Wright flow Classic+, CP10/0005/12, CP20/0020/12, CP30/0069/12, CP40/0180/12 Installation, Operation And Maintenance Manual

...
I
NSTALLATION,
O
PERATION
A
M
AINTENANCE
M
ANUAL
F
OR THE
Range of Pumps
Page 2
Installation, Operation & Maintenance Manual
For The Classic+ Range Of Rotary Lobe Pumps
1.0
Safety Information. 5
1.1
Risk assessment relating to the use of Wright Flow Technologies Limited. Classic+ rotary lobe pumps and pump units in potentially explosive atmospheres. 8
2.0
Introduction. 9
2.1
General. 9
2.2
Wright Flow Technologies Limited Distributors. 9
2.3
Receipts and Storage. 9
2.4
Cleaning. 10
2.5
Pump Model Designation. 10
2.5.1 ATEX Information 11
2.5.2 Equipment Groups & Categories 11
2.6
Pump Model and Serial Number. 12
3.0
General. 14
3.1
Classic+ Pumping Principal. 14
3.2
Classic+ Range Operating Parameters. 15
3.3
System Design. 17
3.3.1 System Design and Installation. 17
3.3.2 Installations with CIP Systems. 19
3.4
Start Up Procedure. 20
3.5
Shutdown Procedure. 21
3.6
Routine Maintenance. 22
3.7
Heating and Cooling Jackets 22
3.8
Integral Pressure Relief Valves 25
3.8.1 Setting and Operating Spring Loaded Valves 26
3.8.2 Setting and Operating Air Loaded Integral Pressure Relief Valves 27
4.0
Classic+ Disassembly and Assembly. 30
4.1
CP10, CP20 and CP30 Pump - Disassembly and Assembly. 32
4.1.1 CP10, CP20 and CP30 Front Cover and Rotor Removal 32
4.1.2 CP10, CP20 and CP30 Rotorcase Removal 35
4.1.2.1 CP10, CP20 and CP30 Rotorcase Removal for Pumps fitted with Single Un­Flushed Mechanical Seals and Single O-Ring Seals 35
4.1.2.2 CP10, CP20 and CP30 Rotorcase Removal for Pumps Fitted with Single Flushed or Double Flushed Mechanical Seals. 37
4.1.3 CP10, CP20 and CP30 Gearbox Disassembly 38
4.1.3 CP10, CP20 and CP30 Gearbox Assembly 42
4.1.4 CP10, CP20 and CP30 Rotorcase, Rotor and Front Cover Assembly 46
4.2
CP40 Pumps - Disassembly and Assembly 48
Page 3
4.2.1
CP40 Front Cover and Rotor Removal 48
4.2.2 CP40 Rotorcase Removal 50
4.2.2.1 CP40 Rotorcase Removal for Pumps fitted with Single Un-flushed Mechanical Seals and O-Ring Seals 50
4.2.2.2 CP40 Rotorcase Removal for Pumps Fitted with Single Flushed or Double Flushed Mechanical Seals. 52
4.2.4 CP40 Gearbox Assembly 55
4.2.5 CP40 Rotorcase, Rotor and Front Cover Assembly 58
4.3
CP50 Pumps - Disassembly and Assembly 59
4.3.1 CP50 Front Cover and Rotor Removal 59
4.3.2 CP50 Rotorcase Removal 61
4.3.2.1 CP50 Rotorcase Removal for Pumps fitted with Single Un-flushed Mechanical Seals and O-Ring Seals 61
4.3.2.2 CP50 Rotorcase Removal for Pumps fitted with Single Flushed and Double Flushed Mechanical Seals 63
4.3.3 CP50 Gearbox Disassembly 64
4.3.4 CP50 Gearbox Assembly 66
4.3.5 CP50 Rotorcase, Rotor and Front Cover Assembly 69
5.0
Classic+ Mechanical Seal Removal & Replacement. 71
5.1
General Procedures for Installing Mechanical Seals. 71
5.2
CP10, CP20, CP30 and CP40 Mechanical Seals 72
5.2.1 CP10, CP20, CP30 and CP40 Single Mechanical Seal Removal 72
5.2.2 CP10, CP20, CP30 and CP40 Single Mechanical Seal Replacement 73
5.2.3 CP10, CP20, CP30 and CP40 Single Flushed Mechanical Seal Removal 74
5.2.4 CP10, CP20, CP30 and CP40 Single Flushed Mechanical Seal Replacement 75
5.2.5 CP10 Double Flushed Mechanical Seal Removal 76
5.2.6 CP10 Double Flushed Mechanical Seal Replacement 77
5.2.7 CP20, CP30 and CP40 Double Flushed Mechanical Seal Removal 78
5.2.8 CP20, CP30 and CP40 Double Flushed Mechanical Seal Replacement 79
5.3
CP50 Mechanical Seals 80
5.3.1 CP50 Single Mechanical Seal Removal 80
5.3.2 CP50 Single Mechanical Seal Replacement 80
5.3.3 CP50 Single Flushed Mechanical Seal Removal 81
5.3.4 CP50 Single Flushed Mechanical Seal Replacement 81
5.3.5 CP50 Double Flushed Mechanical Seal Removal 82
5.3.6 CP50 Double Flushed Mechanical Seal Replacement 83
6.0
Classic+ Single O-Ring Seals 84
6.1
General Procedures for Fitting Single O-Ring Seals 84
6.2
Oring Seals for CP10, CP20, CP30 and CP40 Pumps 85
6.2.1 CP10, CP20, CP30 and CP40 Oring Seal Assembly and Removal 85
6.3
O-Ring Seal for CP50 Pump 86
6.3.1 CP50 O-Ring Seal Assembly and Removal 86
Page 4
6.4
Classic+ Packed Gland Seals 87
6.4.1 General Procedures For Fitting Packed Gland Seals 87
6.5
Packed Gland Seals - CP10, CP20, CP30 and CP40 Series Pumps 88
6.5.1 Packed Gland Seal Removal 88
6.5.2 Packed Gland Seal Replacement 89
6.5.3 Flushed Packed Gland Seal Removal 89
6.5.4 Flushed Packed Gland Seal Replacement 90
6.6
Packed Gland Seals - CP50 Series Pumps. 91
6.6.1 Packed Gland Seal Removal 91
