Body Solid G1S User Manual

Page 1
by
Body-S olid
®
Assembly Instructions
Page 2
STEP
1
Be careful to assemble all components in the sequence they are presented.
NOTE: Finger tighten all hardware in this step. Do Not
A. Attach Main Base Frame (A) to Rear Base Frame (B) using:
B. Attach 2 Foot Caps (9) to Rear Base Frame (B) as shown.
C. Attach Vertical Support Pillar (D) and Flat Plate (10) to Main Base Frame (A) using:
Two 42 (3/8” x 2 3/4” hex head bolt) Four 53 (3/8” flat washer) Two 52 (3/8” nylon lock nut)
D. Attach Angled Support Pillar (E) to Main Base Frame (A) using:
Two 42 (3/8” x 2 3/4” hex head bolt) Four 53 (3/8” flat washer) Two 52 (3/8” nylon lock nut)
wrench tighten until end of step 6.
E. Attach Convex End Cap (3) to the front of the Main Base Frame (A).
Attach Convex End Cap (3) to the top of the short pillar on top of the Main Base Frame (A). Attach Rubber Stop (35) with Jam Nut (34) to the short pillar on the Main Base Frame (A) as shown.
mm
Inch
2
Page 3
STEP
1
3
Page 4
STEP
2
Be careful to assemble all components in the sequence they are presented.
NOTE: Finger tighten all hardware in this step. Do Not
A. Attach Top Frame (F) to Angled Support Pillar (E) using:
Two 43 (3/8” x 2 1/2” hex head bolt) Two 53 (3/8” flat washer)
Note: Both bolts (43) go into the threaded housing inside the Angled Support Pillar (E)
B. Bolt Top Frame (F) and 2”x4” Plate (G) to Vertical Support Pillar (D) using:
Two 43 (3/8” x 2 1/2” hex head bolt)
Note: Both bolts (43) go into the threaded housing inside the Vertical Support Pillar (D)
C. Put Foam Roller Bar (H) through Angled Support Pillar (E) and attach two Foam Rollers (18)
with two 1” Roller End Cap (8) as shown. There are two possible openings to mount Foam Roller Bar (H) to Angled Support Pillar (D). If the main user of this gym is 6’ tall (or more) mount in the top opening, for shorter people (under 6’) mount in the lower opening. This piece is not
inter-changeable, once these pads are installed they are permanent.
wrench tighten until end of step 6.
mm
Inch
4
Page 5
STEP
2
5
Page 6
STEP
3
Be careful to assemble all components in the sequence they are presented.
Note: Wrench tighten all hardware in this bolts until after the installation of the weight stack in step 6.
A. Loosen Allen Head Bolts (63) at the bottom of Bench Press Frame (J).
Slide out Pivot Shaft (Y) from inside of Bench Press Frame (J).
B. Attach Bench Press Frame (J) to Main Base Frame (A) using the Pivot Shaft (Y) as shown.
Retighten Allen Head Bolts (63) at the bottom of Bench Press Frame (J).
C. Attach Convex End Caps (3) to the top of Vertical Support Pillar (D), front of Top Frame (F),
and to the bottom of Bench Press Frame (J) as shown.
step only. Do not wrench tighten Frame
mm
Inch
6
Page 7
STEP
3
7
Page 8
STEP
4
Be careful to assemble all components in the sequence they are presented.
Note: Finger tighten all hardware in this step (except where noted in step 4A).
A. Attach Low Pulley Bracket (K) to Foot Brace (L) using:
One 50 (1/2” nylon lock nut)
Note: Wrench tighten the Nylon Lock Nut (50), but do not over-tighten. Over-tightening will restrict the Low Pulley Bracket (K) range of motion.
B. Attach Foot Brace (L) to Main Frame (A) using:
Two 42 (3/8” x 2 3/4” hex head bolt)
Four 53 (3/8” flat washer)
Two 52 (3/8”nylon lock nut)
Note: Foot Brace (L) goes onto the right side of the gym (standing in front, facing the gym). Make sure holes for the weight stack are on the opposite side (left side).
