Whisper Power W-SQ20 Installation Manual

Page 1
INSTALLATION MANUAL
W-SQ20
- 1500 RPM -
Mobile diesel generating set 230/400V / 50Hz
Digital Diesel Control
V1.1 December 2016
Art.nr. 40200616
WHISPERPOWER BV Kelvinlaan 82 9207 JB Drachten
Netherlands Tel.: +31-512-571550 Fax.: +31-512-571599 www.whisperpower.com
Page 2
CONTENTS
2 December 2016 / W-SQ20 / EN
CONTENTS
1 INTRODUCTION .............................................................................................................................................................. 3
1.1 General .............................................................................................................................................................. 3
1.2 Generating sets for vehicles ............................................................................................................................... 3
2 INSTALLATION ............................................................................................................................................................... 5
2.1 General .............................................................................................................................................................. 5
2.2 Location .............................................................................................................................................................. 5
2.3 Instructions for optimum sound and vibration insulation ..................................................................................... 6
2.3.1 Further recommendations ................................................................................................................. 6
2.4 Ventilation........................................................................................................................................................... 6
2.4.1 General .............................................................................................................................................. 6
2.5 Connections ....................................................................................................................................................... 7
2.5.1 Fuel supply ........................................................................................................................................ 8
2.5.2 Radiator cooling............................................................................................................................... 10
2.5.3 Dry exhaust system ......................................................................................................................... 13
2.5.4 Electrical installation (12 Volt) ......................................................................................................... 15
2.5.5 AC power system (230 / 400 Volt) ................................................................................................... 17
3 INSTALLATION SPECIFICATIONS .............................................................................................................................. 19
3.1 General ............................................................................................................................................................ 19
3.2 Commissioning table ........................................................................................................................................ 19
3.3 Technical data ................................ ................................ .................................................................................. 20
3.4 Installation materials ......................................................................................................................................... 21
4 DIAGRAMS & DRAWINGS ........................................................................................................................................... 25
4.1 Layout generator control for W-SQ20 with 230VAC fan ................................................................................... 25
4.2 Terminal modes 115VAC – 230VAC - 400VAC 50Hz ...................................................................................... 26
4.3 Generator diagram 3 phase with AVR 230V – 400V 50Hz with AVR ............................................................... 27
4.4 AC wiring diagram single phase with AVR 230V Hz (Double Delta) ................................................................. 28
4.5 Electrical diagram radiator fan control 230VAC ................................................................................................ 29
4.6 Remote control panel drawings ........................................................................................................................ 30
4.7 W-SQ20 dimensions and footprint .................................................................................................................... 31
Page 3
CONTENTS
EN / W-SQ20 / December 2016 3
1 INTRODUCTION
1.1 GENERAL
This installation manual applies to the installation of the Whisper Power W-SQ20 generator set in vehicles. This manual is valid for the following models:
Part number
Description
41101320
W-SQ20 230V/400V 1500rpm Mobile
41101326
W-SQ20 230V/400V 1500rpm Mobile -ungrounded
For other models see our website: www.whisperpower.com.
WARNING
A warning symbol draws attention to special warnings, instructions or procedures which, if not strictly observed, may result in damage or destruction of equipment, severe personal injury or loss of life.
DANGER
This danger symbol refers to electric danger and draws attention to special warnings, instructions or procedures which, if not strictly observed, may result in electrical shock which will result in severe personal injury or loss of life.
WARNING! Before working (installation) on the system read the section safety instructions in the user’s manual.
1.2 GENERATING SETS FOR VEHICLES
Whisper Generators originate from the marine sector. But there are also specially designed Whispers available for mobile applications, suitable for supplying power on board of vehicles to use professional apparatus and equipment, strong lightning and air conditioning etc. The cooling system and exhaust system on vehicles is completely different from standard marine systems.
On vehicles the engine of the W-SQ20 is cooled by a radiator with an electric (230V or 3x400V) driven fan. Note that the alternator of the W-SQ20 is cooled by air. The radiator of the engine can be fitted below, on top or in the side of the vehicle.
The exhaust is of the dry type and includes a stainless flexible bellow and high quality mufflers.
Never use rubber exhaust hose, neither fiberglass nor plastic exhaust parts in a dry exhaust system as applied on vehicles. Unless indicated otherwise.
Figure 1: Typical installation with side mounted radiator
Page 4
INTRODUCTION
4 December 2016 / W-SQ20 / EN
Figure 2: Typical installation with top mounted radiator
Figure 3: Typical installation with bottom mounted radiator
Page 5
INSTALLATION
EN / W-SQ20 / December 2016 5
2 INSTALLATION
Figure 4: Schematic installation diagram
2.1 GENERAL
To ensure reliability and durability of the equipment, it is very important that the installation is carried out with the utmost care and attention. To avoid problems, such as temperature problems, noise levels, vibration, etc. the instructions set out in this manual must be followed and all installation work must be carried out professionally.
2.2 LOCATION
When looking for a proper place for a generator in a vehicle all relevant aspects have to be taken into account
Accessibility  Solid foundation  Space to mount the radiator (Refer to par. 2.5.2)  Space to mount the exhaust (Refer to par. 2.5.3)  A way to fit the fuel lines
Since Whisper generating sets have extremely compact dimensions, they can be installed in tight locations. Please consider that even almost maintenance-free machinery must still remain accessible. When selecting the location area in which to mount the generating set, make sure there is sufficient room to carry out any maintenance work. The unit must be easily accessible on the service side and on the distribution side to have access to the V-belt. All models can be serviced from one side. Note that oil filling can be only done on the top side of the engine. Cooling liquid can be filled via the expansion tank. The top of the engine (rocker cover) has to be accessible for adjustment of the valve clearance.
