Bryant 108-451 User Manual

451P
Installation Instructions
GAS-FIRED AIR CONDITIONER

bri|ant

I
Installation of the Model 108-451 Gas Air Conditioning Absorption Unit consists of the following steps:
I. Locate and Mount Absorption Unit VI. Check-Out and Operation
II. Connect Chilled Water Lines VII. Adjust Gas Input III. Electrical Connections VIII. Balance System IV. Gas Connections IX. Purge Non-Condensibles
V. Charge System with Water
Each of the above steps is discussed in detail in this instruction. Read the eiitin starting installation.
^^^s^u(^ton ^^or

DO NOT

SIZE 108
SERIES B
39451D8 Rev. 4/12/65
P V

I. LOCATE AND MOUNT ABSORPTION UNIT

The absorption unit may be located at ground level or on the roof. Consult local codes for information concerning proximity to property lines, height above roof, obstructions, etc.

A. MOUNTING BASE

1. Use non-combustible materials.

2. Suggested types of mounting base for ground installation:
a. Precast concrete lintels.
Use three lintels the depth of unit, one each
urider right and left end of unit and one at center of unit.
b. Concrete blocks.
Use one block at each corner of unit plus blocks under the two long sides midway between the corner blocks.
c. Concrete slab.
Minimum thickness 4 inches.
3. For installation on a roof or other combustible material leave sufficient clearance between unit sub-base and roof for proper air circulation. Use precast concrete lintels or concrete blocks as described in paragraph 2 above or steel beams. Check local codes.

B. CLEARANCES

1. Absorption unit should ance of 2 feet on all sides from any adjacent ob struction.
2. Avoid locating the unit where hot condenser discharge air can impinge on nearby obstructions and mix with the inlet air supply. The condenser air discharges upward. The unit should be located out side of the plumb line from any over-hang.
II. CONNECT CHILLED WATER LINES
A. MATERIALS
Refer to section on “Freezing Weather Protection”
at the end of this instruction.

1. Piping

a. Polyethylene Plastic Pipe — use medium
density flexible pipe whose wall thickness ap proximates Schedule 40 pipe (Commercial Stand ard CS 197-60). Pipe must be virgin plastic. Do not use pipe manufactured from re-claimed plas tic.
b. Copper - satisfactory substitute.
c. Galvanized - satisfactory substitute.

2. Fittings

a. Galvanized - use when possible.
b. Brass - satisfactory substitute.
c. Nylon - satisfactory substitute.
REMOVE
hax&-.a_m.i.aijn.um—clear
WATER OUTLET
ELECTRICAL CONNECTIONS
1"
2 GAS
CONNECTION
Cooling Capacity Heat Input Condenser Air Delivery CFM 14,000 Water Flow (minimum required) GPM
Maximum friction loss handled by Chiller Pump Maximum elevation of coil above chiller Pump Drive 230 v 60 cy 1 phase HP Fan Drive 230 v 60 cy 1 phase HP Minimum Wire Size * Refrigerant Type Refrigerant Amount Approximate Shipping Weight
* Satisfactory where distance, measured along wire path, between unit and connection into main panel does not exceed 100 ft. Where distances are longer, wire sizes should be increased accordingly.
I" KNOCKOUTS
WATER INLET
1 ”

IZ F.P.T.

108-451 BTUH BTUH 330,000
Ft. Head Ft.
AWG 12
LB 55
LB
108,000
22
45 49 1/3
1
717
2200
108/451
2-
Table I
Nominal
Pipe Size
Inches
1
IVa
IV2
* Note: Values shown in above table are for one direction only. The total length of pipe from chiller to coil and return would be double the above table values. The above table applies to single unit installations only.
B. PIPE LENGTH AND DIAMETER
Polyethylene Pipe
Size 108
48' 272' 610'
Table I shows maximum length of pipe of different diameters that can be used between the pump dis charge and the coil inlet and still maintain mini-, mum allowable (design) water flow rate.
1. Multiply table values by two to obtain the total
length of pipe from chiller to coil and return.
2. Length is measured along the pipe path and therefore includes vertical distance between the water coil and the chiller.
Allowable Distance* Between Coil and Chiller
Copper Pipe
Size 108
67'
210'
492'
3. On installations where the outside piping freezes
and the coil is in a heated air stream, precautions must be taken to provide for water expansion. The connecting polyethylene plastic pipe acts as an expansion vessel if there is enough footage of this
pipe in the heated space (space not subject to freezing). The following table shows the minimum lengths (total inlet and outlet) of plastic piping of various diameters that are required for both sizes of coils to provide adequate expansion volume.
Galvanized Pipe
Size 108
72'
285' 642'
3. Lengths shown in Table I are based on using a total of eight elbows in the entire water line (chil
ler to coil and return). Lengths are predicated on the
use of a Bryant matching water coil. For greater distances use larger pipe or add a pump.
C. INSULATION
1. Insulate supply and return lines separately.
2. Material should be of good quality and be covered with a good vapor barrier. Armaflex or equivalent is recommended.
Wall thickness: 1/2'' wall thickness - south of 40° N. latitude
Nominal Pipe Size
Inches
1
VA
Length of Plastic Pipe
in Feet
70 40
IV2 29
If the total plastic chilled water line footage in the heated space is not as long as the minimum values shown in the table, tee a vertical pipe of sufficient volume into either of the coil connections to provide for expansion, or the line should be drained.
3/8" wall thickness - north of 40° N. latitude
D. HEIGHT OF COIL
ABOVE ABSORPTION UNIT
Maximum vertical distance from chiller outlet to top of coil is 49 feet. For greater heights, a greater pumping head is required. Increasing the pipe size will not help.
E. WATER COIL CONNECTIONS
1. If cooling coil is used in connection with heat
ing unit, install cooling coil in parallel with or downstream of heating unit to avoid condensation in the heating unit.
2. If coil is located in warm air stream, do not connect polyethylene pipe directly to coil. Connect a minimum of 24 inches copper or galvanized pipe to both the coil inlet and outlet. Then connect the plastic pipe to these nipples.
III. ELECTRIC CONNECTIONS
1. Make all electric connections in accordance with the National Electrical Code and any local ordi nances or codes that might apply.
2. Provide a separate power supply for the air conditioner.
3. Provide a fused disconnect switch within sight
of and not more than 50 feet from the absorption unit. Use 35 amp standard fuse.
4. The absorption unit is shipped fully wired from the factory. Connection of 230V power and low volt age connection to the thermostat control are re
quired in the field. Before proceeding, inspect factory wiring for loose connections which may have resulted during shipment.
- 3 -
108/451
5. Figures 3 & 4 are the Wiring Diagrams for the natural gas unit. Figures 5 8s 6 are the Wiring Dia grams for an LPG unit.
6. Disconnect pump electrical lead at terminal 7 in front control box before energizing unit when ready to check field wiring.
pump dry.