C. Attach Seat Extension Frame (M) and 2”x5” Plate (N) to Angled Support Pillar (E) using:
Two 41 (3/8” x 3” hex head bolt)
Two 52 (3/8” nylon lock nut)
D. Attach bottom of Seat Extension Frame (M) to Main Base Frame (A) using:
One 42 (3/8” x 2 3/4” hex head bolt)
One 52 (3/8” nylon lock nut)
E. Attach 2 Convex End Caps (5) and Grip Tape (15) to Foot Brace (L) as shown.
Attach 1 Convex End Cap (6) and Rubber Pad (27) to Seat Extension Frame (M) as shown.
Make sure Rubber Stop (35) and Jam Nut (34) is pre-installed into Seat Extension Frame (M).
mm
Inch
8
Page 9
STEP
4
9
Page 10
STEP
5
Be careful to assemble all components in the sequence they are presented.
Note: Finger tighten all hardware in this step (except where noted in step 5B).
A. Put Foam Roller Bar (H) through Leg Frame (P) and attach 2 Foam Rollers (18) with
3” Plastic Washer (26) on the inside and 1” Roller End Cap (8) on the outside as shown.
Note: There are two possible holes to mount Foam Roller Bar (H) to Leg Frame (P). If the main user of this gym is 6’ tall (or more) mount in the lower opening, for shorter people (under 6’) mount in the top opening. This piece is not once these pads are installed they are permanent.
B. Attach Leg Frame (P) to Seat Extension Frame (M) using:
One 40 (1/2” x 3 1/4” hex head bolt) Two 56 (1/2” round end cap washer) One 50 (1/2” nylon lock nut)
Two 21 (1/2” bolt cover)
Note: Wrench tighten bolt (40) only. Leave all other bolts finger tight. Round End Cap Washers (56) hold Bolt Caps (21) in place.
C. Put Foam Roller Bar (H) through Seat Frame (Q) and attach 2 Foam Rollers (18) with
3” Plastic Washer (26) on the inside and 1” Roller End Cap (8) on the outside as shown.
inter-changeable,
D. Put two Convex End Caps (3) into the top and bottom of Leg Frame (P). Put 1 3/4” x 1 3/4”
End Cap (7) into the bottom of Seat Frame (Q). Slide Seat Frame (Q) into Seat Extension
Frame (M), hold in place with Threaded Pop Pin (60). Attach two Convex End Caps (6) to the
front and back of Seat Frame (Q) as shown.
mm
Inch
10
Page 11
STEP
5
11
Page 12
STEP
6
Be careful to assemble all components in the sequence they are presented.
A. Place two 2 1/2” Rubber Donuts (11) on Rear Base Frame (B) over the two widest openings.
Slide two Chrome Guide Rods (R) through the two 2 1/2” Rubber Donuts (11) and into Rear
Base Frame (B).
B. Slide fifteen Weight Stack Plates (30) onto the two Chrome Guide Rods (R). Make sure
the holes in the Weight Stack Plates (30) are facing forward as shown.
C. Connect Top Plate (19) to Selector Rod (20) using:
One 49 (7/16” x 1” round bolt)
Note: Selector Rod Top Bolt (70) is preinstalled in Selector Rod (20).
D. Slide Top Plate (19) and Selector Rod (20) onto Guide Rods (R).
Note: Make sure that the Round Bolt (49) is facing forward as shown.
E. Slide two Shaft Collars (29) onto Guide Rods (R). Make sure the Allen Head Screws inside
the Shaft Collars (29) are loose.
F. Insert two Guide Rods (R) into Top Weight Stack Frame (S).
Attach 2” x 5” Plate (N) and Top Weight Stack Frame (S) to Top Frame (F) using:
Two 41 (3/8” x 3” hex head bolt)
Four 53 (3/8” washer)
Two 52 (3/8” nylon lock nut)
Insert Convex End Cap (3) into Top Weight Stack Frame (S) as shown.
G. Secure two Shaft Collars (29) into Top Weight Stack Frame (S). Tighten the Allen Head
Screws in each Shaft Collar.
