1. Unwrap the machine and check out machine for any physical damage. If so,
report to your dealer as soon as possible. Touch-up paint is inside the toolbox. Use it as needed.
2. Turn vertical handwheel counterclockwise (spindle up) to take out spindle support
block. Swing out control panel out when removing spindle support block.
Control support
Spindle support block
3. Move machine to appropriate location. Put leveling screw, nut and pad on
machine (follow picture)
Leveling screw, nut and pad
4. Remove the six brackets
Six brackets
5. Place vertical screw cover on top of column Vertical screw
cover
6. Check input power that will be used for the machine. Power required for our
machines are: 230V three phase (3Φ) or 460V three phase (3Φ). Power must be first specified upon ordering. Please connect the power to R, S, T, Ground terminal as follows with minimum current of 45 amps (230V).
[R], [S], [T], [GROUND]