Please also note that in spite of the automatic oil pressure sensor it is still essential that the oil level is checked regularly.
Page 6
INSTALLATION
6 December 2016 / W-SQ20 / EN
2.3 INSTRUCTIONS FOR OPTIMUM SOUND AND VIBRATION INSULATION
Position the generating set as low as possible in the vehicle. The generating set is already secured to the base frame by means of flexible engine mountings. The base frame is mounted to the chassis of the vehicle on a second set of rubber mountings that is included in the delivery. Use the included mounting template to determine the mounting spots. When it is possible to mount the unit directly on the chassis of the vehicle this has advantages in preventing vibrations by resonance.
2.3.1 Further recommendations
Whisper generating sets are standard equipped with a sound cover. This sound cover has been designed to give effective sound insulation. For optimum sound and vibration dampening, the following factors should be considered.
1 Most important is the structure on which the generator
is placed to be stiff. Directly below the rubber mountings the structure should be supported vertically to the chassis of the vehicle.
2 In larger vehicles a separate and insulated space for
the generator will help to damp the noise even further.
3 Avoid mounting the generating set in close proximity
to thin walls or floors that may cause resonance.
4 Sound dampening is extremely poor if the generating
set is mounted on a light weight flimsy surface such as plywood which will only amplify vibrations. If mounting on a thinner surface cannot be avoided, this should be reinforced with at least stiffening struts or ribbing. If possible, holes should be drilled or cut through the surface to help reduce the resonance. Covering the surrounding walls and floors with a heavy coating plus foam will certainly improve the situation.
5 Never connect the base of the generating set directly
to walls or tanks.
2.4 VENTILATION
2.4.1 General
The generating set normally draws air from the engine compartment. Engine compartments with natural ventilation must have vent openings of adequate size and location to enable the generating set to operate without overheating. To allow an ample supply of air within the temperature limits of the generating set an opening of at least a half square meter (0,5 m2) is required. A "sealed" engine compartment must have a good extraction ventilator to maintain reasonable ambient temperatures. High temperature of intake air reduces engine performance and increases engine coolant temperatures. Air temperatures above 25°C reduce the engine power by 2% for each 5°C of rise. To minimise these effects, the engine room temperature must not be more than 15ºC above the outside ambient air temperature. Apply a combination of ventilators, blowers and air intake ducting to meet the temperature limit. The air inlet ducts should run to the bottom of the engine compartment to clear fumes from the bilge and to circulate fresh air. Air outlets should be at the top of the engine compartment to remove the hottest air. An engine compartment blower should be used as an extraction ventilator to remove air from the engine room. In cases where it is impossible to meet the above mentioned temperature limit by using engine compartment ventilation, connections are to be made for an air inlet directly to the generator enclosure. With these connections the generating set can be directly connected to an air duct. Air inlets should be louvered, where appropriate, to protect the engine room and to protect the generating set from rain and water spray.
Figure 5: Mounting of the Whisper generating set. X = wrong, V = OK
Page 7
INSTALLATION
EN / W-SQ20 / December 2016 7
2.5 CONNECTIONS
The generating set comes with all supply lines and output cables (i.e. electric cables, coolant connections, exhaust, fuel lines etc.) already connected to the engine and
generator. The supply lines are fed through the capsule’s
front base. The connections are marked as shown in figures 7 till 10. All electrical connections, cable types and sizes must comply with the appropriate national regulations. Supplied
cables are rated for ambient temperatures up to 70°C. If the cables are required to meet higher temperature requirements, they must be run through conduits.
ATTENTION!
Before working (installation) on the system read the section safety instructions
05
Exhaust connection 2”
09
Fuel out Ø8mm
06
Coolant Engine OUT Ø35mm
10
Fuel in Ø8mm
07
Battery positive (+) 35mm²
11
Coolant Engine IN Ø35mm
08
Battery negative (–) 35mm²
Figure 6: Connections of the W-SQ20 for mobile applications
Page 8
INSTALLATION
8 December 2016 / W-SQ20 / EN
2.5.1 Fuel supply
1 FUEL TANK
Fuel tanks should be made of appropriate material such as (stainless) steel or plastic. Steel tanks should not be galvanised or painted inside. Condensation can occur in metal tanks when temperature changes. Therefore, water accumulates at the bottom of the tank and provisions should be made for the drainage of this water. The tank will need a filling connection, a return connection and an air ventilation connection which will require protection against water entry. Some official regulations do not allow connection points at the base of the fuel tank; connections are to be made at the top of the tank with internal tubing down to a few cm above the bottom of the tank. Using the existing fuel tank of the car-engine the fitting should be carried out with extra care. Both a supply line and a return line should be installed and go into the tank from the top. Interference of the two systems (car engine and generator engine) should be avoided.
Do NOT connect the fuel lines to the lines of the vehicles engine fuel supply.
Driving the tank empty below the level of the suction pipe of the generator could make it necessary to bleed the fuel system.
2 FUEL LIFT PUMP
The generating set itself is equipped with a fuel lift pump. Therefore, the tank can be installed at a lower level than the generating set. See figure 8. The maximum suction height is 1 m. The W-SQ20 has a mechanical fuel lift pump that should be primed manually when the first time used. If the pump has to lift the fuel higher than one meter an external fuel lift pump must be installed. (Art. No.