H. You should now wr
ench tighten all bolts and nuts on the main frame unit.
mm
Inch
12
Page 13
STEP
6
13
Page 14
STEP
7
Be careful to assemble all components in the sequence they are presented.
A. Attach Back Pad (T) to Angled Support Pillar (E) using:
Two 47 (5/16” x 2 3/4” hex head bolt)
Two 55 (5/16” spring lock washer)
Two 54 (5/16” flat washer)
Note: Do not over tighten Pad Bolts (47), over tightening will strip the T-nuts pressed into the wood.
B. Attach Seat Pad (U) to Seat Frame (J) using:
Two 48 (5/16” x 1 3/4” hex head bolt)
Two 55 (5/16” spring lock washer)
Two 54 (5/16” flat washer)
Note: Do not over tighten Pad Bolts (48), over tightening will strip the T-nuts pressed into the wood
.
C. Connect the Water Bottle Bracket (31) to the Vertical Support Pillar (D) using:
Two 32 (1/8” x 3/8” screw)
D. Slide the Water Bottle Holder (33) onto the Water Bottle Bracket (31) as shown.
mm
Inch
14
Page 15
STEP
7
15
Page 16
STEP
8
Be careful to assemble all components in the sequence they are presented.
Lat Pulldown Cable (23)
Ball Stop End
Metal Ball End
3225 mm
Note: All Pulleys in this step are 4 1/4” diameter, except where noted in step 8B. Leave all pulley bolts hand tight until step 12 is completed.
A. See diagram 1. Begin at the high pulley station. Route the metal ball end of Lat Cable (23) up and through
the opening where the Pulley (A1) will be installed and then down Pulley (A2) will be installed.
B. See diagram 2. Install 3 1/2” diameter Pulley (A1), under
Install Pulley (A2) into Top Frame (F) under
Two 42 (3/8” x 2 3/4” hex head bolt) Four 13 (pulley spacer) Two 52 (3/8” nylon locknut)
C. Route Cable (23) through the top portion of the Adjustable Double Bracket (V) as shown in diagram 1.
Hold Cable (23) in place by installing Pulley (A3) as shown in diagram 2 using:
One 45 (3/8” x 1 3/4” hex head bolt) One 52 (3/8” nylon locknut)
D. See diagram 1. Route Cable (23) up and through the opening above where Pulley (A4) will be installed and
then down
E. Install Pulley (A5) to the top of the Top Weight Stack Frame (S), as shown using:
One 45 (3/8” x 1 1/2” hex head bolt) One 52 (3/8” nylon lock nut)
Install Pulley (A4) to the bottom of the Top Weight Stack Frame (S), as shown using:
One 44 (3/8” x 1 3/4” hex head bolt) One 52 (3/8” nylon lock nut)
and through the opening next to Pulley (A5) as shown.
Cable (23) using:
Cable (23) and into Top Frame (F) as shown.
10’ 7”
through the next opening where
F. See diagram 1A. The Metal Ball End of Cable (23) should be hanging just above the Weight Stack. Remove
Bolt (71) from Selector Rod Top Bolt (70), slide Metal Ball End of Cable (23) through Selector Rod Top Bolt (70). Attach Cable End Shaft (101) and securely tighten Allen Screw (102). Pull Cable (23) tight, so Cable End Shaft (101) fits securely inside Selector Rod Top Bolt (70). Reinstall Bolt (71) in Selector Rod Top Bolt (70).
Note: Make sure the Selector Rod Top Bolt (70) is threaded inside Selector Rod (20) at least one half inch. Make sure Spring Lock Washer (72) is in place and wrench tighten Jam Nut (73).
mm
Inch
16
Page 17
Diagram 1
Cable Installation
STEP
Lat Pulldown
Cable
3 1/2” diameter pulley
Start at high pulley station by inserting the Metal Ball End here.
!
Selector Rod Top Bolt (70) must be threaded a minumum of 1/2” into the Selector Rod (20), and Jam Nut (73) tightened securely against spring lock washer (72) to ensure proper connection. Check the Jam Nut (73) once a week to make sure it is tight.