6.6.2 Packed Gland Seal Replacement 91
6.6.3 Flushed Packed Gland Seal Removal 92
6.6.4 Flushed Packed Gland Seal Replacement 93
6.6.5 Seal Conversion to Packed Gland (With Shaft Sleeve) 93
6.6.6 Seal Conversion to Flushed Packed Gland (With Shaft Sleeve) 94
7.0
Flushed Product Seals Auxiliary Services 95
7.1
Single Mechanical Seal (for Low-Pressure Quench or Flush) 95
7.2
Double Mechanical Seal (for High Pressure Flush) 96
7.3
Flushed Packed Gland Seal 96
8.0
Specifications 97
8.1
Clearance Chart 97
8.2
Fasteners & Torque Settings. 99
8.3
Lubricants. 100
8.4
Material Specifications. 100
8.5
Foundation Dimensions and Weights. 101
8.6
Rectangular Inlet 103
8.7
Trouble Shooting. 104
8.8
Typical Noise Emission Data - CP10, CP20 and CP30 Pumps. 105
8.9
Typical Noise Emission Data – CP40 and CP50 Pumps. 106
8.10 Service History. 107
8.11 Tool List. 108
9.0
Notes. 110
Page 5
1.0 Safety Information.
INCORRECT INSTALLATION, OPERATION, OR MAINTENANCE OF
EQUIPMENT MAY CAUSE SEVERE PERSONAL INJURY OR DEATH
AND/OR EQUIPMENT DAMAGE AND MAY INVALIDATE THE WARRANTY.
THIS INFORMATION MUST BE READ FULLY BEFORE BEGINNING
INSTALLATION, OPERATION, OR MAINTENANCE AND MUST BE KEPT
WITH THE PUMP. SUITABLY TRAINED OR QUALIFIED PERSONS MUST
UNDERTAKE ALL INSTALLATION AND MAINTENANCE ONLY.
DANGER
DO NOT OPERATE PUMP IF:
- The front cover is not installed correctly.
- Any guards are missing or incorrectly installed.
- The suction or discharge piping is not connected. DO NOT place fingers, etc. into the pumping chamber or its connection ports
or into any part of the gearbox if there is ANY possibility of the pump shafts being rotated. Severe injury will occur.
DO NOT exceed the pumps rated pressure, speed, and temperature, or change the system/duty parameters from those for which the pump was originally supplied, without confirming its suitability for the new duty. Running of the pump outside of its operation envelope can cause mechanical contact, excessive heat and can represent a serious risk to health and safety.
Installation and operation of the pump must always comply with health and safety regulations.
A device must be incorporated into the pump, system, or drive to prevent the pump exceeding its stated duty pressure. It must be suitable for both directions of pump rotation where applicable. Do not allow pump to operate with a closed/blocked discharge unless a pressure relief device is incorporated. If an integral relief valve is incorporated into the pump, do not allow re-circulation through the relief valve for extended periods (refer to section 3.8).
Warning - Safety instructions which
shall be considered for reasons of safe
operation of the pump or pump unit
and/or protection of the pump or pump
unit itself are marked by the sign:
Danger - Failure to follow the listed precautionary measures may result
in serious injury or death are
identified by the following symbol:
WARNING
Page 6
The mounting of the pump or pump unit should be solid and stable.
Pump orientation must be considered in relation to drainage/cavity ventilation requirements. Once mounted, shaft drive elements must be checked for correct alignment. Rotate pump shaft by at least one full revolution to ensure smoothness of operation. Incorrect alignment will produce excessive loading and will create high temperatures and increased noise emissions. It may also be necessary to earth the pump head to avoid the build up of a potential charge difference that could cause a spark.
The installation must allow safe routine maintenance and inspection (to replenish lubricants, check for leakage, monitor pressures, etc) and provide adequate ventilation necessary to prevent overheating.
Fill all gearboxes with the recommended grades and quantities of lubricant (refer to section 3.4 and 8.3). Beware of over/under filling the gearbox as this could cause the pump to overheat and mechanical damage to occur.
Before operating the pump, be sure that it and all parts of the system to which it is connected are clean and free from debris and that all valves in the suction and discharge pipelines are fully opened. Ensure that all piping connecting to the pump is fully supported and correctly aligned with its relevant connections. Misalignment and/or excess loads will cause severe pump damage. This could result in unexpected mechanical contact in the pump head and has the potential to be an ignition source.
Be sure that pump rotation is correct for the desired direction of flow (refer to section 3.4).
