
U
.
O
H
N
B
R
R
S
A
G
O
O
M
E
C
M
P
R
H
R
P
A
O
E
F
L
R
E
E
B
H
Y
E
C
C
S
L
D
E
V
N
I
A
R
N
G
S
O
A
C
U
E
B
R
S
I
E
H
T
R
O
G
F
N
E
I
E
V
B
O
R
M
E
B
01384.0002
P1178
6
10854 030300710854 030300
CLEANING
EXTERIOR SURFACES
The use of a damp cloth rinsed in any mild, nonabrasive, liquid detergent is recommended for cleaning all
surfaces on Bunn-O-Matic equipment. Care should be taken not to scratch the hopper or windows with any
abrasive material. Regular cleaning will keep your grinder looking new for years.
GRIND CHAMBER
1. WARNING - Unplug grinder before removal of any panel or grind chamber housing parts.
2. Empty all beans from both hoppers.
3. Remove upper front inspection panel located below control switches.
4. Remove the two nuts holding dispense chute cover. Carefully wipe inside surface of dispense chute and
cover with a dry clean cloth.
5. Select a grind chamber to clean first. Each grind chamber should be disassembled, cleaned and reassembled
before cleaning the opposite side.
6. Remove the two screws holding front cover to burr housing. Carefully remove burr housing front cover.
Clean the inside surface with a dry stiff nonmetallic bristle brush and wipe with a dry clean cloth.
7. Carefully remove rotor button, rotor, brass bushing and steel washer from grinder. Clean all parts with a dry
stiff nonmetallic bristle brush and wipe with a dry clean cloth.
8. Clean the grind chamber with a dry stiff nonmetallic bristle brush and wipe with a dry clean cloth. Use a small
screw driver to dislodge coffee packed in the discharge chute at the base of the grindchamber and wipe
clean. Use care not to damage dechaffer blade.
9. Reinstall steel washer, brass bushing (flanged end first), rotor, rotor button and front cover to burr housing.
10. Repeat steps 6 through 9 on remaining grind chamber.
11. Reinstall dispense chute cover.
12. Reinstall upper front inspection panel.
13. Refer to adjustments section below to vary the grind dispensed from each grind chamber.
COFFEE GRINDING
1. Select (either left or right hopper) with selector switch and visually inspect the desired hopper for an ample
supply of whole bean coffee.
2. Place a paper filter into the brew funnel. The filter must not be folded-over or tilted to one side.
3. Insert the funnel into the funnel rails and push until it stops.
4. Momentarily press off/on/start switch to the "START" lower position and release. The grinding action will stop
automatically after the preset amount of ground coffee is dispensed into the funnel.
5. Remove the funnel from the grinder and level the bed of grounds by gently shaking.
6. The loaded funnel is now ready for use in any commercial drip coffee brewer according to the manufacturer’s
instructions.
P934
STEP #5
P935
STEP #1
P931
STEP #2
P932P933
STEP #3
STEP #4
8
10854 030300
ADJUSTMENTS
The grind can be set from fine to very coarse. The grind may be adjusted for use in most commercial coffee
brewers. The following procedures should be used to make adjustments.
NOTE - On DG-2 grinders a change in the burr adjustment will also change the amount dispensed. Any adjustment to the burrs should be followed by an adjustment of the timer,
Burr Adjustment
1. Unplug the grinder and empty all beans from the hopper(s).
2. Plug-in the grinder, place funnel with filter into the funnel rails. Momentarily
O
C
-
F
I
E
S
R
A
N
E
press the off/on/start switch to the “START” (lower) position (with desired
hopper selected) and release, run a few grind cycles until all of the coffee in the
grind chamber is dispensed.
3. Remove the upper front inspection panel.
4. Loosen the burr adjustment screw from its locked position.
B
N
U
5. Hand loosen the adjustment locking nut around the screw approximately one
turn.
N
P581
P581
6. Make sure funnel with filter is still in place in the funnel rails. Press the off/on/start switch to the “START”
(lower) position and release,slowly turn the adjusting screw in a clockwise direction until a metallic whine is
heard due to the rubbing of the grinding burrs. (It may be necessary to start more than one grind cycle to
obtain this sound.)
7. Make a mark with a pen on the decal to note the position of the arrow on the grind adjustment screw.
8. The following settings approximately correspond to the CBC recognized grinds. All are referenced from the
arrow position marked in step #7.
FINE GRIND: Rotate the adjusting screw 7 hash marks in a counterclockwise direction.
DRIP GRIND: Rotate the adjusting screw 8 hash marks in a counterclockwise direction.
REGULAR (COARSE) GRIND: Rotate the adjusting screw 12 hash marks in a counterclockwise direction.
NOTE: Exact adjustment will vary according to bean roast or added flavoring.
9. Hold the adjusting screw in its set position with a screwdriver while tightening the lock nut to a snug position
by hand. The lock nut should now be tight against the burr housing front cover.
10. Repeat steps 1 thru 9 for remaining hopper if desired.
11. Reinstall upper front inspection panel.
Timer Adjustment - DG-2
1. Unplug the grinder and remove the lower front inspection panel.
2. Determine the grind setting. (The factory setting is drip, to determine other settings, refer to the previous
section.)