WARNING
Diagram 1A
8
!
Diagram 2
Pulley Installation
3 1/2” diameter
pulley
17
Page 18
STEP
9
Be careful to assemble all components in the sequence they are presented.
Ab Crunch Cable (25)
Ball Stop End
Stamped Eye End
2480 mm
Note: All Pulleys in this step are 4 1/4” diameter, except where noted in step 9B. Leave all pulley bolts hand tight until step 12 is completed.
A. See diagram 1. Insert stamped eye end of the Ab Crunch Cable (25) into the opening in Angled
Support Pillar (E), above Back Pad (T), and pull entire length through.
B. Install 3 1/2” diameter Pulley (B1), under
in diagram 2 using:
One 42 (3/8” x 2 3/4” hex head bolt) Two 13 (pulley spacer) One 52 (3/8” nylon lock nut)
C. Route Cable (25) through Single Pulley Hook (W) as shown in diagam 1 and hold cable in place
by installing Pulley (B2) using:
One 45 (3/8” x 1 1/2” hex head bolt) One 52 (3/8” nylon lock nut)
D. See diagram 1. Route Cable (25) up through the bottom of Adjustable Double Bracket (V),
and hold cable in place by installing Pulley (B3) as shown using:
One 45 (3/8” x 1 1/2” hex head bolt) One 52 (3/8” nylon lock nut)
E. Attach the stamped eye end of Cable (25) to the Vertical Support Pillar (D) with a Snap Link (12)
as shown in diagram 1.
Cable (25) and into Angled Support Pillar (E) as shown
8’ 1”
F. See diagram 1. Take up the slack in the cable by hanging the Double Bracket (X) in the proper
position and install Pulley (B4) as shown in diagram 2 using:
One 45 (3/8” x 1 1/2” hex head bolt) One 52 (3/8” nylon lock nut)
mm
Inch
18
Page 19
Diagram 1
Cable Installation
STEP
9
Start here at ab crunch station by inserting the Stamped Eye End here.
Ab Crunch
Cable
Diagram 2
Pulley Installation
3 1/2” diameter pulley
3 1/2” diameter
pulley
19
Page 20
STEP
10
Be careful to assemble all components in the sequence they are presented.
Low Pulley / Leg Extension Cable (24)
Ball Stop End
3050mm
Note: All Pulleys in this step are 4 1/4” diameter. Leave all pulley bolts hand tight until step 12 is completed.
A. See diagram 1. Insert stamped eye end of the Low Pulley / Leg Extension Cable (24) through
Low Pulley Bracket (K) and install Pulley (C1) as shown using:
One 45 (3/8” x 1 1/2” hex head bolt) Two 53 (3/8” flat washer) One 52 (3/8” nylon lock nut)
B. Route Cable (24) up and through the bottom portion of the Double Pulley Bracket (X), and hold
Cable (24) in place by installing Pulley (C2) as shown using:
One 45 (3/8” x 1 1/2” hex head bolt) One 52 (3/8” nylon lock nut)
C. See diagram 1. Route Cable (24) down and through the hole in the Main Base Frame (A), where
Pulley (C3) will be installed. Route Cable (24) under
D. Route Cable (24) up
be installed. Route Cable (24) through the opening in the Seat / Extension Frame (M). Attach Stamped eye end of Cable (24) to the Leg Frame (P) as shown in diagram 2 using:
One 42 (3/8” x 2 3/4” hex head bolt) Two 13 (pulley spacer) One 52 (3/8” nylon lock nut)
Main Base Frame (A).
and through the opening in the Main Base Frame (A) where Pulley (C4) will
10’
Stamped Eye End
E. Insert Pulley (C5) into Seat / Extension Frame (M), under Cable (24), as shown using:
One 42 (3/8” x 2 3/4” hex head bolt) Two 13 (pulley spacer) One 52 (3/8” nylon lock nut)
F. Take up the slack in the Cable (24) by installing Pulleys (C3) and (C4) into Main Base Frame (A)
as shown in diagram 2 using for each pulley:
One 42 (3/8” x 2 3/4” hex head bolt) Two 13 (pulley spacer) One 52 (3/8” nylon lock nut)
mm
Inch
20
Page 21
Diagram 1
Cable Installation
STEP
10
Start at low pulley station by inserting the Stamped Eye End here.