50201060) The control board is already prepared to connect an extra fuel pump. When using a second electric fuel supply pump, it is recommended to mount a loose supplied pump close to the tank and mount it in an angle or vertical to prevent air bubbles to block the system. The pump will become quite hot and should be mounted out of touch. (Refer to figure 9) The pump makes clicking noises and therefore could be mounted on rubber mountings. When the clicking noises of the pump are not acceptable another noiseless pump is available as an option. (Art. No.
50202200)
Figure 7: Fuel supply (fuel tank is above the generating set)
1 Fuel return 2 Fuel supply 3 Prefilter / Water separator (optional) 5 Fuel Tank
Page 9
INSTALLATION
EN / W-SQ20 / December 2016 9
Figure 8: Fuel supply (fuel tank is below the generating set)
1 Fuel return 2 Fuel supply 3 Prefilter / Water separator (optional) 4 Extra fuel lift pump (optional) 5 Fuel tank
Figure 9: Fuel line assembly with vertical mounted additional pump and fuel lift pump mounted in an angle
A
1
3
2
5
4
Page 10
INSTALLATION
10 December 2016 / W-SQ20 / EN
3 FUEL PIPES
When the tank is above the generating set (figure 7) we recommend ending the return line on the top of the tank. When the return is on the top - in case of a leakage the return line cannot overflow because of siphoning. One will only need a fuel cock in the fuel supply line. When the tank is below the generating set we recommend ending the return line on the bottom of the tank (A) below the inlet of the supply line.
Both supply and return fuel pipe lines should be appropriate material and 8 mm outer diameter tubing. The quality of the tubing of fuel pipes could be submitted to local regulations depending on the application of the vehicle. The fuel pipes can be plumbed to the flexible hoses which are on the generating set and have a connection to fit to 8 mm pipe. This fuel lines fulfils CE standards and are in accordance with to ISO 7840 A2. It is important to avoid bends in the pipes, as they could trap air bubbles. The return pipe should never be connected to the suction pipe. The return pipe should never be connected to the suction pipe. The return line should be of 8 mm diameter and go straight back via the top to the bottom of the tank. When the return is too narrow, has too many bends and goes back to the bottom of the fuel tank, the back-pressure could be too high. This results in irregular running of the engine. When the engine runs irregular, one can check if back-pressure is the problem by disconnecting the return line just outside the canopy and draining it in a canister. When the engine runs smooth now, the return piping has to be changed. It could also help to install a second (electrical 12V) fuel lift pump in the supply line to increase the pressure.
4 FUEL FILTERS
A fine fuel filter is installed which requires maintenance. WhisperPower advises to install an extra fuel filter/ water fuel separator near the fuel tank. Before starting your generating set for the first time follow the fuel system bleeding procedure in the user’s manual.
2.5.2 Radiator cooling
1 GENERAL INSTRUCTIONS
The radiator can be mounted below the floor, in the side or on the roof of the vehicle. Wherever the radiator is mounted the well-functioning of the system depends on the well circulation of the coolant. A roof mounted radiator brings the most risk for circulation problems, because air trapped in the radiator or a low level of the coolant, will immediately affect the cooling capacity of the radiator. It is recommended to keep the radiator as close as possible to the engine. The piping should be fitted as direct as possible. When the radiator is above the engine, the piping should be fitted below the top of the radiator! (refer to figure 10). Bends in the piping, that can trap air bubbles, should be avoided or ventilated (refer to figure 11)
Figure 10: Air traps should be avoided
Figure 11: Ventilating an air trap
Piping should not be fitted above the radiator!
Page 11
INSTALLATION
EN / W-SQ20 / December 2016 11
Special attention should be paid to the ventilation of the system. Each installation system is standard supplied with an expansion tank for the coolant, which is also used to release air bubbles and makes it possible to add coolant into the system in an easy way. This expansion tank should be at the highest point of the system and mounted as high as possible.
Most cooling problems originate from air traps blocking the circulation of the engine coolant.
For the engine we use a pressurised system. The 12 mm connection on the top is closed. Wherever the radiator is mounted it is necessary to ventilate the exhaust manifold of the engine. The exhaust manifold has an 8 mm connection to ventilate the manifold. There is an 8 mm high pressure and high temperature resistant hose in the delivery to connect the hose connection on the side of the manifold with the expansion tank. (refer to figure 6).
Initially the engine cooling system can be filled via the cap on the exhaust manifold of the engine. However, when the radiator is above the engine one can only fill the system to the level of the manifold. Additional filling has to be done via the expansion tank. For large engine cooling systems with long pipes or for extra reserve there is an extra-large expansion tank with a content of 7 litres and an alarm for low coolant level that can be supplied as an option (refer to figure 12).
Figure 12: 7 litres optional expansion tank with low level alarm
When mounting the radiator, it is important to take care that the outgoing connection, which is the connection to the engine inlet, is on the top position (refer to figure 13 detail A) and is connected to the expansion tank. Also when the radiator is mounted flat at the bottom of the vehicle the outgoing connection is connected to the expansion tank This is the best way to have the system release air and to add liquid when necessary.
The expansion tank must be fitted in the outlet of the radiator = the inlet pipe of the engine
Figure 13: Outgoing connection connected to the expansion tank
When the radiator is mounted flat on the roof, the expansion tank should be mounted a little higher. (refer to figure 14 detail B).
Figure 14: Low profile radiator assembly on the roof
Most cooling problems originate from air traps blocking the circulation of the engine coolant.
Page 12
INSTALLATION
12 December 2016 / W-SQ20 / EN
It is very important to use good quality heat resistant hose and fittings. Therefore, it is strongly advised to use WhisperPower installation kits.
