XLT Systems SC60, SC40 Installation Instructions

Page 1
Scissor Lift
Model : SC60
SC40
Installation Instructions
0
Page 2
XLT SCISSOR LIFT
INSTALLATION INSTRUCTIONS
Please read installation instructions carefully before installation and keep it for future reference.
INDEX:
Important Safety Instructions………………………………………………….…2 Scissor Lift
Overview…………………..……………….…..……………………….….....….3
Specifications……………………………………………………………….........5
Dimensions…………………………………………………………………….…5 Installation Instructions
1. Preliminary Checking………………………………………………….…..6
2. Guidelines for Installations………………………………………………...6
3. Installation on Ceiling……………………………………………………...7
4.Connecting to Power Supply……………………………………………….7
5. Installation of Projector……………………………………………...….....8
6. Cable Management…………………………………………….…………...9
7. Installation of Lower Ceiling Cover…………...…………….…………......9
8. Adjusting the positions…………………………………………..................9
9. Optional Accessories…………………………………………………...... 13
10. Safety Brake……………………………………………………………..18
10. Maintenance…………………………………………………………..…19
The information in this manual is subject to change without any prior notice. Updated on August 05, 2014.
1
Page 3
Installation and Operation Manual
This manual explains how to install, operate and maintain theXLTSC-60andSC­40scissor lift for video projector. This manual is for installer, interior designer,
architect, M&E consultant and system integrator who has known about XLT scissor lift.
IMPORTANT SAFETY INSTRUCTIONS
WARNING: FAILURE TO FOLLOW ALL THE FOLLOWING
INSTRUCTIONS CAN RESULT IN SERIOUS PERSONAL INJURY OR DAMAGE TO EQUIPMENT.
CAUTION:
1) The lift is not for outdoor use and it is not a passenger lift.
2) Do not install the lift on adjacent ceiling or light fixture.
3) The equipment is not to be used by children or persons with reduced physical,
sensory or mental capabilities, or lack of experience and knowledge, unless they have been given supervision or instructions.
4) Please do not allow children being supervised to play with the equipment.
5) Entire bottom of the lift must be unobstructed to allow proper operation.
6) The lift must be installed in level from front-to-back and side-to-side.
7) Please do not attach any projector with the weight above maximum weight
capacity.
WARNING:
1) Please read the instruction before installation. Improper installation could lead
to serious injury or damage to the lift.
2) Do not obstruct the operation of scissor lift with hands or any other object. It
may cause serious injury or damage.
3) Keep hands and other objects away from the mechanism when the lift is
operating. Serious injury or damage could result.
4) Clear all persons and obstructions along the lift travel path while it is operating
or in service.
2
Page 4
5) Please do not close the lift while the projector is running or while it is in “cool
down” operation to avoid premature failure to electrical or electronic
components.
6) Please do not step on the lift. Overloading could lead to damage of equipment
or injury.
ELECTRICAL RISK:
1) Please check the standard of the local power supply before installation and
ensure that the operation voltage of the motor is related as the local power supply. The motor may damage due to incorrect voltage supply.
2) Never operate the lift with damaged or faulty cord or plug.
3) Please keep the cord away from heated surface.
4) Please turn off power supply or unplug before cleaning or servicing.
THE SCISSOR LIFT
Overview The lift is powered by a tubular motor which is operated on Single phase 230~240 V
ACwith the convenience of a remote setting controller with 3 programmable positions,
at the ceiling or store level, projection level and maintenance level. It provides an attractive solution to recess a projector in ceiling and it can be fully extended to reach ground level for maintenance.
The lift is shipped with the carton box and the following items are allocated. Please inspect them for any damages once after received the lift.