Diagram 2
Pulley Installation
Low Pulley / Leg
Extension Cable
21
Page 22
STEP
11
Be careful to assemble all components in the sequence they are presented.
Seated Press Cable (22)
Stamped Eye End
1440 mm 4’ 8.5”
Note: All Pulleys in this step are 4 1/4” diameter. Leave all pulley bolts hand tight until step 12 is completed.
A. See diagram 1. Attach either end of Seated Press Cable (22) to Angled Support Pillar (E) as
shown using:
One 43 (3/8” x 2 1/2” hex head bolt)
Two 53 (3/8” flat washer)
One 52 (3/8” nylon lock nut)
B. Route Cable (22) through the pulley bracket on Bench Press Frame (J) and install Pulley (D1)
as shown using:
One 45 (3/8” x 1 1/2” hex head bolt)
One 52 (3/8” nylon lock nut)
C. Route Cable (22) through Angled Support Pillar (E) as shown in diagram 1.
D. Route Cable (22) through pulley bracket where Pulley (D2) will be installed and hold cable in
place by installing Pulley (D2) as shown in diagram 2 using:
One 45 (3/8” x 1 1/2” hex head bolt)
One 52 (3/8” nylon lock nut)
Stamped Eye End
E. Connect the end of Cable (22) to the hook on the bottom of Single Pulley Hook (W) as shown in
diagram 1.
mm
Inch
22
Page 23
Diagram 1
Cable Installation
Seated Press
Cable
STEP
11
Diagram 2
Pulley Installation
Start here by attaching the Seated Press Cable to the Angled Support Pillar.
23
Page 24
STEP
12
Be careful to assemble all components in the sequence they are presented.
NOW IS THE TIME TO MAKE ALL NECESSARY
CABLE ADJUSTMENTS
After cable installation is complete you must check all cables for proper tension. Obvious signs that cable tension problems exist include:
c Top Plate (19) does not rest directly on the top Weight Stack Plate (30). c The holes in the Selector Rod (20) do not line up with holes in the Weight Stack Plates (30). c Cable(s) are sloppy and there is no resistance from the weight stack for the first few
inches of the exercise.
There are Three areas for cable adjustment on the G1S:
A. Selector Rod Top Bolt (70) B. Adjustments in Adjustable Double Bracket (V). C. Rubber Stop (35) on Main Base Frame (A).
SEE NOTE 1 ON PAGE 25
If there is to much tension, and the Top Plate (19) is not resting directly on top of the weight stack plates:
1st. -Tighten Rubber Stop (35). 2nd. -Move Pulley (B3) down
Pulley (A3) up
If there is to much play or excessive slack;
1st. -Loosen Rubber Stop (35). 2nd. -Move Pulley (B3) up
Pulley (A3) down
3rd. -Screw the Selector Rod Top Bolt (70) farther into the Selector Rod (20) of the weight stack.
NOTE: Cables should be inspected daily and adjusted periodically to ensure safe and smooth operation.
NOTE: After cable adjustment is complete, you should now wrench tighten all bolts. Do NOT re-tighten any pad bolts.
to a higher hole in Adjustable Double Bracket (V).
to a lower hole in Adjustable Double Bracket (V), or move
to a higher hole in Adjustable Double Bracket (V), or move
to a lower hole in Adjustable Double Bracket (V).
24
Page 25
STEP
12
NOTE 1
Check Jam Nut (73) weekly to be sure it is tight and locked onto the Selector Rod (20).
Selector Rod
Top Bolt
!
WARNING
Selector Rod Top Bolt (70) must be threaded a minumum of 1/2” into the Selector Rod (20), and Jam Nut (73) tightened securely against spring lock washer (72) to ensure proper connection.