Do not install the pump into a system where it will run dry (i.e. without a supply of pumped media) unless it is equipped with a flushed shaft seal arrangement complete with a fully operational flushing system. Mechanical seals require a thin fluid film to lubricate the seal faces. Dry running can cause excessive heat and seal failure.
Pressure gauges/sensors are recommended, next to the pump suction and discharge connections to monitor pressures.
Caution must be taken when lifting the pump. Suitable lifting devices should be used as appropriate. Lifting eyes installed on the pump must only be used to lift the pump, not pump with drive and/or base plate. If pump is base plate mounted, the base plate must be used for all lifting purposes. If slings are used for lifting, they must be safely and securely attached. For weights of bare shaft pumps refer to section 8.5.
WARNING
WARNING
WARNING
WARNING
WARNING
Page 7
DO NOT attempt any maintenance or disassembly of the pump or pump unit without first ensuring that:
- The pump is fully isolated from the power source (electric, hydraulic, pneumatic).
- The pumping chamber, pneumatic relief valve and any shaft seal support system are depressurised and purged.
- Any temperature control devices (jackets, heat-tracing, etc) are fully isolated, that they are depressurised and purged, and components are allowed to reach a safe handling temperature.
DO NOT attempt to dismantle a pressure relief valve, which has not
had the spring pressure relieved, is still connected to a pressurised gas/air supply or is mounted on a pump that is operating. Serious personal injury or death and/or pump damage may occur.
DO NOT loosen or undo the front cover, any connections to the pump, shaft seal housings, temperature control devices, or other components, until sure that such action will not allow the unsafe escape of any pressurised media.
Pumps and/or drives can produce sound power levels exceeding 85-dB (A) under certain operating conditions. When necessary, personal protection against noise must be taken. Typical noise emission data can be found in section 8.8 and 8.9.
Avoid any contact with hot parts of pumps and/or drives that may cause injury. Certain operating conditions, temperature control devices (jackets, heat­tracing, etc.), bad installation, or poor maintenance can all promote high temperatures on pumps and/or drives.
When cleaning, either manually or by CIP method, the operator must ensure that a suitable procedure is used in accordance with the system requirements. During a CIP cleaning cycle, a pump differential pressure of between 2 and 3 bar (30 and 45 psi) is recommended to ensure suitable velocities are reached within the pump head. The exterior of the pump should be cleaned periodically.
Surface temperature of pump is also dependent on the temperature of pumped medium.
WARNING
Page 8
1.1 Risk assessment relating to the use of Wright Flow Technologies Limited. Classic+ rotary lobe pumps and pump units in potentially explosive atmospheres.
Source Of Hazards Potential Hazards
Frequency Of
Hazards
Recommended Measures
Unvented cavities Build up of explosive gas
Very Rare
Ensure that pump is totally filled.
Consider mounting ports vertically.
See Chapter 1.0
Rotorcase / Rotors / Front
Cover
Unintended mechanical
contact
Rare
Ensure that operating pressures are
not exceeded. Ensure that suffcient
NPSH to prevent cavitation.
See
Chapter 1.0/3.3.1
Service plan.
Pump external surfaces
excess temperature.
Electrostatic charging
Rare
User must ensure temperature limits.
Do not overfill gearboxes with
lubricant. Provide a ground contact
for pump.
See Chapter 1.0 /
Service
plan.
Cover 'O' ring
Pump liquid leakage. Build
up of explosive gas.
Very Rare
Check selection of elastomers are
suitable for application. Ensure cover
retaining nuts are tight. Service plan.
Pump casing / cover
Pump liquid leakage. Build
up of explosive gas.
Very Rare
Stainless steel, Corrosion resistant.
Shaft seals
excess temperature.
Unintended mechanical
contact.
Leakage.
Build up of explosive gas.
Rare
Selection of seal system must be
suitable for application.
See Chapter
5.0
. Service plan. Seals must never
run dry.
Auxiliary system for shaft
sealing
Pump liquid leakage. Build
up of explosive gas.
Rare
Selection of auxiliary seal system
must be suitable for application.
Seals must never run dry.
Rotation direction test Excess temperature
Very Rare
If flushed seals are installed ensure
that flush is applied to seal
assemblys. Only allow pump to run
for minimum period - just a few
seconds.
Closed valve condition
Excess Temperature.
Excess Pressure.
Mechanical contact.
Rare
Can cause excessive pressue, heat
and mechanical contact.
See
Chapter 1.0
Shaft Random induced current
Very Rare
Provide a ground contact for pump.
See Chapter 1.0.
Mechanical shaft coupling
(Torque Protection)
Temperature from friction
Sparks from break up of
shear pins.
Electrostatic charging
Rare
Coupling selection must suit
application.
See Chapter 1.0.
Mechanical shaft coupling
(standard)
Break up of spider.
Unintended mechanical
contact.
Electrostatic charging
Rare
Coupling selection must suit
application. Service plan.
See
Chapter 1.0.
Note:- For a feature to be suitable for an application, The feature must be fit for its
designated purpose and also suitable for the environment where it is to be installed.
Page 9
2.0 Introduction.
2.1 General.
Classic+ rotary lobe pumps are manufactured by Wright Flow Technologies Limited, a unit of the IDEX Corporation.
This manual includes all the necessary information for the Classic+ and should be read prior to beginning installation, operation, or maintenance.