1) The scissor lift
2) Remote Control
3) Lower ceiling cover
4) User Manual
5) A package of screws for projector
3
Page 5
Components of Scissor Lift
Motor cover
Ceiling mounting hole (x4)
Steel wire robe
Scissor arm
Projector tilting kit
Projector mounting plate
Projector cage
Ceiling Cover
4
Page 6
Specifications
Model
SC 60
SC 40
Dimension (W x D)
900 mm x 605 mm
900 mm x 605 mm
Height in Closed Position
670 mm
570 mm
Weight
78kg
68 kg
Max. Weight Capacity
33 kg
35 kg
Power Consumption
240 W
240 W
Voltage
230VAC 50 Hz
230VAC 50 Hz
Rated Current
1.1 A
1.1 A
Max. Travel Distance
6000 mm
4000 mm
Max. available space for projector (W x D x H)
600 x 640 x 310( mm )
600x 640 x 310( mm )
Dimensions
Installation Instructions
5
Page 7
PLEASE ENGAGE LOCAL PROFESSIONAL INSTALLER TO PERFORM INSTALLATION. PLEASE ALWAYS FOLLOW LOCAL BUILDING CODES, ELECTRICAL CODES AND LOCAL LAWS.
1. Preliminary Checking:
1) The ceiling structure should support at least FOUR times the total weight of the
lift and projector. Please reinforce additional supporting structure if needed.
2) Please check the overall dimensions of the lift and ensure that there is sufficient
space above ceiling before installation.
3) 100mm (4″) clearances from all surrounding structures are recommended. The
minimum ceiling space required for the lift to install at ceiling is 1100mm (W) x 800mm (D) x 850mm (H). The installer must be accessible to every sides of the lift in order to install it.
4) Check the dimensions of the projector to be mounted within the available space.
5) Determine the projector installation position based on projection screen location
and projector specifications.
6) Confirm that there is adequate space for installation, operation and maintenance.
7) Arrange the space for service and the access to the lift.
8) Confirm height ofceiling with maximum travel of scissor lift.
9) Physically check for any damages or loose parts on the lift.
2. Guidelines for Installation:
1) An access from above the lift with enough clearance to remove the top cover
should be provided in case of any service is required.
2) Installer must ensure that all fasteners support have adequate strength to
securely support the scissor lift and projector.
3) The lift must be installed in level from front-to-back and side-to-side.
4) Make sure that the liftis level in all directions and weight should be shared
equally by all four threaded mounting rods.
5) Bottom of the lift must be unobstructed after installation.
3. Installation on Ceiling:
6
Page 8
CAUTION:
It is installer’s responsibility to make sure that the ceiling structure can
support at least FOUR times the total weight of the lift and the projector. Reinforce the structure as required before installing the lift.
1) The scissor lift should be supported by four M12 or 1/2″ threaded mounting
rods spaced at800 mm wide x 460 mmdepth.The length of the rods may vary depend on the height of the ceiling.
2) No mounting material is provided. Please use suitable anchors and fasteners
base on the ceiling type.
3) The threaded rods must be supported by a rigid structure and should not extend
more than 2' (600mm). If the rods need to extend more than 2', please use the cross bracing to enhance the stability.
4) The threaded rods must pass through the mounting holes and secure by nuts
above and below.
5) Use the threaded locking compound angle nuts to prevent swinging.
6) Adjust the threaded rods length to get the proper height (the lower ceiling cover
should be same level with the false ceiling).
7) Check that the lift is leveled from front-to-back and side-to-side.
4. Connecting to Power Supply
CAUTION: Please ensure that the operating voltage of the motor is related to the standard of the local power supply. The motor can be damaged due to incorrect voltage supply. Please do not replace power supply cable of the motor. Please call local dealer should you have any problem with the motor.
Please refer diagram below to connect to power supply.
7
Page 9
The recommended cable size is 1.5mm2 (16AWG). The cable has to be connected to building wires and a disconnection means must be provided in accordance with the wiring rules.
5. Installation of Projector:
1) Prior to the installation of projector, the lift should be checked for proper
operation.
2) Check the dimensions of the projector for properly operated within the available
space.
3) The projector should be suspended on projector mounting bracket. Please
follow the projector manufacturer’s instructions.
4) The projector should be adjusted at the screen level as necessary. Please refer
the drawing below for adjustment of Yaw, Pitch and Roll.
8
Page 10
6. Cable Management
1) Please use cable ties to tie up all the projector cables at the cable tie
clampswhich are located along the scissors arms.
2) Please tie cables equally on both sides of the scissor arms to balance the weight.
3) Make sure that the cables are long enough for the lift to go up and down.
4) Please check that all the cables are out of the way of operation.
7. Installation of Ceiling Cover:
1) The ceiling cover is fixed to the underside of the lift which normally greater in
size and serve as platform to receive all types of ceiling materials.