2 HOW AND WHERE TO MOUNT THE RADIATOR
The radiator kit includes rubber mountings to prevent vibrations to be transferred to the body of the vehicle (figure 15). Due to the difference between vehicles general instructions are not available. One has to find out where the best place for mounting is. For OEM customers WhisperPower can supply a special customised installation kit.
Figure 15: Radiator on rubber mountings
Bottom mounted radiator
When bottom mounted the radiator should not be the lowest point of the vehicle to avoid damage. A free flow of air should be guaranteed. When horizontal mounted, the fan should be on top, which causes a flow of air downwards. Often it is possible to find a place where extra space above the fan helps to create a free flow of air. It is recommended to make a shield below the radiator to catch stones and dirt and operates as a spoiler. The distance between the radiator and the shield should be at least 50 mm. Sometimes it is possible to build the radiator and shield on a sub frame that is mounted below the vehicle as a module.
Measures have to be taken to prevent the hot air circulating and reducing the capacity of the radiator. Refer to figure 16
Figure 16: Bottom mounted radiators with shield
Figure 17: Making use of the space below the floor to get an optimal flow of air through the radiator
Side mounted radiator
Most effective and easy is to mount the radiator in the side of the vehicle, if possible below the level of the top of the engine. A louvered grid should protect the radiator from rain and objects, but must not block the airflow. The fan should be inwards which causes the air to blow outwards. A disadvantage of having the radiator in the side is possibly more noise of the electric fan and a flow of air that could be felt by people passing by. A free flow of air should be guaranteed. The ventilation connection of the cooling system that goes to the expansion tank, should be in the outgoing coolant flow on top of the radiator.
Figure 18: Side mounted radiator
Page 13
INSTALLATION
EN / W-SQ20 / December 2016 13
Roof mounted radiator
The radiator on the roof is often the best option from the
point of view of keeping the noise of the fans away from
people and it will give the best result in dissipating the
heat. However, often this option conflicts with the possible
need to keep the vehicle as low as possible. Another disadvantage is that the piping has to go through the roof which requires provisions to be waterproof. Also negative is that a roof mounted radiator is more sensitive for air traps (see figure 10). Where sufficient space is available, it would be ideal to have the radiator vertically mounted on the roof. Note that the expansion tank should be above the radiator. When having the radiator horizontally mounted on the roof (refer to figure 19) enough space (50 mm) should be between the roof and the radiator fan to have a free flow of air. When the radiator is roof mounted there should be protection against weather conditions. To avoid damage while the vehicle is driving at high speed, the use of a spoiler could be necessary.
Figure 19: Two examples of a top mount radiator
3 TWO SPEEDS FAN (OPTIONAL)
To keep the noise as low as possible the fan of the radiator can run at two different speeds. As option a control box is available which can be used to drive the fan with two speeds, depending on the load of the generator. In normal mode the electric motor of the fan is powered by a low voltage and runs at low speed. This is achieved by means of a transformer. In this mode the fan hardly produces any noise. Only when necessary - this is controlled by thermostat switches - the fan is switched to a higher voltage and will blow at full speed (refer to the connection diagrams in paragraph 4.5).
However, when not strictly necessary, we recommend using the standard fan control instead of the two speeds fan control, in order to keep the system as simple as possible.
2.5.3 Dry exhaust system
1 GENERAL REMARKS
A dry exhaust muffler system should be very effective in silencing the exhaust when applying the right mufflers. However, noise could be generated by vibrations in the mufflers and be transferred to the chassis. Tacit factors like the length of specific pipe sections could cause the noise to be amplified. It is very difficult to take these factors into account.
Figure 20: Dry exhaust systems on vehicles
The standard WhisperPower exhaust kit contains the materials to perform a professional installation. In the kit is a stainless steel flexible bellow (hose) to allow for expansion and to prevent vibrations to be transferred. Rubbers are supplied to mount the mufflers flexible. The insulation blanket for the flexible bellow and the resonance muffler are also very effective in damping vibrations. Still it could be that additional measures has to be taken like an extra clamp in a vibrating section of pipe, insulation blankets on other parts of the system and possibly even additional mufflers.
When the exhaust is led through the roof of a vehicle, measures has to be taken to prevent rainwater to enter the system. Special rain caps are available as an option.
Figure 21: Ways to prevent water from getting in
Page 14
INSTALLATION
14 December 2016 / W-SQ20 / EN
A negative feature of a dry exhaust system is the heat radiated by its components. Measures are taken to overcome the heat problem: The exhaust bend to bring the exhaust out of the canopy is cooled by water. Insulation blankets are included in the exhaust kit to insulate the flexible bellow and the first muffler. When a dry exhaust has its outlet on the roof, all the pipes inside the vehicle has to be insulated.
The exhaust pipes will be very hot and all accessible pipes and mufflers are dangerous to people when not insulated.
There are companies that are specialised in insulating hot pipes and fancy systems are available to make it good looking. However, it is also possible to do it yourself by winding fibreglass or Rockwool around the pipes and seal it with aluminium tape.
2 THE STANDARD DRY EXHAUST SYSTEM
The standard exhaust system contains:
On the generator set:
An insulated exhaust bend
In the exhaust installation kit:
A stainless steel shielded flexible bellow  One resonance muffler  One absorption muffler  Clamps and rubbers to mount the system flexible  Fittings, bends and pipes to make the different
connections
Blankets for thermal and sound insulation.
The mufflers are high quality industrial mufflers that are much more effective, robust and durable than mufflers made for automotive use.
