Vinotemp VINO-1900SS, VINO-1500SS User Manual

VINO-1500SS VINO-1900SS
Installer’s Instruction
Federal law requires that WINEMATE split cooling systems be installed by an EPA certified refrigeration technician.
WINEMATE split system is shipped as components and is ready for use only after a certified refrigeration technician has properly installed, charged and tested the system. Proper installation is critical. Vinotemp can only warrant the quality of the components. The installation and proper operation of the system must be warranted by the installer. Installation of the system must be done in accordance with all state and local building codes. The condensing unit and evaporator unit are connected by a liquid line and an insulated suction line that are supplied by the installer. These lines must be properly sized for the distance between the two units. After the units and the lines are installed, the system must be pressure tested. If no leaks are found, evacuate and charge system with R134A. Refrigerant amount will vary depending on the length of line set.
1. Condensing Unit
Place the condensing unit WM-150SCU in a properly ventilated location. If it is not, heat exhausted by the condensing unit will build up and the cooling system will not operate properly.
Leave minimum 5 feet clearance for the exhaust side and leave minimum 1 foot clearance for the fresh air intake side.
Condensing unit shall be elevated to avoid possible flooding and shaded from direct sun. It shall not be exposed to temperatures higher than 110
°F or lower than 45 °F (optional low ambient kit for 20 °F).
2. Evaporator Unit
The WM-15SFC evaporator unit is installed for ceiling mount with the air supply towards horizontally and air return on the bottom.
The WM-19SFC evaporator unit is installed for wall mount with the air supply towards top and air return on the sides.
Supply and return air flow from the evaporator unit shall be unobstructed for at least 1 foot.
There is a gravity drain line so that it can not be installed above the evaporator unit. Otherwise a condensation pump must be used.
3. Refrigeration Piping and Charging
NOTES: ALWAYS USE THE SUPERHEAT AND SUBCOOLING, PRESSURE READINGS TO CHARGE REFRIGERANT PROPERLY, THE LISTED CHARGES ARE FOR REFERENCE ONLY.
The installation order starts from condensing unit (including the receiver), liquid line filter-drier, moisture-liquid indicator (sight glass), liquid line, evaporator unit (including liquid line solenoid valve and thermostatic expansion valve or automatic expansion valve), returning to suction line and condensing unit.
The subcooling at the condensing unit shall be around 10°F. The charge may be complete when there are no more bubbles forming in the sight glass.
The evapor ator superheat is set around 8-10 °F for a 10 °F TD system at factory.
Low side pressure: around 33 psig
High side pressure: 130 -150 psig at 75 -90 °F ambient temperatures
The line sizes and refrigerant charges are listed as follows.
MODEL
VINO-1500SS < 50 FT VINO-1900SS < 50 FT
REFRIGERATION
LINES
LIQUID
LINE
1/4"
OD
1/4"
OD
SUCTION
LINE
3/8” OD 1/2” OD 3/8” OD 3/8” OD
DRAIN
LINE
CHARGE
R134a/
15 OZ
R134a/
15 OZ
4. Pressure, Superheat and Subcooling Readings
NOTES: THE SERVICE VALVES MUST BE IN THE MIDDLE POSITIONS TO READ PROPERLY.
Complaint Possible Causes
a. High suction pressure and low head pressure b. High suction pressure and low head pressure Low superheat and low subcooling
a. Compressor may be bad b. Expansion valve opened, too
much oil
- 1 -