3. Use the instructions below to find the approximate timer setting for the grind and amount of coffee desired.
4. Plug-in grinder and select (left or right) desired hopper. Momentarily press the “DISPLAY” (center) button.
The display will indicate the current timer setting and will allow adjustment. Press the “+” or “-” buttons as
required to obtain the desired grind time. The interval will change slowly for the first second’s indication,
then speed-up for the next fifteen second’s indication, and increase very fast after that until it reaches the
limit on the scale. Set the timer for the desired amount of coffee to be ground.
5. Verify the setting by weighing a few samples. Use the chart on page 10 as an approximate guide only.
9
10854 030300
Coffee Weight/Timer Settings
Approx. 4.0 seconds per ounce, Medium Roast, Drip Grind.
Approx. 5.5 seconds per ounce, Dark Roast, Drip Grind.
Time will vary depending on bean density & grind size.
Check samples by weight.
DIGITAL CONTROL DISPLAY ASSEMBLY FUNCTION LIST - WDG-2
FUNCTION NO. FUNCTION RANGE
Place funnel with filter into rails, press (Func) button to advance to Function
One.
MIN. MAX.
1.When entering this function, load sensor is tared. To gain access to remaining
functions, press (+) or (-) button once to enter password(0). Display will read
(0) now press (Func).
2.Set weight offset, right grinder. Press (+) or (-) to adjust if necessary. Press
(Func).
3.Set weight offset, left grinder. Press (+) or (-) to adjust if necessary. Press
(Func).
4.Enter calibration mode? If yes, press (+) display will read (1) then press (Func).
If no, press (Func).
NOTE - Pressing (Func) will return to idle display.
5.Use present weight as tare for calibration? If yes, press (+). Display will read
(1) then press (Func). If no, press (Func).
6.To calibrate by grinding coffee, press (+) display will then read (1) then press
(Func).
7.Enter desired calibration weight using (+) and (-) buttons. Then press start
switch on grinder. Display changes to 0.00 and shows increasing weight as
coffee is ground. When grinding stops and 7 has reappeared in left corner of
the display. Push (Func) to advance to Function 8
before removing funnel.
0000 9999
0.009.99
0.009.99
0 = No1 = Yes
0 = No1 = Yes
1 = Grind
3.0016.00
8. Weigh sample grind and enter actual weight onto the display by pressing (+)
or (-) if necessary. To abort and retain old calibration enter 0.00. Press (Func)
when complete.
10.Enter new password. To keep same password press (Func), to change password press (+) or (-), press function to enter new password and return to
function 0, normal operation.
NOTE: Display shows "----" when taring. Do not disturb while this is shown.
NOTE: WDG2 Models can be converted from weight based settings to timed
settings by pressing the (+) and (-) buttons for 10 seconds. Repeating the
process will convert back to weight based settings.
10
0.0016.00
00009999
10854 030300
TROUBLESHOOTING
A troubleshooting guide is provided to suggest probable causes and remedies for the most likely problems
encountered. If the problem remains after exhausting the troubleshooting steps, contact the Bunn-O-Matic
Technical Service Department.
•Inspection, testing, and repair of electrical equipment should be performed only by qualified
service personnel.
•All electronic components have 120 volt ac and low voltage dc potential on their terminals.
Shorting of terminals or the application of external voltages may result in board failure.
•Intermittent operation of electronic circuit boards is unlikely. Board failure will normally be
permanent. If an intermittent condition is encountered, the cause will likely be a switch contact
or a loose connection at a terminal or crimp.
•Make certain that all electrical connections are tight and isolated.
WARNING
•Exercise extreme caution when servicing electrical equipment.
•Turn power OFF when servicing, except when electrical tests are specified.
•Follow recommended service procedures.
•Replace all protective shields or safety notices.
Problem
Grinder will not start.
Probable Cause
1. No power or incorrect voltage
2. Off/On/Start switch
3. (A) Timer - DG-2
(B) Weigh Control Board WDG-2
4. Motor overload protector
Remedy
(A) Plug-in the grinder.
(B) Check the voltage at the wall
outlet with a voltmeter. It must
be 120 volts ac.
(A) Momentarily press the Off/On/Start
switch to the “START” (lower) position.
(B) Refer to
switch for testing procedures. See page
13.
Refer to
cedures. See page 16.
Refer to
for testing procedures. See page 18.
Remove Grinder rear cover. Press the
red “Reset” button, one located on rear
of each motor. Listen carefully for a
“click”. This resets the motor protection circuit and indicates that an overload may have been encountered by the
motor. (An overload can occur when
something other than coffee is inserted
into the hopper for grinding.) Refer to
Service -
cedures. See page 14.
Service
Service
Service
- Timer for testing pro-
- Weight Control Board
Motors for disassembly pro-
- Off/On/Start
11
10854 030300
TROUBLESHOOTING (cont.)
ProblemProbable CauseRemedy
Grinder will not start. (cont.)
Grinder will not shut off.
Grinder starts, but will not dispense from
either hopper.
Timer will not display or displays
incorrectly.
5. Motors
6. Fuse
1. Off/On/Start switch
2. Timer
1. Hoppers
2. Blockage of hoppers
1. Timer
Refer to
cedures. See page 14.
Refer to
cedures. See page 20.