!
Loosen
Turn and loosen Rubber Stop (35) to take up space and tighten cable.
25
Page 26
G1S Mainframe Parts List
KEY# QTY PART# DESCRIPTION
A B D E F G H J K L M N P Q R S V W X
1 1 1 1 1 1 3 1 1 1 1 2 1 1 2 1 1 1 1
G1SMBF-A G1SRBF-B G1SVSP-D G1SASP-E G1STF-F G1SP-G G1SFRB-H G1SBPF-J G1SLPB-K G1SFB-L G1SSEF-M G1SP-N G1SLF-P G1SSF-Q G1SCGR-R G1STWSF-S G1SWADB-V G1SSPH-W G1SWDB-X
MAIN BASE FRAME REAR BASE FRAME VERTICAL SUPPORT PILLAR ANGLED SUPPORT PILLAR TOP FRAME
2”X4” PLATE FOAM ROLLER BAR BENCH PRESS FRAME LOW PULLEY BRACKET FOOT BRACE SEAT/EXTENSION FRAME 2” X 5 1/2” PLATE LEG FRAME SEAT FRAME CHROME GUIDE ROD TOP WEIGHT STACK FRAME ADJUSTABLE DOUBLE BRACKET SINGLE PULLEY HOOK DOUBLE BRACKET
Part numbers are required when ordering parts.
26
Page 27
G1S Hardware List
KEY# QTY PART# DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12 13 15 16 17 18 19 20 21 26 27 28 29 30 31 32 33 34 35
1 1 7 2 2 3 1 6 2 1 2 5 12 2 14 2 6 1 1 2 4 1 6 2 15 1 2 1 2 1
JPIN4.25 JSCH.18 JCEC22 JCEC22LE JCEC24 JCEC12 JCEC1.75X1.75 JREC1 JFC22 JFP22.5 JRD2.5 JSNAP3 JPS.62X.37 JGT5.5 JPP4.25W.75 JPP3.5W.75 JFOAM3.5x8 JTP10 JSR15 JBC.5 JPW3 JRP1.5X1.75 JREC1.5 JSC1.37X.75 JSP10 JWBB JS.125X.37FT JWBH JJN.37 JRS1.5
WEIGHT STACK PIN 4 1/4” X 7/16” STEEL CHAIN 3/16” CONVEX END CAP 2” X 2” I.D. 1 3/8” CONVEX END CAP 2” X 2” I.D. 1 7/16” CONVEX END CAP 2” X 4” CONVEX END CAP 1” X 2” END CAP 1 3/4” X 1 3/4” ROLLER END CAP 1” FOOT CAP 2” X 2” FLAT PLATE 2” X 5 1/2” RUBBER DONUT 2 1/2” SNAP LINK PULLEY SPACER 5/8” OD X 3/8” ID X 5/8” L GRIP TAPE 5 1/2” X 3 3/4” PLASIC PULLEY 4 1/4” X 3/4” WIDE PLASIC PULLEY 3 1/2” X 3/4” WIDE FOAM ROLLER 3 1/2” X 8” TOP PLATE (10 lbs.) SELECTOR ROD (15 selector holes) BOLT COVER 1/2” PLASIC WASHER 3” RUBBER PAD 1 1/2” X 1 3/4” ROUND END CAP 1 1/2” SHAFT COLLAR 1 3/8” OD X 3/4” ID 1.5” L WEIGHT PLATE WATER BOTTLE BRACKET SCREW 1/8” X 3/8” FULL THREAD WATER BOTTLE HOLDER JAM NUT 3/8” RUBBER STOP (1 1/2” diameter)
Part numbers are required when ordering parts.