Should you require any additional information regarding the Classic+ contact Wright Flow Technologies Limited or their local authorised distributor, refer to section 2.2.
When asking for assistance please provide the pump model and serial number. This information can be obtained from the pump nameplate which is located on the side of the pump gearbox cover, refer to section
2.6. Should the nameplate be unreadable or missing, the serial number is also
stamped on either side of the rotorcase refer to section 2.6. If the system or product characteristics are to be changed from the
original application for which the pump was selected, Wright Flow Technologies Limited or their authorised distributor should be consulted to ensure the pump is suitable for the new application.
2.2 Wright Flow Technologies Limited Distributors.
Wright Flow Technologies Limited distributes its products internationally via a network of authorised distributors. Throughout this manual where reference is made to Wright Flow Technologies Limited, service and assistance will also be provided by any Wright Flow Technologies Limited authorised distributor for Classic+.
2.3 Receipts and Storage.
Upon receipt of the pump, immediately examine it for any signs of
visible damage. If any damage is noted, contact Wright Flow Technologies Limited or your Wright Flow Technologies Limited distributor and clearly mark upon the carriers’ paperwork that the goods have been received in a damaged condition, with a brief description of damage.
Page 10
If the pump is not required for immediate installation then it should be stored in a clean, dry environment. It is recommended that storage temperature should be between –10° and 40°C (14°F and 105°F).
Further to the above, if the pump is not intended for installation or use within 18 months or more then refer to Wright Flow Technologies Limited, or the Wright Flow Technologies Limited authourised distributor for storage recommendations.
2.4 Cleaning.
The Classic+ pump series is suitable for both manual cleaning and CIP (Cleaning In Place), refer to section 3.3.2.
It is recommended that the exterior of the pump be cleaned periodically with a non-aggressive, non-abrasive cleaning solution.
2.5 Pump Model Designation.
The designations of pump models in the Classic+ range are as follows:
CP10/0005/12 CP20/0020/12 CP30/0069/12 CP40/0180/12 CP50/0351/12 CP10/0008/08 CP20/0031/07 CP30/0113/07 CP40/0250/07 CP50/0525/08 CP10/0011/05
This information, together with the pump serial number, should be provided when requesting additional information on the pump or when ordering spare parts. The pump serial number is stamped on the pump nameplate and the rotorcase, (refer to section 2.6, Figs 2 and 3).
For the maximum operating pressures, temperatures and speeds refer to section 3.2, Fig 6.
Fig 1 CP designated models only.
CP 30 0069
12 / /
P
UMP
R
ANGE
D
ISPLACEMENT
(
LTRS/REV
)
M
ODEL
S
IZE
M
AX
P
RESSURE
(
BAR)
Page 11
2.5.1 ATEX Information
ATEX Pump Requirements Please be aware that mechanical seals are a source of heat and must never be allowed to run dry. We would recommend provision be made to ensure that there is a flow of fluid around the pump seals at all times. If there is a risk of the supply being interrupted, we would recommend that the flush on the seals be fitted with a flow detection device. The surface temperature of the pump is dependent on the temperature of the pumped fluid and due account of this should be taken whilst undertaking your risk assessment of the installation. These pumps are rated to T3.
2.5.2 Equipment Groups & Categories
TEMP - T3
SERIAL NO:
ex
II - 2 - G/D
Group
II.
Category
Unit is suitable for
environments containing
dust or gas
Temperature Class.
Page 12
2.6 Pump Model and Serial Number.
Should you require any information regarding your Classic+ rotary lobe pump contact Wright Flow Technologies Limited or your Wright Flow Technologies Limited distributor, providing the pump model and serial number as stated on the pump nameplate, see Fig 2, which is fixed to the pump gearbox cover.
Should this be damaged or missing, the pump serial number is also stamped on opposite corners of the rotorcase or on the rear face of the rotorcase, (see Fig 3).
Fig 2 Nameplate
Fig 3 Serial Number Position on Rotorcase
12345/A/67
12345/A/67
Or
Page 13
2.7 Standard Pump Component Terms.
ROTORS
FRONT COVER
ROTOR
RETAINER
ROTORCASE
BEARING
HOUSING
FRONT
BEARINGS
GEARBOX
COVER
BREATHER
/FILLER CAP
REAR
BEARINGS
DRIVE
SHAFT
DRIVEN
SHAFT
TIMING
GEARS
Fig 4 Pump Component Terms
Page 14
3.0 General.
3.1 Classic+ Pumping Principal.
The pumping action of the rotary lobe pump principle is generated by the contra rotation of two pumping elements (rotors) within a chamber (rotorcase)
- see Fig 5. The rotors are located on shafts, which in turn are mounted within an external gearbox and supported by the bearings; the timing gears are also located on the shafts. The timing gears transfer the energy from the drive shaft to the driven shaft, synchronising the rotors such that they rotate without contact with each other.
As the rotors pass the suction port, see Fig 5a, the cavity generated increases creating a pressure decrease, which induces the pumped medium to flow into the rotorcase.
The pumped medium is carried around the rotorcase by the rotors; see Fig 5b and 5c, to the discharge side of the pump, Fig 5d. Here the cavity decreases and the pumped medium is discharged from the rotorcase, Fig 5e.
For pump component terms see Fig 4.
Fig 5 Rotary Lobe Pumping Principle.