3 INSTALLATION OF THE EXHAUST
Before determining the location of the generator set one has to consider how to get away with the exhaust. Often one can find space below the vehicle between the chassis to mount the mufflers. The outlet should blow the fumes away from the doors to avoid a nasty smell. When the gasses are in the flow of air blowing from the radiator this will help to avoid the fumes to be noticed. Under no condition the fumes should be sucked into the flow of air into the radiator. In wind still conditions a light smell of exhaust fumes around the vehicle will not be avoidable. To bring the exhaust to the top of the vehicle gives the best results on noise and smell. However, when the pipes go through the vehicle they should be insulated and around the hole in the roof should be a collar to prevent rainwater to leak in. Both mufflers could be on the roof or one of them or both could be below the vehicle. In general, it is better to have the mufflers wide apart: the resonance muffler close to the generator and the absorption muffler on the end of the line. A short pipe (30cm) should be on the far end after the absorption muffler. The absorption muffler has no flow direction and could be mounted both ways. The resonance muffler should be mounted taking into account the indication on the muffler itself.
The resonance muffler should be fitted taking into account the gas flow direction indicated.
In the kit are clamps to mount the exhaust pipes to stainless steel bars. These bars should be mounted to the chassis of the vehicle. It is recommended to use rubber mountings whenever possible. However, take care that the heat conducted through the brackets will not affect the rubber. Refer to figure 22 how to mount the rubber in a safe way. When any doubt an extra safe guard could be constructed from steel wire or chain.
Figure 22: Mounting bracket in rubber with safeguard
Page 15
INSTALLATION
EN / W-SQ20 / December 2016 15
2.5.4 Electrical installation (12 Volt)
1 DIGITAL DIESEL CONTROL SYSTEM
The electrical control system is standard in 12 Volt with negative earth. Non- earth return is available as an option.
All electrical wiring has been prepared on the generating set to the control panel prior to despatch from the factory. The engine is controlled by a very advanced microprocessor based system: Digital Diesel Control.
The “black box” containing the microprocessor is located
on top of the alternator. A local control panel is on the generating set.
Remote control
A remote control panel also containing a microprocessor is in the delivery. A 15 m intermediate 8-pole communication cable is in the standard supply as well (refer to figure 23). If necessary, an optional longer (up to 30m / 100ft) intermediate cable can be connected if the standard length does not suit the required distance. When a longer distance than 30m / 100ft is required, consult the WhisperPower service department for advice.
Figure 23: Remote control cable
One can mount the control panel after drilling a hole in the dashboard using the plastic cover. Refer to the dimensional drawings in chapter 4.
More remote control panels (slave panels) can be put in parallel by using the modular connectors on the back of the units. As a slave one can use the same panel offering all functions again. It is also possible to use an old or new type slave panel only to start and stop the generator. Old type remote panels and system panels can be connected by means of the green connector.
When using the factory settings, installation is very simple: just plug the remote cable into the remote and the generator is ready to use. Refer to figure 24.
Figure 24: Remote box terminals
Acoustic alarm or warning lamp
One can connect an external max.150 mA relay to generate an acoustic warning or applying a warning lamp etc. Be aware of polarity as some relays has a diode inside and should be connected plus to plus and minus to minus as indicated. Refer to figure 24.
Connection for emergency stop / fire alarm switch
To connect an emergency stop button or to stop the generator automatically in case of a fire alarm, you can use the bypass connection between fastons J7 and J18 on the backside of the local control panel. See figure 25. To do so, remove this bypass connection and then replace it
WIRING COLOURS
RED GREEN BROWN YELLOW PINK PURPLE BLUE WHITE
GREY/PINK GREY
RED/BLUE
BLACK
MAX. 150 mA
WARNING RELAY
REMOTE CABLE
REMOTE CABLE
2
1
5
4
3
8
7
6
11
10
9
12
SENSE BAT. 2
12 11 10 9 8 7 6 5 4 3 2 1
Whisper Remote Panel
WRP/2
J3
Page 16
INSTALLATION
16 December 2016 / W-SQ20 / EN
by an emergency switch or a potential free fire alarm switch with normally closed contacts.
Fig. 25: Connection for emergency stop / fire alarm switch
Automatic starting and stopping
Automatic start/stop WhisperPower cannot be held responsible for damage caused by the unattended running generator using the auto­start/stop mode or interval mode.
Using the auto-start/stop (interval) mode the generator can start unexpectedly. When working on the electrical system, the 3 Amp fuse must be removed from the control panel and the battery plus cable must be removed from the battery.
The WhisperPower Digital Diesel Control system offers several options for automatic starting and stopping.
Access to this menu and other menus could be blocked. For de-blocking and setting up this options refer to the APPENDIX of the DDC users manual. One of these options is to monitor a second battery (not being the starter battery) to start the generator automatically when the voltage of this battery drops below a certain setting.
Other names for this second battery are “auxiliary battery”,
“service battery”, ”users battery” or “consumers battery”. We will refer to this battery as “the second battery” (BAT2).
In some menus the starter battery could be indicated as “the first battery” (BAT1). A sense wire to monitor the second battery should be connected (attention polarity!) to the connector on the back of the remote panel. Refer to figure 24. The sense
wires must be connected directly on the second battery before a main switch and be protected by a 3 Amps fuse. (Monitoring the generator starter battery does not require an extra sense connection)
Settings
When one want to apply other settings than the factory settings refer to the DDC user’s manual, especially to the APPENDIX.
2 STARTER BATTERY
For starting, the generator set requires a 12V starter battery with the following capacity:
Model
Capacity
W-SQ20
120Ah
The generating set can be connected with the main engine battery or have its own battery. We strongly recommend the use of a separate battery for the generating set and to keep the wiring system for the vehicle engine and the domestic DC supply system completely separate and individually connected to separate batteries.