A) Place the switch in the “OFF" upper
position.
(B) Refer to
for testing procedures. See page 13.
Refer to
cedures. See page 16.
Begin each grind cycle by visually inspecting the hoppers for ample supplies of whole
bean coffee.
Foreign materials must not block the openings at the bottom of the hoppers..
(A) Unplug the grinder. Wait a few seconds and plug it in again.
Service
Service -
Service
- Motors for testing pro-
Fuse for testing pro-
Service
- Off/On/Start Switch
- Timer for testing pro-
Incorrect amount of coffee. DG-2
Incorrect coffee grind dispensed.
Cooling fan not running.
1. Volume adjustment
2. Motor circuit assembly
1. Burr adjustment
1. Off/On/Start switch
2. Fan
(B) Refer to
cedures. See page 16.
Refer to the
7.
Refer to
bly replacement procedures. See page
16.
Refer to the
7.
Switch must be in the "ON" (middle)
position
Refer to
Service
Adjustments
Service
- Motor Circuit Assem-
Adjustments
Service -
- Timer for testing pro-
section. See page
section. See page
Fan. See page 20.
12
10854 030300
TROUBLESHOOTING (cont.)
Problem
LED will not come on when motor is
running.
Weigh control assembly leaking oil.
WDG-2
Incorrect amount of coffee. WDG-2
Probable CauseRemedy
1. No power
2. Faulty LED
WDG-2 DIGITAL DISPLAY CONTROL FAULT CODES
NOTE:
the fault code. The fault will also show on the digital display.
If the grinder stops or fails to start, the green L.E.D. should be flashing. The number of flashes corresponds to
Check timer and for loose connections.
Refer to
Replace - See removal and replacement
page 23
Check function list on setting the weight
to be ground (page 8), if settings are
ok replace weigh control assembly. See
page 23 for removal and replacement.
Service -
LED. See page 21.
FAULT
1
2
4
PROBLEM
Grinder on for three
seconds without a
weight increase.
Tare error.
Grinder motor shutting off
in middle of grind.
PROBABLE CAUSE
Selected hopper ran out
of whole bean coffee.
Foreign objects in motor
grinding burrs causing
motor to shut off.
Scale cannot find tare due
to excess vibration.
Power or hopper selector
switch changed during
grind.
REMEDY
Fill selected hopper with
whole bean coffee.
Clear motor gringing burs
of all foreign objects and
press the red "RESET"
button on rear of motor.
Move grinder to solid,
vibration free counter.
Do not change switches
during grind.
13
10854 030300
SERVICE
01311.0001(10)
02328.0004(4)
25713.0000
25716.0000(2)
PERSONAL INJURY
HAZARD.
KEEP FINGERS AND
FOREIGN OBJECTS
OUT OF HOPPER
OR CHUTE OPENING.
CAUTION
This section provides procedures for testing and
replacing various major components used in this
grinder should service become necessary. Refer to
Troubleshooting
cause of any problem.
WARNING - Inspection, testing, and repair of electrical equipment should be performed only by qualified
service personnel. The grinder should be unplugged
when servicing, except when electrical tests are required and the test procedure specifically states to
plug-in the grinder.
for assistance in determining the
WARNING
Use only on a properly protected circuit
capable of the rated load.
Electrically ground the chassis.
Follow national/local electrical codes.
Do not use near combustibles.
An extension cord, when used, must be shorter
than 20 feet if 16-gage 3-conductor wire, or
shorter than 10 feet if 18-gage 3-conductor wire.
FAILURE TO COMPLY RISKS EQUIPMENT
DAMAGE, FIRE, OR SHOCK HAZARD
READ THE ENTIRE OPERATING MANUAL
INCLUDING THE LIMIT OF WARRANTY AND
Coffee Brewer Models:
Dual, OT, Single, & System III only.
(24 volt N.E.C. Class 2 circuit only.)
B
U
N
N
N
O
A
I
R
O
T
C
P
R
T
C
O
N
A
M
I
-
N
O
U
-
D
Y
B
B
E
T
R
F
C
U
U
A
N
A
M
A
.S
.
U
S
.
IN
L
I
O
,
I
D
L
IE
L
,
IN
F
S
R
G
P
N
/
S
E
D
O
M
L
T
S
T
W
A
P
M
A
C
.
A
.
S
L
O
T
V
T
H
R
Z
E
IR
E
W
S
A
E
H
P
S
:
E
T
P
N
T
G
A
L
N
W
F
O
I
L
O
F
T
O
E
H
E
R
R
O
O
N
M
O
D
E
R
N
U
E
E
V
R
O
D
C
E
IN
D
G
P
N
B
E
E
Y
S
A
M
E
T
P
E
N
T
H
O
A
R
E
T
R
R
O
O
M
O
E
N
P737
Component Access
WARNING - Unplug the grinder before the removal of
any panel or the replacement of any component.
All components are accessible by the removal
of the upper and lower front inspection panels, hopper assembly, and rear panel.
P735
The upper front inspection panel is attached with
four 8-32 slotted head screws.
The rear panel is attached with eight 8-32 slot-
ted head screws.
NOTE: Disconnect fan motor leads from main wiring
harness.