Page 15
3.2 Classic+ Range Operating Parameters.
The maximum pressure and speed operating parameters are given in Fig 6. In practice these may be limited due to the nature of the product to be pumped and/or design of the system in which the pump is to be installed. Consult Wright Flow Technologies Limited or your Wright Flow Technologies Limited distributor for assistance.
The operating temperature limit of the pump is determined by the rotor clearance. For the CP10, CP20, CP30 and CP40 series pumps there are three rotor clearance bands (class A, B and C), and two (class B and D) for the CP50 series pumps.
If the system or product characteristics are to be changed from the original application for which the pump was selected, Wright Flow Technologies Limited or their authorized distributor should be consulted to ensure the pump is suitable for the new application.
The pump should not be subjected to sudden temperature changes to avoid the risk of damage from sudden expansion/contraction of components. Care should be taken when selecting pumps for handling liquids containing abrasive particles as these may cause wear of pump head components. For advice or assistance contact Wright Flow Technologies Limited or your Wright Flow Technologies Limited distributor.
WARNING
Page 16
Classic+ Series
Operating Temperature Limit (°C)
Class A Class B Class C Class D
CP10, 20, 30, 40 70 100 150 N/A
CP50
N/A 100 N/A 180
N/A = Not Available
Fig 6 Operating Parameters
Pump Range Theoretical Displacement
Nominal
Connection
Size
Max Diff. Pressure
Max.
Speed
Max Speed @ Max Diff. Pressure
Max Diff.
Pressure @
Max Speed
ltr/rev
Imp.gal
/100 rev
US gal
/100 rev
mm inches bar psi rev/min rev/min bar psi
CP10/0005/12 0.046 1.01 1.22 25 1 12 175 1400 1000 8.5 120
CP10/0008/08 0.083 1.83 2.19 38 1.5 8 120 1400 1000 5.5 75
CP10/0011/05 0.111 2.44 2.93 38 1.5 5 70 1400 1000 3.5 50
CP20/0020/12 0.202 4.44 5.34 38 1.5 12 175 1000 750 8.5 120
CP20/0031/07 0.313 6.89 8.27 50 2 7 100 1000 750 5.0 70
CP30/0069/12 0.694 15.27 18.34 50 2 12 175 750 550 8.5 120
CP30/0113/07 1.125 24.75 29.72 76 3 7 100 750 550 5.0 70
CP40/0180/12 1.800 39.60 47.56 76 3 12 175 700 520 8.5 120
CP40/0250/07 2.500 55.00 66.05 101 4 7 100 700 520 5.0 70
CP50/0351/12 3.514 77.31 92.84 101 4 12 175 650 420 8.5 120
CP50/0525/08 5.250 115.50 138.70 152 6 8 115 600 420 5.5 75
CP20/CP30 High Efficiency Operating Parameters.
CP20/0020/07 0.202 4.44 5.34 38 1.5 7 100 1000 750 5.0 70
CP20/0031/04 0.313 6.89 8.27 50 2 4 55 1000 750 3.0 40
CP30/0069/07 0.694 15.27 18.34 50 2 7 100 750 520 5.0 70
CP30/0113/04 1.125 24.75 29.72 76 3 4 55 750 520 3.0 40
Page 17
3.3 System Design.
3.3.1 System Design and Installation. When incorporating any pump into a system it is considered good practice to
minimize piping runs and the number of pipe fittings (tees, unions, bends etc.) and restrictions. Particular care should be taken in designing the suction line, which should be as short and straight as possible with a minimum of pipe fittings to minimise restricting product flow to the pump. The following should be considered at the design stage of any system
Be sure ample room is provided around the pump to allow for:
Access to the pump and drive for routine inspection and maintenance, i.e.
to remove pump front cover and rotors.
Ventilation of the drive to prevent over heating. The exterior of the pump unit may exceed 68°C (154°F),
Appropriate measures must be taken to warn or protect operators. The pump must not be used to support piping. All piping to and from the pump
unit must be independently supported. Failure to observe this may distort the pump head components or assembly and cause serious consequential damage to the pump.
Valves should be provided adjacent to the pump suction and discharge connections to allow the pump to be isolated from the system for routine inspection and maintenance.
Rotary lobe pumps are of the positive displacement type and therefore an overload protection device must be provided. This can take the form of:
An in-line pressure relief system, i.e. external to the pump.
Incorporation of a torque-limiting device in the drive system.
It is recommended that all piping and associated equipment from the tank to the discharge point is thoroughly cleaned before installation of the pump to avoid the possibility of debris entering the pump and causing damage.
Pressure gauges should be installed adjacent to the pump suction and discharge connections such that system pressures can be monitored. These gauges will provide a clear indication of changes in operating conditions and where a relief valve is incorporated in the system, will be necessary for setting and checking the functioning of the valve.
It is imperative that the suction condition at the pump inlet meets the Net Positive Suction Head required (NPSHr) by the pump. Failure to observe this could cause cavitation, resulting in noisy operation, reduction in flow rate and mechanical damage to the pump and associated equipment.
WARNING
WARNING
WARNING
WARNING
Page 18
The Net Positive Suction Head available (NPSHa) from the system must always exceed the Net Positive Suction Head required (NPSHr) by the pump.
Observing the following general guidelines should ensure the best possible suction condition is created.
Suction piping is at least the same diameter as the pump connections.
The length of suction piping is kept to the absolute minimum.