Figure 26: Starter battery
However, the negative of all the batteries on the vehicle should be interconnected to avoid difference in the voltage level of the earth on different places causing trouble to electronic devices which might be in the system. The above recommendation is not valid for vehicles having the starter battery of the vehicle engine or other auxiliary equipment positive grounded. When this is the case an expert should be consulted. A battery switch may be used to interrupt the positive connection. The starter battery is charged by the alternator on the engine. An additional battery charger will help to keep the battery in good condition when the generating set is not used. A battery charger is not included in the standard supply. A high efficiency battery charging unit can be ordered from WhisperPower which is able to charge both the vehicles’s main battery and the starter battery. Also a small charger can be used to charge the starter battery only, such as the
Remove bypass between J7 - J18
Normal operation
Alarm / emergency
local control panel
(rear view)
Page 17
INSTALLATION
EN / W-SQ20 / December 2016 17
such as the WBC Handy 70. A battery switch and a charger are included in the battery installation kit (refer to
3.4).
3 OTHER RECOMMENDATIONS AND WARNINGS
The battery should be secured for poor road conditions and the terminals should be insulated. For extra safety the battery can be enclosed in a wooden, plastic, fiberglas etc. (non metal) box. Even when the earth return system is applied a negative battery cable should be used and the vehicle should not to be used as a conductor. The battery cables are supplied in a standard length of 1.5 m, if longer cables are required a larger cross sectional area should be considered to compensate for voltage reduction.
When two batteries are used in series to provide a 24 Volt supply system, never take off 12 Volt (starting) power from one of these batteries. This will result in severe damage to both batteries within a short time.
Disconnect the battery leads if electrical welding is to be carried out, otherwise damage will be caused to the diodes of the alternator.
As explosive hydrogen gases may be discharged during charging, the battery should be located in a well ventilated room. Ensure that the supplied battery cable connectors are properly fitted and never remove during or shortly after charging as sparking can occur, which may ignite the hydrogen gasses.
2.5.5 AC power system (230 / 400 Volt)
The electric power supplied by the generator is of a high voltage and dangerous to people. Before working (installation) on the system read the sections on safety in the users manual.
Realise hat people are not used to having 230/400 Volt available on a vehicle. Put warning signs on wall sockets and on junction boxes. Instruct non-regular users of the vehicle. Warn maintenance personal of garages that do service on the vehicle.
Generators used on vehicles that are operated in a hazardous environment have often to fulfil special regulations and additional measures have to be taken accordingly.
Be sure that all electrical installations (including all safety systems) comply with all required regulations of the local authorities. All electrical safety/shutdown and circuit breaking systems have to be installed on board as the generating set itself cannot be equipped with such equipment for every possible variation. The vehicle’s power supply system should be suitable and safe for the AC voltage which is applied and the power that will be generated. Special attention has to be paid on dividing the system in branches which are fused individually. It is absolutely essential that each and every circuit in the electrical system is properly installed by a qualified electrician.
The W-SQ20 can be connected as a single phase 230 Volt generator by an arrangement of the wiring in double DELTA. When the wires are arranged in STAR the output will be 230/400Volt. Connected as a three phase 230/400 Volt generator, 3x 400 Volt is available between the phases. At the same time 230 Volt is available between every phase and neutral.
When applying 3 phases the installation should be laid out in such a way that there is a reasonable balance of load between the three phases.
To avoid problems with unbalanced loads one could apply a 400V 3 phase to 230 Volt single phase transformer.
Page 18
INSTALLATION
18 December 2016 / W-SQ20 / EN
1 FUSE
An output fuse (between the generating set and the electrical installation) should be installed to protect the installed electrical system. For the W-SQ20 the maximum single phase current at 230V is 108 Amps. Using three phases the fuses should be three times 36 Amps and mechanically connected. The fuses must be of the slow reacting type. For electrical motors connected to the system, a motor protection switch must be installed.
2 GROUNDING
The AC alternator windings are not grounded. The housing of the alternator and all other metal parts are grounded.
To make a connection between “neutral” and “ground” is
necessary as part of a specific insulation failure protection system. It is possible that the electric installation in the vehicle must be protected against insulation failures. Methods of protection are subjected to rules that can be different depending on the use of the vehicle and local standards. Experts in this field should be consulted.
3 CABLE
For the power cable we recommend the use of 3 wire single phase or 5 wire tri-phase oil resistant cable with a sufficient cross sectional area. One wire for earth is included. For long cables it is recommended to apply cables with a larger cross section (refer to ISO 13297 annex A).
4 TRANSFER SWITCH
A power source selector switch much be installed between the generating set and the vehicle’s electrical supply system. This switch must ensure that all AC consumers can be switched off at once. This switch should also be installed to keep the generating set and shore (grid) power systems separate. Transfer switches - to switch over from a land line to vehicle or from generating set to inverter - should be well designed to switch over all wires including neutral (and not only phases or line) and there should be provisions with the aid of timers to prevent relays from clattering.
Page 19
INSTALLATION SPECIFICATIONS
EN / W-SQ20 / December 2016 19
3 INSTALLATION SPECIFICATIONS
3.1 GENERAL
1 Install the generating set on the 4 anti-vibration
mounts. Use the template included in the shipment to drill the 8 mounting holes.
Figure 27: Anti-vibration mounts
2 Mount the cooling system for the engine. 3 Connect exhaust system. 4 Connect ‘fuel supply line’ to the water separator/ fuel
filter. 5 Connect ‘fuel return line’ to the fuel tank. 6 Connect remote panel (just plug in). 7 Connect the AC cable from the AC box to the power
source selector. 8 Connect plus and minus from the 12V starter battery
to the battery cables. 9 Connect the power supply of the radiator. 10 Install a WhisperPower battery charger (optional).