P738
The lid is attached to hopper divider with four
6-32 slotted head screws. Hopper dividers attached
to hopper and housing with two 6-32 slotted head
screws. Remove lid and hopper divider as an assembly.
Weigh Control Board ................................. 18
Weigh Control Assembly ........................... 21
10854 030300
SERVICE (cont.)
25716.0000(2)
02328.0004(4)
The hopper is attached with ten #8-32 x .25” slotted head locking screws. Remove hopper by lifting
up and swing out the rear of the grinder to avoid
scratching of windows.
Off/On/Start Switch
25713.0000
01311.0001(10)
P739
the switch.
4.Check for continuity across the terminals on the
left side of the switch when it is in the center
"ON" position. Continuity must not be present in
the upper "OFF" position.
If continuity is present as described, reconnect the
wires, the switch is operating properly.
If continuity is not present as described, replace the
switch.
Removal and Replacement:
1.Remove all wires from the switch terminals.
2.Compress the clips inside the front of the housing and gently push the switch through the opening.
3.Push the new switch into the opening and spread
the clips to retain the switch in the housing.
4.Refer to the following illustration when reconnecting the wires.
P740
Location:
The Off/On/Start switch is located to the left side
on the front of the housing above the upper front
inspection panel.
Test Procedure:
1.Unplug the grinder.
2.Remove all wires from the switch terminals.
3.Check for continuity across the terminals on the
right side of the switch when it is held in the
lower "START" position. Continuity must not be
present across these terminals in the center or
upper position.
If continuity is present as described, proceed to #4.
If continuity is not present as described, replace
RED TO J1 - 1
PNK TO SELECTOR SWITCH
REAR VIEW
ORA TO J4 - 7
ORA TO J4 - 6
WHI/RED TO FAN
P741
Hopper Selector Switch
P734
Location:
The Hopper Selector Switch is located in the
center on the front of the housing above the upper
front inspection panel.
15
10854 030300
SERVICE (cont.)
Hopper Selector Switch (cont.)
Test Procedure:
1.Disconnect grinder from the power supply.
2.Remove all wires from the switch terminals.
3.Place the selector switch in the left position.
4.Check for continuity across the center and right
terminals on the rear of the switch.
5.Continuity must not present across the center
and left terminals on the rear of the switch.
6.Check the bottom row, then the top row of terminals.
If continuity is present as described proceed to #7.
If continuity is not present as described, replace the
switch.
7.Place the selector switch in the right position.
8.Check for continuity across the center and left
terminals on the rear of the switch.
9.Continuity must not be present across the center and right terminals on the rear of the switch.
10. Check the bottom row , then the top row of terminals.
Motors
PNK TO OPTIONAL MULTISET SWITCH
PNK TO OFF/ON/ START SWITCH
YEL TO J1- 1
BLU TO RIGHT MOTOR
VIO TO J4 - 3
WHI/ BLU TO LEFT MOTOR
REAR VIEW
4
P742
If continuity is present as described, reconnect the
wires, the switch is operating properly.
If continuity is not present as described, replace the
switch.
Removal and Replacement:
1.Remove all wires from the switch terminals.
2.Compress the clips inside the front of the housing and gently push the switch through the opening.
3.Push the new switch into the opening and spread
the clips to retain the switch in the housing.
4.Refer to the following illustration when re- connecting the wires.
1
2
5
3
NOTICE
For connection to Bunn-Omatic
Coffee Brewer Models:
Dual, OT, Single, & System III only.
(24 volt N.E.C. Class 2 circuit only.)
REAR VIEW
BUNN
M
F
U
N
A
S
M
L
O
E
D
O
R
E
D
N
U
D
E
R
E
O
C
V
M
O
R
O
O
E
N
N
IO
O
T
A
R
O
P
R
C
IC
T
A
O
M
-
-
N
N
U
B
Y
B
D
E
R
U
T
C
A
.
.A
.S
, U
O
IS
IN
L
, IL
D
L
IE
G
F
IN
R
P
/N
S
S
T
T
A
W
P
M
. A
.C
A
S
T
O
L
V
Z
T
R
E
H
E
IR
W
E
S
A
H
P
:
S
T
N
E
T
A
G
P
IN
O
W
L
O
L
F
E
H
T
O
F
O
E
R
M
R
O
E
N
G
IN
D
N
E
P
E
B
Y
M
A
S
T
N
E
T
A
P
R
E
H
T
O
E
R
P743
1. Motor Circuit Assembly
2. Motor & Circuit Assembly Mounting Screws
3. Motor Mounting Screws
4. Hopper Selector Switch
5. Motor Mounting Bracket
16
Location:
The motors are located in the center part of the
housing just below the hopper.
10854 030300
SERVICE (cont.)
Motor (cont.)
Test Procedure:
1.Disconnect grinder from the power supply.
2.Remove upper front inspection panel.
3.Remove the two 1/4"-20 screws (A) holding the
front cover (B).
4.Remove load disc (C) from burr auger rotor/assembly (D).
5.Remove burr auger rotor/spring assembly
(D) from the burr housing (H).
6.Remove rear panel.
7.Disconnect the red, black and blue wires from
the left or right motor to the motor circuit assembly (1).
8.(A) Left Motor - Disconnect blue wire on
the left motor from the blue wire to the
hopper selector switch.