2) The ceiling cover is settled to flush with the false ceiling.
3) A minimum opening of 825mmWx625mmDon false ceiling is required for the
lift to travel.
4) The ceiling cover should be attached to the base plate, below the lift.
5) Please use the screws provided (M5-12mm) to fix the ceiling cover and the lift.
8. Re-adjusting of the UP and DOWN limit:
CAUTION: The UP and DOWN adjusting shall be done within 4 minutes. The motor is
equipped with a built-in thermal overload protector which limits their operations to intermittent use only, the power supply will be cut off temporarily if more than 4 minutes. If such things happen, please wait for the motor to cool down and restart it again.
9
Page 11
‘UP’ button
‘DOWN’ button
‘MY’ button
(SHOW button)
Programming button
Hand Held transmitter
Back of Hand Held transmitter
The hand held transmitter (remote control) is paired with the lift in factory; the transmitter will not communicate with other lift by default.
The lift is preset with Upper (Stored Position) and Lower (Service Position) limits.
7.1. Setting for Lower Position (Service Level) (Down Limit)
a) Power up the lift after installation, press DOWN button, the lift will travel
and stop at the position preset by the factory.
b) To delete the limit setting of this position, press the UP and DOWN button
simultaneously until the lift begins to move briefly (up and down).
c) Adjust the lift to the require position while the UP or DOWN key are
pressed (holding period).
2 to 3 seconds
10
Page 12
OR
d) Press and hold the STOP button until the lift begin to move briefly (up and
down), the new position is recorded.
2 to 3 seconds
7.2. Setting for Upper Position (Stored Level)
CAUTION: Please do not set the UP limit higher than the limit preset by the factory.
a) Press the UP button, the lift will travel and stop at the position preset by the
factory.
b) To delete the limit setting of this position, press the UP and DOWN button
simultaneously until the lift begins to move briefly.
c) Adjust the lift to the require position while the UP or DOWN key are pressed
(holding period).
11
Page 13
OR
d) Press and hold the STOP button until the lift begins to move briefly (up and
down), the new position is recorded.
7.3. Setting for IntermediatePosition (Projection level)
a) Turn on the projector and press UP/STOP or DOWN/STOP buttons to
position the lift to the level where the images are aligned perfectly on the screen.
OR
b) Press and hold the STOP button until the lift begin to move briefly (up and
down), the new position is recorded. (Note: The lift must be completely stopped in the position before setting.)
more than 4 seconds
c) To delete the intermittent position that previously recorded, press STOP
button, the lift will travel to the position that recorded.
12
Page 14
d) Press and hold the STOP button, until the lift begins to move briefly (up and
Transmitter without front cover
Inteo Dry Contact transmitter
LED
Programming button
down), the intermittent position is deleted.
e) Repeat step (a) and (b) to record the new position.
The Upper position (Store Level), intermediate position (Projection Level) and Lower position (Service Level) are recorded. Press Up and Down button and operate the lift to countercheck the recorded positions.
9. Optional Accessories
NOTE: The device must be installed by qualified electrician for whom this instruction is intended. Please read the instructions carefully before installation. Please follow the local electrical codes.
1) Dry Contact Transmitter
If you are interfacing the lift with AMX or Crestron, the Inteo Dry Contact Transmitter will be needed.
a) Please refer the wiring diagram shown below to connect the dry contact
transmitter. (Note: The dry contact transmitter doesn’t need to connect to motor. They will interact each other by means of radio frequency.)
13
Page 15
b) The UP or Down positions are achieved when the up or down inputs (▲ or
Dry Contact Transmitter
▼) are connected with the common input C. The intermittent position is
achieved when the three inputs (▲,▼, C) are connect together.
c) Turn on the power supply to the Dry Contact Transmitter. d) Please confirm the three positions are correctly recorded by pressing UP,
DOWN and STOP buttons on hand held transmitter (remote control).
e) Press and hold the Programming button at the back of the hand held transmitter
( remote control) until the lift begins to move briefly.
14
Page 16
Programming button
PROG button
f) Press and hold the “PROG” button on the frontside of the Dry Contact
Transmitter until the lift begins to move briefly.
g) The three positions are memorized by the Dry Contact Transmitter which
automically quits its programming mode.