3.2 COMMISSIONING TABLE
1 Check if the cooling system for the engine is properly
installed. Note that air traps must be avoided. 2 Check if the exhaust system is properly installed.
Check maximum length of exhaust hose, diameter of
exhaust piping.
3 Check all coolant connections. 4 Check the AC cables and the grounding. 5 Check if an AC breaker is installed before or after the
power source selector. When there is only a circuit breaker, use it to disconnect the generating set from the grid.
6 Check all DC connections, check if the battery switch/
circuit breaker is closed.
7 Open the fuel valve. Check if there are no air leaks in
the fuel supply line, and check if the lift of the fuel is less than 1 meter. Check if there is no air in the water
fuel separator. 8 Check if the air intake in the canopy is not blocked. 9 Check the oil level and colour of the oil. Check the
coolant level of both the alternator cooling and the
engine cooling. 10 To bleed the fuel system, use the manual pump by
turning the cap loose and pumping as long as
necessary to bleed the system. See chapter 4.2.2 of
the user’s manual. 11 Start the engine by pushing the start button 12 Check when the generating set is running, the delay
of 5 to 10 seconds in the power source selector
transfer. 13 Check voltage and frequency under ‘no load’
conditions. 14 Check voltage and frequency under ‘full load’
conditions. 15 Check if the battery charger of the generating set is
working (max. 14.5 Volt). 16 Close the sound shield and check the noise level. 17 Stop the generating set and check the engine again
for leakages of oil, fuel or coolant.
Installation checklist available on our website: www.whisperpower.com. Commissioning form available on our website: www.whisperpower.com.
MOUNTS
ANTIVIBRATION
Page 20
INSTALLATION SPECIFICATIONS
20 December 2016 / W-SQ20 / EN
3.3 TECHNICAL DATA
W-SQ20
Dimensions incl. sound shield.
126 x 68 x 80 cm (L x W x H)
Dimensions w/o. sound shield.
115 x 60 x 75 cm (L x W x H)
Weight incl. sound shield
580 kg
Weight w/o. sound shield
480 kg
Max. operation angle
25°
Remote panel 15 m cable
Digital Diesel Control System
Battery capacity min.
120 Ah
Fuel consumption
1 – 6 l/hr, load dependent
Lift fuel pump
Mechanical driven; manually priming
Max lift fuel pump
1m
Cooling
Radiator cooling
Minimum water supply
20-25 l/min
Alternator
synchronous brushless, maintenance free, air cooled
Voltage regulation
AVR
Output power at power factor cos phi = 1
25kW*, 230V or 230/400V 50Hz
Battery charger
alternator including regulator (50 Amps)
* Note that this value must be reduced by the power to drive the cooling fan of the radiator.
Page 21
INSTALLATION SPECIFICATIONS
EN / W-SQ20 / December 2016 21
3.4 INSTALLATION MATERIALS
230VAC RADIATOR COOLER KIT
no
qty
article no
description
1 1 50230511
Radiator AP 730EB 230 VAC
2 2 50221502
Hose clamp, stainless 20-32mm
3 1 50221064
Double male nipple 1”
4 1 50221044
TEE-fitting-1”
5 2 50221014
Male hose connector 1”x35
6 1 50221107
Straight reducer m/f 1”-3/8”
7 1 50221005
Male hose connector 3/8"x16
14
6m
50220013
Radiator hose, smooth 35x45mm
15 4 50221504
Hose clamp, stainless 35-50mm
16 8 50221597
Hose support, stainless 45x20mm
17 1 50230564
Expansion tank w/o cap
17 1 50230561
Expansion tank cap 1-1.2bar
18
1.5
50220058
Radiator hose 15x22mm
19 2 50221142
Straight reducer m/f 1½”-1”
20
4m
50220005
Hydraulic hose, 7.9x15mm (5/16)
21 2 50221522
Hose clamp, stainless 10-16mm
Not shown
1
50230565
Bracket for expansion tank
Not shown
2
50211484
Starlock washer M8 uncapped
TOTAL
40201897
230VAC Radiator cooler kit for W-SQ27
3x400VAC RADIATOR COOLER KIT, same as article no. 40201897, except:
no
qty
article no
Description
1 1 50230512
Radiator AP 730EB 3x400 VAC
TOTAL
40201898
3x400VAC radiator cooling kit for W-SQ27
OPTIONAL INSTALLATION MATERIALS
no
qty
article no
description
22 1 50230535
Expansion tank 7L with low level alarm switch
Page 22
INSTALLATION SPECIFICATIONS
22 December 2016 / W-SQ20 / EN
DRY EXHAUST KIT
no
qty
article no
description
61 1 50220067
Exhaust hose, 2” stainless 500mm f/m
62 1 50220042
Insulation blanket 52x26 for exhaust hose
63 1 50230574
Absorption muffler, steel 2”
64 1 50230575
Resonance muffler, steel 2”
65 1 50230576
Insulation blanket 70x55 for muffler HD 2”