(B) Right Motor- Disconnect the blue wire
on the right motor from the white/blue
wire to the hopper selector switch.
9.Connect leads of an ohm meter to the blue
wires from the left or right motor. Check
for continuity.
If continuity is present the motor overload is good.
If continuity is not present press the red "RESET" button. Listen carefully for a "click". This resets the motor overload. Recheck for continuity. If continuity is
now present the motor overload is reset. If motor overload does not reset replace motor.
10.Set an ohm meter to read at least 10 ohms.
Connect leads from ohm meter to the black
and red wires from the left or right motor.
The ohm reading should be approximately
10 ohms. Rotate the motor shaft approxi mately 1/8 turn through one full rotation. If
ohm readings are consistent motor wind ings are good. If reading vary more than
±1 ohm, replace motor.
Removal and Replacement:
1.Disconnect red, black and blue wires from the
motor to be removed from the motor circuit assembly (1).
2Loosen the two #10-32 slotted head screws (2)
attaching motor circuit assembly (1) to motor
mounting bracket (5).
3.Remove motor circuit assembly (1) with wires
from harness and the opposite motor connected.
4.Right Motor - Disconnect blue wire on motor
from blue wire on hopper selector switch (4).
Left Motor - Disconnect blue wire on motor from
white/blue wire on hopper selector switch (4).
5.Using a 7/16" socket, extension and rachet remove two 1/4"-20 hex head capscrews and
lockwashers (3) attaching front of motor to front
of mounting bracket (5).
6.Remove two #10-32 slotted hex head screws (2).
7.Lift motor out of mounting bracket (5) and remove through the rear of grinder with hopper
collar and discharge chute assembly attached.
8.Remove four #10-24 slotted hex head screws
attaching discharge chute to motor. Remove discharge chute. Set discharge chute and screws
aside for reassembly.
9.On new motor assembly with hopper collar install discharge chute assembly using four #1024 slotted hex head screws.
10. Mount new motor, hopper collar and discharge
chute assembly on mounting bracket using two
1/4"-20 hex head capscrews and lockwashers
(3) and two #10-32 slotted hex head screws (2)
and one external tooth lockwasher.
11. Install motor circuit assembly (1) between head
of the two #10-32 slotted hex head screws (2)
and external tooth lockwashers. Tighten screws
(2).
12. Refer to wiring diagram (pages 24 & 25) and
connect wires from motor to motor circuit assembly (1) and hopper selector switch (4).
17
10854 030300
SERVICE (cont.)
Motor (cont.)
Removal and Replacement - GRIND CHAMBER
H
G
D
COARSE FINE
COARSE FINE
T
H
E
M
O
P
R
T
O
Y
U
H
G
O
P
H
P
L
Y
C
L
E
Y
L
B
.
E
N
I
F
M
R
-
E
E
E
S
S
R
V
A
S
O
O
A
C
C
E
R
S
I
E
H
T
R
O
G
F
N
E
I
E
V
N
B
N
C
O
U
I
B
R
M
T
E
E
O
N
B
R
E
M
R
A
O
E
F
R
E
B
H
C
D
N
I
A
R
N
G
C
B
20667.0000
20666.0000
F E A
T
H
E
M
O
P
R
T
O
Y
U
H
G
O
H
L
Y
C
COARSE FINE
COARSE FINE
T
O
N
E
P
R
P
O
E
F
R
E
B
H
C
L
D
E
N
I
A
R
N
G
Y
L
B
.
E
N
I
F
M
R
-
E
E
E
S
S
R
V
A
S
O
O
A
C
C
E
R
S
I
E
H
T
R
O
G
F
N
E
I
E
V
N
B
N
C
O
U
I
B
R
M
E
E
B
R
M
A
P744
1.Remove the two 1/4"-20 screws (A) holding the
front cover (B) to the burr housing (H). Carefully
remove the burr housing front cover with adjusting screw and nut. Inspect adjusting screw to
see if worn.
Replace if excessively worn or
damaged.
2.Remove load disc (C) from burr auger rotor/
spring assembly (D). Inspect disc to see if worn.
Replace if excessively worn or damaged.
3.Carefully remove burr auger rotor/spring assembly (D) from burr housing (H). Inspect burr for
wear.
Replace if excessively worn or damaged.
4.Remove bushing (E) and washer (F) from motor
shaft.
5.Remove the two 1/4"-20 screws attaching stationary burr (G) to burr housing (H). Remove
and inspect burr for wear.
Replace if excessively worn or damaged.
6.Inspect the grind chamber and remove any foreign materials. The burrs will not properly seat
in the chamber if any material or coffee particles
remain.
7.Reinstall the stationary burr (G), washer (F),
bushing (E), burr auger rotor/spring
assembly(D), load disc(C) and burr housing front
cover(B) with adjusting screw and nut to the burr
housing(H).
8.Refer to
Adjustments
section (page 7) to vary
the grind dispensed.
Motor Circuit Assembly
P750
Location:
The motor circuit assembly is located on the
rear of motor mounting bracket.
Test Procedure:
1.The motor circuit assembly is a line filter for
motor electrical noise.
2.If the timer settings are erratic or change replace
the motor circuit assembly board.
Removal and Replacement:
1.Remove all wires.