The minimum number of bends, tees and pipework restrictions are used.
Calculations to determine system NPSHa are carried out for the worst
condition see below.
Should advice on pump or system NPSH characteristics be required contact the factory or their authorised distributor.
10.0 Meters (32.8 Feet) Water Column
Suction Lift Or Vacuum
Atmospheric
Pressure
Suction
Head
NPSH
Available
Suction Line Friction Loss
Vapour
Pressure
NPSH
Available
Suction Line
Friction Loss
Vapour
Pressure
For Suction Lift
Or Vacuum Conditions.
For Conditions
With Positive
Suction Head.
Atmospheric
Vacuum
Fig 7 NPSH
WARNING
Page 19
When installing a pump complete with base plate, motor and drive, the following guidelines must be observed:
a) The preferred drive arrangement for any rotary lobe pump is in-line
direct coupled. If an alternative is required please contact Wright Flow Technologies Limited or your Wright Flow Technologies Limited distributor.
b) Flexible couplings must always be incorporated and correctly aligned
within the limits recommended by the coupling manufacturer. To check coupling alignment rotate the shaft by at least one full revolution
and ensure that the shaft rotates smoothly. Couplings of a non-flexible design must never be used. c) Couplings must always be enclosed in a suitable guard to prevent
contact with rotating parts, which could result in personal injury.
Guards should be of suitable material, (see d) and of sufficiently rigid
design to prevent contact with rotating parts under normal operating
conditions. d) When the pump is installed in a flammable or explosive environment,
or is used for handling flammable or explosive materials, special
consideration must be given. Not only to the safety aspects of the
drive unit enclosure but also to the materials used for both the
coupling and the guard to eliminate the risk of explosion. e) Base plates must be secured to a flat level surface such that distortion
and misalignment are avoided. Once base plates are fastened in
position the drive alignment must be re-checked, (see b). f) When using electric motor drives, ensure that the electrical supply is
compatible with the drive and controls and that the method of wiring is
correct for the type of starting required by the motor i.e. Direct On
Line, or other similar method. Ensure all components are correctly
grounded.
3.3.2 Installations with CIP Systems.
The Classic+ pump range is designed to be effectively cleaned by the CIP procedures recommended for in place cleaning of process plant. It is recommended that a differential pressure of 2 to 3 Bar (30 to 45 psi) be developed across the pump head during cleaning in order to develop the necessary fluid velocities required for thorough cleaning.
Page 20
3.4 Start Up Procedure.
- Check that all piping and associated equipment are clean and free from debris and that all pipe connections are secure and leak free.
- For pumps fitted with flushed product seals check all auxiliary services are in place and connected and provide sufficient flow and pressure for flushing purposes, refer to section 7.0.
- Ensure lubrication is provided for both pump and drive. The Classic+ is shipped without oil as standard and should be filled to the level of the oil sight glass - refer to section 8.3 for pump oil capacities and grades.
- If an external relief valve is incorporated in the system, check that it is set correctly. For start up purposes, it is considered good practice to set the relief valve lower than the system design pressure. On completion of start up, the relief valve should be reset to the required setting for the application. The required setting should never exceed the lower of either the pumps maximum pressure rating or the system design pressure. For setting integral relief valves refer to sections 3.8.1 and 3.8.2.
- Be sure both suction and discharge valves are fully opened and that pipe work is free from all obstructions. The Classic+ is a positive displacement type pump and should therefore never be operated against a closed valve as this would result in pressure overload, resulting in damage to the pump and possibly the system.
- Make sure that the drive shaft rotation is correct for the direction of flow required. See Fig 8.
WARNING
WARNING
WARNING
WARNING
WARNING
WARNING
Page 21
Fig 8 Rotation against Suction and Discharge
- Be sure product is available in the suction vessel before starting the pump. This is very important for pumps fitted with un-flushed product seals, as these sealing arrangements must never be allowed to run dry.
- Before beginning operation, it is considered good practice to momentarily start/stop the pump to check the direction of rotation and ensure that the pump is free of obstructions. Once this has been carried out, begin operation keeping a visual check on suction and discharge pressure gauges and monitor the pump temperature and absorbed power where possible.
3.5 Shutdown Procedure.
When shutting the pump down, stop pump, close both the suction and discharge valves and ensure that the necessary safety precautions are taken:
- The prime mover power source has been isolated.
- If installed, pneumatically operated integral relief valve has been depressurised.
- Flushed product seal auxiliary services have been isolated and depressurised.
- Pump head and piping have been drained and purged.
- Before undertaking any work on the pump refer to sections 4, 5, 6 and 7.
WARNING
Page 22
3.6 Routine Maintenance.
- Check oil levels regularly.
- Change the oil every 12 months or 3000 operating hours, whichever is the
sooner.
- For lubricant capacities and grades refer to section 8.3.
3.7 Heating and Cooling Jackets
See Fig 9 and Fig 10. The Classic+ can be supplied with a jacketed front cover and rotorcase for
circulation of a heating/cooling media. The front cover and rotorcase jacket ports are strategically positioned such
that the required thermal effect acts on the pumping chamber. The pressure rating of the Classic+ series jacketed front cover and rotorcase
is 3 Bar (50 psi) and this should not be exceeded without consulting Wright Flow Technologies Limited or your local Wright Flow Technologies Limited distributor.