27
Continued on next page
Page 28
G1S Hardware
KEY# QTY PART# DESCRIPTION
40 41 42 43 44 45 46 47 48 49 50 52 53 54 55 56 60 62 63 64 65 66 70 71 72 73 100 101 102 103
1 4 13 6 1 9 2 2 2 1 2 32 32 4 4 2 1 2 2 2 2 2 1 1 1 1 1 1 1 1
JHEX.5X3.25PTB JHEX.37X3PTB JHEX.37X2.75PTB JHEX.37X2.5PTB JHEX.37X1.75PTB JHEX.37X1.5PTB JCB.37X2.75PTB JHEX.31X2.75PTB JHEX.31X1.75PTB JRAH.43X1.5PTB JNLN.5 JNLN.37 JWFLT.37 JWFLT.31 JWSW.31 JREC.5 JTSPP3 JREC2 JAS.31X.31 JBB.87X.75 JBB.75X.5 JBB.75X.5 JSRTB.5 JHEX.37X.87FTB JSLW.5 JJN.5 JACN.19 JCES JAS.125X.25 JWSPL
HEX HEAD BOLT 1/2” X 3 1/4” PARTIAL THREAD HEX HEAD BOLT 3/8” X 3” PARTIAL THREAD HEX HEAD BOLT 3/8” X 2 3/4” PARTIAL THREAD HEX HEAD BOLT 3/8” X 2 1/2” PARTIAL THREAD HEX HEAD BOLT 3/8” X 1 3/4” PARTIAL THREAD HEX HEAD BOLT 3/8” X 1 1/2” PARTIAL THREAD CARRIAGE BOLT 3/8” X 2 3/4” PARTIAL THREAD HEX HEAD BOLT 5/16” X 2 3/4” PARTIAL THREAD HEX HEAD BOLT 5/16” X 1 3/4” PARTIAL THREAD ROUND ALLEN HEAD 7/16” X 1 1/2” PARTIAL THREAD NYLON LOCK NUT 1/2” NYLON LOCK NUT 3/8” WASHER 3/8” WASHER 5/16” SPRING LOCK WASHER 5/16” ROUND END CAP WASHER 1/2” T-SHAPED POP PIN 3” L ROUND END CAP 2” ALLEN SCREW 5/16” X 5/16” FULL THREAD OILITE BUSHING 7/8”OD 3/4”ID - PREINSTALLED OILITE BUSHING 3/4”OD 1/2”ID 7/16”L- PREINSTALLED OILITE BUSHING 3/4”OD 1/2”ID 7/16”L- PREINSTALLED SELECTOR ROD TOP BOLT 1/2” X 2” FULL THREAD HEX HEAD BOLT 3/8” X 7/8” FULL THREAD SPRING LOCK WASHER 1/2” JAM NUT 1/2” ACORN CAP NUT 3/16” ID - PREINSTALLED CABLE END SHAFT 3/4” L ALLEN SCREW 1/8” X 1/4” FULL THREAD WEIGHT STACK PIN LANYARD
(continued)
Part numbers are required when ordering parts.
28
Page 29
Pads List
KEY# QTY PART# DESCRIPTION
T U
1 1
G1SBP-T G1SSP-U
BACK PAD SEAT PAD
Cable List
KEY# QTY PART# DESCRIPTION
22 23 24 25
1 1 1 1
JSPC1440 JLP3240 JLP3050 JACC2210
SEATED PRESS CABLE LAT PULLDOWN CABLE LOW PULLEY / LEG EXTENSION CABLE AB CRUNCH CABLE
Accessories List
KEY# QTY PART# DESCRIPTION
67 68 69 80 81 82
1 1 1 2 2 2
JE15LB JE15LRB JE15LBP JFG18 JFG8.5 JFG14
LAT BAR LOW ROW BAR LAT BAR PAD FOAM GRIP 1 1/2” OD X 18” L -PREINSTALLED FOAM GRIP 1 1/2” OD X 8 1/2” L -PREINSTALLED FOAM GRIP 1 1/2” OD X 14” L -PREINSTALLED
Part numbers are required when ordering parts.
29
Page 30
30
Page 31
EXPLODED VIEW
DIAGRAM
G1S
© Copyright 2003. Body-Solid. All rights reserved. Body-Solid reserves the right to change design and specifications when we feel it will improve the product.
Body-Solid machines maintain several patented and patent pending features and designs. All rights reserved on all design patents and utility patents.
31