2.Loosen the two #10-32 slotted hex head screw
and lift motor circuit assembly off.
3.Install new motor circuit assembly between head
of screws and external tooth lockwashers.
Tighten screws.
4.Refer to
Wiring Diagram
(pages 24 & 25) and
reinstall wires.
Timer - DG-2
nds)
E (Seco
DISPENSE TIM
Decrease
DISPLAY
.
s
e
t
u
in
m
5
r
Increase
d
o
f
e
t
d
s
e
ju
.
y
d
d
a
l
a
e
p
y
e
is
la
b
p
d
ly
e
is
n
d
+
o
ill b
n
t is
a
w
t
u
u
o
r c
o
d
e
E
G
d
a
a
im
G
e
re
T
A
IN
R
ile
T
h
N
L
w
O
R
V
A
S
U
W
O
D
R
A
Z
A
H
DER
G
IN
GR
OVIN
01516.0000
REM
UNPLUG
RE
BEFO
P745
Location:
The timer is located on the grinder base, behind
the lower front inspection panel.
18
10854 030300
SERVICE (cont.)
Timer - DG-2 (cont.)
Test Procedure:
1.Disconnect grinder from the power source.
2.Slide timer with wires connected from housing.
3.Place the hopper selector switch in the left position.
4.Disconnect eight pin plug J4 from timer board.
5.Check the voltage between J4-1 and J4-2 with
a voltmeter. Connect the grinder to the power
source. The indication must be 120 volts AC.
6.Disconnect grinder from the power source.
10. Disconnect grinder from the power source.
If voltage is present as described, proceed to #11.
If voltage is not present as described, replace timer
and motor circuit board with part number
25725.1000.On grinders prior to S/N DG00002660
also order main wiring harness 25762.0001.
11. Reconnect the wires.
12. Place the hopper selector in the right position.
13. Repeat steps #4 thru 10.
If voltage is present as described, proceed to #7.
If voltage is not present as described, refer to the
wiring diagram and check grinder wiring harness.
7.Check the voltage between J4-2 and J4-6 with
a voltmeter when the "OFF/ON/START" switch is
in the "ON" position.Connect the grinder to the
power source. The indication must be 120 volts
AC.
8.Disconnect grinder from the power source.
If voltage is present as described, proceed to #9.
If voltage is not present as described, refer to the
wiring diagram and check the grinder wiring harness.
9.Grinders prior to S/N DG00002660:
Check the voltage between J4-3 (+) and J4-5 () with a voltmeter set to read DC voltage when
the "OFF/ON/START" switch is in the "START" position. The indication must be 110 volts DC minimum.
Grinders S/N DG00002660 - UP
Check the voltage between J4-3 and J4-5 with a
voltmeter when the "OFF/ON/START" is in the
"START" position. The indication must be 120
volts AC.
Grinders with One or Two Brewer Optional Interface
1.Set the brewer selector switch on one third batch
with grinder "OFF/ON/START" switch in the "ON"
position.
2.Select the two third's batch, if the readout is not
different then adjust the settings and return selector switch to one third batch. The readout
should now be different.
3.Select full batch, if the readout is not different
then adjust the settings and return selector switch
to two third's batch. The readout should be different.
4.Repeat steps 1 thru 3 for the opposite side.
NOTE: Each brew selection has its own readout. If
readouts do not differ with each brew selection after
adjusting settings, check interface cable. If interface
cable is ok replace timer and motor circuit board
with part number 25725.1000. On grinders prior to
S/N DG00002660 also order main wiring harness
part number 25762.0001.
Removal and Replacement:
1.Separate the grinder wiring harness connectors
from the timer circuit board.
2.Refer to the illustration on next page when reat-
taching the connectors.
3.Refer to the
Adjustments
(page 7) section to re-
set the volume dispensed.
19
10854 030300
SERVICE (cont.)
Timer - DG-2 (cont.)
RED TO MOTOR CIRCUIT BOARD
(Prior to S/N DG00002660)
WHI TO MOTOR CIRCUIT BOARD
(S/N DG00002660 - UP)
ORA TO OFF/ON/START SWITCH
ORA TO OFF/ON/START SWITCH
BLK TO FUSE HOLDER
WHI TO POWER CORD
VIO TO SELECTOR SWITCH
5
1
2
6
7
3
8
4
J4
1
2
678
RED TO OFF/ON START SWITCH
YEL TO SELECTOR SWITCH
GRN TO OPTIONAL MULTISET SWITCH
TAN TO OPTIONAL INTERFACE CONNECTOR
GRY TO OPTIONAL INTERFACE CONNECTOR
4
5
3
J1
10
9
Weigh Control Board - WDG-2
TAN TO INTERFACE CONNECTOR
GRY TO INTERFACE CONNECTOR
BLK TO GRINDING LED
PNK TO INTERFACE CONNECTOR
P746
Test Procedure:
1.Disconnect grinder from the power source.
2.Slide the weigh control board with wires connected from housing.
3.Place the hopper selector switch in the left position.
4.Disconnect eight pin plug J4 from weigh control
board.
5.Check the voltage between J4-1 and J4-2 with a
voltmeter. Connect the grinder to the power
source. The indication must be 120 volts AC.
6.Disconect grinder from the power source.
If voltage is present as described, proceed to #7.