IV. GAS CONNECTIONS

Do not operate the
Consult local gas company before making any gas connections. In case of conflict with this instruc tion, local requirements should be followed.
Before selecting the size and type of pipe that is to be used for installing the absorption unit, be sure to check with local gas company for the neces
sary information. The size of the gas pipe to be used between meter and unit will depend upon the length of run and the allowable pressure loss estab lished by the utility.
The gas connections to the unit are made at the 1/2 inch combination regulator-shut offs at each of the two generators. The gas supply pipes enter the
unit through openings located at lower left rear and lower right rear of unit. Install 1/2 inch ground joint unions and 1/2 x 3/4 inch ells adjacent to each combination regulator-shut off using two 1/2 inch X close nipples. The gas supply pipe from the meter should terminate at the rear of the unit with a tee. Install 3/4 inch pipe from this tee through the openings in the rear casing to the 1/2 x 3/4 inch ells adjacent to the regulator-shut offs at each generator.
A. wrench-type shut-off valve should be installed in the gas supply line within sight of, and convenient to, the 451. It is recommended that ground joint unions be installed in the gas supply piping just outside the unit.
Joint compound (pipe dope) which is resistant to
the action of liquefied petroleum gases should be applied sparingly and only to the male threads of
the joints. After gas pipe connections have been made, purge
the lines and check for leakage. Use a soap and water solution or other such material. Turn off power supply to unit when purging the lines to prevent glow coils in reignition pilots from being energized. Never use matches, candles, flame or other source of ignition to check leakage.

PILOT

The natural gas unit is equipped with two reignition type pilots (one pilot in each generator). The pilots will light automatically when supplied with gas and
are electrically energized. The circuit is arranged to light the pilots sequentially. Several minutes must be allowed for the first pilot to ignite and make contact before second pilot will be energized.
To manually light the pilots use the procedure out lined on the Lighting Instruction Plate attached to generators. The pilot flame should be soft blue in color. The flame should be of sufficient length to provide good impingement on the unimetal element
of the Bryant pilot. Flame should extend upward between the carry-over ports of the two adjacent burners.
If the pilot flame does not have the appearance described above, it may be adjusted by means of the manual pilot shut-off valve which is equipped with an adjustable screw. Turn the handle to the full-open position and remove the screw cap on the valve handle, thus exposing the adjustable screw. Turn adjusting screw until flame has the desired appearance. Replace screw cap.

V. CHARGING THE SYSTEM WITH WATER

Caution: Do not run the pump dry. Freezing con
ditions will not damage the pump; however, do not attempt to operate the pump when chiller or chilled water lines are frozen.
1. Turn off main manual gas shut-off valve.
2. Remove the filler caps located on top of both
chiller tanks.
3. Disconnect water line at chiller inlet. (When
installing the chilled water lines, it is advisable to leave this connection open until lines have been flushed.)
4. Fill tanks with tap water through the filler opening of one tank until the distributor pans are covered with water. A garden hose is useful for this filling operation.
5. Start pump. Continue to supply water to the tank and operate pump until all foreign matter has beeii flushed from the lines. Then remove hose.
Note: If water does not circulate when the pump
is started, air may be trapped in the pump. Bleed the air from pump through the 1/8 inch slotted head
108/451
-4-
Loading...
+ 7 hidden pages