Heating/cooling of the pump head is used to maintain, rather than increase/decrease the temperature of the pumped media and should be used as part of a complete system where suction and discharge lines and vessels are also heated/cooled.
Where heating/cooling devices are employed, the heating/cooling media should be circulated 15-20 minutes prior to pump start-up and should be allowed to continue for a similar period of time after the pump has been shut down. Where a CIP cycle is employed as part of the process, then the heating/cooling media should continue to be circulated during the cleaning cycle.
WARNING
Page 23
Fig 9 Dimensions of Front Cover Jacket for Heating/Cooling.
Model
Millimetres Inches
A6 M1 A6 M1 Y4
CP10/0005/12 CP10/0008/08 CP10/0011/05 CP20/0020/12 CP20/0031/07 CP30/0069/12 CP30/0113/07 CP40/0180/12 CP40/0250/07 CP50/0351/12 CP50/0525/08
50.0
50.0
50.0
64.0
64.0
92.5
92.5
130.0
130.0
175.0
175.0
52.0
61.0
61.0
71.0
81.0
81.0
96.0
108.0
123.0
115.0
138.0
1.97
1.97
1.97
2.52
2.52
3.64
3.64
5.12
5.12
6.89
6.89
2.05
2.40
2.40
2.80
3.19
3.19
3.78
4.25
4.84
4.53
5.43
¼” ¼” ¼” ½” ½” ½” ½” ½” ½” ½” ½”
Page 24
Fig 10 Dimensions of Rotorcase Jacket for Heating/Cooling.
Model
Millimetres Inches
A7 BJ D1 M2 A7 BJ D1 M2 Y5 CP10/0005/12 CP10/0008/08 CP10/0011/05 CP20/0020/12 CP20/0031/07 CP30/0069/12 CP30/0113/07 CP40/0180/12 CP40/0250/07 CP50/0351/12 CP50/0525/08
70.0
70.0
70.0
80.0
80.0
118.0
118.0
156.0
156.0
191.0
191.0
56.0
56.0
56.0
64.0
64.0
93.0
93.0
125.0
125.0
155.0
155.0
156.0
156.0
156.0
216.0
216.0
280.0
280.0
352.0
352.0
430.0
430.0
3.0
2.0
7.5
0.0
1.0
1.0
3.5
2.5
3.5
8.0
10.0
2.76
2.76
2.76
3.15
3.15
4.65
4.65
6.14
6.14
7.52
7.52
2.20
2.20
2.20
2.52
2.52
3.66
3.66
4.92
4.92
6.10
6.10
6.14
6.14
6.14
8.50
8.50
11.02
11.02
13.86
13.86
16.93
16.93
0.12
0.08
0.30
0.00
0.04
0.04
0.14
0.10
0.14
0.31
0.39
¼ ¼ ¼ ¼ ¼ ½ ½ ½ ½ ½ ½
Page 25
3.8 Integral Pressure Relief Valves See Fig 11, 12, 13 and 14.
The Classic+ models CP10, CP20, CP30 and CP40 can be supplied with integral pressure relief valves. For the CP10, CP20 and CP30 both spring and air loaded versions are available. The function of the valves can be further enhanced with the option of manual or airlift override, offering particular benefits where CIP or SIP procedures are employed. Valves incorporating this option can be opened to regulate the flow of the cleaning media through the pump chamber, thereby avoiding the need for manual cleaning or external bypass.
Where the pump is mounted onto a portable base plate, complete with motor and drive to be used as a mobile set, an integral pressure relief valve should be installed.
The Classic+ integral pressure relief valves available include: Spring Loaded - see Fig 11.
- Valve can be set to the required pressure relief setting. Spring Loaded with Manual Lift - see Fig 12.
- Valve can be set to the required pressure relief setting. Manual lift
override can be used to open valve without disturbing pressure relief setting.
Spring Loaded with Air Lift - see Fig 13.
- Valve can be set to the required pressure relief setting. Airlift override,
which operates on an air supply of up to 7 Bar (102 psi) depending on pressure relief setting, can be used to open valve without disturbing pressure relief setting.
Air Loaded with Air Lift - see Fig 14.
- Valve, which operates on an air supply of up to 7 Bar (102 psi) regulated
for required setting, can be set to the required pressure relief setting. Airlift override, which operates on an air supply of up to 7 Bar (102 psi) depending on pressure relief setting, can be used to open valve without disturbing pressure relief setting.
Air actuated relief valves can be operated remotely and interfaced with other elements of the system or process control.
Page 26
Integral pressure relief valves are normally used to protect the pump from the effects of increases in system pressure caused, for example, by a restricted or closed discharge line. In response to a pressure increase, the valve opens and internally circulates the pumped media within the pump chamber. When the valve opens, because the volume of liquid circulating is relatively small, the temperature of the liquid in the pump chamber may rise if the pump continues to operate for an extended period. In severe cases, this may result in temperatures in excess of the pumps operating limits, or vaporisation of the liquid, both of which should be avoided. For these reasons when the valve is activated the cause of the system pressure increase should be eliminated as continuous operation of the pump with the valve open is not recommended and may cause severe damage to the pump.
If the pump on which the valve is fitted is to be installed within either a pressurised system or one incorporating a vessel under vacuum then the application of the valve should be referred to Wright Flow Technologies Limited.