66 2 50221404
Pipe nipple, galvanized 2”x300mm
67 2 50221424
Parallel male coupling, 1½” galvanized
68 2 50221414
Straight coupling, 2”galvanized f/f
69 3 50221668
U-clamp 73 mm M10
70 3 50221664
Bracket for U clamp, 25cm 48-60mm passivated
71 6 50211406
Washer, zinc-plated M10
72 6 50211448
Spring washer, zinc-plated M10
73 6 50211466
Hex nut, zinc-plated M10
75 1 50221476
Elbow, 90 deg 2” galvanized m/f
76 2 50230577
Insulation blanket end cover HD 2”
77 1 50230578
Insulation blanket for muffler SDHD 2”
78 2 50230579
Insulation blanket end cover SDHD 2”
TOTAL
40201889
DRY EXHAUST KIT 2”
Page 23
INSTALLATION SPECIFICATIONS
EN / W-SQ20 / December 2016 23
BATTERY INSTALLATION KIT
article no
description
dimensions
61112007
WBC-Handy 70 charger 12V / 7A
225 x 50 x 50 mm
40290093
battery terminal (NEG-)
40290094
battery terminal (POS+)
40290099
M8 battery pole adapter set
40290098
isolation caps (red&black)
502144701
WP-Compact Manual Battery Switch, 300A
72 x 72 x 78 mm
40290108
INSTALLATION KIT FOR BATTERIES > 100 Ah
RECOMMENDED BATTERY
article no
description
dimensions
40290062
AGM-Power 12V 145Ah Absorbed Glass Matt
340 x 173 x 280 mm
FUEL KIT
no
qty
article no
description
dimensions
42
1
50230091
Filter head for fuel strainer/water separator
M14x1.5 mm
43
2
50221618
Parallel male coupling
M14 - 8 mm
44 2 50221619
Parallel male coupling
M14 - 10 mm
45 2 50221620
Hose connection, outer cone
M16x1.5 mm, 8 mm
46 50230092
Filter for fuel strainer/water separator
48 4 50221522
Hose clamp, stainless
10-16 mm
49 2 50221632
Gasket ring
18x14x1.5 mm
not shown
2
50221203
Straight coupling
8 mm
not shown
2
50221252
Barbed-smooth hose nipple
8 mm
TOTAL
40230205
FUEL KIT
OPTIONAL INSTALLATION MATERIALS
no
qty
article no
description
dimensions
48 1 50221522
Hose clamp, stainless
10-16 mm
not shown
per m
50222020
copper fuel pipe
6x8 mm
not shown
per m
50220063
fuel hose
8x16 mm
Page 24
INSTALLATION SPECIFICATIONS
24 December 2016 / W-SQ20 / EN
Figure 28: Rubber mounting kit
Page 25
DIAGRAMS & DRAWINGS
EN / W-SQ20 / December 2016 25
4 DIAGRAMS & DRAWINGS
4.1 LAYOUT GENERATOR CONTROL FOR W-SQ20 WITH 230VAC FAN
Figure 29: Control wiring for W-SQ20 230VAC radiator fan
Optional control for two speeds fans.
See chapter 4.5
Page 26
DIAGRAMS & DRAWINGS
26 December 2016 / W-SQ20 / EN
4.2 TERMINAL MODES 115VAC – 230VAC - 400VAC 50HZ
Figure 30: Terminal modes W-SQ20
Page 27
DIAGRAMS & DRAWINGS
EN / W-SQ20 / December 2016 27
4.3 GENERATOR DIAGRAM 3 PHASE WITH AVR 230V – 400V 50HZ WITH AVR
Figure 31: Three-phase 230V – 400V 50Hz generator diagram with AVR
*
REFER TO 2.1.3 USER MANUAL WHISPER 25U
* TO CONNECT NEUTRAL TO GROUND
* WITH RESPECT TO CONNECTING NEUTRAL TO GROUND, REFER TO 2.1.3 IN USER MANUAL
Page 28
DIAGRAMS & DRAWINGS
28 December 2016 / W-SQ20 / EN
4.4 AC WIRING DIAGRAM SINGLE PHASE WITH AVR 230V HZ (DOUBLE DELTA)
Figure 32: Single phase 230V 50Hz AC wiring diagram with AVR (Double Delta)
* TO CONNECT NEUTRAL TO GROUND
REFER TO 2.1.3 USER MANUAL WHISPER 25U
* WITH RESPECT TO CONNECTING NEUTRAL TO GROUND REFER TO 2.1.3 IN USER MANUAL
Page 29
DIAGRAMS & DRAWINGS
EN / W-SQ20 / December 2016 29
4.5 ELECTRICAL DIAGRAM RADIATOR FAN CONTROL 230VAC
Fig. 34: Electrical diagram fan control using a 230V
AC radiator fan – with two speeds fans (optional)
Fig. 33: Electrical diagram for standard fan control
using a 230V AC radiator fan
Page 30
DIAGRAMS & DRAWINGS
30 December 2016 / W-SQ20 / EN
4.6 REMOTE CONTROL PANEL DRAWINGS
Figure 35: Remote control panel dimensions
The remote panel comes in a carton that can be used as a template to drill the mounting hole.
Page 31
DIAGRAMS & DRAWINGS
EN / W-SQ20 / December 2016 31
4.7 W-SQ20 DIMENSIONS AND FOOTPRINT
Figure 36: W-SQ20 dimensions and footprint
CONNECTIONS W-SQ20:
POWERCABLES
• exhaust:
2”
• W-SQ20 230V
single phase (108 Amps)
3x25 mm² (not included)
• fuel hose:
8 mm
coolant in/out:
Ø 35 mm
• W-SQ20 230/400V 3 phases (3x 36Amps)
5x6 mm² (not included)
• battery +:
35 mm²
• battery -:
35 mm²
REMOTE CABLE (ALL MODELS)
8 wire communication cable, 15 meter (included). For longer lengths (max. 30 m), refer to Whisper Power service department
DIMENSIONS W-SQ20
Incl. sound canopy
Without sound canopy
• length
126 cm
115 cm
• width
68 cm
60 cm
• height
80 cm
75 cm
• weight
580 kg
480 kg