In compliance with the current norms, the machine should be installed only by a technical person qualified for this type
of work. During installation, ensure that:
- The machine is moved as given in chapter II.1.
- The required personal protection devices are worn so as to avoid injuries caused by electrical and mechanical
hazards (injuries by touching panels, sharp edges, etc.)
- Electrical connections are made after the power supply has been shut off, in compliance with the recommendations given in chapter VI.
- Grounding is carried out in compliance with current standards.
- The machine is powered on when installation has finished (ducting installed and inspection doors closed).
I / RECEIVING THE EQUIPMENT
The units are delivered on stringers or palettes then wrapped in plastic film.
I.1 / Checks on reception
When the equipment is received, the state of the packaging and the equipment must be checked. In the event of
damage, make an accurate note of any problems on the carrier's delivery note.
I.2 / Unpacking
When the equipment is unpacked, check the following:
- The total number of packages are present.
- All accessories are present (dampers, roof, electric switchgear, etc.). After unpacking the equipment, the waste must
be disposed of in compliance with the current standards. No packaging should be discarded into the environment.
I.3 / Storing
The equipment must be stored in shade, in a dry place, at a temperature between -20°C and 40°C.
II / INSTALLATION
II.1 / Handling
The units must only be moved in their installation position.
If the device is handled using a fork-lift truck, ensure this supports the load-bearing structure and does not touch
the panels enclosing the unit.
If the device is moved using a crane, use four cables of identical lengths. These must be at least as long as the
greatest distance between two fastening points.
If L + W + H > 5m then the case must be lifted using a lifting beam.
II.2 / Space required
Generally speaking, it is desirable to provide access space of at least the width of the unit on the access side for
maintenance. These units require a siphon and must be installed at a sufficient height to allow this to be installed. Note:
in case of vertical units, provide at least 300mm on the rear for connecting the condensates.
II.3 / Installation
The unit must be laid on a sufficiently rigid and flat surface (use vibration mounts if necessary). For the HVAC
connection, select duct sections based on dimensions of the flexible bands that should be properly stretched.
Install the unit such that bad weather or ambient temperature cannot damage the internal items of the unit during installation as well as when used later (possibly provide a protective cap).
GTDHR FIRST / PREMIUM / INFINITE
ENERGY RECOVERY UNIT
MS-CDF-001 A Ind A update 01/07/2011 Created by JC Validated by AR 4 / 36