I N S T A L L A T I O N I N S T R U C T I O N S
Installation Instruction No.: 1 010 387R1 – Updated February 2012
Products Covered: EFB6S, EFB8S, EFB10S, EFB6S-OG, EFB8S-OG, EFB10S-OG CAUTION: Suitable for use in air handling spaces in accordance with Sec. 300-22 (C) of the National Electrical Code. NOTE: For use on bare (polished) concrete or terrazzo floors. EFB610-CTR is required.
IMPORTANT: Please read all instructions
before beginning.
EVOLUTION SERIES FLOOR BOX COMPONENTS (EFB10S Shown)
End Cap
Cable Guide
Box
Filler Plate
Toggle Clamp
Tunnel
D
ivider
Back Plate
Device Bracket
Concrete Leveling Legs
KO Plates
INSTALLATION INSTRUCTIONS – For Use in a Concrete Pour Application
Step 1 Position box in accordance with job site floor plan
and/or engineering blue print. Use the dimensions given in the following table as a reference for positioning.
FLOOR BOX SIZE WIDTH BOX
(Min.) HEIGHT
8-10 Gang Box – 13" 6" (EFB8S, EFB10S, EFB8S-OG, EFB10S-OG) [330mm] [152mm]
6-Gang Shallow Box 14 1/16" 4" (EFB6S, EFB6S-OG) [357mm] [102mm]
13 13/16"
[351mm]
11 9/16"
[194mm]
15 3/8"
[391mm]
17 11/32"
[441mm]
Width
(See
Chart)
Page 2
Step 2 Remove protective cover (mudcap) from box.
Step 3 Box is provided with a tunnel feature which allows for pass-
through of wires from one side of the box to the other.
A. Remove end cap and tunnel divider as needed to route wires
from one module to the other. Remove tunnel divider by cutting off dividers at the score line with a hacksaw as shown below.
B. If conduit is to be run in the direction of the long side of the box,
remove tunnel components and mounting bracket. Remove required KOs from box sides and attach conduit fittings (not included) to box.
C. If conduit is to be run in the direction of the short side of the box,
Remove KOs from the back plates of the device modules and attach conduit fittings, (not included) to box.
D. Attach leveling skis to bottom of box using the hex nuts in the
included sub-pack.
E. Re-attach tunnel mounting brackets and protective cover to box.
F. For concrete pours, it is recommended that all seams on outside
of the box be taped to minimize concrete egress (Tape not included).
NOTE: Back plates of device modules are removable for
ease of KO removal and conduit fitting installation.
3A: Tunnel Divider Removal
Remove End Cap for access
into the module.
Device Plate
Mounting Screws
Remove Tunnel Divider shown
to pass cables from one
Module to the next.
3B: Long Side of Box
3C: Short Side of Box
2
Page 3
3D: Attaching Leveling Skis S3E: Re-attach Device Modules
S3F: Recommendation for Concrete Pours:
Tape all seams on outside of Box
Step 4 Each device module is supplied with ground leads
and positionable dividers to segregate services. Attach devices to Mounting Brackets using fasteners provided with devices, and re-attach Back Plate to Modules using the screws provided.
ivider
D
ack
B
late
P
Mounting
Bracket
Ground Screw
Step 6 If the top of the floor box cover is to be flush with
the finished concrete floor, install the concrete/terrazzo ring before the concrete pour. (See installation instructions included with concrete terrazzo ring kit.) If the finished floor surface is to be terrazzo, install the trim ring after the concrete pour.
Step 5 Level box as required and anchor box to decking. To
level use 3/8-16 threaded rod cut to length as needed and secure with hex nuts . (Threaded rod & nuts not included). Holes for threaded rod are provided in each end of the leveling legs attached to the bottom of box. Be sure to set height of the top of the box to be flush with the finished level of the concrete pour.
NOTE: There is no provision for post
pour box height adjustment.
Step 7 Pour concrete flush with the top of floor box
protective cover.
WARNING: Pour concrete to within no more than 1/16"
[1.6mm] above box protective cover. Pours of 1/4" [6.4mm] or more over box cover will make it difficult to break out the cover and cause excessive concrete spalling around the edges of the box.
3
Page 4
Step 8 After the concrete has cured, locate box and
lear away any concrete from cover as needed.
c Remove cover from box, device mounting brackets from device modules, and clean out any debris from inside of box.
Step 9 If the finished floor is to be terrazzo, remove the
rotective cover from the box, and install the
p concrete/terrazzo trim ring kit. See instruction sheet included with trim ring kit.
Step 10 Pull wires as specified, and terminate to
appropriate devices (not included).
NOTE: Make sure that each device is properly
grounded in accordance with the National Electrical Code and any local code that may apply.
Step 11 10 Gang Box – Accepts only EFB10 Series Faceplates
8 Gang Box – Accepts standard size device plates
(2 3/4" x 4 1/2" [70mm x 114mm])
6 Gang Box – Accepts standard size device plates
(2 3/4" x 4 1/2" [70mm x 114mm])
NOTE: Various faceplates are available to accommodate
a wide range of devices, colors and styles. (Sold separately.)