If voltage is not present as described, refer to the wiring diagram and check grinder wiring harness.
P929
Location
The weigh control board is located on the grinder base
behind the lower front inspection panel.
20
7.Check the voltage between the J4-2 and J4-6
with a voltmeter when the "OFF/ON/START"
switch is in the "ON" position.Connect grinder to
the power source. The indication must be 120
volts AC.
10854 030300
SERVICE (cont.)
Weigh Control Board - WDG-2 (cont.)
Grinders with One or Two Brewer Optional Interface
8.Disconnect grinder from the power source.
If voltage is present as described, proceed to #9.
If voltage is not present as described, refer to the wiring diagram and check the grinder wiring harness.
9.Check the voltage between J4-3 and J4-5 with a
voltmeter when the "OFF/ON/START" is in the
"START" position. Connect grinder to the power
source. The indication must be 120 volts AC.
10. Disconnect grinder from the power source.
If voltage is present as described, proceed to #11.
If voltage is not present as described, replace weigh
control board.
11. Reconnect the wires.
12. Place the hopper selector in the right position.
13. Repeat steps #4 thru 10.
1.Set the brewer selector switch on one third
batch with grinder "OFF/ON/START" switch in the
"ON" position.
2.Select the two third's batch, if the readout is not
different then adjust the settings and return selector switch to one third batch. The readout
should now be different.
3.Select full batch, if the readout is not different
then adjust the settings and return selector switch
to two third's batch. The readout should be different.
4.Repeat steps 1 thru 3 for the opposite side.
NOTE: Each brew selection has its own readout. If
readouts do not differ with each brew selection after
adjusting settings, check interface cable. If interface
cable is ok replace weigh control board.
Removal and Replacement:
1.Separate the grinder wiring harness connectors
from the weigh control board.
2.Refer to the illustration below when re- attach-
ing the connectors.
3.Refer to the
Adjustments
(page 7) section to re-
set the volume dispensed.
VIO TO SELECTOR SWITCH
WHI TO POWER CORD
BLK TO FUSE HOLDER
WHI TO MOTOR CIRCUIT BOARD
ORA TO OFF/ON/START SWITCH
ORA TO OFF/ON/START SWITCH
2
3
1
4
J4
7
8
556
TAN TO INTERFACE CONNECTOR
GRY TO INTERFACE CONNECTOR
BLK TO GRINDING LED
PNK TO INTERFACE CONNECTOR
RED TO OFF/ON/START SWITCH
YEL TO SELECTOR SWITCH
GRN TO OPTIONAL MULTISET SWITCH
TAN TO OPTIONAL INTERFACE CONNECTOR
GRY TO OPTIONAL INTERFACE CONNECTOR
J5
DIGITAL CONTROL DISPLAY
ASSEMBLY CORD CONNECTION
GRY TO WEIGH CONTROL ASSEMBLY
BLK TO WEIGH CONTROL ASSEMBLY
112
3
J1
49
6
7
8
10
2
J3
3
4
RED TO WEIGH CONTROL ASSEMBLY
ORA TO WEIGH CONTROL ASSEMBLY
P930
21
10854 030300
SERVICE (cont.)
Fan
WARNING
Use only on a properly protected circuit
capable of the rated load.
Electrically ground the chassis.
Follow national/local electrical codes.
Do not use near combustibles.
P747
Fuse
Location:
NOTICE
For connection to Bunn-Omatic
Coffee Brewer Models:
Dual, OT, Single, & System III only.
(24 volt N.E.C. Class 2 circuit only.)
BUNN
M
A
N
U
M
O
D
E
L
C
O
V
E
R
E
D
U
N
D
E
O
N
E
O
R
M
A
F
C
U
T
R
E
D
B
Y
B
U
N
N
-O
-
M
A
IC
C
O
T
R
P
O
R
A
IO
T
N
S
P
R
N
I
G
D
E
L
, I
I
F
IN
O
L
L
IS
.A
U
.
.S
,
S
/N
A
C
V
O
.
S
.
T
L
A
M
P
S
A
T
W
T
P
H
A
S
E
W
R
I
E
H
E
R
Z
T
R
O
N
E
O
R
M
O
R
E
H
O
T
E
F
F
O
O
L
L
IN
G
W
P
A
E
:
N
S
T
T
O
R
O
E
H
T
E
R
P
A
E
N
S
T
M
T
A
B
Y
E
N
E
P
D
N
I
G
P748
Location:
The fan is mounted on upper part of the rear in-
spection panel.
Test Procedure:
1.Unplug the grinder.
2.To gain access remove the rear panel with fan
attached.
3.Disconnect fan motor leads from the main harness.
4.Check voltage across the WHT/RED and WHT
leads to the main harness with a voltmeter. Plugin the grinder. With the "OFF/ON/START" switch
in the center "ON" position the indication must
be 120 volts AC.
5.Unplug the grinder.
If voltage is present as described, replace the fan.
If voltage is not present as described, refer to wiring
diagrams and check the wiring harness.
The fuse is located in the fuse holder on the rear
of grinder near the bottom next to the power cord.
Test Procedure:
1.Unplug the grinder.
2.Remove cap and fuse from fuse holder.
3.Remove fuse from the cap.
4.Check for continuity through the fuse.