The selection, setting and application of integral relief valves is influenced by the viscosity and nature of the pumped media, the pumps operating speed and the required pressure relief setting and mode of operation. For these reasons and to cover the diverse range of products, the conditions under which they are pumped and application demands, it is not practical to factory­set integral relief. Valves and the setting of the valves should be carried out on site, under the proposed duty conditions for which the pump and valve were selected.
For setting and operating Classic+ integral relief valves refer to sections 3.8.1 and 3.8.2. Before beginning the relief valve setting procedure the pump should be installed, refer to section 3.3.1, paragraph (vi), with a pressure gauge in the discharge line adjacent to the pump discharge port.
3.8.1 Setting and Operating Spring Loaded Valves See Fig 11, 12 and 13.
- Remove cover (108). For integral relief valve with manual lift, see Fig 12;
first remove nut (129) and hand wheel (111).
- Unscrew nut (107) using pry bar in holes provided to relieve spring
compression. For integral relief valve with airlift, see Fig 13, the air cylinder must be exhausted prior to unscrewing the nut (107).
- Start pump. - refer to section 3.4.
- Screw in nut (107) using pry bar in holes provided until the required
pressure relief setting is reached.
Note: Care should be taken not to exceed the lower of either the pump's
maximum pressure rating or the system design pressure.
WARNING
WARNING
Page 27
- Reinstall cover (108). For integral relief valve with manual lift, see Fig 12;
reinstall hand wheel (111) and nut (129).
- The relief valve is now set. For Integral Relief Valve with Manual Lift - see Fig 12.
- To operate the manual lift, turn the hand wheel (111) clockwise, which will
lift the valve head (102/128). To resume normal relief valve operation, turn the hand wheel (111) counter-clockwise.
For Integral Relief Valve with Air Lift - see Fig 13.
- To actuate the airlift, connect an air supply not exceeding 7 Bar (102 psi)
to the cylinder (123), connection 'B', which will lift the valve head (112). To resume normal relief valve operation, exhaust the cylinder (123).
3.8.2 Setting and Operating Air Loaded Integral Pressure Relief Valves See Fig 14.
- Connect an air supply, not exceeding 7 Bar (102 psi), via a regulating
valve to the relief valve connection 'A' in the cylinder (114). Do not turn on the air supply.
- Start the pump, refer to section 3.4.
- Using the regulating valve, gradually increase the air pressure until
required pressure relief setting is reached. The air pressure must not exceed 7 Bar (102 psi).
- The relief valve is now set. Note: Care should be taken not to exceed the lower of either the pump's
maximum pressure rating or the system design pressure.
- To use the air lift system, the regulated air supply must be routed through
a change-over valve in order to transfer air from the relief valve load air chamber, connection 'A', to the lift air chamber, connection 'B', while depressurizing the load chamber and vice versa. The change-over valve will actuate the air lift which will lift when the air supply is diverted to connection 'B', and will close, restoring normal relief valve operation, when the air supply is diverted back to connection 'A'.
DANGER
Under no circumstances should any attempt be made to disassemble a
pressure relief valve which has not had the spring pressure relieved, is still
connected to a pressurized air supply or is mounted on a pump that is
operating. Serious personal injury or pump damage may occur.
WARNING
Page 28
Fig 11 Spring Loaded Integral Pressure Relief Valve CP10, CP20, CP30, CP40.
Fig 12 Spring Loaded Integral Pressure Relief Valve with Manual Lift CP10, CP20 and CP30.
Page 29
Fig 13 Spring Loaded Integral Pressure Relief Valve with Air Lift CP10, CP20 and CP30.
Fig 14 Air Loaded Integral Pressure Relief Valve with Air Lift CP10, CP20, CP30 and CP40.
Page 30
4.0 Classic+ Disassembly and Assembly.
Before starting any work on the pump the recommended Shutdown Procedure should be followed, refer to section 3.5.
While disassembling or assembling the pump it is essential to ensure that the pump and/or components are secured to provide adequate stability.
Large pump components or sub-assemblies should be installed using suitable devices. Use threaded holes for the attachment of lifting eyes where appropriate.
During disassembly or before assembly, all components should be inspected for fit, wear and damage. If worn or damaged the components should be replaced.
The position of all parts should be identified as they are removed to ensure they are reinstalled in the same position.
Lipseals and o-rings are incorporated within the gearbox assembly to contain the lubricant for the bearings and timing gears. Regular inspection and correct maintenance of these items will ensure that the lubrication is sustained and the pump maximum working life is achieved. To ensure this, it is extremely important that care is taken when removing and replacing new o-rings and lipseals. When removing and replacing lipseals ensure that the location bore for the outside diameter and the seat for the back of the lipseal is not damaged as this may create a leak path for the lubricant.
When removing lipseals or o-rings care should be taken to avoid cutting or tearing the sealing faces as they pass over keyways, splines, threads or other potentially sharp or abrasive edges. All lipseals and o-rings should be carefully examined and if damaged in any way, be replaced.
All o-rings and sealing lips of lipseals should be lightly lubricated with an appropriate lubricant (suitable for application) before installing.
When installing lipseals do not allow the rear face to come into contact with bearings or other rotating parts.
Prior to beginning assembly, ensure all parts are clean and free from burrs or damage. Where a vice is to be used then this should be installed with protective jaws to avoid damage to components. Do not hammer or apply undue force to install or position components.
All fasteners are required to be tightened to the required torque setting during assembly, refer to section 8.2.
WARNING
Loading...
+ 81 hidden pages