NOTE TO PROGRAMMER:
(i) Please program AMX or Crestron contact closure to trigger the lift by
(ii) Please do not hold the contact closure for more than 3 seconds, the
‘pulse’ only.
record will be deleted.
15
Page 17
2) Wall Mount Switch
UP button
DOWN button
SHOW button
PROG button
Wall Switch
Back of Wall Switch
Should you need to control with wall mount switch, please follow the instructions below to pair wall mount switch and the lift.
a) Press and hold the Programming button at the back of the hand held
transmitter ( remote control) until the lift begins to move briefly.
b) Press and hold “PROG” button on back of the wall switch until the lift begins
to move briefly. The setting is memorized by wall switch.
NOTE: Please visit the following link for video instructions on XLT scissor lift limit settings.
http://www.youtube.com/watch?v=AfSyawTEtKU
10. Safety Brake
The scissor lift is implemented with safety brake which will prevent the lift to fall down in case of failure occurs. At normal operation, the safety brake won’t work. If the safety brake engaged, a safety switch cuts the power of the motor and prevent the consequential damages and injuries.
NOTE: After activation of accident, please engage qualified technician to re-adjust the safety brake.
16
Page 18
11. Maintenance
Scissor arms
Please check the looseness of bolts and nuts
NOTE: ONLY QUALIFIED PERSON IS ALLOWED TO UNDERTAKE THE MAINTENANCE SERVICES.
(1) Please conduct a yearly inspection of the lift. (2) The motor is maintenance free. Please contact the service center if it is not
working properly.
(3) Please perform full travel of the lift and look out for abnormal noise or
inconsistent movement.
(4) Please check all the projector cables are tied nicely along the scissor arms. (5) Please check for any looseness of bolts and nuts on scissor arms. (Fig.1)
Fig.1. Outlook of scissor lift with top motor cover removed
(6) Please open up the motor housing, check on the motor mounting on both
ends to ensure that the motor brackets are securely fastened and no accessible movement when hold down the drums with both ends and shake. (Fig.2)
17
Page 19
Motor bracket
Please check the retaining ring is in position
Please check the motor universal mounting bracket is securely fasten to the motor bracket with the motor
Please check the motor mounting bracket on both ends
Motor
JAW
Fig 2. Motor mounting assembly
(7) Please ensure that the retaining ring (as shown in Fig.3)is screw tightened
and securely sit inside the groove holding both motor and motor universal mounting bracketin position.
(8) Please check the motor universal bracket is securely fastened to the motor
mounting bracket.
Fig.3. Motor and motor universal bracket assembly
18
Page 20
I-Bolt
Cable timber hitch
Steel wire rope (steel cable)
Cable drum
(9) Please check the motor universal bracket for any deformed or bended
“JAWS”.(Fig.3)
IMPORTANT NOTICE: If found out any deformed or bended “JAW”, please STOP OPERATING the lift immediately. Please use safety belt to support the undercarriages of the lift and call the service center for assistance.
WARNING: CONTINUE OPERATION OF THE LIFT MAY LEAD TO SERVERE INJURIES AND DAMAGES.
(10) Ensure all the steel cables are sitting in the grooves of the drums and the
other end is securely fastened to the I-bolts on the projector cage.
Fig4. Steel cable assembly
19
Page 21
Please check the steel cable is sitting well inside the grooves of the drums and cable timber hitch and securely fastened to the I-bolts
Fig.5. Steel cable and cage assembly
(11) Please pay more attention on inspection of steel wire ropes. Only qualified
person should carry out the wire rope inspection and the full length of the wire rope have to be checked.
(12) Use either electromagnetic equipment or visual and physical checking to
inspect the wire rope.
(13) The rope should be replaced when
(i) Three or more broken wires are found in close proximity of the
termination.
(ii) Three or more broken wires are found in one strand or (iii) Five broken wires are found between two adjacent strands within a
length of 30mm.
(iv) The diameter of the wire rope is reduced by 90% of the nominal
diameter 3mm. (i.e. if the rope diameter is reduced to 2.7mm, the rope should be replaced with the new one)
(14) After replacing new wire ropes, the sheaves and drums shall be checked for
eccentricity and the bearing for wear and free running before operation.
20