If continuity is present as described, reinstall the fuse,
the fuse is operating properly.
If continuity is not present as described, replace the
fuse.
Removal and Replacement:
1.Remove cap from fuse holder.
2.Remove fuse from fuse holder, inspect, if
blown discard.
3.Install a new SC 10 x .312" fuse in fuse
holder.
4.Reinstall fuse holder cap.
Removal and Replacement:
1.Remove rear panel with fan attached.
2.Disconnect fan motor leads from main harness
3.Remove four #6-32 flat head screws and locknuts attaching fan and fan guard to rear inspection panel. Discard fan and set guard, screws and
locknuts aside for reinstallation.
4.Reinstall fan guard and new fan to the rear
panel making sure the air flow direction
is away from rear panel.
5.Connect leads from fan to the main wiring
harness.
6.Reinstall rear panel.
22
10854 030300
SERVICE (cont.)
L.E.D
P749
Location:
The L.E.D is located on the front of the grinder
just above hopper selector switch.
Test Procedure:
1.Unplug the grinder.
2.Remove the wire nuts from both sets of wires.
3.With a voltmeter set to read DC volts. Attach the
positive (+) lead to the black and pink wires and
the negative (-) lead to the gray wires.
4.Connect grinder to the power supply.
5.Initiate a grind cycle. Voltage should be approximately 2 volts DC.
Weigh Control Assembly - WDG-2
00718.0000
01593.0000
If the voltage is present as described the L.E.D. is
operating properly.
If the voltage is not present as described proceed to
#6.
6.After initiating a grind cycle in step #5 the voltage was approximately 5 volts DC. Replace the
L.E.D. If the voltage is approximately 0 volts refer to wiring diagrams and check the wiring harness.
Removal and Replacement:
1.Remove upper front inspection panel.
2.Disconnect PNK and GRY wires from L.E.D.
3.Using a 5/16" open end wrench remove nut on
back of front housing securing L.E.D. Remove
L.E.D and discard.
4.Install new L.E.D through front of grinder housing and secure with nut.
5.Connect PNK and GRY wires from L.E.D. Refer
to wiring diagram on pages 24 & 25.
P941
Location:
The weigh control assembly is located behind
the lower front inspection panel just under and
behind the funnel rails.
23
10854 030300
SERVICE (cont.)
Weigh Control Assembly - WDG-2 (cont.)
00718.0000
01593.0000
5
3
4
2
1.Front Inspection Panel
2.Weigh Control Board and Mounting Bracket
3.Weigh Control Mounting Bracket
4.Weigh Control Assembly
6
8
1
7
5.Pivot Arm
6.Funnel Rails Mounting Bracket
7.Funnel Tab
8.Slot in Housing Assembly
P941
24
10854 030300
SERVICE (cont.)
Weigh Control Assembly - WDG-2 (cont.)
Removal and Replacement
1.Disconnect grinder from the power source.
2.Remove the four #6-32 truss head screws securing lower front inspection panel (1). Remove
panel with digital control display assembly attached.
3.Remove the one #6-32 truss head screw securing the weigh control board mounting bracket
(2) to the weigh assembly mounting bracket (3).
4.Slide weigh control board mounting bracket and
control board (2) out of weigh assembly mounting bracket (3) far enough so the connectors on
the grinders main wiring harness and the connector on the weight assembly leads can be disconnected.
5.Disconnect connectors.
6.Remove weigh control board mounting bracket
and weigh control board (2) from the grinder.
7.Remove the two #10-32 slotted head screws
securing weigh control mounting bracket (3) to
the base of the grinder and the two #10-32 keps
nuts securing the weigh control mounting
bracket (3) to the rear of the grinder housing.
8.Slide weigh control mounting bracket (3) from
grinder housing far enough to have access to
weigh control assembly (4).
9.Holding pivot arm w/overload assembly (5) up
remove the four #8-32 pan head screws securing weigh control assembly (4). Remove and discard weigh control assembly (4).
10. Holding pivot arm w/overload assembly (5) up
install the new weigh control assembly (4) to the
mounting bracket (3) using four #8-32 pan head
screws.
11. Slide weigh control assembly mounting bracket
(3) on to the two studs on the rear of the grinder
housing and secure with two #10-32 keps nuts.
NOTE - Carefully guide all wires while installing the
weigh mechanism. The funnel tab (7) on the funnel rails mounting bracket (6) must be in clearance slot (8) in the grinder housing and must
move freely up and down.
12. Secure weigh control assembly mounting bracket
(3) to grinder base with two #10-32 slotted head
screws.
13. Slide the weigh control bracket and weigh control board (2) into the weigh control mounting
bracket (3) far enough to reconnect the eight and
ten pin connectors from the main wiring harness
and the four pin connector from the weigh control assembly. Connect the wiring.
14. Refer to the illustration on page 19 when reattaching the connectors.
NOTE - Inspect for pinched wires.
15. Slide weigh control bracket and weigh control
board (2) the rest of the way into the weigh control mounting bracket (3) and secure with one
#6-32 truss head screw.
16. Reinstall lower front inspection panel with digital control display assembly attached using four
#6-32 truss head screws.
17. Connect the grinder to the power source and follow the function list on page 8 for information
on setting the weight to be ground.