NOTE: EFB10 Series Plates only work with
EFB10S Series Floor Boxes
8 Gang Plate layout 10 Gang Plate layout
Step 12 Formed wire retainers are mounted to the inside
of the box to help route card and cables exiting the box. Retainers can be removed by loosening the attachments screws.
NOTE: Evolution Series Floor
Boxes and Covers are UL/cUL Listed for use with raised floors, wood floors, bare concrete, concrete terrazzo, tile and carpet or wood covered concrete floors.
Step 13 Complete installation by attaching an Evolution
Series Floor Box Cover (Sold separately) following the installation instructions supplied with the cover.
4
Page 5
INSTALLATION INSTRUCTIONS – For Use in a Wood or Raised Floor Application
APPLICATIONS: These units are for wood floor and access floor construction with:
• 1 1/2" [38mm] subflooring with carpet padding or
• 1 1/2" [38mm] subflooring with 1/4" [6.4mm] underlayment or and tile or linoleum floor covering. These requirements represent the maximum floor thickness to ensure enough cross section is available for the box to lock into the subflooring.
Step 1 Position box in accordance with job site floor
plan and/or engineering blue print. Mark and cut hole in wood floor or raised floor panel based on the dimensions given in the following table.
Step 2 Remove protective cover and device modules from
box and lower box into hole cut in floor.
1 9/16"
1
294mm]
[
15 3/8"
[391mm]
Step 3 At front and back sides of box are adjustable toggle clamps that are used to
secure box to floor. Clamps are positioned to allow for up to 1 1/2" thick floors. Tighten clamps so that box is held securely to floor.
Adjustable Toggle
Clamp Screw
NOTE: Modules are removable to facilitate
easier connection of services. Box only needs to be removed during adds, moves and changes.
Toggle Clamp
5
Page 6
Step 4 If cabling is to be run in the direction of the long side
of the box, remove tunnel components. Remove required KOs from box sides and attach cable fittings
Not included) to box.
( A. It will be necessary to remove the end panels from
both the tunnel and the device module to allow access to the module or to be able to pass wires through the box. Module and tunnel end panels are easily disassembled by removing their respective
ounting screws. Remove tunnel divider by cutting
m off dividers at the score line with a hacksaw as shown below.
emove End Cap for access
R
nto the module.
i
Device Plate
Mounting Screws
Remove Tunnel Divider shown
to pass cables from one
Module to the next.
Step 5 Each device module is supplied with ground leads
and positionable dividers to segregate services. Attach devices to Mounting Brackets using fasteners provided with devices, and re-attach Back Plate to Modules using the screws provided.
Divider
Back Plate
Mounting
Bracket
Ground Screw
Step 6 10 Gang Box – Accepts only EFB10 Series Faceplates
8 Gang Box – Accepts standard size device plates
(2 3/4" x 4 1/2" [70mm x 114mm])
6 Gang Box – Accepts standard size device plates
(2 3/4" x 4 1/2" [70mm x 114mm])
8 Gang Plate layout 10 Gang Plate layout
NOTE: Various faceplates are available to accommodate a wide
range of devices, colors and styles. (Sold separately.)
NOTE: EFB10 Series Plates only work with
EFB10S Series Floor Boxes
6
Page 7
Step 7 Attach cable as specified and terminate to
appropriate devices (Not included).
Step 7a Re-install module into box.
Step 8 Formed wire retainers are mounted to the inside of
the box to help route card and cables exiting the box. Retainers can be removed by loosening the attachments screws.
Step 10 Complete installation by attaching an Evolution
Series Floor Box Cover (Sold separately) following the installation instructions supplied with the cover.
Step 9 Re-attach protective cover until ready to install
finish cover.
7
Page 8
tep 11 In a raised floor application, if it is necessary to reposition floor box after box has been wired, (If
S
MC or flex cabling has been used), it is possible to detach device modules and filler plate from box and pass the module out through the back side of the box without disconnecting wiring. Be sure to re-use all fasteners when re-assembling box after repositioning.
NOTE: Be sure to turn off power services before working on floor box.
11A: Remove cover assembly
11B: Remove Tunnel
11C: Remove gasket plates 11D: Pass module through back of floor box
NOTE: Services do not need to be disconnected
in order to move modules.
Step 12 For factory wired EFB6S, EFB8S and EFB10S with Walkerflex®Modular Wiring devices, follow steps 1 through 11.
CAUTION: Do not make or break connections while circuits are energized.
WIREMOLD
U.S. and International:
60 Woodlawn Street • West Hartford, CT 06110 1-800-621-0049 • FAX 860-232-2062 • Outside U.S.: 860-233-6251
Canada:
570 Applewood Crescent • Vaughan, Ontario L4K 4B4 1-800-723-5175 • FAX 905-738-9721
© Copyright 2012 Legrand/Wiremold All Rights Reserved
1 010 387R1 0212
Loading...